Concrete Pump
Operation Manual
Foreword
Sincerely thank you for choosing Loxa Heavy Machinery truck-
mounted concrete pump (hereafter referred to as truck-mounted pump).
We will provide you with high quality product and star-level after-
services.
Guarantee normal downtime and repair cost. Ensure that the manual is
easily accessible as the tools in the toolbox, in order to ease the reading
at all times. You can operate this truck-mounted pump in a skilled and
safe way only after you fully understand the contents of this manual.
Dear friends, thank you for your trust on Loxa Heavy Machinery. We
sincerely wish you to realize own ambition in your career and achieve
great success.
1
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
Tips
Please maintain and operate Foton truck-mounted pump correctly. Our
company will not be liable for the consequences arising from the
violations of the following regulations.
Carefully read this operation manual before the startup and operations of
this machine.
2
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
Contents
Chapter I Main Structure and Function Introduction............................... 5
1. Basic Principles:....................................................................12
1. Operation Preparations.........................................................30
4. Cleaning .................................................................................33
2. Overview ................................................................................36
8. Lubrication.............................................................................38
Chapter VI Troubleshooting.............................................................. 46
4
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
Chapter I
5
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
Figure 1-1
6
2. Basic Parameters and Main Technical Performance Indicators
Table 1-1 Parameter Table 1 of Truck-Mounted Pump
BJ5124THB BJ5124THB BJ5124THB BJ5130THB BJ5130THB BJ5130THB
Product model
90142 90181 100221 90141 90181 100221
Length mm 8980
Exterior
Width mm 2490
Height mm 3120
Vehicle Parameters
pressure) MPa
Inside diameter ×
stroke of delivery Φ230×1800
cylinder mm
Hopper capacity
0.6
m3
Feeding height
1480
mm
Water tank
300
capacity L
Fuel tank capacity
700
L
local
Local control/wire- local control/wire- local control/wire-
Operation mode control/wireless-
control control control
control
Lubrication mode Manual/automatic lubrication
Switching
between high
Automatic switching
pressure and low
pressure
8
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
3. Structural Introduction of Truck-Mounted Pump
The truck-mounted pump is generally composed of chassis, power system, cooling system, electric
system, hydraulic system, support system, water cleaning system, lubrication system, and pumping
system.
The main hydraulic system adopts open-type system, the electric system adopts double-module
programmable controller, the mixing system adopts single motor system, the water cleaning system
adopts high pressure piston water pump, and the lubrication system adopts automatic lubrication
system.
The pumping system adopt S-valve delivery cylinder pumping system, which mainly includes main
cylinder, water tank, delivery cylinder, concrete piston, swing valve cylinder, mixing mechanism,
hopper, and S-pipe valve. Please refer to Parts Catalog of Truck-Mounted Concrete Pump for the
detailed structure.
1. 1’ - main cylinder; 2 - water tank; 3.3’ - delivery cylinder; 4. 4’- concrete piston;
5. 5’ - swing valve cylinder; 6 - hopper; 7 - S-pipe; 8 - Discharge port
Figure 1-2
9
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
10
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
Chapter II
Safety Rules
1. Basic Principles
2. Qualifications and Responsibilities of Truck-Mounted Pump
Operator
3. Safety Precautions
11
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
1. Basic Principles:
This machine can be used for pumping of concrete only and it’s prohibited to use for any other
application, especially those impairing the safety of the machine.
The following precautions shall be guaranteed during the operations of this machine:
(1) The safety devices (including emergency stop button and screen on the hopper) shall never
be removed or altered without consent.
(2) Any safety devices removed during the repair shall be re-assembled immediately at
completion of the repair.
Before operations each time, make sure to check the machine to guarantee the operation safety. Any
detected or suspected malfunction shall be solved immediately. If such malfunctions may impair the
operation safety, stop the operation.
Resale
In event of resale of the truck-mounted pump, pay attention to the following precautions: Hand over
all data of truck-mounted pump (including operation manual, maintenance manual, diagrams, truck-
mounted pump nameplate, and inspection certificate) to the new operator and submit the resale
information or newly procurement information to Loxa Pumping, in order to guarantee your
availability of improvement or safety updates of truck-mounted pump.
2. Qualifications and Responsibilities of Truck-Mounted Pump Operator
The operation personnel of the truck-mounted pump must pass the operation safety training
qualification examinations. The training includes the operation principles of truck-mounted pump,
relevant national regulations, and this operation manual. The untrained operation personnel have the
possibility of endangering your own life and others.
The truck-mounted pump shall be operated and repaired only by the personnel qualifying following
conditions:
(1) The operation personnel must be 18 years old or above. The personnel below 18 are
prohibited for operating this machine.
(2) The operation personnel must be competent for this job in both physical status and mental
status.
