You are on page 1of 22

AIAA 2001-3825

Page 1
DESIGN AND MANUFACTURE OF AN
OXIDIZER TANK ASSEMBLY

Walter H. Tam, Mark D. Drey


Pressure Systems, Inc.
and
Donald E. Jaekle Jr.
PMD Technology
and
Laurie W. Larsson
Orbital Sciences Corporation

ABSTRACT qualification-by-similarity analysis was


performed to validate the tank shell. A
An oxidizer tank assembly is required for a protoflight test program, including vibration
new commercial spacecraft. This tank must testing, was performed on the first flight tank.
provide gas-free expulsion of oxidizer
propellant in a low gravity environment. An INTRODUCTION
internally mounted surface tension propellant
management device (PMD) is utilized to In 1999 Pressure Systems Inc. (PSI) was
achieve this goal. The vane-sponge type contracted to provide a full complement of
PMD, constructed of titanium, was custom propulsion system tanks1 for a new-generation
designed for the spacecraft mission. commercial geosynchronous communications
satellite. The spacecraft utilizes dual mode
To minimize cost, an existing tank shell was propulsion system, and new hydrazine fuel
selected as baseline design and slightly and nitrogen tetroxide oxidizer tanks were
modified for the mission. No modification was developed.
done to the tank membrane to maintain
qualification-by-similarity. The propellant tank The new nitrogen tetroxide oxidizer tank is
shell is constructed of solution treated and designed to store nitrogen tetroxide propellant
aged (STA) 6AL-4V titanium alloy. This and gaseous helium pressurant, and provides
material provides excellent strength to weight the oxidizer to a complement of bipropellant
characteristics and is widely used in the thrusters via propellant manifolds during the
aerospace industry for its excellent material three-axis stabilized velocity increment from
properties and manufacturability. The PMD is geotransfer to geosynchronous orbit. The tank
constructed of annealed 6AL-4V titanium and operates under pressure regulated mode. A
commercially pure titanium material. custom-designed, multi-element, internally-
mounted surface tension propellant
Stress and fracture mechanics analyses were management device (PMD) ensures gas-free
performed to validate the tank shell for the expulsion of propellant upon demand in this
spacecraft mission. PMD performance low gravity environment. A sketch of this tank,
analysis was conducted to design the PMD. with an outline of the PMD, is shown in Figure
Qualification testing was not required, but a 1. Two tanks are required per spacecraft.

Page 2
Figure 1: Oxidizer Tank Assembly

The propellant tank specification requirements are listed below in Table 1:

Table 1: Propellant Tank Assembly Design Requirements

Parameters Requirements
Operating Pressure MEOP is 300 psia @ 50°C (122°F), 50 cycles
Proof Pressure 375 psia @ 50°C (122°F), 12 cycles
Burst Pressure 450 psia minimum @ 50°C (122°F),
Material of Construction Membrane: 6Al-4V titanium, solution treated and aged
Inlet/outlet ports: 3Al-2.5V titanium
PMD: CP and 6Al-4V titanium
Expulsion Efficiency 99.79% minimum for depletion during LAE firing
99.60% minimum for depletion during DMT firing
Propellant Weight 492 lbm (223.2 kg) maximum nitrogen tetroxide
Propellant fill fraction 65% minimum, 95% maximum
Tank Capacity 9712 in3 minimum
Internal dimension 21.25” ID x 34.69” long
Overall Length 41.50”
Tank Weight 20.0 lbm maximum
Propellant Nitrogen tetroxide
Fluid Compatibility N2O4, GAr, GHe, GN2, D.I. water, Isopropyl alcohol
Shell Leakage <1x10-6 std cc/sec He @ 300 psia
Natural Frequency > 75 Hz in lateral direction
> 62 Hz in thrust direction
Failure Mode Leak Before Burst
On-Orbit Temperatures 50 to 122 °F (10 to 50 °C)
Shelf Life 3 years minimum
On Orbit Life 15 years minimum

