Actual Level of Effort Remaining Work Page 1 of 4 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Blended Learning Hubs Education Deptt. GB Classic Schedule Layout 01-Jan-23 09:16 PM
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
12-Mar-23 04:00 PM, Project: BLH GB EDucation Blended Learning Hubs Education Deptt. GB
Contract Procedure
21-Jan-23 04:00 PM, WBS: BLH GB EDucation.Contract Contract Process
Contract Award
Submission of 10% Security
Start Order
21-Jan-23 04:00 PM, WBS: BLH GB EDucation.1 Mobilization
Mobilization Advance
30-Jan-23 04:00 PM, WBS: BLH GB EDucation.2 Drawings
Issuance of Drawings
Verifacation of Drawings
Actual Measurement of The Work
01-Feb-23 04:00 PM, WBS: BLH GB EDucation.3 Procurment of Goods
Procurment of Local Raw Materials
Issuance of Purchase Order to Suppliers
Transportatio n of material to site
29-Jan-23 04:00 PM, WBS: BLH GB EDucation.4 Landscape
Landscape at Gilgit
Landscape at Hunza
Landscape at Ghizer
Landscape at Chilas
Landscape at Skardu
Landscape at Nagar
31-Jan-23 04:00 PM, WBS: BLH GB EDucation.5 Exterior Renovation
Exterior Renovation
16-Feb-23 04:00 PM, WBS: BLH GB EDucation.6 Renovation of Main Building
Renovation
22-Feb-23 04:00 PM, WBS: BLH GB EDucation.7 Inspection
Actual Level of Effort Remaining Work Page 2 of 4 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Blended Learning Hubs Education Deptt. GB Classic Schedule Layout 01-Jan-23 09:16 PM
Activity ID Activity Type Activity Name Original Remaining Schedule % Start Finish Total Float Qtr 4, 2022
Duration Duration Complete
Nov Dec
A1200 Task Dependent
Inspection Gilgit 1 1 0% 16-Feb-23 08:00
16-Feb-23
AM* 04:00 PM
A1210 Task Dependent
Inspection Hunza 1 1 0% 18-Feb-23 08:00
18-Feb-23
AM* 04:00 PM
A1220 Task Dependent
Inspection Ghizer 1 1 0% 19-Feb-23 08:00
19-Feb-23
AM* 04:00 PM
A1230 Task Dependent
Inspection Chilas 1 1 0% 20-Feb-23 08:00
20-Feb-23
AM* 04:00 PM
A1240 Task Dependent
Inspection Skardu 1 1 0% 21-Feb-23 08:00
21-Feb-23
AM* 04:00 PM
A1250 Task Dependent
Inspection Nagar 1 1 0% 22-Feb-23 08:00
22-Feb-23
AM* 04:00 PM
Actual Level of Effort Remaining Work Page 3 of 4 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Blended Learning Hubs Education Deptt. GB Classic Schedule Layout 01-Jan-23 09:16 PM
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Inspection Gilgit
Inspection Hunza
Inspection Ghizer
Inspection Chilas
Inspection Skardu
Inspection Nagar
19-Feb-23 04:00 PM, WBS: BLH GB EDucation.8 Electrical
Electrical Work at Gilgit
27-Feb-23 04:00 PM, WBS: BLH GB EDucation.9 Paint Work
Paint Work
02-Mar-23 04:00 PM, WBS: BLH GB EDucation.10 Final Installation
Final Installation
05-Mar-23 04:00 PM, WBS: BLH GB EDucation.11 Final Inspection
Final Inspection
07-Mar-23 04:00 PM, WBS: BLH GB EDucation.12 Site Cleanup
Site Cleanup
12-Mar-23 04:00 PM, WBS: BLH GB EDucation.13 Demoblization
Demoblization
Actual Level of Effort Remaining Work Page 4 of 4 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation