Professional Documents
Culture Documents
com
CA
INTERMEDIATE
PAPER-3: COST AND MANAGEMENT
ACCOUNTING
COMPILER
Most IMP Collection of Chapterwise
Questions & Answers
CONTENTS
CHAPTER-1
INTRODUCTION TO COST AND MANAGEMENT ACCOUNTING
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -1-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -3-
(ii) Variable Costs – These costs tend to vary with the volume of activity. Any in crease in the activity
results in an increase in the variable cost and vice -versa. For example, cost of direct labour, etc.
(iii) Semi-variable Costs – These costs contain both fixed and variable components and are thus
partly affected by fluctuations i n the level of activity. Examples of semi variable costs are telephone
bills, gas and electricity etc.
Q-9 Discuss the four different methods of costing alongwith their applicability to concerned industry?
Ans. Four different methods of costing along with their applicability to concerned industry have been
discussed as below:
(i) Job Costing: The objective under this method of costing is to ascertain the cost of each job order.
A job card is prepared for each job to accumulate costs. The cost of the job is determined by
adding all costs against the job it has incurred. This method of costing is used in printing press,
foundries and general engineering workshops, advertising etc.
(ii) Batch Costing: This system of costing is used where small components/ parts of the same kind are
required to be manufactured in large quantities. Here batch of sim ilar products is treated as a job
and cost of such a job is ascertained as discussed under (1), above. If in a cycle manufacturing unit,
rims are produced in batches of 2,500 units each, then the cost will be determined in relation to a
batch of 2,500 units.
(iii) Contract Costing: If a job is very big and takes a long time for its completion, then method used for
costing is known as Contract Costing. Here the cost of each contract is ascertained separately. It is
suitable for firms engaged in the construct ion of bridges, roads, buildings etc.
(iv) Operating Costing: The method of Costing used in service rendering undertakings is known as
operating costing. This method of costing is used in undertakings like transport, supply of water,
telephone services, hospitals, nursing homes etc.
Q-10 Discuss the prerequisite of installing cost accounting system.
Ans. Before setting up a system of cost accounting the un der mentioned factors should be studied:
(i) Objective: The objective of costing system , for example whether it is being introduced for fixing
prices or for insisting a system of cost control.
(ii) Nature of Business or Industry: The Industry in which business is operating. Every business industry
has its own peculiar ity and objectives. According to its cost information requirement cost
accounting methods are followed. For example, an oil refinery maintains process wise cost
accounts to find out cost incurred on a particular process say in crude refinement process etc.
(iii) Organisational Hierarchy: Costing system should fulfil the information requirement s of different
levels of management. Top management is concerned with the corporate strategy, strategic level
management is concerned with marketing strategy, product diversification, product pricing etc.
Operational level management needs the information on standard quantity to be consumed,
report on idle time etc.
(iv) Knowing the product: Nature of product determines the type of costing system to be implemented.
The product which has by -products requires costing system which account for by-products as
well. In case of perishable or short self - life, marginal costing method is required to know the
contribution and minimum price at which it can be sold.
(v) Knowing the production process: A good costing system can never be established without the
complete knowledge of the production process. Cost apportionment can be done on the most
appropriate and scientific basis if a cost accountant can identify degree of effort or resources
consumed in a particular process. This also includes some basic technical know -how and process
peculiarity.
(vi) Information synchronisation: Establishment of a department or a system requires substantial
amount of organisational resources. While drafting a costing s ystem, information needs of various
other departments should be taken into account. For example, in a typical business organisation
accounts department needs to submit monthly stock statement to its lender bank, quantity wise
stock details at the time of filing returns to tax authorities etc.
(vii) Method of maintenance of cost records: The manner in which Cost and Financial accounts could
be inter-locked into a single integral accounting system and how the results of separate sets of
accounts i.e. cost and financial, could be reconciled by means of control accounts.
(viii) Statutory compliances and audit: Records are to be maintained to comply with statutory
requirements and applicable cost accounting standards to be followed .
(ix) Information Attributes: Information generated from the Costing system should possess all the
att ributes of information i.e. complete, accurate, timeliness, relevant etc. to have an effective
management information system (MIS).
Q-11 Discuss the essential features of a good cost accounting system.
Ans. The essential features, which a good cost and management accounting system should possess, are as
follows:
(i) Informative and simple: Cost and management accounting system should be tailor-made, practical,
simple and capable of meeting the requirements of a business concern. The system of costing
should not sacrifice the utility by introducing meticulous and unnecessary details.
(ii) Accurate and authentic: The data to be used by the cost and management accounting system
should be accurate and authenticated; otherwise it may distort the output of the system and a
wrong decision may be taken.
(iii) Uniformity and consistency: There should be uniformity and consistency in classification, treatment
and reporting of cost data and related information. This is required for benchmarking and
comparability of the results of the system for both horizontal and vertical analysis.
(iv) Integrated and inclusive: The cost and management accounting system should be integrated with
other systems like financial accounting, taxation, statistics and operational research etc. to have
a complete overview and clarity in results.
(v) Flexible and adaptive: The cost and management accounting system should be flexible enough to
make necessary amendments and modification in the system to incorporate changes in
technological, reporting, regulatory and other requirements.
(vi) Trust on the system: Management should have trust on the system and its output. For this, an
active role of management is required for the development of such a system that reflects a strong
conviction in using information for decision making.
Q-12 State the limitations of cost and management accounting.
Ans. Like other branches of accounting, cost and management accounting is also having certain limitations.
The limitations of cost and management accounting are as follows:
1. Expensive: It is expensive because analysis, allocation and absorption of overheads require
considerable amount of additional work, and hence additional money.
2. Requirement of Reconciliation: The results shown by cost accounts differ from those shown by
financial accounts. Thus Preparation of reconciliation statements is necessary to verify their
accuracy.
3. Duplication of Work: It involves duplication of work as organization has to maintain two sets of
accounts i.e. Financial Account and Cost Account.
4. Inefficiency: Costing system itself does not control costs but its usage does.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -5-
Q-13 Explain the difference between Cost Accounting and Management Accounting
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -7-
(iii) Information Technology with the help of internet (including intranet and extranet) helping in
resource procurement and mobilisation. For example, production department can get materials
from the stores without issuing material requisition note physically. Similarly, purchase orders can
be initiated to the suppliers with the help of extranet. This enables an entity to shift towards Just-
in-Time (JIT) approach of inventory management and production.
(iv) Cost information for a cost centre or cost object is ascertained with accuracy in timely manner. Each
cost centre and cost object is codified and all related costs are assigned to the cost objects or cost
centres using assigned codes. This automates the cost accumulation and ascertainment process.
The cost information can be customised as per the requirement. For example, when an entity
manufacture or provide services, are able to know information job-wise, batch-wise, process-
wise, cost centre wise etc.
(v) Uniformity in preparation of report, budgets and standards can be achieved with the help of IT.
ERP software plays an important role in bringing uniformity irrespective of location, currency,
language and regulations.
(vi) Cost and revenue variance reports are generated in real time basis which enables the management
to take control measures immediately.
(vii) IT enables an entity to monitor and analyse each process of manufacturing or service activity
closely to eliminate non value added activities.
Q-18 State the Method of Costing to be used in the following industries:
(i) Real Estate
(ii) Motor repairing workshop
(iii) Chemical Industry
(iv) Transport service
(v) Assembly of bicycles
(vi) Biscuits manufacturing Industry
(vii) Power supply Companies
(viii) Car manufacturing Industry
(ix) Cement Industry
(x) Printing Press
Ans. Method of costing used in different industries:
S. No. Industries Method of Costing
(i) Real Estate Contract Costing
(ii) Motor Repairing Workshop Job Costing
(iii) Chemical Industry Process Costing
(iv) Transport Service Service/Operating Costing
(v) Assembly of Bicycles Unit/ Single/Output/Multiple Costing
(vi) Biscuits Manufacturing Industry Batch Costing
(vii) Power Supply Companies Service/Operating Costing
(viii) Car Manufacturing Industry Multiple Costing
(ix) Cement Industry Unit/Single/Output Costing
(x) Printing Press Job Costing
-8- Chapter-1 : Introduction to Cost & Management Accounting
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -9-
(ii) Variable Costs – These costs tend to vary with the volume of activity. Any increase in the activity
results in an increase in the variable cost and vice-versa.
For example, cost of direct labour, etc.
(iii) Semi-variable Costs – These costs contain both fixed and variable components and are thus partly
affected by fluctuations in the level of activity. Examples of semi variable costs are telephone
bills, gas and electricity etc.
---0---0---
CHAPTER-2
MATERIAL COST
Q-1 Arnav Electronics manufactures electronic home appliances. It follows weighted average Cost method
for inventory valuation. Following are the data of component X:
Date Particulars Units Rate per
unit (`)
15-12-19 Purchase Order- 008 10,000 9,930
30-12-19 Purchase Order- 009 10,000 9,780
01-01-20 Opening stock 3,500 9,810
05-01-20 GRN*-008 (against the Purchase Order- 008) 10,000 -
05-01-20 MRN**-003 (against the Purchase Order- 008) 500 -
06-01-20 Material Requisition-011 3,000 -
07-01-20 Purchase Order- 010 10,000 9,750
10-01-20 Material Requisition-012 4,500 -
12-01-20 GRN-009 (against the Purchase Order- 009) 10,000 -
12-01-20 MRN-004 (against the Purchase Order- 009) 400 -
15-01-20 Material Requisition-013 2,200 -
24-01-20 Material Requisition-014 1,500 -
25-01-20 GRN-010 (against the Purchase Order- 010) 10,000 -
28-01-20 Material Requisition-015 4,000 -
31-01-20 Material Requisition-016 3,200 -
*GRN- Goods Received Note; **MRN- Material Returned Note Based on the above data, you are required
to CALCULATE:
(i) Re-order level
(ii) Maximum stock level
(iii) Minimum stock level
(iv) PREPARE Store Ledger for the period January 2020 and DETERMINE the value of stock as on 31-01-
2020.
(v) Value of components used during the month of January, 2020.
(vi) Inventory turnover ratio.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -11-
Ans. Workings:
Consumption is calculated on the basis of material requisitions:
Maximum component usage = 4,500 units (Material requisition on 10-01-20)
Minimum component usage = 1,500 units (Material requisition on 24-01-20)
Lead time is calculated from purchase order date to material received date
Maximum lead time = 21 days (15-12-2019 to 05-01-2020)
Minimum lead time = 14 days (30-12-2019 to 12-01-2020)
Calculations:
(i) Re-order level
= Maximum usage × Maximum lead time
= 4,500 units × 21 days = 94,500 units
(ii) Maximum stock level
= Re-order level + Re-order Quantity – (Min. Usage × Min. lead time)
= 94,500 units + 10,000 units – (1,500 units × 14 days)
= 1,04,500 units – 21,000 units = 83,500 units
(iii) Minimum stock level
= Re-order level – (Avg. consumption × Avg. lead time)
= 94,500 units – (3,000 units × 17.5 days)
= 94,500 units – 52,500 units
= 42,000 units
(iv) Store Ledger for the month of January 2020:
Date Receipts Issue Balance
GRN/ Units Rate Amt. MRN/ Units Rate Amt. Units Rate Amt.
MRN ` (` ‘000) MR ` (` ‘000) ` (` ‘000)
01-01-20 - - - - - - - - 3,500 9,810 34,335
05-01-20 008 10,000 9,930 99,300 003 500 9,930 4,965 13,000 9,898 1,28,670
06-01-20 - - - - 011 3,000 9,898 29,694 10,000 9,898 98,980
10-01-20 - - - - 012 4,500 9,898 44,541 5,500 9,898 54,439
12-01-20 009 10,000 9,780 97,800 004 400 9,780 3,912 15,100 9,823 1,48,327
15-01-20 - - - - 013 2,200 9,823 21,611 12,900 9,823 1,26,716
24-01-20 - - - - 014 1,500 9,823 14,734 11,400 9,823 1,11,982
25-01-20 010 10,000 9,750 97,500 - - - - 21,400 9,789 2,09,482
28-01-20 - - - - 015 4,000 9,789 39,156 17,400 9,789 1,70,326
31-01-20 - - - - 016 3,200 9,789 31,325 14,200 9,789 1,39,001
Note: Decimal figures may be rounded-off to the nearest rupee value wherever required)
Value of stock as on 31-01-2020 (` 000) = ` 1,39,001
(v) Value of components used during the month of January 2020:
Sum of material requisitions 011 to 016 (‘000)
= ` 29,694 + ` 44,541 + ` 21,611 + ` 14,734 + ` 39,156 + ` 31,325 = ` 1,81,061
` 1,81,061 ` 1,81,061
= ` 1,3,001 + 34,335 /2 = ` 86,668 = 2.09
Q-2 HBL Limited produces product ‘M’ which has a quarterly demand of 20,000 units. Each product requires
3 kg. and 4 kg. of material X and Y respectively. Material X is supplied by a local supplier and can be
procured at factory stores at any time, hence, no need to keep inventory for material X. The material Y
is not locally available, it requires to be purchased from other states in a specially designed truck
container with a capacity of 10 tons.