Page 4
To minimize the overall program cost, an • Temperature environment;
existing, flight qualified tank shell was selected • Material properties, STA titanium;
as the baseline design, and modified to meet • Material properties, annealed titanium;
the specification requirements. This is a • Volumetric requirements;
popular design approach2 widely used by PSI • Mass properties of tank shell material;
to maximize value and minimize cost. The
cost reduction is the result of (1) eliminating • Mass properties of fluid;
the need to fabricate a qualification tank, (2) • Fluids used by the tank;
eliminating the need to conduct a weld • Tank pressurization history;
development and qualification program, (3) • External loads;
eliminating the need to conduct a qualification • Girth weld offset and weld suck-in;
testing program, and (4) minimizing the
number of new engineering drawings, shop • Size of girth weld bead;
travelers, and NC programs, and (5) • Resonant frequency;
maximizing the use of existing tooling. This • Tank boundary conditions;
design approach also provided schedule • Residual stress in girth weld;
assurance to the customer. However,
• Load reaction points; and
conservatism was still exercised, and
complete stress and fracture mechanics • Design safety factors.
analyses were conducted to validate the tank
shell in the new operating environment. A This stress analysis validated the use of the
Qualification-by-Similarity (QBS) report was existing tank shell design, plus the modified
generated to document the QBS status. mounting features, for the new mission
requirements. The analysis dynamic model
All completed flight tanks require acceptance provided predictions on the first resonant
testing prior to delivery. Because the frequencies of the tank. The responses are
qualification testing was eliminated, the first shown below:
flight tank was subjected to protoflight vibration
testing. Both acceptance and protoflight Figure 2: First axial (Z) response
testing include tank shell integrity verification
and PMD functional testing.

TANK ANALYSES

The tank analyses included stress analysis


and fracture mechanic analysis for the tank
shell, stress analysis for the PMD, and the
PMD performance analysis. Since the PMD is
completely enclosed within the tank shell, by
definition a fracture mechanics analysis is not
required for the PMD. All analyses used
assumptions, computer tools, test data and
experimental data utilized on a majority of the
pressure vessels and PMD’s successfully
designed, fabricated, tested and qualified
during the past three decades. Conservatism
was used throughout the analysis process,
and the worst case scenarios were analyzed.

TANK SHELL STRESS ANALYSIS

A stress analysis was performed to establish


that the tank meets the oxidizer tank
specification requirements. The analysis took
into consideration the requirements such as:

Page 5
Figure 3: First lateral (X) response The analysis concluded with positive margins of
safety for all design parameters, as summarized
in Table 2.

Table 2: Propellant Tank Safety Margins

Characteristics M.S.
Pressurant sphere, proof, yield +0.19
Pressurant sphere, burst, ultimate +0.09
Cylinder, proof, yield +0.17
Cylinder, burst, ultimate +0.05
Weld, proof, yield +0.17
Weld, burst, ultimate +0.07
Side boss, external load, yield >0.23
Side boss, external load, ultimate >0.17
Shell buckling, external load +3.21
Weld, external load, yield +2.10
Weld, external load, ultimate +2.00
Outlet/inlet tube, yield +10.50
Figure 4: First lateral (Y) response
Outlet/inlet tube, ultimate +6.60

TANK SHELL FRACTURE MECHANICS


ANALYSIS

A fracture mechanics analysis was performed


to establish whether the growth of an initial
flaw in the anticipated cyclic and sustained
pressure environment may cause a failure in
the tank shell. The analysis was performed
using external and internal stresses from the
stress analysis, and using NASA/FLAGRO
with minimum thicknesses as parameters.
Special fracture critical dye-penetrant and
radiographic inspections are required to detect
flaws. The minimum flaw size that can be
detected by such special fracture critical
inspections was used as initial flaw size for
this fracture mechanics crack propagation
analysis. The analysis was performed at:

• Girth welds and heat affected zones;


• Maximum pressure stress location in the
hemisphere;
• Maximum stress location in the cylinder;
• Maximum stress location in the cylinder
side boss;

