Professional Documents
Culture Documents
4.1 Grafik Gantchart - Rev
4.1 Grafik Gantchart - Rev
Finish PredecessorsResource Names Cost July 2021 August 2021 September 2021 October 2021 November 2021 December 2021 January 2022
Mode 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 4 6 8 10 12 14 16 18 20
1 PEMBANGUNAN GEDUNG OLAHRAGA 144 days Sat 6/12/21 Wed 12/1/21 Rp1,940,687,918
2 PEKERJAAN LANTAI 1 144 days Sat 6/12/21 Wed 12/1/21 Rp1,150,665,487
3 PEKERJAAAN PERSIAPAN 22 days Sat 6/12/21 Wed 7/7/21 Rp183,595,457
4 Pembersihan Lokasi 8 days Sat 6/12/21 Mon 6/21/21 Pekerja[2],Mandor Rp2,200,000 Pekerja[2],Mandor
5 Pemasangan Bowplank dan Pengukuran 18 days Sat 6/12/21 Fri 7/2/21 Kayu Kelas III - Balok Usuk (Meranti) Uk. 5 xRp31,742,957
7 cm; 400 cm[2.62 m3],Mandor,Kepala Tukang,Tukang Kayu,Pekerja[2],Paku Biasa - Uk. 2 - 5 inch[4.36 Kayukg],Kayu
Kelas III Kelas
- BalokIIIUsuk
- Papan Uk. 3/20[1.53
(Meranti) Uk. 5 x 7 m3]
cm; 400 cm[2.62 m3],Mandor,Kepala Tukang,Tukang Kayu,Pekerja[2],Paku Biasa - Uk. 2 - 5 inch[4.36 kg],Kayu Kelas III - Papan Uk. 3/20[1.53 m3]
6 Direksi Keet dan Gudang 4 days Sat 7/3/21 Wed 7/7/21 5 Mandor,Kepala Tukang,Tukang Batu,Pekerja[2],Kayu
Rp149,652,500 Kelas III - Balok Usuk (Meranti) Uk. 5 x 7 cm; 400 cm[21 m3],Triplek - Uk. 122 x 244 cm; tbl. 4 mm[60 lembar],Skrup Asbes -Tukang,Tukang
Mandor,Kepala Uk. 4 inch.[45 Batu,Pekerja[2],Kayu
kg],Plafon Asbes Eternit
Kelas- Tbl.
III -4Balok
mm; Usuk
5 mm;(Meranti)
6 mm[74.4 Uk.lembar],As...
5 x 7 cm; 400 cm[21 m3],Triplek - Uk. 122 x 244 cm; tbl. 4 mm[60 lembar],Skrup Asbes - Uk. 4 inch.[45 kg],Plafon Asbes Eternit - Tbl. 4 mm; 5 mm; 6 mm[74.4 lembar],As...
7 PEKERJAAN TANAH 14 days Sat 7/3/21 Mon 7/19/21 Rp11,206,415
8 Galian Tanah Pondasi Strauss Pile 8 days Sat 7/3/21 Mon 7/12/21 5 Mandor,Pekerja[2] Rp1,760,000 Mandor,Pekerja[2]
9 Galian Tanah Pondasi Pile Cap 1 day Tue 7/13/21 Tue 7/13/21 8 Mandor,Pekerja[2] Rp320,000 Mandor,Pekerja[2]
10 Urugan Pasir Bawah Pondasi Pile Cap 1 day Wed 7/14/21 Wed 7/14/21 9 Mandor,Pekerja[2],Pasir Urug[1.98 m3] Rp607,290 Mandor,Pekerja[2],Pasir Urug[1.98 m3]
11 Urugan Tanah Kembali Untuk Pondasi Pile Cap 1 day Thu 7/15/21 Thu 7/15/21 10 Mandor,Pekerja[2] Rp240,000 Mandor,Pekerja[2]
12 Urugan Pasir Bawah Lantai 3 days Fri 7/16/21 Mon 7/19/21 11 Mandor,Pekerja[2],Pasir Urug[40.75 m3] Rp8,279,125 Mandor,Pekerja[2],Pasir Urug[40.75 m3]
13 PEKERJAAN PENULANGAN 57 days Wed 7/21/21 Mon 9/27/21 Rp39,022,537
14 Pekerjaan Penulangan Strauss Pile & Pile Cap P1 4 days Thu 7/22/21 Mon 8/30/21 19 Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Rp4,449,453
Beton - Polos/Ulir[288.92 kg],Kawat beton[4.13 kg] Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[288.92 kg],Kawat beton[4.13 kg]
15 Pekerjaan Penulangan Strauss Pile & Pile Cap P2 7 days Mon 8/30/21 Tue 9/7/21 14 Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Rp5,529,116
Beton - Polos/Ulir[273.53 kg],Kawat beton[3.91 kg] Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[273.53 kg],Kawat beton[3.91 kg]
16 Pekerjaan Penulangan Strauss Pile & Pile Cap P3 3 days Tue 9/7/21 Fri 9/10/21 15 Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Rp3,682,146
Beton - Polos/Ulir[260.03 kg],Kawat beton[3.71 kg] Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[260.03 kg],Kawat beton[3.71 kg]
17 Pekerjaan Penulangan Strauss Pile & Pile Cap P4 1 day Fri 9/10/21 Sat 9/11/21 16 Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Rp3,591,159
Beton - Polos/Ulir[279.24 kg],Kawat beton[3.99 kg] Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[279.24 kg],Kawat beton[3.99 kg]
18 Pekerjaan Penulangan Sloof 5 days Mon 8/30/21 Sat 9/4/21 14 Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,BesiRp10,067,120
Beton - Polos/Ulir[728.16 kg],Kawat beton[10.4 kg] Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[728.16 kg],Kawat beton[10.4 kg]
19 Pekerjaan Penulangan Lantai Kerja 1 day Wed 7/21/21 Wed 7/21/21 12 Mandor,Pekerja,Kepala Tukang,Tukang Besi,Besi Rp391,962
Beton - Polos/Ulir[8.46 kg],Kawat beton[0.12 kg] Mandor,Pekerja,Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[8.46 kg],Kawat beton[0.12 kg]
20 Pekerjaan Penulangan Kolom K1 45/45 7 days Sat 9/4/21 Mon 9/13/21 18 Mandor,Pekerja,Kepala Tukang,Tukang Besi,Besi Rp3,267,285
Beton - Polos/Ulir[97.69 kg],Kawat beton[1.4 kg] Mandor,Pekerja,Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[97.69 kg],Kawat beton[1.4 kg]
21 Pekerjaan Penulangan Kolom Pedestal 45/45 6 days Mon 9/13/21 Mon 9/27/21 20 Mandor,Pekerja,Kepala Tukang,Tukang Besi,Besi Rp8,044,296
Beton - Polos/Ulir[546.71 kg],Kawat beton[7.81 kg] Mandor,Pekerja,Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[546.71 kg],Kawat beton[7.81 kg]
22 PEKERJAAN BEKISTING 28 days Mon 9/6/21 Fri 10/8/21 Rp348,991,626
23 Pekerjaan Bekisting Pile Cap P1 1 day Mon 9/6/21 Tue 9/7/21 Mandor,Kepala Tukang,Tukang Kayu,Pekerja,Paku
14FS+6 days Rp3,215,001
Biasa - Uk. 2 - 5 inch[3.46 kg],Minyak Bekisting[1.15 liter],Kayu Kelas III - Papan[0.46 m3] Mandor,Kepala Tukang,Tukang Kayu,Pekerja,Paku Biasa - Uk. 2 - 5 inch[3.46 kg],Minyak Bekisting[1.15 liter],Kayu Kelas III - Papan[0.46 m3]
24 Pekerjaan Bekisting Pile Cap P2 1 day Tue 9/7/21 Wed 9/8/21 23 Mandor,Kepala Tukang,Tukang Kayu[2],Pekerja[2],Paku
Rp6,398,256 Biasa - Uk. 2 - 5 inch[6.19 kg],Minyak Bekisting[2.3 liter],Kayu Kelas III - Papan[0.92 m3] Mandor,Kepala Tukang,Tukang Kayu[2],Pekerja[2],Paku Biasa - Uk. 2 - 5 inch[6.19 kg],Minyak Bekisting[2.3 liter],Kayu Kelas III - Papan[0.92 m3]
25 Pekerjaan Bekisting Pile Cap P3 3 days Wed 9/8/21 Sat 9/11/21 24 Mandor,Kepala Tukang,Tukang Kayu[4],Pekerja[5],Paku
Rp21,734,558 Biasa - Uk. 2 - 5 inch[21.12 kg],Minyak Bekisting[7.04 liter],Kayu Kelas III - Papan[2.82 m3] Mandor,Kepala Tukang,Tukang Kayu[4],Pekerja[5],Paku Biasa - Uk. 2 - 5 inch[21.12 kg],Minyak Bekisting[7.04 liter],Kayu Kelas III - Papan[2.82 m3]
26 Pekerjaan Bekisting Pile Cap P4 1 day Sat 9/11/21 Mon 9/13/21 25 Mandor,Kepala Tukang,Tukang Kayu,Pekerja,Paku Rp2,622,032
Biasa - Uk. 2 - 5 inch[2.69 kg],Minyak Bekisting[0.9 liter],Kayu Kelas III - Papan[0.36 m3] Mandor,Kepala Tukang,Tukang Kayu,Pekerja,Paku Biasa - Uk. 2 - 5 inch[2.69 kg],Minyak Bekisting[0.9 liter],Kayu Kelas III - Papan[0.36 m3]
27 Pekerjaan Bekisting Kolom K1 45/45 & Pedestal 45/45 20 days Wed 9/15/21 Fri 10/8/21 28SS+2 Mandor,Kepala Rp192,078,490 Mandor,Kepala Tukang,Tukang Kayu,Pekerja[2],Paku Biasa - Uk. 2 - 5 inch[153.22 kg],Minyak Bekisting[76.61 liter],Kayu Kelas III - Papan[15.32 m3],Kayu Kelas II - Balok[5.75 m3],Plywood - Uk. 9 mm[134.06 lembar],Dolken Kayu - Dia. 8-10/400 cm[766.08 bat...