The cost and other information related with the materials are as follows:
Particulars Material –X Material-Y
Purchase price per kg. (excluding GST) `140 `640
Rate of GST 18% 18%
Freight per trip (fixed, irrespective of quantity) - ` 28,000
Loss of materials in transit* - 2%
Loss in process* 4% 5%
*On purchased quantity
Other information:
- The company has to pay 15% p.a. to bank for cash credit facility.
- Input credit is available on GST paid on materials.
Required:
(i) CALCULATE cost per kg. of material X and Y
(ii) CALCULATE the Economic Order quantity for both the materials.
Ans. Working Notes:(a) Annual purchase quantity for material X and Y:
Annual demand for product M- 20,000 units × 4 = 80,000 units
Particulars Mat-X Mat-Y
Quantity required for per unit of product M 3 kg. 4 kg.
Net quantity for materials required 2,40,000 kg. 3,20,000 kg.
Add: Loss in transit - 6,881 kg.
Add: Loss in process 10,000 kg. 17,204 kg
Purchase quantity 2,50,000 kg. 3,44,085 kg
Note - Input credit on GST paid is available; hence, it will not be included in cost of material.
(i) Calculation of cost per kg. of material X and Y:
Particulars Mat-X Mat-Y
Purchase quantity 2,50,000 kg. 3,44,085 kg.
Rate per kg. `140 `640
Purchase price `3,50,00,000 `22,02,14,400
Add: Freight 0 ` 9,80,000*
Total cost `3,50,00,000 `22,11,94,400
Net Quantity 2,40,000 kg. 3,20,000 kg
Cost per kg. ` 145.83 ` 691.23
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -13-
3,44,085kg
*No. of trucks = = 34.40 trucks or 35 trucks
10 ton × 1,000
Therefore, total freight = 35 trucks × ` 28,000 = ` 9,80,000
(ii) Calculation of Economic Order Quantity (EOQ) for Mat.-X and Y:
18,200 kg.
= 364 days + 20 kg. 8 days = 560 kg.
(iv) Minimum consumption per day of raw material ‘Dee’:
Average Consumption per day = 50 Kg.
Hence, Maximum Consumption per day = 50 kg. + 20 kg. = 70 kg.
So Minimum consumption per day will be
Min.consumption Max.consumption
Average Consumption =
2
Min.consumption + 70 kg.
Or, 50 kg. =
2
Or, Min. consumption = 100 kg – 70 kg. = 30 kg.
(a) Re-order Quantity :
EOQ – 200 kg. = 1,200 kg. – 200 kg. = 1,000 kg.
(b) Maximum Stock level:
= Re-order level + Re-order Quantity – (Min. consumption per day × Min. lead time)
= 560 kg. + 1,000 kg. – (30 kg. × 4 days)
= 1,560 kg. – 120 kg. = 1,440 kg.
(c) Minimum Stock level:
= Re-order level – (Average consumption per day × Average lead time)
= 560 kg. – (50 kg. × 6 days) = 260 kg.
(d) Impact on the profitability of the company by not ordering the EOQ.
When purchasing the ROQ When purchasing the EOQ
I Order quantity 1,000 kg. 1,200 kg.
17,200 kg. 17,200 kg.
II No. of orders a year = 17.2 or 18 orders = 14.33 or 15orders
1,000 kg. 1,200 kg.
III Ordering Cost 18 orders × ` 720 = `12,960 15 orders × ` 720 = `10,800
1,000 kg. 1,200 kg.
IV Average Inventory = 500kg. = 600kg.
2 2
V Carrying Cost 500 kg. × ` 17.2 = ` 8,600 600 kg. × ` 17.2 = ` 10,320
VI Total Cost ` 21,560 ` 21,120
Extra Cost incurred due to not ordering EOQ = ` 21,560 - ` 21,120 = `440
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -15-
Inventory Control
Q-5 Rounak Ltd. is the manufacturer of monitors for PCs. A monitor requires 4 units of Part-M. The following
are the details of its operation during 20X8:
Average monthly market demand 2,000 Monitors
Ordering cost ` 1,000 per order
Inventory carrying cost 20% per annum
Cost of Part ` 350 per part
Normal usage 425 parts per week
Minimum usage 140 parts per week
Maximum usage 710 parts per week
Lead time to supply 3-5 weeks
COMPUTE from the above:
(i) Economic Order Quantity (EOQ). If the supplier is willing to supply quarterly 30,000 units of Part-
M at a discount of 5%, is it worth accepting?
(ii) Reorder level
(iii) Maximum level of stock
(iv) Minimum level of stock.
Ans.
(1) A = Annual usage of parts = Monthly demand for monitors × 4 parts × 12 months
= 2,000monitors × 4 parts × 12 months = 96,000 units
O = Ordering cost per order = ` 1,000/- per order
C1 = Cost per part =` 350/-
96,000 units 1
= (96,000 units × ` 332.50) + × `1, 000 + (30,000 units × 20% × ` 332.50)
30,000 units 2
= `3,19,20,000 + `3,200* + `9,97,500= `3,29,20,700
Total cost (when order size is 1,656 units):
96,000 units 1
= (96,000 units × `350) + × `1, 000 + (1,656 units × 20% × `350)
1,656 units 2
= `3,36,00,000 + `57,970* + `57,960 = `3,37,15,930
Since, the total cost under the supply of 30,000 units with 5% discount is lower than that when order
size is 1,656 units, therefore the offer should be accepted.
Note: While accepting this offer consideration of capital blocked on order size of 30,000 units has been
ignored.
*Order size can also be taken in absolute figure.
(2) Reorder level
= Maximum consumption × Maximum re-order period
= 710 units × 5 weeks = 3,550 units
(3) Maximum level of stock
= Re-order level + Reorder quantity – (Min. usage × Min. reorder period)
= 3,550 units + 1,656 units – (140 units × 3 weeks) = 4,786 units.
(4) Minimum level of stock
= Re-order level – Normal usage × Average reorder period
= 3,550 units – (425 units × 4 weeks) = 1,850 units.
Q-6 Aditya Brothers supplies surgical gloves to nursing homes and polyclinics in the city. These surgical
gloves are sold in pack of 10 pairs at price of ` 250 per pack.
For the month of April 2018, it has been anticipated that a demand for 60,000 packs of surgical gloves
will arise. Aditya Brothers purchases these gloves from the manufacturer at ` 228 per pack within a 4 to
6 days lead time. The ordering and related cost is ` 240 per order. The storage cost is 10% p.a. of average
inventory investment.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -17-
Required:
(i) CALCULATE the Economic Order Quantity (EOQ)
(ii) CALCULATE the number of orders needed every year
(iii) CALCULATE the total cost of ordering and storage of the surgical gloves.
(iv) DETERMINE when should the next order to be placed. (Assuming that the company does maintain
a safety stock and that the present inventory level is 10,033 packs with a year of 360 working days).
Ans.
(i) Calculation of Economic Order Quantity:
Ans. Working:
Calculation of Annual demand of raw material
= 4,000 Litres (per quarter) x 4 (No. of Quarter in a year) x 2 kg. (raw material required for each Litre of
paint)
= 32,000 kg.
Calculation of Carrying cost
Storage rate = 2%
Interest Rate = 6%
Total = 8% per annum
Carrying cost per unit per annum = 8% of ` 50 = ` 4 per unit per annum
2× 32,000kg × ` 40
= = 800 Kg
`4
(ii) Total Annual Inventory Cost
Purchasing cost of 32,000 kg @ ` 50 per kg = ` 16,00,000
32,000kg
Ordering Cost × ` 40 = ` 1,600
800kg
15 days
Carrying Cost of Inventory × 800 Kg × ` 40 = ` 1,600
30 days
` 16,03,200
Q-8 The following are the details of receipt and issue of material ‘CXE’ in a manufacturing Co. during the
month of April 2019:
Date Particulars Quantity (kg) Rate per kg
April 4 Purchase 3,000 ` 16
April8 Issue 1,000
April15 Purchase 1,500 ` 18
April 20 Issue 1,200
April 25 Return to supplier out of purchase made on April 15 300
April 26 Issue 1,000
April 28 Purchase 500 ` 17
Opening stock as on 01-04-2019 is 1,000 kg @ ` 15 per kg.
On 30th April, 2019 it was found that 50 kg of material ‘CXE’ was fraudulently misappropriated by the
store assistant and never recovered by the Company.
Required:
(i) Prepare a store ledger account under each of the following method of pricing the issue:
(a) Weighted Average Method (b) LIFO
(ii) What would be the value of material consumed and value of closing stock as on 30-04-2019 as per
these two methods?
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -19-
Ans.
(i) (a) Stores Ledger Account for the month of April, 2019 (Weighted Average Method)
Receipt Issue Balance
Date Qty Units Rate Amount Qty Units Rate Amount Qty Units Rate Amount
(` ) (` ) (` ) (` ) (` ) (` )
1-4-19 _ _ _ _ _ _ 1,000 15.00 15,000
4-4-19 3,000 16.00 48,000 _ _ _ 4,000 15.75 63,000
8-4-19 _ _ _ 1,000 15.75 15,750 3,000 15.75 47,250
15-4-19 1,500 18.00 27,000 _ _ _ 4,500 16.50 74,250
20-4-19 _ _ _ 1,200 16.50 19,800 3,300 16.50 54,450
25-4-19 _ _ _ 300 18.00 5,400 3,000 16.35 49,050
26-4-19 _ _ _ 1,000 16.35 16,350 2,000 16.35 32,700
28-4-19 500 17.00 8,500 _ _ _ 2,500 16.48 41,200
30-4-19 _ _ _ 50 16.48 824 2,450 16.48 40,376
(b) Stores Ledger Account for the month of April, 2019 (LIFO)
Date Qty Units Rate Amount Qty Units Rate Amount Qty Units Rate Amount
(` ) (` ) (` ) (` ) (` ) (` )
1-4-19 _ _ _ _ _ _ 1,000 15 15,000
4-4-19 3,000 16 48,000 _ _ _ 1,000 15 15000
3,000 16 48,000
8-4-19 _ _ _ 1,000 16 16,000 1,000 15 15,000
2,000 16 32,000
15-4-19 1,500 18 27,000 _ _ _ 1,000 15 15,000
2,000 16 32,000
1,500 18 27,000
20-4-19 _ _ _ 1,200 18 21,600 1,000 15 15,000
2,000 16 32,000
300 18 5,400
25-4-19 _ _ _ 300 18 5,400 1,000 15 15,000
2,000 16 32,000
26-4-19 _ _ _ 1,000 16 16,000 1,000 15 15,000
1,000 16 16,000
28-4-19 500 17 8,500 _ _ _ 1,000 15 15,000
1,000 16 16,000
500 17 8,500
30-4-19 _ _ _ 50 17 850 1,000 15 15,000
1,000 16 16,000
450 17 7,650
(ii) Value of Material Consumed and Closing Stock
Weighted Average LIFO
method (`) method(`)
Opening stock as on 01-04-2019 15,000 15,000
Add: Purchases 83,500 83,500
98,500 98,500
Less: Return to supplier 5,400 5,400
Less: Abnormal loss 824 850
Less: Closing Stock as on 30-04-2019 40,376 38,650
Value of Material Consumed 51,900 53,600
Q-9 M/s. X Private Limited is manufacturing a special product which requires a component "SKY BLUE". The
following particulars are available for the year ended 31st March, 2018:
Annual demand of "SKY BLUE" 12000 Units
Cost of placing an order ` 1,800
Cost per unit of "SKY BLUE” ` 640
Carrying cost per annum 18.75%
The company has been offered a quantity discount of 5 on the purchases of "SKY BLUE" provided the
order size is 3000 components at a time.
You are required to:
(i) Compute the Economic Order Quantity.
(ii) Advise whether the quantity discount offer can be accepted.
