ID Task Task Name Duration Start Finish PredecessorsResource Names Cost July 2021 August 2021 September 2021

Finish PredecessorsResource Names Cost July 2021 August 2021 September 2021 October 2021 November 2021 December 2021 January 2022
Mode 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 4 6 8 10 12 14 16 18 20
1 PEMBANGUNAN GEDUNG OLAHRAGA 144 days Sat 6/12/21 Wed 12/1/21 Rp1,940,687,918
2 PEKERJAAN LANTAI 1 144 days Sat 6/12/21 Wed 12/1/21 Rp1,150,665,487
3 PEKERJAAAN PERSIAPAN 22 days Sat 6/12/21 Wed 7/7/21 Rp183,595,457
4 Pembersihan Lokasi 8 days Sat 6/12/21 Mon 6/21/21 Pekerja[2],Mandor Rp2,200,000 Pekerja[2],Mandor
5 Pemasangan Bowplank dan Pengukuran 18 days Sat 6/12/21 Fri 7/2/21 Kayu Kelas III - Balok Usuk (Meranti) Uk. 5 xRp31,742,957
7 cm; 400 cm[2.62 m3],Mandor,Kepala Tukang,Tukang Kayu,Pekerja[2],Paku Biasa - Uk. 2 - 5 inch[4.36 Kayukg],Kayu
Kelas III Kelas
- BalokIIIUsuk
- Papan Uk. 3/20[1.53
(Meranti) Uk. 5 x 7 m3]
cm; 400 cm[2.62 m3],Mandor,Kepala Tukang,Tukang Kayu,Pekerja[2],Paku Biasa - Uk. 2 - 5 inch[4.36 kg],Kayu Kelas III - Papan Uk. 3/20[1.53 m3]
6 Direksi Keet dan Gudang 4 days Sat 7/3/21 Wed 7/7/21 5 Mandor,Kepala Tukang,Tukang Batu,Pekerja[2],Kayu
Rp149,652,500 Kelas III - Balok Usuk (Meranti) Uk. 5 x 7 cm; 400 cm[21 m3],Triplek - Uk. 122 x 244 cm; tbl. 4 mm[60 lembar],Skrup Asbes -Tukang,Tukang
Mandor,Kepala Uk. 4 inch.[45 Batu,Pekerja[2],Kayu
kg],Plafon Asbes Eternit
Kelas- Tbl.
III -4Balok
mm; Usuk
5 mm;(Meranti)
6 mm[74.4 Uk.lembar],As...
5 x 7 cm; 400 cm[21 m3],Triplek - Uk. 122 x 244 cm; tbl. 4 mm[60 lembar],Skrup Asbes - Uk. 4 inch.[45 kg],Plafon Asbes Eternit - Tbl. 4 mm; 5 mm; 6 mm[74.4 lembar],As...
7 PEKERJAAN TANAH 14 days Sat 7/3/21 Mon 7/19/21 Rp11,206,415
8 Galian Tanah Pondasi Strauss Pile 8 days Sat 7/3/21 Mon 7/12/21 5 Mandor,Pekerja[2] Rp1,760,000 Mandor,Pekerja[2]
9 Galian Tanah Pondasi Pile Cap 1 day Tue 7/13/21 Tue 7/13/21 8 Mandor,Pekerja[2] Rp320,000 Mandor,Pekerja[2]
10 Urugan Pasir Bawah Pondasi Pile Cap 1 day Wed 7/14/21 Wed 7/14/21 9 Mandor,Pekerja[2],Pasir Urug[1.98 m3] Rp607,290 Mandor,Pekerja[2],Pasir Urug[1.98 m3]
11 Urugan Tanah Kembali Untuk Pondasi Pile Cap 1 day Thu 7/15/21 Thu 7/15/21 10 Mandor,Pekerja[2] Rp240,000 Mandor,Pekerja[2]
12 Urugan Pasir Bawah Lantai 3 days Fri 7/16/21 Mon 7/19/21 11 Mandor,Pekerja[2],Pasir Urug[40.75 m3] Rp8,279,125 Mandor,Pekerja[2],Pasir Urug[40.75 m3]
13 PEKERJAAN PENULANGAN 57 days Wed 7/21/21 Mon 9/27/21 Rp39,022,537
14 Pekerjaan Penulangan Strauss Pile & Pile Cap P1 4 days Thu 7/22/21 Mon 8/30/21 19 Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Rp4,449,453
Beton - Polos/Ulir[288.92 kg],Kawat beton[4.13 kg] Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[288.92 kg],Kawat beton[4.13 kg]
15 Pekerjaan Penulangan Strauss Pile & Pile Cap P2 7 days Mon 8/30/21 Tue 9/7/21 14 Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Rp5,529,116
Beton - Polos/Ulir[273.53 kg],Kawat beton[3.91 kg] Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[273.53 kg],Kawat beton[3.91 kg]
16 Pekerjaan Penulangan Strauss Pile & Pile Cap P3 3 days Tue 9/7/21 Fri 9/10/21 15 Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Rp3,682,146
Beton - Polos/Ulir[260.03 kg],Kawat beton[3.71 kg] Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[260.03 kg],Kawat beton[3.71 kg]
17 Pekerjaan Penulangan Strauss Pile & Pile Cap P4 1 day Fri 9/10/21 Sat 9/11/21 16 Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Rp3,591,159
Beton - Polos/Ulir[279.24 kg],Kawat beton[3.99 kg] Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[279.24 kg],Kawat beton[3.99 kg]
18 Pekerjaan Penulangan Sloof 5 days Mon 8/30/21 Sat 9/4/21 14 Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,BesiRp10,067,120
Beton - Polos/Ulir[728.16 kg],Kawat beton[10.4 kg] Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[728.16 kg],Kawat beton[10.4 kg]
19 Pekerjaan Penulangan Lantai Kerja 1 day Wed 7/21/21 Wed 7/21/21 12 Mandor,Pekerja,Kepala Tukang,Tukang Besi,Besi Rp391,962
Beton - Polos/Ulir[8.46 kg],Kawat beton[0.12 kg] Mandor,Pekerja,Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[8.46 kg],Kawat beton[0.12 kg]
20 Pekerjaan Penulangan Kolom K1 45/45 7 days Sat 9/4/21 Mon 9/13/21 18 Mandor,Pekerja,Kepala Tukang,Tukang Besi,Besi Rp3,267,285
Beton - Polos/Ulir[97.69 kg],Kawat beton[1.4 kg] Mandor,Pekerja,Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[97.69 kg],Kawat beton[1.4 kg]
21 Pekerjaan Penulangan Kolom Pedestal 45/45 6 days Mon 9/13/21 Mon 9/27/21 20 Mandor,Pekerja,Kepala Tukang,Tukang Besi,Besi Rp8,044,296
Beton - Polos/Ulir[546.71 kg],Kawat beton[7.81 kg] Mandor,Pekerja,Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[546.71 kg],Kawat beton[7.81 kg]
22 PEKERJAAN BEKISTING 28 days Mon 9/6/21 Fri 10/8/21 Rp348,991,626
23 Pekerjaan Bekisting Pile Cap P1 1 day Mon 9/6/21 Tue 9/7/21 Mandor,Kepala Tukang,Tukang Kayu,Pekerja,Paku
14FS+6 days Rp3,215,001
Biasa - Uk. 2 - 5 inch[3.46 kg],Minyak Bekisting[1.15 liter],Kayu Kelas III - Papan[0.46 m3] Mandor,Kepala Tukang,Tukang Kayu,Pekerja,Paku Biasa - Uk. 2 - 5 inch[3.46 kg],Minyak Bekisting[1.15 liter],Kayu Kelas III - Papan[0.46 m3]
24 Pekerjaan Bekisting Pile Cap P2 1 day Tue 9/7/21 Wed 9/8/21 23 Mandor,Kepala Tukang,Tukang Kayu[2],Pekerja[2],Paku
Rp6,398,256 Biasa - Uk. 2 - 5 inch[6.19 kg],Minyak Bekisting[2.3 liter],Kayu Kelas III - Papan[0.92 m3] Mandor,Kepala Tukang,Tukang Kayu[2],Pekerja[2],Paku Biasa - Uk. 2 - 5 inch[6.19 kg],Minyak Bekisting[2.3 liter],Kayu Kelas III - Papan[0.92 m3]
25 Pekerjaan Bekisting Pile Cap P3 3 days Wed 9/8/21 Sat 9/11/21 24 Mandor,Kepala Tukang,Tukang Kayu[4],Pekerja[5],Paku
Rp21,734,558 Biasa - Uk. 2 - 5 inch[21.12 kg],Minyak Bekisting[7.04 liter],Kayu Kelas III - Papan[2.82 m3] Mandor,Kepala Tukang,Tukang Kayu[4],Pekerja[5],Paku Biasa - Uk. 2 - 5 inch[21.12 kg],Minyak Bekisting[7.04 liter],Kayu Kelas III - Papan[2.82 m3]
26 Pekerjaan Bekisting Pile Cap P4 1 day Sat 9/11/21 Mon 9/13/21 25 Mandor,Kepala Tukang,Tukang Kayu,Pekerja,Paku Rp2,622,032
Biasa - Uk. 2 - 5 inch[2.69 kg],Minyak Bekisting[0.9 liter],Kayu Kelas III - Papan[0.36 m3] Mandor,Kepala Tukang,Tukang Kayu,Pekerja,Paku Biasa - Uk. 2 - 5 inch[2.69 kg],Minyak Bekisting[0.9 liter],Kayu Kelas III - Papan[0.36 m3]
27 Pekerjaan Bekisting Kolom K1 45/45 & Pedestal 45/45 20 days Wed 9/15/21 Fri 10/8/21 28SS+2 Mandor,Kepala Rp192,078,490 Mandor,Kepala Tukang,Tukang Kayu,Pekerja[2],Paku Biasa - Uk. 2 - 5 inch[153.22 kg],Minyak Bekisting[76.61 liter],Kayu Kelas III - Papan[15.32 m3],Kayu Kelas II - Balok[5.75 m3],Plywood - Uk. 9 mm[134.06 lembar],Dolken Kayu - Dia. 8-10/400 cm[766.08 bat...