days Tukang,Tukang
28 Pekerjaan Bekisting Sloof 20 days Mon 9/13/21 Wed 10/6/21 26 Kayu,Pekerja[2],Paku
Mandor,Kepala Biasa -
Tukang[2],Tukang Kayu,Pekerja[2],Paku
Rp122,943,289 Biasa - Uk. 2 - 5 inch[122.04 kg],Minyak Bekisting[40.68 liter],Kayu Kelas III - Papan[18.31 m3] Mandor,Kepala Tukang[2],Tukang Kayu,Pekerja[2],Paku Biasa - Uk. 2 - 5 inch[122.04 kg],Minyak Bekisting[40.68 liter],Kayu Kelas III - Papan[18.31 m3]
29 PEKERJAAN BETON 36 days Mon 8/30/21 Mon 10/11/21 Rp254,036,878
30 Pekerjaan Strauss Pile P1 6 days Mon 8/30/21 Mon 9/6/21 14 Mandor,Kepala Tukang[2],Tukang Batu,Pekerja[2],Semen
Rp7,014,033Portland - 50 kg[2,756.74 kg],Pasir Beton[3.32 m3],Air[1,459.85 liter],Kerikil - Max. 30 mm[3.87 m3] Mandor,Kepala Tukang[2],Tukang Batu,Pekerja[2],Semen Portland - 50 kg[2,756.74 kg],Pasir Beton[3.32 m3],Air[1,459.85 liter],Kerikil - Max. 30 mm[3.87 m3]
31 Pekerjaan Strauss Pile P2 1 day Tue 9/7/21 Wed 9/8/21 15 Mandor,Kepala Tukang[2],Tukang Batu[6],Pekerja[8],Semen
Rp15,566,813 Portland - 50 kg[7,653.1 kg],Pasir Beton[9.22 m3],Air[4,052.75 liter],Kerikil - Max. 30 mm[10.75 m3] Mandor,Kepala Tukang[2],Tukang Batu[6],Pekerja[8],Semen Portland - 50 kg[7,653.1 kg],Pasir Beton[9.22 m3],Air[4,052.75 liter],Kerikil - Max. 30 mm[10.75 m3]
32 Pekerjaan Strauss Pile P3 1 day Fri 9/10/21 Sat 9/11/21 16 Mandor,Kepala Tukang[4],Tukang Batu[6],Pekerja[8],Semen
Rp56,840,617 Portland - 50 kg[31,115.84 kg],Pasir Beton[37.48 m3],Air[16,477.6 liter],Kerikil - Max. 30 mm[43.69 m3] Mandor,Kepala Tukang[4],Tukang Batu[6],Pekerja[8],Semen Portland - 50 kg[31,115.84 kg],Pasir Beton[37.48 m3],Air[16,477.6 liter],Kerikil - Max. 30 mm[43.69 m3]
33 Pekerjaan Strauss Pile P4 1 day Sat 9/11/21 Mon 9/13/21 17,30SS Mandor,Kepala Tukang,Tukang Batu[2],Pekerja[8],Semen
Rp5,703,125Portland - 50 kg[2,448.18 kg],Pasir Beton[2.95 m3],Air[1,296.45 liter],Kerikil - Max. 30 mm[3.35 m3] Mandor,Kepala Tukang,Tukang Batu[2],Pekerja[8],Semen Portland - 50 kg[2,448.18 kg],Pasir Beton[2.95 m3],Air[1,296.45 liter],Kerikil - Max. 30 mm[3.35 m3]
34 Pekerjaan Pondasi Pile Cap P1 1 day Tue 9/7/21 Wed 9/8/21 23,30 Mandor,Kepala Tukang,Tukang Batu,Pekerja,Semen Rp1,619,810
Portland - 50 kg[584.64 kg],Pasir Beton[0.7 m3],Air[309.6 liter],Kerikil - Max. 30 mm[0.82 m3] Mandor,Kepala Tukang,Tukang Batu,Pekerja,Semen Portland - 50 kg[584.64 kg],Pasir Beton[0.7 m3],Air[309.6 liter],Kerikil - Max. 30 mm[0.82 m3]
35 Pekerjaan Pondasi Pile Cap P2 1 day Wed 9/8/21 Thu 9/9/21 24,34 Mandor,Kepala Tukang,Tukang Batu,Pekerja[5],SemenRp4,134,158 Portland - 50 kg[1,843.24 kg],Pasir Beton[2.22 m3],Air[976.1 liter],Kerikil - Max. 30 mm[2.26 m3] Mandor,Kepala Tukang,Tukang Batu,Pekerja[5],Semen Portland - 50 kg[1,843.24 kg],Pasir Beton[2.22 m3],Air[976.1 liter],Kerikil - Max. 30 mm[2.26 m3]
36 Pekerjaan Pondasi Pile Cap P3 1 day Sat 9/11/21 Mon 9/13/21 25,35 Rp12,969,142 Portland - 50 kg[6,252.4 kg],Pasir Beton[7.53 m3],Air[3,311 liter],Kerikil - Max. 30 mm[8.78 m3]
Mandor,Kepala Tukang[2],Tukang Batu[6],Pekerja[8],Semen Mandor,Kepala Tukang[2],Tukang Batu[6],Pekerja[8],Semen Portland - 50 kg[6,252.4 kg],Pasir Beton[7.53 m3],Air[3,311 liter],Kerikil - Max. 30 mm[8.78 m3]
37 Pekerjaan Pondasi Pile Cap P4 1 day Mon 9/13/21 Tue 9/14/21 26,36 Mandor,Kepala Tukang,Tukang Batu,Pekerja,Semen Rp1,691,740
Portland - 50 kg[625.24 kg],Pasir Beton[0.75 m3],Air[331.1 liter],Kerikil - Max. 30 mm[0.88 m3] Mandor,Kepala Tukang,Tukang Batu,Pekerja,Semen Portland - 50 kg[625.24 kg],Pasir Beton[0.75 m3],Air[331.1 liter],Kerikil - Max. 30 mm[0.88 m3]
38 Pekerjaan Kolom K1 45/45 & Pedestal 45/45 3 days Tue 9/21/21 Fri 9/24/21 37FS+6 days Rp89,650,698 Portland - 50 kg[71,494.54 kg],Pasir Beton[21.07 m3],Air[9,264.35 liter],Kerikil - Max. 30 mm[24.56 m3]
Mandor,Kepala Tukang[2],Tukang Batu[4],Pekerja[6],Semen Mandor,Kepala Tukang[2],Tukang Batu[4],Pekerja[6],Semen Portland - 50 kg[71,494.54 kg],Pasir Beton[21.07 m3],Air[9,264.35 liter],Kerikil - Max. 30 mm[24.56 m3]
39 Pekerjaan Sloof Beton Bertulang 8 days Fri 10/1/21 Mon 10/11/2138FS+6 days
Mandor,Kepala Tukang,Tukang Batu,Pekerja[2],Semen
Rp58,846,742 Portland - 50 kg[32,236.4 kg],Pasir Beton[38.83 m3],Air[17,071 liter],Kerikil - Max. 30 mm[45.26 m3] Mandor,Kepala Tukang,Tukang Batu,Pekerja[2],Semen Portland - 50 kg[32,236.4 kg],Pasir Beton[38.83 m3],Air[17,071 liter],Kerikil - Max. 30 mm[45.26 m3]
40 PEKERJAAN TANGGA 11 days Wed 7/14/21 Tue 7/27/21 Rp36,737,793
41 Pekerjaan Tangga Utama 11 days Wed 7/14/21 Tue 7/27/21 Rp36,737,793
42 a. Pekerjaan Pondasi Tangga 5 days Wed 7/14/21 Mon 7/19/21 Rp12,058,170
43 - Urugan pasir bawah pondasi 1 day Wed 7/14/21 Wed 7/14/21 10SS Mandor,Pekerja,Pasir Urug[0.22 m3] Rp340,810 Mandor,Pekerja,Pasir Urug[0.22 m3]
44 - Lantai kerja 1 day Thu 7/15/21 Thu 7/15/21 43 Mandor,Pekerja,Kepala Tukang,Tukang Batu Rp600,000 Mandor,Pekerja,Kepala Tukang,Tukang Batu
45 - Urugan tanah kembali 1 day Thu 7/15/21 Thu 7/15/21 44SS Mandor,Pekerja Rp300,000 Mandor,Pekerja
46 - Bekisting 1 day Sat 7/17/21 Sat 7/17/21 47 Mandor,Pekerja,Kepala Tukang,Tukang Batu,Kayu Rp1,984,118
Kelas III - Papan[0.12 m3],Paku Biasa - Uk. 2 - 5 inch[1.59 kg],Minyak Bekisting[0.6 liter],Kayu Kelas II - Balok[0.06 m3],Plywood - Uk. 9 mm[1.39Mandor,Pekerja,Kepala
lembar],Dolken Kayu -Tukang,Tukang
Dia. 8-10/400 cm[7.96
Batu,Kayubatang]
