Professional Documents
Culture Documents
TUNNEL
MAJOR
PROJECT
REPORT LONDON TIDEWAY
IMPROVEMENTS
The Thames Tunnel is a
new relief Tunnel ThaT is
parT of Thames waTer’s
scheme To reduce
Foreword
04 all provide additional capacity and
improve water quality in the river.
Becoming a reality Clearly this is a huge investment for
London Tideway Improvements London and like other schemes,
are making progress such as the Olympics and Crossrail,
it does not just affect central
06 London, it affects a whole range of
sites across the city.
Thames Tunnel By looking at alternative options
Taking wastewater under we have significantly reduced the
central London number of construction sites. This
will reduce the impact of the
16 tunnel’s construction on customers
This may not be the
❝
and businesses. We still have some
Tunnelling challenge For the last 150 years
❝
way to go in terms of refining our most fragrant
Multiple tunnelling methods are London has benefited proposals for the main Thames infrastructure project
needed for the Thames Tunnel from the fantastic work Tunnel, and that is the benefit of but it’s extremely
carried out by the consulting with people across important - creating around
18 Victorians in the 1860s. The sewer London - we want to collect their 4,000 jobs and apprentices in
network created by Sir Joseph thoughts on how we can minimise the next few years and the
Lee Lessons Bazalgette and his team is still in the impact. long-term prospect of a cleaner
Experience from the Lee Tunnel is excellent condition, but it badly Learning points from around the Thames and better quality of life.
helping work on the Thames Tunnel needs greater capacity. When it world, in locations such as Sydney London led the world when
was built London had 2.5 million and Singapore where similar Marc Isambard Brunel and his
20 residents. Today the population schemes have been constructed, is son, Isambard Kingdom Brunel
has trebled - and it is still growing. built the first Thames tunnel and
Lee Tunnel In addition the system is facing
that if you want to invest in the
future then you need to invest in Joseph Bazalgette conceived
London’s deepest tunnel is new pressures. Areas that have the environment. the sewers, so helping to crack
now under construction been paved over are increasing the The challenge for us now is to the problems of cramped
amount and speed of run-off ensure that we have the most metropolitan living that
26 water into the system, and climate effective solution, not just in terms threatened the prosperity of
change is altering rainfall patterns.
History The environmental standards in
of standards and engineering but Victorian London. These
Bazalgette’s groundbreaking the most cost-effective solution engineering marvels set the
the 1850s were quite that delivers value for money. standard for city living that we
Victorian legacy straightforward with engineers Over the past 10 to 20 years the take for granted today. More
simply asked to clean up the need to invest in the future has than 150 years after the ‘Great
30 Thames and get rid of the smell. been suppressed, but this can only Stink’ of London, the planned
Any overflows went into a river
Other upgrades which had been biologically dead
be done for so long. It cannot be Thames ‘super sewer’ will
Wastewater capacity increases are continually put back. ensure we can manage new
for many years. These standards London is a world-leading city, challenges and the demands of
under way across the capital were nowhere near as high as and its success leads to continued a growing capital.
those we expect today. growth. We now need to invest in
38 The time has come to decide the future in the same way that the Boris Johnson, London mayor
Procurement what we are going to do for the Victorians had the foresight to do
next 150 years. 150 years ago.
Getting the best from the Our planned London Tideway
best construction firms Improvements programme is Martin Baggs,
about building on the past and chief executive officer,
42 creating a legacy for the future. The Thames Water
Skills & jobs upgrades to London’s five main
sewage treatment works along the
The Tideway Tunnels will be
River Thames, the Lee Tunnel and
London’s biggest employer the proposed Thames Tunnel will
Becoming
a reality
Planning and consultation
Bernadette Redfern
150
a wet year it can be three times that,” These improvements will be completed proposed Thames Tunnel is still some
says Phil Stride, head of London between 2012 and 2014. way off. Two years in fact. It depends
Tideway Tunnels at Thames Water. “At The second element of the on the scheme obtaining planning
some CSOs it takes only 2mm of programme is the Lee Tunnel which is permission. The first round of public
rainfall to generate a discharge and about reducing flows discharging into consultation began in September and
People in the project team clearly this is not acceptable,” he says. the River Thames as soon as possible. will end after a 14 week period. After
The London Tideway Improvements The project involves the construction of considering the feedback, the project
programme has three elements, all at a storage tunnel to intercept the largest team will then review the design and
9%
different stages of development. “The single CSO accounting for an average present a final proposal for a second
sewage works upgrades are already of 16M.m3 in discharges every year. consultation round commencing in
underway. This is the extension and This CSO is located at Abbey Mills spring/summer 2011. A planning
modification of Thames Water’s pumping station in Stratford and will submission is scheduled to be made in
sewage treatment works discharging be mitigated by the 6.9km, 7.2m 2012.
Design complete to the tidal River Thames – at Beckton, internal diameter Lee Tunnel, which Plans for the Thames Tunnel itself
under central
THELondon
THAMES TUNNEL over 50% fewer proposed
worksites.
After two and a half years of detailed
design work involving over 150
Thames Tunnel professionals, the Thames Tunnel team
has reached a critical milestone. The
Bernadette Redfern team which is made up of civil
ISLINGTON
The Thames Tunnel
The Thames Tunnel project would not only
create one of the largest and deepest tunnels
in London but would create a cleaner, healthier
CSO
Combined Sewer Overflows allow
London’s combined storm
sewage system to overflow in wet
34
Number of CSOs captured by T
Thames. It would extend the capital’s Victorian weather. As little as 2mm of rain the proposed Thames Tunnel HA
sewers to meet 21st century challenges and is enough to cause overflow and
Blackfriars
C
capture approximately 39M.m3 of sewage discharge of sewage to the River CITY OF
Thames Bridge
discharged to the Thames each year Foreshore LONDON
EALING Victoria
CITY OF WESTMINSTER Embankment
Foreshore
Acton Storm Tanks
Houses of
Parliament
HAMMERSMITH Chelsea
& FULHAM KENSINGTON Embankment BE
& CHELSEA Foreshore
HOUNSLOW Albert
Hammersmith Embankment
Pumping Station Foreshore
GEOLOGY PREFERRED ROUTE London Clay Thanet Sands & Lambeth Beds
Acton storm tanks Barn Elms (main shaft) Tideway Walk (main shaft)
5
Main shafts
17
CSO diversion shafts
engineers, project managers, planners, shorter than the original project Thames, collecting the sewage from
hydraulic specialists and environmen- presented to the Department for the “The preferred route the worst polluting combined sewer
talists has developed what it believes is Environment Food and Rural Affairs option is 9km shorter and overflows (CSOs) along the way. All
the most technically appropriate and (Defra) in December 2006. three routes will deal with 34 of the 36
about £700M cheaper in
cost efficient alignment for the new “The preferred route option is 9km CSOs that were identified as a priority
sewer tunnel that is set to reduce the shorter and about £700M cheaper in relative terms” by the Environment Agency, the other
volume of sewage overflowing into the relative terms,” says head of London Phil Stride, head of two CSOs being dealt with by separate
River Thames by 96%. Tideway Tunnels Phil Stride. London Tideway Tunnels Thames Water projects. And all three
Although three potential routes The proposed project fundamentals routes will ensure that London is
have been identified, the Thames remain unchanged. The 7.2m internal compliant with the requirements of
Tunnel team has now developed a diameter tunnel would start in West the European Union Urban Wastewa-
preferred option which is significantly London and run beneath the River ter Treatment Directive.