(3) The operation personnel must pass the special training for operation and repair of this
machine, get familiar with this operation manual, and bear the training certificate.
(4) The operation personnel must be competent to own job. It’s absolutely prohibited to remove
or replace any safety device and the safety devices must be correctly used during operations.
Before starting the operations of the truck-mounted pump, check all functional parts for normal
functioning. Upon detection of abnormal functioning of certain functional parts, immediately take
measures to solve the malfunction.
3. Safety Precautions
As the truck-mounted pump contains high pressure fluid during the working, the following safety
precautions must be cautioned during the operations.
3.1 Precautions before operations
(1) Check the installation condition of the truck-mounted pump. The truck-mounted pump shall
be installed on a level and solid ground. To prevent the automatic slippage accident, the
truck-mounted pump can’t be parked on slopes.
12
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
(2) Check delivery pipelines for correct arrangements and whether the mode and capability for
the delivery and feeding of concrete can guarantee the normal working.
(3) Check the power supply and water supply and ensure that the power supply and water supply
can guarantee the normal working and the electric system, hydraulic system, and mechanical
system are correct.
(4) Check the oil level of hydraulic oil tank and top up if insufficient. The hydraulic oil added
shall meet the specification.
(5) Check whether the lubricating grease in the lubricating grease pump is sufficient and top up
if insufficient. For those with manual lubricating pump, firstly conduct the manual
lubrication and then dry apply the lubricant to check whether the supply of lubricating grease
is normal for various lubricating points.
(6) Before starting the truck-mounted concrete pump in accordance with the operation
specification, check whether the hopper screen is properly closed and check the water tank
for presence of foreign material and add clean water to the water tank. After the diesel engine
is started, idle at (800r/min) for (3~5) min.
(7) Under cold weathers, idle the diesel engine for a certain period, till the temperature of
hydraulic oil is above 20ºC, before feeding the materials and starting the pumping.
(8) Idle for 10min, check all instruments (including oil suction and return indicators) for normal
indications, check mixing device for reverse pumping capability, and check for normal
reverse pumping.
3.2 Precautions during operations
(1) Before pumping the concrete, firstly pump the water and check the locations of various pipe
clamps to ensure the air-tightness and leakage-free. Then pump the pipeline lubricant.
Generally the mortar is used and the cement paste may be also used). The volume of mortar
will be 0.5m3/200m.
(2) Pour the mortar into the hopper for pumping. When the pumping of mortar is almost
completed, pour the qualified concrete for normal pumping. In event of blockage during the
pumping of mortar, disassemble the most forward section of piping, remove its internal
dehydrated block, and connect the piping to resume normal pumping.
(3) The slump of the pumped concrete shall not have high variation and the variation shall be
controlled within (80~230) mm. Before pouring the concrete into the hopper by concrete
mixer truck, mix rapidly in the mixing drum for several minutes.
(4) While starting or stopping the pumping of concrete, get in touch with the front end hose
operator.The bending radius of the front end hose shall be higher than 1m and the operator
shall not stand at the pipe outlet to prevent the sudden spray of concrete from causing
personal injury.
13
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
(5) When the truck-mounted concrete pump is working, it’s strictly prohibited to insert your
hand into the hopper or water tank.
Figure 2-1
(6) The delivery pipeline shall be secured and solidly cushioned and it’s strictly prohibited to
bend the delivery hose, in order to prevent the explosion of hose.
Figure 2-2
(7) While resuming the pumping after the blockage of pipeline is solved, the end of hose will
rapidly swing and the concrete may spray out instantaneously. In such case, the operators
shall keep away from the hose.
Danger
Figure 2-3
14
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
(8) Never grasp with hand the end hose by standing at the edge of a building, as the swing of
hose or spray of concrete may cause the operators to fall off from the building.
Danger
Figure 2-4
(9) During the pumping, ensure that the concrete is above the mixing axis. No empty suction or
empty pumping is allowed.
(10) When it’s necessary to pause the pumping for a relatively long period, start the pumping at
an interval of (15~30) min to reverse pump for 1~2 strokes and forward pump for 1~2
strokes, in order to prevent the solidification of concrete within the pipe.
(11) During the pumping, if the pumping pressure increases suddenly or there are vibrations in
the delivery pipeline, immediately turn on the reverse pump button for 2~3 strokes and then
resume forward pumping. Alternatively, knock the locations vulnerable to blockage (such as
taper pipe and bend) with a wooden hammer. If the pumping pressure is still high after the
above method is repeated for several times, the pipe may be blocked. In such case, pause the
pumping and conduct the pipeline blockage treatment.