Kelas III - Papan[0.12 m3],Paku Biasa - Uk. 2 - 5 inch[1.59 kg],Minyak Bekisting[0.6 liter],Kayu Kelas II - Balok[0.06 m3],Plywood - Uk. 9 mm[1.39 lembar],Dolken Kayu - Dia. 8-10/400 cm[7.96 batang]
47 - Penulangan 1 day Fri 7/16/21 Fri 7/16/21 45 Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Rp7,808,594
Beton - Polos/Ulir[688.74 kg],Kawat beton[9.84 kg] Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[688.74 kg],Kawat beton[9.84 kg]
48 - Pekerjaan Beton 1 day Mon 7/19/21 Mon 7/19/21 46 Mandor,Kepala Tukang,Tukang Batu,Pekerja,Semen Rp1,024,648
Portland - 50 kg[244.09 kg],Pasir Beton[0.29 m3],Air[129.26 liter],Kerikil - Max. 30 mm[0.34 m3] Mandor,Kepala Tukang,Tukang Batu,Pekerja,Semen Portland - 50 kg[244.09 kg],Pasir Beton[0.29 m3],Air[129.26 liter],Kerikil - Max. 30 mm[0.34 m3]
49 b. Pekerjaan Tangga 1 6 days Wed 7/21/21 Tue 7/27/21 Rp24,679,623
50 - Penulangan 1 day Wed 7/21/21 Wed 7/21/21 48 Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Rp7,178,529
Beton - Polos/Ulir[605.05 kg],Kawat beton[8.64 kg] Mandor,Pekerja[2],Kepala Tukang,Tukang Besi,Besi Beton - Polos/Ulir[605.05 kg],Kawat beton[8.64 kg]
51 - Bekisting 3 days Thu 7/22/21 Sat 7/24/21 50 Mandor,Pekerja[5],Kepala Tukang,Kayu Kelas Rp14,053,290
III - Papan[0.75 m3],Paku Biasa - Uk. 2 - 5 inch[10.06 kg],Minyak Bekisting[3.77 liter],Kayu Kelas II - Balok[0.38 m3],Plywood - Uk. 9 mm[8.81 lembar],Dolken Kayu - Dia. 8-10/400 cm[50.36 batang],Tukang
Mandor,Pekerja[5],Kepala Kayu[2]Kelas III - Papan[0.75 m3],Paku Biasa - Uk. 2 - 5 inch[10.06 kg],Minyak Bekisting[3.77 liter],Kayu Kelas II - Balok[0.38 m3],Plywood - Uk. 9 mm[8.81 lembar],Dolken Kayu - Dia. 8-10/400 cm[50.36 batang],Tukang Kayu[2]
Tukang,Kayu
52 - Pekerjaan Beton 2 days Mon 7/26/21 Tue 7/27/21 51 Mandor,Kepala Tukang,Pekerja[2],Semen Portland Rp3,447,804
- 50 kg[244.09 kg],Pasir Beton[0.29 m3],Air[8,245.04 liter],Kerikil - Max. 30 mm[0.34 m3],Tukang Besi Mandor,Kepala Tukang,Pekerja[2],Semen Portland - 50 kg[244.09 kg],Pasir Beton[0.29 m3],Air[8,245.04 liter],Kerikil - Max. 30 mm[0.34 m3],Tukang Besi
53 PEKERJAAN DINDING 17 days Mon 10/18/21 Mon 11/8/21 Rp175,484,598
54 Pas. Batu Bata Merah 1Pc : 6Psr 3 days Mon 10/18/21 Fri 10/22/21 39FS+6 days
Semen Portland - 50 kg[2,450.64 kg],Batu Bata Rp20,085,802
Merah[17,721.55 buah],Pasir Pasang[11.39 m3],Mandor[0.2],Kepala Tukang[0.2],Tukang Batu[2],Pekerja Semen Portland - 50 kg[2,450.64 kg],Batu Bata Merah[17,721.55 buah],Pasir Pasang[11.39 m3],Mandor[0.2],Kepala Tukang[0.2],Tukang Batu[2],Pekerja
55 Pas. Batu Bata Trasram 1 Pc : 4Psr 3 days Mon 10/18/21 Fri 10/22/21 39FS+6 days
Semen Portland - 50 kg[8,566.09 kg],Batu Bata Rp50,997,568
Merah[45,169.6 buah],Pasir Pasang[30.01 m3],Kepala Tukang[0.2],Mandor[0.1],Tukang Batu,Pekerja Semen Portland - 50 kg[8,566.09 kg],Batu Bata Merah[45,169.6 buah],Pasir Pasang[30.01 m3],Kepala Tukang[0.2],Mandor[0.1],Tukang Batu,Pekerja
56 Benangan 2 days Fri 10/22/21 Mon 10/25/2155 Semen Portland - 50 kg[54,119.52 kg],Pasir Pasang[189.57
Rp89,244,206m3],Mandor[0.1],Tukang Batu[2],Pekerja[2] Semen Portland - 50 kg[54,119.52 kg],Pasir Pasang[189.57 m3],Mandor[0.1],Tukang Batu[2],Pekerja[2]
57 Plesteran Halus 1 Pc : 4Psr 1 day Fri 10/29/21 Sat 10/30/21 54FS+6 days
Semen Portland - 50 kg[7,185.55 kg],Pasir Pasang[27.64
Rp12,455,222 m3],Mandor[0.1],Kepala Tukang[0.2],Tukang Batu,Pekerja Semen Portland - 50 kg[7,185.55 kg],Pasir Pasang[27.64 m3],Mandor[0.1],Kepala Tukang[0.2],Tukang Batu,Pekerja
58 Acian 1 day Sat 11/6/21 Mon 11/8/21 57FS+6 days
Semen Portland - 50 kg[2,131.8 kg],Mandor[0.2],Kepala
Rp2,701,800 Tukang[0.2],Tukang Batu[2],Pekerja[2] Semen Portland - 50 kg[2,131.8 kg],Mandor[0.2],Kepala Tukang[0.2],Tukang Batu[2],Pekerja[2]
59 PEKERJAAN KUSEN 8 days Tue 10/19/21 Fri 10/29/21 Rp22,572,373
60 Pas. Kusen Pintu Type P1 2 days Tue 10/19/21 Fri 10/22/21 Rp3,935,203
61 - Kusen 2 days Tue 10/19/21 Fri 10/22/21 54SS+25%Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kusen Rp2,363,003 Alumunium Profil - Uk. 4 inch.[10 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.15 kg],Lem Plastic Steel Epoxy - 48 gr[0.03 kg] Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kusen Alumunium Profil - Uk. 4 inch.[10 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.15 kg],Lem Plastic Steel Epoxy - 48 gr[0.03 kg]
62 - Handle Pintu 1 day Tue 10/19/21 Thu 10/21/21 61SS Kepala Tukang,Tukang Besi[2],Handle Pintu[2 buah] Rp380,000 Kepala Tukang,Tukang Besi[2],Handle Pintu[2 buah]
63 - Engsel Pintu 1 day Tue 10/19/21 Thu 10/21/21 61SS Kepala Tukang,Tukang Besi,Engsel Kupu-KupuRp401,400 - Besi/Alumunium 2 inch[6 buah] Kepala Tukang,Tukang Besi,Engsel Kupu-Kupu - Besi/Alumunium 2 inch[6 buah]
64 - Grendel Besar 1 day Tue 10/19/21 Thu 10/21/21 61SS Kepala Tukang,Tukang Besi,Grendel - Brass/StainlessRp356,000Steel Uk. 6 inch.[4 buah] Kepala Tukang,Tukang Besi,Grendel - Brass/Stainless Steel Uk. 6 inch.[4 buah]
65 - Kunci Tanam 1 day Tue 10/19/21 Thu 10/21/21 61SS Kepala Tukang,Tukang Besi,Kunci Silinder - Brass/Alumunium
Rp434,800 Uk. 60 mm[2 buah] Kepala Tukang,Tukang Besi,Kunci Silinder - Brass/Alumunium Uk. 60 mm[2 buah]
66 Pas. Kusen Pintu Type P2 8 days Tue 10/19/21 Fri 10/29/21 Rp4,825,931
67 - Kusen 4 days Tue 10/19/21 Mon 10/25/2154SS+25%Mandor,Kepala Tukang,Pekerja[2],Kusen Alumunium Rp2,353,731Profil - Uk. 4 inch.[7 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.11 kg],Lem Plastic Steel Epoxy - 48 gr[0.02 kg],Tukang Kayu Mandor,Kepala Tukang,Pekerja[2],Kusen Alumunium Profil - Uk. 4 inch.[7 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.11 kg],Lem Plastic Steel Epoxy - 48 gr[0.02 kg],Tukang Kayu