graphic: © www.paulweston.info
Abbey Mills Route
Abbey Mills
Pumping Station
6.9km Beckton Sewage
Treatment Works
(preferred) t (main shaft site)
TOWER Cu Lee Tunnel
u se (under construction)
HAMLETS e ho
Butcher Row Lim
ath
King Edward ne
Be
Memorial Park NEWHAM
Foreshore
King’s Stairs
The O2
Gardens Arena WOOLWICH
(major work ISLE OF
Druid Street
site for DOGS
connecting
tunnels) Earl Pumping Legend
BERMONDSEY Station CSO - Combined sewer
River GREENWICHN overflow
Thames Tunnel -
Thames Route common to all options
Rotherhithe (alternative option) Abbey Mills Route
Route (alternative (preferred)
option) Lee Tunnel
Greenwich Pumping Station
Borthwick Wharf Foreshore River Thames Route
Rotherhithe Route
SOUTHWARK Preferred sites
LEWISHAM
22km
The length of the
7.2m 35 - 75m 5 million
The diameter The depth of the tunnel Tonnes of material would
Thames Tunnel for of the tunnel below London be excavated during
storm & waste water construction of this tunnel
STORAGE of 1.5M.m3
The tunnel will have the capacity to
ands intercept and capture, acting as a huge 75m
Chalk storage tank
ISLINGTON TOWER
HAMLETS
C
CITY OF
“The interceptor sewers LONDON
Tunnel follow the original alignment facilities required at the main tunnel
but with a major diversion at drive sites. In total we are going to be
Limehouse leading the tunnel into the handling 5M.t of excavated material
FLeeT MAIn HoLLowAy newly constructed Lee Tunnel arising from the TBMs. So there is a
beginning at Abbey Mills in Stratford massive amount of work to do, and
and running along to Beckton Sewage planning out the logistics strategy at
Treatment Works. This option only this stage is essential,” says Stride.
emerged following design changes to The major work sites will require up
the 6.9km Lee Tunnel. “Initially the to approximately 20,000m2 of land
design for the Lee Tunnel at Abbey take and involve 25m diameter shafts
Mills was not low enough to take flow that will potentially be driven to depths
by gravity from the Thames Tunnel,” of up to 75m in the east.
says Stride. By reducing the number of principal
“A geological feature known as a main construction sites to just five the
graben, the German word meaning team has potentially reduced the
ditch, was discovered during the disruption on the surface. In determin-
Holloway NEWHAM investigations for the Lee Tunnel. This ing the possible location of these five
Storm Relief
feature consists of a series of sites a rigorous site selection process
WOOLWICH down-faulted blocks of ground creating was followed, beginning with
The O2 an area of potentially disturbed ground examining land 500m either side of
Arena
ISLE OF and variable face conditions. the River Thames. Immediate
DOGS
Beckton Sewage “We realised that it would be better exclusions were applied to World
GREENWICH Treatment Works to lower the Lee Tunnel by 10m to Heritage Sites, existing concentrated
minimise the length of tunnel through residential areas, the Palace of
this disturbed zone,” says Stride. “This Westminster, Westminster Abbey, St
then presented us with the option of Margaret’s Church, the Tower of
graphic: © www.paulweston.info
LEWISHAM
shortening the main Thames Tunnel London and Maritime Greenwich.
and connecting it in at Abbey Mills.” The second step was to create a long
Having developed a possible route list of potential sites within the 500m
that is only 22km long, approximately zone using desktop surveys, aerial
9km shorter than the original photos and Ordnance Survey maps.
proposal, the team then set about These sites were then evaluated using
rationalising the design and minimis- environmental, planning, engineering,
ing the construction impacts. “There property and community impact
was concern that by potentially taking assessments leading to a draft shortlist
this route we would miss out the CSO of sites. Further scrutiny led to a final
at Charlton, but we would deal with shortlist and after site suitability
this using other measures,” says Stride. studies were carried out, a preferred
These “other measures” are in fact shortlist was created. “ The four drive
being used on a number of the CSOs shafts proposed for the preferred
along the routes and include things like scheme are at Barn Elms, Abbey Mills,
connection tunnels and hydraulic Tideway Walk for the main tunnel, plus
adjustments to the existing system to significant connection tunnel
prevent overflows. Part of the effort to construction from King’s Stairs Gardens
minimise disruption means reducing (see map). We envisage construction
the number of work sites at the surface at these points will be ongoing for
Barn elms: Proposed TBM launch site and the design team has had great around seven years,” says Stride.
success in eliminating the need for The same methodology was also
surface work. “This is great news from applied to the CSO connection shafts
an engineering design development which will divert the overflows from
perspective. The original route looked the CSOs into the new tunnel.
at six main shafts with five intermedi-
ate shafts. We have potentially
narrowed this down to just three main
tunnel drive shafts and a further drive “Lowering the Lee Tunnel
site for the most significant connection by 10m at Abbey Mills
tunnels in the east” says Stride.
presented us with the
The main drive shafts are the sites at
which the tunnel boring machines option of shortening the
(TBMs) would be launched and these main Thames Tunnel”
sites would operate 24 hours a day to Phil Stride head of
maintain tunnelling operations.
King edward Memorial Park: Proposed site for North East Storm Relief CSO “There are significant construction
London Tideway Tunnels
Thames Tunnel
sewers backing
up when sytem
Overflow pipe is overloaded
with rainwater
96%
net
San internal
ds diameter Landin
“The smaller CSO shafts will have a connection tunnel at the base would Low level interceptor sewers run key CSO drop shaft locations. By adding
much shorter construction periods of divert the flow into the Thames Tunnel. along either bank of the Thames and three connections into the low level
two to three years. These sites typically For the CSOs that do not have single are known as the North and South Low sewer and relieving pressure on the
vary in size from 300m2 to 3,000m2,” dedicated shafts, longer connecting Level Sewer. system with the other drop shafts we
says Stride. pipes are proposed to connect two or By making a number of strategic are diverting the same number of CSOs
“The key difference between the three CSOs into one shaft. In other connections into the northern low level with the least amount of disruption, “
main shafts and the CSO shaft sites is locations some hydraulic adjustments interceptor sewer, additional hydraulic says Stride.
the amount of activity and materials are proposed to prevent overflows capacity in this existing sewer can be The project requires a significant
storage required. The smaller shaft from occurring. created, allowing CSO flows to then be number of sites to be in the foreshore
sites would have working hours of conveyed through the existing system. and is a key reason for the rise in the
typically 8am to 6pm,” explains Stride. This significantly reduces the number cost estimate for the scheme (see
The team has developed alternative of CSO interception shafts required. intro). At many locations no viable
ways to collect the sewage from the 34 “It is not really a sewer, even “It [the low level interceptor] really land-based locations were identified.
