TOTAL
JUMLAH JADWAL PELAKSANAAN
HARGA
No URAIAN PEKERJAAN BOBOT % KET
MINGGU KE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
PEKERJAAN PENDAHULUAN
PEKERJAAN PENDAHULUAN Rp 22,100,000.00 0.40 0.13 0.13 0.13
PEKERJAAN SARANA DAN PRASARANA PEKERJAAN Rp 11,800,000.00 0.21 0.11 0.11
PEKERJAAN PLUMBING
PEKERJAAN PENGADAAN POMPA AIR BERSIH Rp 50,000,000.00 0.90 0.23 0.23 0.23 0.23
PEKERJAAN INSTALASI PEMIPAAN AIR BERSIH TOILET Rp 9,045,456.66 0.16 0.08 0.08
PEKERJAAN INSTALASI PEMIPAAN AIR AIR BEKAS, KOTOR DAN VENT Rp 47,324,845.50 0.85 0.43 0.43
PEKERJAAN INSTALASI PEMIPAAN AIR AIR HUJAN Rp 10,004,373.75 0.18 0.18
5,550,842,084.33 100.00
TOTAL 5,550,842,084
PPn 10 % 555,084,208
JUMLAH TOTAL + PPn 10 % 6,105,926,293
100.00 WAKTU PELAKSANAAN 160 HARI KALENDER
JUMLAH TOTAL DIBULATKAN 6,106,000,000
RENC. MINGGUAN % 0 0.24 2.13 1.89 1.89 1.89 3.79 2.03 2.42 5.98 4.79 3.29 3.66 6.63 3.97 6.74 9.34 10.02 9.59 9.38 7.38 2.97 - -
RENC. KOMULATIF MINGGUAN % 0 0.24 2.37 4.26 6.15 8.04 11.83 13.86 16.28 22.26 27.05 30.33 33.99 40.62 44.59 51.32 60.66 70.68 80.27 89.65 97.03 100.00 100.00 100.00
PROGRESS RENCANA RENC. BULANAN %
KOMULATIF BULANAN %
Keterangan : PHO
HADI PRANOTO, ST
Direktur
REKAPITULASI
RAB
KEGATAN : REHAB SEDANG / BERAT GEDUNG KANTOR
PEKERJAAN : REHAB GEDUNG KESBANGPOL PROV. JAMBI
LOKASI : KOTA JAMBI
TAHUN ANGGARAN : 2015
JUMLAH HARGA
NO. URAIAN PEKERJAAN
( Rp.)
1 2 3
B PEKERJAAN INTERIOR
I PEKERJAAN INTERIOR 166,709,900.00
HARGA TOTAL
NO. URAIAN PEKERJAAN SAT. VOLUM
SATUAN HARGA
E
1 2 3 4 5 6
JUMLAH I 5,100,000.00
II PEKERJAAN TANAH DAN URUGAN
JUMLAH II 1,600,798.80
III PEKERJAAN PONDASI, KOLOM HINGGA SLOOF
1 Pek. Cor Lantai Kerja Bawah Pondasi K100 M3 1.44 752,070.00 1,082,980.80
2 Pek. Pondasi Batu Bata M3 9.76 1,054,470.00 10,291,627.20
3 Pek. Beton Bertulang Pondasi Tapak uk. 60 x 60 cm K-175 ( 120 Kg Besi + Bekisting ) M3 1.00 4,337,200.00 4,337,200.00
4 Pek. Beton Bertulang Sloof uk. 20 /30 cm K-175 ( 126 Kg Besi + Bekisting ) M3 1.08 4,865,261.60 5,254,482.53
5 Pek. Beton Bertulang Sloof uk. 15 /20 cm K-175 ( 165 Kg Besi + Bekisting ) M3 0.92 5,434,919.00 5,000,125.48
1 Pek. Beton Bertulang Kolom Uk. 30 / 30 cm K-175 ( 115 Kg Besi + Bekisting ) M3 4.10 6,055,289.00 24,826,684.90
2 Pek. Beton Bertulang Kolom Uk. 20 / 30 cm K-175 ( 100 Kg Besi + Bekisting ) M3 1.51 5,836,190.00 8,812,646.90
3 Pek. Beton Bertulang Kolom Praktis Uk. 11 /11 cm K-175 ( 225 Kg Besi + Bekisting ) M3 0.35 7,662,015.00 2,681,705.25
4 Pek. Beton Bertulang Balok B2 Uk. 13/15 Cm elv. + 3,20 cm K-175 ( 215 Kg + Bekisting ) M3 0.29 7,650,949.00 2,218,775.21
5 Pek. Beton Bertulang Balok B1 Uk. 20/30 Cm elv. + 3,20 cm K-175 ( 165 Kg + Bekisting ) M3 1.44 6,920,619.00 9,965,691.36
6 Pek. Beton Bertulang Plat Dak T. 12 Cm elv. + 3,20 cm K-175 (110 Kg + Bekisting ) M3 2.85 5,673,265.00 16,168,805.25
7 Pek. Beton Bertulang Ring Balok Uk. 13/15 Cm elv. + 3,50 cm K-175 ( 215 Kg + Bekisting ) M3 0.32 7,650,949.00 2,448,303.68
8 Pek. Beton Bertulang Ring Balok Uk. 13/15 Cm elv. + 4,20 cm K -175 ( 215 Kg + Bekisting ) M3 0.72 7,650,949.00 5,508,683.28
JUMLAH IV 72,631,295.83
V PEKERJAAN PASANGAN DAN PLASTERAN
1 Pek. Pas. Dinding Bata Tebal 1/2 Bata ad. 1 : 4 M2 111.89 87,035.00 9,738,346.15
2 Pek. Plasteran Dinding t. 1,5 Cm ad. 1 : 4 M2 223.78 48,176.40 10,780,914.79
3 Pek. Pas. Dinding Batu Alam M2 36.24 381,805.00 13,836,613.20
JUMLAH V 34,355,874.14
HARGA TOTAL
NO. URAIAN PEKERJAAN SAT. VOLUM
SATUAN HARGA
E
1 2 3 4 5 6
VI PEKERJAAN KUNSEN PINTU DAN JENDELA
JUMLAH VI 28,223,234.74
VII PEKERJAAN RANGKA DAN PLAFOND
JUMLAH IX 8,895,000.00
X PEKERJAAN LANTAI
JUMLAH X 65,447,908.38
XI PEKERJAAN SANITASI
JUMLAH XI 5,179,462.40
XII PEKERJAAN KUNCI DAN PENGGANTUNG
1 Pek. Cat Dinding Tender Layar + Tiang Kolom dan kolom M2 223.78 29,330.60 6,563,601.67
2 Pek. Cat Kunsen Pintu Dan Jendela M2 39.41 26,539.00 1,045,901.99
3 Pek. Cat Listplank M2 16.64 26,539.00 441,608.96
1 Pek. Rangka + Dinding Panel Bawah Fin. HPL M2 27.00 1,100,000.00 29,700,000.00
2 Pek. Rangka + Tiang Kolom Semu Fin. HPL Unit 2.00 1,900,000.00 3,800,000.00
3 Pek. Ranka + Dinding Backdroop Fin. HPL M2 24.00 1,170,000.00 28,080,000.00
4 Pek. Rangka + Dinding Panel Fin. HPL M2 102.69 980,000.00 100,636,200.00
5 Pek. List Dinding Estetika M' 99.86 45,000.00 4,493,700.00
JUMLAH I 166,709,900.00
SUB JUMLAH B 166,709,900.00
C PEKERJAAN REHAB GEDUNG KANTOR
I PEKERJAAN PEMBONGKARAN
JUMLAH 4,700,000.00
II PEKERJAAN ATAP
JUMLAH 2 84,269,082.80
III PEKERJAAN RANGKA DAN PLAFOND
JUMLAH 29,348,835.00
IV PEKERJAAN FINISHING
Pek. Cat Dinding Tender Layar + Tiang Kolom dan kolom M2 415.95 29,330.60 12,200,063.07
Pek. Cat Kunsen Pintu Dan Jendela M2 144.00 26,539.00 3,821,616.00
Pek. Cat Listplank M2 66.00 26,539.00 1,751,574.00
JUMLAH I 17,773,253.07
SUB JUMLAH C 136,091,170.87
ANALISA BIAYA
Memasang 1 M2 dinding bata merah ukuran ( 5 x 11 x 22 ) cm tebal 1/2 bata, campuran spesi 1 PC : 3 PP
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Bata merah Buah 70.000 500.00 35,000.00
- Portland cement (PC) Kg 14.370 1,360.00 19,543.20
- Pasir Pasang (PP) M3 0.040 85,000.00 3,400.00
Jumlah a 57,943.20
b. Upah - Pekerja OH 0.300 72,000.00 21,600.00
- Tukang Batu OH 0.100 89,000.00 8,900.00
- Kepala Tukang OH 0.010 92,000.00 920.00
- Mandor OH 0.015 88,000.00 1,320.00
Jumlah. b 32,740.00
Jumlah a + b 90,683.20
