a handbook of
rational practices
for planners and designers
prepared for
Transportation Systems Center
by
Birger Schmidt
Parsons Brinckerhoff Quade & Douglas, Inc.
New York 10001
Notices
Acknowledgment:
C. John Dunnicliff of Soil & Rock Instrumentation,
Inc. participated in the original studies for this
Handbook and reviewed much of its
inspired and
contents. Edited by W. D’Ambrosio; cover and graphic
arts by Barbara B. Towery, both of Parsons,
Brinckerhoff, Quade & Douglas, Inc. Original photos by
B. Schmidt; other photos and graphics from
manufacturer’s literature and trade journals too
numerous to list individually.
Oept of TfaRspartaHon
JUL0?«ff
i
tftay I
.
H£T
\%s
.^7
/V£?.
Technical Report Documentation Page
1 . Report No. 2. Government Accession No. 3. Recipient’s Catalog No.
Parsons, Brinckerhof f ,
Quade § Douglas Inc. UM704/R7706
250 West 34th Street 11. Contract or Grar. No.
16. Abstract
The objectives of the Urban Mass Transportation Administration
Tunneling Program are to lower subway construction costs and
(UMTA)
reduce construction hazards and damage to the environment. Advances
in the practice of technology of construction monitoring of soft
ground tunnels and deep excavations can lead to a better control, and
in some cases reductions in, transit construction costs. This hand-
book documents the findings of a recent UMTA construction monitoring
instrumentation research project. The handbook is directed to systems
managers and planners to show how to incorporate successful monitoring
programs in their systems to help control and reduce costs. Recom-
mendations are made for planning and specifying the purchase and
installation of instrumentation.
19. Security Classif. (of this report) 20. Security Classif. (of this page) 21* No. of P ages 22. Price
Unclassified Unclassified 70
CONVERSION
METRIC
i
Contents
Page
FOREWORD
Preamble vii
1. OVERVIEW
Is It Profitable? 1-1
Is It Possible? 1-1
Is It Necessary? 1-1
Contents
Page
6. SELECTION OF MONITORING PARAMETERS AND HARDWARE
6.1 Groundwater Parameters 6-2
6.2 Ground Deformations 6-3
6.3 Observations on Existing Structures 6-5
6.4 Soil-Structure Interaction Monitoring 6-5
6.5 Gases in Tunnels 6-6
6.6 Progress Monitoring 6-7
6.7 Systematic Guide to Selection of Parameters 6-10
6.8 Monitoring Cost 6-12
BIBLIOGRAPHY
ILLUSTRATIONS
1 Building on Right Settled Toward a Deep Excavation, Opening the Joint Between the
Two Buildings 1-3
2-3 Jack Shoes Form a Ring to Push Against the Erected Lining 2-3
2-4 Rotary McAlpine Digger Shield (with T railing Power Pack) — for Firm Soils 2-3
2-5 Calweld "Windshield Wiper" Digger Shield With Four Oscillating Sets of Spokes 2-3
2-8 Bentonite Under Pressure Keeps Tunnel Face Stable Without Compressed Air in Tunnel 2-4
2-12 Width of Settlement Trough — Empirical Data From Construction Monitoring Case
Histories — Tunnels in Cohesive Soils 2-7
2-16 Typical Ground Surface Cracking and Distortion Caused by Adjacent Excavation 2-12
IV
1
Contents
Page
2-
3-
2-17 Sidewalk Settling Away From Buildings on Piles or Piers 2-12
3-
2-18
4- Another Example of Settlement Effects 2-13
5- 19 Damage Criteria for Settlement of Buildings Under Their Own Weight 2-13
6-
1 Who Makes Monitoring Work? 3-0
6-4 Another Set of Typical T ransverse Settlement Profiles (Toronto Subway, Contract B4) 6-3
6-5 Three Centerline Surface Settlement Records Shown as a Function of Shield Advance
(Toronto Subway, Contract B4) 6-3
6-14 Typical Lining Distortion Measurements (Toronto Subway, Contract El) 6-7
6-15 Inclinometer Data Show Effects of Excavation Below Last-Placed Strut 6-8
6-16 Typical Research and High-Intensity Monitoring Stations for Ground Movements 6-1
v
Foreword
— ”
“ Benefits of monitoring are not automatic they are managed and engineered.
— The Author
tions can help reduce the construction cost of urban veyances and their system planners and engineers.
underground facilities. These efforts can also reduce Consulting and design firms who prepare plans and
construction hazards and minimize the impact of con- specifications for underground systems will also bene-
struction on existing structures and facilities, as well fit. Chief designers, project managers, and specifica-
as on city traffic. In the long term, monitoring provides tion writers will particularly benefit. It may also be
the essential information to improve design and con- useful to those engineers who execute the final design
struction methods, as well as methods of predicting of the monitoring system, and to those who install and
and controlling ground movements and settlements, read monitoring instruments and interpret and imple-
loads and stresses. In the short term, monitoring bene- ment the results.
fits the project directly by providing the essential The Handbook gives guidance to those who make
means to make intelligent decisions during policy decisions, and to those responsible for overall
construction. planning, specifications, and contract and insurance
arrangements.
VII
Foreword
Stages of Tunnel Construction Monitoring underground structures in soil, and those that affect
the way owners pay for such facilities, and the way
When employed, its purposes must be
monitoring is construction is managed, inspected, controlled, and
clearly defined at the outset, whether for short- or insured.
long-term benefits, and it must be made an integral
part of design and construction if it is to serve the
immediate needs of the project on which it is used. Basic Needs
Procedures for reading and recording, and interpreta-
tion and implementation must be carefully prepared A study sponsored by the Urban Mass Transporta-
during design. Many stages must be considered in a tion Administration (UMTA) disclosed that, although
monitoring program: the art of instrumentation and monitoring is well ad-
vanced, monitoring has not nearly been used to its full
• Definitions of benefits and purposes of program potential on tunneling projects. One of the main rea-
sons for this was found to be a lack of general proce-
• Design and project specifications to draw the full dures and guidelines, and a general lack of expertise
benefits of program on these subjects among those who make decisions
regarding tunnel monitoring. This Handbook was com-
• Selection of monitoring parameters missioned by UMTA to help overcome these difficul-
ties. Since much of its content has little written prece-
• Selection of instruments and writing of specifica- dence in this country, the author realizes that certain
tions for procurement and installation ideas and procedures must be tested in actual prac-
tice; hence, this Handbook should be termed a “Work-
• Procurement and installation ing Draft.” It is hoped that the implementation of
procedures suggested in this text will lead to improve-
• Observations, reading and maintenance of ments that may be incorporated as revisions to this
instruments Handbook.
The Handbook intended to stimulate discussions
is
• Data storage and retrieval beyond the scope ofits contents, as well as the devel-
viii
1. Overview
modern construction alternatives. When used in con- essential to monitor the water table; when tunneling
junction with appropriate design techniques and con- through soil near existing structure, at least ground
struction methods, it affords new opportunities for surface movements (settlements) must be monitored
cost and time savings, and reduction of construction and the existing structures observed.
hazards and environmental impact. These premises These measurements and observations are neces-
are briefly examined in the following paragraphs. sary for the safety of the work and for legal protection
Is It Profitable?
For a $30-million subway station and tunnel con- Some Basic Considerations:
tract,the design of a monitoring program might cost
$15,000 to $40,000; instrumentation might cost • Each important underground project war-
$50,000 to $150,000, including installation; and rants the diligent study of possible or
monitoring and implementation perhaps a similar potential benefits, either long-term or
amount. This total amounts to between one-third and short-term, that may be derived from
one percent of the total cost, or somewhere near ten
construction monitoring or test sections.
percent of the design cost, or five percent of the design
plus construction supervision cost. • Funding of a meaningful monitoring
Another comparison is more illustrative: The cost of program should be a matter of course; it
design and execution of a monitoring program is equiv-
should be considered a fully justifiable
alent to a typical single building underpinning job. If
design or construction cost. When scien-
monitoring can eliminate just one underpinning job, or
tific use and development requires addi-
otherwise save just one percent of the total cost, it will
tional data not otherwise needed, public
have paid its own way.
funds may be sought.
Is It Possible?
• When monitoring only for direct benefits,
consider also the likelihood that addition-
al or better data will provide benefits for:
Instrumentation and monitoring technology has
reached a stage where virtually any parameter of future extensions of the monitored proj-
interest to the tunnel constructor can be measured ect, similar projects not yet underway,
and monitored. Improvements can be made in instru- and increasing the general knowledge of
ment accuracy, and cost, but basically the
reliability tunneling.
state-of-the-art mature. Instrumentation know-how
is
is not particularly abundant at this time; however, • Data centers and central coordination of
guidelines, manuals, and experience should improve research efforts on a local or regional
monitoring planning, instrument selection, and instal- basis,and efforts to disseminate existing
lation. The adversary relationship between owners and or new knowledge, are essential to the
contractors has often made it difficult to achieve the future success of underground design and
full benefits of monitoring, but minor modifications of
construction projects.
construction specifications will make these benefits
achievable.
1-1
Overview
of the owner or the contractor. More than a basic gible benefits, as well as the possible risks that may be
minimal monitoring effort is necessary, however, if either eliminated or incurred through properly applied
monitoring is to save construction costs. For this pur- monitoring practices. Such cost-and-risk analyses are
pose, monitoring must be structured so as to allow often not carried out because owners do not request
predictions of future ground or tunnel behavior, diag- them and do not include them explicitly in the scope of
noses of adverse behavior and, most importantly, ac- work for which design is contracted.
tion based on monitoring interpretation. Hence, the owners have an obligation to request a
To many engineers, the deliberate use of monitor- certain level of design effort directed toward a defini-
ing in this fashion is unfamiliar or even totally foreign; tion of the utility of monitoring principles.
they have no confidence in it. To these people, we must But owners are not know-it-alls. The planners and
demonstrate that the concept works. design engineers in negotiating a design contract have
For this reason, and also for the development of the obligation to provide the proper feedback so that
new technology and design techniques, the accumula- appropriate emphasis is placed on minimizing costs
tion of case history data of sufficient breadth and through monitoring and associated quality control.
necessary. Tunnel construction even
reliability is also Once the most feasible level of monitoring has been
more than other types of earthworks, eludes sophisti- established for a given project, it is the designer’s
cated theoretical analysis, and the study of empirical obligation to scope out and develop a complete design
data is absolutely necessary for advancing design and incorporating all necessary implements to make the
technology, and hence, reducing the cost of the next monitoring program work according to intent. Con-
tunnel project. tractdocuments are very important, and the specifica-
tion writers play a significant role in this effort. Special-
istconsultants may be required.
What’s in the Future? Finally, the contractor’s indulgence is desired, and,
most importantly, the educated crew of inspecting
Underground construction today is expensive and engineers, the owner’s representatives, must vigilantly
often unattractive because of cost and surface disrup- recover, interpret and act on all pertinent monitoring
tions. Technological advancements and improvements data.
incontract arrangements are needed, but improve- For continuity and to derive the full benefits
—
ments don’t just happen they are engineered and through proper feedback, a central coordination group
managed. should have responsibility for construction monitoring
Real technological progress comes with the obser- for an entire transportation system. This is often best
vation of prototype construction. The daring use of done under the auspices of a construction manager
flexibly jointed tunnel liners in London, and massive cooperating closely with the designers.
grouting in lieu of underpinning of landmarks in Paris,
could not be executed except through the use of
carefully engineered test sections and construction
monitoring.
