Tacks
Welded Joint RepresentationEx.No.1 SINGLE V-BUTT JOINT
Aim:
To make a Single V-Butt joint using are welding on the given work pieces.
Material supplied:
Mild steel plate of size 100 x 50 x 6mm - 2 Nos.
Tools required:
eeranesene
10.
Ih
«Power supply (AC or DC)
Welding Torch
Electrodes
Tongs
Chipping hammer
Wire brush
Gloves
Apron
Shield
Safety goggles
Earthing clamps
Sequence of operations:
1
2.
3.
4.
5,
6.
. Edge preparation (Removal of rust, scale etc.)
. Tacking
|. Welding
Cooling
. Chipping
|. Cleaning
Working steps
2
3.
4
5.
6.
7.
8
9.
10.
ist ofall, the work pieces must be thoroughly cleaned to remove rust, scale and other foreign
materials.
Then the given work pieces are placed on the table in such a way that two work pieces are
brought close to each other so that it forms a *V-Shape’ when the plates butt each other.
Appropriate power supply should be given to the electrode and work pieces.
|. Now the welding current output may be existed.
When current is passed, arc is produced between the electrode and work pieces.
). Now set the two work pieces in correct position and maintain the gap 3mm and drack at both
ends of the work pieces as shown in the figure.
‘Then the welding is carried out throughout the length.
‘As soon as the welding process is finished, switched off the current supply and allow the work
piece to cool.
Slags are removed by chipping process with the help of chipping hammer.
Finally using wire brush, welded portions are cleaned,
Result:
“Thus the desired Single V-Butt joint is obtained using arc welding.Ex.No.2 LAP JOINT
Aim:
To make a lap joint using are welding on the given workpieces.
Material supplied:
Mild steel! plate of size 102 x 51 x 6mm - 2 Nos.
Tools required:
Power supply (AC or DC)
Welding Torch
Electrodes
‘Tongs
Chipping hammer
Wire brush
Gloves
Apron
Shield
10. Safety goggles
11. Earthing clamps
Sequence of operations:
. Edge preparation (Removal of rust, scale etc.,)
Tacking
Welding
Cooling
Chipping
Cleaning
Working steps:
1. First ofall, the work pieces must be thoroughly cleaned to remove rust, scale and other foreign
materials.
2. Then the given work pieces are placed on the table in such a way that two work pieces are
overlapped one over another as shown in fig.
. Appropriate power supply should be given to the electrode and work pieces.
|. Now the welding current output may be existed.
|. When current is passed, arc is produced between the electrode and work pieces.
. Set the two work pieces in correct position like lap joint and tack at both ends of the work
pieces as shown in the figure.
Then the welding is carried out throughout the length of the work piece.
8. As soon as the welding process is finished, switch off the current supply and allow the work
piece to cool.
9. Slags are removed by chipping process with the help of chipping hammer.
10. Finally using wire brush, welded portions are cleaned.
Pee eNe Penansen-
eee
~
Result:
“Thus the desired lap joint is obtained using arc welding.(?SS—Yys
Ly
ASS
LA
Welded Joint Representationsotto
Welded Joint RepresentationEx.No.3 T-FILLET JOINT
Aim:
To make a T-Fillet joint using arc welding on the given workpieces.
Material supplied:
Mild steel plate of sive 100 x 50 x 6mm - 2 Nos.
‘Tools required:
Power supply (AC or DC)
Welding Torch
Electrodes
Tongs
. Chipping hammer
Wire brush
Gloves
Apron
. Shield
10. Safety goggles
11. Earthing clamps
SPesensune
Sequence of operations:
Fdge preparation (Removal of rust, scale etc.,)
‘Tacking
. Welding
Cooling
. Chipping
. Cleaning
Working steps:
1. First ofall, the work pieces must be thoroughly cleaned ta remove rust, scale and other foreiga,
materials,
2. Then the given work pieces are placed on the table in such a way that two work pieces are
brought close to each other so that it forms a ‘T* shape is shown in the fig.
3. Appropriate power supply shuld be given to the electrade and work pleces.
4. Now the welding current output may be existed.
5. When current is passed, arc is produced between the electrode and work pieces,
6. Set the two work pieces in correct pasition like T’-Fillet joint and tack at both ends of the work
pices as shown in the figure.
7. The joint is placed on a welding table in a fal position by keeping the tack side down.
8, Then the welding is carried out throughout the length.
9. Assoonas the welding process is finished, switched off the current supply and allow the work
piece to cool
10, Slags are removed by chipping process with the help of chipping hammer.
11. Finally using wire brush, welded portions are cleaned.
eusene
Result:
‘Thus the desired T-Fillet joint is obtained using arc welding.