Overhead 0% -
Jumlah Total 90,683.20
Memasang 1 M2 dinding bata merah ukuran ( 5 x 11 x 22 ) cm tebal 1/2 bata, campuran spesi 1 PC : 4 PP
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Bata merah Buah 70.000 500.00 35,000.00
- Portland cement (PC) Kg 11.500 1,360.00 15,640.00
- Pasir Pasang (PP) M3 0.043 85,000.00 3,655.00
Jumlah a 54,295.00
b. Upah - Pekerja OH 0.300 72,000.00 21,600.00
- Tukang Batu OH 0.100 89,000.00 8,900.00
- Kepala Tukang OH 0.010 92,000.00 920.00
- Mandor OH 0.015 88,000.00 1,320.00
Jumlah. b 32,740.00
Jumlah a + b 87,035.00
Overhead 0% -
Jumlah Total 87,035.00
ANALISA BIAYA KONSTRUKSI - PEKERJAAN PLESTERAN
Membuat dan memasang 1 M3 kusen pintu dan kusen jendela, kayu kelas I
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Balok kayu Klas I M3 1.100 7,500,000.00 8,250,000.00
- Paku 10 cm Kg 1.250 17,000.00 21,250.00
- Lem kayu Kg 1.000 14,000.00 14,000.00
Jumlah a 8,285,250.00
b. Upah - Pekerja OH 7.000 72,000.00 504,000.00
- Tukang Kayu OH 21.000 89,000.00 1,869,000.00
- Kepala Tukang OH 2.100 92,000.00 193,200.00
- Mandor OH 0.350 88,000.00 30,800.00
Jumlah. b 2,597,000.00
Jumlah a + b 10,882,250.00
Overhead 0% -
Jumlah Total 10,882,250.00
Membuat dan memasang 1 M2 daun pintu panel, kayu kelas I
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Papan kayu Klas I M3 0.040 9,000,000.00 360,000.00
- Lem kayu Kg 0.500 14,000.00 7,000.00
Jumlah a 367,000.00
b. Upah - Pekerja OH 1.000 72,000.00 72,000.00
- Tukang Kayu OH 3.000 89,000.00 267,000.00
- Kepala Tukang OH 0.300 92,000.00 27,600.00
- Mandor OH 0.050 88,000.00 4,400.00
Jumlah. b 371,000.00
Jumlah a + b 738,000.00
Overhead 0% -
Jumlah Total 738,000.00
Membuat dan memasang 1 M2 pintu dan jendela jalusi, kayu kelas I atau II
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Papan kayu Klas I M3 0.064 9,000,000.00 576,000.00
- Lem kayu Kg 0.500 14,000.00 7,000.00
Jumlah a 583,000.00
b. Upah - Pekerja OH 1.000 72,000.00 72,000.00
- Tukang Kayu OH 3.000 89,000.00 267,000.00
- Kepala Tukang OH 0.300 92,000.00 27,600.00
- Mandor OH 0.050 88,000.00 4,400.00
Jumlah. b 371,000.00
Jumlah a + b 954,000.00
Overhead 0% -
Jumlah Total 954,000.00
Memasang 1 M2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Kaso-kaso (5 x 7) cm M3 0.0163 2,700,000.00 44,010.00
- Paku Biasa 2" - 5" Kg 0.250 17,000.00 4,250.00
Jumlah a 48,260.00
b. Upah - Pekerja OH 0.200 72,000.00 14,400.00
- Tukang Kayu OH 0.300 89,000.00 26,700.00
- Kepala Tukang OH 0.030 92,000.00 2,760.00
- Mandor OH 0.010 88,000.00 880.00
Jumlah. b 44,740.00
Jumlah a + b 93,000.00
Overhead 0% -
Jumlah Total 93,000.00
Memasang 1 M2 rangka Dinding / langit-langit Hollow (60 x 60) cm, Pipa Hollow 20 x 40 mm
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Rangka Hollow Galvanis Btg 1.0000 35,000.00 35,000.00
- Paku Skrup Kg 0.150 20,000.00 3,000.00
Jumlah a 38,000.00
b. Upah - Pekerja OH 0.200 72,000.00 14,400.00
- Tukang Kayu OH 0.300 89,000.00 26,700.00
- Kepala Tukang OH 0.030 92,000.00 2,760.00
- Mandor OH 0.010 88,000.00 880.00
Jumlah. b 44,740.00
Jumlah a + b 82,740.00
Overhead 0% -
Jumlah Total 82,740.00
Memasang 1 M2 rangka Dinding / langit-langit Hollow (60 x 60) cm, Pipa Hollow 30 x 30 mm
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Hollow 50 x 50 mm Btg 1.0000 35,000.00 35,000.00
- Paku Skrup Kg 0.150 20,000.00 3,000.00
Jumlah a 38,000.00
b. Upah - Pekerja OH 0.200 72,000.00 14,400.00
- Tukang Kayu OH 0.300 89,000.00 26,700.00
- Kepala Tukang OH 0.030 92,000.00 2,760.00
- Mandor OH 0.010 88,000.00 880.00
Jumlah. b 44,740.00
Jumlah a + b 82,740.00
Overhead 0% -
Jumlah Total 82,740.00
Jumlah a 319,500.00
b. Upah - Pekerja OH 0.100 72,000.00 7,200.00
- Tukang Kayu OH 0.100 89,000.00 8,900.00
- Kepala Tukang OH 0.010 92,000.00 920.00
- Mandor OH 0.005 88,000.00 440.00
Jumlah. b 17,460.00
Jumlah a + b 336,960.00
Overhead 0% -
Jumlah Total 336,960.00
Memasang 1 M2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm,4 mm dan 6 mm
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Tripleks Lembar 0.375 63,000.00 23,625.00
- Paku Tripleks Kg 0.030 19,000.00 570.00
Jumlah a 24,195.00
b. Upah - Pekerja OH 0.100 72,000.00 7,200.00
- Tukang kayu OH 0.100 89,000.00 8,900.00
- Kepala Tukang OH 0.010 92,000.00 920.00
- Mandor OH 0.005 88,000.00 440.00
Jumlah. b 17,460.00
Jumlah a + b 41,655.00
Overhead 0% -
Jumlah Total 41,655.00
Memasang 1 M2 Langit - langit Gypsum Board uk. 120 x 240 cm, tebal 9 mm
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Gypsum Board Lembar 0.375 97,750.00 36,656.25
- Paku Skrup Kg 0.030 20,000.00 600.00
Jumlah a 37,256.25
b. Upah - Pekerja OH 0.100 72,000.00 7,200.00
- Tukang kayu OH 0.100 89,000.00 8,900.00
- Kepala Tukang OH 0.010 92,000.00 920.00
- Mandor OH 0.005 88,000.00 440.00
Jumlah. b 17,460.00
Jumlah a + b 54,716.25
Overhead 0% -
Jumlah Total 54,716.25
1 m³ Membuat Beton 1 Pc : 2 Ps : 3 Kr
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Portland cement (PC) Kg 336.000 1,360.00 456,960.00
- Pasir beton M3 0.540 85,000.00 45,900.00
- Batu Pecah/Split M3 0.810 400,000.00 324,000.00
Jumlah a 826,860.00
b. Upah - Pekerja OH 2.000 72,000.00 144,000.00
- Tukang Batu OH 0.350 89,000.00 31,150.00
- Kepala Tukang OH 0.035 92,000.00 3,220.00
- Mandor OH 1.000 88,000.00 88,000.00
Jumlah. b 266,370.00
Jumlah Total 1,093,230.00