Page 6
• Maximum stress location in the PMD PERFORMANCE ANALYSIS AND
hemisphere/cylinder transition; PMD DESIGN
• Intersection between the hemisphere and
A comprehensive PMD performance analysis
the pressurant boss;
was performed to design and validate the
• Intersection between the hemisphere and PMD. The passive, all titanium, surface
the propellant boss; and tension propellant management device was
• Maximum external load stress in the designed to provide gas-free hydrazine
hemisphere near the pressurant and the delivery throughout the spacecraft mission. As
with most PMD’s, this PMD was designed
propellant bosses. specifically for the spacecraft mission. The
PMD is designed to (a) survive spinning
The fracture mechanics analysis established operations, (b) provide gas free propellant
the leak-before-burst (LBB) characteristics of delivery throughout mission, including system
the propellant tank. This analysis concluded priming, LAE ignition, and LAE steady state
that the existing tank shell meets all the firing, and (c) retain residual propellant in the
fracture mechanics requirements. The special aft end of the tank to prevent on orbit slosh
NDE requirement established by this fracture and CG migration.
mechanics analysis include:
• Special fracture critical dye-penetrant on The PMD was designed to be installed into the
tank shell outlined in Figure 1, with 10.625-
all surfaces; and
inch radius hemispherical heads and a 13.44-
• Special fracture critical radiograph on inch cylindrical center section. It was
welds. designed for use with nitrogen tetroxide
oxidizer. Additional features were
These requirements were instituted as part of incorporated into the design to provide optimal
the tank fabrication requirements. service. First, because the PMD is a passive
device with no moving parts, the design is
PMD STRESS ANALYSIS inherently reliable. Second, the design is
constructed entirely of titanium. Thus the
A PMD stress analysis was also performed to PMD is lightweight and offers exceptional
validate the structural integrity of the PMD compatibility, long life, and reliability. Finally,
design. The analysis took into consideration the PMD was designed not only to provide
design requirements such as material propellant during steady flow conditions but
properties, fluid properties, vibration loads, also to allow some operation in some off
and design safety factors. The PMD stress design conditions, thus providing additional
analysis concluded with positive margins of operational safety.
safety for all design parameters, as
summarized below: A sketch of the PMD is provided in Figure 5.
The key components of this PMD are:
Table 3: PMD Safety Margins 1) The Sponge,
2) The Geysering Limiting Baffle,
Characteristics M.S. 3) The Trough & Pick Up Assy, and
4) The Perforated Sheet.
Vane, Flexible, yield +0.28
Vane, Rigid, yield +0.15 All PMD components are located over the tank
outlet.
Pickup assembly, yield +0.09
Top plate, yield +0.30 The sponge: The sponge consists of 24
radial titanium sheet metal panels extending
Solid vane in trough, buckling +1.80
from the central support cylinder. The panels
Half dome cover, yield +0.51 are attached to the center post as well as the
geyser limiting baffle. Each panel is 2.5
Center post, fluid loads, yield +3.17
inches high and is positioned 0.75 inches
Center post, random vib, lateral, yield +1.98 above the pick up assembly to allow space for
the trough and to allow gas to be rejected

Page 7
from under the sponge during zero g. The inch of the tank shell and to within 0.1 inch of
radial sponge panel position creates a the pick up assy. These extended panels limit
tapered gap between panels that ejects gas in propellant motion from one side of the sponge
zero g and retains propellant during lateral to the other during despin. For this reason,
thruster firing. these two panels are solid. The other 22
panels are perforated to allow cross flow and
22 of the 24 panels extend to within 0.75 and reduce metal mass.
1.25 inches of the tank wall at the base and
top of the sponge panels respectively. This The thickness of the titanium sponge panels
tapered gap aids gas bubble rejection in zero is determined by structural analysis and does
g. The other two panels extend to within 0.1 not affect the PMD functional properties.

Figure 5: PMD Configuration

Page 8
The Geysering Limiting Baffle: On top of PMD OPERATIONS
the sponge is a geyser limiting baffle that
consists of a 7.5-inch diameter plate designed The Oxidizer Tank PMD is designed to
to limit axial flow near the tank centerline. This provide gas free propellant to the tank outlet
limits geysering near the sponge. The plate is throughout the mission. During ground
designed to support the sponge panels as operations, the PMD is designed to enable
well. The baffle is partially perforated with tank filling, tank handling, and tank draining.
large holes for the purpose of weight During launch, the PMD does not function and
reduction, but still offers sufficient solid area to is designed to maintain propellant over the
limit geysering. perforated sheet and not be adversely
affected by the launch conditions
The thickness of the baffle is determined by encountered. During the final stages of
structural analysis and does not affect the ascent, the spacecraft is spun up to 60 rpm
PMD functional properties. during which a large solid rocket upper stage
motor is fired (AKM Firing). Subsequently,
The Trough & Pick Up Assy: Below the the spacecraft is despun without using any
sponge is a trough that retains liquid over the NTO. During the despin operations, a flat
pick up window during the high Z axis spin spin may be encountered and the PMD is
phase of the mission. The trough is a semi- designed to survive flat spin with no
cylindrical housing with a sloped top. The compromise in future PMD operations. The
opening to the trough is inboard (on the trough PMD is designed to provide gas free
diameter) and 0.7 inches high. The slope in propellant to the tank outlet subsequent to the
the top of the trough is designed to push gas spinning operation. The primary use of the
bubbles out of the trough during zero g coast. PMD is to provide gas free NTO during the
Inside, and bisecting, the trough is a fin which three axis stabilized ascent following launch.
limits the cross flow within the trough. In addition, the PMD is designed to retain
residual propellant in the aft end of the tank
Below the trough is the pick up assembly while on orbit – thus preventing any significant
containing an off axis, perforated sheet CG shift due to NTO movement.
covered window. The window flow area is
2.07 in2 nominal and 1.83 in2 minimum. The FLOW PATH THROUGH THE PMD
window location is a minimum of 2.5 inches
from the trough entrance and 4.3 inches from The flow path through the PMD is illustrated in
the propellant surface during the 60 rpm spin. Figure 6. The propellant flows between and
The perforated sheet has 0.008 inch maximum around the sponge panels to the trough
diameter electron beam drilled holes on a 2:1 entrance. The trough entrance is inboard and
approximate spacing to hole diameter on a 60 propellant access outside the trough entrance
degree array. The pick up assembly provides is uninhibited by the sponge panels – all but
a flow path from the perforated sheet to the two are elevated above the trough. A solid
propellant outlet. metal fin bisects the trough, forcing propellant
to flow to the perforated window on either side
The Perforated Sheet: The perforated sheet of the trough and preventing propellant from
is located over the tank outlet, inside of the flowing from one side of the trough to the
trough. This is the only location of a porous other. Once propellant passes through the
capillary barrier in the PMD design. This PMD pick up assy perforated sheet window, it flows
contains no screen. The perforated sheet was freely to the tank outlet. The perforated sheet
chosen to have low flow losses while window is the only capillary barrier to gas
maintaining a bubble point in excess of twice within the PMD. This PMD is designed to
the loads applied. The perforated sheet is minimize flow losses. The maximum flight
fabricated from titanium sheet with electron flow loss through the PMD, including the
beam drilled holes a maximum of 0.008 inches outlet region, is calculated to be less than
in diameter. The open area is approximately 0.04 psid (except at depletion where the sheet
22% of the total area. bubble point of 0.08 psi will raise the flow loss
to 0.12 psid).