Ans. (i) Calculation of Economic Order Quantity
Q
Carrying Cost ( × C × i - 600 units x ` 640 x ½ x 18.75/100) 36,000
2
Total Cost 77,52,000
Q-10 Explain ‘Just In Time’ (JIT) approach of inventory management.
Ans. Just in Time (JIT) Inventory Management
JIT is a system of inventory management with an approach to have a zero inventories in stores. According
to this approach material should only be purchased when it is actually required for production.
JIT is based on two principles
(i) Produce goods only when it is required and
(ii) the products should be delivered to customers at the time only when they want.
It is also known as ‘Demand pull’ or ‘Pull through’ system of production. In this system, production
process actually starts after the order for the products is received. Based on the demand, production
process starts and the requirement for raw materials is sent to the purchase department for purchase.
This can be understood with the help of the following diagram:
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -21-
2 A O
(i) Re-order Quantity or EOQ =
c i
A = Annual Consumption = 13,000 kg
2 ×13,000 ×1,500
EOQ = 9.75
39000000
= 2000 kg.
9.75
(ii) Re-order level = Max. re-order period × Max, Consumption
= 7 weeks × 300 kg = 2,100 kg
(iii) Maximum level = Re-order level + Re-order Qty – (Min re-order Period × Min. Consumption)
= 2100 kg + 2000 kg – (5 × 200) kg = 3100 kg.
(iv) Minimum level = Re-order level – (Avg. re-order period × Avg. Consumption)
= 2,100 kg – (6 × 250) kg = 600 kg.
1
(v) Avg. stock level = (Max. level +Min.level)
2
1
= (3100 + 600) = 1850 kg OR
2
1
= Minimum level + ROQ
2
1
= 600 kg. + × 2000 kg. = 1600 kg.
2
Q-13 XYZ Ltd. has obtained an order to supply 48000 bearings per year from a concern. On a steady basis, it is
estimated that it costs ` 0.20 as inventory holding cost per bearing per month and the set-up cost per
run of bearing manufacture is ` 384.
You are required to:
(i) compute the optimum run size and number of runs for bearing manufacture.
(ii) compute the interval between two consecutive runs.
(iii) find out the extra costs to be incurred, if company adopts a policy to manufacture 8000 bearings
per run as compared to optimum run Size.
(iv) give your opinion regarding run size of bearing manufacture.
Assume 365 days in a year.
Ans.
(i) Optimum batch size or Economic Batch Quantity (EBQ):
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -23-
Total cost = Set-up cost + Inventory holding cost= (12.245×384)+ 4704= ` 9,406 (approx.)
OR
Total cost = Set-up cost + Inventory holding cost= (13×384)+ 4704= ` 9,696 (approx.)
(iv) To save cost the company should run at optimum batch size i.e. 3,920 Units. It saves ` 2,498 or
2208. Run size should match with the Economic production run of bearing manufacture. When
managers of a manufacturing operation make decisions about the number of units to produce
for each production run, they must consider the costs related to setting up the production
process and the costs of holding inventory
Alternative presentation to part 3(a) (iii)
Statement showing Total Cost at Production Run size of 3,600 and 8,000 bearings
A. Annual requirement 48,000 48,000
B. Run Size 3,920 8,000
C. No. of runs (A/B) 12.245 6
D. Set up cost per run ` 384 ` 384
E. Total set up cost (CxD) ` 4,702 ` 2,304
F. Average inventory (B/2) 1,960 4,000
G. Carrying cost per unit p.a. 2.40 2.40
H. Total Carrying cost (FxG) 4,704 9,600
I. Total cost (E+H) 9,406 11,904
Extra cost incurred, if run size is of 8,000= `11,904-9,406= ` 2,498
Q-14 Explain obsolescence and circumstances under which materials become obsolete. State the steps to
be taken for its treatment.
Ans. Obsolescence: Obsolescence is defined as “the loss in the intrinsic value of an asset due to its
supersession”.
Materials may become obsolete under any of the following circumstances:
(i) where it is a spare part, or a component of a machinery used in manufacture and that machinery
becomes obsolete;
(ii) where it is used in the manufacture of a product which has become obsolete;
(iii) where the material itself is replaced by another material due to either improved quality or fall in
price.
Treatment:In all three cases, the value of the obsolete material held in stock is a total loss and immediate
steps should be taken to dispose it off at the best available price. The loss arising out of obsolete
materials on abnormal loss does not form part of the cost of manufacture.
Q-15 Arnav Motors Ltd. manufactures pistons used in car engines. As per the study conducted by the Auto
Parts Manufacturers Association, there will be a demand of 80 million pistons in the c oming year.
Arnav Motors Ltd. is expected to have a market share of 1.15% of the total market demand of the
pistons in the coming year. It is estimated that it costs Rs.1.50 as inventory holding cost per piston per
month and that the set-up cost per run of piston manufacture is Rs. 3,500.
(i) DETERMINE the optimum run size for piston manufacturing?
(ii) Assuming that the company has a policy of manufacturing 40,000 pistons per run, Calculate how
much extra costs the company would be incurring as compared to the optimum run suggested in
(i) above?
Ans.
2 D S
(i) Optimum run size or Economic Batch Quantity (EBQ) =
C
Where, D = Annual demand i.e. 1.15% of 8,00,00,000 = 9,20,000 units
S = Set-up cost per run = Rs. 3,500
C = Inventory holding cost per unit per annum
= Rs. 1.5 × 12 months = Rs. 18
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -25-
EOQ =
(d) Impact on the profitability of the company by not ordering the EOQ.
When purchasing the ROQ When purchasing the EOQ
I Order quantity 1,497 kg. 1,697 kg.
II No. of orders a year 34,400kg./1,497kg. 34,400 kg./1,697kg.
= 22.9or 23orders = 20.27or 21orders
III Ordering Cost 23 orders × Rs. 720 = Rs.16,560 21 orders × Rs. 720 =
Rs.15,120
IV Average Inventory 1,497kg./2 = 748.5kg. 1,697kg./2 = 848.5kg.
V Carrying Cost 748.5 kg. × Rs. 17.2 = 848.5 kg. × Rs. 17.2 =
Rs.12,874.2 Rs.14,594.2
VI Total Cost Rs. 29,434.20 Rs. 29,714.20
Cost saved by not ordering EOQ = Rs. 29,714.20 - Rs. 29,434.20 = Rs. 280.
Q-17 A store keeper has prepared the below list of items kept in the store of the factory.
Item Units Unit cost (`)
A 12,000 30.00
B 18,000 3.00
C 6,000 35.00
D 750 220.00
E 3,800 75.00
F 400 105.00
G 600 300.00
H 300 350.00
I 3,000 250.00
J 20,000 7.50
K 11,500 27.50
L 2,100 75.00
The store keeper requires your help to classify the items for prioritization. You are required to APPLY
ABC analysis to classify the store items as follows:
Store items which constitutes approx 70%, 20% and 10% of total value as A, B and C respectively.
Ans. Statement of Total Cost and Ranking
Item Units % of Total Unit cost (`) Total cost (`) % of Total cost Ranking
units
A 12,000 15.30% 30.00 3,60,000 12.97% 2
B 18,000 22.94% 3.00 54,000 1.95% 11
C 6,000 7.65% 35.00 2,10,000 7.57% 5
D 750 0.96% 220.00 1,65,000 5.95% 7
E 3,800 4.84% 75.00 2,85,000 10.27% 4
F 400 0.51% 105.00 42,000 1.51% 12
G 600 0.76% 300.00 1,80,000 6.49% 6
H 300 0.38% 350.00 1,05,000 3.78% 10
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -27-
Selling price of the products ‘P1’ and ‘P2’ at split off point is ` 110 per kg and ` 325 per kg respectively.
Selling price of new product ‘YP1’ is ` 150 per kg.
You are required to:
(i) Prepare a statement showing apportionment of joint costs, in the ratio of value of sales, net of
selling expenses.
(ii) Prepare a Statement showing profitability at split off point.
(iii) Prepare a Statement of profitability of ‘YP1’.
(iv) Determine that would you recommend further processing of P1?
Ans. Working Notes:
Input output ratio of material processed in Department X = 100:90
Particulars Quantity (Kg)
Material input 9,00,000
Less: Loss of material in process @ 10% of 9,00,000 kgs (90,000)
Output 8,10,000
Output of department X is product ‘P1’ and ‘P2’ in the ratio of 60 : 40.
60 8,10,000
Output ‘P1’ = = 4,86,000 kgs.
100
40 8,10,000
Output ‘P2’ = = 3,24,000 kgs.
100
Statement showing ratio of net sales
Product P1 P2 Total
Quantity (kgs) 4,86,000 3,24,000 8,10,000
Selling price per kg (`) 110.00 325.00
Sales Value (` in lakhs) 534.60 1,053.00 1587.60
Less: Selling Expenses (` in l akhs) (28.38) (25.00) (53.38)
Net Sales (` in lakhs) 506.22 1,028.00 1,534.22
Ratio 33% 67% 100.00
Computation of Joint Costs
Particulars Amount (` Lakhs)
Raw Material input 9,00,000 kgs @ ` 95 per kg 855.00
Direct Materials 95.00
Direct Wages 80.00
Variable Overheads 100.00
Fixed Overheads 75.00
Total 1,205.00
(i) Statement showing apportionment of joint costs in the ratio of net sales
Particulars Amount (` in lakhs)
Joint cost of P1 – 33% of ` 1,205 lakhs 397.65
Joint cost of P2 – 67% of ` 1,205 lakhs 807.35
Total 1,205.00
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -29-
Economic batch quantity can be determined with the help of a table, graph or mathematical formula.
The mathematical formula usually used for its determination is as follows:
2DC
EBQ =
C
Where,
D = Annual demand for the product
S = Setting up cost per batch
C = Carrying cost per unit of production per annum
Q-20 The annual demand for an item of raw material is 4,000 units and the purchase price is expected to be
Rs. 90 per unit. The incremental cost of processing an order is Rs. 135 and the annual cost of storage is
estimated to be Rs. 12 per unit. COMPUTE the optimal order quantity and total relevant cost of this
order quantity?
Suppose that Rs. 135 as estimated to be the incremental cost of processing an order is incorrect and
should have been Rs. 80. All other estimates are correct. ESTIMATE the difference in cost on account of
this error?
Assume at the commencement of the period that a supplier offers 4,000 units at a price of Rs. 86. The
materials will be delivered immediately and placed in the stores. Assume that the incremental cost of
placing the order is zero and original estimate of Rs. 135 for placing an order for the economic batch is
correct. ANALYSE, should the order be accepted?
Ans. (i) Optimal order quantity i.e. E.O.Q.
2 4,000 135
= 90,000 = 300 units
12
Relevant Cost of this order quantity Rs.
4,000
Ordering cost = 13.33 say 14 orders at Rs. 135 1,890
300
1
Carrying Cost = × 300 × 12 1,800
2
Relevant cost 3,690
2 4,000 80
(ii) Revised EOQ = = 231 units
12
4,000
Ordering cost = = 17.32 say 18 orders at Rs. 80 1,440
231
1
Carrying cost = × 231 × 12 1,386
2
2,826
Different in cost on account of this error = 3,690 – 2,826 = Rs. 864
(iii) In case of discount in purchase price, the total cost of Purchase cost, ordering cost and carrying cost
should be compared.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -31-
Original offer at Rs. 90 per unit Supplier offered at Rs. 86 per unit
Rs. Rs.
Purchase Cost 3,60,000 Purchase cost 4,000 × 86 3,44,000
Ordering cost 1,890 Ordering cost Nil
1
Carrying cost 1,800 Carrying cost × 4,000 × 12 24,000
2
Total cost 3,63,690 3,68,000
This special offer at Rs. 86 per unit should not be accepted as its total cost is higher by Rs. 4,310 (3,68,000
– 3,63,690).as compared to original offer.
Q-21 A Ltd. manufactures a product X which requires two raw materials A and B in a ratio of 1:4. The sales
department has estimated a demand of 5,00,000 units for the product for the year. To produce one unit
of finished product, 4 units of material A is required.
Stock position at the beginning of the year is as below:
Product- X 12,000 units
Material A 24,000 units
Material B 52,000 units
To place an order the company has to spend Rs.15,000. The company is financing its working
capital using a bank cash credit @13% p.a.
Product X is sold at Rs.1,040 per unit. Material A and B are purchased at Rs.150 and Rs.200
respectively.