Membuat 1m3 beton mutu F'c=19.3 Mpa ( K. 225 ) Slump ( 12 ± 2 ) cm. w/c = 0,58
Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/Upah ( Rp )
Rp.
Bahan - Portland cement Kg 371.000 1,360.00 504,560.00
- Pasir beton Kg 698.000 60.71 42,378.57
- Kerikil (maksimum 30mm) Kg 1047.000 222.22 232,666.67
- Air Liter 215.000 2,500.00 537,500.00
Upah - Pekerja OH 1.65 72,000.00 118,800.00
- Tukang Batu OH 0.275 89,000.00 24,475.00
- Kepala Tukang OH 0.028 92,000.00 2,576.00
- Mandor OH 0.083 88,000.00 7,304.00
Jumlah Harga Per - Satuan Pekerjaan 1,470,260.24
Overhead 0% -
Jumlah Total 1,470,260.24
1 M3 Pondasi Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 190 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.900 1,460,660.00 2,775,254.00
- Bekisting Untuk Pondasi M2 8.300 179,660.00 1,491,178.00
Jumlah a + b 5,359,662.00
Overhead 0% -
Jumlah Total 5,359,662.00
1 M3 Pondasi Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 195 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.950 1,460,660.00 2,848,287.00
- Bekisting Untuk Pondasi M2 8.300 179,660.00 1,491,178.00
Jumlah a + b 5,432,695.00
Overhead 0% -
Jumlah Total 5,432,695.00
1 M3 Pondasi Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 200 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 2.000 1,460,660.00 2,921,320.00
- Bekisting Untuk Pondasi M2 8.300 179,660.00 1,491,178.00
Jumlah a + b 5,505,728.00
Overhead 0% -
Jumlah Total 5,505,728.00
1 M3 Sloof Beton Bertulang uk 20/30 Beton Site Mix K-175 ( 126 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.260 1,460,660.00 1,840,431.60
- Bekisting Untuk Sloof M2 10.000 193,160.00 1,931,600.00
Jumlah a + b 4,865,261.60
Overhead 0% -
Jumlah Total 4,865,261.60
1 M3 Sloof Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 145 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.450 1,460,660.00 2,117,957.00
- Bekisting Untuk Sloof M2 10.000 193,160.00 1,931,600.00
Jumlah a + b 5,142,787.00
Overhead 0% -
Jumlah Total 5,142,787.00
1 M3 Sloof Beton Bertulang uk 15/20 Beton Site Mix K-175 ( 165 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.650 1,460,660.00 2,410,089.00
- Bekisting Untuk Sloof M2 10.000 193,160.00 1,931,600.00
Jumlah a + b 5,434,919.00
Overhead 0% -
Jumlah Total 5,434,919.00
1 M3 Sloof Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 170 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.700 1,460,660.00 2,483,122.00
- Bekisting Untuk Sloof M2 10.000 193,160.00 1,931,600.00
Jumlah a + b 5,507,952.00
Overhead 0% -
Jumlah Total 5,507,952.00
1 M3 Sloof Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 180 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.800 1,460,660.00 2,629,188.00
- Bekisting Untuk Sloof M2 10.000 193,160.00 1,931,600.00
Jumlah a + b 5,654,018.00
Overhead 0% -
Jumlah Total 5,654,018.00
1 M3 Sloof Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 197 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.970 1,460,660.00 2,877,500.20
- Bekisting Untuk Sloof M2 10.000 193,160.00 1,931,600.00
Jumlah a + b 5,902,330.20
Overhead 0% -
Jumlah Total 5,902,330.20
1 M3 Sloof Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 200 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 2.000 1,460,660.00 2,921,320.00
- Bekisting Untuk Sloof M2 10.000 193,160.00 1,931,600.00
Jumlah a + b 5,946,150.00
Overhead 0% -
Jumlah Total 5,946,150.00
1 M3 Sloof Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 217 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 2.170 1,460,660.00 3,169,632.20
- Bekisting Untuk Sloof M2 10.000 193,160.00 1,931,600.00
Jumlah a + b 6,194,462.20
Overhead 0% -
Jumlah Total 6,194,462.20
1 M3 Sloof Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 225 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 2.250 1,460,660.00 3,286,485.00
- Bekisting Untuk Sloof M2 10.000 193,160.00 1,931,600.00
Jumlah a + b 6,311,315.00
Overhead 0% -
Jumlah Total 6,311,315.00
1 M3 Kolom Beton Bertulang uk 20/30 Beton Site Mix K-175 ( 100 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.000 1,460,660.00 1,460,660.00
- Bekisting Untuk Kolom M2 10.000 328,230.00 3,282,300.00
Jumlah a + b 5,836,190.00
Overhead 0% -
Jumlah Total 5,836,190.00
1 M3 Kolom Beton Bertulang uk 30/30 Beton Site Mix K-175 ( 115 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.150 1,460,660.00 1,679,759.00
- Bekisting Untuk Kolom M2 10.000 328,230.00 3,282,300.00
Jumlah a + b 6,055,289.00
Overhead 0% -
Jumlah Total 6,055,289.00
1 M3 Kolom Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 130 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.300 1,460,660.00 1,898,858.00
- Bekisting Untuk Kolom M2 10.000 328,230.00 3,282,300.00
Jumlah a + b 6,274,388.00
Overhead 0% -
Jumlah Total 6,274,388.00
1 M3 Kolom Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 135 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.350 1,460,660.00 1,971,891.00
- Bekisting Untuk Kolom M2 10.000 328,230.00 3,282,300.00
Jumlah a + b 6,347,421.00
Overhead 0% -
Jumlah Total 6,347,421.00
1 M3 Kolom Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 140 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.400 1,460,660.00 2,044,924.00
- Bekisting Untuk Kolom M2 10.000 328,230.00 3,282,300.00
Jumlah a + b 6,420,454.00
Overhead 0% -
Jumlah Total 6,420,454.00