CSOs, which has been achieved with though it collects sewage. It acts as a hydraulic conduit. In some However work in the foreshore
only 22 shafts in total, with CSOs is really a vast underground areas we have been able to prevent massively reduces work on the surface,
combined where possible with the CSOs from overflowing by increasing for example, service diversions. It is
main tunnel shafts. For the majority of
storage tank” the weir height,” says Stride. also considered to be much less
the overflows the shaft would sit Phil Stride, head of “This keeps flows in the sewer disruptive. Work in the foreshore would
adjacent to the CSO and once the London Tideway Tunnels instead of overflowing. Then we require some heavy engineering and
sewage has poured into the new shaft connect to the low level interceptor at creates the need for some permanent
Combined
Sewer - Sewage
and rainwater
run off The hydraulic challenge CSOs: The worst offenders
The vertical shafts that would rotational effect. “The floor of the
HYDRAULIC CHALLENGE transfer storm sewage into the new channel also drops to accelerate the
ANALYSIS
One of the great challenges
50+ m
Influent drop
Thames Tunnel present a range of
hydraulic challenges to the
flow before entering the tube,”
explains Thomas.
designers working on the project. “Both types of drop structures
of this project was what to
Connecting need to control the amount of air
do with the energy and
turbulence caused by the culvert As the influent is set to drop as much entering the tunnel,” says Thomas.
50m + drop to the Thames as 50m, the team has to contend Essentially, air that gets into the
Tunnel. The designers used
Vortex with the turbulence created when system could build up into significant
extensive 3D modeling and
drop the water reaches the bottom of the air pockets that Thomas likens to
computational fluid Vortex drop Transfer shaft. “There is a lot of energy “big springs”. The pressure of these
dynamics modeling to shaft created when a mass of water drops could be enough to force water back
explore a number over this distance,” says design up to the surface of the ground, if
of solutions manager Gareth Thomas. “And we not properly designed. “Clearly this is
have two main options for dealing totally unacceptable and we have to
with this.” ensure that there will be no
Landings Thames The first involves the construction significant air pockets in the system,”
tunnel of a series of steps within the shafts, says Thomas.
referred to as a cascade. The water The first step was to use a 2D
drops onto a series of landings catchment model built using
designed to allow the water’s energy Info-works software platform. “This
to be progressively dissipated. “This models the catchment characteristics
obviously involves a lot of construc- and gives the flow rates into the new
tion and it has operational system and allows us to check the
challenges as all these landings need levels so that there is no flooding or
to be inspected and maintained,” surcharging,” says Thomas.
says Thomas. The next step was to develop 3D
The second method favoured by models using a computational fluid
the team is the use of vortex drops, dynamics package to replicate how
where the sewage is introduced to the water will move through the
the shaft in a way that encourages it drop shafts and tunnels. This was
to spiral downwards around the followed by the creation of physical
outside walls of the vortex tube. To models of some of the larger drop
create the swirling motion required structures and shafts, which is
for the sewage to flow correctly, the allowing the team to see how the
connection sewers will taper on water and air in the system are
approach to the shaft creating a behaving. “
structures once construction is team envisages extending the river the Environment Agency were for a Dissolved oxygen is a crucial
completed. For example at Blackfriars wall and creating a new hard standing storage system with a capacity of measure as a certain level is required
Bridge, the Fleet Main CSO must be area to support the required structures. 1.6M.m3 and, although the new route to sustain aquatic life. Stride says that
intercepted but the area is home to a Construction at this location would take gives a cumulative storage capacity the reduced volume is not going to
network of existing infrastructure in excess of three years. (including Lee Tunnel) of just less than cause bottlenecks or system con-
making this a highly congested area. A key concern for the team when this at 1.5M.m3, the Agency has straints. “It is not really a sewer even
Along with the road and rail bridge excavating in such locations is the reviewed the preferred option and says though it collects sewage and has a
are the District Line, Waterloo & City potential for archaeological finds that that it meets the threshold levels for gradient from west to east. It is really a
Line, EDF’s Bankside cable tunnel, the could delay the project and increase dissolved oxygen. vast underground storage tank. It is not
Victoria Embankment (A3211) and the costs. “We obviously have to being designed as a conventional
Blackfriars Underpass. incorporate some contingencies in the conveyance pipeline,” he explains.
To prevent disruption here the team event that we do find something and After its progress on developing a
is proposing to carry out the work further investigation is required,” says “It appeals more to preferred route the team is now
along the foreshore but this would Stride. the market to make focused on the next major milestone
result in the need to realign the river The result of the design team’s the packages a for the tunnel: achieving planning
wall and install long term structures for efforts is a slightly smaller, but much permission. Extensive public consulta-
ventilation and air filtration facilities. cheaper stormwater storage system
manageable size” tion is now underway and the first
Views are to be sought from the public that prevents 96% of sewage from Phil Stride, head of round of this will last for 14 weeks.
and stakeholders on site location, and overflowing into the River Thames. London Tideway Tunnels The feedback will be used to modify
how these structures should look. The Recommendations originally made by the plans and address any concerns
before a revised design is published for Paddington. “We have worked very majority of people see that this project
consultation in mid 2011. A planning hard to develop what we believe is the is really needed,” says Stride.
application would then be made to the optimum solution according to the “While a lot of work has been done
Major Infrastructure Planning Unit at challenge that was set by government. in developing a preferred scheme, no
the Planning Inspectorate in 2012. By engaging with stakeholders and final decisions on tunnel route or site
Construction of the Thames Tunnel working as a team we have come up locations have been made. The first
is then expected to begin in 2013, with what I believe is a feasible and phase of public consultation will be the
with the expectation of four or five buildable scheme in terms of land start of a major engagement that will
major contracts. As with the required and getting disruption to a help us decide the selected scheme
neighbouring Lee Tunnel and fellow reasonable level. I do not think this that we will be then submit for
giant tunnelling project Crossrail, the would have been the case with the planning consent.
Thames Tunnel team leaders expect original scheme proposal.” “Although nothing is set in stone at
that consortiums of international and Although the public consultation is this stage, if London wants to remain a
UK based tunnelling experts will bid for just beginning the tunnel team has key international city, then something
these enormous packages of work. already conducted extensive initial has to be done about the sewage
“It appeals more to the market to engagement with stakeholders in a bid overflows,” says Stride, who is keen to
make the packages a manageable size to seek the best way to design and ensure that all stakeholder concerns
and from a client’s perspective it build this much needed environmental “Both types of drop structure are heard and considered carefully. But
means that you don’t have all your solution. “There isn’t a wastewater need to control the amount at the same time he and the team are
eggs in one basket,” says Stride. project anywhere in the UK that has excited about building the UK’s longest
Stride says that the extensive design gone through such an urbanised area
of air entering the tunnel” and deepest ever tunnel. “In the
work and reduction of site disruption is and dealt with so many local Gareth Thomas, history of the UK water industry there
due to the dedication of the team of authorities. To date we have done over design manager has never been a larger or more
international experts based at 200 presentations and the vast exciting scheme.”
