You are on page 1of 1

REKAPITULASI ANGGARAN BIAYA

PEKERJAAN PEMBANGUNAN MUSHOLLA AL IKLAS - 2021


JAKARTA

JUMLAH HARGA
No. URAIAN PEKERJAAN
(Rp)

A. STANDAR

I. PEKERJAAN PERSIAPAN Rp 72,225,450.00

II. PEKERJAAN STRUKTUR Rp 284,287,675.74


A PEK. TANAH Rp 1,746,228.63
B PEK. PONDASI Rp 35,504,179.03
C PEK. KONSTRUKSI BETON Rp 247,037,268.08

III. PEKERJAAN ARSITEKTUR Rp 661,715,461.10


A PEK. DINDING Rp 535,874,616.50
B PEK. LANTAI Rp 27,650,840.00
C PEK. KUSEN LENGKAP Rp 52,784,800.00
D PEK. PENUTUP ATAP Rp 6,702,750.00
E PEK. PLAFOND Rp 22,838,560.00
F PEK. SANITAIR Rp 1,385,700.00
G PEK. PENGECATAN Rp 14,478,194.60

IV. PEKERJAAN MEKANIKAL Rp 27,651,644.00


A PEK. INSTALASI PLAMBING Rp 27,651,644.00

V. PEKERJAAN ELEKTRIKAL Rp 20,606,300.00


A PEK. LISTRIK Rp 14,806,300.00
B PEK. PENANGKAL PETIR Rp 5,800,000.00

SUB TOTAL STANDAR : Rp 1,066,486,530.84


BIAYA TAK TERDUGA (5%) : Rp 53,324,326.54
TOTAL : Rp 1,119,810,857.38
DIBULATKAN : Rp 1,119,000,000.00

B. NON STANDAR

I SOUND SYSTEM MUSHOLLA 2% x Rp 1,066,486,531 Rp 21,329,730.62


II AC / EXHAUST FAN 2% x Rp 1,066,486,531 Rp 21,329,730.62
III KEBERSIHAN/KEAMANAN/SANITASI 1% x Rp 1,066,486,531 Rp 10,664,865.31

SUB TOTAL NON STANDAR : Rp 53,324,326.54


BIAYA TAK TERDUGA (5%) : Rp 2,666,216.33
TOTAL : Rp 55,990,542.87
DIBULATKAN : Rp 55,900,000.00
TOTAL STANDAR + NON STANDAR Rp 1,175,000,000.00
TERBILANG : Satu milyar seratus tujuh puluh lima juta rupiah