days Tukang,Tukang
28 Pekerjaan Bekisting Sloof 20 days Mon 9/13/21 Wed 10/6/21 26 Kayu,Pekerja[2],Paku
Mandor,Kepala Biasa -
Tukang[2],Tukang Kayu,Pekerja[2],Paku
Rp122,943,289 Biasa - Uk. 2 - 5 inch[122.04 kg],Minyak Bekisting[40.68 liter],Kayu Kelas III - Papan[18.31 m3] Mandor,Kepala Tukang[2],Tukang Kayu,Pekerja[2],Paku Biasa - Uk. 2 - 5 inch[122.04 kg],Minyak Bekisting[40.68 liter],Kayu Kelas III - Papan[18.31 m3]
29 PEKERJAAN BETON 36 days Mon 8/30/21 Mon 10/11/21 Rp254,036,878
30 Pekerjaan Strauss Pile P1 6 days Mon 8/30/21 Mon 9/6/21 14 Mandor,Kepala Tukang[2],Tukang Batu,Pekerja[2],Semen
Rp7,014,033Portland - 50 kg[2,756.74 kg],Pasir Beton[3.32 m3],Air[1,459.85 liter],Kerikil - Max. 30 mm[3.87 m3] Mandor,Kepala Tukang[2],Tukang Batu,Pekerja[2],Semen Portland - 50 kg[2,756.74 kg],Pasir Beton[3.32 m3],Air[1,459.85 liter],Kerikil - Max. 30 mm[3.87 m3]
31 Pekerjaan Strauss Pile P2 1 day Tue 9/7/21 Wed 9/8/21 15 Mandor,Kepala Tukang[2],Tukang Batu[6],Pekerja[8],Semen
Rp15,566,813 Portland - 50 kg[7,653.1 kg],Pasir Beton[9.22 m3],Air[4,052.75 liter],Kerikil - Max. 30 mm[10.75 m3] Mandor,Kepala Tukang[2],Tukang Batu[6],Pekerja[8],Semen Portland - 50 kg[7,653.1 kg],Pasir Beton[9.22 m3],Air[4,052.75 liter],Kerikil - Max. 30 mm[10.75 m3]
32 Pekerjaan Strauss Pile P3 1 day Fri 9/10/21 Sat 9/11/21 16 Mandor,Kepala Tukang[4],Tukang Batu[6],Pekerja[8],Semen
Rp56,840,617 Portland - 50 kg[31,115.84 kg],Pasir Beton[37.48 m3],Air[16,477.6 liter],Kerikil - Max. 30 mm[43.69 m3] Mandor,Kepala Tukang[4],Tukang Batu[6],Pekerja[8],Semen Portland - 50 kg[31,115.84 kg],Pasir Beton[37.48 m3],Air[16,477.6 liter],Kerikil - Max. 30 mm[43.69 m3]
33 Pekerjaan Strauss Pile P4 1 day Sat 9/11/21 Mon 9/13/21 17,30SS Mandor,Kepala Tukang,Tukang Batu[2],Pekerja[8],Semen
Rp5,703,125Portland - 50 kg[2,448.18 kg],Pasir Beton[2.95 m3],Air[1,296.45 liter],Kerikil - Max. 30 mm[3.35 m3] Mandor,Kepala Tukang,Tukang Batu[2],Pekerja[8],Semen Portland - 50 kg[2,448.18 kg],Pasir Beton[2.95 m3],Air[1,296.45 liter],Kerikil - Max. 30 mm[3.35 m3]
34 Pekerjaan Pondasi Pile Cap P1 1 day Tue 9/7/21 Wed 9/8/21 23,30 Mandor,Kepala Tukang,Tukang Batu,Pekerja,Semen Rp1,619,810
Portland - 50 kg[584.64 kg],Pasir Beton[0.7 m3],Air[309.6 liter],Kerikil - Max. 30 mm[0.82 m3] Mandor,Kepala Tukang,Tukang Batu,Pekerja,Semen Portland - 50 kg[584.64 kg],Pasir Beton[0.7 m3],Air[309.6 liter],Kerikil - Max. 30 mm[0.82 m3]
35 Pekerjaan Pondasi Pile Cap P2 1 day Wed 9/8/21 Thu 9/9/21 24,34 Mandor,Kepala Tukang,Tukang Batu,Pekerja[5],SemenRp4,134,158 Portland - 50 kg[1,843.24 kg],Pasir Beton[2.22 m3],Air[976.1 liter],Kerikil - Max. 30 mm[2.26 m3] Mandor,Kepala Tukang,Tukang Batu,Pekerja[5],Semen Portland - 50 kg[1,843.24 kg],Pasir Beton[2.22 m3],Air[976.1 liter],Kerikil - Max. 30 mm[2.26 m3]
36 Pekerjaan Pondasi Pile Cap P3 1 day Sat 9/11/21 Mon 9/13/21 25,35 Rp12,969,142 Portland - 50 kg[6,252.4 kg],Pasir Beton[7.53 m3],Air[3,311 liter],Kerikil - Max. 30 mm[8.78 m3]
Mandor,Kepala Tukang[2],Tukang Batu[6],Pekerja[8],Semen Mandor,Kepala Tukang[2],Tukang Batu[6],Pekerja[8],Semen Portland - 50 kg[6,252.4 kg],Pasir Beton[7.53 m3],Air[3,311 liter],Kerikil - Max. 30 mm[8.78 m3]
37 Pekerjaan Pondasi Pile Cap P4 1 day Mon 9/13/21 Tue 9/14/21 26,36 Mandor,Kepala Tukang,Tukang Batu,Pekerja,Semen Rp1,691,740
Portland - 50 kg[625.24 kg],Pasir Beton[0.75 m3],Air[331.1 liter],Kerikil - Max. 30 mm[0.88 m3] Mandor,Kepala Tukang,Tukang Batu,Pekerja,Semen Portland - 50 kg[625.24 kg],Pasir Beton[0.75 m3],Air[331.1 liter],Kerikil - Max. 30 mm[0.88 m3]
38 Pekerjaan Kolom K1 45/45 & Pedestal 45/45 3 days Tue 9/21/21 Fri 9/24/21 37FS+6 days Rp89,650,698 Portland - 50 kg[71,494.54 kg],Pasir Beton[21.07 m3],Air[9,264.35 liter],Kerikil - Max. 30 mm[24.56 m3]
Mandor,Kepala Tukang[2],Tukang Batu[4],Pekerja[6],Semen Mandor,Kepala Tukang[2],Tukang Batu[4],Pekerja[6],Semen Portland - 50 kg[71,494.54 kg],Pasir Beton[21.07 m3],Air[9,264.35 liter],Kerikil - Max. 30 mm[24.56 m3]
39 Pekerjaan Sloof Beton Bertulang 8 days Fri 10/1/21 Mon 10/11/2138FS+6 days
Mandor,Kepala Tukang,Tukang Batu,Pekerja[2],Semen
Rp58,846,742 Portland - 50 kg[32,236.4 kg],Pasir Beton[38.83 m3],Air[17,071 liter],Kerikil - Max. 30 mm[45.26 m3] Mandor,Kepala Tukang,Tukang Batu,Pekerja[2],Semen Portland - 50 kg[32,236.4 kg],Pasir Beton[38.83 m3],Air[17,071 liter],Kerikil - Max. 30 mm[45.26 m3]
40 PEKERJAAN TANGGA 11 days Wed 7/14/21 Tue 7/27/21 Rp36,737,793
41 Pekerjaan Tangga Utama 11 days Wed 7/14/21 Tue 7/27/21 Rp36,737,793
42 a. Pekerjaan Pondasi Tangga 5 days Wed 7/14/21 Mon 7/19/21 Rp12,058,170
43 - Urugan pasir bawah pondasi 1 day Wed 7/14/21 Wed 7/14/21 10SS Mandor,Pekerja,Pasir Urug[0.22 m3] Rp340,810 Mandor,Pekerja,Pasir Urug[0.22 m3]
44 - Lantai kerja 1 day Thu 7/15/21 Thu 7/15/21 43 Mandor,Pekerja,Kepala Tukang,Tukang Batu Rp600,000 Mandor,Pekerja,Kepala Tukang,Tukang Batu
45 - Urugan tanah kembali 1 day Thu 7/15/21 Thu 7/15/21 44SS Mandor,Pekerja Rp300,000 Mandor,Pekerja
46 - Bekisting 1 day Sat 7/17/21 Sat 7/17/21 47 Mandor,Pekerja,Kepala Tukang,Tukang Batu,Kayu Rp1,984,118
Kelas III - Papan[0.12 m3],Paku Biasa - Uk. 2 - 5 inch[1.59 kg],Minyak Bekisting[0.6 liter],Kayu Kelas II - Balok[0.06 m3],Plywood - Uk. 9 mm[1.39Mandor,Pekerja,Kepala
lembar],Dolken Kayu -Tukang,Tukang
Dia. 8-10/400 cm[7.96
Batu,Kayubatang]
Kelas III - Papan[0.12 m3],Paku Biasa - Uk. 2 - 5 inch[1.59 kg],Minyak Bekisting[0.6 liter],Kayu Kelas II - Balok[0.06 m3],Plywood - Uk. 9 mm[1.39 lembar],Dolken Kayu - Dia. 8-10/400 cm[7.96 batang]