(12) During the pumping, frequently pay attention to the temperature of hydraulic oil. If the oil
temperature rises to 55ºC, the air cooling is automatically started. If the oil temperature
increases further to be higher than 80ºC, stop the machine for checking.
(13) During the pumping, the hopper shall not be fully emptied, otherwise the concrete residue
will probably spray out at high speed to damage the machine and injure surrounding
personnel.
(14) If the slump of the concrete is too low, it’s disallowed to add water into the hopper for
mixing. Instead, add the cement mortar (of which the water-cement ratio shall be same with
that of the concrete being pumped) into the mixer truck or mixer for uniform mixing and
then feed into the hopper.
(15) The hopper screen shall not be fully stacked with concrete. The feeding rate shall be
controlled and the oversized aggregate and foreign material shall be timely removed.
(16) If the mixing shaft is blocked against rotation, pause the pumping and timely solve the
malfunction.
(17) Upon detection of separation phenomenon in the concrete feeding into the hopper, pause the
pumping and mix uniformly before resuming pumping. Upon detection of serious separation
of aggregate and clearly insufficient mortar in the hopper, remove some aggregates and add
the mortar for re-mixing.
(18) When resuming pumping after the vertically upward pumping is paused, firstly reverse pump
to recover the concrete of distributor valve back to the hopper.
15
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
(19) Whenever the working is paused, if the pipeline is equipped with gate pipe, properly insert
the gate plate to prevent the backflow of concrete in the vertical or upward inclined pipeline.
3.3 Precautions after stop
(1) Idle run the diesel engine for (3~5) min before stop at the completion of pumping.
(2) At completion of concrete pumping each time, immediately clean the concrete residue from
the truck-mounted pump and the pipeline.
(3) When the ambient temperature is below 5ºC, fully drain the cooling water from the truck-
mounted pump (especially the residual water in the water cooler) to prevent the frost
cracking of the machine parts.
(4) Before the after-shift maintenance (For instance: tighten parts and add lubricating oil to the
transmission parts), make sure that the power unit stops rotation and the pressure of
accumulator is relieved.
(5) During driving, make sure that the outriggers are fully retracted.
3.4 Precautions for repair
(1) During the repair of this machine, please carefully read the Operation Manual and Parts
Catalog. In event of any procedure or technical questions, please consult with our after-
service department.
(2) To prevent any accident during repair, stop the engine, relieve the pressure of accumulator,
and ensure that the switches of all electric devices are placed at position OFF.
(3) When it’s necessary to conduct the electric welding on the truck-mounted pump, the high
voltage generated may damage the electric units of remote control system and wire control
system. Therefore, make sure to take following measures before the welding:
① Remove the remote control plug from the remote control socket and cover the
connecting socket with a cap.
② Disconnect the positive and negative connectors from the battery.
③ While disposing fuel, hydraulic oil, or other functional fluid (such as battery electrolyte),
to eliminate the possibility of combustion and explosion, please abide by the relevant
product safety specifications and local laws and regulations for recovery or recycling.
(4) Do not add seawater or salty water into water tank or hopper.
(5) Cautions shall be taken to avoid interconnecting the positive and negative posts of the battery
or avoid connecting the positive post of battery to a metal, in order to prevent the electric
discharge from causing personal injuries.
16
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
Chapter III
17
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
18
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
19
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
20
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
Pumping time
Parameter Settings
Concrete return
displacement
Minimum
displacement
Maximum
displacement
Minimum energy-saving
displacement
In above figure, the “concrete return displacement” can be adjusted within 200~350, the “maximum
displacement” can be adjusted within 600~750, the “minimum displacement” can be adjusted
within 200~400, and the “energy-saving speed” can be adjusted within 1,350~1,750.
21
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
1.3.2.3 After the setting of parameters, press corresponding functional button of “Homepage” to
return to homepage. Press the corresponding function button of “Input” in the homepage
to access the input point detection interface.
The input detection interface has two pages. Press the Previous Page and Next Page to turn pages.
22
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
1.3.2.4 Press the corresponding function button of “Output” in the homepage to access the output
point detection interface.
The main interface has two pages. Press the Previous Page and Next Page to turn pages.
Cooling valve
Outrigger valve
Reverse mixing
23
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
1.3.2.5 The diesel engine speed, displacement setting (adjustable within 0~100), working status,
diesel engine working time, pumping time, pumping number, and pumped volume are
displayed in the main interface.
Pumping time
The main interface has two pages. Press the Previous Page and Next Page to turn pages.
24
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
25
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
that the proximity switch circuit is normal, check the hydraulic circuit (Refer to hydraulic
schematic diagram).
26
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
27
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
28
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
Chapter IV
Operation Instructions
1. Operation Preparations
2. Operation Functional Tests
3. Pumping Procedure
4. Cleaning
5. Reset of Machine
29
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
1. Operation Preparations
1.1 The machine shall be installed on a solid and level cement ground and the working site shall
be larger than the minimum arrangement space of the truck-mounted pump.