Required:
COMPUTE economic order quantity (EOQ):
(i) If purchase order for the both materials is placed separately.
(ii) If purchase order for the both materials is not placed separately.
Ans. Workings:
Annual production of Product X = Annual demand – Opening stock
= 5,00,000 – 12,000 = 4,88,000 units
Annual requirement for raw materials = Annual production × Material per unit – Opening stock of
material
Material A = 4,88,000 × 4 units – 24,000 units = 19,28,000 units
Material B = 4,88,000 × 16 units – 52,000 units = 77,56,000 units
(i) Computation of EOQ when purchase order for the both materials is placed separately
(ii) Computation of EOQ when purchase order for the both materials is not placed separately
1,93,68,000 Rs.15,000
= = 1,08,452units
Rs.24.7
1,08,452 19,28,000
Material A = =21,592units
96,84,000
1,08,452 × 77,56,000
Material A = = 86,860units
96,84,000
4. It can be used for the purpose of 4. It is useful in arriving historical cost only.
quotation.
5. It helps in keeping a quantitative 5. It shows the material actually drawn from
control on materials drawn through stores.
Stores Requisition.
Q-23 A company manufactures a product from a raw material, which is purchased at Rs. 54 per kg. The
company incurs a handling cost of Rs.1,500 plus freight of Rs.4,000 per order. The incremental carrying
cost of inventory of raw material is Rs.1.50 per kg per month. In addition, the cost of working capital
finance on the investment in inventory of raw material is Rs.8 per kg per annum. The annual production
of the product is 96,000 units and 4 units are obtained from one kg of raw material.
Required:
(i) CALCULATE the economic order quantity of raw materials.
(ii) ADVISE, how frequently orders should be placed for procurement.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -33-
(iii) If the company proposes to rationalize placement of orders on quarterly basis, DETERMINE what
percentage of discount in the price of raw materials should be negotiated?
Ans.
2AO
(i) EOQ =
C
(ii) Number of Optimum runs = 48,000 ÷ 5,060 = 9.49 or 10 runsInterval between 2 runs (in days) = 365 days
÷ 10 = 36.5 days
(iii) Minimum Inventory Cost = Average Inventory × Inventory Carrying Cost per unit per annum
Average Inventory = 5,060 units ÷ 2 = 2,530 units
Carrying Cost per unit per annum = ` 1 × 12 months = ` 12
Minimum Inventory Holding Costs = 2,530 units × ` 12 = ` 30,360.
Q-25 Arnav Motors Ltd. manufactures pistons used in car engines. As per the study conducted by the Auto
Parts Manufacturers Association, there will be a demand of 80 million pistons in the coming year. Arnav
Motors Ltd. is expected to have a market share of 1.15% of the total market demand of the pistons in
the coming year. It is estimated that it costs Rs.1.50 as inventory holding cost per piston per month and
that the set-up cost per run of piston manufacture is Rs. 3,500.
(i) DETERMINE the optimum run size for piston manufacturing?
(ii) Assuming that the company has a policy of manufacturing 40,000 pistons per run, CALCULATE the
extra costs company would be incurring as compared to the optimum run suggested in (i) above?
(iii) IDENTIFY variability of cost with respect to unit and batch level from the following cost:
(a) Inventory carrying cost; (b) Designing cost for a job; (c) Machine set-up cost to run
production and (d) Depreciation of factory building.
Ans.
2D S
(i) Optimum run size or Economic Batch Quantity (EBQ) =
C
Where, D = Annual demand i.e. 1.15% of 8,00,00,000 = 9,20,000 units
S = Set-up cost per run = ` 3,500
C = Inventory holding cost per unit per annum
= ` 1.5 × 12 months = ` 18
Q-26 A Ltd. manufactures pistons used in car engines. As per the study conducted by the Auto Parts
Manufacturers Association, there will be a demand of 80 million pistons in the coming year. A Ltd. is
expected to have a market share of 1.15% of the total market demand of the pistons in the coming year.
It is estimated that it costs Rs.1.50 as inventory holding cost per piston per month and that the set-up
cost per run of piston manufacture is Rs. 3,500.
(i) COMPUTE the optimum run size for piston manufacturing?
(ii) Assuming that the company has a policy of manufacturing 40,000 pistons per run, CALCULATE how
much extra costs the company would be incurring as compared to the optimum run suggested in
(i) above?
Ans.
2×D × S
(i) Optimum run size or Economic Batch Quantity (EBQ) =
C
Where, D = Annual demand i.e. 1.15% of 8,00,00,000 = 9,20,000 units
S = Set-up cost per run = Rs. 3,500
C = Inventory holding cost per unit per annum
= Rs.1.5 × 12 months = Rs. 18
2 × 9,20,000units × Rs.3,500
EBQ = = 18,915 units
Rs.18
(ii) Calculation of Total Cost of set-up and inventory holding
Batch size No. of setups Set-up Cost Inventory Total Cost
(Rs.) holding cost (Rs.)
(Rs.)
A 40,000 units 23 80,0500 3,60,000 4,40,500
9, 20, 000 40, 000 × Rs.18
(23 × Rs. 3,500)
40, 000 2
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -37-
18,200kg
= + 20kg × 8 days = 560kg.
364 days
(4) Minimum consumption per day of raw material ‘Dee’:
Average Consumption per day = 50 Kg.
Hence, Maximum Consumption per day = 50 kg. + 20 kg. = 70 kg
So, Minimum consumption per day will be
Min.consumption + Max.consumption
Average Consumption =
2
Min.consumption + 70kg.
Or, 50 kg =
2
Or, Min. consumption = 100 kg – 70 kg. = 30 kg.
(i) Re-order Quantity:
EOQ – 200 kg. = 1,200 kg. – 200 kg. = 1,000 kg.
(ii) Maximum Stock level:= Re-order level + Re-order Quantity – (Min. consumption per day × Min.
lead time)= 560 kg. + 1,000 kg. – (30 kg. × 4 days) = 1,560 kg. – 120 kg. = 1,440 kg
(iii) Minimum Stock level:
= Re-order level – (Average consumption per day × Average lead time)
= 560 kg. – (50 kg. × 6 days) = 260 kg
(iv) Impact on the profitability of the company by not ordering the EOQ
When purchasing the ROQ When purchasing the EOQ
I Order quantity 1,000 kg. 1,200 kg
17,200 kg 17,200 kg
II No. of orders a year = 17.2 or 18 orders = 14.33 or 15 orders
1,000 kg 1,200 kg
III Ordering Cost 18 orders × Rs. 720 15 orders × Rs. 720
= Rs.12,960 = Rs.10,800
1, 000 kg 1,200 kg
IV Average Inventory = 500 kg = 600 kg
2 2
V Carrying Cost 500 kg. × Rs. 17.2 600 kg. × Rs. 17.2
= Rs. 8,600 = Rs. 10,320
VI Total Cost Rs. 21,560 Rs. 21,120
Extra Cost incurred due to not ordering EOQ = Rs. 21,560 - Rs. 21,120 = Rs.440.
Q-29 A company deals in trading of a toy car ‘Terminato’. The annual demand for the toy car is 9,680 units.
The company incurs fixed order placement and transportation cost of ` 200 each time an order is
placed. Each toy costs ` 400 and the trader has a carrying cost of 20 percent p.a.
The company has been offered a quantity discount of 5% on the purchase of ‘Terminato’ provided the
order size is 4,840 units at a time.
Required:
(i) COMPUTE the economic order quantity
(ii) STATE whether the quantity discount offer can be accepted.
Ans.(i) Calculation of Economic Order Quantity
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -39-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -41-
2 D S
Ans. (i) Optimum run size or Economic Batch Quantity (EBQ) =
C
Where, D = Annual demand i.e. 2.15% of 8,00,00,000 = 17,20,000 units
units
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -43-
4. Total cost of procurement and storage when the order size is equal to EOQ or 2,000 kg.
No. of orders (40,000 kg. 2,000 kg.) = 20 times
Ordering cost (20 orders x `1,000) = ` 20,000
Carrying cost (`) (1/2 x 2,000 kg. x ` 20) = ` 20,000
Total cost ` 40,000
(i) Re-order point = Safety stock + Lead time consumption
40,000 kg.
= 1,000 kg. + x 36 days
360 days
= 1,000 kg. + 4,000 kg. = 5,000 kg.
(ii) Statement showing the total cost of procurement and storage of raw materials
(after considering the discount)
Order No. of Total cost of Average Total cost of Discount Total cost
size orders procurement stock storage of raw
materials
Kg. (`) Kg. (`) (`) (`)
(1) (2) (3)=(2) x ` 1,000 (4)=1/2x(1) (5)=(4)x ` 20 (6) (7)=[(3)+(5)x(6)]
40,000 1 1,000 20,000 4,00,000 40,000 3,61,000
20,000 2 2,000 10,000 2,00,000 32,000 1,70,000
10,000 4 4,000 5,000 1,00,000 20,000 84,000
8,000 5 5,000 4,000 80,000 4,000 81,000
(iii) Number of orders which the company should place to minimize the costs after taking EOQ also into
consideration is 20 orders each of size 2,000 kg. The total cost of procurement and storage in this case
comes to ` 40,000, which is minimum. (Refer to working notes 3 and 4)
Q-34 MM Ltd. has provided the following information about the items in its inventory.
Item Code Number Units Unit Cost (`)
101 25 50
102 300 01
103 50 80
104 75 08
105 225 02
106 75 12
MM Ltd. has adopted the policy of classifying the items constituting 15% or above of Total Inventory
Cost as ‘A’ category, items constituting 6% or less of Total Inventory Cost as ‘C’ category and the remaining
items as ‘B’ category.
You are required to:
(i) Rank the items on the basis of % of Total Inventory Cost.
(ii) Classify the items into A, B and C categories as per ABC Analysis of Inventory Control adopted by
MM Ltd.
2DS
Economic Batch Quantity (EBQ) =
C
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -45-
2 10,00,000 `225
EBQ =
18
= 5,000 units of Stents
(ii) Minimum inventory holding cost
Minimum Inventory Cost = Average Inventory × Inventory Carrying Cost per unit per annum
= (5,000 ÷ 2) × ` 18
= ` 45,000
(iii) Calculation of the extra cost due to manufacturing policy
When run size is 4,000 When run size is 5,000
units units i.e. at EBQ
10,00,000 10,00,000
Total set up cost x ` 225 x ` 225
4,000 4,000
= ` 56,250 = ` 45,000
Total Carrying cost ½ × 4,000 × ` 18 ½ × 5,000 × ` 18
= ` 36,000 = ` 45,000
Total Cost ` 92,250 ` 90,000
Extra cost = ` 92,250 - ` 90,000 = ` 2,250
Q-36 An automobile company purchases 27,000 spare parts for its annual requirements. The cost per order is
` 240 and the annual carrying cost of average inventory is 12.5%. Each spare part costs ` 50.
At present, the order size is 3,000 spare parts.
(Assume that number of days in a year = 360 days)
Find out:
(i) How much the company’s cost would be saved by opting EOQ model?
(ii) The Re-order point under EOQ model if lead time is 12 days.
(iii) How frequently should orders for procurement be placed under EOQ model?
Ans. Working Notes:
Annual requirement (A) = 27,000 units
Cost per order (O) = ` 240
Inventory carrying cost (i) = 12.5%
Cost per unit of spare (c) = ` 50
Carrying cost per unit (i × c) = ` 50 × 12.5% = ` 6.25
2 A O
Economic Order Quantity (EOQ) =
i c
2 27,000 240
= 1440 units
6.25
(i) Calculation of saving by opting EOQ:
Existing Order policy EOQ Model
No. of orders 9 18.75 or 19
27,000 27,000
3,000 1,440
A. Ordering Cost (`) 2,160 4,500
27,000
(` 240 × 9) `240
1,440
B. Carrying cost (`) 9,375 4,500
27,000 units
Consumption per day = = 75 units
360 days
Re-order point/ Re-order level = 75 units × 12 days = 900 units
(iii) Frequency of Orders (in days):
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -47-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -49-
year
Inventory
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -51-
You are required to CALCULATE cost per unit of material purchased by Sky & Co.