47 - Penulangan 1 day Fri 7/16/21 Fri 7/16/21 45 Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Rp7,808,594
Beton - Polos/Ulir[688.74 kg],Kawat beton[9.84 kg] Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[688.74 kg],Kawat beton[9.84 kg]
48 - Pekerjaan Beton 1 day Mon 7/19/21 Mon 7/19/21 46 Mandor,Kepala Tukang,Tukang Batu,Pekerja,Semen Rp1,024,648
Portland - 50 kg[244.09 kg],Pasir Beton[0.29 m3],Air[129.26 liter],Kerikil - Max. 30 mm[0.34 m3] Mandor,Kepala Tukang,Tukang Batu,Pekerja,Semen Portland - 50 kg[244.09 kg],Pasir Beton[0.29 m3],Air[129.26 liter],Kerikil - Max. 30 mm[0.34 m3]
49 b. Pekerjaan Tangga 1 6 days Wed 7/21/21 Tue 7/27/21 Rp24,679,623
50 - Penulangan 1 day Wed 7/21/21 Wed 7/21/21 48 Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Rp7,178,529
Beton - Polos/Ulir[605.05 kg],Kawat beton[8.64 kg] Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[605.05 kg],Kawat beton[8.64 kg]
51 - Bekisting 3 days Thu 7/22/21 Sat 7/24/21 50 Mandor,Pekerja[5],Kepala Tukang,Kayu Kelas Rp14,053,290
III - Papan[0.75 m3],Paku Biasa - Uk. 2 - 5 inch[10.06 kg],Minyak Bekisting[3.77 liter],Kayu Kelas II - Balok[0.38 m3],Plywood - Uk. 9 mm[8.81 lembar],Dolken Kayu - Dia. 8-10/400 cm[50.36 batang],Tukang
Mandor,Pekerja[5],Kepala Kayu[2]Kelas III - Papan[0.75 m3],Paku Biasa - Uk. 2 - 5 inch[10.06 kg],Minyak Bekisting[3.77 liter],Kayu Kelas II - Balok[0.38 m3],Plywood - Uk. 9 mm[8.81 lembar],Dolken Kayu - Dia. 8-10/400 cm[50.36 batang],Tukang Kayu[2]
Tukang,Kayu
52 - Pekerjaan Beton 2 days Mon 7/26/21 Tue 7/27/21 51 Mandor,Kepala Tukang,Pekerja[2],Semen Portland Rp3,447,804
- 50 kg[244.09 kg],Pasir Beton[0.29 m3],Air[8,245.04 liter],Kerikil - Max. 30 mm[0.34 m3],Tukang Besi Mandor,Kepala Tukang,Pekerja[2],Semen Portland - 50 kg[244.09 kg],Pasir Beton[0.29 m3],Air[8,245.04 liter],Kerikil - Max. 30 mm[0.34 m3],Tukang Besi
53 PEKERJAAN DINDING 17 days Mon 10/18/21 Mon 11/8/21 Rp175,484,598
54 Pas. Batu Bata Merah 1Pc : 6Psr 3 days Mon 10/18/21 Fri 10/22/21 39FS+6 days
Semen Portland - 50 kg[2,450.64 kg],Batu Bata Rp20,085,802
Merah[17,721.55 buah],Pasir Pasang[11.39 m3],Mandor[0.2],Kepala Tukang[0.2],Tukang Batu[2],Pekerja Semen Portland - 50 kg[2,450.64 kg],Batu Bata Merah[17,721.55 buah],Pasir Pasang[11.39 m3],Mandor[0.2],Kepala Tukang[0.2],Tukang Batu[2],Pekerja
55 Pas. Batu Bata Trasram 1 Pc : 4Psr 3 days Mon 10/18/21 Fri 10/22/21 39FS+6 days
Semen Portland - 50 kg[8,566.09 kg],Batu Bata Rp50,997,568
Merah[45,169.6 buah],Pasir Pasang[30.01 m3],Kepala Tukang[0.2],Mandor[0.1],Tukang Batu,Pekerja Semen Portland - 50 kg[8,566.09 kg],Batu Bata Merah[45,169.6 buah],Pasir Pasang[30.01 m3],Kepala Tukang[0.2],Mandor[0.1],Tukang Batu,Pekerja
56 Benangan 2 days Fri 10/22/21 Mon 10/25/2155 Semen Portland - 50 kg[54,119.52 kg],Pasir Pasang[189.57
Rp89,244,206m3],Mandor[0.1],Tukang Batu[2],Pekerja[2] Semen Portland - 50 kg[54,119.52 kg],Pasir Pasang[189.57 m3],Mandor[0.1],Tukang Batu[2],Pekerja[2]
57 Plesteran Halus 1 Pc : 4Psr 1 day Fri 10/29/21 Sat 10/30/21 54FS+6 days
Semen Portland - 50 kg[7,185.55 kg],Pasir Pasang[27.64
Rp12,455,222 m3],Mandor[0.1],Kepala Tukang[0.2],Tukang Batu,Pekerja Semen Portland - 50 kg[7,185.55 kg],Pasir Pasang[27.64 m3],Mandor[0.1],Kepala Tukang[0.2],Tukang Batu,Pekerja
58 Acian 1 day Sat 11/6/21 Mon 11/8/21 57FS+6 days
Semen Portland - 50 kg[2,131.8 kg],Mandor[0.2],Kepala
Rp2,701,800 Tukang[0.2],Tukang Batu[2],Pekerja[2] Semen Portland - 50 kg[2,131.8 kg],Mandor[0.2],Kepala Tukang[0.2],Tukang Batu[2],Pekerja[2]
59 PEKERJAAN KUSEN 8 days Tue 10/19/21 Fri 10/29/21 Rp22,572,373
60 Pas. Kusen Pintu Type P1 2 days Tue 10/19/21 Fri 10/22/21 Rp3,935,203
61 - Kusen 2 days Tue 10/19/21 Fri 10/22/21 54SS+25%Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kusen Rp2,363,003 Alumunium Profil - Uk. 4 inch.[10 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.15 kg],Lem Plastic Steel Epoxy - 48 gr[0.03 kg] Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kusen Alumunium Profil - Uk. 4 inch.[10 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.15 kg],Lem Plastic Steel Epoxy - 48 gr[0.03 kg]
62 - Handle Pintu 1 day Tue 10/19/21 Thu 10/21/21 61SS Kepala Tukang,Tukang Besi[2],Handle Pintu[2 buah] Rp380,000 Kepala Tukang,Tukang Besi[2],Handle Pintu[2 buah]
63 - Engsel Pintu 1 day Tue 10/19/21 Thu 10/21/21 61SS Kepala Tukang,Tukang Besi,Engsel Kupu-KupuRp401,400 - Besi/Alumunium 2 inch[6 buah] Kepala Tukang,Tukang Besi,Engsel Kupu-Kupu - Besi/Alumunium 2 inch[6 buah]
64 - Grendel Besar 1 day Tue 10/19/21 Thu 10/21/21 61SS Kepala Tukang,Tukang Besi,Grendel - Brass/StainlessRp356,000Steel Uk. 6 inch.[4 buah] Kepala Tukang,Tukang Besi,Grendel - Brass/Stainless Steel Uk. 6 inch.[4 buah]
65 - Kunci Tanam 1 day Tue 10/19/21 Thu 10/21/21 61SS Kepala Tukang,Tukang Besi,Kunci Silinder - Brass/Alumunium
Rp434,800 Uk. 60 mm[2 buah] Kepala Tukang,Tukang Besi,Kunci Silinder - Brass/Alumunium Uk. 60 mm[2 buah]
66 Pas. Kusen Pintu Type P2 8 days Tue 10/19/21 Fri 10/29/21 Rp4,825,931
67 - Kusen 4 days Tue 10/19/21 Mon 10/25/2154SS+25%Mandor,Kepala Tukang,Pekerja[2],Kusen Alumunium Rp2,353,731Profil - Uk. 4 inch.[7 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.11 kg],Lem Plastic Steel Epoxy - 48 gr[0.02 kg],Tukang Kayu Mandor,Kepala Tukang,Pekerja[2],Kusen Alumunium Profil - Uk. 4 inch.[7 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.11 kg],Lem Plastic Steel Epoxy - 48 gr[0.02 kg],Tukang Kayu