The progressive use of monitoring may allow devel-
opment of new design and construction concepts that
otherwise might not be possible; conversely, the use of To Implement Monitoring:
new and unproven concepts require diligent monitor-
• Include examination of benefits of monitor-
ing and testing in pilot projects, test sections or proto-
ing and preparation of monitoring program
type construction.
in planners' and section designers' contracts
with owners
Who Can Make These Concepts Work? • Develop organizational review, coordination,
and implementation tools
Some changes in philosophy and basic approach
are required to achieve the greatest benefit of monitor- • Educate engineers and specification writers
ing. First, the decisionmakers must be made fully
aware of the benefits of monitoring and the cost of • Provide funds commensurate with expected
alternatives, and confidence in the application of the benefits
principles must be The need for monitoring is,
instilled.
of course, quite apparent in most instances, but full • Develop confidence in concepts of monitor-
benefit derived only by a conscientious effort on the
is ing
part of the decisionmakers.
A cost-and-risk analysis carried out by planners or • Do not antagonize the contractor
designers should clearly point out to owners and deci-
sionmakers the most probable cost benefits and intan-
1-2
Overview
1-3
0
S- y*
p •
|
|
T
i i
2. Problems of Tunneling and Deep Excavations in Soil
2.1. Planning and Design Insurance and Project Responsibility. Wrap-up in-
surance, by which the owner insures the contractors’
When monitoring is done essentially for research work against third-party damage or accidents, is com-
purposes, the design of a tunnel project is not ordinar- monly used (e.g. Bay Area Rapid Transit Authority,
ily greatly affected by the decision to perform monitor- Washington Metropolitan Area Transit Authority). The
ing, and minimal monitoring “for the record” does not decision to employ this type of insurance is in part
greatly influence design decisions. political, in part economical. It tends to lift some
However, when monitoring is intended to benefit responsibilitiesaway from those who execute the work.
directly the project being monitored, the design and Diagnostic monitoring will often indicate work de-
the contract documents must carefully consider not tails that may be improved or work items that may be
only the mechanical implementation of the monitoring alternately employed or instituted. Contractors may
program, but also the design aspects for which bene- not be willing to react to such monitoring results
fits are expected to accrue, and the full implementa- without the incentive inherent in full project responsi-
tion of the results of monitoring. bility. This responsibility extends to the contractor’s
Subsequently, details of design and implementation provision of his own insurance. For this and related
will be examined. This section describes some of the reasons wrap-up insurance affects the working climate
planning and design decisions that will be affected by and the quality of parts of the work, and should affect
the decision to utilize directly the benefits of the type of monitoring and the way it is used.
monitoring. Acquisition or Protection of Adjacent Property.
When little control of construction methods is exer-
cised, directly or indirectly through proper responsibil-
ity allocation, and when the contractor’s performance
2-1
Problems of Tunneling and
Deep Excavations in Soil
Construction Procedures and Field Decisions. different distribution than a process not including
The contractor for a bored tunnel spends much time monitoring. Some bid or unit prices or quantities will
and money in mobilizing tunneling equipment and in increase, and some modifications and delays may have
setting up his project plant. Construction materials to be paid for, while other costs —
underpinning, street
and expendables are ordered early, and once tunneling restoration, utilities retributions, contingencies
is underway, it is difficult and costly to make signifi- vanish ordiminish.
cant changes in the basic construction methodology. It Summary. Construction monitoring is not a concept
is, therefore, essential that the contractor prepare in that by itself, guarantee a full return on the
will,
advance his construction plant in anticipation of the investment. Monitoring is a required activity resulting
demands on his work. To do this, he must, in the from a decision to exercise a certain level of control on
contract documents and appurtenant geotechnical re- the contractor’s performance and the results of his
ports, be given the basic philosophy of design, the work, and is a representation of an adopted design
expected quality of performance, the nature of any philosophy that must be carried through deliberately.
field decisions that may be required, and all appropri- This design philosophy, to be productive and cost
ate geotechnical data. Equitable pay items and distri- effective, must influence and permeate the affected
bution of responsibilities must also be given. Specifica- portions of planning, design, construction, and control
tions based in part on performance criteria require activities, as well as the contract documents. Monitor-
dependable monitoring of appropriate geotechnical or ing as a part of design and construction should be
construction parameters. intended and structured for significant benefit in the —
For an open cut, or cut-and-cover project, there are short or the long term —
beyond its own cost.
greater possibilities for modifying construction details
as construction proceeds, and implementation of mon-
itoring results is easier. Nonetheless, the basic perfor- 2.2. A Summary of Tunneling Procedures
mance requirements must be presented to the con- and Problems
tractor in the contract documents.
A design and construction process that involves Typical Tunneling Procedures (see Figs. 2-1
monitoring activity will incur construction costs of a thru 2-9). Most modern transportation tunneling in
Fig. 2-2. Business End of 10-Foot Robbins Tunneling Machine. Note slant of cutting edge, crown doors for face breasting
and excavator.
Problems of Tunneling and
Deep Excavations in Soil
Fig. 2-3. Jack Shoes Form a Ring to Push Against the Erected
then shoved forward by jacking against the last
Lining. erected ring, a void is left between the lining and the
soil. The thickness of this void is theoretically equal to
soil employs a shield which is shoved forward by the sum of the clearance between ring and tail, and the
jacking against the erected lining (Fig. 2-3). The shield shield tail thickness. The lining may also consist of
is a steel cylinder, 1 2 to 18 feet long, with a vertical or steel rings or ribs with an H-shaped cross section, with
slanted cutting edge in front. The forward end is often timber or steel lagging between rings. This is later
hooded, i.e., the leading top (crown) edge overhangs followed by a permanent concrete lining. It is some-
the bottom (invert) front edge to protect workers close times possible to expand a lining directly against the
to the face and to help in keeping the working face soil behind the tail, if the soil stand-up time is ade-
stable in granular soils. quate. Under those circumstances, the lining is often
2-3
Problems of Tunneling and
Deep Excavations in Soil
Fig. 2-6. Hooded 8-Foot Lawrence Shield. Note reinforce- the tunnel brings about elastic or elasto-plastic strains
ment of shield front. Shield is 9 feet long and is advanced and displacements.
by six 40-ton jacks. Soil movements caused by singular incidents or
2-4
Problems of Tunneling and
Deep Excavations in Soil
2-5
Problems of Tunneling and
Deep Excavations in Soil
sion of the soil occurs on the other side. This leads to sive face losses. In most instances, where the face is
an increased tail void thickness and adds to the possi- kept stable, the ground loss through the face is quite
ble tail void loss. While the tail void loss is controllable small. In cohesive sands or sands kept stable by other
to an extent, the curvature loss is much less controlla- means, and in stiff or hard clays, the loss is usually
ble because the added void space is first exposed considerably less than 1.0 percent. In softer clays, on
behind the shield, and the soil may settle onto the the other hand, face losses are often significant and
shield before grouting or other measures are provided. are a function of the ratio of overburden pressure to
The maximum possible ground loss in this instance soil strength. The most severe ground losses through
can be estimated on a purely geometrical basis. With a the face are those caused by running or especially
12-foot-long shield, 18-foot-diameter shield, an 800- flowing soil, types of instability that the contractor
foot curve could generate an additional ground loss of usually attempts to prevent but that may nonetheless
0.1 5 percent. occur. Other types of face ground loss occur when it
becomes necessary to manually remove boulders
• Yaw. Usually, it is not possible to drive the shield ahead of the cutting edge, or when a cutting wheel
perfectly parallel to the theoretical tunnel axis. Irregu- works at an excessively low jacking pressure.
larities in the resistance of the soil to the shield cutting
edge and irregularities in the applied jack pressures • Delayed Ground Losses. Depending on the type of
will make the shield wiggle on its course in a yawing ground and type of lining, certain other types of
fashion. The mechanism of the resulting ground loss is ground loss can occur. Losses due to lining deflection
similar to that of the curvature loss, but the magnitude usually are small, but may be significant where ribs
of the loss evidently will vary greatly with soil condi- and lagging are used. Delayed losses may occur due to
tions, shield details, and operator’s skills. either reconsolidation of disturbed cohesive soils
around the tunnel or collapse of voids inadvertently
• Plowing. Considerably more important in many in- left open.
stances is the plowing action that results from having
to steer the shield at a greater or lesser inclination than Estimating Ground Losses. When an estimate of
the theoretical tunnel axis inclination, either because ground losses has to be made, it is convenient to
of an unfavorable weight distribution in the shield or separate the estimate into three items:
other shield details, or because of differential soil
resistance. A pitch difference of 1.0 percent
is not • Category 1 Losses. Those that must be considered
uncommon; Hansmire and Cording (1972) report an unavoidable under the given soil conditions and with
upward differential pitch of up to 3.0 percent. This the inherent capabilities of a selected construction
could result in a ground loss of 3.0 percent if the shield method: elastic movements due to changes of stresses
is as long as it is tall. in the soil, nominal face losses, a percentage of the
2-6
Problems of Tunneling and
Deep Excavations in Soil
i
,
standard deviation of the error function) and z 0 /2a is neers, meet the phenomenon,
the first time they
the ratio of centerline depth to tunnel or shield diame- how far the influence of bad or unsafe construction
methods can extend from the source of the opera-
tion, e.g. many contractors will attempt to dig in
Tunnel.
Centerline of Tunnel building within a radius of 100 yds or more can
”
£ rightly be attributed to their operations.
- H. Q. Golder, 1971
2-7
Problems of Tunneling and
Deep Excavations in Soil
ground can become unstable, resulting in soil and ing due to excessive moments is highly unusual. An
water flows that in the extreme could bury the tunnel- aging process takes place in cohesive soils which
ing equipment. The gradients of water flowing toward causes distortion of the lining (vertical diameter de-
the tunnel opening may weaken granular soils to the creases, horizontal diameter increases). However, ex-
point where quicksand conditions occur. When an cept for unusual external influences, linings in granular
aquifer, a permeable lens or stratum filled with water, soils generally retain their shape.
is opened up by the tunnel excavation, a sudden inflow Loads and stresses in tunnel linings are often hard
of water may carry large quantities of soil into the to measure; it is easier to monitor the accompanying
tunnel. A chimney may be created to the ground distortions. Monitoring is frequently required to verify
surface or,stronger cohesive soils exist above, large
if that the lining is not overloaded and that it stays within
horizontal soil flows may occur, resulting in wide- tolerances. Typical actual measurements are shown in
spread settlements or local collapse depending on the Section 6.4.
geological conditions. One external influence is of significance: the driving
These occurrences of instability, even if not as of an adjacent tunnel. This is particularly important
catastrophic as indicated above, cause substantial since most rapid transit tunnels are driven in pairs.
delays in tunneling and a considerable risk to the When the two tunnels are closer than one-half to one
tunnel workers. The associated ground movements diameter clear, the driving of the second tunnel in-
can have serious effects on overlying and adjacent creases the load on top of the first tunnel and at the
utilities and structures, and be a significant hazard to same time removes horizontal support. Sometimes,
surface traffic. for this reason, the first tunnel is temporarily sup-
For these reasons, tunneling below the groundwater ported with braces or tierods. Monitoring of tunnel
table in granular soils or soils with aquifers must distortions is required to determine the need for such
usually employ measures of groundwater control such temporary supports.
as pre-construction dewatering, compressed air in the
tunnel balancing the water pressure, or combinations,
or on occasions grouting or freezing. Monitoring of 2.3. Shafts and Cut-and-Cover Construction
groundwater pressures is employed to ascertain the
need for, and the adequacy of, such control measures. Open excavations produce ground movements
Stresses and Strains in Tunnel Liners. When a liner somewhat similar to those produced by tunneling.
ring is erected in the shield tail, it is subjected only to While a reduction of settlements due to tunneling is
loads from its own weight, yet it usually experiences a often difficult and uncertain, there are many options
slight squat due in part to play in the joints. The first available for reducing ground movements produced by
significant stresses come from the shield propulsion open excavations. Loads and stresses in the support-
jacks. These may be more severe than any other ing structural members in an open cut are more signifi-
stresses the lining will ever experience. As the shield cant than those in tunnel liners.