Ans. Calculation of cost per unit:
Particulars Units (`)
Listed Price of Materials 5,000 2,50,000
Less: Trade discount @ 10% on invoice price (25,000)
2,25,000
Add: CGST @ 6% of ` 2,25,000 13,500
Add: SGST @ 6% of ` 2,25,000 13,500
2,52,000
Add: Toll Tax 5,000
Freight and Insurance 17,000
Commission and Brokerage Paid 10,000
Add: Cost of returnable containers:
Amount deposited ` 30,000
Less: Amount refunded ` 20,000 10,000
2,94,000
Add: Other Expenses @ 2% of Total Cost (` 2,94,000/98×2) 6,000
Total cost of material 3,00,000
Less: Shortage material due to normal reasons @ 20% 1,000 -
Total cost of material of good units 4,000 3,00,000
Cost per unit (` 3,00,000/4,000 units) 75
Note:
1. GST is payable on net price i.e., listed price less discount.
2. Cash discount is treated as interest and finance charges; hence it is ignored.
3. Demurrage is penalty imposed by the transporter for delay in uploading or off-loading of materials. It
is an abnormal cost and not included.
4. Shortage due to normal reasons should not be deducted from cost to ascertain total cost of good units.
Q-42 XYZ Ltd. uses two types of raw materials – ‘Material A’ and ‘Material B’ in the production process and
has provided the following data for the year ended on 31st March, 2021:
Particulars Material A Material B
(`) (`)
Opening stock as on 01.04.2020 30,000 32,000
Purchase during the year 90,000 51,000
Closing stock as on 31.03.2021 20,000 14,000
(i) You are required to calculate:
(a) The inventory turnover ratio of ‘Material A’ and ‘Material B’.
(b) The number of days for which the average inventory is held for both materials ‘A’ and ‘B’.
(ii) Based on above calculations, give your comments.
(Assume 360 days in a year.)
Ans.
(i) Calculation of Inventory Turnover ratios and number of days:
Material A (`) Material B (`)
Opening stock 30,000 32,000
Add: Purchases 90,000 51,000
1,20,000 83,000
Less: Closing stock 20,000 14,000
Materials consumed 1,00,000 69,000
Average inventory: (Opening Stock + Closing Stock) 2 25,000 23,000
(a) Inventory Turnover ratio: (Consumption Average inventory) 4 times 3 times
(b) Number of days for which the average inventory held
(Number of Days in a year/IT ratio) 90 days 120 days
(ii) Comments: Material A is moving faster than Material B. Or Material A has a less holding period.
Q-43 What is Bill of Material? Describe the uses of Bill of Material in following departments:
(i) Purchases Department
(ii) Production Department
(iii) Stores Department
(iv) Cost/Accounting Department
Ans. Bill of Material: It is a detailed list specifying the standard quantities and qualities of materials and
components required for producing a product or carrying out of any job.
Uses of Bill of Material in different department:
Purchase Production Stores Cost/ Accounting
Department Department Department Department
Materials are Production is planned It is used as a It is used to estimate
procured according to the nature, reference document cost and profit. Any purchase,
(purchased) on volume of the materials while issuing materials issue and usage are compared/
the basis of required to be used. to the requisitioning verified against this document.
specifications Accordingly, material department.
mentioned in it. requisition lists are
prepared.
Purchase Department Production Department Stores Department Cost/ Accounting Department
Materials are procured (purchased) on the basis of specifications mentioned in it.
Production is planned according to the nature, volume of the materials required to be used. Accordingly,
material requisition lists are prepared.
It is used as a reference document while issuing materials to the requisitioning department.
It is used to estimate cost and profit. Any purchase, issue and usage are compared/ verified against this
document.
Q-44 M/s SE Traders is a distributor of an electronic items. A periodic inventory of electronic items on hand
is taken when books are closed at the end of each quarter. The following information is available for
the quarter ended on 30th September, 2021:
Sales ` 2,19,30,000
Opening Stock 12,500 units @ ` 600 per unit
Administrative Expenses ` 5,62,500
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -53-
Notes:
1. GST is payable on net price i.e., listed price less discount.
2. Detention charges/ fines imposed for non-compliance of rule or law by any statutory authority. It is an
abnormal cost and not included with cost of purchase.
3. Shortage due to normal reasons should not be deducted from cost to ascertain total cost of good units.
---0---0---
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -55-
CHAPTER-3
EMPLOYEE COST AND DIRECT EXPENSES
Q-1 From the following information, CALCULATE employee turnover rate using – (i) Separation Method, (ii)
Replacement Method, (iii) New Recruitment Method, and (iv) Flux Method:
No. of workers as on 01.01.2019 = 3,600
No. of workers as on 31.12.2019 = 3,790
During the year, 40 workers left while 120 workers were discharged. 350 workers were recruited during
the year, of these 150 workers were recruited because of exits and the rest were recruited in accordance
with expansion plans.
Ans. Employee turnover rate using:
(i) Separation Method:
No. of workers left + No. of workers discharged
= ×100
Average number of workers
40 + 120 160
= 3,600 + 3,790 /2 ×100 = 3,895 ×100 = 4.33%
(ii) Replacement Method:
No. of workers replaced 150
= ×100 = = 4,06%
Average number of workers 3,695
(iii) New Recruitment Method:
No. of workers newly recruited
= ×100
Average number of wor kers
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -57-
Q-2 ADV Pvt. Ltd. manufactures a product which requires skill and precision in work to getquality products.
The company has been experiencing high labour cost due to slow speedof work. The management of
the company wants to reduce the labour cost but without compromising with the quality of work. It
wants to introduce a bonus scheme but is indifferent between the Halsey and Rowan scheme of bonus.
For the month of November 2019, the company budgeted for 24,960 hours of work. The workers are
paid ‘80 per hour.
Required:
(i) CALCULATE and suggest the bonus scheme where the time taken (in %) to time allowed to complete
the works is (a) 100% (b) 75% (c) 50% & (d) 25% of budgeted hours.
Ans. The Cost of labour under the bonus schemes are tabulated as below:
Time Time Wages (`) Bonus (`) Total Wages (`) Earning per hour(`)
* Bonus under Halsey Plan = 50% of (Time Allowed – Time Taken) × Rate per hour
Time taken
** Bonus under Rowan Plan = × Time saved×Rarte per hour
Time allowed
Rowan scheme of bonus keeps checks on speed of work as the rate of incentive increases only upto 50% of
time taken to time allowed but the rate decreases as the time taken to time allowed comes below 50%. It
provides incentives for efficient workers for saving in time but also puts check on careless speed. On
implementation of Rowan scheme, the management of ADV Pvt. Ltd. would resolve issue of the slow speed
work while maintaining the skill and precision required maintaining the quality of product.
Q-3 Zico Ltd. has its factory at two locations viz Nasik and Satara. Rowan plan is used at Nasik factory and
Halsey plan at Satara factory. Standard time and basic rate of wages are same for a job which is similar
and is carried out on similar machinery. Normal working hours is 8 hours per day in a 5 day week.
Job in Nasik factory is completed in 32 hours while at Satara factory it has taken 30 hours. Conversion
costs at Nasik and Satara are ` 5408 and ` 4950. Overheads account for ` 25 per hour.
Required:
(i) To find out the normal wage; and
(ii) To compare the respective conversion costs.
Ans.
Particulars Nasik Satara
Hours worked 32 hr. 30 hr.
Conversion Costs ` 5,408 ` 4,950
Less: Overheads ` 800 ` 750
(` 25×32 hr.) (` 25×30 hr.)
Labour Cost ` 4,608 ` 4,200
(i) Finding of Normal wage rate:
Let Wage rate be ‘R per hour, this is same for both the Nasik and Satara factory.
Normal wage rate can be found out taking total cost of either factory.
Nasik: Rowan Plan
Total Labour Cost = Wages for hours worked + Bonus as per Rowan plan
Time saved
` 4,608 = Hours worked × Rate per hour + ×Hours worked×Rate per hour)
Time allowed
40 - 32
Or, ` 4,608 = 32 hr. × R + × 32 ×R
40
Or, ` 4,608 = 32R + 6.4R
R = ` 120
Normal wage = 32 hrs × ` 120 = ` 3,840
OR
Satara: Halsey Plan
Total Labour Cost = Wages for hours worked + Bonus as per Halsey plan
` 4,200 = Hours worked × Rate per hour + (50%×Hours saved×Rate per hour)
` 4,200 = 30 hr. × R + 50% × (40 hr. – 30 hr.) × R
` 4,200 = 35 R
Or R = ` 120
Normal Wage = 30 hrs × ` 120 = ` 3,600
(ii) Comparison of conversion costs:
Particulars Nasik (`) Satara (`)
Normal Wages (32 x 120) 3,840
(30x120) 3,600
Bonus (6.4 x 120) 768
(5 x 120) 600
Overhead 800 750
5,408 4,950
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -59-
Q-4 A Company is undecided as to what kind of wage scheme should be introduced. The following particulars
have been compiled in respect of three workers. Which are under consideration of the management.
I II III
Actual hours worked 380 100 540
Hourly rate of wages (in `) 40 50 60
Productions in units:
- Product A 210 - 600
- Product B 360 - 1350
- Product C 460 250 -
Standard time allowed per unit of each product is:
A B C
Minutes 15 20 30
For the purpose of piece rate, each minute is valued at ` 1/-
You are required to CALCULATE the wages of each worker under:
(i) Guaranteed hourly rate basis
(ii) Piece work earning basis, but guaranteed at 75% of basic pay (Guaranteed hourly rate if his earnings
are less than 50% of basic pay.)
(iii) Premium bonus basis where the worker received bonus based on Rowan scheme.
Ans.
(i) Computation of wages of each worker under guaranteed hourly rate basis
Worker Actual hours Hourly wage rate Wages (`)
worked (Hours) (`)
I 380 40 15,200
II 100 50 5,000
III 540 60 32,400
(ii) Computation of Wages of each worker under piece work earning basis
Product Piece rate Worker-I Worker-II Worker-III
per unit (`) Units Wages (`) Units Wages (`) Units Wages
(` )
A 15 210 3,150 - - 600 9,000
B 20 360 7,200 - - 1,350 27,000
C 30 460 13,800 250 7,500 - -
Total 24,150 7,500 36,000
Since each worker’s earnings are more than 50% of basic pay. Therefore, worker -I, II and III will be paid the
wages as computed i.e. ` 24,150, ` 7,500 and ` 36,000 respectively.
Working Notes :
1. Piece rate per unit
Product Standard time per Piece rate each Piece rate per
unit in minute minute (`) unit (`)
A 15 1 15
B 20 1 20
C 30 1 30
8 hrs ` x 10 hrs
2 40 hrs 30hrs ` x
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -61-
3. Total wages:
Workman A: 32x + 4x = ` 36x
Workman B: 30x + 7.5x = ` 37.5x
Statement of factory cost of the job
Workmen A (`) B (`)
Material cost (assumed) y y
Wages (shown above) 36x 37.5x
Works overhead 240 225
Factory cost (given) 2,600 2,600
The above relations can be written as follows:
36x + y + 240 = 2,600 (i)
37.5x+ y+ 225 = 2,600 (ii)
Subtracting (i) from (ii) we get
1.5x – 15 = 0
Or, 1.5 x = 15
Or, x = ` 10 per hour
On substituting the value of x in (i) we get y = ` 2,000
Hence the wage rate per hour is ` 10 and the cost of raw material is ` 2,000 on the job.
Q-6 Jyoti Ltd. wants to ascertain the profit lost during the year 2017-18 due to increased labour turnover. For
this purpose, it has given you the following information:
(1) Training period of the new recruits is 50,000 hours. During this period their productivity is 60% of
the experienced workers. Time required by an experienced worker is 10 hours per unit.
(2) 20% of the output during training period was defective. Cost of rectification of a defective unit
was ` 25.
(3) Potential productive hours lost due to delay in recruitment were 1,00,000 hours.
(4) Selling price per unit is ` 180 and P/V ratio is 20%.
(5) Settlement cost of the workers leaving the organization was ` 1,83,480.
(6) Recruitment cost was ` 1,56,340
(7) Training cost was ` 1,13,180
Required:
CALCULATE the profit lost by the company due to increased labour turnover during the year 2017-18.
50,000
Ans. Output by experienced workers in 50,000 hours = = 5,000 units
10
Output by new recruits = 60% of 5,000 = 3,000 units
Loss of output = 5,000 – 3,000 = 2,000 units
Total loss of output = Due to delay recruitment + Due to inexperience
= 10,000 + 2,000 = 12,000 units
Contribution per unit = 20% of `180 = ` 36
Total contribution lost = `36 × 12,000 units = ` 4,32,000
Cost of repairing defective units = 3,000 units × 0.2 × ` 25 = ` 15,000
Profit forgone due to labour turnover
-62- Chapter-3 : Employee Cost
(` )
Loss of Contribution 4,32,000
Cost of repairing defective units 15,000
Recruitment cost 1,56,340
Training cost 1,13,180
Settlement cost of workers leaving 1,83,480
Profit forgone in 2017-18 9,00,000
Q-7 M/s Zeba Private Limited allotted a standard time of 40 hours for a job and the rate per hour is ` 75. The
actual time taken by a worker is 30 hours.