68 - Handle Pintu 4 days Mon 10/25/21 Fri 10/29/21 67 Kepala Tukang,Tukang Besi,Handle Pintu[2 buah] Rp1,400,000 Kepala Tukang,Tukang Besi,Handle Pintu[2 buah]
69 - Engsel Pintu 1 day Mon 10/25/21 Tue 10/26/21 67 Kepala Tukang,Tukang Besi,Engsel Kupu-KupuRp401,400 - Besi/Alumunium 2 inch[6 buah] Kepala Tukang,Tukang Besi,Engsel Kupu-Kupu - Besi/Alumunium 2 inch[6 buah]
70 - Grendel Besar 1 day Mon 10/25/21 Tue 10/26/21 67 Kepala Tukang,Tukang Besi,Grendel - Brass/StainlessRp356,000Steel Uk. 6 inch.[4 buah] Kepala Tukang,Tukang Besi,Grendel - Brass/Stainless Steel Uk. 6 inch.[4 buah]
71 - Kunci Tanam 1 day Fri 10/22/21 Sat 10/23/21 61 Kepala Tukang,Tukang Besi[2],Kunci Silinder - Rp314,800
Brass/Alumunium Uk. 60 mm[2 buah] Kepala Tukang,Tukang Besi[2],Kunci Silinder - Brass/Alumunium Uk. 60 mm[2 buah]
72 Pas. Kusen Pintu Type PB1 3 days Tue 10/19/21 Sat 10/23/21 Rp2,847,142
73 - Kusen 3 days Tue 10/19/21 Sat 10/23/21 54SS+25%Mandor,Kepala Tukang[0.1],Tukang Besi,Pekerja,Kusen
Rp1,444,442 Alumunium Profil - Uk. 4 inch.[5 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.08 kg],Lem Plastic Steel Epoxy - 48 gr[0.02 kg] Mandor,Kepala Tukang[0.1],Tukang Besi,Pekerja,Kusen Alumunium Profil - Uk. 4 inch.[5 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.08 kg],Lem Plastic Steel Epoxy - 48 gr[0.02 kg]
74 - Handle Pintu 1 day Fri 10/22/21 Sat 10/23/21 61 Kepala Tukang,Tukang Besi,Handle Pintu[2 buah] Rp500,000 Kepala Tukang,Tukang Besi,Handle Pintu[2 buah]
75 - Engsel Pintu 1 day Fri 10/22/21 Sat 10/23/21 61 Kepala Tukang,Tukang Besi,Engsel Kupu-KupuRp401,400 - Besi/Alumunium 2 inch[6 buah] Kepala Tukang,Tukang Besi,Engsel Kupu-Kupu - Besi/Alumunium 2 inch[6 buah]
76 - Grendel Besar 1 day Fri 10/22/21 Sat 10/23/21 61 Kepala Tukang,Tukang Besi,Grendel - Brass/StainlessRp207,500Steel Uk. 6 inch.[4 buah] Kepala Tukang,Tukang Besi,Grendel - Brass/Stainless Steel Uk. 6 inch.[4 buah]
77 - Kunci Tanam 1 day Fri 10/22/21 Sat 10/23/21 61 Kepala Tukang,Tukang Besi,Kunci Silinder - Brass/Alumunium
Rp293,800 Uk. 60 mm[2 buah] Kepala Tukang,Tukang Besi,Kunci Silinder - Brass/Alumunium Uk. 60 mm[2 buah]
78 Pas. Kusen Jendela Type J1 3 days Tue 10/19/21 Sat 10/23/21 Rp4,897,648
79 - Kusen 1 day Tue 10/19/21 Thu 10/21/21 54SS+25%Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kusen Rp3,845,135 Alumunium Profil - Uk. 4 inch.[18.93 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.28 kg],Lem Plastic Steel Epoxy - 48 gr[0.06 kg] Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kusen Alumunium Profil - Uk. 4 inch.[18.93 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.28 kg],Lem Plastic Steel Epoxy - 48 gr[0.06 kg]
80 - Kaca Mati 1 day Fri 10/22/21 Sat 10/23/21 61 Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kaca Rp1,052,513
Polos Bening - tbl. 5 mm[7.07 m2],Silicone Rubber Sealent[0.32 tube] Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kaca Polos Bening - tbl. 5 mm[7.07 m2],Silicone Rubber Sealent[0.32 tube]
81 Pas. Kusen Type J2 4 days Tue 10/19/21 Mon 10/25/21 Rp6,066,448
82 - Kusen 1 day Tue 10/19/21 Thu 10/21/21 54SS+25%Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kusen Rp3,816,135 Alumunium Profil - Uk. 4 inch.[18.93 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.28 kg],Lem Plastic Steel Epoxy - 48 gr[0.06 kg] Mandor,Kepala Tukang,Tukang Besi,Pekerja[2],Kusen Alumunium Profil - Uk. 4 inch.[18.93 m'],Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm[0.28 kg],Lem Plastic Steel Epoxy - 48 gr[0.06 kg]
83 - Kaca Mati 1 day Fri 10/22/21 Sat 10/23/21 61 Mandor,Kepala Tukang,Tukang Besi,Pekerja[3],Kaca Rp1,408,013
Polos Bening - tbl. 5 mm[7.07 m2],Silicone Rubber Sealent[0.32 tube] Mandor,Kepala Tukang,Tukang Besi,Pekerja[3],Kaca Polos Bening - tbl. 5 mm[7.07 m2],Silicone Rubber Sealent[0.32 tube]
84 - Hak Angin 1 day Fri 10/22/21 Sat 10/23/21 61 Kepala Tukang,Tukang Besi,Hak Angin Sikutan Rp328,000
Biasa[2 m2] Kepala Tukang,Tukang Besi,Hak Angin Sikutan Biasa[2 m2]
85 - Engsel Jendela 1 day Fri 10/22/21 Sat 10/23/21 61 Kepala Tukang,Tukang Besi[2],Engsel Kupu-Kupu Rp198,800
- Besi/Alumunium 2 inch[2 buah] Kepala Tukang,Tukang Besi[2],Engsel Kupu-Kupu - Besi/Alumunium 2 inch[2 buah]
86 - Grendel Kecil 2 days Fri 10/22/21 Mon 10/25/2161 Kepala Tukang,Tukang Besi,Grendel - Brass/StainlessRp315,500Steel Uk. 6 inch.[1 buah] Kepala Tukang,Tukang Besi,Grendel - Brass/Stainless Steel Uk. 6 inch.[1 buah]
87 PEKERJAAN INSTALASI AIR 7 days Thu 7/15/21 Fri 7/23/21 Rp21,794,452
88 Kran Air 3/4" 1 day Thu 7/15/21 Thu 7/15/21 10 Kran Air Stainless Steel - Dia. 1/2 - 3/4 inch.[11 Rp545,192
unit],Sealtape[0.28 buah],Kepala Tukang,Tukang Pipa Kran Air Stainless Steel - Dia. 1/2 - 3/4 inch.[11 unit],Sealtape[0.28 buah],Kepala Tukang,Tukang Pipa
89 Instalasi Air Bersih PVC Ø 3/4" 2 days Fri 7/16/21 Sat 7/17/21 88 Mandor,Kepala Tukang,Tukang Pipa,Pekerja[2],Pipa Rp1,591,444
PVC - Type AW Dia. 3/4 inch. pjg. 400 cm[18.04 batang] Mandor,Kepala Tukang,Tukang Pipa,Pekerja[2],Pipa PVC - Type AW Dia. 3/4 inch. pjg. 400 cm[18.04 batang]
90 Instalasi Air Kotor PVC Ø 3" 1 day Mon 7/19/21 Mon 7/19/21 89 Tukang Pipa,Pipa PVC - Type AW Dia.3 inch. pjg. Rp634,800
400 cm[1 batang],Kepala Tukang,Mandor,Pekerja[2] Tukang Pipa,Pipa PVC - Type AW Dia.3 inch. pjg. 400 cm[1 batang],Kepala Tukang,Mandor,Pekerja[2]
