Professional Documents
Culture Documents
LNS 2019 1 1380 Hoenmoira
LNS 2019 1 1380 Hoenmoira
BETWEEN
AND
BETWEEN
AND
1
[2019] 1 LNS 1380 Legal Network Series
(NRIC: 671124-14-5250)
THE JUDGMENT OF
Parties
[2] The plaintiffs are siblings, a brother and a sister, and they had
inherited lot 2 from their deceased father. On lot 2 stands a 2 storey
shophouse for the last 70 years bearing address No. 2 Jalan Utara, Off
Jalan Imbi, 55100, Kuala Lumpur.
[3] The plaintiffs operate a sundry shop business from the ground
floor of their property. They have been doing that since 1956 with the
family members residing in the said property as well. The first
plaintiff, PW 4 Goh Aik Chin, now stays in Singapore but the second
plaintiff, PW 3 Goh Aik Bee, stays with her children in the said
property.
2
[2019] 1 LNS 1380 Legal Network Series
[4] The first and second defendants (D1 and D2) are sisters and they
are the owners of the adjacent Lots 6 and 4 respectively along the
same row of pre-war shop houses.
Problem
3
[2019] 1 LNS 1380 Legal Network Series
[9] After a full trial the Sessions Court judge found in favour of the
plaintiffs and awarded damages of RM 604,055.40 together with
interest at the rate of 5% per annum from date of the writ to
realization against all the defendants jointly and severally.
[11] The Session Court Judge had found that the defendants owed the
plaintiffs a duty of care based on the neighbour principle first
expounded in the seminal case of Donoghue v. Stevenson [1932] AC
562. She also found that the defendants had breached that duty and
that the damage was foreseeable.
4
[2019] 1 LNS 1380 Legal Network Series
[14] D3 further pleaded that the cracks had already existed before
they commenced the works and that the plaintiffs’ building was a pre-
war building prone to cracks and settlement even without any works
being done on the defendants owners property.
[15] The trial judge based on the evidence adduced and the expert
opinion of PW 5 dismissed the defences of the defendants including
that of D3.
[16] Against that decision and judgment given, all three defendants
had appealed to the High Court.
[17] This appeal coming up in this Court is only with respect to the
appeal by D3 as appellant. The other appeal by D1 and D2 is before
another High Court and had not been disposed of when this appeal
was heard.
[18] It was agreed by counsel for both parties that this appeal can be
heard independently of the defendants landowners’ appeal.
5
[2019] 1 LNS 1380 Legal Network Series
Principles
“…The rule that you are to love your neighbour becomes in law,
you must not injure your neighbour; and the lawyer’s question,
Who is my neighbour? receives a restricted reply. You must take
reasonable care to avoid acts or omissions which you can
reasonably foresee would be likely to injure your neighbour.
Who, then, in law is my neighbour? The answer seems to be
— persons who are so closely and directly affected by my act
that I ought reasonably to have them in contemplation as
6
[2019] 1 LNS 1380 Legal Network Series
[22] I have no difficulty in holding, as the trial court had held, that
D3 owed a duty of care in carrying out the construction works to the
property of the defendants owners in such a manner as not to cause
damage to the plaintiffs’ adjacent and adjoining property.
[23] Learned counsel for the plaintiffs referred to the scope of duty
of care as well established in the Federal Court case of Arab-
Malaysian Finance Bhd v. Steven Phoa Cheng Loon & Ors and other
Appeals [2003] 1 MLJ 567 where in the context of the duty owed by
one property owner to another adjoining property owner it was
observed as follows at page 579:
7
[2019] 1 LNS 1380 Legal Network Series
8
[2019] 1 LNS 1380 Legal Network Series
[38] The Federal Court in Lok Kok Beng & 49 Ors v. Loh Chiak
Eong & Anor [2015] 4 MLJ 734;; [2015] MLJU 261;; [2015] 7
CLJ 1008 citing with approval the House of Lord’s decision in
Caparo Industries plc v. Dickson [1990] 2 AC 605, held that the
elements giving rise to a duty of care are foreseeability,
proximity and policy consideration. Zainun Ali FCJ held that:
[28] It is not necessary for this Court for the purpose of this appeal
to consider whether the nature of the construction works carried out
by D3 was one necessarily attended with risk such that the defendants
owners cannot free themselves from liability. In a case where there is
attendant risks involved the defendants owners would not be able to
free themselves from liability and indeed would be held to be jointly
liable with their independent contractor as joint-tortfeasors.