1 M3 Kolom Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 145 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.450 1,460,660.00 2,117,957.00
- Bekisting Untuk Kolom M2 10.000 328,230.00 3,282,300.00
Jumlah a + b 6,493,487.00
Overhead 0% -
Jumlah Total 6,493,487.00
1 M3 Kolom Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 150 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.500 1,460,660.00 2,190,990.00
- Bekisting Untuk Kolom M2 10.000 328,230.00 3,282,300.00
Jumlah a + b 6,566,520.00
Overhead 0% -
Jumlah Total 6,566,520.00
1 M3 Kolom Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 160 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.600 1,460,660.00 2,337,056.00
- Bekisting Untuk Kolom M2 10.000 328,230.00 3,282,300.00
Jumlah a + b 6,712,586.00
Overhead 0% -
Jumlah Total 6,712,586.00
1 M3 Kolom Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 170 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.700 1,460,660.00 2,483,122.00
- Bekisting Untuk Kolom M2 10.000 328,230.00 3,282,300.00
Jumlah a + b 6,858,652.00
Overhead 0% -
Jumlah Total 6,858,652.00
1 M3 Kolom Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 210 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 2.100 1,460,660.00 3,067,386.00
- Bekisting Untuk Kolom M2 10.000 328,230.00 3,282,300.00
Jumlah a + b 7,442,916.00
Overhead 0% -
Jumlah Total 7,442,916.00
1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr +215 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 2.150 1,460,660.00 3,140,419.00
- Bekisting Untuk Balok M2 10.000 341,730.00 3,417,300.00
Jumlah a + b 7,650,949.00
Overhead 0% -
Jumlah Total 7,650,949.00
1 M3 Kolom Praktis Beton Bertulang Uk 11/11 Beton Site Mix K-175 ( 225 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 2.250 1,460,660.00 3,286,485.00
- Bekisting Untuk Kolom M2 10.000 328,230.00 3,282,300.00
Jumlah a + b 7,662,015.00
Overhead 0% -
Jumlah Total 7,662,015.00
1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr +126 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.260 1,460,660.00 1,840,431.60
- Bekisting Untuk Balok M2 10.000 341,730.00 3,417,300.00
Jumlah a + b 6,350,961.60
Overhead 0% -
Jumlah Total 6,350,961.60
1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 130 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.300 1,460,660.00 1,898,858.00
- Bekisting Untuk Balok M2 10.000 341,730.00 3,417,300.00
Jumlah a + b 6,409,388.00
Overhead 0% -
Jumlah Total 6,409,388.00
1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 145 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.450 1,460,660.00 2,117,957.00
- Bekisting Untuk Balok M2 10.000 341,730.00 3,417,300.00
Jumlah a + b 6,628,487.00
Overhead 0% -
Jumlah Total 6,628,487.00
1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr +160 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.600 1,460,660.00 2,337,056.00
- Bekisting Untuk Balok M2 10.000 341,730.00 3,417,300.00
Jumlah a + b 6,847,586.00
Overhead 0% -
Jumlah Total 6,847,586.00
1 M3 Balok Beton Bertulang uk 20/30 Beton Site Mix K-175 (165 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.650 1,460,660.00 2,410,089.00
- Bekisting Untuk Balok M2 10.000 341,730.00 3,417,300.00
Jumlah a + b 6,920,619.00
Overhead 0% -
Jumlah Total 6,920,619.00
1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr +180 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.800 1,460,660.00 2,629,188.00
- Bekisting Untuk Balok M2 10.000 341,730.00 3,417,300.00
Jumlah a + b 7,139,718.00
Overhead 0% -
Jumlah Total 7,139,718.00
1 M3 Balok Pinggang Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 170 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.700 1,460,660.00 2,483,122.00
- Bekisting Untuk Balok M2 10.000 341,730.00 3,417,300.00
Jumlah a + b 6,993,652.00
Overhead 0% -
Jumlah Total 6,993,652.00
1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 180 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.800 1,460,660.00 2,629,188.00
- Bekisting Untuk Balok M2 10.000 341,730.00 3,417,300.00
Jumlah a + b 7,139,718.00
Overhead 0% -
Jumlah Total 7,139,718.00
1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 185 Kg Besi + Bekisting)
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.850 1,460,660.00 2,702,221.00
- Bekisting Untuk Balok M2 10.000 341,730.00 3,417,300.00
Jumlah a + b 7,212,751.00
Overhead 0% -
Jumlah Total 7,212,751.00
1 M3 Balok Beton Bertulang uk 13/15 Beton Site Mix K-175 ( 215 Kg Besi + Bekisting)
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 2.150 1,460,660.00 3,140,419.00
- Bekisting Untuk Balok M2 10.000 341,730.00 3,417,300.00
Jumlah a + b 7,650,949.00
Overhead 0% -
Jumlah Total 7,650,949.00
1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr +233 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 2.330 1,460,660.00 3,403,337.80
- Bekisting Untuk Balok M2 10.000 341,730.00 3,417,300.00
Jumlah a + b 7,913,867.80
Overhead 0% -
Jumlah Total 7,913,867.80
1 M3 Ring Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 145 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.450 1,460,660.00 2,117,957.00
- Bekisting Untuk Balok M2 10.000 341,730.00 3,417,300.00
Jumlah a + b 6,628,487.00
Overhead 0% -
Jumlah Total 6,628,487.00
1 M3 Plat Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 165 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.650 1,460,660.00 2,410,089.00
