You are on page 1of 2

1. It is an important characteristic that influence the behavior of soil.

It is the ratio of the


weight/mass of water to the weight/mass of dry soil.
a. Moisture Content
b. Specific Gravity
c. Unit Weight
d. Organic content
2. It is defined as the lowest moisture content at which the soil will flow upon the
application of a very small shearing force. It gives a certain measure of the shearing
resistance of a soil when mixed with water.
a. Plastic Limit
b. Plasticity Index
c. Liquid Limit
d. Shrinkage Limit
3. Since cement accounts for more than half the cost of concrete, the role of concrete mix
design is to come up with the largest amount of cement that will satisfy the required
properties of the hardened state of concrete.
a. True
b. False
c. Sometimes true.
d. Sometimes false
4. ___________________. It is the process of selecting a part (sample), which will be used
to judge the whole (lot). It shall be in accordance with the Standard Sampling
Procedures to obtained a true representative of a lot and based on the minimum testing
requirements as prescribe for the item of works. Materials Sampling
5. The Purpose of taking sample in the Laboratory SOURCE OF APPROVAL
6. The Purpose of taking sample in the Laboratory JOB CONTROL
7. The Purpose of taking sample in the Laboratory ACCEPTANCE
13-15. Sampling, testing and inspection requirements of pre-fabricated structure or
component structure materials if IMPORTED.
16. AASHTO stands for _______________________________. AMERICAN
ASSOCIATION OF STATE HIGHWAY and TRANSPORTATION OFFICIALS.
17. It is a documented proof of the quality of materials indicating it meets or it fails the
desired properties as called for in the specification requirements of an approved contract.
MATERIALS TESTING
18. The prescribed tests on the construction materials to be used in a project based on
approved contract quantities. Minimum Testing Requirements
19. It is a document with complete and accurate information about a project and duly
signed by authorized representatives for the submission of samples in a laboratory.
SAMPLE CARD
20. Samples are taken on a day-to-day basis during production or use of material, and
include samples of material from approved sources, production plants and at the project
site. Job Control samples are taken by the user to insure adequate quality control. JOB
CONTROL
The following are some of the specified quantities in a certain project. Aggregates used are
rounded for Item 311 and Angular for Item 405. Use CF=11 for Item 311 and CF=12 for
Item 405. (35 POINTS)

Item No. Description Unit Quantity


103 Structure Excavation Cu.m. 512
104 Embankment from Borrow Cu.m. 5,705.00
105 Subgrade Preparation Sq.m. 7,886.00
201 Aggregate Base Course Cu.m. 6,131.00
311 Portland Cement Concrete Pavement Sq.m. 8,040.00
Thickness=30 cm, Width=3.35m
404 Reinforcing Steel Bars kg 33,484
(16mm dia. = 12,235.78 kg, 12mm
dia.=21,248.22 kg)
405 Structural Concrete Cu.m. 2,722.00

Prepare a complete and correct QUALITY CONTROL PROGRAM for the given project.

A Blank QCP format is provided. ERASURES are INVALID.