Professional Documents
Culture Documents
Page 1
DESIGN AND MANUFACTURE OF AN
OXIDIZER TANK ASSEMBLY
Page 2
Figure 1: Oxidizer Tank Assembly
Parameters Requirements
Operating Pressure MEOP is 300 psia @ 50°C (122°F), 50 cycles
Proof Pressure 375 psia @ 50°C (122°F), 12 cycles
Burst Pressure 450 psia minimum @ 50°C (122°F),
Material of Construction Membrane: 6Al-4V titanium, solution treated and aged
Inlet/outlet ports: 3Al-2.5V titanium
PMD: CP and 6Al-4V titanium
Expulsion Efficiency 99.79% minimum for depletion during LAE firing
99.60% minimum for depletion during DMT firing
Propellant Weight 492 lbm (223.2 kg) maximum nitrogen tetroxide
Propellant fill fraction 65% minimum, 95% maximum
Tank Capacity 9712 in3 minimum
Internal dimension 21.25” ID x 34.69” long
Overall Length 41.50”
Tank Weight 20.0 lbm maximum
Propellant Nitrogen tetroxide
Fluid Compatibility N2O4, GAr, GHe, GN2, D.I. water, Isopropyl alcohol
Shell Leakage <1x10-6 std cc/sec He @ 300 psia
Natural Frequency > 75 Hz in lateral direction
> 62 Hz in thrust direction
Failure Mode Leak Before Burst
On-Orbit Temperatures 50 to 122 °F (10 to 50 °C)
Shelf Life 3 years minimum
On Orbit Life 15 years minimum
Page 4
To minimize the overall program cost, an • Temperature environment;
existing, flight qualified tank shell was selected • Material properties, STA titanium;
as the baseline design, and modified to meet • Material properties, annealed titanium;
the specification requirements. This is a • Volumetric requirements;
popular design approach2 widely used by PSI • Mass properties of tank shell material;
to maximize value and minimize cost. The
cost reduction is the result of (1) eliminating • Mass properties of fluid;
the need to fabricate a qualification tank, (2) • Fluids used by the tank;
eliminating the need to conduct a weld • Tank pressurization history;
development and qualification program, (3) • External loads;
eliminating the need to conduct a qualification • Girth weld offset and weld suck-in;
testing program, and (4) minimizing the
number of new engineering drawings, shop • Size of girth weld bead;
travelers, and NC programs, and (5) • Resonant frequency;
maximizing the use of existing tooling. This • Tank boundary conditions;
design approach also provided schedule • Residual stress in girth weld;
assurance to the customer. However,
• Load reaction points; and
conservatism was still exercised, and
complete stress and fracture mechanics • Design safety factors.
analyses were conducted to validate the tank
shell in the new operating environment. A This stress analysis validated the use of the
Qualification-by-Similarity (QBS) report was existing tank shell design, plus the modified
generated to document the QBS status. mounting features, for the new mission
requirements. The analysis dynamic model
All completed flight tanks require acceptance provided predictions on the first resonant
testing prior to delivery. Because the frequencies of the tank. The responses are
qualification testing was eliminated, the first shown below:
flight tank was subjected to protoflight vibration
testing. Both acceptance and protoflight Figure 2: First axial (Z) response
testing include tank shell integrity verification
and PMD functional testing.
TANK ANALYSES
Page 5
Figure 3: First lateral (X) response The analysis concluded with positive margins of
safety for all design parameters, as summarized
in Table 2.
Characteristics M.S.