68 - Handle Pintu 4 days Mon 10/25/21 Fri 10/29/21 67 Kepala Tukang,Tukang Besi,Handle Pintu[2 buah] Rp1,400,000 Kepala Tukang,Tukang Besi,Handle Pintu[2 buah]
69 - Engsel Pintu 1 day Mon 10/25/21 Tue 10/26/21 67 Kepala Tukang,Tukang Besi,Engsel Kupu-KupuRp401,400 - Besi/Alumunium 2 inch[6 buah] Kepala Tukang,Tukang Besi,Engsel Kupu-Kupu - Besi/Alumunium 2 inch[6 buah]
70 - Grendel Besar 1 day Mon 10/25/21 Tue 10/26/21 67 Kepala Tukang,Tukang Besi,Grendel - Brass/StainlessRp356,000Steel Uk. 6 inch.[4 buah] Kepala Tukang,Tukang Besi,Grendel - Brass/Stainless Steel Uk. 6 inch.[4 buah]
71 - Kunci Tanam 1 day Fri 10/22/21 Sat 10/23/21 61 Kepala Tukang,Tukang Besi[2],Kunci Silinder - Rp314,800
Brass/Alumunium Uk. 60 mm[2 buah] Kepala Tukang,Tukang Besi[2],Kunci Silinder - Brass/Alumunium Uk. 60 mm[2 buah]
72 Pas. Kusen Pintu Type PB1 3 days Tue 10/19/21 Sat 10/23/21 Rp2,847,142
73 - Kusen 3 days Tue 10/19/21 Sat 10/23/21 54SS+25%Mandor,Kepala Tukang[0.1],Tukang Besi,Pekerja,Kusen
Rp1,444,442 Alumunium Profil - Uk. 4 inch.[5 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.08 kg],Lem Plastic Steel Epoxy - 48 gr[0.02 kg] Mandor,Kepala Tukang[0.1],Tukang Besi,Pekerja,Kusen Alumunium Profil - Uk. 4 inch.[5 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.08 kg],Lem Plastic Steel Epoxy - 48 gr[0.02 kg]
74 - Handle Pintu 1 day Fri 10/22/21 Sat 10/23/21 61 Kepala Tukang,Tukang Besi,Handle Pintu[2 buah] Rp500,000 Kepala Tukang,Tukang Besi,Handle Pintu[2 buah]
75 - Engsel Pintu 1 day Fri 10/22/21 Sat 10/23/21 61 Kepala Tukang,Tukang Besi,Engsel Kupu-KupuRp401,400 - Besi/Alumunium 2 inch[6 buah] Kepala Tukang,Tukang Besi,Engsel Kupu-Kupu - Besi/Alumunium 2 inch[6 buah]
76 - Grendel Besar 1 day Fri 10/22/21 Sat 10/23/21 61 Kepala Tukang,Tukang Besi,Grendel - Brass/StainlessRp207,500Steel Uk. 6 inch.[4 buah] Kepala Tukang,Tukang Besi,Grendel - Brass/Stainless Steel Uk. 6 inch.[4 buah]
77 - Kunci Tanam 1 day Fri 10/22/21 Sat 10/23/21 61 Kepala Tukang,Tukang Besi,Kunci Silinder - Brass/Alumunium
Rp293,800 Uk. 60 mm[2 buah] Kepala Tukang,Tukang Besi,Kunci Silinder - Brass/Alumunium Uk. 60 mm[2 buah]
78 Pas. Kusen Jendela Type J1 3 days Tue 10/19/21 Sat 10/23/21 Rp4,897,648
79 - Kusen 1 day Tue 10/19/21 Thu 10/21/21 54SS+25%Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kusen Rp3,845,135 Alumunium Profil - Uk. 4 inch.[18.93 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.28 kg],Lem Plastic Steel Epoxy - 48 gr[0.06 kg] Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kusen Alumunium Profil - Uk. 4 inch.[18.93 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.28 kg],Lem Plastic Steel Epoxy - 48 gr[0.06 kg]
80 - Kaca Mati 1 day Fri 10/22/21 Sat 10/23/21 61 Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kaca Rp1,052,513
Polos Bening - tbl. 5 mm[7.07 m2],Silicone Rubber Sealent[0.32 tube] Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kaca Polos Bening - tbl. 5 mm[7.07 m2],Silicone Rubber Sealent[0.32 tube]
81 Pas. Kusen Type J2 4 days Tue 10/19/21 Mon 10/25/21 Rp6,066,448
82 - Kusen 1 day Tue 10/19/21 Thu 10/21/21 54SS+25%Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kusen Rp3,816,135 Alumunium Profil - Uk. 4 inch.[18.93 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.28 kg],Lem Plastic Steel Epoxy - 48 gr[0.06 kg] Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kusen Alumunium Profil - Uk. 4 inch.[18.93 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.28 kg],Lem Plastic Steel Epoxy - 48 gr[0.06 kg]
83 - Kaca Mati 1 day Fri 10/22/21 Sat 10/23/21 61 Mandor,Kepala Tukang,Tukang Besi,Pekerja[3],Kaca Rp1,408,013
Polos Bening - tbl. 5 mm[7.07 m2],Silicone Rubber Sealent[0.32 tube] Mandor,Kepala Tukang,Tukang Besi,Pekerja[3],Kaca Polos Bening - tbl. 5 mm[7.07 m2],Silicone Rubber Sealent[0.32 tube]
84 - Hak Angin 1 day Fri 10/22/21 Sat 10/23/21 61 Kepala Tukang,Tukang Besi,Hak Angin Sikutan Rp328,000
Biasa[2 m2] Kepala Tukang,Tukang Besi,Hak Angin Sikutan Biasa[2 m2]
85 - Engsel Jendela 1 day Fri 10/22/21 Sat 10/23/21 61 Kepala Tukang,Tukang Besi[2],Engsel Kupu-Kupu Rp198,800
- Besi/Alumunium 2 inch[2 buah] Kepala Tukang,Tukang Besi[2],Engsel Kupu-Kupu - Besi/Alumunium 2 inch[2 buah]
86 - Grendel Kecil 2 days Fri 10/22/21 Mon 10/25/2161 Kepala Tukang,Tukang Besi,Grendel - Brass/StainlessRp315,500Steel Uk. 6 inch.[1 buah] Kepala Tukang,Tukang Besi,Grendel - Brass/Stainless Steel Uk. 6 inch.[1 buah]
87 PEKERJAAN INSTALASI AIR 7 days Thu 7/15/21 Fri 7/23/21 Rp21,794,452
88 Kran Air 3/4" 1 day Thu 7/15/21 Thu 7/15/21 10 Kran Air Stainless Steel - Dia. 1/2 - 3/4 inch.[11 Rp545,192
unit],Sealtape[0.28 buah],Kepala Tukang,Tukang Pipa Kran Air Stainless Steel - Dia. 1/2 - 3/4 inch.[11 unit],Sealtape[0.28 buah],Kepala Tukang,Tukang Pipa
89 Instalasi Air Bersih PVC Ø 3/4" 2 days Fri 7/16/21 Sat 7/17/21 88 Mandor,Kepala Tukang,Tukang Pipa,Pekerja[2],Pipa Rp1,591,444
PVC - Type AW Dia. 3/4 inch. pjg. 400 cm[18.04 batang] Mandor,Kepala Tukang,Tukang Pipa,Pekerja[2],Pipa PVC - Type AW Dia. 3/4 inch. pjg. 400 cm[18.04 batang]
90 Instalasi Air Kotor PVC Ø 3" 1 day Mon 7/19/21 Mon 7/19/21 89 Tukang Pipa,Pipa PVC - Type AW Dia.3 inch. pjg. Rp634,800
400 cm[1 batang],Kepala Tukang,Mandor,Pekerja[2] Tukang Pipa,Pipa PVC - Type AW Dia.3 inch. pjg. 400 cm[1 batang],Kepala Tukang,Mandor,Pekerja[2]
91 Instalasi Kotoran PVC Ø 4" 2 days Wed 7/21/21 Thu 7/22/21 90 Pipa PVC - Type AW Dia.4 inch. pjg. 400 cm[11.25 Rp5,010,375