You are required to calculate the total earnings under the following plans:
(i) Halsey Premium Plan (Rate 50%) (ii) Rowan Plan
(iii) Time Wage System (iv) Piece Rate System
(v) Emerson Plan
Ans.
(i) Halsey Premium plan :
1
= (Time taken × Rateper hour) + ( × Time saved × Rate per hour)
2
1
= (30 hours × ` 75) + ( × 10 hours × ` 75)
2
= ` 2,250 + ` 375 = ` 2,625
(ii) Rowan Premium plan :
Time saved
= (Time taken × Rateper hour) + ( × Time saved × Rate per hour)
Time allowed
10
= (30 hours × ` 75) + ( × 30 × ` 75)
40
= ` 2,250 + ` 375 = ` 2,625
= ` 2,250 + ` 562.5 = ` 2,812.5 or ` 2,813
(iii) Time wage system :
= T ime taken × Rate per hour
= 30 × ` 75 = ` 2,250
(iv) Piece Rate System :
= Std. T ime × Rate per hour
= 40 × ` 75 = ` 3,000
(v) Emerson plan :
Efficiency level = 40/30 = 133.33%
Time taken × (120% + 33.33%) of Rate
= 30 hours × 153.33% of ` 75 = ` 3,450
Q-8 Explain Direct Expenses and how these are measured and their treatment in cost accounting.
Ans. Direct Expense: Expenses other than direct material cost and direct employee cost, which are incurred
to manufacture a product or for provision of service and can be directly traced in an economically
feasible manner to a cost object. The following costs are examples for direct expenses:
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -63-
2.
Effective Working hours (310 days × 8 hours) 2480 hours
Less: Leave days (30 days × 8 hours) 240 hours*
Available Working hours 2240 hours
Less: Normal Loss @ 70 hours
2170 hours
507780
Employee Cost per hour = ` 234
2170
*It is assumed 310 working days are without taking leave permitted into consideration
3. Cost of abnormal idle time per employee = ` 234× 50 hours= ` 11700
Alternative solution for Part (2) and (3)
(2) Calculation of Employee cost per hour:
Working hours per annum 2,480 *
Less: Normal Idle time hours 70
Effective hours 2,410
Employee cost 5,07,780
Employee cost per hour 210.70
*It is assumed 310 working days are after adjusting leave permitted during the year.
(3) Cost of Abnormal idle time per employee:
Abnormal Idle time hours 50
Employee cost per hour 210.70
Cost of Abnormal idle time (210.70 ×50) 10,534.85
Q-10 A worker takes 15 hours to complete a piece of work for which time allowed is 20 hours.
His wage rate is ` 5 per hour. Following additional informa tion are also available:
Material cost of work ` 50
Factory overheads 100% of wages
Calculate the factory cost of work under the following methods of wage payments:
(i) Rowan Plan
(ii) Halsey Plan
Ans.
`
(i) Rowan Plan : Normal time wage = 15 hours @ ` 5= 75
Bonus = Time saved /Time allowed × (Time taken × Time rate)
5
= x (15 x 5) 18.75
20
93.75
(ii) Halsey Plan: Normal time wage = 15 hours @ ` 5 = 75
Bonus = 50% of (Time saved x Time rate) = 50% of (5x5) = 12.5
87.5
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -65-
10 x 365
Equivalent Annual Turnover Rate = = 117.74%
31
(iii) Flux Method:
Labour turnover rate = No. of separations + No. of accessions × 100
Average number of workers
(100 + 300) 400
= 100 = 100 = 40%
(900 + 1100 2) 1,000
40 365
Equivalent Annual Turnover Rate = 470.97%
31
OR
(iii) Flux Method:
Labour turnover rate = No. of separation + No. of replaced × 100
Average number of workers
100 + 75
100 = 17.5%
1000
17.5 x 365
Equivalent Annual Turnover Rate = = 206.05%
31
Q-12 A, B and C are three industrial workers working in Sports industry and are experts in making cricket
pads. A, B and C are working in Mahi Sports, Virat Sports and Sikhar Sports companies respectively.
Workers are paid under different incentive schemes. Company wise incentive schemes are as follows:
Company Incentive scheme
Mahi Sports Emerson’s efficiency system
Virat Sports Merrick differential piece rate system
Sikhar Sports Taylor’s differential piece work system
The relevant information for the industry is as under:
Standard working hours 8 hours a day
Standard output per hour (in units) 2
Daily wages rate Rs. 360
No. of working days in a week 6 days
Actual outputs for the week are as follows:
A B C
132 units 108 units 96 units
You are required to calculate effective wages rate and weekly earnings of all the three workers.
Ans.
Calculation of effective wages rate and weekly earnings of the workers A, B and C
Workers A B C
Standard Output 96 units 96 units 96 units
(8 hrs. × 2 units × 6 days) (8 hrs. × 2 units × 6 days) (8 hrs. × 2 units × 6 days)
Actual Output 132 units 108 units 96 units
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -67-
Q-13 Discuss the accounting treatment of Idle time and overtime wages.
Ans. Accounting treatment of idle time wages & overtime wages in cost accounts: Normal idle time is
treated as a part of the cost of production. T hus, in the case of direct workers, an allowance for normal
idle time is built into the labour cos t rates. In the case of indirect workers, normal idle time is spread
over all the products or jobs through the process of absorption of factory overheads.
Under Cost Accounting, the overtime premium is treated as follows:
If overtime is resorted to at the desire of the customer, then the overtime premium may be charged to
the job directly.
If overtime is required to cope with general production program or for meeting urgent orders, the
overtime premium should be treated as overhead cost of particular depart ment or cost center which
works overtime.
Overtime worked on account of abnormal conditions should be charged to costing Profit & Loss Account.
If overtime is worked in a department due to the fault of another department the overtime premium
should be charged to the latter department.
Q-14 State : Direct Expenses with examples.
Ans. Expenses other than direct material cost and direct employee cost, which are incurred to manufacture
a product or for provision of service and can be directly traced in an economically feasible manner to a
co st object. T he following costs are examples for direct expenses:
(a) Royalty paid/ payable for production or provision of service;
(b) Hire charges paid for hiring specific equipment;
(c) Cost for product/ service specific design or drawing;
(d) Cost of product/ service specific software;
(e) Other expenses which are directly related with the production of goods or provision of service.
Q-15 Two workers ‘A’ and ‘B’ produce the same product using the same material. Their normal wage rate is
also the same. ‘A’ is paid bonus according to Rowan scheme while ‘B’ is paid bonus according to Halsey
scheme. The time allowed to make the product is 120 hours. ‘A’ takes 90 hours while ‘B’ takes 100 hours
to complete the product. The factory overhead rate is ` 50 per hour actually worked. The factory cost of
product manufactured by ‘A’ is ` 80,200 and for product manufactured by ‘B’ is ` 79,400.
Required:
(i) COMPUTE the normal rate of wages.
(ii) CALCULATE the material cost.
(iii) PREPARE a statement comparing the factory cost of the product as made by two workers.
Ans. Let x be the cost of material and y be the normal rate of wage/hour
Worker A (`) Worker B (`)
Material cost x x
Labour wages 90 y 100 y
Bonus Rowan system Halsey system
Time saved
hour worked rate Hours saved x 50% x rate
Time allowed
30 1
90 y = 22.5y 20 y = 10 y
120 2
Overheads 90 x ` 50 = 4,500 100 x ` 50 = 5,000
Factory cost x + 112.5y + 4,500 = 80,200 x + 110y + 5,000 = 79,400
x + 112.5y = 75,700……... (1) x + 110y = 74,400…. (2)
30 1
90 520 20 × × 520
120 2
Overheads 4,500 5,000
(90 x ` 50) (100 x ` 50)
Factory cost 80,200 79,400
Q-16 Corrs Consultancy Ltd. is engaged in BPO industry. One of its trainee executives in the Personnel
department has calculated labour turnover rate 24.92% for the last year using Flux method.
Following is the some data provided by the Personnel department for the last year:
Employees At the beginning Joined Left At the end
Data Processors 540 1,080 60 1,560
Payroll Processors ? 20 60 40
Supervisors ? 60 --- ?
Voice Agents ? 20 20 ?
Assistant Managers ? 20 --- 30
Senior Voice Agents 4 --- --- 12
Senior Data Processors 8 --- --- 34
Team Leaders ? --- --- ?
Employees transferred from the Subsidiary Company
Senior Voice Agents --- 8 --- ---
Senior Data Processors --- 26 --- ---
Employees transferred to the Subsidiary Company
Team Leaders --- --- 60 ---
Assistant Managers --- --- 10 ---
At the beginning of the year there were total 772 employees on the payroll of the company. The
opening strength of the Supervisors, Voice Agents and Assistant Managers were in the ratio of 3 : 3 : 2.
The company has decided to abandon the post of Team Leaders and consequently all the Team Leaders
were transferred to the subsidiary company.
The company and its subsidiary are maintaining separate set of books of account and separate Personnel
Department.
You are required to CALCULATE:
(a) Labour Turnover rate using Replacement method and Separation method.
(b) Verify the Labour turnover rate calculated under Flux method by the trainee executive of the
Corrs Consultancy Ltd.
Ans. Working Notes:
(i) Calculation of no. of employees at the beginning and end of the year
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -69-
= No.of employees (Re placed New recruited Separated) during the year x 100
Average no.of employees onroll
1,234 + 210
x 10 = 112.46%
1,284
Labour Turnover calculated by the executive trainee of the Personnel department is incorrect as it has
not taken the No. of new recruitment while calculating the labour turnover under Flux method.
Q-17 Discuss the remedial steps to be taken to minimize the labour turnover.
Ans. The following steps are useful for minimizing labour turnover:
(a) Exit interview: An interview to be arranged with each outgoing employee to ascertain the reasons
of his leaving the organization.
(b) Job analysis and evaluation: to ascertain the requirement of each job.
(c) Organization should make use of a scientific system of recruitment, placement and promotion for
employees.
(d) Organization should create healthy atmosphere, providing education, medical and housing
facilities for workers.
(e) Committee for settling workers grievances.
Q-18 RST Company Ltd. has computed labour turnover rates for the quarter ended 31st March, 2017 as 20%,
10% and 5% under flux method, replacement method and separation method respectively. If the
number of workers replaced during that quarter is 50,
Calculate :
(i) Workers recruited and joined
(ii) Workers left and discharged and
(iii) Average number of workers on roll.
Ans.
No. of workers replaced
Labour Turnover Rate (Replacement method) = × 100
Average no. of workers
10 50
Or, =
100 Average no. of workers
Thus, Average No. of workers = 500
No. of workers replaced
Labour Turnover Rate (Separation method) = × 100
Average no. of workers
80 320 × 100 =
400
× 100 = 5%
=
7, 600 + 8, 400 ÷ 2 8, 000
Q-20 State various causes of and treatment of Overtime Premium in Cost Accounting.
Ans. Causes and Treatment of Overtime premium in cost accounting
Causes Treatment
(1) The customer may agree to bearthe (1) If overtime is resorted to at the desire ofthe
entire charge of overtimebecause customer, then overtime premium maybe
urgency of work. charged to the job directly.
(2) Overtime may be called for tomake (2) If overtime is required to cope with
up any shortfall inproduction due to generalproduction programmes or for
someunexpected development. meetingurgent orders, the overtime
premiumshould be treated as overhead cost of
the particular department or cost centre
which works overtime.
(3) Overtime work may be necessary to (3) If overtime is worked in a department dueto the
make up a shortfall inproduction due to fault of another department, the over time
some fault ofmanagement. premium should be charged tothe latter
department
(4) Overtime work may be resorted to,to (4) Overtime worked on account of abnormal
secure an out-turn in excess of the conditions such as flood, earthquake etc.,should
normal output to takeadvantage of an not be charged to cost, but toCosting Profit and
expanding marketor of rising demand Loss Account.