Pressurant sphere, proof, yield +0.19
Pressurant sphere, burst, ultimate +0.09
Cylinder, proof, yield +0.17
Cylinder, burst, ultimate +0.05
Weld, proof, yield +0.17
Weld, burst, ultimate +0.07
Side boss, external load, yield >0.23
Side boss, external load, ultimate >0.17
Shell buckling, external load +3.21
Weld, external load, yield +2.10
Weld, external load, ultimate +2.00
Outlet/inlet tube, yield +10.50
Figure 4: First lateral (Y) response
Outlet/inlet tube, ultimate +6.60
Page 6
• Maximum stress location in the PMD PERFORMANCE ANALYSIS AND
hemisphere/cylinder transition; PMD DESIGN
• Intersection between the hemisphere and
A comprehensive PMD performance analysis
the pressurant boss;
was performed to design and validate the
• Intersection between the hemisphere and PMD. The passive, all titanium, surface
the propellant boss; and tension propellant management device was
• Maximum external load stress in the designed to provide gas-free hydrazine
hemisphere near the pressurant and the delivery throughout the spacecraft mission. As
with most PMD’s, this PMD was designed
propellant bosses. specifically for the spacecraft mission. The
PMD is designed to (a) survive spinning
The fracture mechanics analysis established operations, (b) provide gas free propellant
the leak-before-burst (LBB) characteristics of delivery throughout mission, including system
the propellant tank. This analysis concluded priming, LAE ignition, and LAE steady state
that the existing tank shell meets all the firing, and (c) retain residual propellant in the
fracture mechanics requirements. The special aft end of the tank to prevent on orbit slosh
NDE requirement established by this fracture and CG migration.
mechanics analysis include:
• Special fracture critical dye-penetrant on The PMD was designed to be installed into the
tank shell outlined in Figure 1, with 10.625-
all surfaces; and
inch radius hemispherical heads and a 13.44-
• Special fracture critical radiograph on inch cylindrical center section. It was
welds. designed for use with nitrogen tetroxide
oxidizer. Additional features were
These requirements were instituted as part of incorporated into the design to provide optimal
the tank fabrication requirements. service. First, because the PMD is a passive
device with no moving parts, the design is
PMD STRESS ANALYSIS inherently reliable. Second, the design is
constructed entirely of titanium. Thus the
A PMD stress analysis was also performed to PMD is lightweight and offers exceptional
validate the structural integrity of the PMD compatibility, long life, and reliability. Finally,
design. The analysis took into consideration the PMD was designed not only to provide
design requirements such as material propellant during steady flow conditions but
properties, fluid properties, vibration loads, also to allow some operation in some off
and design safety factors. The PMD stress design conditions, thus providing additional
analysis concluded with positive margins of operational safety.
safety for all design parameters, as
summarized below: A sketch of the PMD is provided in Figure 5.
The key components of this PMD are:
Table 3: PMD Safety Margins 1) The Sponge,
2) The Geysering Limiting Baffle,
Characteristics M.S. 3) The Trough & Pick Up Assy, and
4) The Perforated Sheet.
Vane, Flexible, yield +0.28
Vane, Rigid, yield +0.15 All PMD components are located over the tank
outlet.
Pickup assembly, yield +0.09
Top plate, yield +0.30 The sponge: The sponge consists of 24
radial titanium sheet metal panels extending
Solid vane in trough, buckling +1.80
from the central support cylinder. The panels
Half dome cover, yield +0.51 are attached to the center post as well as the
geyser limiting baffle. Each panel is 2.5
Center post, fluid loads, yield +3.17
inches high and is positioned 0.75 inches
Center post, random vib, lateral, yield +1.98 above the pick up assembly to allow space for
the trough and to allow gas to be rejected
Page 7
from under the sponge during zero g. The inch of the tank shell and to within 0.1 inch of
radial sponge panel position creates a the pick up assy. These extended panels limit
tapered gap between panels that ejects gas in propellant motion from one side of the sponge
zero g and retains propellant during lateral to the other during despin. For this reason,
thruster firing. these two panels are solid. The other 22
panels are perforated to allow cross flow and
22 of the 24 panels extend to within 0.75 and reduce metal mass.
1.25 inches of the tank wall at the base and
top of the sponge panels respectively. This The thickness of the titanium sponge panels
tapered gap aids gas bubble rejection in zero is determined by structural analysis and does
g. The other two panels extend to within 0.1 not affect the PMD functional properties.