batang],Tukang Pipa,Mandor,Kepala Tukang,Pekerja[2] Pipa PVC - Type AW Dia.4 inch. pjg. 400 cm[11.25 batang],Tukang Pipa,Mandor,Kepala Tukang,Pekerja[2]
92 Klosed Duduk 1 day Fri 7/23/21 Fri 7/23/21 91 Kloset Duduk/Monoblock[5.3 buah],Mandor,Kepala Rp7,681,500
Tukang,Tukang Pipa,Pekerja[2] Kloset Duduk/Monoblock[5.3 buah],Mandor,Kepala Tukang,Tukang Pipa,Pekerja[2]
93 Septictank 2 days Fri 7/16/21 Sat 7/17/21 89SS Mandor,Tukang Pipa,Pekerja[4],Semen Portland Rp3,001,918
- 50 kg[0.12 kg],Pasir Pasang[0.01 m3],Septictank Biofilter 1 m3[1 unit] Mandor,Tukang Pipa,Pekerja[4],Semen Portland - 50 kg[0.12 kg],Pasir Pasang[0.01 m3],Septictank Biofilter 1 m3[1 unit]
94 Bak kontrol 1 day Thu 7/22/21 Thu 7/22/21 95 Mandor,Kepala Tukang,Pekerja[6],Batu Bata Merah[40
Rp1,237,305 buah],Semen Portland - 50 kg[44 kg],Pasir Pasang[0.07 m3],Pasir Beton[0.06 m3],Kerikil - Max. 30 mm[0.07 m3],Besi Beton - Polos/Ulir[1.6 kg],Tukang Batu Mandor,Kepala Tukang,Pekerja[6],Batu Bata Merah[40 buah],Semen Portland - 50 kg[44 kg],Pasir Pasang[0.07 m3],Pasir Beton[0.06 m3],Kerikil - Max. 30 mm[0.07 m3],Besi Beton - Polos/Ulir[1.6 kg],Tukang Batu
95 Sumur Peresap 2 days Mon 7/19/21 Wed 7/21/21 93 Semen Portland - 50 kg[0.12 kg],Pasir Pasang[0.01Rp2,091,918
m3],Batu Bata Merah[70 buah],Pas. Ijuk[2.5 kg],Mandor,Tukang Batu,Pekerja[4] Semen Portland - 50 kg[0.12 kg],Pasir Pasang[0.01 m3],Batu Bata Merah[70 buah],Pas. Ijuk[2.5 kg],Mandor,Tukang Batu,Pekerja[4]
96 PEKERJAAN LANTAI 39 days Fri 10/15/21 Wed 12/1/21 Rp36,993,681
97 Keramik Lantai 40 x 40 cm 4 days Thu 11/18/21 Tue 11/23/21 178SS Keramik Putih - Uk. 40 x 40 cm[107.41 m2],Semen Rp17,261,857
Portland - 50 kg[939.82 kg],Pasir Pasang[4.32 m3],Semen Warna - Nat[124.67 kg],Mandor,Kepala Tukang,Tukang Batu[2],Pekerja[8] Keramik Putih - Uk. 40 x 40 cm[107.41 m2],Semen Portland - 50 kg[939.82 kg],Pasir Pasang[4.32 m3],Semen Warna - Nat[124.67 kg],Mandor,Kepala Tukang,Tukang Batu[2],Pekerja[8]
98 Plester 2 days Mon 11/29/21 Wed 12/1/21 178FS+6 days
Semen Portland - 50 kg[1,320.82 kg],Pasir Pasang/Plester[5.08
Rp2,234,204 m3] Semen Portland - 50 kg[1,320.82 kg],Pasir Pasang/Plester[5.08 m3]
99 PEKERJAAN INSTALASI LISTRIK 8 days Fri 10/15/21 Tue 10/26/21 Rp17,497,620
100 Titik Lampu 1 day Fri 10/15/21 Sat 10/16/21 161SS Kabel NYA - 1 x 2.5 mm[1,080 m'],Pipa PVC -Rp9,676,400
Type C Dia. 5/8 inch. pjg. 400 cm[288 m'],Fitting Lampu Plafon[72 kg],T Dos PVC[72 buah],Kepala Tukang,Tukang Listrik[2],Pekerja[5] Kabel NYA - 1 x 2.5 mm[1,080 m'],Pipa PVC - Type C Dia. 5/8 inch. pjg. 400 cm[288 m'],Fitting Lampu Plafon[72 kg],T Dos PVC[72 buah],Kepala Tukang,Tukang Listrik[2],Pekerja[5]
101 Lampu Down light 1 day Mon 10/25/21 Tue 10/26/21 100FS+6 days
Lampu Down Light LED 18 watt[29 buah],Tukang Rp3,721,000
Listrik[2],Pekerja[4],Kepala Tukang Lampu Down Light LED 18 watt[29 buah],Tukang Listrik[2],Pekerja[4],Kepala Tukang
102 Saklar 1 day Thu 10/21/21 Fri 10/22/21 54FF Saklar Dinding - Ganda[8 buah],Kepala Tukang,Tukang
Rp1,011,600 Listrik[2],Pekerja[4] Saklar Dinding - Ganda[8 buah],Kepala Tukang,Tukang Listrik[2],Pekerja[4]
103 Stop Kontak 1 day Thu 10/21/21 Fri 10/22/21 54FF Kabel NYA - 1 x 2.5 mm[270 m'],Pipa PVC - Type Rp2,874,520
C Dia. 5/8 inch. pjg. 400 cm[14.4 m'],Stop Kontak - Tunggal[18 kg],T Dos PVC[18 buah],Kepala Tukang,Tukang Listrik[3],Pekerja[4] Kabel NYA - 1 x 2.5 mm[270 m'],Pipa PVC - Type C Dia. 5/8 inch. pjg. 400 cm[14.4 m'],Stop Kontak - Tunggal[18 kg],T Dos PVC[18 buah],Kepala Tukang,Tukang Listrik[3],Pekerja[4]
104 Box MCB 1 day Thu 10/21/21 Fri 10/22/21 54FF MCB Panel Box - Outbow 4 Grup[1 buah],Tukang Rp214,100
Listrik MCB Panel Box - Outbow 4 Grup[1 buah],Tukang Listrik
105 PEKERJAAN PENGECATAN 30 days Tue 10/19/21 Wed 11/24/21 Rp20,229,677
106 Pengecatan Dinding Eksterior (Weatherbond) 5 days Thu 11/18/21 Wed 11/24/21171SS Cat Tembok Exterior - Primer - Weather Shield[16.22
Rp16,834,525kaleng],Plamir Tembok[67.58 kg],Thinner[67.58 liter],Pisau Pallet[10.14 buah],Kuas Cat[10.14 buah],Kepala Tukang,Tukang Cat[2],Pekerja[5],Cat Tembok Exterior - Finishing - Weather Shield[24.33 kaleng] Cat Tembok Exterior - Primer - Weather Shield[16.22 kaleng],Plamir Tembok[67.58 kg],Thinner[67.58 liter],Pisau Pallet[10.14 buah],Kuas Cat[10.14 buah],Kepala Tukang,Tukang Cat[2],Pekerja[5],Cat Tembok Exterior - Finishing - Weather Sh
107 Pengecatan Dinding Interior (Spoot-Less) 1 day Tue 10/19/21 Thu 10/21/21 161 Cat Tembok Interior - Primer[3.21 kaleng],CatRp3,395,152
Tembok Interior - Finishing[8.34 kaleng],Plamir Tembok[8.02 kg],Amplas - No.240[80.17 lembar],Pisau Pallet[1.2 buah],Kuas Cat[1.2 buah],Mandor,Kepala Tukang,Tukang Cat,Pekerja[2] Cat Tembok Interior - Primer[3.21 kaleng],Cat Tembok Interior - Finishing[8.34 kaleng],Plamir Tembok[8.02 kg],Amplas - No.240[80.17 lembar],Pisau Pallet[1.2 buah],Kuas Cat[1.2 buah],Mandor,Kepala Tukang,Tukang Cat,Pekerja[2]
108 PEKERJAAN LANTAI 2 48 days Fri 10/1/21 Sat 11/27/21 Rp790,022,431
109 PEKERJAAN KONSTRUKSI BAJA 17 days Fri 10/22/21 Thu 11/11/21 Rp286,201,543
110 Pekerjaan Kolom K2 2 days Fri 10/22/21 Mon 10/25/21104 Baja Profil[4,570.56 kg],Mandor,Kepala Tukang,Tukang,Pekerja[2]
Rp82,473,524 Baja Profil[4,570.56 kg],Mandor,Kepala Tukang,Tukang,Pekerja[2]
111 Pekerjaan Kolom K3 2 days Fri 10/29/21 Mon 11/1/21 107SS+8 days
Tukang,Baja Profil[5,486.88 kg],Kepala Tukang,Mandor,Pekerja[2]
