Professional Documents
Culture Documents
Cash Flow Notes
Cash Flow Notes
RICS HQ
Parliament Square
London SW1P 3AD
Advancing standards in land, property and construction.
RICS is the world’s leading qualification when it comes to
Cash flow forecasting
United Kingdom professional standards in land, property and construction.
Worldwide media
In a world where more and more people, governments, banks and 1st edition, guidance note
enquiries:
commercial organisations demand greater certainty of professional
e pressoffice@rics.org
standards and ethics, attaining RICS status is the recognised
Contact Centre: mark of property professionalism.
e contactrics@rics.org
t +44 (0)870 333 1600 Over 100 000 property professionals working in the major established
f +44 (0)20 7334 3811 and emerging economies of the world have already recognised the
importance of securing RICS status by becoming members.
RICS is an independent professional body originally established
in the UK by Royal Charter. Since 1868, RICS has been committed
to setting and upholding the highest standards of excellence and
integrity – providing impartial, authoritative advice on key issues
affecting businesses and society.
RICS is a regulator of both its individual members and firms enabling
it to maintain the highest standards and providing the basis for
unparalleled client confidence in the sector.
RICS has a worldwide network. For further information simply contact
the relevant RICS office or our Contact Centre.
rics.org/standards
Cash flow forecasting
Contentsiii
Acknowledgmentsv
Introduction2
This publication provides best practice expenses incurred due to a specific event that
guidance on cash flow forecasting for project has occurred on the project due to no fault of
and cost managers in all world regions. The the contractor.
purpose of this guidance note is to ensure
consistent practice, delivered in a professional ‘Foreign exchange exposure’ is defined as the
manner that is in line with internationally exposure a project may have to increased (or
recognised guidance. The guidance sets a decreased) costs due to the fluctuations in
framework for best practice, subject to specific exchange rates when purchases or payments
local legislative requirements and local market are being undertaken in a different currency to
specifics. the project’s expressed currency.
Where the legislative requirements differ by The following is a list of items included in this
jurisdiction, these have been referred to as ‘local guidance note which may not be applicable in
legislative requirements’. Where requirements all jurisdictions:
or issues differ by jurisdiction, these have been
referred to as ‘local jurisdiction issues’. Taxation • Contractual penalties (section 3.6.2).
issues have been referred to as ‘local taxation
issues’. The following items are not discussed in detail
in this guidance note, but may have an impact
‘Third-party certification’ is defined as a third and need to be taken into account when
party or independent consultant (normally preparing cash flow forecasts:
appointed by the owner) undertaking the
measurement and valuation of the work • advance payments
performed to date, for the purpose of
• retention guarantees
determining payment.
• foreign exchange exposure and exchange
A ‘provisional sum’ is defined as an estimated rate hedging
sum included in the contract for work, which
could not be clearly defined before entering into • escalation
the contract and which may be amended once • the use of cash flows to identify trends and
the scope of the work becomes clearly defined. potential change orders, and
‘Claim for loss and expense’ refers to a claim • the international use of cash flow forecasts,
made by the contractor for loss of profit and such as for earned value calculations.
Practice statement
RICS practice statement Document that provides members with mandatory Mandatory
requirements under Rule 4 of the Rules of Conduct
for members
Guidance
RICS code of practice Document approved by RICS, and endorsed by Mandatory or recommended
another professional body/stakeholder that provides good practice (will be
users with recommendations for accepted good confirmed in the document
practice as followed by conscientious practitioners itself)
RICS guidance note (GN) Document that provides users with recommendations Recommended good practice
for accepted good practice as followed by competent
and conscientious practitioners
RICS information paper (IP) Practice based information that provides users with Information and/or
the latest information and/or research explanatory commentary
This guidance note summarises what cash flow or when variations to the model occur (i.e.
forecasting is, how to produce a useful forecast non-expenditure of provisional sums, claims,
and how to then use the forecast to assess extension of times).
progress on site, as well as other issues. It also
aims to assist both employers and contractors Guidance is given in relation to the main forms
to analyse actual expenditure against forecast of contract and main procurement routes,
expenditure. under the following headings which map to the
Assessment of Professional Competence (APC):
For the purposes of giving guidance the
client is referred to as the ‘employer’ and the • General principles (Level 1: Knowing)
main contractor as the ‘contractor’. However, • Practical application (Level 2: Doing)
much of the guidance can equally be applied • Practical considerations (Level 3: Doing/
to a contractor/sub-contractor or supplier Advising).
arrangement.
Guidance is given in this section in respect of: from the employer to the main contractor unless
what purposes cash flow forecasts are used for; otherwise stated.
their usefulness in terms of running a business
and predicting business failure; the various Other directions of cash flow to consider are
contractual mechanisms for dealing with cash the main contractor’s cash flow to their sub-
flows; the relevant legislative items and the contractors and suppliers, the employer’s cash
formulas or ‘curves’ used to predict the cash flow to consultants (i.e. architect and cost
flow for construction projects. manager, etc.) and other fees (fit-out costs, local
taxation issues, etc.) for an overall project cash
(see Table 1).