1.2 The working ambient temperature shall be -25ºC~45ºC. However, the average temperature
within 24 hours shall not exceed 35ºC and the lowest ambient temperature during the non-
working period shall not be below -40ºC (fully drain the oil and water from the concrete
pump). The maximum working temperature of the hydraulic oil in the oil tank shall not
exceed 80ºC during the working. The relative humidity in the working environment shall be
30%~95%.
1.3 Checking of electric units
(1) All switches on the operating board and remote control box are at position OFF.
(2) The electric units shall be free of broken wire, off wire, loose contact screw, and short-circuit.
1.4 Checking and preparation of engine
(1) Before the start, make sure to check that the coolant suitable to environment temperature is
added to the designated level of the water tank.
(2) Use the fuel and engine oil suitable to local environmental temperature and check the levels
of fuel and engine oil.
(3) Check the battery and circuits. Ensure that the voltage is within (24±2) and the circuits are
free of broken wire, off wire, and looseness.
(4) Check the connectors and sealing surfaces of the fuel, engine oil, and coolant pipes for
presence of leakage.
1.5 Extending/retracting of truck-mounted pump outriggers
After the position of the truck-mounted pump is properly adjusted, start the diesel engine and
operate the hydraulic outrigger operating lever to lower four outriggers onto the ground
simultaneously. In event of any factor leading to deteriorated stability, immediately stop the
operations, retract the hydraulic outriggers, and solve the malfunction before reinstallation as per
the specification. The factors leading to deteriorated stability include:
(1) The variation of ground conditions due to rain, snow or other water source.
(2) Sink of ground on one side of hydraulic outriggers.
(3) Leakage of outrigger cylinder.
1.6 Pipe arrangement
1.6.1 Vertically upward pipe arrangement and concrete pumping
While arranging the vertically upward pipes, when the distribution valve of truck-mounted pump
reverses to suck in concrete (or the pumping is stopped), the gravity force of the concrete within the
vertical pipes will generate a counter-flow pressure (referred to as backpressure) to the truck-
mounted pump. The higher the vertical pipe is, the higher the counter-flow pressure is. This
counter-flow pressure will reduce the volumetric efficiency of concrete, influence the displacement
of truck-mounted pump, and cause blockage of pipe due to separation of concrete. Therefore, take
the following measures to overcome this counter-flow pressure during vertically upward pipe
arrangement:
(1) When the vertical height is low, a certain length of horizontal pipe shall be set between lower
end of vertical pipe and truck-mounted pump. Generally, the length proportion between
30
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
vertical pipe and horizontal pipe shall be 3:1 and the length of horizontal pipe shall be no
less than 15m, in order to utilize the friction force between concrete mixture and walls of
delivery pipe within the horizontal pipe to balance the counter-flow pressure.
(2) In event of high vertical height or site limitations, the setup of horizontal pipe is difficult to
balance the counter-flow pressure. It’s preferable to setup one gate valve pipe (also referred
to as gate pipe) between the tapered pipe of delivery pipeline and straight pipe so that, when
the pumping is stopped, the gate valve can be closed to prevent the back-flow of concrete.
The elbows shall have solid foundation to avoid transmitting the vibration of truck-mounted
pump to the vertical pipes as far as possible and the vertical pipes shall be securely fixed to
prevent vibrations.
If the pumping height is higher than 30m during vertically upward pumping, arrange the
new or wear-free pipes or the pipes with thick walls at the start position of the pipeline, in
order to prevent the accidents due to over-high pressure within pipes. When necessary,
inspect the wall thickness of pipes. In event of high wear of pipes due to long-term service,
replace all pipes with high pressure.
1.6.2 Downward pipe arrangement and concrete pumping
During downward pipe arrangement and pumping, to prevent the blockage of delivery pipe due to
self-flow and separation of concrete, arrange a horizontal pipe equivalent to more than 5 times of
fall on the front end of downward inclined pipe, in order to utilize its friction resistance to restrain
the self-flow of concrete. In addition, an air bleeding valve shall be arranged on the upper end of
downward inclined pipe. During the pumping, if there are voids in the inclined pipe, firstly open the
air bleeding valve to bleed the air. When the inclined pipe is full of concrete and the motor
overflows from the air bleeding valve, close the air bleeding valve and start the normal pumping. If
there is no room to arrange the horizontal pipe on the front of the downward inclined pipe due to
limitation of site conditions, the horizontal pipe may be substituted by hose, elbow, or annular pipe
to increase the friction resistance and restrain the self-flow of concrete within downward inclined
pipe.