Rp98,927,152 Tukang,Baja Profil[5,486.88 kg],Kepala Tukang,Mandor,Pekerja[2]
112 Pekerjaan Balok WF 450.200 3 days Mon 11/1/21 Thu 11/4/21 111 Tukang,Baja Profil[699.2 kg],Kepala Tukang,Mandor,Pekerja[2]
Rp13,604,180 Tukang,Baja Profil[699.2 kg],Kepala Tukang,Mandor,Pekerja[2]
113 Pekerjaan Balok WF 400.200 2 days Tue 11/2/21 Thu 11/4/21 112FF Tukang,Baja Profil[1,442.1 kg],Kepala Tukang,Mandor,Pekerja[2]
Rp26,319,590 Tukang,Baja Profil[1,442.1 kg],Kepala Tukang,Mandor,Pekerja[2]
114 Pekerjaan Balok WF 300.150 3 days Thu 11/4/21 Mon 11/8/21 113 Baja Profil[801.9 kg],Kepala Tukang,Mandor,Tukang[2],Pekerja[3]
Rp15,820,510 Baja Profil[801.9 kg],Kepala Tukang,Mandor,Tukang[2],Pekerja[3]
115 Pekerjaan Balok WF 250.125 3 days Mon 11/8/21 Thu 11/11/21 114 Tukang,Baja Gording[136.85 kg],Kepala Tukang,Mandor,Pekerja[2]
Rp3,002,615 Tukang,Baja Gording[136.85 kg],Kepala Tukang,Mandor,Pekerja[2]
116 Pekerjaan Sambungan A 1 day Fri 10/22/21 Sat 10/23/21 Rp7,388,797
117 - Baja WF 1 day Fri 10/22/21 Sat 10/23/21 110SS Tukang,Baja Profil[122.36 kg],Kepala Tukang,Mandor,Pekerja[2]
Rp2,492,244 Tukang,Baja Profil[122.36 kg],Kepala Tukang,Mandor,Pekerja[2]
118 - Plat 1 day Fri 10/22/21 Sat 10/23/21 110SS Tukang,Baja Profil[153.38 kg],Kepala Tukang,Mandor,Pekerja[2]
Rp3,047,502 Tukang,Baja Profil[153.38 kg],Kepala Tukang,Mandor,Pekerja[2]
119 - Baut 1 day Fri 10/22/21 Sat 10/23/21 110SS Mur Baut - Uk. 10 cm[640 buah],Kepala Tukang,Mandor,Pekerja[2],Tukang
Rp1,390,000 Mur Baut - Uk. 10 cm[640 buah],Kepala Tukang,Mandor,Pekerja[2],Tukang
120 - Las 1 day Fri 10/22/21 Sat 10/23/21 110SS Solar Industri[1.22 liter],Minyak Pelumas[0.16 liter],Kawat
Rp459,051 Las Elektroda - Dia. 2 mm; pjg. 300 mm[1.62 kg],Las Listrik - 900 watt[0.69 jam],Kepala Tukang,Pekerja[3],Mandor,Tukang Solar Industri[1.22 liter],Minyak Pelumas[0.16 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[1.62 kg],Las Listrik - 900 watt[0.69 jam],Kepala Tukang,Pekerja[3],Mandor,Tukang
121 Pekerjaan Sambungan B 9 days Sat 10/23/21 Wed 11/3/21 Rp6,071,609
122 - Plat 1 day Sat 10/23/21 Mon 10/25/21120 Baja Profil[10.74 kg],Mandor,Kepala Tukang,Tukang[2],Pekerja[4]
Rp612,246 Baja Profil[10.74 kg],Mandor,Kepala Tukang,Tukang[2],Pekerja[4]
123 - Baut 4 days Mon 10/25/21 Fri 10/29/21 122 Mur Baut - Uk. 10 cm[120 buah],Kepala Tukang,Mandor,Tukang,Pekerja
Rp2,604,000 Mur Baut - Uk. 10 cm[120 buah],Kepala Tukang,Mandor,Tukang,Pekerja
124 - Las 4 days Fri 10/29/21 Wed 11/3/21 123 Tukang,Solar Industri[3.52 liter],Minyak Pelumas[0.47
Rp2,855,363 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[4.7 kg],Las Listrik - 900 watt[2 jam],Kepala Tukang,Pekerja,Mandor Tukang,Solar Industri[3.52 liter],Minyak Pelumas[0.47 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[4.7 kg],Las Listrik - 900 watt[2 jam],Kepala Tukang,Pekerja,Mandor
125 Pekerjaan Sambungan C 4 days Sat 10/23/21 Thu 10/28/21 Rp9,733,451
126 - Baja WF 1 day Sat 10/23/21 Mon 10/25/21117 Baja Profil[51.89 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[6]
Rp2,778,831 Baja Profil[51.89 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[6]
127 - Plat 1 day Mon 10/25/21 Tue 10/26/21 126 Baja Profil[46.62 kg],Kepala Tukang,Mandor,Pekerja,Tukang[6]
Rp2,184,498 Baja Profil[46.62 kg],Kepala Tukang,Mandor,Pekerja,Tukang[6]
128 - Baut 1 day Tue 10/26/21 Wed 10/27/21127 Mur Baut - Uk. 10 cm[400 buah],Kepala Tukang,Mandor,Pekerja[6],Tukang[6]
Rp2,211,500 Mur Baut - Uk. 10 cm[400 buah],Kepala Tukang,Mandor,Pekerja[6],Tukang[6]
129 - Las 1 day Wed 10/27/21 Thu 10/28/21 128 Solar Industri[11.69 liter],Minyak Pelumas[1.56 Rp2,558,622
liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[15.58 kg],Las Listrik - 900 watt[6.62 jam],Kepala Tukang,Mandor,Tukang[2],Pekerja[4] Solar Industri[11.69 liter],Minyak Pelumas[1.56 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[15.58 kg],Las Listrik - 900 watt[6.62 jam],Kepala Tukang,Mandor,Tukang[2],Pekerja[4]
130 Pekerjaan Sambungan D 1 day Mon 11/1/21 Tue 11/2/21 Rp6,752,725
131 - Baja WF 1 day Mon 11/1/21 Tue 11/2/21 112SS Baja Profil[35.53 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
Rp1,311,987 Baja Profil[35.53 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
132 - Plat 1 day Mon 11/1/21 Tue 11/2/21 112SS Baja Profil[36 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang
Rp1,744,400 Baja Profil[36 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang
133 - Baut 1 day Mon 11/1/21 Tue 11/2/21 112SS Mur Baut - Uk. 10 cm[360 buah],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
Rp1,320,000 Mur Baut - Uk. 10 cm[360 buah],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
134 - Las 1 day Mon 11/1/21 Tue 11/2/21 112SS Solar Industri[10.27 liter],Minyak Pelumas[1.37 Rp2,376,338
liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[13.7 kg],Las Listrik - 900 watt[5.82 jam],Kepala Tukang,Mandor,Pekerja[4],Tukang[2] Solar Industri[10.27 liter],Minyak Pelumas[1.37 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[13.7 kg],Las Listrik - 900 watt[5.82 jam],Kepala Tukang,Mandor,Pekerja[4],Tukang[2]
135 Pekerjaan Sambungan E 1 day Mon 11/8/21 Tue 11/9/21 Rp2,899,086
136 - Plat 1 day Mon 11/8/21 Tue 11/9/21 115SS Baja Profil[0.76 kg],Kepala Tukang,Mandor,Pekerja[4],Tukang
Rp428,604 Baja Profil[0.76 kg],Kepala Tukang,Mandor,Pekerja[4],Tukang
137 - Baut 1 day Mon 11/8/21 Tue 11/9/21 115SS Mur Baut - Uk. 10 cm[60 buah],Kepala Tukang,Mandor,Tukang[6],Pekerja[8]