- Bekisting Untuk Lantai M2 8.300 358,230.00 2,973,309.00
Jumlah a + b 6,476,628.00
Overhead 0% -
Jumlah Total 6,476,628.00
1 M3 Plat T=12 cm Beton Bertulang Beton Site K-175 ( 110 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.100 1,460,660.00 1,606,726.00
- Bekisting Untuk Lantai M2 8.300 358,230.00 2,973,309.00
Jumlah a + b 5,673,265.00
Overhead 0% -
Jumlah Total 5,673,265.00
1 M3 Plat Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 125 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.250 1,460,660.00 1,825,825.00
- Bekisting Untuk Lantai M2 8.300 358,230.00 2,973,309.00
Jumlah a + b 5,892,364.00
Overhead 0% -
Jumlah Total 5,892,364.00
1 M3 Plat Bordes Beton Bertulang Tangga (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 110 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.100 1,460,660.00 1,606,726.00
- Bekisting Untuk Lantai M2 8.300 358,230.00 2,973,309.00
Jumlah a + b 5,673,265.00
Overhead 0% -
Jumlah Total 5,673,265.00
1 M3 Plat Bordes Beton Bertulang Tangga (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 177 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.770 1,460,660.00 2,585,368.20
- Bekisting Untuk Lantai M2 8.300 358,230.00 2,973,309.00
Jumlah a + b 6,651,907.20
Overhead 0% -
Jumlah Total 6,651,907.20
1 M3 Beton Bertulang Tangga (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 119 Kg Besi + Bekisting )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/Upah Harga
- Beton Site Mix ad. 1 Pc:2 Ps:3 Kr M3 1.000 1,093,230.00 1,093,230.00
- Besi Beton Bertulang/100 Kg 1.190 1,460,660.00 1,738,185.40
- Bekisting Untuk Tangga M2 8.300 300,580.00 2,494,814.00
Jumlah a + b 5,326,229.40
Overhead 0% -
Jumlah Total 5,326,229.40
1 m² Pengecatan Tembok Baru Weater Shield ( 1 Alkali, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Alkali Kg 0.100 25,000.00 2,500.00
- Cat Dasar Kg 0.100 22,500.00 2,250.00
- Amplas Lbr 1.000 4,000.00 4,000.00
- Rol Cat Bh 0.500 12,000.00 6,000.00
- Cat Tembok Weater Shield Kg 0.260 96,000.00 24,960.00
Jumlah a 39,710.00
b. Upah - Pekerja OH 0.0200 72,000.00 1,440.00
- Tukang Cat OH 0.063 89,000.00 5,607.00
- Kepala Tukang OH 0.0063 92,000.00 579.60
- Mandor OH 0.0025 88,000.00 220.00
Jumlah. b 7,846.60
Jumlah a + b 47,556.60
Overhead 0% -
Jumlah Total 47,556.60
1 m² Pengecatan Tembok Baru Interior/Ruang Dalam( 1 Alkali, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Alkali Kg 0.100 25,000.00 2,500.00
- Cat Dasar Kg 0.100 22,500.00 2,250.00
- Amplas Lbr 1.000 4,000.00 4,000.00
- Rol Cat Bh 0.500 12,000.00 6,000.00
- Cat Tembok Interior Kg 0.260 25,900.00 6,734.00
Jumlah a 21,484.00
b. Upah - Pekerja OH 0.0200 72,000.00 1,440.00
- Tukang Cat OH 0.063 89,000.00 5,607.00
- Kepala Tukang OH 0.0063 92,000.00 579.60
- Mandor OH 0.0025 88,000.00 220.00
Jumlah. b 7,846.60
Jumlah a + b 29,330.60
Overhead 0% -
Jumlah Total 29,330.60
1 m² Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup )
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Plamir/Dempul Kg 0.100 10,000.00 1,000.00
- Cat Dasar Kg 0.100 22,500.00 2,250.00
- Amplas Lbr 1.000 4,000.00 4,000.00
- Rol Cat Bh 0.500 12,000.00 6,000.00
- Cat Tembok Kg 0.260 25,900.00 6,734.00
Jumlah a 19,984.00
b. Upah - Pekerja OH 0.0200 72,000.00 1,440.00
- Tukang Cat OH 0.063 89,000.00 5,607.00
- Kepala Tukang OH 0.0063 92,000.00 579.60
- Mandor OH 0.0025 88,000.00 220.00
Jumlah. b 7,846.60
Jumlah a + b 27,830.60
Overhead 0% -
Jumlah Total 27,830.60
1 m² Mengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 2 Lapis Cat Penutup
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Cat Meni Kg 0.200 22,500.00 4,500.00
- Plamir Kg 0.150 10,000.00 1,500.00
- Cat Dasar Kg 0.170 22,500.00 3,825.00
- Cat Kayu Glotek Kg 0.260 38,850.00 10,101.00
Jumlah a 19,926.00
b. Upah - Pekerja OH 0.070 72,000.00 5,040.00
- Tukang Cat OH 0.009 89,000.00 801.00
- Kepala Tukang OH 0.006 92,000.00 552.00
- Mandor OH 0.0025 88,000.00 220.00
Jumlah. b 6,613.00
Jumlah a + b 26,539.00
Overhead 0% -
Jumlah Total 26,539.00
1 m² Pintu Plat Baja T. 4 mm
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Besi Siku Kg 15.000 30,000.00 450,000.00
- Besi Plat Kg 65.940 35,000.00 2,307,900.00
- Kawat Las Kg 0.050 25,000.00 1,250.00
Jumlah a 2,759,150.00
b. Upah - Pekerja OH 1.050 72,000.00 75,600.00
- Tukang OH 1.050 89,000.00 93,450.00
- Kepala Tukang OH 0.105 92,000.00 9,660.00
- Mandor OH 0.0520 88,000.00 4,576.00
Jumlah. b 183,286.00
Jumlah a + b 2,942,436.00
Overhead 0% -
Jumlah Total 2,942,436.00
1 m² Rangka Dinding
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Balok Kayu M3 0.028 4,500,000.00 126,000.00
- Paku Kg 0.150 17,000.00 2,550.00
-
Jumlah a 128,550.00
b. Upah - Pekerja OH 0.150 72,000.00 10,800.00
- Tukang OH 0.450 89,000.00 40,050.00
- Kepala Tukang OH 0.045 92,000.00 4,140.00
- Mandor OH 0.0080 88,000.00 704.00
Jumlah. b 55,694.00
Jumlah a + b 184,244.00
Overhead 0% -
Jumlah Total 184,244.00
1 m² Rangka Dinding
Harga Satuan Jumlah
Kebutuhan Satuan Indeks
Bahan/Upah Harga
a. Bahan - Balok Kayu M3 0.028 4,500,000.00 126,000.00
- Paku Kg 0.150 17,000.00 2,550.00
-
Jumlah a 128,550.00
b. Upah - Pekerja OH 0.150 72,000.00 10,800.00
- Tukang OH 0.450 89,000.00 40,050.00
- Kepala Tukang OH 0.045 92,000.00 4,140.00
- Mandor OH 0.0080 88,000.00 704.00
Jumlah. b 55,694.00
Jumlah a + b 184,244.00
Overhead 0% -
Jumlah Total 184,244.00
1 #REF! Rp.