King’s
Bench
Walk
John Carpenter Street
Carmelite Street
Watergate
Temple Avenue
Artist’s impression: How the above ground structures will look Fleet storm
Inner Temple Low Level Sewer relief sewer
ock
Garden
Puddle D
CSO t
District & en Blackfriars
drop shaft n km
Circle line
m ba Station
i aE
tor
Vic
CSO
Main construction site intercept
Proposed Vent
tunnel column chamber
Jetties & Wharves
route
Low level Short term
sewer intercept construction site
chamber
Blackfriars Bridge
River Thames
graphic: © www.paulweston.info
City of London
C
Blacfriars
work site Southwark
Lambeth
LONDON
50m
N
Multiple methods
for variable ground
The boring challenge
Bernadette Redfern
Overcoming
challenges
Learning from the Lee Tunnel
Bernadette Redfern
By the time boring of the accelerator (sodium silicate) which to be processed once removed, so the
proposed Thames Tunnel is means that the grout leaves the unit as optimum for these work sites is
a gel. However blockages of this thicker 18,000m2,” he says.
due to begin, in 2014/2015
grout can occur and the usual method In terms of removing the excavated
the 6.9km long Lee Tunnel to deal with it is to push a mechanical spoil the Lee Tunnel team is using a
will be complete. This will reamer and a high pressure hose filter press system to separate the fine
provide the Thames Tunnel through the lines. However, this has chalk particles from the water. Derek
water ingress risks, and to prevent this Arnold says that this could also be used
engineering team with Butler says the team has created a on the Thames Tunnel at the chalky
valuable information to Y-shaped piece that can be screwed eastern bore, but that the manage-
help mitigate project risks. into the accelerator additive location ment team is looking at options and
on the tailskin,so the reaming machine would listen to contractors’ sugges-
can be inserted through a stuffing box tions. The chalk is then being removed
From the outset the Lee Tunnel project while controlling the flow of water on the Lee Tunnel project by barge and
team has worked hard to mitigate through the other branch of the Y this is another option open for
potential problems. “We engaged with piece. This allows the blockage to be excavated material on the Thames
MVB early and have held risk meetings cleared without allowing in water. Tunnel but economic and impacts
“We engaged with MVB throughout. We identified some really “The same techniques should be of analysis must be carried out to discern
early and have held risk critical issues from managing and benefit to the chalk tunnelling in the whether or not the river route is most
meetings throughout” removing spoil to reducing wear on the eastern end of the Thames Tunnel. It sustainable. “We are committed to
Nick Butler, Lee Tunnel cutterheads,” explains Nick Butler should provide excellent experience as using the river wherever economic and
tunnel construction manager on the by the time the Thames Tunnel starts practicable as it may lend itself to high
Lee Tunnel project. we will know how successful our volume movements of material. But
Butler credits the broad expertise of methods have been,” says Butler. smaller volumes of materials coming
the project team in putting measures The design team planning the in to the sites may need to come in by
in place to mitigate potential problems Thames Tunnel will still have big road,” says Maurice Gallagher,
before they arise. “Empirical evidence challenges of their own to overcome. construction and logistics planner.
from the team told us that larger disc Preparing the sites for the arrival of the In addition to the main bores
cutters have a higher longevity. We TBMs means allocating sufficient space anticipated for the Thames Tunnel, on
had nominally identified 17 inch cutters for the access shaft, excavated material the preferred route 10.6km of
in the original specification and are storage and segmental ring storage. connection tunnels would also be
now using 19 inch. Our studies show “Ideally, the main work site for the driven to provide a route for the
that this will give us 40% extra life on slurry machine needs to be around sewage into the new main tunnel.
40%
the tools,” he says. 20,000m2. Smaller sites are feasible if These would range in size from
Another challenge identified by the space is limited,” explains Thames 2.2m internal diameter to the
Lee Tunnel “TBM task force”, which Tunnel design manager Derek Arnold. largest at 4.5m internal diameter at
included members from contractors “For the EPB sites we don’t need so King’s Stairs Gardens in Southwark
MVB, TBM manufacturer Herrenknecht much space as the spoil does not need running for 4km along to Greenwich
Greater life expected for cutting and Thames Water, was the potential Pumping Station.
tools following risk analysis for high pressure water to enter the Construction of the new Thames
tunnel when unblocking the grouting “The same techniques Tunnel with its major work sites and
system. The water pressure on the face connecting tunnels is a number of
6.9km
should benefit the chalk
of the TBM will be 7.5 bar at maximum years away, but experience from sister
depth, so any pathway could expose tunnelling in the eastern project the Lee Tunnel will be a key tool
the TBM crew to dangerous, end of the Thames Tunnel” in ensuring that the UK’s biggest ever
pressurised water. The two part Nick Butler, Lee Tunnel waste water project is delivered on
Length of the Lee Tunnel grouting system uses a chemical time and to budget.
382,000m3 16M m3
graphic: © www.paulweston.info
LEWISHAM
Total Capacity of Sewage overflow
tunnel and shafts diverted each year
The main construction equivalent to over 60 spills every year, John Corcoran.
meaning that the CSO is needed on In exceptional circumstances, when
phase of the Lee Tunnel will average more than once a week. the entire storage space of 382,000m3
begin this Autumn creating Designing and building the Lee provided by the tunnel and shafts is
the deepest tunnel in the Tunnel is the Morgan Sindall/Vinci filled with storm sewage, additional
capital diverting 16M.m3 a Construction Grand Projets/Bachy Sole- overflows will continue 0.85km further
tanche partnership known as MVB. In down the Lee Tunnel to an overflow
year of sewage overflows extreme storm events, the £635M culvert that will empty directly into the
into the Thames. sewer will act as an underground Thames. It is anticipated that it this
storage tank until the Beckton Sewage might happen six to eight times per
The Lee tunnel may only capture Treatment Works has capacity free to year on average. This would reduce
discharges from one combined sewer treat the additional load. Stored further once the Thames Tunnel is
overflow, and it may only run for overflows are then pumped out more completed.