10
[2019] 1 LNS 1380 Legal Network Series
12
[2019] 1 LNS 1380 Legal Network Series
[32] Learned counsel for the plaintiffs submitted that the negligence
of D3 consisted of the following precautions that were not taken to
ensure that the integrity of the existing foundation of the plaintiffs’
property was not compromised as explained by the plaintiffs’ expert
witness in PW 5:
13
[2019] 1 LNS 1380 Legal Network Series
[33] The trial judge was satisfied that PW 5 was eminently qualified
to give his opinion on matters of geotechnical engineering especially
with respect to pre-war buildings, having published his research on
this subject and she had accepted the expert report of PW 5. His PhD
was in Civil and Structural Engineering from the University of
Sheffield and he had published in Majalah Akitek in June 1976 his
research article on “Old Row Houses In Peninsular Malaysia where he
had described and explained the features of old row houses. His
Expert Report dated 9.5.2017 covered the following:
[34] D3 had not called any expert witness to contradict the evidence
of the plaintiffs’ expert witness in PW 5.
14
[2019] 1 LNS 1380 Legal Network Series
[35] The trial court had found that the works done by D3 consisted of
Demolition Works, Hoarding Works and Piling Works from the
breakdown of the contract sum of D3. The Demolition Works included
demolishing the existing timber staircase, reinforced concrete floor
slabs, columns, beams, sub-structure works, demolishing half brick
wall, hacking off existing floors and that these were done using
demolition machinery and hammer backhoe. The Piling Works were
by way of micro-piling.
[36] All that D3 said was that they had not breached their duty of
care for they had complied with the Architect’s and Engineer’s
directions and instructions and the conditions laid down by DBKL.
The Architect was Tetuan Meor Architect and the consultant Engineer
was one Ir Azlina from Experts Engineers Sdn Bhd. The defendants
did not call the Architect to testify.
15
[2019] 1 LNS 1380 Legal Network Series
16
[2019] 1 LNS 1380 Legal Network Series
[44] It was submitted by learned counsel for D3 that since DBKL had
issued the Certificate of Completion and Compliance (“CCC”) to the
defendants owners’ property after the works, it must mean that all the
works approved had been properly carried out.
[46] After all a CCC is issued primarily to certify that the property
on which works had been done had complied with the plans submitted
and approved by DBKL.
[47] The plaintiffs also stressed that the defendants and in particular
D3 had demolished the building without proper propping or shoring
works which would be required as explained by PW 5.
17
[2019] 1 LNS 1380 Legal Network Series
[50] The expert witness, PW 5, had observed and concluded that the
new foundation is erected separate from the foundation of the
plaintiffs’ property wherein the micro-pile is situated at least half
(1/2) a meter away from the Party Wall. The placement of the new
micro-pile foundation (which is further away from the existing Party
Wall) along with the absence of propping and shoring had caused the
plaintiffs’ property, which is a corner lot, to become a standalone
building, thereafter allowing it to tilt and rotate away from the
adjacent property (Lot 4 and 6). In fact, a gap exists between the
original Party Wall of the plaintiffs’ property and the newly
constructed Party Wall of the adjacent property. There is also the
worrying problem of the seepage of water resulting from this said gap
which has yet to be fixed.
[52] D3 had not been able to refute that all of the damage sustained
by the plaintiffs’ property as stated above evidently arose from the
incompetent execution of construction works by D3. The defendants’
witnesses were themselves D1 and D2 as DW 1 and DW 2. DW 3 who
is the husband of D2 also gave evidence. D3 called DW 4 their
contractor and DW 5 the Engineer.
18
[2019] 1 LNS 1380 Legal Network Series
[55] In any event the nature and position of the cracks that were
complained of by the plaintiffs were evidently fresh cracks that were
aggravated by further works of D3. At page 974 of the Appeal Record
D3 had by their letter of 27.11.2014 admitted that the cracks at the
kitchen of the plaintiffs’ building were caused by them.