1.1 Uses of cash flow forecasts From Employer Main Sub
There are two main types of cash flow forecast: contractor contractors
To Main Sub Suppliers
• The cash flow forecast of a company (i.e. a contractor contractors
contractor or consultant) – otherwise known Consultants Suppliers Specialist
as organisational cash flow.
Specialist HM
• The cash flow forecast of a particular contractors Revenue &
construction contract or project – otherwise Customs
known as project cash flow. HM Revenue & Designers
The cash flow forecast of a company will Customs
review and analyse the predicted incoming Direct
and outgoing cash for a set period of time appointments
(usually a year) and is often used for business
and resource planning, and for analysing the Table 1: Potential directions of cash flow
financial health of companies.
The following list is not exhaustive but aims to
The cash flow forecast of a construction illustrate some of the common usages of cash
contract or project deals specifically with the flow forecasts:
payments due under a particular construction
contract. The construction contract cash flow 1.1.1 Obtaining loans and bank
will often inform a company’s overall cash flow
monitoring
as they are intrinsically linked. It is important
to understand both types of cash flow forecast In simple terms the purpose of a cash flow
and how and why they are used within the forecast is to ensure that the employer has an
construction industry. accurate assessment of what needs to be paid
to the contractor and at what periods, therefore
Various parties within a construction contract the employer’s bank or funder needs to be
use cash flow forecasts for different reasons aware of drawdowns to manage the movement
and it is therefore not uncommon to present of funds to meet the contractual timescales
cash flow forecasts in different ways to fit the of payment. Although especially important for
requirement. It is also important to note that developers and clients if they are obtaining debt
cash flow can travel in different directions, but finance (loans) to fund their projects, it is also
for the purposes of this guidance note any important if they are using their own money. It is
reference to cash flow shall mean the cash flow not uncommon for banks and other funders to
4 Valuation of works done to date on At pre-agreed periods the value Provides lowest predictability
site (third-party certification) of work on site is assessed of cash flow forecast but high
accuracy of value of works done
to date
1.3.2 The effect of valuation method the milestone payments the more accurate the
upon cash flow forecast assessment of works will be. However, this
inevitably leads to a less accurate predictability
1.3.2.1 Stage payments of the cash flow.
Stage payments are often used under design Therefore there may be a time lag between
and build contracts and are effectively pre- the completion of an activity under an activity
agreed values to be paid to the contractor schedule and recognition of that completed
at predetermined times. These are not tied activity, whereas with a milestone payment a
to milestones and are the least accurate contractor can ask for certification once the
assessment of works carried out on site. There milestone is complete.
is a benefit to the employer in knowing the
exact amount due at any given time but this 1.3.2.4 Third-party certification
increases the risk of overpaying (or indeed
This is when a third party (usually the cost
underpaying) the contractor. A valuation of
manager) measures and values the works
works done on site could therefore be very
carried out to date by visiting sites and
different to a third-party certification if they are
assessing the value of preliminaries, works
not tied to milestones.
carried out, materials on site, materials off site
1.3.2.2 Milestone payments (if applicable), and any instructed variations.
This provides the most accurate assessment of
Milestone payments are a type of stage works carried out on site to date.
payment but instead of being triggered by
reaching a given date, payment is triggered 1.3.2.5 Actual cost/target cost
by completing a pre-agreed milestone. In its
If an actual cost/target cost contract is used,
simplest form this could constitute a single
and if both parties agree, then the monthly
payment at the completion of the building, but
valuations are assessed by ascertaining the
more likely they will be tied to elements (e.g.
contactors actual costs plus any agreed
completion of foundations, completion of frame,
fee percentages. This can be carried out by
etc). It is also possible to be very prescriptive
reviewing actual invoices. It should be noted
and have milestones payments associated with
that these are not lump sum contracts and there
sub-sections of elements (e.g. completion of
is a risk that actual costs could exceed the
laying rebar to first floor). The more prescriptive
target cost.
requirements 40
This section looks in more detail at the practical The user of the cash flow forecast should be
applications of producing a cash flow forecast kept in mind when reviewing the following
and the information required to improve the sections.
accuracy of the forecast. This section deals
specifically with cash flow forecasting at
construction project level (see Figure 3), but 2.2 Identifying the employer’s
many of the principles will equally apply to brief for the cash flow
organisational cash flow forecasting.
forecast
Wherever possible the cash flow forecast
should be written in conjunction with the main Before undertaking a cash flow forecast it
contractor who will often be able to provide is imperative that a brief is taken from the
more detailed and specific information, although employer to make certain that it provides the
it is recognised that this will often not be information that the employer requires. The
possible at the early stages of a project. following are examples of the types of questions
that should be asked:
A differential should also be made between the
overall cash flow profiles for a project, which will • Is it for the employer or contractor?
be the accumulation of a number of separate • Should it be produced for the whole
cash flow profiles for the many cost centres development or just the construction
within a project (see Figure 4). contract?