91 Instalasi Kotoran PVC Ø 4" 2 days Wed 7/21/21 Thu 7/22/21 90 Pipa PVC - Type AW Dia.4 inch. pjg. 400 cm[11.25 Rp5,010,375
batang],Tukang Pipa,Mandor,Kepala Tukang,Pekerja[2] Pipa PVC - Type AW Dia.4 inch. pjg. 400 cm[11.25 batang],Tukang Pipa,Mandor,Kepala Tukang,Pekerja[2]
92 Klosed Duduk 1 day Fri 7/23/21 Fri 7/23/21 91 Kloset Duduk/Monoblock[5.3 buah],Mandor,Kepala Rp7,681,500
Tukang,Tukang Pipa,Pekerja[2] Kloset Duduk/Monoblock[5.3 buah],Mandor,Kepala Tukang,Tukang Pipa,Pekerja[2]
93 Septictank 2 days Fri 7/16/21 Sat 7/17/21 89SS Mandor,Tukang Pipa,Pekerja[4],Semen Portland Rp3,001,918
- 50 kg[0.12 kg],Pasir Pasang[0.01 m3],Septictank Biofilter 1 m3[1 unit] Mandor,Tukang Pipa,Pekerja[4],Semen Portland - 50 kg[0.12 kg],Pasir Pasang[0.01 m3],Septictank Biofilter 1 m3[1 unit]
94 Bak kontrol 1 day Thu 7/22/21 Thu 7/22/21 95 Mandor,Kepala Tukang,Pekerja[6],Batu Bata Merah[40
Rp1,237,305 buah],Semen Portland - 50 kg[44 kg],Pasir Pasang[0.07 m3],Pasir Beton[0.06 m3],Kerikil - Max. 30 mm[0.07 m3],Besi Beton - Polos/Ulir[1.6 kg],Tukang Batu Mandor,Kepala Tukang,Pekerja[6],Batu Bata Merah[40 buah],Semen Portland - 50 kg[44 kg],Pasir Pasang[0.07 m3],Pasir Beton[0.06 m3],Kerikil - Max. 30 mm[0.07 m3],Besi Beton - Polos/Ulir[1.6 kg],Tukang Batu
95 Sumur Peresap 2 days Mon 7/19/21 Wed 7/21/21 93 Semen Portland - 50 kg[0.12 kg],Pasir Pasang[0.01Rp2,091,918
m3],Batu Bata Merah[70 buah],Pas. Ijuk[2.5 kg],Mandor,Tukang Batu,Pekerja[4] Semen Portland - 50 kg[0.12 kg],Pasir Pasang[0.01 m3],Batu Bata Merah[70 buah],Pas. Ijuk[2.5 kg],Mandor,Tukang Batu,Pekerja[4]
96 PEKERJAAN LANTAI 39 days Fri 10/15/21 Wed 12/1/21 Rp36,993,681
97 Keramik Lantai 40 x 40 cm 4 days Thu 11/18/21 Tue 11/23/21 178SS Keramik Putih - Uk. 40 x 40 cm[107.41 m2],Semen Rp17,261,857
Portland - 50 kg[939.82 kg],Pasir Pasang[4.32 m3],Semen Warna - Nat[124.67 kg],Mandor,Kepala Tukang,Tukang Batu[2],Pekerja[8] Keramik Putih - Uk. 40 x 40 cm[107.41 m2],Semen Portland - 50 kg[939.82 kg],Pasir Pasang[4.32 m3],Semen Warna - Nat[124.67 kg],Mandor,Kepala Tukang,Tukang Batu[2],Pekerja[8]
98 Plester 2 days Mon 11/29/21 Wed 12/1/21 178FS+6 days
Semen Portland - 50 kg[1,320.82 kg],Pasir Pasang/Plester[5.08
Rp2,234,204 m3] Semen Portland - 50 kg[1,320.82 kg],Pasir Pasang/Plester[5.08 m3]
99 PEKERJAAN INSTALASI LISTRIK 8 days Fri 10/15/21 Tue 10/26/21 Rp17,497,620
100 Titik Lampu 1 day Fri 10/15/21 Sat 10/16/21 161SS Kabel NYA - 1 x 2.5 mm[1,080 m'],Pipa PVC -Rp9,676,400
Type C Dia. 5/8 inch. pjg. 400 cm[288 m'],Fitting Lampu Plafon[72 kg],T Dos PVC[72 buah],Kepala Tukang,Tukang Listrik[2],Pekerja[5] Kabel NYA - 1 x 2.5 mm[1,080 m'],Pipa PVC - Type C Dia. 5/8 inch. pjg. 400 cm[288 m'],Fitting Lampu Plafon[72 kg],T Dos PVC[72 buah],Kepala Tukang,Tukang Listrik[2],Pekerja[5]
101 Lampu Down light 1 day Mon 10/25/21 Tue 10/26/21 100FS+6 days
Lampu Down Light LED 18 watt[29 buah],Tukang Rp3,721,000
Listrik[2],Pekerja[4],Kepala Tukang Lampu Down Light LED 18 watt[29 buah],Tukang Listrik[2],Pekerja[4],Kepala Tukang
102 Saklar 1 day Thu 10/21/21 Fri 10/22/21 54FF Saklar Dinding - Ganda[8 buah],Kepala Tukang,Tukang
Rp1,011,600 Listrik[2],Pekerja[4] Saklar Dinding - Ganda[8 buah],Kepala Tukang,Tukang Listrik[2],Pekerja[4]
103 Stop Kontak 1 day Thu 10/21/21 Fri 10/22/21 54FF Kabel NYA - 1 x 2.5 mm[270 m'],Pipa PVC - Type Rp2,874,520
C Dia. 5/8 inch. pjg. 400 cm[14.4 m'],Stop Kontak - Tunggal[18 kg],T Dos PVC[18 buah],Kepala Tukang,Tukang Listrik[3],Pekerja[4] Kabel NYA - 1 x 2.5 mm[270 m'],Pipa PVC - Type C Dia. 5/8 inch. pjg. 400 cm[14.4 m'],Stop Kontak - Tunggal[18 kg],T Dos PVC[18 buah],Kepala Tukang,Tukang Listrik[3],Pekerja[4]
104 Box MCB 1 day Thu 10/21/21 Fri 10/22/21 54FF MCB Panel Box - Outbow 4 Grup[1 buah],Tukang Rp214,100
Listrik MCB Panel Box - Outbow 4 Grup[1 buah],Tukang Listrik
105 PEKERJAAN PENGECATAN 30 days Tue 10/19/21 Wed 11/24/21 Rp20,229,677
106 Pengecatan Dinding Eksterior (Weatherbond) 5 days Thu 11/18/21 Wed 11/24/21171SS Cat Tembok Exterior - Primer - Weather Shield[16.22
Rp16,834,525kaleng],Plamir Tembok[67.58 kg],Thinner[67.58 liter],Pisau Pallet[10.14 buah],Kuas Cat[10.14 buah],Kepala Tukang,Tukang Cat[2],Pekerja[5],Cat Tembok Exterior - Finishing - Weather Shield[24.33 kaleng] Cat Tembok Exterior - Primer - Weather Shield[16.22 kaleng],Plamir Tembok[67.58 kg],Thinner[67.58 liter],Pisau Pallet[10.14 buah],Kuas Cat[10.14 buah],Kepala Tukang,Tukang Cat[2],Pekerja[5],Cat Tembok Exterior - Finishing - Weather Sh
107 Pengecatan Dinding Interior (Spoot-Less) 1 day Tue 10/19/21 Thu 10/21/21 161 Cat Tembok Interior - Primer[3.21 kaleng],CatRp3,395,152
Tembok Interior - Finishing[8.34 kaleng],Plamir Tembok[8.02 kg],Amplas - No.240[80.17 lembar],Pisau Pallet[1.2 buah],Kuas Cat[1.2 buah],Mandor,Kepala Tukang,Tukang Cat,Pekerja[2] Cat Tembok Interior - Primer[3.21 kaleng],Cat Tembok Interior - Finishing[8.34 kaleng],Plamir Tembok[8.02 kg],Amplas - No.240[80.17 lembar],Pisau Pallet[1.2 buah],Kuas Cat[1.2 buah],Mandor,Kepala Tukang,Tukang Cat,Pekerja[2]
108 PEKERJAAN LANTAI 2 48 days Fri 10/1/21 Sat 11/27/21 Rp790,022,431
109 PEKERJAAN KONSTRUKSI BAJA 17 days Fri 10/22/21 Thu 11/11/21 Rp286,201,543
110 Pekerjaan Kolom K2 2 days Fri 10/22/21 Mon 10/25/21104 Baja Profil[4,570.56 kg],Mandor,Kepala Tukang,Tukang,Pekerja[2]
Rp82,473,524 Baja Profil[4,570.56 kg],Mandor,Kepala Tukang,Tukang,Pekerja[2]