moves forward, the lining emerges into the tail void, One method of excavation (Fig. 2-13) begins with
and the loading of the liner depends on the soil stabili- the installation of soldier piles (H-piles driven or
ty, the time of exposure before filling of the void, and placed in pre-bored holes to a depth below the excava-
the pressure of the grout filling. If a later secondary tion floor or socketed into rock). Utilities crossing the
grouting is performed, the loading changes again. line of the soldier piles are usually exposed and relo-
Since grouting is never performed uniformly, the load- cated as needed before the placement of the piles. As
ing of the lining is quite irregular. In very weak soils, the excavation proceeds, timber lagging is placed between
load will quickly approach a condition of relatively the soldiers to retain the earth, and when excavation
uniform radial pressures, approximately equal to the has reached a point beneath the level for the first strut,
overburden pressure. In stiff, cohesive soils, long term walers and struts or anchors are placed. These sup-
reconsolidation will eventually (after months or years) ports may be prestressed to minimize ground move-
also lead to relatively uniform radial loads often ap- ments. Before they can be placed, however, the cantile-
proximating the overburden pressure. At some depth vered wall will move toward the opening. This move-
in granular soils, the load may be somewhat smaller ment is associated with a relaxation of the original soil
than the overburden pressure, controlled by construc- pressures on the back, and ground settlements. The
tion procedures and arching of the soils above the movement is generally unavoidable but can be minim-
tunnel. Load changes also take place when air pressure zied by: (1) using very stiff soldier piles or a heavy,
is returned to normal in a compressed air tunnel, or slurry-trench tremie concrete wall, (2) placing the first
when the groundwater rises again after dewatering. support very high, and (3) prestressing. The primary
Each load change brings about changes in compres- functions of prestressing are to eliminate the play in
sive lining stresses and in the moment distribution. the connections and to eliminate the movements
However, except in occasional instances where large caused by elastic shortening of the strut.
voids or other irregularities have been left behind the As excavation proceeds to below the next level of
lining to produce large unbalanced loads, overstress- supports, additional stress redistributions occur on
2-8
Problems of Tunneling and
Deep Excavations in Soil
of structural members
1
Thrust and moment in soldier pile and wale, increase
and redistribute with depth of excavation
5^3
Strut Level /
hi Strut Level 3
Bottom of excavation
the back of the wall, before these struts can be placed. through the timber lagging may erode the soil, leaving
The piles tend to bend inward, but are restrained by local voids and contributing to settlements. Without
the upper strut and the earth .below. Vertical and groundwater control, there is a risk of creating quick-
horizontal ground movements occur, moments de- sand conditions, boils, or similar problems as the
velop in the soldier piles and walers, and the strut load bottom of the excavation proceeds below the ground-
changes. A prestressing of the lower strut will change water table. The factors controlling these effects are
loads and stresses throughout, but cannot generally be similar to those controlling face stability in tunnels.
counted on to reverse movements that have already The groundwater level is usually drawn down by dewa-
occurred. Excavation below the second strut will re- tering, unless soft strata exist in the environment
peat these processes at a deeper level. The horizontal which would compress intolerably due to dewatering.
extent of movements increases with the depth of A watertight wall, consisting for example of steel
excavation. sheets or a slurry wall, is often employed where exten-
The bottom of the excavation tends to heave slightly sive dewatering cannot be performed. These walls
due to the removal of overburden. In competent soils must, of course, be designed to withstand the water
this rebound heave is elastic and nominal; in cohesive pressure. Where settlements cannot be tolerated close
soils, the heave may be subject to a time delay. In to the wall, a rigid slurry-trench tremie concrete wall is
softer cohesive soils, where the ratio of overburden often used.
pressure to shear strength is high, plastic displace- It is often economically advantageous to eliminate
ments occur, and there is a risk of plastic bottom cross-lot bracing, thereby allowing much easier access
failure for very high overburden/strength ratios. These and more working room within the excavation. Instead
bottom heaves contribute to settlements behind the of struts, earth or rock anchors are used. Interaction
wall. with the wall and the soil is then similar to that of the
If the groundwater level is not lowered, waterflow struts, except that the supporting force is inclined, and
2-9
Problems of Tunneling and
Deep Excavations in Soil
the support is generated by stressing soil materials in associated with major ground loss may severely impair
the anchor zone, far behind the wall. existing structures within the zone of influence. Al-
though major and catastrophic face or roof instability,
ground loss, or face collapse are relatively rare occur-
2.4. Safety Hazards rences, whenever they do occur they are extremely
hazardous and costly for the tunnel workers and the
tunneling operation, as well as for the surface and
“In the present state of technique, adequately
subsurface environment.
planned field observations can be expected to reduce Another relatively rare type of accident is explosion
the risk of accident by surprise to a small fraction due to accumulation of natural gas, or utility gas from
”
of the risk in former days. leading or ruptured gas mains. The most recent severe
gas explosion accidents occurred in a sewer tunnel
— under Lake Erie at Port Huron (Michigan) and in a
Terzaghi & Peck, 1967
water tunnel at Sylmar (California), where 39 tunnel
workers lost their lives. Another occurred in a 9-foot
A study of accident statistics for heavy construction sewer tunnel in Green Bay, Wisconsin where a methane
and tunneling shows that more than 80 percent of all gas explosion reportedly trapped four workers. Such
accidents are due to errors in judgment or careless- accidents, though rare, are extremely costly. The oc-
ness, rather than to adverse conditions. In tunnels, a currence of natural gas is geologically determined, and
large proportion of accidents associated with muck
is usually local experience will indicate the likelihood or
handling. In deep excavations, a large proportion is risk of encountering gas. Gas is potentially more haz-
due to materials handling. Accidents caused by ad- ardous in tunnels that are unlined or lined with pervi-
verse geotechnical conditions, however, are frequently ous liners than in tunnels lined with tight segments;
severe and costly, primarily because they are often hence, they are more hazardous in rock than in most
associated with severe construction delays. soil tunnels, where the gas can only enter at the face. In
In soil tunnels, the most frequent accidents gener- a compressed-air-filled tunnel, the air overpressure
ated by adverse or unsafe conditions are associated tends to displace the gas away from the tunnel. It is
with face and roof instability. Such accidents include often prudent to monitor the presence of gasses in
those caused by boulders or blocks of soil falling from tunnels using automatic devices.
a temporarily unsupported roof or the upper part of In braced, open cuts, severe accidents are occa-
the face. The severity and occurrence rate of these sionally caused by boulders or soil falling out of the
incidents increase with the tunnel diameter. The risk is excavation wall, or by bottom instability. The occasions
significantly increased when it is necessary to work are rare, but such incidents can be bothersome and
manually in front of the excavator, in particular when cause significant delays. More often, severe accidents
excavation in front of the protective shield is required. are caused by buckling of struts, pull-out of anchors or
For example, this may be necessary to remove boul- kick-in of the toe of the wall. There is almost always an
ders or other obstructions (piles, rubble, etc.) that inherent risk built into the support system of an open
cannot be handled by the excavator and mucking excavation. Struts are loaded in compression, and
equipment. buckling failure caused by excessive strut loads may
Face instability due to excessive hydrostatic head occur with little or no warning. Moreover, the system is
or groundwater flow is quite common, but fortunately without redundancy; if one strut buckles, or one earth
in most instances is not dangerous to the workers. anchor snaps, loads are distributed to adjacent mem-
However, if a severe face blow does occur, the conse- bers that are not usually capable of carrying these
quences can be severe. On infrequent occasions, a extra loads. The failure is, therefore, often progressive,
face blow can inundate and bury the entire tunnel and an entire wall can collapse if just one strut or
excavator and shield and several hundred feet of anchor fails.
tunnel or more in a matter of minutes; the hazard to Excessive strut loads are sometimes caused by
tunnel workers is obvious. To guard against instability faulty design or overly optimistic earth pressure as-
caused by groundwater, a monitoring program of the sumptions, but just as often are caused by the buildup
water table and the dewatering process and related of water pressures that exceed design parameters.
observations must be maintained. Kick-out of the toe of the wall may be caused by
Whenever face instability results in major ground insufficient embedment of the wall below the excava-
loss, there is a possibility of burial of equipment and tion, in conjunction with a long vertical lower span of
workers, but other effects are also severe. Utilities the wall. This is usually the result of careless design.
above may, and frequently will, rupture, resulting in On occasions, toe kick-out is caused by a loss of
various communication losses. The rupture of water, available passive pressure against the toe, due for
sewer or gas lines severely aggravates the problem. example to upward water gradients (quicksand-like
Chimneying to the ground surface creates a severe conditions). A relatively common kick-out failure oc-
hazard to surface traffic, and widespread settlements curs when a wall socketed into rock above the excava-
2-10
Problems of Tunneling and
Deep Excavations in Soil
- H. Q. Golden 1971
Fig. 2-14. Settlement T rough is Revealed by Shadow Across
Settlements and horizontal displacements caused Center of Photo.
by tunneling and deep excavations are generally un-
avoidable, but can be minimized by proper construc- settlements of the first category. To do this, the de-
tion procedures and care during construction. Typical signer must know the pertinent soil conditions and
surface expressions of underground construction are anticipate the contractor’s procedures. On the same
shown in Figs. 2-14 through 2-1 8. The ground move- basis, an estimate must be made of the magnitude of
ments can be classified in three categories of increas- the second category, peak settlements and their likely
ing severity in accordance with their general magni- frequency. Considerable experience is required for
tude and their basic causes (see Estimating Ground such estimates, and recorded case histories resulting
Losses). from intelligent construction monitoring form the most
During the design process for an urban tunnel, the valuable source of experience data. Settlements of the
designer must estimate the likely settlements along third category are generally to be avoided, but the
the tunnel centerline, and the likely range of discern- designer must assess the risk of experiencing such
ible or significant settlements, considering first the extraordinary settlements and weigh the possible con-
Fig. 2-16. Typical Ground Surface Cracking and Distortion Fig. 2-17. Sidewalk Settling Away From Buildings on Piers
Caused by Adjacent Excavation. or Piles.
2-12
Problems of Tunneling and
Deep Excavations in Soil
100 200 300 400 500 600 700 800 900 1000
' ' '
' ' '
I
2-13
PLANNER/DESIGNER
DESIGN TO
I
DESIGN
’
INCLUDE PRINCIPLES 1
I
CONSTRUCTION MANAGER INSTRUMENTATION
OWNER'S REPRESENTATIVE SPECIALIST
I
CONDUCT
MONITORING
PROGRAM
I
NTERPRET
— few
i/IPLEMEN
RESULTS
SAVE MONEY,
TIME,AGGRAVATION.
REDUCE RISKS AND
ENVIRONMENTAL
IMPACT
“Monitoring cannot by itself reduce costs or provide greater safety; rather, it provides the data base
for making intelligent cost and safety-related decisions. ”
- The Author
3.1. The People and the Organizations praisal of monitoring benefits on his allotted segment,
involving the necessary risk and cost-benefit analyses,
To execute a monitoring program for a tunnel or and present recommendations for approval. Under
deep excavation project and to ensure success in guidance from the general designer's specialists, and
deriving all desired benefits are complex matters. The possibly instrumentation specialists, the final designer
process requires involvement by almost all agencies must then prepare contract documents that will safely
associated with the design and construction of rapid take advantage of the benefits of monitoring, and
transit tunnels. detail the monitoring program. The selection of moni-
The owner must be made aware of the possibilities toring parameters and instrumentation hardware is
afforded by tunnel construction monitoring and instru- treated in detail in Chapter 6, while Chapter 7 de-
mentation, both as regards the possible cost savings scribes the requirements of the contract documents
and other benefits to the project segments being and other arrangements. At a minimum, the final
monitored, and the long-term benefits that may accrue designer’s geotechnical engineers, tunnel or structural
to future segments of the transit system. In the same engineers, and specification writers must become
vein, national funding agencies must be made aware of involved.
the long-term research and development needs of the The monitoring or instrumentation specialist enters
profession which may be fulfilled by monitoring ef- as a consultant to the general and the final designer.
forts. These benefits and needs are described in detail This specialist will develop basic monitoring require-
in Chapters 4 and 5. Section 5.3 describes a setup ments and advise on practical instrumentation selec-
that will allow maximum benefits to be realized on a tions and layouts. He may also be asked to perform the
systemwide basis. installation of certain types of instruments and other
Unless the owner is apprised of these benefits, he duties for the inspecting engineers (see Chapter 7).
will not be able to allocate the required resources to The contractor’s obligations must be specified in
monitoring efforts that will include the appropriate the contract documents. To be of benefit, the results of
required expertise. The owner also needs this informa- monitoring must be made to influence the contractor’s
tion to properly phrase contracts with design firms to work. The documents must tell as accurately as possi-
include in the scope of work a thorough examination of ble just how monitoring results may influence his work
the benefits and cost-effectiveness of monitoring and or limit his prerogatives. Responsibilities regarding the
instrumentation both on individual segments and in actual execution of monitoring tasks must also be
the entire system. explained.