Rp1,042,500 Mur Baut - Uk. 10 cm[60 buah],Kepala Tukang,Mandor,Tukang[6],Pekerja[8]
138 - Las 1 day Mon 11/8/21 Tue 11/9/21 115SS Solar Industri[2.93 liter],Minyak Pelumas[0.39Rp1,427,982
liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[3.9 kg],Las Listrik - 900 watt[1.66 jam],Kepala Tukang,Tukang[2],Mandor,Pekerja[4] Solar Industri[2.93 liter],Minyak Pelumas[0.39 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[3.9 kg],Las Listrik - 900 watt[1.66 jam],Kepala Tukang,Tukang[2],Mandor,Pekerja[4]
139 Pekerjaan Sambungan F 1 day Thu 11/4/21 Fri 11/5/21 Rp3,415,563
140 - Plat 1 day Thu 11/4/21 Fri 11/5/21 114SS Baja Profil[14.39 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
Rp886,081 Baja Profil[14.39 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
141 - Baut 1 day Thu 11/4/21 Fri 11/5/21 114SS Mur Baut - Uk. 10 cm[190 buah],Kepala Tukang,Mandor,Pekerja[6],Tukang[5]
Rp1,101,500 Mur Baut - Uk. 10 cm[190 buah],Kepala Tukang,Mandor,Pekerja[6],Tukang[5]
142 - Las 1 day Thu 11/4/21 Fri 11/5/21 114SS Solar Industri[2.93 liter],Minyak Pelumas[0.39Rp1,427,982
liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[3.9 kg],Las Listrik - 900 watt[1.66 jam],Kepala Tukang,Mandor,Tukang[2],Pekerja[4] Solar Industri[2.93 liter],Minyak Pelumas[0.39 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[3.9 kg],Las Listrik - 900 watt[1.66 jam],Kepala Tukang,Mandor,Tukang[2],Pekerja[4]
143 Pekerjaan Sambungan 1A 6 days Fri 10/29/21 Fri 11/5/21 Rp7,358,216
144 - Baja WF 1 day Fri 10/29/21 Sat 10/30/21 111SS Baja Gording[54.68 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
Rp1,635,772 Baja Gording[54.68 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
145 - Plat 1 day Fri 10/29/21 Sat 10/30/21 111SS Baja Profil[27.72 kg],Kepala Tukang,Mandor,Tukang[6],Pekerja[6]
Rp2,346,188 Baja Profil[27.72 kg],Kepala Tukang,Mandor,Tukang[6],Pekerja[6]
146 - Baut 6 days Fri 10/29/21 Fri 11/5/21 111SS Tukang,Mur Baut - Uk. 10 cm[140 buah],Kepala Rp2,088,000
Tukang,Mandor,Pekerja[2] Tukang,Mur Baut - Uk. 10 cm[140 buah],Kepala Tukang,Mandor,Pekerja[2]
147 - Las 1 day Fri 10/29/21 Sat 10/30/21 111SS Solar Industri[8.26 liter],Minyak Pelumas[1.1 liter],Kawat
Rp1,288,256Las Elektroda - Dia. 2 mm; pjg. 300 mm[11.01 kg],Las Listrik - 900 watt[4.68 jam],Kepala Tukang,Mandor,Pekerja[2],Tukang Solar Industri[8.26 liter],Minyak Pelumas[1.1 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[11.01 kg],Las Listrik - 900 watt[4.68 jam],Kepala Tukang,Mandor,Pekerja[2],Tukang
148 Pekerjaan Sambungan 1B 1 day Mon 11/1/21 Tue 11/2/21 Rp2,434,525
149 - Baja WF 1 day Mon 11/1/21 Tue 11/2/21 112SS Baja Profil[27.23 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang
Rp656,417 Baja Profil[27.23 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang
150 - Plat 1 day Mon 11/1/21 Tue 11/2/21 112SS Baja Profil[27.72 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang
Rp665,188 Baja Profil[27.72 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang
151 - Baut 1 day Mon 11/1/21 Tue 11/2/21 112SS Mur Baut - Uk. 10 cm[140 buah],Kepala Tukang,Mandor,Pekerja[2],Tukang
Rp415,000 Mur Baut - Uk. 10 cm[140 buah],Kepala Tukang,Mandor,Pekerja[2],Tukang
152 - Las 1 day Mon 11/1/21 Tue 11/2/21 112SS Solar Industri[4.13 liter],Minyak Pelumas[0.55 liter],Kawat
Rp697,920 Las Elektroda - Dia. 2 mm; pjg. 300 mm[5.5 kg],Las Listrik - 900 watt[2.34 jam],Kepala Tukang,Pekerja[2],Mandor,Tukang Solar Industri[4.13 liter],Minyak Pelumas[0.55 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[5.5 kg],Las Listrik - 900 watt[2.34 jam],Kepala Tukang,Pekerja[2],Mandor,Tukang
153 PEKERJAAN PENULANGAN 3 days Tue 10/12/21 Fri 10/15/21 Rp73,809,008
154 Pekerjaan Penulangan Plat Lantai 3 days Tue 10/12/21 Fri 10/15/21 Rp73,809,008
155 - Penulangan plat lantai 6x6 1 day Tue 10/12/21 Wed 10/13/21159FS+2 days
Besi Beton - Polos/Ulir[3,228.44 kg],Kawat beton[46.12
Rp35,271,352 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang Besi Besi Beton - Polos/Ulir[3,228.44 kg],Kawat beton[46.12 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang Besi
156 - Penulangan plat lantai 6x5 1 day Wed 10/13/21 Thu 10/14/21 155 Besi Beton - Polos/Ulir[1,362.01 kg],Kawat beton[19.46
Rp14,968,511 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang Besi Besi Beton - Polos/Ulir[1,362.01 kg],Kawat beton[19.46 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang Besi
157 - Penulangan plat lantai 6x8 1 day Thu 10/14/21 Fri 10/15/21 156 Besi Beton - Polos/Ulir[2,152.34 kg],Kawat beton[30.75
Rp23,569,145 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang Besi Besi Beton - Polos/Ulir[2,152.34 kg],Kawat beton[30.75 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang Besi
158 PEKERJAAN BEKISTING 7 days Fri 10/1/21 Sat 10/9/21 Rp48,682,993
159 Pekerjaan Bekisting Plat Lantai 7 days Fri 10/1/21 Sat 10/9/21 38FS+6 days
Kayu Kelas III - Papan[3.16 m3],Paku Biasa -Rp48,682,993
Uk. 2 - 5 inch[31.58 kg],Minyak Bekisting[15.79 liter],Kayu Kelas II - Balok[1.18 m3],Plywood - Uk. 9 mm[27.63 lembar],Dolken Kayu - Dia. 8-10/400 cm[473.7 batang],Kepala Tukang,Mandor,Pekerja[2],Tukang Kayu Kayu Kelas III - Papan[3.16 m3],Paku Biasa - Uk. 2 - 5 inch[31.58 kg],Minyak Bekisting[15.79 liter],Kayu Kelas II - Balok[1.18 m3],Plywood - Uk. 9 mm[27.63 lembar],Dolken Kayu - Dia. 8-10/400 cm[473.7 batang],Kepala Tukang,Mandor,Pekerja[2],Tukang Kayu
160 PEKERJAAN BETON 3 days Fri 10/15/21 Tue 10/19/21 Rp108,037,585