111 Pekerjaan Kolom K3 2 days Fri 10/29/21 Mon 11/1/21 107SS+8 days
Tukang,Baja Profil[5,486.88 kg],Kepala Tukang,Mandor,Pekerja[2]
Rp98,927,152 Tukang,Baja Profil[5,486.88 kg],Kepala Tukang,Mandor,Pekerja[2]
112 Pekerjaan Balok WF 450.200 3 days Mon 11/1/21 Thu 11/4/21 111 Tukang,Baja Profil[699.2 kg],Kepala Tukang,Mandor,Pekerja[2]
Rp13,604,180 Tukang,Baja Profil[699.2 kg],Kepala Tukang,Mandor,Pekerja[2]
113 Pekerjaan Balok WF 400.200 2 days Tue 11/2/21 Thu 11/4/21 112FF Tukang,Baja Profil[1,442.1 kg],Kepala Tukang,Mandor,Pekerja[2]
Rp26,319,590 Tukang,Baja Profil[1,442.1 kg],Kepala Tukang,Mandor,Pekerja[2]
114 Pekerjaan Balok WF 300.150 3 days Thu 11/4/21 Mon 11/8/21 113 Baja Profil[801.9 kg],Kepala Tukang,Mandor,Tukang[2],Pekerja[3]
Rp15,820,510 Baja Profil[801.9 kg],Kepala Tukang,Mandor,Tukang[2],Pekerja[3]
115 Pekerjaan Balok WF 250.125 3 days Mon 11/8/21 Thu 11/11/21 114 Tukang,Baja Gording[136.85 kg],Kepala Tukang,Mandor,Pekerja[2]
Rp3,002,615 Tukang,Baja Gording[136.85 kg],Kepala Tukang,Mandor,Pekerja[2]
116 Pekerjaan Sambungan A 1 day Fri 10/22/21 Sat 10/23/21 Rp7,388,797
117 - Baja WF 1 day Fri 10/22/21 Sat 10/23/21 110SS Tukang,Baja Profil[122.36 kg],Kepala Tukang,Mandor,Pekerja[2]
Rp2,492,244 Tukang,Baja Profil[122.36 kg],Kepala Tukang,Mandor,Pekerja[2]
118 - Plat 1 day Fri 10/22/21 Sat 10/23/21 110SS Tukang,Baja Profil[153.38 kg],Kepala Tukang,Mandor,Pekerja[2]
Rp3,047,502 Tukang,Baja Profil[153.38 kg],Kepala Tukang,Mandor,Pekerja[2]
119 - Baut 1 day Fri 10/22/21 Sat 10/23/21 110SS Mur Baut - Uk. 10 cm[640 buah],Kepala Tukang,Mandor,Pekerja[2],Tukang
Rp1,390,000 Mur Baut - Uk. 10 cm[640 buah],Kepala Tukang,Mandor,Pekerja[2],Tukang
120 - Las 1 day Fri 10/22/21 Sat 10/23/21 110SS Solar Industri[1.22 liter],Minyak Pelumas[0.16 liter],Kawat
Rp459,051 Las Elektroda - Dia. 2 mm; pjg. 300 mm[1.62 kg],Las Listrik - 900 watt[0.69 jam],Kepala Tukang,Pekerja[3],Mandor,Tukang Solar Industri[1.22 liter],Minyak Pelumas[0.16 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[1.62 kg],Las Listrik - 900 watt[0.69 jam],Kepala Tukang,Pekerja[3],Mandor,Tukang
121 Pekerjaan Sambungan B 9 days Sat 10/23/21 Wed 11/3/21 Rp6,071,609
122 - Plat 1 day Sat 10/23/21 Mon 10/25/21120 Baja Profil[10.74 kg],Mandor,Kepala Tukang,Tukang[2],Pekerja[4]
Rp612,246 Baja Profil[10.74 kg],Mandor,Kepala Tukang,Tukang[2],Pekerja[4]
123 - Baut 4 days Mon 10/25/21 Fri 10/29/21 122 Mur Baut - Uk. 10 cm[120 buah],Kepala Tukang,Mandor,Tukang,Pekerja
Rp2,604,000 Mur Baut - Uk. 10 cm[120 buah],Kepala Tukang,Mandor,Tukang,Pekerja
124 - Las 4 days Fri 10/29/21 Wed 11/3/21 123 Tukang,Solar Industri[3.52 liter],Minyak Pelumas[0.47
Rp2,855,363 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[4.7 kg],Las Listrik - 900 watt[2 jam],Kepala Tukang,Pekerja,Mandor Tukang,Solar Industri[3.52 liter],Minyak Pelumas[0.47 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[4.7 kg],Las Listrik - 900 watt[2 jam],Kepala Tukang,Pekerja,Mandor
125 Pekerjaan Sambungan C 4 days Sat 10/23/21 Thu 10/28/21 Rp9,733,451
126 - Baja WF 1 day Sat 10/23/21 Mon 10/25/21117 Baja Profil[51.89 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[6]
Rp2,778,831 Baja Profil[51.89 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[6]
127 - Plat 1 day Mon 10/25/21 Tue 10/26/21 126 Baja Profil[46.62 kg],Kepala Tukang,Mandor,Pekerja,Tukang[6]
Rp2,184,498 Baja Profil[46.62 kg],Kepala Tukang,Mandor,Pekerja,Tukang[6]
128 - Baut 1 day Tue 10/26/21 Wed 10/27/21127 Mur Baut - Uk. 10 cm[400 buah],Kepala Tukang,Mandor,Pekerja[6],Tukang[6]
Rp2,211,500 Mur Baut - Uk. 10 cm[400 buah],Kepala Tukang,Mandor,Pekerja[6],Tukang[6]
129 - Las 1 day Wed 10/27/21 Thu 10/28/21 128 Solar Industri[11.69 liter],Minyak Pelumas[1.56 Rp2,558,622
liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[15.58 kg],Las Listrik - 900 watt[6.62 jam],Kepala Tukang,Mandor,Tukang[2],Pekerja[4] Solar Industri[11.69 liter],Minyak Pelumas[1.56 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[15.58 kg],Las Listrik - 900 watt[6.62 jam],Kepala Tukang,Mandor,Tukang[2],Pekerja[4]
130 Pekerjaan Sambungan D 1 day Mon 11/1/21 Tue 11/2/21 Rp6,752,725
131 - Baja WF 1 day Mon 11/1/21 Tue 11/2/21 112SS Baja Profil[35.53 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
Rp1,311,987 Baja Profil[35.53 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
132 - Plat 1 day Mon 11/1/21 Tue 11/2/21 112SS Baja Profil[36 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang
Rp1,744,400 Baja Profil[36 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang
133 - Baut 1 day Mon 11/1/21 Tue 11/2/21 112SS Mur Baut - Uk. 10 cm[360 buah],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
Rp1,320,000 Mur Baut - Uk. 10 cm[360 buah],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
134 - Las 1 day Mon 11/1/21 Tue 11/2/21 112SS Solar Industri[10.27 liter],Minyak Pelumas[1.37 Rp2,376,338
liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[13.7 kg],Las Listrik - 900 watt[5.82 jam],Kepala Tukang,Mandor,Pekerja[4],Tukang[2] Solar Industri[10.27 liter],Minyak Pelumas[1.37 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[13.7 kg],Las Listrik - 900 watt[5.82 jam],Kepala Tukang,Mandor,Pekerja[4],Tukang[2]
135 Pekerjaan Sambungan E 1 day Mon 11/8/21 Tue 11/9/21 Rp2,899,086
136 - Plat 1 day Mon 11/8/21 Tue 11/9/21 115SS Baja Profil[0.76 kg],Kepala Tukang,Mandor,Pekerja[4],Tukang
Rp428,604 Baja Profil[0.76 kg],Kepala Tukang,Mandor,Pekerja[4],Tukang