In his appraisals, the owner is assisted by planners The inspecting engineers or the construction man-
and general designers. Planning, staging, staffing and ager, supported as required by the designer’s experts
funding requirements and decisions are made jointly and specialist consultants, must carry out their allot-
by the planners and general designers, and the owner. ted part of the monitoring program, perform the nec-
Each general designer must give the owner his ap- essary interpretations, and ensure that the intentions
praisal of monitoring benefits, must set up the orga- of the designers are carried out in full. Perhaps the
nization necessary to derive the benefits (see Section heaviest and most important responsibilities for the
5.3), must include an appropriate scope of work for successful use of a monitoring program are those of
the final designer, and must monitor the final design- the inspecting engineers. Complex instrumentation,
er’s work. The general designer may acquire the serv- and especially such instrumentation and monitoring
ices of specialist soil consultants or specialist instru- that offers little or no interference with the contrac-
mentation consultants to assist in this work. tor’s work, should usually be installed, maintained, and
Each final designer must execute the detailed ap- read under the guidance of the inspecting engineers.
3-1
Monitoring — Implementation
Objectives and Functions
Owner:
• Assessment of needs and benefits of monitoring
• Insiston design evaluation of immediate and basic design to take advantage of monitoring
benefits from monitoring
• Selection of monitoring parameters and how to
• Consider long-term benefits for system monitor them
• Work out standard procedures for monitor- shown 3-2. It is axiomatic that all tasks must be
in Fig.
carried out with equal care and expertise. If just one
ing efforts and their implementation
step is deficient, the whole benefit of monitoring may
be lost.
Section Designer: The pivot around which the whole monitoring pro-
gram revolves is the definition of the specific purpose
• Analyze all situations where monitoring is
and benefit desired for the program. Without this
required definition it is not possible to prepare appropriate con-
struction documents and select the proper monitoring
• Analyze all possibilities for integrating
parameters and methods. The most important func-
monitoring into design; cost out alternatives tions and benefits of monitoring programs are defined
using risk analysis in Section 3.3 and in Chapters 4 and 5.
3-2
Monitoring — Implementation
Objectives and Functions
3-3
—
Monitoring — Implementation
Objectives and Functions
• Determine assignments
3.3. Objectives and Functions of Monitoring
• Select instruments, components and systems
• Plan procedures for ensuring correct and ters 4 and 5. For monitoring to achieve these objec-
tives, it must serve five basic functions: diagnostic,
reliable data
predictive, legal, documentation and verification, and
• Plan instrument layout research and development. Depending on the specific
objectives, several or all of these functions come into
• Write procurement and Installation specifi- play. It is useful to examine these functions in a little
cations more detail, because they affect the level of the re-
quired monitoring effort, the types of monitoring re-
• Plan procedures for implementation; incor- quired, the contractual distribution of responsibilities,
porate in specifications and the impact of monitoring decisions on design and
construction parameters and on criteria.
Through combinations of the following five func-
tions, a number of benefits may be obtained by moni-
toring, as described in Chapter 4.
Engineering criteria for selecting instrumentation Diagnostic Functions. To determine the interaction
hardware, and installation and data acquisition me- of the soil and groundwater with excavation and con-
thods include at least the following: struction processes, to determine the suitability of
construction and dewatering details for a specific soil
• Reliability. The tunneling process is dynamic and environment, to form the basis for modification of
there may not be a second chance to recover data. these details during construction, and to help maintain
the safety of the work.
• Accuracy. There must be no question as to the Predictive Functions. To permit a prediction of soil
credibility and accuracy of the data. Provisions for behavior, face stability, and ground movements under
field verification are desirable. similar conditions later in the project; to predict future
and delayed settlements of streets and buildings; to
• Sturdiness. On building sites, vandalism and con- predict the effects of driving an adjacent tunnel; and to
struction hazards are rampant. Simplicity is preferred form the basis for modification of construction details
to sophistication. or implementation of protective features such as
grouting, underpinning, and compressed air.
• Monitoring must not impede construc-
Practicality. Legal Functions. Documents that show actual set-
tion and not introduce extraordinary costs. tlements, displacements and strains of streets, build-
ings and other structures —
before-and-after records
• Safety. Frequently, measurements must be taken in are valuable material during litigation, and may even
the midst of heavy street traffic; in such instances encourage out-of-court settlements of claims on the
remote reading may be suitable, though costly. part of property owners or contractors.
Documentation and Verification Functions. Obli-
As a rule, monitoring data must be examined and gations of the contractor, for example, to meet lines
analyzed quickly, and a task force must be made and grades within certain tolerances, or to conduct the
available to do so. The makeup of such a task force is work with contractually stipulated acceptable ground
described in Section 7.7. The credibility of the data movements, require documentation of the actual re-
must be assessed at once, and the impact on the sults of his work. In many instances assumptions
specific identified problems must be determined as
3-4
:
Monitoring — Implementation
Objectives and Functions
3-5
Fig. 4-1. Underpinning Design Chart.
4. Immediate Benefits of Monitoring
“
Traditionally underpinning of a structure
, is more often executed because of uncertainties in estimat-
"
ing settlements and their effects than because of the calculated effects of estimated settlements.
- The Author
Whenconstruction monitoring is part of a deliber- Some of the most important possible or probable
ate scheme to eliminate underpinning of structures, to immediate benefits of a well-conceived, planned, and
save on horizontal braces in an excavation, or to avoid executed monitoring program are discussed in this
installation of temporary tie rods in a tunnel, the chapter. Long-term benefits are discussed in Chapter
benefits can be measured with some accuracy in terms 5.
of dollars and cents. But how does one measure the
economic benefit of an accident that did not take
was not incurred, a building that did
place, a delay that 4.1. Cost Reduction Through Avoidance of
not crack? And how does one measure the value of Underpinning
monitoring data when they result in favorable claims
settlements out of court? A possibly large and tangible cost saving on a bored
Although many benefits associated with monitoring tunnel results from avoidance of utilities relocation,
are hard and tangible, other benefits, though signifi- underpinning or other protective measures. This sav-
cant, can only be realized intuitively or in probabilistic ing may come about in one of two fashions.
fashion. First, instead of providing positive protective mea-
sures, theowner and designer may elect to restrict
ground movements through prohibition of certain con-
struction methods that are known to result in exces-
sive ground losses. Alternatively, certain construction
Direct and Immediate Monitoring Benefits: methods designed to minimize ground losses may be
enforced. In these cases the contractor is required to
• Avoid underpinning — save money perform in accordance with specific ground movement
tolerances stipulated in the construction documents.
• Assist in restoration or safe maintenance
The cost of tunneling may increase, but the added cost
of structures
may be more than offset by the savings in protection.
In this instance, monitoring is required to show adher-
• Reduce some environmental hazards — set-
ence to requirements, to predict movements further
tlements, noise, fumes, etc.
down the line, and to diagnose sources of lost ground
• Safety — avoid accidents that may be eliminated through minor changes in
construction details.
• I mprove quality control In addition, it may be profitable to defer decisions
regarding underpinning until the contractor’s perfor-
• Reduce requirements for temporary sup- mance in a given environment has been evaluated. It is
ports while maintaining safety realized that this approach often encounters practical
opposition, and that it has rarely been followed in the
• Verify design assumptions past. The approach is clearly not possible for struc-
tures near the beginning of a contract, but structures a
• Keep track of important construction
few months down the line may well be treated this way.
parameters — groundwater loads, etc. If this course of action is selected, the design and
claims, etc.
are in increasing order of severity as previously dis-
cussed. Category settlements are the estimated mini-
I
4-1
,
mum and unavoidable settlements. Category 2 settle- repair cost (CR 2 may be estimated.
) Further, slight
ments are the peaks of the normal settlement profile, probability of incurring major Category 3 settle-
caused essentially by more or less random variations ments (P 3 may be estimated, and the effect of
)
of the soil or the construction details. Category 3 such settlement assessed in terms of hazards and
settlements are catastrophic settlements, those that rehabilitation costs.
should never occur, but that may occur due to totally
unanticipated soil problems or gross misjudgment of If the risk of Category 2 settlements occurring is P 2
soil conditions. Obviously, those personnel responsible = 30 percent, and the repair cost is CR 2 =
for such analyses and judgment must be highly quali- $50,000, the expected monetary value is
fied and experienced tunnel engineers on the design- $15,000. If the risk of Category 3 settlements is
er’s staff. While settlements of Category have an
I
P 3 = 4.0 percent and the rehabilitation cost isCR 3
occurrence probability near unity, settlements of Cate- = $500,000, then the expected value is $20,000.
gories 2 and 3 have probabilities of occurrence at a It is evidently advantageous to eliminate
given spot significantly less than one. underpinning.
To determine if a deferred decision is appropriate,
it is necessary to estimate costs of underpinning Such risk analyses are uncertain and are based on
(CUP! on the chart), construction monitoring (CM), assumptions regarding the contractor and the ca-
and repairs and rehabilitation if needed (CRi,CR 2 , pabilities of his procedures, made at a time when
CR 3 ). Recognizing that a deferred decision will, in the contractor is not even selected. However, if the
some instances, result in a need for underpinning, the effects of tunneling are monitored at an early stage
cost of that underpinning, including any delay costs, of construction, predictions can be made through
must also be estimated (CUP 2 ). To perform the risk careful analysis and extrapolation of real and appli-
analysis, probabilities of occurence must be estimated cable data. Thus, as soon as monitoring data are
(Pi P 2 P 3 ). including the probability (P 4 ) that moni-
, available, the risks can be reassessed intelligently,
toring will in fact indicate the need for underpinning. A and several options may be made available. If ex-
monitoring program is then required at the beginning cessive ground movements can be diagnosed and
of the project to verify magnitudes of settlements and shown to be caused by specific construction details
probabilities of occurrence, so that the deferred deci- and procedures, the contractor can modify these
sionmay be made. At the second decision point, the procedures, and the effect of the modifications can
termCR n P n refers to the largest ofCR Pi,CR 2 P 2
1
be ascertained through continued monitoring. If
and CR 3 P 3 The final verification of P 4 is made after
.
excessive ground movements must be ascribed to
executing the monitoring program, at which time field ground conditions more adverse than anticipated,
values replace estimated probabilities. and construction modifications cannot be counted
While this entire risk analysis and decision se- on to reduce the predicted settlements, then a
quence may appear complicated, it is not much differ- decision may be made to execute underpinning.
ent from the sequence of thoughts the owner and
designer must intuitively go through in any case where In this last instance, it is not usually possible to
a decision on underpinning or protection must be finish underpinning or other protection at the origi-
made. It is clear that, when used in this way, monitor- nally anticipated cost; also, a delay in tunneling
ing is an integral part of both design and construction must be expected. The protection may cost
and that construction documents must be carefully $200,000 instead of $150,000, and two weeks’
prepared to allow deferred decisions of this nature in tunneling delay may cost another $250,000, for a
an equitable fashion. total of CUP 2 = $450,000. This is three times the
originally estimated underpinning cost. Clearly, un-
Example: Assume that a building is located on the derpinning should not be performed in this in-
flank of the anticipated settlement trough, and stance, before construction begins, unless there is
Category 1 settlement of the building extremity is more than about 30 percent probability (P 4 that )
4-2
Immediate Benefits of Monitoring
to be moderate and where conventional underpinning procedure). At least the following options for modifica-
would be expensive, a suitable structure may be re- tion are usually available, depending on the general
stored through installation of a jacking system to allow procedure employed:
raising individual columns or walls as needed to nearly • Adjust the air pressure in a compressed air tunnel
maintain the original elevation of the structure. The to provide better support of soft clay or to counterba-
jacks may rest on the original foundations or on spe- lance hydrostatic pressures.
cially prepared new foundations. Settlements may oc-
cur quite rapidly, and nearly continuous monitoring is • Increase the efficiency of dewatering or temporarily
required as an integral part of this protection scheme. halt construction until the groundwater level is at an
As a variant example of this scheme, consider the acceptable elevation.