[57] In any event their termination did not affect their liability
eventhough the cracks may surface later.
[58] The nature of the damage caused was something that was
foreseeable and indeed D3 had taken out an insurance policy to cover
for such damage or loss arisen therefrom.
19
[2019] 1 LNS 1380 Legal Network Series
[60] The trial judge had found as a matter of fact that the plaintiffs’
property was safe, stable and in sound condition from the evidence
and photographs produced by PW 1 and PW 4 who had themselves
taken the photographs. The comparison had been set out at the trial
between the photographs pre and post demolition and reconstruction.
There was no evidence of the time stamp in the photographs having
been tampered with as suggested by the defendants. Bearing in mind
that he who alleges must prove under section 101 Evidence Act 1950
(“EA”) and more so when the other party cannot prove a negative that
the photographs had not been tampered with, D3 had not discharged
this burden. See the Federal Court in Letchumanan Chettiar
Alagappan @ L Allagappan (as executor to SL Alameloo Achi alias
Sona Lena Alamelo Acho, deceased) & Anor v. Secure Plantation Sdn
Bhd [2017] 4 MLJ 697 where it was held that the burden of proof lies
with the party who seeks to adduce a fact, as the other party is unable
to prove a negative.
20
[2019] 1 LNS 1380 Legal Network Series
[66] At any rate this is a fit case for application of the egg-shell
principle which was applied in a case not very dissimilar to the
present case in Cheong Fatt Tze Mansion Sdn Bhd v. Hotel
Continental Sdn Bhd (Hong Hing Thai Enterprise Sdn Bhd, third
party) [2011] 4 MLJ 354 where the High Court Judge Chew Soo Ho
JC (as he then was) held at page 372 to 375, paragraph 28 to 32 as
follows:
21
[2019] 1 LNS 1380 Legal Network Series
22
[2019] 1 LNS 1380 Legal Network Series
[29] In the instant case, the defendant was well aware of the
possibility or probability of damage to the mansion which had
non- reinforced walls from the concern expressed by PW1 to
DW1 which the defendant ought to endorse that they had been
fore-warned. Foreseeability of damage on the defendant, to this
court, is proved by the plaintiff as defendant ought to have so
anticipated since their attention had been drawn to the non-
reinforced structure of the mansion that hammer-driven piles
system with its excessive vibrations might likely cause damage
to the mansion. The defendant’s contention, principally is
that the mansion itself is century old; it is fragile and
vulnerable. Hence the cracks and/or damages had or would
have occurred as a matter of course. Defence also contended
that the cracks as appeared were superficial, with dirt marks and
traces of fungus and produced several photographs of the cracks
which as submitted by the plaintiff were actually cracks on the
boundary wall and not cracks on the plaintiff’s mansion. Such
contention is unsubstantiated under the thin skull rule above.
Having been fully aware of the fragility of the mansion, all
the most defendant ought to exercise more care to avoid any
probable and foreseeable damage. On the defence’s claim of
reasonable user of land, plaintiff contended that there can be no
defence to actionable nuisance when damage was caused to the
mansion by the hammer-driven piling system used by the
defendant. The English case of Hoare & Co v. McAlpine [1923]
23
[2019] 1 LNS 1380 Legal Network Series
24
[2019] 1 LNS 1380 Legal Network Series
[69] The trial judge found as a matter of fact that the quotation of
RM625,585.40 given by PW 2 from Lembina Bina Sdn Bhd is
reasonable with the expert witness PW 5 stating that if at all, it is
probably on the lower side as in being under-quoted.
[71] The defendants and that included D3 had not produced evidence
of an alternative quote. Like all quotes they are based on an
estimation. PW2 had concluded the calculation for the damages
sustained by the plaintiffs’ property and the amount of monies
required to conduct the necessary repairs based on the engineer’s
requirements, the owners’ list of damage and also his own past
experience. See generally the factors to be considered with respect to
reinstatement of damaged property and the cases referred to in the
Court of Appeal case of Milik Perusahaan Sdn Bhd & Anor v.