137 - Baut 1 day Mon 11/8/21 Tue 11/9/21 115SS Mur Baut - Uk. 10 cm[60 buah],Kepala Tukang,Mandor,Tukang[6],Pekerja[8]
Rp1,042,500 Mur Baut - Uk. 10 cm[60 buah],Kepala Tukang,Mandor,Tukang[6],Pekerja[8]
138 - Las 1 day Mon 11/8/21 Tue 11/9/21 115SS Solar Industri[2.93 liter],Minyak Pelumas[0.39Rp1,427,982
liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[3.9 kg],Las Listrik - 900 watt[1.66 jam],Kepala Tukang,Tukang[2],Mandor,Pekerja[4] Solar Industri[2.93 liter],Minyak Pelumas[0.39 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[3.9 kg],Las Listrik - 900 watt[1.66 jam],Kepala Tukang,Tukang[2],Mandor,Pekerja[4]
139 Pekerjaan Sambungan F 1 day Thu 11/4/21 Fri 11/5/21 Rp3,415,563
140 - Plat 1 day Thu 11/4/21 Fri 11/5/21 114SS Baja Profil[14.39 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
Rp886,081 Baja Profil[14.39 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
141 - Baut 1 day Thu 11/4/21 Fri 11/5/21 114SS Mur Baut - Uk. 10 cm[190 buah],Kepala Tukang,Mandor,Pekerja[6],Tukang[5]
Rp1,101,500 Mur Baut - Uk. 10 cm[190 buah],Kepala Tukang,Mandor,Pekerja[6],Tukang[5]
142 - Las 1 day Thu 11/4/21 Fri 11/5/21 114SS Solar Industri[2.93 liter],Minyak Pelumas[0.39Rp1,427,982
liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[3.9 kg],Las Listrik - 900 watt[1.66 jam],Kepala Tukang,Mandor,Tukang[2],Pekerja[4] Solar Industri[2.93 liter],Minyak Pelumas[0.39 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[3.9 kg],Las Listrik - 900 watt[1.66 jam],Kepala Tukang,Mandor,Tukang[2],Pekerja[4]
143 Pekerjaan Sambungan 1A 6 days Fri 10/29/21 Fri 11/5/21 Rp7,358,216
144 - Baja WF 1 day Fri 10/29/21 Sat 10/30/21 111SS Baja Gording[54.68 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
Rp1,635,772 Baja Gording[54.68 kg],Kepala Tukang,Mandor,Pekerja[6],Tukang[4]
145 - Plat 1 day Fri 10/29/21 Sat 10/30/21 111SS Baja Profil[27.72 kg],Kepala Tukang,Mandor,Tukang[6],Pekerja[6]
Rp2,346,188 Baja Profil[27.72 kg],Kepala Tukang,Mandor,Tukang[6],Pekerja[6]
146 - Baut 6 days Fri 10/29/21 Fri 11/5/21 111SS Tukang,Mur Baut - Uk. 10 cm[140 buah],Kepala Rp2,088,000
Tukang,Mandor,Pekerja[2] Tukang,Mur Baut - Uk. 10 cm[140 buah],Kepala Tukang,Mandor,Pekerja[2]
147 - Las 1 day Fri 10/29/21 Sat 10/30/21 111SS Solar Industri[8.26 liter],Minyak Pelumas[1.1 liter],Kawat
Rp1,288,256Las Elektroda - Dia. 2 mm; pjg. 300 mm[11.01 kg],Las Listrik - 900 watt[4.68 jam],Kepala Tukang,Mandor,Pekerja[2],Tukang Solar Industri[8.26 liter],Minyak Pelumas[1.1 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[11.01 kg],Las Listrik - 900 watt[4.68 jam],Kepala Tukang,Mandor,Pekerja[2],Tukang
148 Pekerjaan Sambungan 1B 1 day Mon 11/1/21 Tue 11/2/21 Rp2,434,525
149 - Baja WF 1 day Mon 11/1/21 Tue 11/2/21 112SS Baja Profil[27.23 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang
Rp656,417 Baja Profil[27.23 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang
150 - Plat 1 day Mon 11/1/21 Tue 11/2/21 112SS Baja Profil[27.72 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang
Rp665,188 Baja Profil[27.72 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang
151 - Baut 1 day Mon 11/1/21 Tue 11/2/21 112SS Mur Baut - Uk. 10 cm[140 buah],Kepala Tukang,Mandor,Pekerja[2],Tukang
Rp415,000 Mur Baut - Uk. 10 cm[140 buah],Kepala Tukang,Mandor,Pekerja[2],Tukang
152 - Las 1 day Mon 11/1/21 Tue 11/2/21 112SS Solar Industri[4.13 liter],Minyak Pelumas[0.55 liter],Kawat
Rp697,920 Las Elektroda - Dia. 2 mm; pjg. 300 mm[5.5 kg],Las Listrik - 900 watt[2.34 jam],Kepala Tukang,Pekerja[2],Mandor,Tukang Solar Industri[4.13 liter],Minyak Pelumas[0.55 liter],Kawat Las Elektroda - Dia. 2 mm; pjg. 300 mm[5.5 kg],Las Listrik - 900 watt[2.34 jam],Kepala Tukang,Pekerja[2],Mandor,Tukang
153 PEKERJAAN PENULANGAN 3 days Tue 10/12/21 Fri 10/15/21 Rp73,809,008
154 Pekerjaan Penulangan Plat Lantai 3 days Tue 10/12/21 Fri 10/15/21 Rp73,809,008
155 - Penulangan plat lantai 6x6 1 day Tue 10/12/21 Wed 10/13/21159FS+2 days
Besi Beton - Polos/Ulir[3,228.44 kg],Kawat beton[46.12
Rp35,271,352 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang Besi Besi Beton - Polos/Ulir[3,228.44 kg],Kawat beton[46.12 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang Besi
156 - Penulangan plat lantai 6x5 1 day Wed 10/13/21 Thu 10/14/21 155 Besi Beton - Polos/Ulir[1,362.01 kg],Kawat beton[19.46
Rp14,968,511 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang Besi Besi Beton - Polos/Ulir[1,362.01 kg],Kawat beton[19.46 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang Besi
157 - Penulangan plat lantai 6x8 1 day Thu 10/14/21 Fri 10/15/21 156 Besi Beton - Polos/Ulir[2,152.34 kg],Kawat beton[30.75
Rp23,569,145 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang Besi Besi Beton - Polos/Ulir[2,152.34 kg],Kawat beton[30.75 kg],Kepala Tukang,Mandor,Pekerja[2],Tukang Besi
158 PEKERJAAN BEKISTING 7 days Fri 10/1/21 Sat 10/9/21 Rp48,682,993
159 Pekerjaan Bekisting Plat Lantai 7 days Fri 10/1/21 Sat 10/9/21 38FS+6 days
Kayu Kelas III - Papan[3.16 m3],Paku Biasa -Rp48,682,993
Uk. 2 - 5 inch[31.58 kg],Minyak Bekisting[15.79 liter],Kayu Kelas II - Balok[1.18 m3],Plywood - Uk. 9 mm[27.63 lembar],Dolken Kayu - Dia. 8-10/400 cm[473.7 batang],Kepala Tukang,Mandor,Pekerja[2],Tukang Kayu Kayu Kelas III - Papan[3.16 m3],Paku Biasa - Uk. 2 - 5 inch[31.58 kg],Minyak Bekisting[15.79 liter],Kayu Kelas II - Balok[1.18 m3],Plywood - Uk. 9 mm[27.63 lembar],Dolken Kayu - Dia. 8-10/400 cm[473.7 batang],Kepala Tukang,Mandor,Pekerja[2],Tukang Kayu
