Task Task Name Duration Start Finish Predecessors Sep ' Oct ' Nov ' Dec '

Start Finish Predecessors Sep ' Oct ' Nov ' Dec ' Jan ' Feb ' Mar ' Apr
1120012301220112001220112011200
1
2 Normalisasi Rute SKKL Interisland Anambas Link Tarempa-Jemaja 107 days 10/10/2022 07/03/2023
3 Penetapan pelaksana Pekerjaan 1 day 10/10/2022 10/10/2022
4 Kick Off Meeting 1 day 12/10/2022 12/10/2022
5 survey 16 days 14/10/2022 04/11/2022
6 Ijin SPKBA, TO, SO 7 days 14/10/2022 24/10/2022
7 Mobilisasi kapal survey 3 days 22/10/2022 25/10/2022
8 Clearance in 2 days 25/10/2022 26/10/2022
9 survey dan olah data 6 days 25/10/2022 01/11/2022 6
10 Demobilisari kapal survey dan Survey Report 25 days 02/11/2022 06/12/2022 9
11 Ijin Pemindahan sebagian Jalur SKKL Tarempa - Jemaja 23 days 13/12/2022 12/01/2023 10
12 Ijin SPKBA Pelaksanaan Normalisasi Tarempa Jemaja TO/SO 14 days 13/01/2023 01/02/2023 11
13 Cable Loading Makassar 3 days 22/12/2022 26/12/2022
14 Cable Transport ke Batam 11 days 10/01/2023 24/01/2023 13
15 Mobilisasi personel dan diver cable searching dan marking 2 days 02/02/2023 03/02/2023
16 receive cable from LCT & Mobilisasi DP2 Cable Laying Vessel 3 days 02/02/2023 06/02/2023
17 clearance in dan out, loading cable dari cable trasporter 2 days 04/02/2023 06/02/2023 16
18 Transit to site 1 day 07/02/2023 07/02/2023 17
19 PLGR 2 days 09/02/2023 10/02/2023 18
20 pekerjaan Link Jemaja Tarempa 8 days 11/02/2023 22/02/2023
21 Pickup Cable di KP 4.0 dari Jemaja, cut, endcupped, marked 1 day 11/02/2023 11/02/2023 19
22 Cable Roll Back dari KP 4.0 sampai KP 50 3 days 13/02/2023 15/02/2023 21
23 Laying Cable start KP 50 dan Jointing dengan kabel baru 3 days 16/02/2023 20/02/2023 22
24 Pick up Cable's end Jemaja 1 day 21/02/2023 21/02/2023 23
25 Final Joint 1 day 22/02/2023 22/02/2023 24
26 Cable testing 1 day 24/02/2023 24/02/2023 25,20
27 Post lay Burial 4 days 27/02/2023 02/03/2023 26
28 Demobilization 2 days 03/03/2023 06/03/2023 27
29 unloading cable to Makassar Depot 1 day 07/03/2023 07/03/2023 28
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline

Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only