6.9km, but the smaller of the two than 6km south east to the sewage The Lee Tunnel will total 6.9km in
tunnel projects certainly packs a punch, treatment works. At the moment the “Each pump will have a length, with an internal diameter of
and its benefits will be significant. sewage treatment works is being pump out rate of 3m3/ 7.2m. But the most remarkable thing
In diverting the discharges from the expanded to deal with these increased second. They will have a about it is the depth. At its lowest point
combined sewer outfall (CSO) at Abbey volumes. This involves increasing the tunnel dives down to 75m below
Mills pumping station in Stratford the capacity from 1,426M.litres/day to vital role in the functioning ground and its shafts will boast what
Lee tunnel will prevent a massive 2,333M.litres/day. “In principle this is a of the project” MVB believes are the deepest
16M.m3 of untreated storm sewage massive storage tank that transfers François Pogu, Lee Tunnel diaphragm walls in the UK. This
from pouring into the River Thames via flows to Beckton,” says MVB extreme depth is designed to enable
project director, MVB
it major tributary the River Lee. This is enabling works and tunnel manager the storm sewage to flow downwards
graphic: © www.paulweston.info
Abbey Mills Shaft Beckton Tideway pumping Beckton
Connection station shaft overflow shaft
25m shaft
diameter 38m
diameter
68m
depth
25m Pumping 20m Beckton
1.2m diameter station diameter outfall
diaphragm
wall thickness
4 or 5 3.5MW 3m3/s culvert
(to the
Number of
pumps
Power of
each pump
Pump out rate
of each pump 86.5m Thames)
78.5m depth
depth
1.8m 74.5m
depth
Thames 1.5m diaphragm
wall thickness
Tunnel 83m diaphragm wall thickness
1.5m
Connection diaphragm wall depth Suction tunnel diaphragm
wall thickness
90m
TUNNEL SECTION GEOLOGY 92m 98m Beckton diaphragm
wall depth
diaphragm diaphragm overflow
of the deepest wall depth wall depth tunnel
Precast concrete tunnel in london
tunnel
segments Abbey Mills Made ground/Aluvium Harwich formation Beckton Works
River terrace gravel
83m
London Clay
The Plaistow
Graben
Lambeth group
Thanet sand
98m 1.7M t
7.2m White chalk subgroup
6.9km
Material removed
boring the Lee Tunnel
to Beckton while also avoiding the connection shaft, and another will be located; and a third site to existing structure obstructions ahead
warren of tunnels, pipelines and cables connecting the Beckton overflow shaft house two new batchers that will of shaft construction.
that exists under London, particularly to the River Thames. supply concrete for the entire works “We have removed the old Victorian
the Olympic Park cable tunnels. “We’re Tunnel and pump shaft work sites from within the Beckton site. “That will infrastructure underneath the first
below the normal obstacles or utilities will be limited to Abbey Mills and limit transport movements around the shaft site as it could have affected the
that you might encounter on a Beckton, meaning that the main site,” says Corcoran. Meanwhile, excavation of the diaphragm wall
transport tunnel,” says CH2M HILL Lee construction phase will take place on precast concrete sections for the tunnel which has extremely tight verticality
Tunnel project manager Robert land already owned by Thames Water. will be cast at Ridham Dock in Kent. tolerances,” says MVB project engineer
Hayden. “The Thames Tunnel is a vast project Enabling works are underway at Martin Stanley.
The tunnel will feature four shafts: a which needs considerably longer to Beckton which include clearing the For example a 19th century
connection shaft at Abbey? figure
Mills to take plan and build, whereas the Lee Tunnel work sites and preparing access roads, pumping station was previously
overflows from the CSO down fortowall
the could be procured and developed in as well as extensive coring to remove housed at Beckton, and after the
tunnel; a connection shaftthicknes
at Beckton advance because we own the launch station was demolished its basement
to take flows from the tunnel to the site for the tunnel boring machine was filled with foam concrete. It is part
pump station shaft; a pumping shaft (TBM) and the finish site,” says Thames of the basement that MVB has
adjacent to that which will pump the Water head of capital delivery “We’re below the normal removed with the coring. A listed
sewage up to the treatment works Lawrence Gosden. obstacles and utilities that masonry chimney designed by
when appropriate; and an overflow Abbey Mills, where the tunnel ends, you might encounter on a Bazalgette as part of the improve-
shaft which overflows into the River will house one work site, while Beckton ments to the northern outfall sewer at
Thames. The scope of works also will have three – one at the overflow
transport tunnel” Beckton between 1887 and 1889 was
includes two culvert systems at either shaft, which will be the starting point Robert Hayden, CH2M HILL, previously positioned over the area
end of the Lee Tunnel – one set for tunnelling; one at the point where Lee Tunnel project manager where the overflow shaft is to be built.
connecting the CSO to the Abbey Mills the connection and pumping shafts So this has also had to be temporarily
Ground breaking Victorian waste. First appearing in the medieval Unusually hot summers in 1855 and
construction created a era and growing steadily more 1858 made the Thames’ stench of
ubiquitous over the following untreated sewage unbearable. By this
sewerage system for London
centuries, cess pits stored sewage until time more than 400,000t of sewage
that has endured for over a being emptied by rakers. flowed into the Thames each day,
century but more innovation Some were designed with culverts totalling around 150M.t a year.
is required to secure its to channel overflows into the street or The warm weather caused bacteria
into a water course – which was illegal to thrive – but left the river otherwise
future. but still common. For those without ecologically dead. “It was devoid of
Sir Joseph Bazalgette is widely such a culvert, backed-up cesspits led life,” says Environment Agency tideway
recognised as a Victorian pioneer in to overflows on their land that not only strategy project manager Isobel Bain.
civil engineering. As the chief engineer threatened public health and “It was noxious; it was almost septic,
of the Metropolitan Board of Works he damaged buildings, but were black and bubbling.” Cholera had also
created the sewers, pumping stations extremely unpleasant. become widespread and was at the
and treatment works that have By 1850 it was made legal to time believed to be caused by airborne
allowed Londoners to enjoy a reliable connect cesspits to sewers but ‘miasma’ from the sewage in the
In 1859 Bazalgette sewerage system for 150 years. London’s population was by now grow- Thames. While the disease was
proposed a network of However until Bazalgette’s ing at an alarming rate. The city had actually caused by bacteria which
intervention in the mid 1850s the city’s expanded into surrounding rural areas, spread through the contaminated
huge underground brick sewage system was in a grim state. In tripling its land area between 1802 and drinking water, its association with the
sewers to intercept sewage medieval London, which existed as the 1832. Building companies began to foul rivers was accurate.
outflow City of London, with Westminster still construct man-made sewers that Parliament, being housed next to
just a town a few miles up the river, channelled away household waste. the river, could not fail to notice the
15
waste was simply jettisoned into the These were built speculatively by growing problem. Limited action had
street. This led to the development of a private companies, resulting in poorly been taken through the Metropolitan
fleet of rakers, who collected street planned and constructed – and often Commission of Sewers Act 1848 which
waste on carts and took it to ‘laystalls’ open – sewer systems. had created a commission to survey
outside the city. In the late 14th century By the mid-18th century, all public London’s sewerage system. The
rakers were taken on by the govern- waterways had become foul and Commission decided to close the open
The number of years it took to build ment at public expense, marking the contaminated, compounded by the cesspits, but its work was disrupted as
Bazalgette’s sewer network beginning of an organised industry for growing popularity of flush toilets, the Commission was repeatedly
the disposal of waste. introduced in the 1780s. disbanded and reorganised before
At that time, the word ‘sewer’ All sewage was eventually being superseded in 1855 by the
referred to any water course in the city, channelled into the Thames, from Metropolitan Board of Works led by
whether it contained human waste or which water companies pumped it Joseph Bazalgette.