During the downward pumping of concrete, the self-flow of concrete is closely related to the
concrete slump. To prevent the downward self-flow and the separation of concrete, during large-
angle downward pumping, install the foamed rubber balls into the pipeline before the start of
pumping.
1.7 Start of truck-mounted pump
The truck-mounted pump can be started after all checking works are completed:
(1) Disengage the engine from the driven devices (to stop the forward/reverse pumping).
(2) Engage the power switch and press the “start control power supply”. The indicator lamp
turns on and the instruments indicate the current status.
(3) Press “Start diesel engine” button and hold for (approximately 2~10s). After the diesel
engine is started, immediately release the start button. In such case, all instruments indicate
the current working status of the diesel engine. The interval between two consecutive starts
shall be 2~3min.
(4) Once the engine is started, immediately observe the parameter measurement devices
(instruments), including engine oil pressure, voltage, and diesel engine speed, and start the
loaded works after all parameters are normal.
2. Operation Functional Tests
2.1 Inch the swing cylinder or drive cylinder. When the swing cylinder or drive cylinder reaches
its travel end, the system pressure of the main pump indicated by pressure gauge shall not
31
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
exceed 30~35MPa and the pressure of swing cylinder shall not exceed 20MPa. At the
reversing instant of distribution valve, the pressure will drop (by approximately 4~6Mpa). If
the pressure drop is too high, the probably insufficient pressure of the accumulator shall be
taken into consideration (Refer to 2.9 for the nitrogen charging method). The mixing relief
pressure is 12MPa.
2.2 Increase the engine speed to 2,000~2,100r/min, adjust to maximum displacement, run the
pistons at rated speed, and measure whether the reversing number per minute meets the
specification (Refer to Table 1-1 and Table 1-2).
2.3 Check the vacuum pressure gauge on the oil suction filter. When the oil temperature is
higher than 40ºC and the concrete pistons are running at highest speed, check whether the
pointer of vacuum pressure gauge is beyond the green zone (The vacuum pressure shall not
exceed 0.04MPa). Generally, the oil suction vacuum pressure shall be less than 0.02MPa and
the reading of oil turn pressure gauge shall be less than 0.35MPa. If beyond above values,
clean or replace the filter element.
2.4 Rotate the reverse pumping switch to check for presence of reverse pumping.
2.5 Operate the lever of mixing control valve and observe whether the mixer is running.
2.6 Operate the water pump control valve lever to operate the water gun and observe whether the
high pressure water is pumped out.
2.7 Check the charged pressure of accumulator, maximum swing pressure, and minimum swing
pressure.
2.8 Press the “emergency stop" switch and observe whether the pumping cylinder can stop
pumping.
2.9 Nitrogen charging method of accumulator
(1) Unscrew the protective nut of accumulator charging valve, connect one end of charging tool
pressure gauge to a nitrogen cylinder, and connect the other end to the accumulator. The
nitrogen outputted from the nitrogen cylinder must flow through a reducing valve.
(2) Slowly open the air valve of nitrogen cylinder. When the reading of pressure gauge reaches
the specified valve (8.5MPa), close the air valve of nitrogen cylinder, maintain for
approximate 20min, and observe whether the pressure drops.
(3) Disassemble the end of charging tool from the accumulator and disassemble the charging
tool.
(4) Tighten the protective nut of accumulator charging valve. Caution: The accumulator can be
charged only by nitrogen and the charging pressure must meet the specification.
3. Pumping Procedure
The concrete pumping can be started after the test run of the truck-mounted pump is normal and the
hydraulic oil temperature increases to 20~25ºC.
3.1 Before pumping the concrete, firstly pump the water and check the locations of various pipe
clamps to ensure the air-tightness and leakage-free. Then pump the pipeline lubricant.
Generally the mortar is used and the cement paste may be also used).
3.2 When the pumping of mortar is almost completed, pour the qualified concrete for normal
pumping. In event of blockage at the pumping of mortar, disassemble the most forward
section of piping, remove the internal dehydrated block, and connect the piping to resume
normal working.
3.3 In event of blockage during pumping, immediately conduct the reverse pumping for 3~4
32
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
travels to suck back the concrete within the pipeline into the hopper for re-mixing. Then,
pump slowly, till the blockage is solved, before resuming normal pumping. It’s disallowed
for reversing at will during normal pumping.
3.4 Blockage causes:
(1) Poor workability of concrete.
(2) Under-low sand ratio or disqualified grading.
(3) Insufficient mixing of concrete or separation of concrete due to long retention time.
(4) Unstable slump, poor cohesiveness, and poor water retention of concrete.
(5) Poor sealing of delivery pipe and loss of mortar.
(6) Improper parameter settings of hydraulic system.
(7) Residual concrete in S swing pipe and delivery pipe from previous operations.