7th Street Bridge over 1-95 in Washington, D. C., where
four tunnels beneath the bridge would cause some • Institute or increase the use and effectiveness of
settlements. To minimize ground losses in the tunnel, face breasting.
the soil was stabilized by chemical grouting. Accept-
ing, nonetheless, possible slight damage or displace- • Apply ground stabilization locally (grouting,
ment of pier and abutments, the bridge girders were freezing).
individually adjusted by jacks as settlements occurred,
thus avoiding excessive twist or differential settle- • Prevent overexcavation in front of shield.
ments. Eventually, the bridge surface was restored and
bearings reconstituted, allowing continuous unhin- • Increase jacking pressure on fully covered wheel
dered traffic on the bridge. Here, again, settlement excavator.
monitoring is an integral part of the scheme.
Compensation Grouting or Mud-jacking. These are • Apply tail void filling sooner and more frequently to
techniques of injecting thick, viscous cement grout reduce time of exposure of soil in the tail void.
into the soil or beneath slabs to compact the soil and
raise the overlying structure. These techniques can be • Change backfill grout mix or replace grout seal if
4-3
immediate Benefits of Monitoring
face, for example, is reduced by proper face breasting. in the first tunnel, and it may itself become distorted.
Potentially, the most severe hazard is the innundation Monitoring is usually required to determine these ef-
of the tunnel by a massive soil and water flow. The risk fects and the needs for tie-rods.
of such occurrences can be virtually eliminated by
proper surveillance of the groundwater pressures in
the tunnel region, and by proper dewatering when 4.6. Benefits for Deep Excavations
needed.
Monitoring of groundwater pressures, or groundwa- Temporary remaining walls for deep excavations
ter levels, serves to reduce or eliminate the hazards of are designed for reasonably conservative earth pres-
major and minor soil and water flows into the tunnel sures and groundwater level assumptions. The distri-
and to check the efficiency and adequacy of dewater- bution of earth pressures and the movements asso-
ing procedures. Monitoring of water pressures imme- ciated with the excavation are quite uncertain, how-
diately at the crown of the tunnel before the leading ever, and monitoring is frequently called for to ensure
edge reaches the point of monitoring is particularly the compliance with assumptions regarding water lev-
important in this respect, but to preclude the possibil- els and to minimize ground movements.
ity of encountering water-bearing seams within the Cost savings may on occasion accrue by the moni-
height of the tunnel, observation wells extending toring of wall movements, settlements and strut loads.
throughout the height of the tunnel are also useful. If wall movements are considerably smaller than ex-
Depending on the general continuity of strata, these pected, or the effect of strut prestressing better than
observation wells do not necessarily have to be located anticipated, it is sometimes possible to eliminate some
within the horizontal extent of the tunnel. or all of the lower struts. Alternatively, the vertical
Other safety and health related monitoring efforts
4.5. spacing of struts may be increased, thereby not only
should include air quality, noxious and explosive reducing the cost of strutting, but allowing more effi-
fumes, air-borne dust, and special health hazards as- cient operations due to the improved working space.
sociated with compressed air tunneling. These items At the same time, monitoring of strut loads provides a
are not treated in this Handbook. measure of safety. Since buckling of a single strut or
snapping of a single anchor can have catastrophic
effects, monitoring of loads in some of these members
Verification of Design Assumptions allows the detection of dangerous overloads.
4-4
Immediate Benefits of Monitoring
4-5
tation Program.
5. Long-Term Benefits of Monitoring
”
those who refuse to learn from the mistakes of the past are forever condemned to repeat them.
Santayana
the past, most monitoring of tunnel construction, contracts, particularly those executed in the same
In
and a great deal of deep excavation monitoring, have geological setting; for example, future contracts of the
been performed to gather data for advancing the state- same transportation system.
of-the-art. In many instances, when monitoring was Many concepts of soil behavior applicable to tunnel
expected to benefit a project directly, this benefit was construction are reasonably well understood at this
not fully achieved due to inadequate planning or other time. However, the owner’s, designer’s, and contrac-
reasons. Yet these data, when subjected to later ana- tor’s confidence in predictions of soil behavior based
lyses, have increased the understanding of soil behav- on these concepts is limited for the following reasons:
ior, soil-structure interaction, and the effects of tunnel-
ing and deep excavations. • The quality and quantity of geotechnical data
The concepts discussed in the previous chapters (stratigraphy, soil properties) usually available for
have been directed toward the optimization of moni- analysis are insufficient for proper correlation with
toring benefits to the project from which the data are empirical data and for thorough theoretical analysis.
collected. Most of these data will also be extremely
• The concepts and methods of analysis have never
been fully tested by comparing predictions based on
full analyses with measured performance.
Types of Monitoring Projects Defined:
• Monitoring for Demonstration Projects: • The effects on soil behavior of a great variety of
available or conceivable construction procedures have
Verification and demonstration of eco-
not been critically tested.
nomic and technical feasibility and
applicability of novel techniques
• The great variety of construction procedures has
never been subjected to a full and critical review with
• Monitoring of Research Test Sections/
respect to their effects on soil behavior in tunneling.
Stations: Research and development in
local area of project, primarily to further
• Recorded experience of soil behavior is limited to
systemwide or national goals, secondarily several reasonably well-documented histories, many of
to benefit project itself which are not easily accessible, and most of which
have not been subjected to analyses using modern
• Intensive Project Monitoring: Often in-
concepts.
cludes test stations, primarily intended for
project control, secondarily for system- Because of the vagaries of tunneling and the pecu-
wide or nationwide goals. liar effects of tunneling on soil behavior, theoretical
work can only supply a background or framework,
• Limited Project Monitoring: Not usually
providing approximate functional relationships be-
including test sections; primarily serves
tween parameters, causes, and effects. No theoretical
legal and contractural obligations, and result can be trusted until verified and modified by
construction convenience (groundwater empirical data. Because of the importance of being
monitoring); secondarily useful for gather- able to predict tunnel behavior in advance, it is of great
ing systemwide and similar statistics importance to gather monitoring data intelligently and
to make these data available for research.
5-1
.
5.2. Local Systems Benefits verse relations between different agencies, of delayed
or incomplete dissemination, and of failure to carry
Several times in the recent past, major rapid transit through on the conclusions.
construction was begun in cities where no significant
comparable underground construction experience ex-
isted —
San Francisco, Washington, D.C., and Toronto 5.3. Systemwide Organization for Monitor-
are the most prominent examples and construction — ing and Construction Improvement
is beginning in other cities (Baltimore, Atlanta). Experi-
ences with sewer construction and deep basements It cannot be emphasized too strongly that such local
are often inadequate for extrapolation to the massive research and development through test sections, ex-
construction efforts required for underground rapid perimentation and demonstration projects, must be
transit. based on specific yet flexible goals and purposes, set
Each has its own geological setting and inherent
city out in advance, with a deliberate, dedicated, and con-
soil problems; each city develops its own basic require- tinuous program of interpretation, implementation
ments for a rapid transit system; and each city has its and dissemination. This requires attention, and invest-
own political environment. Many experiences learned ments, on the part of the owner and foresight on the
in one city cannot profitably be transferred to another part of his chief advisors. It also requires the establish-
city. ment of an organization within the organization: i.e., a
Sometimes the construction climate — union regula- group of knowlegeable professionals whose sole or
tions; availability of knowledgeable designers and
local primary purpose is to provide the continuous guidance
contractors; prevailing construction con-
types of and the implementation policy for a pre-considered
tracts; general fairness of reimbursement for con- improvement program. Such an improvement pro-
struction effort and settlement of claims; insurance gram may be set up, for example, as shown in Fig. 5-1
—
arrangements and regulations, etc. are just as impor- The systemwide monitoring implementation group
tant as the resolution of purely technical problems. For must initially be established by the Owner and his
this reason, demonstration projects in the beginning of Planners or General Designer. This group should in-
a series of major construction efforts are useful in clude geotechnical, instrumentation, and tunnel engi-
developing a proper atmosphere of mutual trust, lead- neers. Once established, this group is responsive to
ing to fairness of contracts and limitation of spurious the Owner’s needs. In addition, it is responsible for
law suits. Such demonstration projects require model developing the basic goals set up by the General
specifications and contractual arrangements, and full Designer and analyzing the feasibility of new goals it
documentation of the efforts, based in part on exten- may itself initiate. The scope may include items of
sive monitoring. improvement other than those directly related to moni-
But this is an intangible benefit. The development of toring, such as improvements to contract documents,
technological knowhow is of more direct relevance. improvements and standardization of design based on
Demonstration projects, or projects with test sections local conditions, and modifications of geotechnical
designed specifically for research and development exploration standards, all of which to greater or lesser
purposes, are extremely useful in defining the re- extent depend on observation and analysis of ongoing
sponse of typical local soil strata to tunneling and deep or completed projects.
excavations of various types, and in establishing crite- Results of the work should be channeled back to the
ria for dewatering, compressed air, geometry, and General and Section Designers as soon as they are
other technical details. Unknown problems, specifi- available. In this fashion early experiences may be put
cally related to the pecularities of local geology, may to use promptly. This feedback may take the form of
well surface in the course of such deliberate research. case histories or reports, and may be followed up by
When such data are accumulated, properly inter- recommendations that may become standards or
preted, and disseminated, they can serve to set or directives.
change basic design criteria, specifications, or con- To accomplish this, systematic procedures must be
struction for later projects in the system. In addition, developed to recover the necessary construction data
these data can serve to establish goals for ground and statistics. If a single Construction Manager is
movement control, and demonstrate what can, indeed, selected to serve as the Owner’s representative on all
be accomplished under the given circumstances. They separate contracts, the Construction Manager’s moni-
will also help in determining the proper attitudes to- toring team (see Section 7.7) may step in to provide
ward underpinning or other protection decisions, right- most of the necessary monitoring and other data;
of-way arrangements, insurance requirements and eq- indeed the Construction Manager could take over most
uitable types of insurance arrangements, all of which of the tasks described.If, on the other hand, construc-
in the final analysis spell financial benefits. tion supervision is done by different firms (e.g., the
Past experiences have not always fully demon- original Section Designers for different sections) a
strated these benefits. There have been problems with central group under the General Designer is required.
lack of centralized planning and coordination, of ad-
5-2
Long-Term Benefits of Monitoring
Similar benefits,perhaps with greater technical ing data, groundwater observations and observations
emphasis and less emphasis on administrative and of groundwater problems in tunnels are required.
contractual matters, are derived from proper develop-
ment programs based on construction monitoring, on 7. Development element computing methods
of finite
a national scale. Current sponsored research is, and for predictionground movements and lining
of
has been, emphasizing development of new theories stresses. Major problem is determining boundary con-
and technologies. The taking and utilization of con- ditions as function of construction procedures and
struction monitoring data has had but a small place in appropriate soil properties. All data in 1 through 4 and
the ongoing research programs. 6 above are required.