not. It was only later, when these rivers back into the water supply. The In 1859 Bazalgette proposed the
and streams became constantly used situation climaxed in the 19th century construction of a network of huge
as channels for waste that the word with the infamous Great Stink of 1858 underground brick sewers to intercept
‘sewer’ took on its modern meaning. forcing action from government. sewage outflows, diverting them to
Accordingly, in 1531 the Statute of where they could be more safely
Sewers created Commissions of Sewers “In 1855 the Thames was deposited in the Thames downstream
which had the authority to oversee from London. The city’s topography
maintenance of London’s water noxious; it was almost made pumping stations necessary to
courses, protecting flows and dealing septic, black and bubbling” maintain the flow, so Bazalgette
with damage. Isobel Bain, planned for major ones to be built at
Cess pits were the first chambers Deptford, Crossness, Abbey Mills and
Environment Agency
built specifically as receptacles for Chelsea Embankment. Beckton and
Blac
Mid works,
Ty
k Le
stb
Walbrook e
b
Ditc
urn
Beckton
ou
graphic: © www.paulweston.info
INTERCEPTING SEWERS
Bazalgette devised a network of River Thames
sewers to intercept sewage outflows Ear
l ’s e er To
Sluic l sew
rn o u t fa l Southern
So uthe outfall
er
el sew works
Effra
l ev at Crossness
l ow
e
ern
sbourn
South
Southern high level sewer
oke
bro
Falc
Raven
Kid
on
TIME LINE
1844-47
Metropolitan buildings act
1848
Various commissions looked
1849
Fish had disappeared
1858
The Great Stink forces
1865
First phase of Bazalgette’s
requires all new buildings be at the problem of pollution from the Thames action by government system is opened
connected to common sewers in the Thames
£675M
the legacy of the original Bazalgette declares Gosden. First the site has set “Essentially we are adding a third
sewerage scheme to clean up Victorian up a “site integration team” formed stream to the secondary treatment
London. Beckton, covering 132ha, is from members of Thames’ own capital process,” says Thames Water project
Europe’s largest treatment plant, and works team, from the senior contracts manager Jaymin Patel.
The amount being spent on upgrades will have a through flow of 27m3/sec operations staff, and then from the There will be new grit removal and
at five wastewater treatment works when work finishes in 2014. Crossness consultants and contractors. These are screening channels, primary sludge
over the next five years has just over half the capacity of its primarily C2HM HILL and Tamesis, a settlement, new aeration tanks and
northern sister. Laing O’Rourke-led consortium with then 16 new final settlement tanks,
60%
Each is getting a significant water specialist IMTECH. Tunnel each 44.5m in diameter. Additional
expansion to its treatment capacity, contractor consortium MVB compris- pumping is also required, as is a
ranging from initial grit removal and ing Morgan Sindall, Vinci Construction blower house for the feed to the fine
screening through primary sedimenta- Grands Projets with Bachy Soletanche bubble diffusers at the bottom of the
Increase in capacities during storm tion to secondary treatment. is also represented. 7.5m deep process tanks.
flows created by the programme New aeration tanks will allow much “The team meets frequently and Most of this is being built within the
Cleaning up
the River Thames
Environmental drivers
Bernadette Redfern
Preventing sewage from treatment facilities for large towns and says that the sewage causes other
overflowing into the River cities must put in place adequate problems too.
Thames is set to ensure treatment facilities by December 2005. “The tidal Thames is an important
The legislation does allow habitat for juvenile fish, and these are
London meets European discharges from the system under adversely affected by sewage
legislation and will storm conditions. Unfortunately not all discharges. Regular CSO discharges
significantly improve the of the CSOs in the River Thames need could inhibit or prevent juveniles
storm conditions to overflow. “There joining adult populations in the North
waterside environment. has been much debate as to whether Sea, including sensitive species such as
the current system is compliant as the salmon, sea trout and smelt,” she says.
The three major engineering projects situation with regard to discharges In determining the extent of the
that make up the London Tideway from CSOs is far from clear cut,” says problem, Thames Water created a
Improvements scheme are set to de Garis. hydraulic model of the network, which
provide a raft of environmental Following extensive research the was then verified by field based
benefits to the tidal River Thames. Department for the Environment Food investigation. In doing this a range of
“A CSO incident at the wrong The Beckton and Crossness and Rural Affairs (Defra) and the assumptions surrounding the effects of
catchments, which serve central Environment Agency decided that the CSOs were made, including that
time can wipe out a whole London, discharge 39M.m3 of remediating the 36 most polluting 10% of the litter in the river is caused
load of fish that are less than untreated storm sewage into the CSOs was necessary if the directive’s by sewage discharge.
one year old” Thames in an average year. requirements are to be met. “We would then look at the
Yvette de Garis, head of By preventing sewage from “In 2007 the minister at Defra wrote proportion of that 10% that would
discharging into the waterway from to Thames Water and required us to be linked to the CSOs by volume,”
environment and quality the 36 most polluting combined sewer progress with the development of a says de Garis.
strategy, Thames Water overflows (CSOs), aquatic life will scheme to remedy the situation,” says “Similarly we built a model that
benefit from reduced depletion of de Garis. made predictions on how water quality
dissolved oxygen, currently depressed Thames Water had also been would change under a CSO event and
as a consequence of untreated storm studying the impact of the CSOs on varied the parameters to reflect the
sewage entering the riverand the river. “What we found was that increased load expected in the future,
triggering bacteriological activity. discharges from the CSOs led to an including climate change effects. This
Reducing sewage derived litter is increased risk of health-related model would then predict the variation
also a very welcome outcome, as is the illnesses, an increased risk of sewage of dissolved oxygen in the river as a
expected reduction in potential health derived litter in the river and an result of the discharges.”
problems related to exposure to increased risk of fish kill,” says de Garis. Another key issue that Thames
10%
untreated stormwater discharges. “A CSO incident at the wrong time Water’s research identified concerned
“There has been concern over the can wipe out large numbers of fish fry the quality of effluent being dis-
impact of the combined sewer – fish that are less than one year ol d.” charged from the five major sewage
overflows on the Thames Tideway for The main reason for the damage to works along the river.
some time, but what has brought it to aquatic life is the increased competi- “When we modelled the Tideway
a head is the issue of compliance with tion for dissolved oxygen created when we found that the problem wasn’t just
Of the litter in the Thames is caused
the Urban Waste Water Treatment untreated storm-combined sewage is about the discharges during storms
by sewage discharge
Directive,” explains Thames Water introduced to the river. This contains but there were also underlying
head of environment and quality bacteria which compete with the problems with the discharge quality
120
strategy Yvette de Garis. natural demand for oxygen from fish coming from sewage treatment works.