Page 9
Figure 6: Flow Path Within the PMD

GROUND OPERATIONS fill conditions, a small bubble may exist. This


gas is compressed significantly during
The ground operations can be divided into pressurization and is likely to be dissolved into
three parts; filling, handling, and draining. the unsaturated propellant. In any case, the
These are important not only from a flight gas quantity is too small to be a concern. The
standpoint but also from a testing standpoint. filling process is straightforward and should
One must be able to fill the tank in a introduce no difficulties either to the technician
reasonable time when following a standard or to the PMD.
procedure. Similarly, handling and ground
draining must be accomplished without Handling: Typical handling occurs with the
excessive effort. Figure 7 shows these ground tank in the outlet down position. The tank can
operations. be tilted significantly before gas will come into
contact with the perforated sheet. Gas will not
Filling: Filling occurs with the tank upright in enter the pick up assembly during handling
the outlet down position. The tank is at because the PMD itself will act as a baffle
atmospheric pressure when propellant is preventing gas from reaching the perforated
introduced into the tank through the propellant sheet. Additionally, the slosh amplitude
outlet line. During the filling process, a small required to compromise the PMD functional
quantity of gas may be trapped under the design is so large that it is unlikely gas will
perforated sheet window. Nominally, no gas come in contact with the perforated sheet.
should be trapped. But assuming worst-case

Page 10
Figure 7: Operational Sequence: Ground Operations

Ground Fill
Ground Handling Ground Drain
Launch

may occur on the pad due to wind induced


Draining: Ground draining may have to be
vortex shedding and showed that gas will not
accomplished with propellants and will be
reach the perforated sheet. In addition, the
necessary with test fluids. The liquid
structural loads on the PMD was determined
remaining in the tank at the end of ground
to be less than the worse-case design load.
draining will have to be evaporated from the
tank, and it is desirable to minimize this
Figure 8 below is a representation of
quantity of liquid. The tank is drained in the
propellant position during ground slosh.
outlet down position. A small tilt may slightly
increase ground drain residuals as liquid is
trapped in a pool near the outlet. The ground Figure 8: Propellant Position During
drain residuals will be minimized by preventing Ground Slosh
significant tilt of the tank assembly during
draining. Ground draining does not present
any difficulties.

Ground Handling and Pad Slosh: The


primary concerns during ground handling are
the capillary integrity of the perforated sheet
and the structural loads on the sponge due to
pad slosh. To provide gas free propellant
demand during the operational phases of
mission, gas must not enter the pick up
assembly through the perforated sheet. If,
during handling or any other mission phase,
the tank is accelerated sufficiently to force gas
through the perforated sheet, that gas will be
ingested into the propulsion system, thus
compromising the performance of the PMD.
The PMD analysis examined the slosh which

Page 11
ASCENT OPERATIONS to upright ground handling, there is no danger
of gas ingestion into the outlet pick up
Ascent operations can be divided into five assembly. Slosh during launch does not
stages: launch, 60 rpm spinning, AKM firing, provide a force large enough to drive gas into
despin, and, possibly, flat spin. The PMD is the perforated sheet. In addition, the
designed to withstand the structural loads positioning of the trough and sponge above
during these stages of ascent as well as the pick up assy provides a fluid stagnation
prevent gas from penetrating into the pick up region where fluid velocities will always be
assembly. Figure 9 below presents the small. Even if gas were driven down toward
operational sequence of the ascent the pick up assembly by slosh, the sponge,
operations. trough, and the sheet itself will prevent the gas
from penetrating into the pick up assy. Launch
Launch: The PMD is designed to be is illustrated in Figure 7 (similar to ground
launched in the outlet down position. Similar handling).