Tunnel construction monitoring is required in at
least three general areas:
8.Development of more appropriate and economical
methods of tunnel lining design. Data on stresses and
1.To verify assumptions made in the development of lining distortion are required.
new design and construction methods, for example,
during demonstration projects. 9. Development of criteria for design of grouting to
minimize ground loss and to serve as protection of
2. To improve the data base on which tunnel lining adjacent structures. Requires development of grout
design, selection of construction methods, specifica- selection criteria based on soil properties and stratifi-
tion writing, and the setting of construction criteria are cation, lab and field evaluation of grouted soil strength
made. and coherence, development of analytical procedures,
and field verification through testing, monitoring, and
3. To enhance the confidence with which designers observations.
and contractors regard the prediction of ground be-
havior during construction.
The following are also required for deep
excavations:
Some of the important concept developments for
tunneling that require accumulation of data from expe-
1 Improved analyses of beneficial effects of wall rigid-
rience are listed below. These concepts are not neces-
.
5-3
Fig. 6-1. Plan Showing Typical Layout of Instrumentation.
This illustration shows the arrangement of monitoring instru-
ments emplaced at the beginning of a tunneling project.
These instruments allow data gathering for project control,
for modification of tunneling procedures as required, and
for evaluating the need for protection of buildings further
along. Monitoring intensities and types of instrumentation
vary greatly with local conditions and specific project
requirements.
6. Selection of Monitoring Parameters and Hardware
explanatory. But it is necessary in this Handbook to be subject to change due to construction activity
more specific. Previous chapters dealt with various
• Parameter change must be associated with a signifi-
types of problems and their effects. In this chapter, the
cant problem related to cost, environmental impact,
,
• Soil and groundwater conditions predictive purposes, however, it is essential that the
data gathering points be distributed so as to make
• Type and location of existing structures
tion. At best, the interpretation and implementation • Should match capability of available personnel.
could be delayed; at worst, the real problems could be
buried in a huge volume of paperwork. The optimum
6-1
)
6-2
Selection of Monitoring Parameters and Hardware
SETTLEMENT, INCHES
SOUTH TUNNEL
Approaching Moving away
6-4
Selection of Monitoring Parameters and Hardware
Fig. 6-9. Aluminum Slope Indicator Casing. • Strain in Utilities (of limited use except when utili-
Self-aligning grooves in the casing orient the ties are truly continuous).
slope indicator instrument while readings
are taken.
6.4. Soil-Structure Interaction Monitoring
6-5
Selection of Monitoring Parameters and Hardware
Structural Loads and Moments in Walers, Soldier research purposes. Water pressures are measured
Piles or Walls. These are measured using vibrating using piezometers and earth pressures by either using
wire, resistance, or mechanical strain gages. earth pressure cells, or backfiguring from circumfer-
Horizontal Displacements of Temporary Retain- ential strain gage measurements at frequent intervals
ing Walls. Measurements of horizontal displacements around the liner. For cut-and-cover excavations earth
of temporary retaining walls (steel sheet piles, soldier pressures may be measured using earth pressure
piles, slurry-trench tremie concrete, or other) are very cells, but in practice these cells have frequently mal-
useful in determining the efficiency of the support functioned. Alternatively, pressures may be backfig-
system and the effects of excavation. Such measure- ured from load measurements in bracing, but it must
ments are often desirable when an excavation is adja- be remembered that horizontal earth pressures are
cent to existing structures, and settlements must be radically altered if bracing is prestressed.
minimized. Ordinarily, a series of inclinometer casings Thrusts and Moments in Tunnel Linings. Measure-
just behind the wall would be monitored for this pur- ments of these forces are required if a test station is
pose. Figure 6-14 shows a typical application of such completely monitored for research purposes. Circum-
measurements. ferential stresses and longitudinal stresses due to
Distortions of Tunnel Linings. These are observed shield jacking are measured using electrical strain
to verify that distortions will remain within tolerances gages with automatic recording facilities. Loads in
and to determine need for temporary tie-rods. Obser- shield jacks are most readily measured by adding a tee
vations are normally made to define increase in hori- in each hydraulic line and monitoring hydraulic pres-
zontal diameter and lowering of crown, using conven- sure using electrical pressure transducers.
tional surveying procedures. Typical results of such
measurements are shown in Fig. 6-15. Measurements
of the entire distorted shape are made for research 6.5. Gases in Tunnels
purposes, using a variable length tape or rod exten-
someter and a trilateration procedure. In many parts of the country, notably the Detroit
Earth and Water Pressure on Walls and Linings. and Los Angeles areas, natural gases in the soils pose
These measurements in bored tunnels are made for potential dangers of explosions in tunnels. Elsewhere,
6-6
Selection of Monitoring Parameters and Hardware
6-7
Selection of Monitoring Parameters and Hardware
OBSERVATIONS
OF
NO.
OBSERVATIONS
OF
NO.
6-8
Selection of Monitoring Parameters and Hardware
A 1 1 1
Above groundwater B 1
- 1 1
C 1 or 3 — 5 4
Below groundwater; A 1 2 — 2
no water control B 1 3 - 2
contemplated C 2 or 3 3 or 4 — 4
A 2 2 2
Below groundwater;
B 3 or 4 3 or 4 4
compressed air
-
C 5 5 4
Below groundwater; A 2 2 2 2
dewatering or B 2 3 or 4 2 or 3 2
other control C 3 5 5 4
5 = As 4 plus subsurface horizontal displacements; tail void encroachment; lining distortion; possibly
also temporary and permanent stresses in lining and earth and water loads in lining employed
for limited lengths only or for research.
— = Not applicable.
Note The above guide is a gross simplification, and selection must always recognize specific needs
:
and constraints of each project. Progress monitoring is required in all cases, and should include obser-
vations of ground movement from within tunnel and other factors listed in text “Progress Monitoring".
• Curvature of tunnel (from design drawings) to esti- • Environmental factors which may, in themselves,
mate theoretical ground loss due to plowing affect monitored data, for example temperature,
nearby construction activities
• Soil encountered, especially if different from ex-
pected and if associated with a problem • Incidence of extraordinary ground losses, ground-
water behavior, observed distress, deviations from
• Water quantity entering the tunnel through face or normal construction procedures, or any other unusual
elsewhere event
6-9
Selection of Monitoring Parameters and Hardware
A 1
— 1
Above groundwater B 1
- 1
C 1 or 3 — 4
Below groundwater; A 1 2 —
no water control B 1 3 -
contemplated C 2 or 3 5 —
Below groundwater; A 2 2 2
dewatering or B 2 3 2
other control C 2 or 3 5 4
4 = Groundwater if appropriate; strut or anchor loads; surface and subsurface settlements and hori-
zontal displacements of structures, soil and supporting walls; possibly stresses in walls and earth
and water pressures on walls.
— = Not applicable.
Note ; The above guide is a gross simplification, and selection must always recognize specific needs and
constraints of each project, and the conservatism of temporary support design. Progress monitoring is
required in all cases, and should include all factors listed in text "Progress Monitoring".
For cut-and-cover tunnels, progress monitoring • Complete as-bui/t construction plans and records,
should include at least the following: including pile drivingand soil log
• A record of depth of excavation versus time, at • Environmental factors which may, in themselves,
close stations, including berm details, if any affect monitored data, e.g. temperature, nearby con-
struction activities.
• Time of installation of walers and struts, with
all
6-10
Selection of Monitoring Parameters and Hardware
]
Typical layout for research Typical layout for high intensity
|
Soil-structure interaction monitoring not shown; these would include at least tunnel distortions.
Fig. 6-16. Typical Research and High-Intensity Monitoring Stations for Ground Movements
however, that this guide is highly simplified. It is diffi- • Six to twelve medium-intensity monitoring stations
cult to include possible conditions in a simple table,
all
and local practices, regulations, and labor conditions • Low-intensity stations roughly every 50 feet
influence the selection of monitoring parameters.
Some typical monitoring layouts are shown on the The research-type stations should be located near
accompanying figures following the tables. Figure the beginning and near the middle of the tunnel drive.
6-1 shows a monitoring plan at the beginning of a Since the initial distance of a tunnel drive is not usually
tunnel project. Figures 6-16 and 6-17 show typical typical of the contractor’s capability, a research-type
monitoring arrangements of various intensities. For a station should perhaps be placed one or several hun-
pair of bored tunnels some 2,000 to 3,000 feet long dred feet from the beginning.
in soil, where construction monitoring is deemed vital, However, it is important that any problems be
a suitable selection of monitoring stations or cross diagnosed early. Therefore, several high-intensity
sections might include: monitoring stations should be placed within the first
several hundred feet. Other high-intensity stations
• Two research-type stations should be placed where ground conditions have
changed significantly, or where the data would have
• Four to six high-intensity monitoring stations specific interest relating to existing structures down
6-11
Selection of Monitoring Parameters and Hardware
Line of
the line. Medium- and low-intensity stations would be The necessary number and the location of observa-
placed so as to gather sufficient coverage and suffi- tion wells depend greatly on the geologic conditions
cient statistical material and to cover specific existing and on the locations of dewatering wells.
structures. For deep excavations, monitoring points may in-
The layouts shown are idealized. With street and clude surface settlements and horizontal displace-
building patterns prevailing in downtown areas where ments every 50 feet along the wall, and inclinometer
monitoring is of interest, it is not usually possible to casings every 200 feet. The need for strut or anchor
provide complete monitoring stations. The station lo- load measurements will depend greatly on the type of
cations should be carefully chosen to take advantage structure.
of available space and to minimize traffic interference.
Some of the measuring points may be on the exterior
walls of buildings. It is often of interest whether the 6.8. Monitoring Cost
adjacent ground surface settles more or less than the
building; therefore, it is often useful to place observa- The cost of monitoring includes not only the pro-
tion points on the ground and on the building, close curement and installation of instruments and reading
together. points, but also the design work, maintenance and
It is sometimes also necessary to monitor ground reading, and interpretation work. Often, the instru-
movements inside buildings; for example, interior col- mentation itself is but a small portion of the total cost.
umns, basement floors, or walls might be monitored. For most buried instruments, the cost of installation
These points, however, are often poorly accessible, exceeds the cost of the instrument itself. Assuming
and their number should be minimized. that drilling a hole 4 inches in diameter costs $10 per
6-12
Selection of Monitoring Parameters and Hardware
foot (or adrill rig costs $450 per day), some typical through several contract items and amongst the own-
estimate prices for procurement and installation of er, designer, contractor, and inspecting engineers.
type and length of cable installation probably the most important type of ground move-
(not applicable to inclinometer) ment monitoring. Deep settlement anchors should not
add for each $1 ,000-$1 ,500 be eliminated as a cost-savings measure.
Dollar for dollar, the most cost-effective and essen-
Marking and installing surface points,
tial effort is in the interpretive and implementation
per point
work, provided sufficient data are available for use.
Following is an example of monitoring essentially
for research purposes; items of soil-structure interac-
These estimates include the cost of engineering tion monitoring are included.
supervision, but not of special readout equipment,
survey instruments, inclinometer torpedoes, and other Example: A sewer tunnel in Staten Island was in-
equipment. strumented essentially for research purposes as
With prices such as these, the procurement and follows:
installation costs of the complete stations, shown pre-
viously on the figures, are about as follows: • Strain gages to measure tunnel lining
stresses caused by jack shoving loads
Typical research monitoring station: $22,000
• Strain gages to measure also circumferential
High-intensity monitoring station: $5,500 stresses
Finally, the use of a computer for data storage and a problem akin to the determination of precisely how
retrieval and assistance in interpretation, is estimated many exploratory borings and tests are necessary to
at between $1 5,000 and $20,000. properly carry out design and construction. It is intui-
The total cost of a complete, intensive monitoring tively known that the more data obtained, the better
program is, of course, highly variable, depending on its that conditions can be predicted. Yet, there is a point
purpose and magnitude and the general conditions. To of diminshing returns, and a point at which ordinary
obtain the full benefits of a program of the scope just data handling and engineering just cannot cope with
outlined, a cost of at least $200,000 to $300,000 the mass of data to derive meaningful results. With
must be expected. These costs are not often easily future computer usage, perhaps the utility of such
determined on an actual project, since they are spread large data quantities can be extended.