2 Memasang 1 M2 dinding bata merah ukuran ( 5 x 11 x 22 ) cm tebal 1 bata, campuran spesi 1 PC : 3 PP Rp.
3 Memasang 1 M2 dinding bata merah ukuran ( 5 x 11 x 22 ) cm tebal 1/2 bata, campuran spesi 1 PC : 2 PP Rp.
4 Memasang 1 M2 dinding bata merah ukuran ( 5 x 11 x 22 ) cm tebal 1/2 bata, campuran spesi 1 PC : 3 PP Rp.
5 Memasang 1 M2 dinding bata merah ukuran ( 5 x 11 x 22 ) cm tebal 1/2 bata, campuran spesi 1 PC : 4 PP Rp.
1 Membuat dan memasang 1 M3 kusen pintu dan kusen jendela, kayu kelas I Rp.
2 Membuat dan memasang 1 M2 daun pintu panel, kayu kelas I Rp.
3 Membuat dan memasang 1 M2 daun pintu panel, kayu kelas II Rp.
4 Membuat dan memasang 1 M2 pintu dan jendela kaca, kayu kelas I atau II Rp.
5 Membuat dan memasang 1 M2 pintu dan jendela jalusi, kayu kelas I atau II Rp.
6 Memasang 1 M2 jalusi kusen, kayu kelas I atau II Rp.
7 #REF! Rp.
8 #REF! Rp.
9 #REF! Rp.
10 #REF! Rp.
11 Memasang 1 M2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III Rp.
12 Memasang 1 M2 rangka Dinding / langit-langit Hollow (60 x 60) cm, Pipa Hollow 20 x 40 mm Rp.
13 Memasang 1 M2 rangka Dinding / langit-langit Hollow (60 x 60) cm, Pipa Hollow 30 x 30 mm Rp.
14 Memasang 1 M1 lisplank ukuran 2x (1.5 x 20) cm, GRC Board Rp.
15 Memasang 1 M1 lisplank ukuran 2x (2 x 20) cm, kayu kelas I atau II Rp.
16 #REF! Rp.
1 Memasang 1 M2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm,4 mm dan 6 mm Rp.
2 Memasang 1 M2 langit-langit GRC Board ukuran (120 x 240) cm, tebal 4 mm Rp.
3 Memasang 1 M2 Langit - langit Gypsum Board uk. 120 x 240 cm, tebal 9 mm Rp.
4 Memasang 1 M' list langit-langit profil Gypsum L 10 cm Rp.
5 #REF! Rp.
1 1 M3 Beton Tumbuk Bertulang (Beton Site Mix ad. 1 Pc : 3 Ps : 5 Kr + 85 Kg Besi + Bekisting ) Rp.
2 #REF! Rp.
3 1 M3 Pondasi Beton Bertulang Beton Site Mix K -175 ( 120 Kg Besi + Bekisting ) Rp.
4 1 M3 Pondasi Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 190 Kg Besi + Bekisting ) Rp.
5 #REF! Rp.
6 0 Rp.
7 0 Rp.
8 1 M3 Sloof Beton Bertulang uk 20/30 Beton Site Mix K-175 ( 126 Kg Besi + Bekisting ) Rp.
9 1 M3 Sloof Beton Bertulang uk 15/20 Beton Site Mix K-175 ( 165 Kg Besi + Bekisting ) Rp.
10 1 M3 Sloof Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 170 Kg Besi + Bekisting ) Rp.
11 1 M3 Sloof Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 180 Kg Besi + Bekisting ) Rp.
12 1 M3 Sloof Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 197 Kg Besi + Bekisting ) Rp.
13 1 M3 Sloof Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 217 Kg Besi + Bekisting ) Rp.
14 0 Rp.
15 0 Rp.
16 1 M3 Kolom Beton Bertulang uk 20/30 Beton Site Mix K-175 ( 100 Kg Besi + Bekisting ) Rp.
17 1 M3 Kolom Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 130 Kg Besi + Bekisting ) Rp.
18 1 M3 Kolom Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 135 Kg Besi + Bekisting ) Rp.
19 1 M3 Kolom Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 140 Kg Besi + Bekisting ) Rp.
20 1 M3 Kolom Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 150 Kg Besi + Bekisting ) Rp.
21 1 M3 Kolom Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 160 Kg Besi + Bekisting ) Rp.
22 1 M3 Kolom Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 170 Kg Besi + Bekisting ) Rp.
23 1 M3 Kolom Praktis Beton Bertulang Uk 11/11 Beton Site Mix K-175 ( 225 Kg Besi + Bekisting ) Rp.
22 #REF! Rp.
23 1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr +215 Kg Besi + Bekisting ) Rp.
24 1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr +126 Kg Besi + Bekisting ) Rp.
25 1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 130 Kg Besi + Bekisting ) Rp.
26 1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 145 Kg Besi + Bekisting ) Rp.
27 1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr +160 Kg Besi + Bekisting ) Rp.
28 1 M3 Balok Beton Bertulang uk 20/30 Beton Site Mix K-175 (165 Kg Besi + Bekisting ) Rp.
29 1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr +180 Kg Besi + Bekisting ) Rp.
30 1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 180 Kg Besi + Bekisting ) Rp.
31 1 M3 Balok Beton Bertulang uk 13/15 Beton Site Mix K-175 ( 215 Kg Besi + Bekisting) Rp.
32 1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr +233 Kg Besi + Bekisting ) Rp.
33 1 M3 Balok Pinggang Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 170 Kg Besi + Bekisting ) Rp.
34 1 M3 Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 185 Kg Besi + Bekisting) Rp.
35 1 M3 Ring Balok Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 145 Kg Besi + Bekisting ) Rp.
36 #REF! Rp.
37 1 M3 Plat Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 65 Kg Besi + Bekisting ) Rp.
38 1 M3 Plat Beton Bertulang (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 165 Kg Besi + Bekisting ) Rp.
39 1 M3 Plat T=12 cm Beton Bertulang Beton Site K-175 ( 110 Kg Besi + Bekisting ) Rp.
40 1 M3 Plat Bordes Beton Bertulang Tangga (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 110 Kg Besi + Bekisting ) Rp.
41 1 M3 Beton Bertulang Tangga (Beton Site Mix ad. 1 Pc : 2 Ps : 3 Kr + 119 Kg Besi + Bekisting ) Rp.
1 1 m² Pengecatan Tembok Baru Weater Shield ( 1 Alkali, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) Rp.
2 1 m² Pengecatan Tembok Baru Interior/Ruang Dalam( 1 Alkali, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) Rp.
3 1 m² Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) Rp.
4 1 m² Mengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 2 Lapis Cat Penutup Rp.
5 #REF! Rp.
5 #REF! Rp.
JUMLAH HARGA
AN
324,445.00
51,950.00
34,841.00
#REF!
#REF!
H
68,760.00
#REF!
22,920.00
167,700.00
40,400.00
115,000.00
100,480.00
NG
#REF!
188,027.00
96,742.00
90,683.20
87,035.00
AN
53,254.64
50,180.36
48,176.40
39,125.20
47,177.00
29,520.00
ASI
864,195.00
485,970.00
1,054,470.00
10,882,250.00
738,000.00
538,000.00
517,000.00
954,000.00
477,150.00
#REF!
#REF!
#REF!
#REF!
93,000.00
82,740.00
82,740.00
134,636.67
99,840.00
#REF!
ANGIT
41,655.00
46,155.00
54,716.25
21,544.00
#REF!
1,093,230.00
752,070.00
114,302.00
146,066.00
4,941,995.00
8,147,825.00
6,286,805.00
5,498,985.00
5,402,709.00
212,525.00
99,470.00
1,355,863.00
#REF!
4,337,200.00
5,359,662.00
#REF!