The Urban Waste Water Treatment and other aquatic life and increases This showed that the estuary was
Directive is a wide ranging piece of what’s known as the biochemical already under stress when storms
European legislation that came into oxygen demand (BOD). occurred.”
force in May 1991. It requires that all Environment Agency tideway In response, a £675M programme
Species of fish recorded in the Thames wastewater collecting systems and strategy project manager Isobel Bain of upgrading the sewage treatment
MIGRATORY FISH
Particularly affected are
migratory fish such as
Cormorant Salmon
38
Species of birds
350
Species of
salmon, sea trout and smelt
supported by the invertebrates
tidal Thames found in the
BIOCHEMICAL Thames
OXYGEN DEMAND
Untreated sewage discharge
depletes the dissolved oxygen in
the water killing fish and increasing
Sea trout
bacteriological activity
Smelt
120
Species of fish FRY
recorded in the A CSO incident at the wrong
graphic: © www.paulweston.info
INCREASED Thames time can wipe out vulnerable
BACTERIOLOGICAL fish fry
Eel
ACTIVITY
39M.m3
Average volume of untreated sewage
57
The number of sewage
10%
Of litter in the
discharged into the Thames each year outfalls along the tidal Thames caused by
Thames sewage discharge
works through expanding the facilities congestion, air quality impact, waste
An army of volunteers
was commissioned to improve the “As a world class city, generation and noise.”
baseline condition of the estuary. Over the past 15 years a small London needs a clean An additional factor is that the River
As for the CSOs in the sewer army of 8,000 individuals has Thames is currently failing to meet
network, the proposed Thames been working away to clean up
and healthy river” challenging water standards that were
Tunnel will capture discharges from London’s waterways. Isobel Bain, Environment ushered in by the Water Framework
34 of these by 2020. But the biggest Agency tideway strategy Directive 2000. As a heavily modified
offender, a CSO at Abbey Mills These volunteers are part of the project manager watercourse, the River Thames is
responsible for 41% of the annual Thames21 initiative dedicated to required to meet good ecological
discharges, will be collected by the improving water quality in London’s potential by 2027. The Thames Tunnel
Lee Tunnel. waterways. They clear rubbish from is a positive step towards meeting this
“The Lee Tunnel has been the River Thames and tributaries, standard.
developed first as Abbey Mills CSO is a and organise educational activities. sewage capture. The importance of The River Thames
key overflow, causing significant But riverside events have to be “Because the driver is compliance to London cannot be underestimated
pollution to the River Lee,” says cancelled if sewage has been with the Urban Waste Water and although European Law is driving
Thames Water environmental impact discharged into London’s Treatment Directive interpreted as a set the need for change, there is also an
assessment manager for the project waterways. Preventing overflows of dissolved oxygen standards for the undercurrent of support from
Suzanne Burgoyne. would allow Thames21 to continue estuary, all of the options have been stakeholders and users of the
Although the final route of the its efforts. “Our volunteers are designed to meet these standards as a waterway who want a better aquatic
Thames Tunnel is still under consulta- thrilled that something is finally minimum,” says de Garis. environment and see economic
tion, de Garis and Burgoyne say that all being done,” says Thames21 chief “So environmental gains come with benefits stemming from a cleaner river.
three options offer virtually the same executive Debbie Leach. the preferred option of building a “As a world class city, London needs
environmental benefits in terms of shorter tunnel that reduces disruption, a clean and healthy river,” says Bain.
Extensive engagement UK’s biggest ever sewer tunnel. and we had to make sure we had the
with the construction So far a number of major contracts right technical solution in place and the
have already been awarded. The right cost to go along with that to
industry is key to the Thames
construction contract for the Lee Tunnel minimise risks during delivery.”
Tunnel team’s plans to was awarded in January 2010, Construction of the 7km, 7.2m
successfully deliver the UK’s representing a major milestone for the internal diameter sewer is now
biggest ever wastewater UK water sector as the industry’s largest underway and Otta and the London
single construction contract to date. The Tideway Tunnels team must now focus
project. NEC3 contract was let to the MVB on the next set of contracts. The
consortium of Morgan Sindall, Vinci proposed Thames Tunnel will require up
There are many variables to consider Construction Grands Projets and Bachy to 60 enabling works packages, as well
when planning the UK’s largest ever Soletanche following a six month as four or five main tunnelling contracts.
wastewater project and Thames Water tender process and a 12 month Enabling works contracts could start to
plans to use the best available evaluation period. be awarded as soon as 2012.
knowledge in the construction industry “The criteria were weighted With 22 engineering framework
to deliver the proposed Thames Tunnel. between technical competency and contractors already working for Thames
“We have a very challenging
To do this the company will launch an commercial terms, so we weren’t Water, there is seemingly no shortage
project and we will be initial market consultation exercise in looking solely at cost but for the best of potential delivery partners, but Otta
seeking as much innovation January 2011 that the company hopes combination of technical and cost – this says that they could be awarded
and creativity as we can get will see the most experienced firms in gives greater certainty that we have the outside the framework if current
the construction sector offering their right skills to deliver the project and partners have capacity constraints. “It
out of the market” thoughts as to the best way to build minimise risk,” says Otta. depends on the ability of the existing
Jim Otta, project director, London’s new ‘super sewer.’ “The commercial section was kept framework contractors to actually do
London Tideway Tunnels “We have a very challenging project locked up until after we had done the more work because they do have quite
and we will be seeking as much technical ranking and scoring, and then a bit of work under the existing
innovation and creativity as we can get we took two of those bidders into the agreement, but the contracts do lend
out of the market,” says London final round where we opened the themselves more to companies that
Tideway Tunnels project director Jim commercial packages. This was to avoid are already here and have done work
Otta. “We have a large network of any bias that might creep in the in London – whereas the tunnelling
companies on our technical framework technical evaluation due to cost construction contracts are typically
agreements. Between them they have differences.” In addition, Otta says that multinational consortiums.”
been involved in every major tunnelling the complex nature and large scale of In terms of timing and structure,
job in the UK over the last decade, so the scheme demanded careful Otta says that the Thames Tunnel will
there is all kinds of technical expertise evaluation of the technical proposals. be split into four or five major
£3.6bn
here and we now need to reach out to “The project is the deepest and packages. “We think that is about the
firms that will actually build the project largest tunnel that has ever been right size to attract the maximum
to seek their input.” constructed in London. It is in the chalk amount of competition. If we go bigger
In fact Thames Water already has than that we think it might be too big
Forecasted cost of proposed around 50 firms working for it on its and limit the number of firms who
Thames Tunnel existing £5bn capital investment “We had to make sure we could bid,” he says.
programme for asset management had the right technical Of course the final contract packages
£635M
plan period 5 (AMP 5) that runs from will only be determined once planning
2010 to 2015. This should give it a solution and the right cost” permission for the tunnel is obtained,
considerable head start when it comes Jim Otta, project director, and at the moment there are potentially
to consulting the industry on the best London Tideway Tunnels three routes. So the timing of the
Lee Tunnel project cost and most cost effective way to build the awards will depend on the progress the
scheme makes through the planning integrated team pulling the best out of
system. The team is planning for
Thames Tunnel: the contracts the framework partners,” says Otta.
construction to start in late 2013. Contract Anticipated award date Thames Water is looking for several
“It really depends on consultation key attributes in potential future
and planning. We make our planning Contract bids begin mid-2012 and run partners.
submission in 2012 and in mid-2013 we Enabling works – 50 to 60 packages “We will be encouraging contractors
through until 2013/2014
are going out for the main tunnel to be good community partners and
contract awards with the idea that they Thames Tunnel reference designers Contract bids to begin 2012 that involves trying to employ as many
would start somewhere in late 2013 for locals as they can, responding to the
completion in 2020,” says Otta. Thames Tunnel main contracts – 4/5 Contract bids to begin 2013 public and being open and honest
An interesting conundrum exists for about what is happening,” says Otta.
consultants who must choose where to Just as important is ensuring that
focus their efforts. For each of the going forward, but in terms of final health and safety is at the top of the
tunnel contracts the Thames Tunnel “For a capital programme of contract arrangements they have yet to agenda. “For a capital programme of
team will require a reference designer, this size, health and safety be determined,” says Baggs. “It is a this size, health and safety has to be at
a role carried out by Aecom for the Lee possibility that our own capital delivery the top of the agenda at every meeting.