Page 8
The Geysering Limiting Baffle: On top of PMD OPERATIONS
the sponge is a geyser limiting baffle that
consists of a 7.5-inch diameter plate designed The Oxidizer Tank PMD is designed to
to limit axial flow near the tank centerline. This provide gas free propellant to the tank outlet
limits geysering near the sponge. The plate is throughout the mission. During ground
designed to support the sponge panels as operations, the PMD is designed to enable
well. The baffle is partially perforated with tank filling, tank handling, and tank draining.
large holes for the purpose of weight During launch, the PMD does not function and
reduction, but still offers sufficient solid area to is designed to maintain propellant over the
limit geysering. perforated sheet and not be adversely
affected by the launch conditions
The thickness of the baffle is determined by encountered. During the final stages of
structural analysis and does not affect the ascent, the spacecraft is spun up to 60 rpm
PMD functional properties. during which a large solid rocket upper stage
motor is fired (AKM Firing). Subsequently,
The Trough & Pick Up Assy: Below the the spacecraft is despun without using any
sponge is a trough that retains liquid over the NTO. During the despin operations, a flat
pick up window during the high Z axis spin spin may be encountered and the PMD is
phase of the mission. The trough is a semi- designed to survive flat spin with no
cylindrical housing with a sloped top. The compromise in future PMD operations. The
opening to the trough is inboard (on the trough PMD is designed to provide gas free
diameter) and 0.7 inches high. The slope in propellant to the tank outlet subsequent to the
the top of the trough is designed to push gas spinning operation. The primary use of the
bubbles out of the trough during zero g coast. PMD is to provide gas free NTO during the
Inside, and bisecting, the trough is a fin which three axis stabilized ascent following launch.
limits the cross flow within the trough. In addition, the PMD is designed to retain
residual propellant in the aft end of the tank
Below the trough is the pick up assembly while on orbit – thus preventing any significant
containing an off axis, perforated sheet CG shift due to NTO movement.
covered window. The window flow area is
2.07 in2 nominal and 1.83 in2 minimum. The FLOW PATH THROUGH THE PMD
window location is a minimum of 2.5 inches
from the trough entrance and 4.3 inches from The flow path through the PMD is illustrated in
the propellant surface during the 60 rpm spin. Figure 6. The propellant flows between and
The perforated sheet has 0.008 inch maximum around the sponge panels to the trough
diameter electron beam drilled holes on a 2:1 entrance. The trough entrance is inboard and
approximate spacing to hole diameter on a 60 propellant access outside the trough entrance
degree array. The pick up assembly provides is uninhibited by the sponge panels – all but
a flow path from the perforated sheet to the two are elevated above the trough. A solid
propellant outlet. metal fin bisects the trough, forcing propellant
to flow to the perforated window on either side
The Perforated Sheet: The perforated sheet of the trough and preventing propellant from
is located over the tank outlet, inside of the flowing from one side of the trough to the
trough. This is the only location of a porous other. Once propellant passes through the
capillary barrier in the PMD design. This PMD pick up assy perforated sheet window, it flows
contains no screen. The perforated sheet was freely to the tank outlet. The perforated sheet
chosen to have low flow losses while window is the only capillary barrier to gas
maintaining a bubble point in excess of twice within the PMD. This PMD is designed to
the loads applied. The perforated sheet is minimize flow losses. The maximum flight
fabricated from titanium sheet with electron flow loss through the PMD, including the
beam drilled holes a maximum of 0.008 inches outlet region, is calculated to be less than
in diameter. The open area is approximately 0.04 psid (except at depletion where the sheet
22% of the total area. bubble point of 0.08 psi will raise the flow loss
to 0.12 psid).
Page 9
Figure 6: Flow Path Within the PMD
Page 10
Figure 7: Operational Sequence: Ground Operations
Ground Fill
Ground Handling Ground Drain
Launch
Page 11
ASCENT OPERATIONS to upright ground handling, there is no danger
of gas ingestion into the outlet pick up
Ascent operations can be divided into five assembly. Slosh during launch does not
stages: launch, 60 rpm spinning, AKM firing, provide a force large enough to drive gas into
despin, and, possibly, flat spin. The PMD is the perforated sheet. In addition, the
designed to withstand the structural loads positioning of the trough and sponge above
during these stages of ascent as well as the pick up assy provides a fluid stagnation
prevent gas from penetrating into the pick up region where fluid velocities will always be
assembly. Figure 9 below presents the small. Even if gas were driven down toward
operational sequence of the ascent the pick up assembly by slosh, the sponge,
operations. trough, and the sheet itself will prevent the gas
from penetrating into the pick up assy. Launch
Launch: The PMD is designed to be is illustrated in Figure 7 (similar to ground
launched in the outlet down position. Similar handling).