Figure 9: Operational Sequence: Ascent Operations

5 & 60 rpm Z Axis Spinning AKM Shutdown

5 rpm Flat Spin


Despin

Page 12
Simple Spin: After the initial launch, the Figure 11: Propellant Position After AKM
vehicle is spun up to 60 rpm about a spin axis Firing
parallel to the tank centerline and 30.3 inches
away (inboard of the trough). Oxidizer is not
used to spin up or spin down the vehicle.
During simple spinning, the propellant is
positioned outboard by the centripetal forces.
The propellant interface is cylindrical and the
trough entrance is submerged. Simple
spinning at the minimum fill fraction is
illustrated in Figure 10.

During 60 rpm spinning the main concerns


are: (a) the porous element loads, (b) the
submergence of the trough entrance, (c) the
trough’s ability to accommodate slosh, and d)
the structural loads induced during AKM
ignition and shutdown. The PMD performance
analysis shows that the trough entrance and
the perforated sheet are submerged in the
propellant and gas exposure is not possible,
and the slosh load is not an issue.
AKM Shutdown: At AKM shutdown,
Figure 10: Propellant Position During propellant slosh will result. Propellant can
Simple Spinning move away from the outlet region during this
slosh as illustrated in the operational
sequence. Gas is prevented from reaching
the perforated sheet by the trough, which
keeps the window buried in propellant. Figure
12 shows the propellant position during AKM
shutdown.

Figure 12: Propellant Position during


AKM shutdown

AKM Firing: While the vehicle is spinning at


60 rpm, AKM firing occurs producing a large
axial acceleration. The propellant reorients in
the tank with the surface a paraboloid of
revolution. Propellant access is not required
during AKM firing but is possible with this
PMD. The propellant motion created by the
high g environment causes high loads on the
PMD sponge. The sponge is designed to
accommodate these loads. Figure 11 shows
the propellant position after AKM firing.

Page 13
Despin: After AKM firing, the vehicle is Figure 14: Propellant Position During a
despun from 60 rpm to between 0 and 5 rpm Transition to Flat Spin
very rapidly. The tangential acceleration
created by the rapid depin is large and the
propellant will move laterally in response to the
acceleration. The PMD is designed to prevent
any gas from reaching the perforated sheet
window during depin. Despin is illustrated in
the operational sequence. Figure 13 shows
the propellant position at the end of despin.

Figure 13: Propellant Position at the End


of Despin

Separation: After the ascent, the spacecraft


is separated from the last launcher stage and
the spacecraft spun down to a 0.1 rpm Z axis
spin. No oxidizer is required for this despin.

ORBITAL OPERATIONS

System Priming: System priming of the


oxidizer tank will occur while the spacecraft is
spinning about its axis at up to 0.1 rpm. This
is the first demand from the oxidizer tank. In
the absence of the 0.1 rpm rotation, the gas in
the tank resides in a free floating spherical
5 rpm Spin: Following despin and after bubble. The bubble is maintained away from
separation from some launch vehicles, the the trough entrance by the sponge. With a 0.1
spacecraft is spinning about the Z axis at up to rpm rotation, the bubble will be buoyed
5 rpm. At 5 rpm, the propellant location is inboard and slightly flattened by the centripetal
identical to 60 rpm spinning. 5 rpm Z axis spin acceleration. The bubble is free to move
is illustrated in the operational sequence in axially within the tank cylindrical section, but
Figure 9. away from the trough entrance. The liquid-gas
surface is not a cylinder in shape due to the
Flat Spin: It is possible that the spacecraft surface tension forces present. When oxidizer
could enter a flat spin. The propellant will is demanded during system priming, no gas
continue to submerged the trough entrance will be ingested into the PMD due to the large
and the perforated sheet will not be exposed distance between the bubble and the trough
to gas since at 5 rpm, the perforated sheet can entrance and the distance between the trough
easily keep the gas from penetrating into the entrance and the perforated sheet window.
pick up assy. 5 rpm flat spin is illustrated in System priming is illustrated in Figure 15, the
the operational sequence in Figure 9. Figure operational sequence for orbital operations.
14 below shows the propellant position during
a transition to flat spin.