(8) Solidification of concrete due to long stop or waiting time.
In event of pipe blockage, immediately conduct the reverse pumping for dredging. If the
reverse pumping fails to dredge the blockage, immediately judge the blockage location, stop
the machine, and clean the pipeline. Resume the pumping after the blockage is solved.
4. Cleaning
During the cleaning of the machine, do not use corrosive solvent, acid, alkali, or aggressive solution,
otherwise it will damage the surface paint, chrome plating, and all non-metallic parts of the machine.
Do not spray the water flow or water mist towards personnel, machine control cabinet, or electric
units, otherwise it will lead to serious danger. At completion of pumping, timely clean the delivery
pipeline, hopper, and whole machine.
4.1 Cleaning of pipeline
Insert the gate plate into the gate pipe, disassemble the front end hose, disassemble the pipe
connector from the taper pipe, pour out the concrete from this taper pipe, properly install the
cleaning tools (sponge plug and cleaning piston), reconnect the taper pipe, secure the pipe clamps,
top up the hopper with water and connect it with water source, unplug the gate plate, start the truck-
mounted pump, and press “forward pumping” to start the pumping of water. The cleaning tools are
driven forward through the pipeline, till the sponge plug and cleaning piston are emerged from the
front end. Continue the pumping of water, till there is no further outflow of subsequent residual
concrete. The cleaning of delivery pipe is completed.
4.2 Cleaning of truck-mounted pump
(1) Firstly adjust the main oil pump to minimum displacement, idle for 3~4 strokes to drain
residual concrete, and then stop the idling strokes.
(2) Remote the residual concrete from the hopper and S-pipe by auxiliary tools (including shovel
and crowbar), open the bottom gate of hopper, flush the inside and outside of hopper by
water thoroughly, and then clos the gate.
(3) Top up the hopper with water and run for 3~4 strokes to pump out the residual concrete
along with the water. After the water is fully pumped, idle for 20min to further supply the
lubricating grease.After the cleaning, stop the machine and cut off the power supply.
(4) Open the bottom cover of hopper to drain residual water and thoroughly clean the S swing
pipe, hopper, delivery cylinder, water trough, and all portions in direct contact with concrete
by high pressure water.
(5) If there is a danger of freezing, drain the water from the water tank, water trough, and
33
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
flushing water pump. Normally, drain the water from the water trough whenever the water is
not in use (at overnight or weekends).
5. Reset of Machine
At completion of operation, reset the cleaned truck-mounted pump as per the following procedure:
(1) Properly retract the outriggers.
(2) Stop the machine and cut off the power supply.
(3) During the driving, abide by the road traffic regulations.
34
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
Chapter V
Safety Rules
1. Maintenance Periods
2. Overview
3. Daily Maintenance
4. First 50h Maintenance
5. Every 100h Maintenance
6. Every 500h Maintenance
7. Every 1,000h Maintenance
8. Lubrication
9. Replacement and Adjustment of Wearing Parts
10. Maintenance of Diesel Engine
11. Technical Data Related to Repair of Equipment
35
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
1. Maintenance Periods
(1) Daily maintenance: The maintenances before the operations and after the operations each
day.
(2) First 50h maintenance: The maintenance to be conducted after the truck-mounted pump
works for the first 50 hours.
(3) Every 100h maintenance: The maintenances to be conducted once every 100 working hours
of the truck-mounted pump.
(4) Every 500h maintenance: The maintenances to be conducted once every 500 working hours
of the truck-mounted pump.
(5) Every 1,000h maintenance: The maintenances to be conducted once every 1,000 working
hours of the truck-mounted pump.
2. Overview
The pump shall be checked once every 1,000 hours and at least once a year by our trained
professionals. Checking items: Control pressure and high pressure of pump, pressure of
accumulator, mixing pressure, and oil leakage and permeation of pump.
3. Daily Maintenance
Make sure to fulfill the maintenance items before the operations of truck-mounted pump each day:
(1) Check for sufficient fuel, hydraulic oil, engine oil, and coolant and add if insufficient.
(2) Drain the sediments from the bottom of the hydraulic oil tank, till the hydraulic oil flows out.
(3) Check the parts in direct contact with concrete for damage and replace damaged parts.
(4) Check the wear status of the delivery pipes by knocking method or wall thickness gauge and
replace worn pipes.
(5) Lubricate the pressure casing and seals on two ends of mixing shaft.
(6) Observe the hydraulic pipelines to ensure leakage-free.
(7) Remove dust and dirt from the surfaces of hydraulic oil radiator.
(8) Lubricate all lubricating points on the S swing pipe cylinder and top up the grease distributor
with lubricating grease (add once every two hours during operations).
(9) Check the electric switches for sensitivity and reliability.
