As Pare Oshad Cop 53.1 Ohs
As Pare Oshad Cop 53.1 Ohs
رقم المشروع
Project / Contract
اسم المشروع /العقد
Name
Contractor Name اسم المقاول
Location الموقع
CONTENTS المحتويـــــــــــــــــــــات
Appendices الملحقــــــــــــــــــــــــــــات
1|P a g e
contractor, how will execute the work without any noncompliance in the system as low as
reasonably practicable.
Transportation:
Fm200 system will be transported to the site by the supplier.
All items delivered to the site will be first inspected to check that they are in
accordance
with delivery documents, and that they are free from any damage caused
during
transportation to site
Loading and unloading of Fm200 systems (cylinder, nozzles, extinguishing
panels including accessories should be carried out through tower/ mobile
crane or by adequate boom loader.
Handling:
Fm200 cylinder, fittings, extinguishing panel including accessories should not
be dropped and should not be dragged along the ground.
Loading and unloading of Fm200 cylinder including accessories should be
carried out through tower/ mobile crane or by adequate boom loader.
Handling to be strictly as per manufacturer's recommendations.
On the receipt of System, a visual check will be made to determine if any
damage has occurred in transit. The typical points to look for are: broken or
crack equipment e.g. base frame, motor, pump feet and flanges, Bent shafts,
damaged motor end bells, bent eyebolt or damaged boxes
Check loose parts are often wrapped individually and or fastened to the
equipment.
Delivery documentation shall be checked for completeness
Storage:
If the system is not to be installed immediately after delivery at site, it should
be stored in a clean, dry area with protection from moisture, dust, dirt and
2|P a g e
foreign bodies. In particular, the following action should be taken;
Storage - to be strictly as per manufacturer's recommendations.
No materials will be permitted to be used without being inspected on arrival
to the site
Protect the system accessories from dust and moisture during storage
Keep all FM200 Clean Agent Fire Extinguishing System accessories in
factory packed
shipping boxes until time of installation.
Adequate storage facilities will be provided to ensure the pipe tubes and
fittings do not
suffer any deterioration from the ‘as new’ delivered condition
Inspection of Materials:
Upon receipt of Fm200 cylinder, fittings, extinguishing panel including
accessories on site these will have to be inspected by the Storekeepers and
QC Engineer or representative’s QC Engineer, to ensure correctness of
materials in accordance with approved material submittals and quantities
QA / QC Engineer shall raise a MIR for submission to the Engineer for
approval.
Pre-Installation Procedures.
Ensure that the approved materials are available to carry out the work,
as per the approved Material Submittal & Project Specification.
Physical verification of materials will be carried out for any damages
prior taking from stores.
Prior to commencement of work, areas and access will be inspected to
confirm that site is ready to commence the work, as per approved
drawings.
Extra care will be observed in unpacking the shipping boxes of the
FM200 Clean Agent
Fire Extinguishing System accessories during inspection and
installation to prevent from
any damage
All relevant documentation (catalogue, Shop Drawings and
coordination drawings) and Materials applicable to particular section
of works will be checked by the Supervisor prior to commencement of
work and ensure that all personnel are working on the same drawing.
Check all proper tools and equipment are available to carry out the
work and in compliance with contract specification. Ensure that all
drawings to be used at site are approved drawing.
The Project Engineer / Supervisor will give necessary instructions to
tradesmen and provide necessary approved Shop drawings along with
3|P a g e
the coordinated layouts.
FM200 Clean Agent Fire Extinguishing System pipes will be painted
by the approved paint
by the consultant as per specification.
Prepare tools/equipment and materials for installation of FM200
Clean Agent Fire
Extinguishing System.
Prior to installation works verify the location for the approved
clearance of
civil/architectural finish.
Coordinate the FM200 Clean Agent Fire Extinguishing System
installation with other MEP
services installation and make adjustment if need.
Correct any unsatisfactory conditions detrimental to the proper and
timely completion of
the installation.
Installation drawing and approved shop drawing/related to the
approved coordination
drawing will be available at all times on site and they are issued for
construction.