• Should it show values at valuation date,
2.1 Contractor versus certificate date, invoice date or payment
date?
employer’s approach to • Should gross or net values be used?
cash flow forecasting • Should it show cumulative payments,
It should be noted that there is generally a monthly payments or both?
difference in the approach to producing a Different construction contracts have different
cash flow forecast between an employer and payment terms and timescales, which have a
a contractor. Different considerations will be significant impact on the cash flow profile of a
important to each party, in terms of payment project. It is always important to check whether
dates and presentation of the cash flow the employer intends to amend contracts
forecast, and some issues will not be applicable to provide different payment periods for the
or will differ between one party and another employer.
(i.e. the employer may hold retention against
the contractor, but the contractor may not hold In an international context it is also important
retention against their sub-contractors). The that other issues are addressed such as
remainder of this section does not differentiate escalation, currency and foreign exchange
explicitly between these different approaches. exposure.
rio t
es rac
lia fect
pe trac
pe ility
wo itati
d
Fe on
d
s
b
rio
Co
cil
C
e-
Fa
Pr
This section looks at the practical has been based on the programme/schedule
considerations that have to be made when or an activity schedule, then it can be inferred
producing and analysing cash flow forecasts. that variances to the forecast therefore mean
variances to the programme/schedule. This is
A chartered surveyor should consider the not always strictly true as the variances may be
following when advising on the uses of a cash a result of re-sequencing or other factors, but
flow forecast and, in particular, when using the it does provide a good guide and may prompt
cash flow forecast to monitor progress on site questions.
or when assessing claims.
If the valuation for a particular month is
significantly lower than the cash flow forecast
3.1 Cash flow representation then it could be inferred that the contractor
is simply behind their intended programme/
Graphs can be used: schedule.
• to visually illustrate the cash flow forecast Some of the reasons for actual payments being
• to show either the cumulative or a periodic below the cash flow include:
cash flow
(a) site conditions
• to show periodic payments on a bar chart
(b) adverse weather
• to show both cumulative and periodic
(c) re-sequencing of works (perhaps due to
payments together (see Figure 6).
procurement of sub-contractors)
(d) materials being stored off site (and not
3.2 Reasons for variances to claimed for)
cash flow (e) project progressing slower than anticipated
(f) materials not being delivered on time
Once a cash flow is established then it should
also be used to monitor variances to it. It can (g) cash flow not being accurate in the first
be used as a tool to compare the forecast place, and
with the actual payments and ascertain what (h) inaccurate calculation of the work performed
these results show. If the cash flow forecast to date.
3.0 M 10 M
Periodic
2.5 M
8M
Cumulative
2.0 M
6M
Periodic 1.5 M Cumulative
4M
1.0 M
2M
0.5 M
0M 0M
May
Aug
Mar
Sep
Apr
Oct
Jun
Feb
Jan
Jul
Figure 6: Graph showing the relationship between periodic and cumulative payments
Variations / compensation
Construction events
Claims
Final account Final account
Figure 7: Diagram showing the relationship between the stage of the project
and the information used in the production of the cash flow forecast
e
ice
rks
am
rv
Fr Se
wo
es
lo
+E
ish
ve
and taking into account any pain/gain share. In
Gro
g
En
Fin
lin
FF
Pi
this scenario the cash flow forecast should be Time
updated regularly to reflect the actual costs as The various overlapping cash flows within a
they emerge. construction management procurement route
es
rvic
(see Figure 8). The contractual relationships fees an
d se
io nal
in a construction management procurement Pro
fess
RICS HQ
Parliament Square
London SW1P 3AD
Advancing standards in land, property and construction.
RICS is the world’s leading qualification when it comes to
Cash flow forecasting
United Kingdom professional standards in land, property and construction.
Worldwide media
In a world where more and more people, governments, banks and 1st edition, guidance note
enquiries:
commercial organisations demand greater certainty of professional
e pressoffice@rics.org
standards and ethics, attaining RICS status is the recognised
Contact Centre: mark of property professionalism.
e contactrics@rics.org
t +44 (0)870 333 1600 Over 100 000 property professionals working in the major established
f +44 (0)20 7334 3811 and emerging economies of the world have already recognised the
importance of securing RICS status by becoming members.
RICS is an independent professional body originally established
in the UK by Royal Charter. Since 1868, RICS has been committed
to setting and upholding the highest standards of excellence and
integrity – providing impartial, authoritative advice on key issues
affecting businesses and society.
RICS is a regulator of both its individual members and firms enabling
it to maintain the highest standards and providing the basis for
unparalleled client confidence in the sector.
RICS has a worldwide network. For further information simply contact
the relevant RICS office or our Contact Centre.
rics.org/standards