Q-21 In a factory, the basic wage rate is ` 300 per hour and overtime rates are as follows:
Before and after normal working hours 180% of basic wage rate
Sundays and holidays 230% of basic wage rate
During the previous year, the following hours were worked
- Normal time 1,00,000 hours
- Overtime before and after working hours 20,000 hours
Overtime on Sundays and holidays 5,000 hours
Total 1,25,000 hours
The following hours have been worked on job ‘A’
Normal 1,000 hours
Overtime before and after working hrs. 100 hours.
Sundays and holidays 25 hours.
Total 1,125 hours
You are required to CALCULATE the labour cost chargeable to job ‘A’ and overhead in each of the
following instances:
(i) Where overtime is worked regularly throughout the year as a policy due to the workers’ shortage.
(ii) Where overtime is worked irregularly to meet the requirements of production.
(iii) Where overtime is worked at the request of the customer to expedite the job.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -73-
Ans. Workings
Basic wage rate : ` 300 per hour
Overtime wage rate before and after working hours: ` 300 × 180% = ` 540 per hour
Overtime wage rate for Sundays and holidays : ` 300 × 230% = ` 690 per hour
Computation of average inflated wage rate (including overtime premium):
Particulars Amount (`)
Annual wages for the previous year for normal time (1,00,000 hrs. × ` 300) 3,00,00,000
Wages for overtime before and after working hours (20,000 hrs. × ` 540) 1,08,00,000
Wages for overtime on Sundays and holidays (5,000 hrs. × ` 690) 34,50,000
Total wages for 1,25,000 hrs. 4,42,50,000
(f) Work of holiday and Sunday Double of per day basic rate provided works
atleast 4 hours. The holiday and Sunday basic is
eligible for all allowances and statutory
deductions.
(h) Earned leave & Casual leave These are paid leave.
(h) Employer’s contribution to 12% of basic and DA
Provident fund
(i) Employer’s contribution to 7% of basic and DA
Pension fund
The company normally works 8-hour a day and 26-day in a month. The company provides 30 minutes
lunch break in between.
During the month of August 2020, Mr.Z works for 23 days including 15th August and a Sunday and
applied for 3 days of casual leave. On 15th August and Sunday he worked for 5 and 6 hours respectively
without lunch break.
On 5th and 13th August he worked for 10 and 9 hours respectively.
During the month Mr. Z worked for 100 hours on Job no.HT200.
You are required to CALCULATE:
(i) Earnings per day
(ii) Effective wages rate per hour of Mr. Z.
(iii) Wages to be charged to Job no.HT200.
Ans. Workings:
1. Normal working hours in a month = (Daily working hours – lunch break) × no. of days
= (8 hours – 0.5 hours) × 26 days = 195 hours
2. Hours worked by Mr.Z = No. of normal days worked + Overtime + holiday/ Sunday worked
= (21 days × 7.5 hours) + (9.5 hours + 8.5 hours) + (5 hours + 6 hours)
= 157.5 hours + 18 hours + 11 hours = 186.50 hours.
(i) Calculation of earnings per day
Particulars Amount (`)
Basic salary (`1,000 × 26 days) 26,000
Dearness allowance (20% of basic salary) 5,200
31,200
House rent allowance (16% of basic salary) 4,160
Employer’s contribution to Provident fund (12% × ` 31,200) 3,744
Employer’s contribution to Pension fund (7% × ‘31,200) 2,184
41,288
No. of working days in a month (days) 26
Rate per day 1,588
Transport allowance per day 50
Earnings per day 1,638
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -75-
(ii) Computation of Wages of each worker under piece work earning basis
Product Piece Worker-M Worker-N Worker-O
rate per
unit
(`) Units Wages (`) Units Wages (`) Units Wages (`)
A 22.50 210 4,725 - - 600 13,500
B 30.00 360 10,800 - - 1,350 40,500
C 45.00 460 20,700 250 11,250 - -
Total 36,225 11,250 54,000
Since each worker’s earnings are more than 50% of basic pay. Therefore, worker-M, N and O will be
paid the wages as computed i.e. ` 36,225, ` 11,250 and ` 54,000 respectively.
Working Notes:
1. Piece rate per unit
Product Standard time per Piece rate each Piece rate per unit
unit (in minutes) minute (`) (`)
A 15 1.5 22.50
B 20 1.5 30.00
C 30 1.5 45.00
Q-24 ABC Ltd. has its factory at two locations viz Noida and Patparganj. Rowan plan is used at Noida factory
and Halsey plan at Patparganj factory.
Standard time and basic rate of wages are same for a job which is similar and is carried out on similar
machinery. Normal working hours is 9 hours per day in a 5 day week.
Job at Noida factory is completed in 36 hours while at Patparganj factory it has taken 33 hours 45
minutes. Conversion costs at Noida and Patparganj are ` 6,084 and ` 5,569 respectively.
Overheads account for ` 25 per hour.
REQUIRED:
(i) To find out the normal wage; and
(ii) To compare the respective conversion costs.
Ans.
Particulars Noida Patparganj
Hours worked 36 hr. 33.75 hr.
Conversion Costs ` 6,084 ` 5,569
Less: Overheads ` 900 ` 844
( ` 25 x 36 hr.) ( ` 25 x 33.75 hr.)
Labour Cost ` 5,184 ` 4,725
(i) Finding of Normal wage rate:
Let Wage rate be ` R per hour, this is same for both the Noida and Patparganj factory.
Normal wage rate can be found out taking total cost of either factory.
Noida: Rowan Plan
Total Labour Cost = Wages for hours worked + Bonus as per Rowan plan
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -77---
Time saved
` 5,184 = Hours worked × Rate per hour + ×Hours worked ×Rate per hour)
Time allowed
45- 36
Or, ` 5,184 = 36 hr. × R + × 36 ×R
45
Or, ` 5,184 = 36R + 7.2R
R = ` 120
Normal wage = 36 hrs x ` 120 = ` 4,320
OR
Patparganj: Halsey Plan
Total Labour Cost = Wages for hours worked + Bonus as per Halsey plan
` 4,725 = Hours worked x Rate per hour + (50% x Hours saved x Rate per hour )
` 4,725 = 33.75 hr. x R + 50% x (45 hr. - 33.75 hr.) x R
` 4,725 = 39.375 R
R = ` 120
Normal Wage = 33.75 hrs x ` 120 = ` 4,050
(ii) Comparison of conversion costs:
Particulars Noida ( `) Patparganj ( `)
Normal Wages (36 x 120) 4,320
(33.75 x 120) 4,050
Bonus (7.2 x 120) 864
(5.625 x 120) 675
Overhead 900 844
6,084 5,569
Q-25 Following information is given of a newly setup organization for the year ended on 31st March, 2021.
Number of workers replaced during the period 50
Number of workers left and discharged during the period 25
Average number of workers on the roll during the period 500
You are required to:
(i) Compute the Employee Turnover Rates using Separation Method and Flux Method.
(ii) Equivalent Employee Turnover Rates for (i) above, given that the organization was setup on 31st
January, 2021.
Ans.(i) Employee Turnover rate
Using Separation method:
= Number of employees Separated during the period x 100
Average number of employees during the period on roll
50+25
= ×100 = 15%
500
9,600 hours
= × 2,487 hours × ` 50 = ` 98,764
12,087 hours
Total wages to be paid to 50 workers are ( ` 4,80,000 + ` 98,764) ` 5,78,764, if Z Ltd. considers the
introduction of Rowan Incentive Scheme to increase the worker productivity.
(i) (a) Effective hourly rate of earnings under Halsey scheme:
(Refer to Working Notes 1, 2 and 3)
= = ` 56.48
(ii) (a) Saving in terms of direct labour cost per unit under Halsey scheme:
(Refer to Working Note 3)
Labour cost per unit (under time wage scheme)
= 1.975 hours × ` 50 = ` 98.75
Labour cost per unit (under Halsey scheme)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -81-
Ans. (i) Calculation of Net Wages paid to Worker ‘R’ and ‘S’
Particulars R ( `) S ( `)
Basic Wages 15,000.00 30,000.00
Dearness Allowance (DA) (50% of Basic Wages) 7,500.00 15,000.00
Overtime Wages (Refer to Working Note 1) 4,500.00 ——
Gross Wages earned 27,000.00 45,000.00
Less: Provident Fund (7% × ` 15,000); (7.5% × ` 30,000) (1,050.00) (2,250.00)
Less: ESI (2% × ` 15,000); (2% × ` 30,000) (300.00) (600.00)
Net Wages paid 25,650.00 42,150.00
Calculation of ordinary wage rate per hour of Worker ‘R’ and ‘S’
R ( `) S ( `)
Gross Wages (Basic Wages + DA) 22,500.00 45,000.00
(excluding overtime)
Employer’s contribution to P.F. and E.S.I. 1,350.00 2,850.00
23,850.00 47,850.00
Ordinary wages Labour Rate per hour
( ` 23,850 ÷ 200 hours); ( ` 47,850 ÷ 200 hours) 119.25 239.25
(ii) Statement Showing Allocation of workers cost to each Job
Total Jobs
Wages A B C
Worker R
Ordinary Wages (15:2:3) 23,850.00 17,887.50 2,385.00 3577.50
Overtime 4500.00 4500.00 -
Worker S
Ordinary Wages (2:1:2) 47,850.00 19,140.00 9,570.00 19,140.00
76,200.00 41,527.50 11,955.00 22,717.50
Working Note:
Normal Wages are considered as basic wages.
2 x (Basic wage + D.A.) x 20 hours
Over time =
200 hours
`22,500
= 2x 20 hours
200
= ` 4,500
Q-28 Discuss any four objectives of ‘Time keeping’ in relation to attendance and payroll procedures.
Ans. The objectives of time-keeping in relation to attendance and payroll procedures are as follows:
(i) For the preparation of payrolls.
(ii) For calculating overtime.
(iii) For ascertaining and controlling employee cost.
(iv) For ascertaining idle time.
(v) For disciplinary purposes.
(vi) For overhead distribution
Q-29 Textile Ltd. pays following overtime premium for its labour beside normal wages of ` 100 per hour:
Before and after normal working hours 80% of basic wage rate
Sundays and holidays 150% of basic wage rate
During the previous year 2019-20, the following hours were worked:
Normal time 3,00,000 hours
Overtime before and after normal working hours 60,000 hours
Overtime on Sundays and holidays 15,000 hours
Total 3,75,000 hours
During the current year 2020-21, the following hours have been worked on job `Spinning’:
Normal 4,000 hours
Overtime before and after normal working hours 400 hours
Overtime on Sundays and holidays 100 hours
Total 4,500 hours
You are required to CALCULATE the labour cost chargeable to job `Spinning’ and overhead in each of the
following instances:
(a) Where overtime is worked regularly throughout the year as a policy due to the workers’ shortage.
(b) Where overtime is worked irregularly to meet the requirements of production.
(c) Where overtime is worked at the request of the customer to expedite the job.
Ans. Workings:
Basic wage rate = ` 100 per hour
Overtime wage rate before and after working hours = ` 100 + ( ` 100 × 80%)
= ` 180 per hour
Overtime wage rate for Sundays and holidays = ` 100 + ( ` 100 × 150%)
= ` 250 per hour
Computation of average inflated wage rate (including overtime premium):
Particulars Amount ( `)
Annual wages for the previous year for normal time 3,00,00,000
(3,00,000 hrs. × ` 100)
Wages for overtime before and after normal working hours 108,00,000
(60,000 hrs. × ` 180)
Wages for overtime on Sundays and holidays 37,50,000
(15,000 hrs. × ` 250)
Total wages for 3,75,000 hrs. 4,45,50,000
` 4,45,50,000
Average inflated wage rate = = ` 118.80
3,75,000 hours
(a) Where overtime is worked regularly as a policy due to workers’ shortage
The overtime premium is treated as a part of employee cost and job is charged at an inflated wage
rate. Hence, employee cost chargeable to job `Spinning’
= Total hours × Inflated wage rate = 4,500hrs. × ` 118.80 = ` 5,34,600
(b) Where overtime is worked irregularly to meet the requirements of production
Basic wage rate is charged to the job and overtime premium is charged to factory overheads as
under:
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -83-
M J Total
( `) ( `) ( `)
Basic Wages 1,200 1,680 2,880
(100 Hrs. × `12) (140 Hrs. × ` 12)
Bonus (as per Halsey Scheme) 120 168
(50% of Time Saved × Excess (50% of 20 Hrs. × ` 12) (50% of 28 Hrs. × ` 12) 288
Rate)
Excess Wages Paid 1,320 1,848 3,168
(ii) Calculation of loss incurred due to incorrect rate selection had Rowan scheme of bonus payment
followed:
M J Total
( `) ( `) ( `)
Basic Wages 1,200 1,680 2,880
(100 Hrs. × ` 12) (140 Hrs. × ` 12)
Bonus (as per Rowan Scheme)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -85-
Time Saved
Bonus = × Time taken × Rate per hour
Time Allowed
Example explaining highly efficient worker and less efficient worker obtaining same bonus:
Time rate (per Hour) ` 60
Time allowed 8 hours.