Page 14
Figure 15: Operational Sequence: Orbital Operations

System Priming During 0.1 rpm Z Axis Spin Late Coasts

LAE Ignition LAE Firing Depletion

Steady Lateral Acceleration

Zero g Coast: The system priming oxidizer LAE Ignition: The zero g coast positions
position illustrated in Figure 15 operational shown are also the propellant position at the
sequence is also the zero g coast oxidizer onset of LAE ignition. During the initial phase
position which will occur between each LAE of the LAE burn, oxidizer is reoriented to the
firing. As oxidizer is consumed, the slightly tank bottom by the settling acceleration. Upon
flattened gas bubble will grow larger until it can reaching the bottom of the tank, the propellant
no longer fit within the tank. At this point, the continues its motion – forming a geyser in the
oxidizer in the upper hemisphere will no longer middle of the tank. The sponge is designed to
be contiguous with the oxidizer within the provide propellant during this ignition transient
sponge. The sponge is designed to retain the and the geyser limiting baffle above the
oxidizer needed for LAE ignition. Later in sponge is designed to prevent the geyser from
mission zero g coast is illustrated in Figure 15. stripping the sponge of its propellant. LAE

Page 15
ignition is illustrated in Figure 15. Figure 16 tank outlet during the required conditions until
shows an LAE firing at 30% fill fraction. the fill fraction of the tank falls below 0.5%
(0.1% is the goal). Depletion is illustrated in
Figure 16: Propellant Position at 30% the Figure 15 operational sequence.
Fill Fraction
At the end of the final LAE firing (and the last
use of propellant), up to 9.44 lbm of oxidizer
could reside in the tank. The PMD is designed
to prevent this propellant from migrating within
the tank during lateral thruster firings, which
produce a maximum acceleration of 0.00037
g. The last illustration in the operational
sequence of Figure 15 shows the propellant
held within, and around, the sponge during this
lateral acceleration. The propellant moves off
the tank centerline but is retained in the aft
end of the tank by the surface tension forces
within the sponge. See Figure 17.
Initial Condition Geyser Formation
Figure 17: Propellant Position at
LAE Firing: As the LAE firing continues,
propellant is settled over the outlet by the main
engine acceleration. The acceleration is
sufficiently high to produce a flat propellant
surface in the tank with surface tension effect
limited to within an inch of two of the tank wall.
Propellant access is straightforward as
propellant flows between, through and around
the sponge panels to the trough entrance.
From the trough entrance, the propellant flows
directly to the perforated sheet, into the pick
up assy and out the tank outlet. LAE steady
firing is illustrated in the operational sequence.

Depletion: During the last LAE firing, Depletion


depletion can occur. Propellant is settled as
described above and access straight forward. TANK SHELL DESIGN HERITAGE
As propellant is consumed, the liquid surface
falls until the tough entrance is exposed to This oxidizer tank is a derivative of an existing,
gas. The surface tension effects will prevent flight qualified tank. It belongs to PSI’s family
gas from entering the trough until nearly all the of 21.2-inch diameter propellant (diaphragm
propellant outboard of the entrance is and PMD) tank product line. See Figure 18.
consumed. Finally, the trough propellant is The QBS is based on similarity to PSI P/N
consumed and the perforated window is 80390-1, 80394-1, 80405-1, and 80406-1, all
exposed to gas. When sufficient area is of which have similar tank shells.
exposed, the flow losses will exceed the Modifications are limited to the propellant and
bubble point and gas will be drawn into the pressurant ports, the side mount, and the
pick up assy. Since there are no other barriers internal PMD. The PMD in this tank is more
to gas, this marks depletion. Residual sophisticated than the PMD’s in its
propellant can be found in the sponge, in the predecessor tanks and offers significantly
trough, and within pick up assy. The PMD is more capabilities.
designed to provide gas free propellant to the

Page 16
Figure 18: Propellant tank heritage.

80390-1 80394-1

80405-1, -101 80406-1, -101

80426-1
TANK FABRICATION

The oxidizer tank shell consists of two


hemispherical heads and a cylindrical center
section. All three shell components are
machined from 6AL-4V titanium alloy forgings.
All raw forgings have annealed properties at
time of receipt. Each forging is rough
machined, solution treated and aged, and
finish machined to the tank shell thickness as
required by the stress analysis. The solution
heat treat process increases the strength of
the titanium alloy, thus minimizing the weight Figure 20: A Machined Head, ID
of the tank shell. The excellent strength to
weight property, coupled with its
manufacturability, make this titanium alloy the
material of choice for aerospace application.
Figures 19 and 20 show a machined
hemispherical head.
Figure 19: A Machined Head, OD

The PMD is installed on the propellant


hemisphere over the propellant outlet. PMD
installation is performed in two phases. Phase
1 installs the trough assembly (Figure 21) over
the propellant outlet. As shown in Figure 22.