161 Pekerjaan Beton Plat Lantai 3 days Fri 10/15/21 Tue 10/19/21 157 Semen Portland - 50 kg[61,950 kg],Pasir Beton[72.9
Rp108,037,585
m3],Kerikil - Max. 30 mm[85.05 m3],Air[32,250 liter],Kepala Tukang,Mandor,Tukang Batu,Pekerja[2] Semen Portland - 50 kg[61,950 kg],Pasir Beton[72.9 m3],Kerikil - Max. 30 mm[85.05 m3],Air[32,250 liter],Kepala Tukang,Mandor,Tukang Batu,Pekerja[2]
162 PEKERJAAN DINDING 13 days Wed 10/27/21 Thu 11/11/21 Rp86,065,632
163 Pas. Batu Bata Merah 1Pc : 6Psr 7 days Wed 10/27/21 Thu 11/4/21 161FS+6 days
Semen Portland - 50 kg[8,518.4 kg],Batu BataRp66,810,480
Merah[61,600 buah],Pasir Pasang[39.6 m3],Kepala Tukang,Mandor,Pekerja[2],Tukang Batu Semen Portland - 50 kg[8,518.4 kg],Batu Bata Merah[61,600 buah],Pasir Pasang[39.6 m3],Kepala Tukang,Mandor,Pekerja[2],Tukang Batu
164 Plesteran Halus 1 Pc : 4Psr 2 days Tue 11/9/21 Thu 11/11/21 163FS+4 days
Semen Portland - 50 kg[10,982.4 kg],Pasir Pasang/Plester[42.24
Rp19,255,152 m3],Kepala Tukang,Mandor,Pekerja[2],Tukang Batu Semen Portland - 50 kg[10,982.4 kg],Pasir Pasang/Plester[42.24 m3],Kepala Tukang,Mandor,Pekerja[2],Tukang Batu
165 PEKERJAAN LANTAI 2 8 days Thu 11/18/21 Sat 11/27/21 Rp3,304,832
166 Plester 6 days Thu 11/18/21 Sat 11/27/21 177 Semen Portland - 50 kg[998.4 kg],Pasir Pasang[3.84
Rp3,304,832
m3],Kepala Tukang,Mandor,Tukang Batu,Pekerja[2] Semen Portland - 50 kg[998.4 kg],Pasir Pasang[3.84 m3],Kepala Tukang,Mandor,Tukang Batu,Pekerja[2]
167 PEKERJAAN INSTALASI LISTRIK 5 days Thu 11/18/21 Wed 11/24/21 Rp8,648,000
168 Titik Lampu 2 days Mon 11/22/21 Wed 11/24/21178 Kabel NYA - 1 x 2.5 mm[600 m'],Pipa PVC - Type Rp5,511,000
C Dia. 5/8 inch. pjg. 400 cm[160 m'],Fitting Lampu Plafon[40 kg],T Dos PVC[40 buah],Kepala Tukang,Tukang Listrik,Pekerja[2] Kabel NYA - 1 x 2.5 mm[600 m'],Pipa PVC - Type C Dia. 5/8 inch. pjg. 400 cm[160 m'],Fitting Lampu Plafon[40 kg],T Dos PVC[40 buah],Kepala Tukang,Tukang Listrik,Pekerja[2]
169 Lampu Down light 1 day Thu 11/18/21 Fri 11/19/21 177 Lampu Down Light LED 18 watt[30 buah],Tukang Rp3,137,000
Listrik,Kepala Tukang,Pekerja[2] Lampu Down Light LED 18 watt[30 buah],Tukang Listrik,Kepala Tukang,Pekerja[2]
170 PEKERJAAN PENGECATAN 2 days Thu 11/18/21 Sat 11/20/21 Rp53,532,544
171 Pengecatan Dinding Interior (Spoot-Less) 2 days Thu 11/18/21 Sat 11/20/21 177 Cat Tembok Interior - Primer[35.2 kaleng],CatRp32,505,264
Tembok Interior - Finishing[91.52 kaleng],Plamir Tembok[88 kg],Thinner[88 liter],Amplas - No.240[880 lembar],Pisau Pallet[13.2 buah],Kuas Cat[13.2 buah],Kepala Tukang,Mandor,Tukang Cat,Pekerja[2] Cat Tembok Interior - Primer[35.2 kaleng],Cat Tembok Interior - Finishing[91.52 kaleng],Plamir Tembok[88 kg],Thinner[88 liter],Amplas - No.240[880 lembar],Pisau Pallet[13.2 buah],Kuas Cat[13.2 buah],Kepala Tukang,Mandor,Tukang Cat,Pekerja[2]
172 Pengecatan Dinding Eksterior (Weatherbond) 2 days Thu 11/18/21 Sat 11/20/21 177 Cat Tembok Exterior - Primer - Weather Shield[21.12
Rp21,027,280kaleng],Cat Tembok Exterior - Finishing - Weather Shield[31.68 kaleng],Plamir Tembok[88 kg],Thinner[88 liter],Amplas - No.240[880 lembar],Pisau Pallet[13.2 buah],Kuas Cat[13.2 buah],Kepala Tukang,Tuka... Cat Tembok Exterior - Primer - Weather Shield[21.12 kaleng],Cat Tembok Exterior - Finishing - Weather Shield[31.68 kaleng],Plamir Tembok[88 kg],Thinner[88 liter],Amplas - No.240[880 lembar],Pisau Pallet[13.2 buah],Kuas Cat[13.2 buah],Kepala Tukang,T
173 PEKERJAAN ATAP 9 days Thu 11/11/21 Mon 11/22/21 Rp121,740,294
174 Pemasangan Kuda-kuda Rangka Baja WF 350.175 2 days Thu 11/11/21 Sat 11/13/21 115 Mandor,Kepala Tukang,Tukang,Pekerja[2],Besi Rp22,476,893
Profil WF 350.175[1,221.67 kg] Mandor,Kepala Tukang,Tukang,Pekerja[2],Besi Profil WF 350.175[1,221.67 kg]
175 Pemasangan Gording C 150.65.20.2,3 1 day Sat 11/13/21 Mon 11/15/21174 Baja Gording[193.6 kg],Kepala Tukang,Pekerja[2],Tukang
Rp3,723,940 Baja Gording[193.6 kg],Kepala Tukang,Pekerja[2],Tukang
176 Pemasangan Papan Reuter 3/30 1 day Mon 11/15/21 Tue 11/16/21 175 Paku Biasa - Uk. 2 - 5 inch[1.75 kg],Kayu Kelas Rp1,815,825
III - Papan Uk. 3/20[0.25 m3],Kepala Tukang,Mandor,Pekerja[2],Tukang Paku Biasa - Uk. 2 - 5 inch[1.75 kg],Kayu Kelas III - Papan Uk. 3/20[0.25 m3],Kepala Tukang,Mandor,Pekerja[2],Tukang
177 Pemasangan Bubungan Atap Keramik Mclass 2 days Tue 11/16/21 Thu 11/18/21 176 Semen Portland - 50 kg[5.12 kg],Pasir Pasang[1.02Rp4,593,516
m3],Bubungan Keramik Mclass[160 buah],Kepala Tukang,Mandor,Pekerja[2],Tukang Semen Portland - 50 kg[5.12 kg],Pasir Pasang[1.02 m3],Bubungan Keramik Mclass[160 buah],Kepala Tukang,Mandor,Pekerja[2],Tukang
178 Pemasangan Atap Genteng Keramik Mclass 3 days Thu 11/18/21 Mon 11/22/21177 Genteng Keramik Mclass[9,032.32 buah],Kepala Rp89,130,120
Tukang,Mandor,Pekerja[2],Tukang Genteng Keramik Mclass[9,032.32 buah],Kepala Tukang,Mandor,Pekerja[2],Tukang

Project: Laporan MS PROJECT Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress
Date: Fri 7/30/21

Page 1
February 2022 March 2022 April 2022 May 2022 June 2022 July 2022 August 2022 September 2022 October 2022 November 2022
20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2

ang,Tukang Cat[2],Pekerja[5],Cat Tembok Exterior - Finishing - Weather Shield[24.33 kaleng]

],Kuas Cat[13.2 buah],Kepala Tukang,Mandor,Tukang Cat,Pekerja[2]


0[880 lembar],Pisau Pallet[13.2 buah],Kuas Cat[13.2 buah],Kepala Tukang,Tuka...

Project: Laporan MS PROJECT Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress
Date: Fri 7/30/21