Layout the location of anchorage for the FM200 Clean Agent Fire
Extinguishing System
and accessories and coordinate with other installed and un-installed
MEP services.
The Project Engineer / Supervisor will also check that adequate no. of
tradesmen including proper tools and equipment are available to carry
out the work and are in compliance with the contract specifications.
Thorough coordination with Main Contractor must be implemented
before & during installation work
Ensure that the area for materials preparation / fabrication for pipe
installation have been identified
Ensure that the pipes and fittings are painted as per the specification
after taking it from the stores & before installing them in site. (refer
approved MS for Installation of Wet Riser System and Sprinkler
System)
Temporary DBs are provided and inspected regularly by the
tradesmen prior to execution of the works.
The Project Engineer/Safety officer also explains the tradesmen
regarding safety precautions to be observed.
All works must be carried out according to method statement and risk
assessment.
All chemicals must be used, storage & disposal according to material
safety data sheet (MSDS) requirements.
4|P a g e
MSDS copy shall be distributed in the working area, storage area and
to the safety department.
Appropriate PPE must be used as required.
All operatives must be aware about chemical hazards.
Trained & competent persons only allowed to the job.
Proper supervision is required.
Fire extinguisher must be provided.
Fix the supports for pipes on the ceiling/wall as per approved drawings
Cut pipes as per approved drawings and thread those using sharp dies.
Clean the pipes internally to remove burrs and foreign material. Ensure pipes are free from
particulate
matter and oil residue before installation.
Install pipes as per approved drawings. Apply joint/tape only to the male portion of the
threads of pipes.
Seal all penetration with fire stopping sealant.
Arrange visual inspection of pipes for proper location.
Paint the pipes as per approved specification Check that the location of cylinders is suitable
for inspection, testing, recharging and other
maintenance activities. If it is found otherwise, inform the concerned get the approval for
an alternate location.
Check that nozzles are installed as per the part numbers shown on drawings.
Check that correct type of nozzle (180°/360°) is used.
Check that 360° nozzles are located at the center of the room and 0° near the wall of the
room.
Check that pipe work is pneumatically tested as per NFPA 2001 with Nitrogen gas.
Duration of 10Minutes at 40psi (276kpa) at the end of 10Minites, the pressure drop shall
not exceed 20% of the test pressure.
Check the nameplate of the cylinders to confirm the weight of the agent. Tare weight,
gross weight and super pressurization level are as per the shop drawings.
Verify that the pressure gauge of cylinder is within the ‘green range’.
5|P a g e
Install & Label the initiating and releasing circuits as per approved drawings
Identify the cables as with tags and terminate cables with ferrules.
Ensure that location of the manual release unit is accessible always even during fire
conditions.
Locate all devices so that it will not be subjected to damage.
Install smoke detectors as per approved drawings
Ensure that detectors are installed in a cross zoned configuration.
Check that EOL resistors are installed for all devices and are of correct.
Ensure that terminations inside the control panel are completed as per approved wiring
diagrams.
Check that battery is provided inside the control panel.
Ensure that Interface between the FM-200 System with the Building Fire Alarm System.
Ensure that Fire Proof cable (2C X1.5mm sq.) laid between FM200 systems with BMS for
the interfacing.
Ensure that Interface between the FM-200 System with the HVAC dampers for the room
integrity.
Check that EOL resistors are installed in the detection and bell circuits.
Check that warning sign is installed at the entrance of the protected area.
6|P a g e
TESTING PROCEDURE (Pneumatic Pressure Test):
Ensure that the piping network are inspected and accepted by consultant prior to
7|P a g e
conducting pneumatically testing.
Ensure the piping shall be pneumatically tested in a closed circuit for a period of10minutes
at 40 psig (276 kPa). At the end of 10 minutes, the pressure drop shall not
exceed 20 percent of the test pressure.
A flow test using nitrogen or an inert gas shall be performed on the piping network to
verify unobstructed.
Repair leaks and defects, if any, and retest the piping system.