Tunnel. Consultants may opt to
has to be at the top of the team will manage the construction The last thing that we want to see is any
continue in the frameworks, do the agenda at every meeting,” phase, but it will need a much larger accidents. We want everyone involved
reference design, or alternatively work Martin Baggs, chief executive team than the smaller works. It is going to go home safe at the end of every
in consortiums with contractors on the officer, Thames Water to be significantly different to the day,” says Baggs.
tunnelling packages. construction of a sewage treatment In March, Thames Water launched
As for the contract types to be used, works,” he says. Until October 2009 the its AMP5 programme with a health
Otta says there is a range of options. entire project was managed under the and safety conference to emphasise
“We tend to use NEC as it is what the have moved on and more of a NEC project management contract the importance of this issue in the
market prefers for this type of project, programme management approach so executed by CH2M Hill in association coming years. “We now have a joint
but we will be using a suite of contracts the whole aim of the new approach is with Halcrow. But as the Lee Tunnel health and safety board. I’d like to see
for the enabling works. Some of those to give contractors more flexibility to entered the construction phase it was that same approach develop further on
will be under the existing Thames deliver,” says Baggs. integrated into Thames Water’s own project and programme delivery,” says
Water contracts, which tend to have What this means is that contractors capital delivery team’s programme. Baggs.Firms wishing to work with
specific terms and conditions,” he says. are given design responsibility and “This aligns it with the resources Thames Water in the future certainly
Going into AMP5 Thames Water therefore more freedom to deliver their and expertise inside Thames Water,” have a lot to prove, from technical
changed its approach to procurement, schemes in the most efficient way. says Otta. excellence, to health and safety,
mainly driven by the new CEO Martin As for the Thames Tunnel itself, this The Thames Tunnel project team extensive community engagement and
Baggs, who was formally appointed in could also go down the NEC route, but continues to manage the works with a cost efficiency. But with investment of
March 2010. “Traditionally we awarded Otta says this is not yet decided, nor is 150 strong team, which includes staff over £10bn within the next decade, the
on a project by project basis, but when the final delivery structure. “There will from some of the 30 framework benefits for the industry will most
you look at the rest of the industry they be a whole range of new contracts consultants. “We operate as an definitely flow in both directions.
Working on
the tunnels
Skills & jobs
Adrian Greeman
4000
The large-scale engineering the extra engineers will work from their That number may not be enough
required for the proposed own offices however. however, especially when the “churn”
The big demand is for skilled or turnover of workers is taken into
Thames Tunnel means that
construction work and fortunately for account over the lifetime of a project, a
it is set to take over from the scheme, a pool of labour has built factor which could multiply the
Employees to work on project
construction
Crossrail as London’s major up recently in London in the past numbers actually employed on the
civil engineering and tunnel period. Terminal Five at Heathrow had scheme by a factor of 10.
a large workforce, and the Olympic Otta says the project team has also
600
employer. Park has become a major employer. been making visits into Europe to
The Thames Tunnel project is the largest Some of that workforce at least is likely assess skills and availability overseas.
waste water project in Europe in terms to move over to the Crossrail tunnel “There is a small highly skilled
of capital expenditure and will demand project which is picking up momentum workforce that tends to move to where
labour and skills on a corresponding with preparatory site work and design the projects are,” he says. Most recently
Consultants to be engaged in design
scale. An estimated 4,000 people are now underway. the team had a look at a tunnel project
expected to be employed on the Lee That scheme will help with the core underway in Amsterdam.
and Thames Tunnel during its needs of the Thames Tunnel project by Certainly the European tunnelling
construction. This will be complement- supplying experienced tunnelling and mining community could provide
ed by several hundred professionals, workers. “There was some tunnelling some of the very highly experienced
project managers and design engineers for the Olympics but there is a greater workforce needed for the main sewer
employed directly and in consultancies amount on Crossrail,” says Otta. tunnel. But even so, as much as
and specialist advisers. So much tunnelling is happening in possible the aim is to recruit locally and
“Most of those will not actually fact, with major power tunnel projects the team plan to engage with the 14
begin work until late 2014 but the underway for EDF and the National boroughs along the route to see what
design, investigation and preparation Grid, London Underground improve- the availability is for labour and the
teams have already been gearing up,” ments, and other schemes, that a new need for employment. From 2011 the
says Thames Tunnel project director Jim training facility, the Tunnels & Thames Tunnel will also offer work
Otta. He comes from consultant Underground Construction Academy is experience opportunities to at least 30
CH2M HILL and has himself garnered being formed. It was initiated by the people from across the local boroughs
experience on big tunnels from Crossrail project but is supported either each year to encourage awareness of
Singapore’s deep sewer scheme to a financially or with resources by opportunities in engineering.
similar project in Sydney. contractors. The scheme got underway “For the Lee Tunnel we have
But although there are a few more with £8M from Crossrail’s London engaged with the local borough to
expatriates in the core management Mayoralty funding in 2009 and had an identify available skills and we are
team, the majority are drawn locally or additional £5M boost from the trying to match the needs of our project
from 50 or so firms currently working previous Labour government’s Learning with it,” says Otta.” We want to engage
on the scheme. These are primarily & Skills Council in March this year. the local employment market and
“Most of those will not selected from the Thames Water’s Permanent premises are under identify the sets of skills that could
framework consultants. construction near Ilford in the London come from various areas.”
actually begin work until “We currently have a team of 150 Borough of Newham, in a facility which All this could be of major significance
late 2014 but the design, based in Paddington,” says Otta “which will include a simulated tunnel boring in the coming period. The economic
investigation and has grown from an initial start-up machine (TBM) environment and one downturn has created an ever greater
preparation teams have group of around 25 starting out from for the back-up train. There will also need for employment and with the
offices in Richmond.” He expects the be a sprayed concrete facility and prospect of 4,000 site staff and
already been gearing up” central team to climb to around 600 classrooms and workshops. It opens in hundreds of designers over the coming
Jim Otta, project director, during reference design of the various March 2011 and should put through at years, the Thames Tunnel project is set
London Tideway Tunnels packages, including those drawn in by least 1,800 trainees each year, learning to give a significant boost to London’s
the various consultancy firms. Most of operational and safety skills. construction industry.