Page 17
Figure 21: The Trough Assembly

Figure 22: The Trough Assembly


Installed Over the Propellant Outlet

Two girth welds are required to assemble the


tank. The first weld joins the propellant
hemisphere and the cylindrical center section.
See Figure 25.

Figure 25: The Welded Propellant


Hemisphere and Cylinder

Phase 2 is the installation of the completed


sponge assembly (Figure 23) over the trough
assembly, see Figure 24.

Figure 23: The Sponge Assembly

The second girth weld joins together the


hemisphere/cylinder assembly to the
pressurant hemisphere to complete the tank
closure. See Figure 26.
Figure 24: The Sponge Assembly
Installed Over the Trough Assembly Figure 26: The Propellant Tank Closure
Weld

Page 18
Both girth welds are subjected to radiographic
and dye penetrant inspections. After closure
the tank assembly is stress relieved in a
vacuum furnace to remove residual stress
from the weld operations. After the completion
of the acceptance tests, the propellant and
pressurant port shear plates are installed prior
to final clean and delivery.

A photograph of a completed tank is shown in


Figure 27.

Page 19
Figure 27: A Completed Oxidizer Tank - Cleanliness
Assembly
Conservatism is exercised throughout the test
program, and all pressure testing is
temperature adjusted for the worst case
operating temperature (50 °C). Pass/Fail
criteria consists of acceptance type external
leak tests and non-destructive evaluations
conducted at intervals throughout the test
program.

Volumetric Capacity Examination: The


capacity of the oxidizer tank is measured
utilizing the weight of water method, using
clean, filtered deionized water as the test
medium. This test is conducted before and
after the proof pressure test to verify that the
proof pressure test does not significantly alter
the tank capacity. A successful validation
indicates that the tank shell is manufactured
properly and that the tank can operate in the
pressure environment under which it was
designed for. Typically, the volumetric growth
after proof pressure test is zero.

TANK WEIGHT The post-proof test capacity examination also


serves to verify that the tank meets the
The propellant tank weight per the designed volume requirement.
specification is not to exceed 20 lbs. The
actual tank weight of the protoflight unit is Proof Pressure Test: The proof pressure test
17.87 lbs. With the addition of 0.94 lbs for the is typically the first pressurization cycle applied
two flex plates, the as-delivered tank weight is to the tank after fabrication. It is intended to
18.81 lbs. Weight savings on a per shipset validate the workmanship by verifying the
basis is approximately 2.4 lbs. strength and integrity of the tank shell. The
test must be conducted in a “safe”
environment to minimize hazards to test
PROTOFLIGHT TEST PROGRAM
technicians. The test is conducted
hydrostatically at proof pressure (375 psia,
The tank shell is qualified by similarity and a
normalized for test temperature) for a pressure
tank qualification program is not required.
hold period of 1 minute minimum.
However, the first flight tank underwent
protoflight testing to verify the tank shell and
Differential Pressure Test: The oxidizer tank
PMD design. Protoflight test consists of the
must meet the pressure drop requirement of
following tests:
not-to-exceed 5.0 psid at a maximum flow rate
- Preliminary examination of 0.1 lbm/sec. The test is conducted by
- Pre-proof volumetric capacity measuring the pressure differential between
- Ambient proof pressure test ullage and the tank outlet while pressuring the
- Post-proof volumetric capacity tank (and the test fluid) through the pressurant
- Differential pressure test port. The measured differential pressure is 4.0
- Protoflight vibration test psid.
- PMD bubble point test
- External leakage test Protoflight Vibration Test: The protoflight
- Penetrant inspection of girth welds vibration test is designed to verify the
- Radiographic inspection of girth welds workmanship of the PMD and the integrity of
- Mass measurement the tank shell. There are only two phases of
- Final visual examination the protoflight vibration testing: wet random

Page 20
and wet sine. All three principal axes are Control accelerometers are placed on the
tested at each phase. The vibration spectrum vibration test fixture near each attachment
is listed below in Table 4. For both wet boss to control energy input. Tri-axial
random and wet sine vibration testing, the response accelerometers are used to monitor
protoflight tank is loaded with 492 lbm of the tank responses. The vibration test setup is
PF5060 performance fluid. The tank is presented in Figure 28.
pressurized to MEOP for all vibration testing.
Typical lateral and axial responses are shown
The vibration test fixture is designed to in Figure 29.
simulate the tank-to-spacecraft installation
interface. The fixture is also sufficiently stiff to
be considered rigid for the test frequencies.