(10) Check the gap between S swing pipe reversing valve and anti-wearing plate. If above 5mm,
the adjustment is required.
(11) After the operations each day, make sure to carefully clean all parts coming into contact with
the concrete and the complete vehicle to guard the concrete delivery system against being
blocked by residual concrete.
4. First 50h Maintenance
Make sure to fulfill the following maintenance items after the truck-mounted pump works for the
first 50 hours:
(1) Replace the oil of engine and power takeoff.
36
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
① Stop the machine when the oil temperature is at 40ºC~50ºC and drain the lubricating
oil and hydraulic oil from the tanks while the oils are still hot.
② The new oils for replacement shall follow the oil trademarks specified by this manual.
(2) Sufficiently lubricate the lubricating points and add specified lubricating grease to the
lubricating center.
(3) Clean the filter element and screen and the dirt collector of the hydraulic system and replace
damaged filter element or blocked paper filter element.
5. Every 100h Maintenance
Make sure to fulfill the following maintenance items every 100 working hours of the truck-mounted
pump:
(1) Fulfill all maintenance items and first 50h maintenance items.
(2) Check the lock bolts and nuts of the concrete piston connecting flanges for presence of
damage or looseness. If loose, re-tighten the hexagon bolts on the piston and flange. If
damaged, replace.
(3) Check the reversing number at maximum delivery capacity.
(4) Check the oil filter element, clean the magnetic bar and filter cartridge, and replace the oil
filter element depending on actual situation. Only use the filter element products provided by
our company.
(5) While cleaning the magnetic bars, use a cloth strip to wipe from the head to the tail.
(6) While cleaning the filter screens, immerse the filter screens into the fluid capable of
dissolution of lubricating oil (such as acetone, petroleum ether, and crude oil) for
approximate 10~15min and then use high pressure air to blow the filter screen from outside
to inside. During the air blowing, place a round bar wrapped with paper tape into the filter
screen so that the particulates are attached to the paper tape.
6. Every 500h Maintenance
Make sure to fulfill the following maintenance items every 500 working hours of the truck-mounted
pump:
(1) Fulfill all maintenance items of every 100h maintenance.
(2) Clean the water pump suction filter.
(5) Clean the hydraulic oil tank and replace hydraulic oil after the first 500 working hours.
(4) Afterwards, handle depending on the actual hydraulic oil quality every 500 hours (The solid
particulate contamination level of hydraulic oil shall not be higher than 18/15).
7. Every 1,000h Maintenance
Make sure to fulfill the following maintenance items every 1000 working hours of the truck-
mounted pump:
(1) Fulfill all maintenance items of every 500h maintenance.
(2) Check all mechanical and hydraulic devices by professionals dispatched by our company
along with the user.
37
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
8. Lubrication
To guarantee the service life of the truck-mounted pump, it’s necessary to periodically lubricate all
portions with relative movements.
8.1 Trademarks of lubricating grease:
Summer: Select 00# lithium-based lubricating grease.
Winter: Select 000# lithium-based lubricating grease.
Caution: It’s prohibited to use molybdenum disulfide lubricants.
8.2 Lubrication regulation
(1) After 100 pumping hours (there is a hourmeter on the control cabinet), make sure to check
the bearings and seals and replace when necessary.
(2) Upon detection of oily or cement mixture or oil or mortar leakage at the hopper bearings,
make sure to replace the bearings immediately.
(3) At the time of repair, make sure to tighten the casing of S swing pipe to prevent the axial
movement of casing under high pressure.
9. Replacement and Adjustment of Wearing Parts
9.1 Disassembly and installation of concrete piston
Press the concrete return button to return one cylinder piston rod to the root position and replace the
piston as per the following procedure.
Caution: Replace the piston within the water trough only after the engine is stopped.
(1) Fully drain the water from the water trough.
(2) Loosen the clamp screws, withdraw the concrete piston, replace corresponding worn parts,
and reinstall the concrete piston.
9.2 Disassembly and installation of S-valve Refer to Figure 5-1.
38
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
1. Anti-wearing plate 2. Cutting ring 3. Rubber spring 4. S-valve 5. Nylon bushing 6. Bearing block
7. Anti-wearing sleeve 8. Flange plate 9. Rubber plate 10. Anti-wearing sleeve 11. Hexagon socket screw
12. Hexagon socket screw 13. Spring washer
The S-valve, anti-wearing plate, and cutting ring are subject to wear after being serviced normally
for a period. Measure the gap between the cutting ring and anti-wearing plate (Above figure). Use
the adjustment bolt ① to adjust the gap to 1~3mm. If the gap is above 5mm, make sure to replace
the anti-wearing plate and cutting ring.