#REF!
#REF!
4,865,261.60
5,434,919.00
5,507,952.00
5,654,018.00
5,902,330.20
6,194,462.20
-
-
5,836,190.00
6,274,388.00
6,347,421.00
6,420,454.00
6,566,520.00
6,712,586.00
6,858,652.00
7,662,015.00
#REF!
7,650,949.00
6,350,961.60
6,409,388.00
6,628,487.00
6,847,586.00
6,920,619.00
7,139,718.00
7,139,718.00
7,650,949.00
7,913,867.80
6,993,652.00
7,212,751.00
6,628,487.00
#REF!
5,015,968.00
6,476,628.00
5,673,265.00
5,673,265.00
5,326,229.40
127,908.00
191,368.00
80,924.00
#REF!
#REF!
#REF!
AIR
2,166,590.00
515,910.00
1,014,700.00
909,326.00
35,980.00
23,080.00
13,271.15
#REF!
45,899.80
65,737.30
#REF!
N KACA
193,504.00
141,580.00
43,376.00
25,584.00
40,876.00
30,876.00
23,416.00
23,416.00
116,126.00
#REF!
DAN DINDING
198,530.00
180,245.00
201,294.00
210,728.00
381,805.00
98,603.40
#REF!
ATAN
47,556.60
29,330.60
27,830.60
26,539.00
#REF!
#REF!
DAFTAR HARGA SATUAN
I. HARGA UPAH
1 Kepala Tukang Rp. 92,000.00 / Hari
2 Tukang Rp. 89,000.00 / Hari
3 Pekerja Rp. 72,000.00 / Hari
4 Mandor Rp. 88,000.00 / Hari
B. BAHAN LANTAI
1 Keramik 40 x 40 cm Rp. 13,500.00 / Bh
2 Keramik 30 x 30 cm Rp. 6,000.00 / Bh
3 Keramik 20 x 20 cm Rp. 3,450.00 / Bh
4 Keramik 20 x 25 cm Rp. 3,500.00 / Bh
5 Cincin Keramik Rp. 96,000.00 / M1
6 Batu Alam Rp. 250,000.00 / M2
7 Granite 60 x 60 Rp. 100,000.00 / Bh
E. BAHAN KAYU
1 Kayu Balok Klas I (Kulim/Sejenis) Rp. 7,500,000.00 / M3
2 Kayu Balok Klas II Rp. 4,500,000.00 / M3
3 Kayu Balok Klas III Rp. 2,700,000.00 / M3
4 Kayu Papan Klas I Rp. 9,000,000.00 / M3
5 Kayu Papan Klas II Rp. 4,000,000.00 / M3
6 Kayu Papan Klas III Rp. 250,000.00 / M3
7 Kayu Dolken Rp. 7,500.00 / Btg
8 Kayu Cerucuk Galam Rp. 35,000.00 / Btg
9 Roster Kusen t. 3 Cm Rp. 45,000.00 / Bh
10 Multiplek t .9 mm Rp. 130,000.00 / Lbr
11 Bambu Rp. 12,000.00 / Btg
12 Tali Ijuk Rp. 8,000.00 / Kg
F. BAHAN BESI
1 Besi Beton Rp. 12,500.00 / Kg
2 Kawat Ikat Rp. 17,000.00 / Kg
3 Paku Halus Rp. 19,000.00 / Kg
4 Paku Biasa Rp. 17,000.00 / Kg
5 Paku Bulian Rp. 27,000.00 / Kg
6 Paku Skrup Rp. 20,000.00 / Kg
7 Mour Baut/Begel/Besi Rp. 7,000.00 / Bh
8 Plat Strip 4 x 40 Rp. 15,000.00 / Kg
9 Railing Hollow Block dan Sun Screen Rp. 370,000.00 / M2
10 Hollow Block Rp. 35,000.00 / Btg
H. BAHAN SANITAIR
1 Pipa PVC, Dia 1/2" Rp. 3,500.00 / M'
2 Pipa PVC, Dia 3" Rp. 20,000.00 / M'
3 Pipa PVC, Dia 4" Rp. 35,000.00 / M'
4 Daun Pintu Fiber Wc/Km Terpasang Rp. 450,000.00 / Bh
5 Closet Jongkok Standar Rp. 150,000.00 / Bh
6 Wastafel Rp. 750,000.00 / Bh
7 Tempat Cuci Piring Stainless steel Rp. 700,000.00 / Bh
8 Bak Mandi Fiver Glass 0.3 M3 Rp. 465,000.00 / Bh
9 Kran Air Rp. 12,000.00 / Bh
10 Seal Tape Rp. 4,000.00 / Bh
11 Sealant Rp. 35,000.00 / Tube
12 Floor Drain Rp. 25,000.00 / Bh
I. BAHAN FINISHING
1 Cat Kilat/Cat Kayu Rp. 38,850.00 / Kg
2 Cat Tembok Weater Shield Rp. 96,000.00 / Kg
3 Cat Tembok Setara Metrolite/Catilac Rp. 25,900.00 / Kg
4 Cat Dasar/Menie Kayu dan Besi Rp. 22,500.00 / Kg
5 Vernis Rp. 45,000.00 / Kg
6 Dempul Rp. 10,000.00 / Kg
7 Plamour Rp. 10,000.00 / Kg
8 Alkali Rp. 25,000.00 / Kg
9 Minyak Cat Rp. 13,000.00 / Ltr
10 Minyak Bekisting Rp. 13,000.00 / Ltr
11 Amplas Rp. 4,000.00 / Lbr
12 Lem Kayu Rp. 14,000.00 / Kg
13 Rol Cat Rp. 12,000.00 / Bh
14 Kuas Rp. 14,000.00 / Bh
JUMLAH
Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :
Pengawas Lapangan Konsultan Pengawas Kontraktor Pelaksana
Dinas Pekerjaan Umum Kabupaten Muaro 0
0
Jambi
1.000
40.000
367.68
39.62
448.302
jukan Oleh :
aktor Pelaksana
0
MASURI
LAKSANA
BACK UP DATA
Departemen/Instansi : 0
Program : 0
Paket Pekerjaan : 0
Tahun Anggaran : 0
Nomor Kontrak/Tanggal : 0
Pelaksana Pekerjaan : 0
Konsultan Pengawas : 0
JUMLAH
Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :
Pengawas Lapangan Konsultan Pengawas Kontraktor Pelaksana
Dinas Pekerjaan Umum Kabupaten Muaro 0
0
Jambi
0.700
0.700
jukan Oleh :
aktor Pelaksana
0
MASURI
LAKSANA
BACK UP DATA
Departemen/Instansi : 0
Program : 0
Paket Pekerjaan : 0
Tahun Anggaran : 0
Nomor Kontrak/Tanggal : 0
Pelaksana Pekerjaan : 0
Konsultan Pengawas : 0
JUMLAH
Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :
Pengawas Lapangan Konsultan Pengawas Kontraktor Pelaksana
Dinas Pekerjaan Umum Kabupaten Muaro 0
0
Jambi
23.023
9.87
32.893
jukan Oleh :
aktor Pelaksana
0
MASURI
LAKSANA
BACK UP DATA
Departemen/Instansi : 0
Program : 0
Paket Pekerjaan : 0
Tahun Anggaran : 0
Nomor Kontrak/Tanggal : 0
Pelaksana Pekerjaan : 0
Konsultan Pengawas : 0
JUMLAH
Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :
Pengawas Lapangan Konsultan Pengawas Kontraktor Pelaksana