Table 4a: Protoflight Random Vibration Levels

Axis Frequency Range PSD Level (g2/Hz)


(Hz)
X, Y, and Z 20 0.01
20-50 +2.1 dB/oct
50-600 0.01875
600-2000 –1.6 dB/oct
2000 0.01
Overall 5.4 Grms
Duration: 60 seconds per axis
Wet Tank

Table 4b: Protoflight Sine Vibration Levels

Axis Frequency Acceleration Sweep Rate


(Hz) (g)
Spacecraft thrust 4-13.4 0.5 in DA 4 oct/min
(Z)
13.4-50 15.5
50-100 5.0
Spacecraft lateral 4-15.5 0.5 in DA 4 oct/min
(X)
15.5-50 10.6
50-100 4.5
Spacecraft lateral 4-8.4 0.5 in DA 4 oct/min
(Y)
8.4-50 6.8
50-100 3.0

Page 21
Figure 28: Vibration Test Setup

Figure 29: Random Vibration Test Results

Lateral Response Axial Response

Page 22
PMD Functional Test: The tank assembly - Cleanliness
level PMD bubble point test is intended to
verify the PMD performance. Successful CONCLUSION
completion of the PMD bubble point test after
the vibration testing validates the PMD The oxidizer tank assembly has successfully
workmanship. concluded protoflight testing without failure.
The production program is in progress and two
External Leak Test: The external leak test flight tanks have been delivered.
verifies the integrity of the tank shell and also
serves to validate the above vibration testing. The oxidizer tank PMD is specifically designed
The tank is placed in a vacuum chamber, to meet the mission requirements. The PMD
evacuated to under 0.2 microns of mercury, has a simple, robust design and is easy to
and helium pressurized to 300 psia for 30 manufacture. It has been protoflight tested
minutes. The helium leak rate cannot exceed and shows excellent strength, durability, and
1 x 10-6 std cc per second after a 10-minute reliability.
stabilization period.
The oxidizer tank assembly is lightweight, high
Non-Destructive Examination: Following the performance, and easy to manufacture. The
pressure tests, the tank shell is screened for tank assembly is accomplished using standard
flaws using fracture critical penetrant manufacturing processes and procedures.
inspection and fracture critical radiographic Special materials and processes are not
inspection techniques. Tank acceptance after required.
NDE marks the successful completion of
protoflight testing. ACKNOWLEDGMENT
Cleanliness Verification: After the non- We wish to thank Mr. Mike Hersh, Mr. Gary
destructive examination, the interior of each Kawahara, Mr. Jerry Kuo, Mr. Bill Lay, Mr.
flight tank is cleaned to the cleanliness level Tom Meyer, Mr. Lou Rattenni, Mr. Joe Vaz
specified below in Table 5: and Mr. Ben Wada for their significant
Table 5: Tank Cleanliness Level contribution to the success of this program.
Additionally, thanks are expressed to Mr. John
Particle Size Range Maximum Allowed Bittle, Mr. Ray Button, Mr. Jim Judd, and Mr.
(Microns) per 100 ml Mike Tomasulo for their patience and
0 to 5 Unlimited dedicated support.
6 to 10 600 REFERENCE
11 to 25 80
26 to 50 20 1. M. Drey, A. Jackson, D. Jaekle, L. Rattenni,
51 to 100 4 A. Gaio, “Design and Manufacture of a
101 and over 0 Hydrazine Tank Assembly”, AIAA 2001-
3827
ACCEPTANCE TESTING
2. W. Tam, M. Debreceni, M. Hersh and C.
After the flight tank is assembled, it is Nye, “Low Cost Derivative Tanks for
subjected to the following acceptance tests Spacecraft and Launch Vehicles”, AIAA 99-
prior to delivery: 2831.
- Preliminary examination ABOUT THE AUTHORS
- Pre-proof volumetric capacity
- Ambient proof pressure Mr. Walter Tam is a Program Manager at
- Post-proof volumetric capacity Pressure Systems, Inc. (PSI), Commerce,
- PMD bubble point test California. Mr. Mark Drey is the Engineering
- External leakage test Manager at PSI.
- Penetrant inspection of girth welds
- Radiographic inspection of girth welds Mr. Don Jaekle Jr. is a PMD designer DBA PMD
- Mass measurement Technology, North Andover, Massachusetts.
- Final visual examination

Page 23

You might also like