160 PEKERJAAN BETON 3 days Fri 10/15/21 Tue 10/19/21 Rp108,037,585
161 Pekerjaan Beton Plat Lantai 3 days Fri 10/15/21 Tue 10/19/21 157 Semen Portland - 50 kg[61,950 kg],Pasir Beton[72.9
Rp108,037,585
m3],Kerikil - Max. 30 mm[85.05 m3],Air[32,250 liter],Kepala Tukang,Mandor,Tukang Batu,Pekerja[2] Semen Portland - 50 kg[61,950 kg],Pasir Beton[72.9 m3],Kerikil - Max. 30 mm[85.05 m3],Air[32,250 liter],Kepala Tukang,Mandor,Tukang Batu,Pekerja[2]
162 PEKERJAAN DINDING 13 days Wed 10/27/21 Thu 11/11/21 Rp86,065,632
163 Pas. Batu Bata Merah 1Pc : 6Psr 7 days Wed 10/27/21 Thu 11/4/21 161FS+6 days
Semen Portland - 50 kg[8,518.4 kg],Batu BataRp66,810,480
Merah[61,600 buah],Pasir Pasang[39.6 m3],Kepala Tukang,Mandor,Pekerja[2],Tukang Batu Semen Portland - 50 kg[8,518.4 kg],Batu Bata Merah[61,600 buah],Pasir Pasang[39.6 m3],Kepala Tukang,Mandor,Pekerja[2],Tukang Batu
164 Plesteran Halus 1 Pc : 4Psr 2 days Tue 11/9/21 Thu 11/11/21 163FS+4 days
Semen Portland - 50 kg[10,982.4 kg],Pasir Pasang/Plester[42.24
Rp19,255,152 m3],Kepala Tukang,Mandor,Pekerja[2],Tukang Batu Semen Portland - 50 kg[10,982.4 kg],Pasir Pasang/Plester[42.24 m3],Kepala Tukang,Mandor,Pekerja[2],Tukang Batu
165 PEKERJAAN LANTAI 2 8 days Thu 11/18/21 Sat 11/27/21 Rp3,304,832
166 Plester 6 days Thu 11/18/21 Sat 11/27/21 177 Semen Portland - 50 kg[998.4 kg],Pasir Pasang[3.84
Rp3,304,832
m3],Kepala Tukang,Mandor,Tukang Batu,Pekerja[2] Semen Portland - 50 kg[998.4 kg],Pasir Pasang[3.84 m3],Kepala Tukang,Mandor,Tukang Batu,Pekerja[2]
167 PEKERJAAN INSTALASI LISTRIK 5 days Thu 11/18/21 Wed 11/24/21 Rp8,648,000
168 Titik Lampu 2 days Mon 11/22/21 Wed 11/24/21178 Kabel NYA - 1 x 2.5 mm[600 m'],Pipa PVC - Type Rp5,511,000
C Dia. 5/8 inch. pjg. 400 cm[160 m'],Fitting Lampu Plafon[40 kg],T Dos PVC[40 buah],Kepala Tukang,Tukang Listrik,Pekerja[2] Kabel NYA - 1 x 2.5 mm[600 m'],Pipa PVC - Type C Dia. 5/8 inch. pjg. 400 cm[160 m'],Fitting Lampu Plafon[40 kg],T Dos PVC[40 buah],Kepala Tukang,Tukang Listrik,Pekerja[2]
169 Lampu Down light 1 day Thu 11/18/21 Fri 11/19/21 177 Lampu Down Light LED 18 watt[30 buah],Tukang Rp3,137,000
Listrik,Kepala Tukang,Pekerja[2] Lampu Down Light LED 18 watt[30 buah],Tukang Listrik,Kepala Tukang,Pekerja[2]
170 PEKERJAAN PENGECATAN 2 days Thu 11/18/21 Sat 11/20/21 Rp53,532,544
171 Pengecatan Dinding Interior (Spoot-Less) 2 days Thu 11/18/21 Sat 11/20/21 177 Cat Tembok Interior - Primer[35.2 kaleng],CatRp32,505,264
Tembok Interior - Finishing[91.52 kaleng],Plamir Tembok[88 kg],Thinner[88 liter],Amplas - No.240[880 lembar],Pisau Pallet[13.2 buah],Kuas Cat[13.2 buah],Kepala Tukang,Mandor,Tukang Cat,Pekerja[2] Cat Tembok Interior - Primer[35.2 kaleng],Cat Tembok Interior - Finishing[91.52 kaleng],Plamir Tembok[88 kg],Thinner[88 liter],Amplas - No.240[880 lembar],Pisau Pallet[13.2 buah],Kuas Cat[13.2 buah],Kepala Tukang,Mandor,Tukang Cat,Pekerja[2]
172 Pengecatan Dinding Eksterior (Weatherbond) 2 days Thu 11/18/21 Sat 11/20/21 177 Cat Tembok Exterior - Primer - Weather Shield[21.12
Rp21,027,280kaleng],Cat Tembok Exterior - Finishing - Weather Shield[31.68 kaleng],Plamir Tembok[88 kg],Thinner[88 liter],Amplas - No.240[880 lembar],Pisau Pallet[13.2 buah],Kuas Cat[13.2 buah],Kepala Tukang,Tuka... Cat Tembok Exterior - Primer - Weather Shield[21.12 kaleng],Cat Tembok Exterior - Finishing - Weather Shield[31.68 kaleng],Plamir Tembok[88 kg],Thinner[88 liter],Amplas - No.240[880 lembar],Pisau Pallet[13.2 buah],Kuas Cat[13.2 buah],Kepala Tukang,T
173 PEKERJAAN ATAP 9 days Thu 11/11/21 Mon 11/22/21 Rp121,740,294
174 Pemasangan Kuda-kuda Rangka Baja WF 350.175 2 days Thu 11/11/21 Sat 11/13/21 115 Mandor,Kepala Tukang,Tukang,Pekerja[2],Besi Rp22,476,893
Profil WF 350.175[1,221.67 kg] Mandor,Kepala Tukang,Tukang,Pekerja[2],Besi Profil WF 350.175[1,221.67 kg]
175 Pemasangan Gording C 150.65.20.2,3 1 day Sat 11/13/21 Mon 11/15/21174 Baja Gording[193.6 kg],Kepala Tukang,Pekerja[2],Tukang
Rp3,723,940 Baja Gording[193.6 kg],Kepala Tukang,Pekerja[2],Tukang
176 Pemasangan Papan Reuter 3/30 1 day Mon 11/15/21 Tue 11/16/21 175 Paku Biasa - Uk. 2 - 5 inch[1.75 kg],Kayu Kelas Rp1,815,825
III - Papan Uk. 3/20[0.25 m3],Kepala Tukang,Mandor,Pekerja[2],Tukang Paku Biasa - Uk. 2 - 5 inch[1.75 kg],Kayu Kelas III - Papan Uk. 3/20[0.25 m3],Kepala Tukang,Mandor,Pekerja[2],Tukang
177 Pemasangan Bubungan Atap Keramik Mclass 2 days Tue 11/16/21 Thu 11/18/21 176 Semen Portland - 50 kg[5.12 kg],Pasir Pasang[1.02Rp4,593,516
m3],Bubungan Keramik Mclass[160 buah],Kepala Tukang,Mandor,Pekerja[2],Tukang Semen Portland - 50 kg[5.12 kg],Pasir Pasang[1.02 m3],Bubungan Keramik Mclass[160 buah],Kepala Tukang,Mandor,Pekerja[2],Tukang
178 Pemasangan Atap Genteng Keramik Mclass 3 days Thu 11/18/21 Mon 11/22/21177 Genteng Keramik Mclass[9,032.32 buah],Kepala Rp89,130,120
Tukang,Mandor,Pekerja[2],Tukang Genteng Keramik Mclass[9,032.32 buah],Kepala Tukang,Mandor,Pekerja[2],Tukang
Project: Laporan MS PROJECT Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress
Date: Fri 7/30/21
Page 1
February 2022 March 2022 April 2022 May 2022 June 2022 July 2022 August 2022 September 2022 October 2022 November 2022
20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2
Project: Laporan MS PROJECT Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress
Date: Fri 7/30/21
Page 2