Dinas Pekerjaan Umum Kabupaten Muaro 0
0
Jambi
1.830
1.830
jukan Oleh :
aktor Pelaksana
0
MASURI
LAKSANA
BACK UP DATA
Departemen/Instansi : 0
Program : 0
Paket Pekerjaan : 0
Tahun Anggaran : 0
Nomor Kontrak/Tanggal : 0
Pelaksana Pekerjaan : 0
Konsultan Pengawas : 0
JUMLAH
Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :
Pengawas Lapangan Konsultan Pengawas Kontraktor Pelaksana
Dinas Pekerjaan Umum Kabupaten Muaro 0
0
Jambi
3.850
3.850
jukan Oleh :
aktor Pelaksana
0
MASURI
LAKSANA
BACK UP DATA
Departemen/Instansi : 0
Program : 0
Paket Pekerjaan : 0
Tahun Anggaran : 0
Nomor Kontrak/Tanggal : 0
Pelaksana Pekerjaan : 0
Konsultan Pengawas : 0
JUMLAH
Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :
Pengawas Lapangan Konsultan Pengawas Kontraktor Pelaksana
Dinas Pekerjaan Umum Kabupaten Muaro 0
0
Jambi
1.1895
1.1895
jukan Oleh :
aktor Pelaksana
0
MASURI
LAKSANA
BACK UP DATA
Departemen/Instansi : 0
Program : 0
Paket Pekerjaan : 0
Tahun Anggaran : 0
Nomor Kontrak/Tanggal : 0
Pelaksana Pekerjaan : 0
Konsultan Pengawas : 0
JUMLAH
Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :
Pengawas Lapangan Konsultan Pengawas Kontraktor Pelaksana
Dinas Pekerjaan Umum Kabupaten Muaro 0
0
Jambi
-
jukan Oleh :
aktor Pelaksana
0
MASURI
LAKSANA
#REF!
#REF!
b Titik instalasi
- Titik Instalsi Cahaya 165.00 ttk 175,000.00 28,875,000.00
- Titik Instalasi Stop Kontak 1 Phs 16A 60.00 ttk 200,000.00 12,000,000.00
Jumlah A 70,357,560.00
B INSTALASI PENERANGAN LANTAI 2
a Assesories lampu,saklar dan stop kontak
- Lampu TL 2 x 36 W (TKI) 18.00 bh 450,000.00 8,100,000.00
- Lampu TL 2 x 18 W (TKI) 40.00 bh 300,000.00 12,000,000.00
- Lampu DL PL 18 W 62.00 bh 87,000.00 5,394,000.00
- Lampu Gantung 2500 W 1.00 bh 10,000,000.00 10,000,000.00
- Saklar Tunggal (legrand) 7.00 bh 31,680.00 221,760.00
- Saklar Ganda (legrand) 20.00 bh 50,820.00 1,016,400.00
- Outlet Stop Kontak (legrand) 60.00 bh 22,440.00 1,346,400.00
- Box Panel Hagger 5 Group 10.00 bh 250,000.00 2,500,000.00
b Titik instalasi
- Titik Instalsi Cahaya 121.00 ttk 175,000.00 21,175,000.00
- Titik Instalasi Stop Kontak 1 Phs 16A 60.00 ttk 200,000.00 12,000,000.00
Jumlah B 73,753,560.00
C PANEL PENERANGAN
a PP-LP LT.1
- Box Panel 1.00 unit 2,000,000.00 2,000,000.00
- MCCB 60-80A 3P 380/415V 50Hz 36KA 1.00 bh 950,000.00 950,000.00
- MCB 16A 3P 220V 50Hz 6KA 4.00 bh 100,000.00 400,000.00
- MCB 16A 1P 220V 50Hz 6KA 6.00 bh 65,000.00 390,000.00
- Indicator Lamp+fuse 3.00 bh 30,000.00 90,000.00
- Accessories (Busbar, shunt Kabel, termination, 1.00 unit 1,800,000.00 1,800,000.00
Labeling/grouping etc.)
b PP-LP LT.2
- Box Panel 1.00 unit 2,000,000.00 2,000,000.00
- MCCB 60-80A 3P 380/415V 50Hz 36KA 1.00 bh 950,000.00 950,000.00
- MCB 16A 3P 220V 50Hz 6KA 2.00 bh 100,000.00 200,000.00
- MCB 16A 1P 220V 50Hz 6KA 14.00 bh 65,000.00 910,000.00
- Indicator Lamp+fuse 3.00 bh 30,000.00 90,000.00
- Accessories (Busbar, shunt Kabel, termination, 1.00 unit 1,800,000.00 1,800,000.00
Labeling/grouping etc.)
c SDP-UTAMA
- Box Panel 1.00 unit 3,000,000.00 3,000,000.00
- MCCB 125-160A 3P 380/415V 50Hz 36KA 1.00 bh 1,100,000.00 1,100,000.00
- MCCB 60-80A 3P 380/415V 50Hz 36KA 2.00 bh 950,000.00 1,900,000.00
- MCB 25A 3P 220V 50Hz 6KA 2.00 bh 100,000.00 200,000.00
- MCB 40A 3P 220V 50Hz 6KA 2.00 bh 100,000.00 200,000.00
- Indicator Lamp+fuse 3.00 bh 30,000.00 90,000.00
- Accessories (Busbar, shunt Kabel, termination, 1.00 unit 2,500,000.00 2,500,000.00
Labeling/grouping etc.)
Jumlah C 20,570,000.00
VOLUME HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN
SATUAN
( Rp.) ( Rp.)
Lantai 1
a. Ceiling speaker 3 W 20.00 bh 100,000.00 2,000,000.00
b. Attenuator 30 w 5.00 bh 300,000.00 1,500,000.00
c. Terminal box tata suara 1.00 bh 250,000.00 250,000.00
d. Instalasi Speaker termasuk kabel & konduit 20.00 ttk 200,000.00 4,000,000.00
Lantai 2
a. Ceiling speaker 3 W 20.00 bh 100,000.00 2,000,000.00
b. Attenuator 30 w 5.00 bh 300,000.00 1,500,000.00
c. Terminal box tata suara 1.00 bh 250,000.00 250,000.00
d. Instalasi Speaker termasuk kabel & konduit 20.00 ttk 200,000.00 4,000,000.00
Jumlah G 23,350,000.00
H PERALATAN UTAMA INSTALASI - TELEPHONE.
1 Basic Cabinet Central P.A.B.X. 200 EXTENTION 1.00 unit 23,000,000.00 23,000,000.00
lengkap dengan capasitas :
Capasitas Instalasi.
Dengan Peralatan.
- Attendant Console AC4+ Headset
- Modem remote maintenance.
- Power supply included battery
- Music on hold.
- MDF.
- WAMS module (Interface ke LAN untuk
Existing Maintenance Terminal)