Page 12
Simple Spin: After the initial launch, the Figure 11: Propellant Position After AKM
vehicle is spun up to 60 rpm about a spin axis Firing
parallel to the tank centerline and 30.3 inches
away (inboard of the trough). Oxidizer is not
used to spin up or spin down the vehicle.
During simple spinning, the propellant is
positioned outboard by the centripetal forces.
The propellant interface is cylindrical and the
trough entrance is submerged. Simple
spinning at the minimum fill fraction is
illustrated in Figure 10.
Page 13
Despin: After AKM firing, the vehicle is Figure 14: Propellant Position During a
despun from 60 rpm to between 0 and 5 rpm Transition to Flat Spin
very rapidly. The tangential acceleration
created by the rapid depin is large and the
propellant will move laterally in response to the
acceleration. The PMD is designed to prevent
any gas from reaching the perforated sheet
window during depin. Despin is illustrated in
the operational sequence. Figure 13 shows
the propellant position at the end of despin.
ORBITAL OPERATIONS
Page 14
Figure 15: Operational Sequence: Orbital Operations
Zero g Coast: The system priming oxidizer LAE Ignition: The zero g coast positions
position illustrated in Figure 15 operational shown are also the propellant position at the
sequence is also the zero g coast oxidizer onset of LAE ignition. During the initial phase
position which will occur between each LAE of the LAE burn, oxidizer is reoriented to the
firing. As oxidizer is consumed, the slightly tank bottom by the settling acceleration. Upon
flattened gas bubble will grow larger until it can reaching the bottom of the tank, the propellant
no longer fit within the tank. At this point, the continues its motion – forming a geyser in the
oxidizer in the upper hemisphere will no longer middle of the tank. The sponge is designed to
be contiguous with the oxidizer within the provide propellant during this ignition transient
sponge. The sponge is designed to retain the and the geyser limiting baffle above the
oxidizer needed for LAE ignition. Later in sponge is designed to prevent the geyser from
mission zero g coast is illustrated in Figure 15. stripping the sponge of its propellant. LAE
Page 15
ignition is illustrated in Figure 15. Figure 16 tank outlet during the required conditions until
shows an LAE firing at 30% fill fraction. the fill fraction of the tank falls below 0.5%
(0.1% is the goal). Depletion is illustrated in
Figure 16: Propellant Position at 30% the Figure 15 operational sequence.
Fill Fraction
At the end of the final LAE firing (and the last
use of propellant), up to 9.44 lbm of oxidizer
could reside in the tank. The PMD is designed
to prevent this propellant from migrating within
the tank during lateral thruster firings, which
produce a maximum acceleration of 0.00037
g. The last illustration in the operational
sequence of Figure 15 shows the propellant
held within, and around, the sponge during this
lateral acceleration. The propellant moves off
the tank centerline but is retained in the aft
end of the tank by the surface tension forces
within the sponge. See Figure 17.
Initial Condition Geyser Formation
Figure 17: Propellant Position at
LAE Firing: As the LAE firing continues,
propellant is settled over the outlet by the main
engine acceleration. The acceleration is
sufficiently high to produce a flat propellant
surface in the tank with surface tension effect
limited to within an inch of two of the tank wall.
Propellant access is straightforward as
propellant flows between, through and around
the sponge panels to the trough entrance.
From the trough entrance, the propellant flows
directly to the perforated sheet, into the pick
up assy and out the tank outlet. LAE steady
firing is illustrated in the operational sequence.
Page 16
Figure 18: Propellant tank heritage.
80390-1 80394-1
80426-1
TANK FABRICATION
Page 17
Figure 21: The Trough Assembly
Page 18
Both girth welds are subjected to radiographic
and dye penetrant inspections. After closure
the tank assembly is stress relieved in a
vacuum furnace to remove residual stress
from the weld operations. After the completion
of the acceptance tests, the propellant and
pressurant port shear plates are installed prior
to final clean and delivery.
Page 19
Figure 27: A Completed Oxidizer Tank - Cleanliness
Assembly
Conservatism is exercised throughout the test
program, and all pressure testing is
temperature adjusted for the worst case
operating temperature (50 °C). Pass/Fail
criteria consists of acceptance type external
leak tests and non-destructive evaluations
conducted at intervals throughout the test
program.