Caution: Make sure to stop the engine before adjustment of S-valve and
disassembly/installation of anti-wearing plate.
39
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
40
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
● ● Leakage status
● ● ● ● ● ● Cooling system
● ● ● Fuel system
Valve clearance
● ● ● (adjust when
necessary)
● ● ● Engine suspension
● ● ● V-belt
● ● Alarm device
● ● Fasteners
● ● Preheating plug
● ● Coolant
Concentration of
● ● cooling medium
additive
● ● Coolant level
Hose connector/pipe
● ●
clamp, air intake side
41
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
Figure 5-3 Engine Oil Filler Port Figure 5-4 Engine Oil Dipstick
(2) Check the engine oil, diesel, and coolant pipe connectors for presence of fluid permeation.
(3) Check the intake pipeline for presence of damage and check connector clamps for presence
of looseness and air leakage.
(4) Check and clean the dry air filter.
Figure 5-5 Air Filter Structure Figure 5-6 Dust Drainage of Air Filter
(5) Check the battery and wires.
(6) Check and add coolant: Please carefully read the self-adhesive maintenance diagram label on
the diesel engine radiator for details.
(7) Replace the engine oil filter element.
42
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
③ Observe the coolant level during running and timely add the coolant.
④ Install the filler port cap 1.
(5) Check the battery and wires.
(6) Bleed the air from the diesel engine before start.
Figure 5-11 Manual Pump (integral coarse Figure 5-12 High Pressure Fuel Pipe of Diesel
filter of pump filter) Engine
① Pump the fuel of diesel engine by manual pump "1" on the fuel-gas separator.
② When the resistance of the manual pump is too high for further pumping, loosen 6
monoblock pump high pressure fuel pipe connectors "2" of diesel engine to relieve the air
bubbles.
③ After there is no more air bubble, lock 6 monoblock pump high pressure fuel pipe connectors
"2" of diesel engine.
④ Further pump the fuel of diesel engine by manual pump "1" on the fuel-gas separator and
attempt to start the diesel engine. If the engine fails to start in 10s, repeat the step ② and step
③. If the engine fails to start, wait for at least 1min before retry.
⑤ Start the diesel engine and at the same time pump the fuel of diesel engine by manual pump
"1" on the fuel-gas separator, till the diesel engine is running completely.
(7) Conduct the test run.
After the engine is running under no-load for approximately 10min:
① Check the engine for presence of leakage.
② After the engine is stopped, check the engine oil level. If the oil level is lightly higher than
the minimum marking “Min”, make sure to add engine oil, as shown in Figure 5-4 (Engine
Oil Dipstick).
44
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
45
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
Chapter VI
Troubleshooting
46
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
1. Typical Malfunctions
Precautions:
(1) The electric cabinet and hydraulic system must be repaired by the professionals.
(2) The table below describes the simple typical malfunctions and troubleshooting. The specific
complicated malfunctions can be solved only through site analysis. In event of special
malfunctions, please contact the After-Service Department of our company for
troubleshooting assistance.
47
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
Symptom Possible Malfunction Troubleshooting
48
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
2. Status Record
49
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
Chapter VII
Safety Rules
50
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
51
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
Engine module
J1939 interface
PTO request Keyhole circuit
Pressure Temperature
gauge gauge
Local Remote
Chassis control control
interface
Handbrake
signal
Remote
Condensing External Remote control Local control
Feedback Engine oil pressure Coolant temperature display Flameout Diesel engine alternator and charging Battery and power Hopper lamp Remote control forward/reverse Reverse Remote control control Remote control
Odometer PTO Driving Transfer case limit solenoid Start solenoid valve and relay Start motor and start control power Clearance lamp Power start and emergency stop control displacement adjustment forward/revers Local control displacement +/-
indicator lamp display and alarm and alarm electromagnet control main switch control pumping mixing emergence stop indicator signal
valve socket +/- e pumping
lamp
Pressure
Oil Remote Forward/ High Return Preheater
Displacement Engine Proximity Proximity Outrigger relay and Start of main Cooling Engine Pressure Temperature Emergency Manual speed Chassis Water Accelerator Inching of swing
Reserved temperature Reserved Reserved Mix control reverse pressure Linear motor and its control Accumulator Reserved Reserved of OFF
up/down speed switch A switch B operations reverse cylinder A/B fan start alarm alarm stop up/down PTO cleaning motor limit cylinder A/B
signal signal pumping switchover piston
mixing
Linear motor
Black
Display
White Blue
Grey
Chassis CAN
52
Operation Manual of Loxa Heavy Machinery Truck-Mounted Concrete Pump
Main
Main cylinder B
Left Right
cylinder
Mixing motor
Swing
Swing
cylinder A
Water pump cylinder B
motor
Air-cooling
motor
Water cooler
53