6 - 13 / 6-14
7. Tools for Implementation
7-1
Tools for Implementation
may make it desirable to let the contractor monitor monitoring devices (often through
parameters that are not strictly essential for his work specialist subcontractor)
but may be required for other purposes.
The responsibilities of the designers are relatively • Supervise and check contractor data
clear. They must define the scope and purpose of recovery
monitoring; prepare contract drawings, specifications
and other materials such as to take full advantage of • Interpret
monitoring benefits; select monitoring parameters; de-
• Implement
sign a monitoring program, including instrumentation;
and prepare the necessary specifications for monitor- The responsibilities of the contractor, which should
ing and instrumentation. They must also advise the be carefully defined in the specifications, would in-
owner of the most appropriate contracting arrange- clude the procurement and installation of all instru-
ments, insurance arrangements, and inspection proce- ments within his direct work area, and certain other
dures. It is clear that inspection, insurance, contract- types of instruments. They would also include certain
ing procedures, and specifications must mesh, but reading and maintenance tasks, replacement and re-
several combinations of arrangements may work moval of instruments, restoration, etc. The contractor
satisifactorily. may or may not be required to install instruments
7 2
Tools for Implementation
Type of
Instrumentation Simple Sophisticated Sophisticated
Monitoring
Location of
Outside contractor Inside contractor
Instruments or Anywhere
work area work area
Monitoring
Regular Item in
.n
Suitable Not suitable Not usually suitable
l/l Prime Contract
'c
Fui
Install
Separate
to Not required Suitable Not usually suitable
Specialist
ract
and
Contract
+>
c
o
o Cost-Plus Items
Not required Suitable
Suitable, usually
in Prime Contract preferable
outside his direct work area. As a rule, the contractor and necessary follow-up of the monitoring program. It
must employ a specialist instrumentation subcontrac- isprobably necessary, as a general rule, to employ the
tor to supply, install, and maintain —
and possibly read- consulting services of the original designer if he is not
— sophisticated or complex instrumentation. Contrac- himself conducting construction inspection. The vari-
tual arrangements must ensure that the specialist ous possible arrangements and organizations for im-
instrumentation subcontractor is employed on the ba- plementing a monitoring program are examined in the
sis of experience and cost, rather than on cost alone. following section.
The contractor must also be responsive to sugges-
tions and/or directives based on the results of moni-
toring. Clearly, monitoring is a way of measuring a
contractor’s performance, and certain boundaries 7.3. Contract Arrangements
would have been established to define acceptable
performance. If the contractor does not meet perfor- The most feasible contract arrangements are ap-
mance requirements, modifications to his construction parent from the preceding discussion, but some spe-
methods or remedial actions may be required. Specifi- cial concerns and favorable arrangements should be
cation items must be included to cope with this noted. The box indicates three basic contract types
situation. that may be used for various monitoring programs.
The responsibilities of the inspecting engineers are Items Within Contractor’s Expertise. Monitoring
somewhat broadened by the effective use of monitor- and instrumentation items that do not fall outside the
ing. They include supervision of instrument procure- ordinary contractor’s expertise may be included in the
ment and installation in accordance with specifications specifications as contractor-supplied items (unless
and standards, certain reading and maintenance supplied and handled by the inspecting engineers).
tasks, and data storage, retrieval, interpretation, and These may include:
implementation, i.e., corrective action if required. It is
very important that the inspecting engineers are fully • Observation Wells. Standard, standpipe-type wells
aware of the designer’s intent as regards the purposes or piezometers installed according to standard specif i-
7-3
Tools for Implementation
cations at locations and elevations to be indicated by With this arrangement, the owner is assured quality
the design engineer. Elevations may be subject to field instrumentation and monitoring work because the spe-
changes depending on soil stratification; it is desirable cialist will be hired on the basis of qualifications, not
to place well screens immediately at a boundary be- solely on least cost; yet the specialist works for the
tween a lower impervious and upper pervious stratum, contractor, who will be able to properly schedule all
particularly if the tunnel is in part to be located in the required work with least interference. It is also possible
pervious stratum. tomake even radical changes to the monitoring pro-
—
gram during the course of the work which is often
• Dimensional Measurements Within Tunnel. The necessary or desirable —without having to stop for
contractor will, for his own purposes, need a surveying lengthy renegotiations with the contractor.
system for steering and control of alignment and Monitoring items that may fall into this category
dimensions. Due to the severely restricted space avail- include, for open cuts, loads and stresses in anchors or
able within the working tunnel, the introduction of tiebacks, and displacements within the excavation; for
unnecessary people, agents, measuring gadgetry and tunnels, monitoring of tail void space encroachment,
activities must be discouraged to minimize interfer- stresses and loads in linings or tierods, and extensom-
ence with work progress. To avoid conflicts, in-tunnel eters, if required.
measurements (alignment checks, crown elevation, Where the owner or the construction manager em-
horizontal diameter, and variations of these) should ploys a team devoted to the implementation and utili-
usually be made by the contractor or an agent under zation of monitoring efforts (more or less as described
his control. The log books of activities (chronological in Section 5.3), it would sometimes be appropriate to
record) of grout quantities and water discharge quanti- execute these types of monitoring directly by this team
ties may also be kept by the contractor. or under its jurisdiction. Supervision approval, check-
ing, interpretation, and implementation certainly fall
Itemphasized that the inspecting engineer must
is within this team’s responsibility.
have and immediate access to these data, must be
full Items Outside Contractor’s Work Area. A third
allowed to monitor the taking of data, and must make category of monitoring items can be performed by
occasional verification as needed. As for the observa- noncontractor personnel with little or no interference
tion wells, the inspecting engineers must have access with contractor progress. This category includes sur-
to their reading as well. face settlements and horizontal displacements of sur-
Conventionally these items can be included in the face points and points on buildings adjacent to open
bid. Observation wells can be included with a bid price cuts and over tunnels; deep settlements measured by
per unit or per foot of installed well. These prices extensometer rods or similar; and deep horizontal
should include maintenance, reading, replacement, displacements measured by inclinometers. Though at
and removal. In-tunnel measurements and logging can least the surface settlements could be read by the
be included either as a separate lump sum or as part of contractor, all of these items could be made the re-
excavation costs. sponsibility of the inspecting engineers (but allowing
Minimum requirements for log keeping as to detail the contractor access to the data). This will allow
and frequency must be presented in the specifications. consistency in the taking and interpretation of the
It is often a good idea to present a form or format to be data. Groundwater level observations may be included
used for data presentation. in this package of monitoring, as well, provided the
Items Outside Contractor’s Expertise. Items that contractor has the opportunity to request readings to
fall outside most contractors’ expertise, but are signifi- serve his needs.
cantly within their areas of work, or are of significant Since the measurement of ground movements and
pecuniary interest to the contractor, should be in- their effects is part of the owner’s control of the
cluded in his contract as cost-plus items, but should be contractor’s performance and not usually or tradition-
carried out by a specialist subcontractor. It is recom- ally of the contractor’s interest, it stands to reason
mended that the required specialist instrumentation that, while the contractor may well install parts of the
subcontractor be selected in advance by the owner on monitoring system, most such monitoring and all inter-
a professional basis, or by the contractor in accor- pretation should be the responsibility of the inspecting
dance with strict qualification requirements, and be engineers in collaboration with the original designers.
subject to approval. The contractor will be allowed to Often, however, because of the relative simplicity of
bid a markup on the specialist’s estimated cost to the work, surface settlements are measured by the
retain a degree of competition, but will not be responsi- contractor. Groundwater level observations are also
ble for the final selection of the specialist nor will he —
most often carried out by the contractor or more
control his price. The approximate cost must be esti- —
properly by his dewatering subcontractor as an inte-
mated by the designer (and/or the specialist) and gral part of his dewatering program.
entered in the bid schedule as fixed. The scope of the
instrumentation work must be presented in such detail Example: For a section of the Baltimore Rapid Tran-
that the contractor may assess the possible interfer- sitSystem, the proposed distribution of duties and
ence with his work. responsibilities are as follows:
7-4
Tools for Implementation
7-5
Tools for Implementation
the Engineer’s consent, unless he tions and responsibilities as set forth herein or as
ceases to be in the Consultant’s amended by mutual consent, the Engineer may
employ. deem this non-compliance to be just cause for
D. Responsibilities and Duties. dismissal. The Engineer may then order the termi-
(1) Know all available relevant geo- nation of the Consultant’s services and his immedi-
technical data ate replacement, and may order cessation of all
(2) Know the purpose and intent of related or affected work, until such time as the
monitoring instrumentation program is again operative in the
(3) Perform pre-installation tests opinion of the Engineer, all at no extra cost to the
and calibrations as necessary to ensure Owner.
acceptability and proper function of all
instruments 6. Inspection and Data Availability
(4) Install or supervise installation of The Owner, Engineer, or any designated rep-
all required equipment and service resentative may inspect equipment to be used, may
same inspect installation and monitoring operations, and
(5) Perform all required measure- may perform his own observations using any in-
ments, readings, and observations stalled equipment. Ail data and observations shall
(6) Report all certified data to Engi- be available to all parties of the contract. However,
neer in accordance with designated no data shall be divulged to any outside party or
schedules published in any form at any time without the
(7) All monitoring items, instrument, Owner’s written approval.
and equipment selection and schedules
to be approved by the Engineer 7. Measurement and Payment
(8) Evaluate and interpret all data (if A. Hardware. Payment for equipment and
selected to be within Consultant’s instrumentation hardware based on ac-
3.
duties). Notify Engineer of any devia- tual cost, supported by approved pur-
tion from design assumptions or crite- chase invoices, to include all procure-
riaor established trends. Recommend ment, delivery, and storage expenses.
course of action if required
B. Labor. Payment for direct labor
(9) Submit interim and final reports other than that performed by persons
as scheduled herein in Consultant’s employ, performed un-
(10) Attend all meetings that are der the Consultant’s supervision and at
deemed necessary for the progress of his request, plus associated materials,
the project, at the request of the at cost plus overhead, plus a 10 per-
Engineer cent profit, based on documented ex-
(11) Perform such other duties as may penditures. (Other force account pro-
be requested by the Engineer, consis- cedures may be used.)
tent with the requirements of this
C. Consultant Services. Payment for Con-
section
sultant’s services on a professional fee
E. Program Planning.
basis based on approved, negotiated
(Contains schedule of required confer-
subcontract between Contractor and
ences and submittals, and methods of
Consultants, plus a Contractor's
submitting modification proposals.)
markup of maximum 10 percent (bid
item).
Instrumentation and Monitoring
(Contains all procurement, storage, installa- D. Allowances. Include the following
tion, servicing, protection, and monitoring specifi- allowances in Base Bid to cover all work
cations and schedules, restoration requirements, specified in this section. Actual pay-
and equipment salvage procedures; for more detail ment shall accordance with the
be in
7-6
Tools for Implementation
Portions of the monitoring program to be carried Either way, the specification or contract must, in
out by the contractor can be detailed in relevant addition to the elaboration of the general contractual
sections of the technical specifications. For example: arrangements and requirements, contain the neces-
sary details of instrument selection (if not already
• Observation well installation and monitoring, when selected), procurement, installation, reading, and re-
carried out by the contractor, belong in the section on porting. The scope of this Handbook does not allow a
dewatering. In this way, the observation of groundwa- complete description of detailed instrumentation
ter more clearly becomes an integral part of the dewa- specifications. For this, the reader is referred to Cord-
tering program. ing etal (1 976), Schmidt and Dunnicliff (1 975) and a
7-7
Tools for Implementation
• Removal: Instrument removal and restoration of those directly related to steering and the achievement
street surface; salvage of instruments if possible. of devised tunnel geometry. This item may also be
placed in the instrument specification.