Kembang Masyur Sdn Bhd [2003] 1 MLJ 6 at page 12 where it was
observed as follows:
25
[2019] 1 LNS 1380 Legal Network Series
Since this case was decided in the High Court, the question
of the correct measure of damages in circumstances such
as those now before us was considered by May J in CR
Taylor Ltd v. Hepworths Ltd. Among the passages cited
with approval in the judgment in that case is the following
from McGregor on Damages (13 th Ed – 1972) at para 1061:
26
[2019] 1 LNS 1380 Legal Network Series
[72] PW 2 had explained that when he went to visit the site, he did
examine the amount of work required and the manner of repairing the
damage. PW 2 also further justified the amount by explaining to the
Sessions Court Judge roughly what was included in each item in the
said quotation.
28
[2019] 1 LNS 1380 Legal Network Series
[76] I accept the fact that the damages assessed should fall more
appropriately under general damages rather than special damages as
no payments had been incurred or made out yet. It is a matter of
nomenclature and does not affect the substance of the claim in terms
of the damages assessed.
[77] Surely D3 is not saying that until the repair and rectification
work had been done there is no basis for the plaintiffs to make their
claim for damages.
[78] There may be many reasons why repair and rectification had not
commenced yet and the lack of funds would be one reason for already
costs had to be incurred in commencing this suit in the Sessions
Court, not to mention the costs of engaging an expert and also to
resist this appeal and the appeal by the defendants owners.
[79] To say that the plaintiffs cannot make a claim until they have
the funds and incurred the costs of the repair might be to wait until
limitation setting in. It would be a double blow for the injured party.
[80] That has not been the position of the law. In the Singapore High
Court case of Afro-Asia Shipping Company (Pte) Ltd v. Da Zhong
29
[2019] 1 LNS 1380 Legal Network Series
Investment Pte Ltd & Others [2004] 2 SLR 117, the plaintiff’s
building had tilted, cracks had developed, floors had sunk and seepage
of water had occurred because of works done in the 1 st defendant’s
land when it constructed a building on its land called Robinson
Centre. When the plaintiff sued the 1 s t defendant and other defendants
being the consultants and contractors who worked on the building for
negligence and claimed based on a quotation of the rectification
works, it was argued that as the amount had not been incurred yet then
the plaintiff would only be entitled to mere nominal damages. Her
Ladyship Judith Prakash J (now JA) followed a simple common
sensical approach when she observed as follows:
Pronouncement
31
[2019] 1 LNS 1380 Legal Network Series
[86] The decision of the trial judge with respect to D3 was affirmed
and thus the appeal of D3 was dismissed with costs of RM10,000.00
and allocator shall be paid before extraction of the order of the Court.
COUNSEL:
For the appellant - Nur’ Izzah Mohd Tahir; M/s Zainul Rijal Talha &
Amir
32
[2019] 1 LNS 1380 Legal Network Series
Arab-Malaysian Finance Bhd v. Steven Phoa Cheng Loon & Ors and
other Appeals [2003] 1 MLJ 567
Mestika Bistari Sdn Bhd & Anor v. Telekom Malaysia Bhd [2018] 1
LNS 373
Charles Dalton Appellant; And Henry Angus & Co. Respondents. The
Commissioners Of Her Majesty's Works And Public Buildings
Appellants; And Henry Angus & Co. Respondents [1881] 6 App. Cas.
740
Mehrzad Nabavieh & Anor v. Chong Shao Fen & Anor and another
appeal [2016] 3 MLJ 500
Cheong Fatt Tze Mansion Sdn Bhd v. Hotel Continental Sdn Bhd
(Hong Hing Thai Enterprise Sdn Bhd, third party) [2011] 4 MLJ 354
Milik Perusahaan Sdn Bhd & Anor v. Kembang Masyur Sdn Bhd
[2003] 1 MLJ 6
Tenaga Nasional Berhad v. Ichi-Ban Plastic (M) Sdn Bhd and other
appeals [2018] 3 MLJ 141
33
[2019] 1 LNS 1380 Legal Network Series
34