Page 20
and wet sine. All three principal axes are Control accelerometers are placed on the
tested at each phase. The vibration spectrum vibration test fixture near each attachment
is listed below in Table 4. For both wet boss to control energy input. Tri-axial
random and wet sine vibration testing, the response accelerometers are used to monitor
protoflight tank is loaded with 492 lbm of the tank responses. The vibration test setup is
PF5060 performance fluid. The tank is presented in Figure 28.
pressurized to MEOP for all vibration testing.
Typical lateral and axial responses are shown
The vibration test fixture is designed to in Figure 29.
simulate the tank-to-spacecraft installation
interface. The fixture is also sufficiently stiff to
be considered rigid for the test frequencies.
Page 21
Figure 28: Vibration Test Setup
Page 22
PMD Functional Test: The tank assembly - Cleanliness
level PMD bubble point test is intended to
verify the PMD performance. Successful CONCLUSION
completion of the PMD bubble point test after
the vibration testing validates the PMD The oxidizer tank assembly has successfully
workmanship. concluded protoflight testing without failure.
The production program is in progress and two
External Leak Test: The external leak test flight tanks have been delivered.
verifies the integrity of the tank shell and also
serves to validate the above vibration testing. The oxidizer tank PMD is specifically designed
The tank is placed in a vacuum chamber, to meet the mission requirements. The PMD
evacuated to under 0.2 microns of mercury, has a simple, robust design and is easy to
and helium pressurized to 300 psia for 30 manufacture. It has been protoflight tested
minutes. The helium leak rate cannot exceed and shows excellent strength, durability, and
1 x 10-6 std cc per second after a 10-minute reliability.
stabilization period.
The oxidizer tank assembly is lightweight, high
Non-Destructive Examination: Following the performance, and easy to manufacture. The
pressure tests, the tank shell is screened for tank assembly is accomplished using standard
flaws using fracture critical penetrant manufacturing processes and procedures.
inspection and fracture critical radiographic Special materials and processes are not
inspection techniques. Tank acceptance after required.
NDE marks the successful completion of
protoflight testing. ACKNOWLEDGMENT
Cleanliness Verification: After the non- We wish to thank Mr. Mike Hersh, Mr. Gary
destructive examination, the interior of each Kawahara, Mr. Jerry Kuo, Mr. Bill Lay, Mr.
flight tank is cleaned to the cleanliness level Tom Meyer, Mr. Lou Rattenni, Mr. Joe Vaz
specified below in Table 5: and Mr. Ben Wada for their significant
Table 5: Tank Cleanliness Level contribution to the success of this program.
Additionally, thanks are expressed to Mr. John
Particle Size Range Maximum Allowed Bittle, Mr. Ray Button, Mr. Jim Judd, and Mr.
(Microns) per 100 ml Mike Tomasulo for their patience and
0 to 5 Unlimited dedicated support.
6 to 10 600 REFERENCE
11 to 25 80
26 to 50 20 1. M. Drey, A. Jackson, D. Jaekle, L. Rattenni,
51 to 100 4 A. Gaio, “Design and Manufacture of a
101 and over 0 Hydrazine Tank Assembly”, AIAA 2001-
3827
ACCEPTANCE TESTING
2. W. Tam, M. Debreceni, M. Hersh and C.
After the flight tank is assembled, it is Nye, “Low Cost Derivative Tanks for
subjected to the following acceptance tests Spacecraft and Launch Vehicles”, AIAA 99-
prior to delivery: 2831.
- Preliminary examination ABOUT THE AUTHORS
- Pre-proof volumetric capacity
- Ambient proof pressure Mr. Walter Tam is a Program Manager at
- Post-proof volumetric capacity Pressure Systems, Inc. (PSI), Commerce,
- PMD bubble point test California. Mr. Mark Drey is the Engineering
- External leakage test Manager at PSI.
- Penetrant inspection of girth welds
- Radiographic inspection of girth welds Mr. Don Jaekle Jr. is a PMD designer DBA PMD
- Mass measurement Technology, North Andover, Massachusetts.
- Final visual examination
Page 23