Internal testing shall be performed and if found satisfactory, then the same will be offer
for inspection to consultant
6.0- Equipment & Resource to be Used 6.0- المعـــدات والمصـادر التـــي يجـب إستخدامــها
No. Equipment’s No. Equipment’s
01 Standard Mechanical Tool Box 10 Straight edge/Feeler Gauges
In the event of emergency and health safety staff shall present in the area will automatically take
appropriate action to provide first aid and lifesaving assistance till the arrival of the emergency
8|P a g e
rescue team or the ambulance.
Siren/Alarm Tones
Upon emergency general will be a “Continuous Tone”
After evacuation (all clear) alarm will be “short double tone”
All workplaces will have safe access and egress well defined with escape routes displayed.
The site of work will be screened off. All opening, edges of excavations will be protected or
barricaded with warning signs displayed.
Permits Required Yes No Assessments Required (attach if “Yes) Yes No
Work permit COSHH
Hot works Noise
Boom Loader Check List Manual handling
9|P a g e
Confined space entry Other (state)
Work at Height.
Further Control Measures / Security Requirements
Prior to doing maintenance the information shall be passed to the and approval shall be
taken.
11 | P a g e
g. Responsible for the development HSE system including plan, HSE procedures, Task risk
Assessment and requirement of adequate PPE to execute the activity safely.
h. Advice and assist the project manager for implementing the HSE system.
i. Duties and responsibilities include planning and scheduling the safety provisions of the
works at project sites.
j. Report to the project manager/coordinator on a regular basis.
k. Work closely with the project manager to assist/advise HSE measures at the workplaces.
l. Inspecting and recording the site safety activities and advising the site personnel for safe
work at sites.
m. Inspecting the welfare facilities of the working crew at sites.
n. Inspecting the traffic management arrangements at sites.
Appendices الملحقــــــــــات
.1 Risk Assessments 1. تقييمــــــــــــــــــات المخاطـــــــــــــــــــــــــــــر
Hazard Identification Yes No Hazard Identification Yes No
Slip and Trips Coshh
Manual Handing Noise
Hand Tolls Work at High
Welding Dust/Fumes
Machinery/Lifting Equipment Lighting
Fire 3rd party (Contractor)
Fall of Material Environmental
Electrical Other
Who Might Be Harmed?
Own Personnel Yes ☒ No ☐ Office Staff or Visitors Yes ☐ No ☒
Other Contractors’ Yes ☐ No ☒ Members of the Public Yes ☐ No ☒
First Aid Reportable Major Disablement Fatal
Potential Severity of Injury or Illness
☒ ☒ ☒ ☐ ☐
1 2-5 6-20 21-100 10+
Number of workers exposed to hazard
☐ ☒ ☐ ☐ ☐
Probability of injury or illness Happens Happens Happens on Happens Certain to
12 | P a g e
rarely each Year most jobs regularly happen
☒ ☐ ☐ ☐ ☐
Overall assessment of risk prior to the Low Moderate Substantial High
implementation of control measure ☐ ☒ ☐ ☐
2. Drawings, BOQ and Specifications References 2. مراجع المواصفـات وجدول الكميات ومخططــات
No. Ref. to B.O.Q / Spec. Ref. QY. Unit Material Description
The company certifies that all information a above found to تشهد الشركة بان كل المعلومات التى اصدرت تحت هذا التقديم قد تم
be following the Contract documents. التحقق منها ووجدت مطابقه مع وثائق العقد.
Company الشركة
contractor التاريخ النوقيع األسم
Engr. Hussain
Date Signature Name
االسم االسم
Name Name
Resident Engineer Comments مالحظات المهندس المقيم
فقط تعبىء إذا تم اإلشارةعلىـ المربع المخصص أعاله بالشخصـ ذات الصلة:مالحظات مديرالمشروع
Project Manager Comments: (to be filled ONLY if the escalation box above to the relevant person is Ticked)
Review Status (by Final Approver) )حالةالمراجعة (منخالآلخرموافقة
NO OBJECTION= A ☐ موافق
No Objection AS Noted = B ☐ موافقمعالمالحظات
REVISE & RESUBMIT = C ☐ يراجعويعادتقديمه
13 | P a g e
REJECTED = D ☐ مرفوض
Comments raised to PM = E ☐ مالحضات تم رفعها لمدير المشروع
Comments مالحظات
14 | P a g e