• Checks and Calibrations: Calibrations where possi-
ble at regular intervals and/or immediately before • Explanation of all monitoring efforts not included in
critical measurements. the contractor’s efforts, but which may affect his work.
• Measurement Schedule: Timing and frequency of • Incentive awards (or penalties) based on monitored
readings related to construction progress and actual performance. Cash awards may be made for the driv-
data. ing of tunnels in designated sections with resulting
settlements less than a specified amount. The first, say
• Other Data: Those that are necessary for interpreta- 100 feet, may be excluded from such award, and the
tion, such as temperature, progress data, and miscel- award may be reduced by a progressive formula for
laneous observations. each segment unsuccessfully tunneled.
• Record Keeping and Reporting: Format of records, Example: Assume 3,000 feet of twin tunnels in an
schedule and timing of reports. urban area. A maximum $300,000 award may be
given for driving these tunnels from a point 100
These items of specifications for monitoring and feet from the edge of the construction shaft to the
instrumentation deal with the data gathering process. end, with monitored settlements everywhere less
The manner of implementing the results of the moni- than, say, two inches. For each 100-foot section
toring program is, perhaps, of even greater impor- (with designated boundaries) completed with maxi-
tance. If there is no mechanism for requesting a modi- mum single-point settlement between two and three
fication of work methods based on monitoring data, inches, but average centerline settlement less than
the data become nearly useless except as a legal and two inches, $10,000 would be subtracted from the
contractual record. The next section examines some of award. For each 100-foot section with maximum
the ways to provide equitably for such modifications. single-point settlement greater than three inches,
or average greater than two inches, $20,000 would
be subtracted. The settlement measurements.appli-
7.5. Specifications for Implementation cable to this provision would be those taken after
the second of the twin tunnels has passed 100 feet
General Contractual Provisions. Specifications are beyond the section in question.
often separated into three parts: the general provi-
sions, the special provisions, and the technical specifi- Depending on the type of insurance and arrange-
cations.The complete document also includes plans ments with adjacent property owners, incentives could
and drawings. The general provisions are included in also be tied to recognized damage or claims from
allcontracts of the type considered. property owners.
Since monitoring programs are tailor-made for indi- Technical Specifications. The items to be covered
vidual contracts, little material relevant to monitoring under technical specifications are discussed in the
enters the general provisions. These do, however, spell following subsections.
out in general terms the contractual and insurance
arrangements that may have relevance to the writing • Instrumentation and Monitoring. The specifications
of other pertinent paragraphs in other parts of the covering the instrumentation and monitoring efforts
specifications. themselves are described in Section 7.4.
Special Provisions. These will contain some or all of
the following items: • Excavation. Excavation covers a multitude of con-
struction efforts.Some or all of the following items
• Amendments and additions to the general provi- may be affected by monitoring results.
sions regarding contractual arrangements, such .as the
requirement that the instrumentation specialist to be 1. If compressed air is used, the air pressure
in charge of specific items (mandatory), be (a) the one may be determined in part on the basis of
selected by the owner, (b) one of several specialists ground movement monitoring and observa-
prequalified by the owner, (c) meet specific qualifica- tions at the face.
tion requirements and approved by the engineer.
2. Face support may be requested or modified
• Method of payment for monitoring and instrumen- based on monitoring data and observations.
tation tasks designated for the contractor to imple- Note that anticipated face support require-
ment. Preset estimated cost with markup as the sole ments may affect the contractor’s choice of
bid item is preferred for most of these tasks except equipment (wheel or hoe excavator).
7-8
Tools for Implementation
3. Excavation beyond the cutting edge of the standby grouting equipment (with a mobilization bid
shield may or may not be allowed, depending item), (2) availability of qualified grouting personnel
on monitoring data. This item may work out to at, say, 24-hour notice, and (3) unit bid items (or upset
the advantage of the contractor, allowing him items) for grout application by measured materials
to work ahead of the face if data are and for delay time measured from the time the engi-
favorable. neer requests or approves the grout application and
tunnel driving stops until the last grout application is
• Dewatering. As an example, work may be halted (at finished. Such grouting may be conducted from the
no extra cost for delay time) if soil is not adequately ground surface or from the tunnel itself. In the former
dewatered by the system of wells. The term ‘‘ade- case, delay time may not be invoked. Grouting in lieu of
quately dewatered" must be clearly defined, e.g. by the dewatering shall not be paid for unless the ground
allowed height of groundwater above an impervious water has been drawn down to the required elevation
strata boundary. The requirement may be relaxed if or unless the engineer determines that it is impractical
monitoring data and observations demonstrate that no or impossible to do so.
significant ground movement or ground loss will result.
While the layout of observation wells may be developed • Excavation (Shafts and Stations). The maximum
in principle by the designer, it is considered advisable allowed excavation depth below the last installed strut
to have the contractor or his subcontractor design the or anchor level should be stipulated. If unanticipated
dewatering system and the detailed layout of observa- excessive ground movements can be ascribed to this
tion wells. To achieve the most efficient dewatering feature by diagnostic analysis of monitoring data, the
system, it is usually necessary to log the soils en- maximum allowed excavation depth may be adjusted.
counted during placement of pumping and observa- Assuming, however, that the engineers have not disap-
tion wells, and to monitor both pumped quantities and proved excavation and shoring plans submitted by the
water levels in observation wells. Specifications should contractor, a reimbursement for the extra effort is
require a groundwater monitoring effort that is com- called for, and provisions should be made for negotiat-
mensurate with the anticipated approach to dewater- ing this as a change. In rare instances, appropriate bid
ing, and the complexity of the groundwater regime, to items based on several different support spacings may
be carried out by the contractor. Observations at the cover this contingency. If, on the other hand, excava-
tunnel face and in the excavation are necessary to tion at one point has reached bottom with ground
ensure that the dewatering goals are achieved. movements better than anticipated, the contractor
may be allowed to propose a greater support spacing
• Lining and Backfilling. The success of ground con- or other changes, subject to approval and negotiation
trol inthe region of the tail void is highly dependent on of a reduced price.
proper timing and execution of grout backfilling. In
areas of caving soil (as diagnosed by observations • Bracing. Should strut load measurements or other
and/or by measured ground movements, preferably observations indicate impending danger, the contrac-
extensometers just above the centerline), grout shall tor shall be obliged to stop any work that might
be applied under adequate pressure to achieve com- increase the danger and install appropriate additional
plete filling as soon as possible after each shove. This support at no extra cost to the owner unless conditions
requirement may be relaxed in areas shown to be qualify for the changed condition clause.
stable. The grout seal shall be maintained in an ade-
quate state of repair. Work may be halted (at no extra • Underpinning and Other Protection. It is unlikely
cost to the owner) if the seal will not allow proper filling that unanticipated underpinning would be required
in diagnosed caving areas. Temporary tie rods may be during the course of construction. This may happen
required until grout backfilling is complete if measure- when an underpinning decision has been deliberately
ments show difficulty in achieving the desired circular deferred and performance monitoring discloses signif-
shape (the acceptable deviations must be defined else- icantly adverse ground movements, or it may be due to
where under tolerances). Likewise, temporary tie rods truly changed and adverse conditions. In such in-
may be required in soft soils in the first of two twin stances, provisions should be available for giving the
tunnels when the second tunnel passes nearby, if contractor standby payments, perhaps deliberately
measurements show excessive distortions of the first preset lower than cost to discourage misuse of such an
tunnel due to the driving of the second tunnel. A unit item, and a negotiated or force account payment for
price pay item is needed for each tie rod installed and underpinning items. It is easier to accommodate within
removed with the engineer’s approval or at his request. the contract additional protective work in the form of
injection grouted walls or foundation support. Such
• Ground Improvement. Where injection grouting is work may be included in a format similar to that
foreseen as a possible remedy against excessive indicated previously under Ground Improvements.
ground movement, ground losses at the face or in the
tail void, or ground losses caused by groundwater flow, • Final Note on Specifications. It must be recognized
the specifications should require (1) the availability of that no specification items and no monitoring can be
7-9
Tools for Implementation
7-10
Tools for Implementation
7 - 11 / 7-12
Bibliography
Design and Construction of Tunnels and Terzaghi, K., “Geological Aspects of Soft Ground Tun-
Deep Excavations neling,” Applied Sedimentation, 1950.
Ash, J.L., Russell, J.E., Rommel, R.R., “Improved Sub- Xanthakos, P.P., “Underground Construction in Fluid
surface Investigation for Highway Tunnel Design and Trenches,” presented at National Education Seminar,
Construction,” report prepared for Federal Highway University of Illinois at Chicago Circle, 1974 (avail-
Administration, 1974 (FHWA-RD-74-29/30). able: Prof. M.L. Silver, Department of Materials Engi-
neering, University of Illinois, Chicago Circle, Chicago,
Deere, D.U., Peck, R.B., Monsees, J.E., and Schmidt, B., Illinois 60680).
“Design of Tunnel Liners and Support Systems,” re-
port prepared for the Office of High Speed Ground
Transportation, 1969 (NTIS No. PB-1 83-799). Contractual
Peck, R.B., “Deep Excavation and Tunneling in Soft Abrahamson, M., “Contractual Risks in Tunneling:
Ground,” 7th International Conference on Soil Me- How They Should Be Shared,” Tunnels and Tunnelling,
chanics and Foundation Engineering, State-of-the-Art London, January and March 1974.
Volume, pp 225-290, Mexico, 1969.
National Committee on Tunneling Technology, “Better
Peck, R.B., Deere, D.U., Monsees, J.E., Parker, H.W., Contracting for Underground Construction,” prepared
and Schmidt, B., “Some Design Considerations in the for National Science Foundation, UMTA, and Corps of
Selection of Underground Support Systems,” report Engineers, 1974 (NTIS No. PB-236-973).
prepared for the Office of High Speed Ground Trans-
portation, 1969 (NTIS No. PB-190-443).
Ground Movements
Schmidt, B., Dunnicliff, C.J., Alsup, S.A., and Mataraz-
zi, B., “Subsurface Exploration Methodologies for Soft Peck, “Deep Excavation,” 7th Int. Conf., 1 969.
Ground Rapid Transit Tunnels,” prepared for U.S.
A
Bibliography
Effects of Ground Movements Cording, E.J., Hendron, A.J., MacPherson, H.H., Han-
smire, W.H., Jones, R.A., Mahar, J., O’Rourke, T.D.,
D’Appolonia, D.J., “Effects of Foundation Construction “Methods for Geotechnical Observations and Instru-
on Nearby Structures,” proc. 4th Pan American Con- mentation in Tunneling,” report prepared for National
ference of Soil Mechanics and Foundation Engineering, Science Foundation, 1976.
V. 1, pp 189-236, Puerto Rico, 1971.
Grant, R., Christian, J.T., Vanmarcke, E.H., “Differen- Schmidt, B., Dunnicliff, C.J., "Construction Monitoring
tial Settlement of Buildings,” proc. ASCE, GT9, pp of Soft —
Ground Rapid Transit Tunnels A Definition of
973-992, 1974. Needs and Potential Developments,” prepared for U.S.
Department of Transportation, Urban Mass Transpor-
Skempton, A.W., MacDonald, D.H., “The Allowable tation Administration, 1974 (NTIS No. PB-241-535,
Settlements of Buildings,” proc. Institution of Civil 241-536,241-537).
Engineers (ICE), V. 3, 1956.
Terzaghi, K., Peck, R.B., “Soil Mechanics in Engineer- London Clay,” proc. 6th International Conference,
ing Practice,” Wiley, 1967. S.M. and F.E., V. 2, pp 432-436, Montreal, 1 965.
B
DOT LIBRARY
7A E5
'
T.
•I
i
U.
S.
KENDALL
a
2
>
DEPARTMENT
TRANSPORTATION
SQUARE.
i
OF