Time taken by ‘X’ 6 hours.
Time taken by ‘Y’ 2 hours.
Bonus = Time Saved / Time Allowed × Time taken × Rate per hour
For ‘X’ = 2 hours / 8 hours × 6 hours × ` 60 = ` 90
For ‘Y’ = 6 hours8 hours × 2 hours × ` 60 = ` 90
From the above example, it can be concluded that a highly efficient worker may obtain same bonus as
less efficient worker under this system.
Q-32 A total of 108 labour hours have been put in a particular job card for repair work engaging a semi-skilled
and skilled labour (Mr. Deep and Mr. Sam respectively).
The hours devoted by both the workers individually on daily basis for this particular job are given
below:
Monday Tuesday Wednesday Thursday Friday
10.5 8.0 10.5 9.5 10.5
The skilled labour also worked on Saturday for 10 hours.
Sunday is a weekly holiday and each worker has to work for 8 hours on all week days and 5 hours on
Saturdays; the workers are however paid full wages for Saturday (8 hours for 5 hours worked).
Semi-skilled and skilled worker is paid ordinary wage @ ‘ 400 and ‘ 600 respectively per day of 8 hours
labour. Further, the workers are also paid dearness allowance @ 20%.
Extra hours worked over and above 8 hours are also paid at ordinary wage rate however, overtime
premium of 100% of ordinary wage rate is paid if a worker works for more than 9 hours in a day AND 48
hours in a week.
You are required to COMPUTE the wages payable to Mr. Deep (Semi-skilled) and Mr. Sam (Skilled).
Ans. Calculation of total normal hours to be paid for Mr. Deep (Semi-skilled):
Day Normal Extra Overtime Equivalent Total normal
hours hours hours normal hours for hours
overtime worked
A B C D = C×2 E = A+B+D
Monday 8 1 1½ 3 12
Tuesday 8 — — — 8
Wednesday 8 1 1½ 3 12
Thursday 8 1 ½ 1 10
Friday 8 1 1½ 3 12
Saturday — — — — —
Total 40 4 5 10 54
Calculation of total normal hours to be paid for Mr. Sam (Skilled):
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -87-
= ` 180
750
T= = 7.14 hours
105
Q-34 R Ltd. is facing increasing employee turnover in the factory and before analyzing the causes and taking
remedial steps; the management wants to have an idea of the profit foregone as a result of employee
turnover in the last year.
Last year sales amounted to ` 99,63,960 and P/V ratio was 20%.
The total number of actual hours worked by the direct employee force was 5.34 lakhs. The actual direct
employee hours included 36,000 hours attributable to training new recruits, out of which half of the
hours were unproductive. As a result of the delays by the Personnel Department in filling vacancies
due to employee turnover, 1,20,000 potentially productive hours (excluding unproductive training
hours) were lost.
The costs incurred consequent on employee turnover revealed, on analysis, the following:
Settlement cost due to leaving ` 52,584
Recruitment costs ` 32,088
Selection costs ` 15,300
Training costs ` 36,588
Assuming that the potential production lost as a consequence of employee turnover could have been
sold at prevailing prices, FIND the profit foregone last year on account of employee turnover.
Ans. Workings:
(i) Computation of productive hours
Actual hours worked 5,34,000
Less: Unproductive training hours 18,000
Actual productive hours 5,16,000
(ii) Productive hours lost:
Loss of potential productive hours + Unproductive training hours
= 1,20,000 + 18,000 = 1,38,000 hours
(iii) Loss of contribution due to unproductive hours:
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -89-
Working Notes:
Calculation of bonus hours:
Time saved 120 hours Time saved 216 hours
For first 20% of time allowed i.e. 48 hours 12 12
(25% of 48 hours) (25% of 48 hours)
For next 30% of time allowed i..e. 72 hours 28.80 28.80
(40% of 72 hours) (40% of 72 hours)
For next 30% of time allowed i..e. 72 hours - 21.60
(30% of 72 hours)
For next 20% of time allowed i..e. 48 hours - 2.40
(10% of 24 hours)
Bonus hours 40.80 64.80
CHAPTER- 4
OVERHEADS-ABSORPTION COSTING METHOD
Q-1 PLR Ltd. manufacturers a single product and recovers the overheads by adopting a single blanket rate
based on machine hours. The budgeted production overheads of the factory for the FY 2019-20 are
`50,40,000 and budgeted machine hours are 6,000.
For a period of first six months of the financial year 2019?20, following information were extracted
from the books:
Actual production overheads `34,08,000
Amount included in the production overheads:
Paid as per court’s order `4,50,000
Expenses of previous year booked in current year `1,00,000
Paid to workers for strike period under an award `4,20,000
Obsolete stores written off `36,000
Production and sales data of the concern for the first six months are as under:
Production:
Finished goods 1,10,000 units
Works-in-progress
(50% complete in every respect) 80,000 units
Sale:
Finished goods 90,000 units
The actual machine hours worked during the period were 3,000 hours. It is revealed from
the analysis of information that 40% of the over/under-absorption was due to defective
production policies and the balance was attributable to increase in costs.
You are required:
(i) to determine the amount of over/ under absorption of production overheads for theperiod,
(ii) to show the accounting treatment of over/ under-absorption of production overheads,and
(iii) to apportion the over/ under-absorbed overheads over the items.
Ans. (i) Amount of over/ under absorption of production overheads during the period of firstsix months
of the year 2019-20:
Amount(`) Amount(`)
Total production overheads actually incurred during theperiod 34,08,000
Less: Amount paid to worker as per court order 4,50,000
Expenses of previous year booked in the currentyear 1,00,000
Wages paid for the strike period under an award 4,20,000
Obsolete stores written off 36,000 10,06,000
24,02,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -91-
` 50,40,000
*Budgeted Machine hour rate (Blanket rate) = = ` 840 per hour
6,000 hours
(ii) Accounting treatment of over absorbed production overheads: As, 40% of the over absorbed overheads
were due to defective production policies, this being abnormal, hence should be credited to Costing
Profit and Loss Account.
Amount to be credited to Costing Profit and Loss Account = `1,18,000× 40% = `47,200.
Balance of over absorbed production overheads should be distributed over Works in progress, Finished
goods and Cost of sales by applying supplementary rate*. Amount to be distributed = `1,18,000× 60% =
`70,800
` 70,800
Supplementary rate = = ` 0.472 per unit
1,50,000 units
(iii) Apportionment of over absorbed production overheads over WIP, Finished goods and Cost of sales:
Equivalent Amount
completed units (`)
Work-in-Progress (80,000 units × 50% ×0.472) 40,000 18,880
Finished goods (20,000 units × 0.472) 20,000 9,440
Cost of sales (90,000 units × 0.472) 90,000 42,480
Total 1,50,000 70,800
Q-2 The Union Ltd. has the following account balances and distribution of direct charges on 31st March,
2019.
Total Production Depts. Service Depts.
Machine Shop Packing General Stores
Plant
Allocated Overheads: (`) (`) (`) (`) (`)
Indirect labour 29,000 8,000 6,000 4,000 11,000
Maintenance Material 9,900 3,400 1,600 2,100 2,800
Misc. supplies 5,900 1,500 2,900 900 600
Supervisor’s salary 16,000 — — 16,000 —
Cost & payroll salary 80,000 — — 80,000 —
Overheads to be apportioned:
Power 78,000
Rent 72,000
Fuel and Heat 60,000
Insurance 12,000
Taxes 8,400
Depreciation 1,20,000
The following data were compiled by means of the factory survey made in the previous year:
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -93-
Working Note:
Rate per unit of cost driver:
Power : (`40,00,000 ÷ 50,000 kWh) = `80/kWh
Quality Inspection : (`60,00,000 ÷ 10,000 inspections) = `600 per inspection
(ii) Calculation of cost of unused capacity for each activity:
(`)
Power 4,00,000
(`40,00,000 – `36,00,000)
Quality Inspections
(`60,00,000 – `54,00,000) 6,00,000
Total cost of unused capacity 10,00,000
(iii) Factors management consider in choosing a capacity level to compute the budgeted fixed overhead
cost rate:
- Effect on product costing & capacity management
- Effect on pricing decisions.
- Effect on performance evaluation
- Effect on financial statements
- Regulatory requirements.
- Difficulties in forecasting for any capacity level.
Q-4 Sree Ajeet Ltd. having fifteen different types of automatic machines furnishes information as under
for 20X8-20X9
(i) Overhead expenses: Factory rent ` 1,80,000 (Floor area 1,00,000 sq. ft.), Heat and gas ` 60,000 and
supervision ` 1,50,000.
(ii) Wages of the operator are ` 200 per day of 8 hours. Operator attends to one machine when it is
under set up and two machines while they are under operation.
In respect of machine B (one of the above machines) the following particulars are furnished:
(i) Cost of machine `1,80,000, Life of machine- 10 years and scrap value at the end of its life ` 10,000
(ii) Annual expenses on special equipment attached to the machine are estimated as ` 12,000
(iii) Estimated operation time of the machine is 3,600 hours while set up time is 400 hours per annum
(iv) The machine occupies 5,000 sq. ft. of floor area.
(v) Power costs ` 5 per hour while machine is in operation.
ESTIMATE the comprehensive machine hour rate of machine B. Also find out machine costs to be
absorbed in respect of use of machine B on the following two work orders
Work order- 1 Work order-2
Machine set up time (Hours) 15 30
Machine operation time (Hours) 100 190
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -95-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -97-
(b) Balance of under absorbed production overheads should be distributed over Finished goods and
Cost of sales by applying supplementary rate*.
Amount to be distributed = ` 2,34,000 × 2/3 =` 1,56,000
` 1,56,000
*Supplementary rate = ` 5.20 per hour
30,000 units
(iii) Apportionment of under absorbed production overheads over Finished goods and Cost of sales:
Particular Units Amount (`)
Finished goods (3,000 units × `5.20) 3,000 15,600
Cost of sales (27,000 units × ` 5.20) 27,000 1,40,400
Total 30,000 1,56,000
Q-7 M/s Zaina Private Limited has purchased a machine costing ` 29,14,800 and it is expected to have a
salvage value of ` 1,50,000 at the end of its effective life of 15 years.
Ordinarily the machine is expected to run for 4,500 hours per annum but it is estimated that 300 hours
per annum will be lost for normal repair & maintenance. The other details in respect of the machine
are as follows :
(i) Repair & Maintenance during the whole life of the machine are expected to be ` 5,40,000.
(ii) Insurance premium (per annum) 2% of the cost of the machine.
(iii) Oil and Lubricants required for operating the machine (per annum) ` 87,384.
(iv) Power consumptions: 10 units per hour @ ` 7 per unit. No power consumption during repair and
maintenance. ·
(v) Salary to operator per month ` 24,000. The operator devotes one third of his time to the machine.
You are required to calculate comprehensive machine hour rate.
Ans. Effective machine hour = 4,500 – 300 = 4,200 hours
Calculation of Comprehensive machine hour rate
Elements of Cost and Revenue Amount (`) Per
Annum
Repair and Maintenance(`5,40,000 ÷15 years) 36,000
Power (4,200 hours × 10 units × `7) 2,94,000
` 29,14,800 - ` 1,50,000
Depreciation 1,84,320
15 years
Insurance (` 29,14,800 × 2%) 58,296
Oil and Lubricant 87,384
Salary to Operator {(`24,000×12)/3} 96,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -99-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -103-
(`) (`)
(A) Standing charges (per annum)
Rent 5,400.00
Heat and light 9,720.00
Forman’s salary 12,960.00
Other miscellaneous expenditure 18,000.00
Standing charges (per annum) 46,080.00
Total expenses for one machine for four week period 1,181.54
` 46,080
3 machines 13 four - week period
Wages (48 hours × 4 weeks × ` 20 × 3 operators) 11,520.00
Bonus {(176 hours × ` 20 × 3 operators) x 10%} 1,056.00
Total standing charges 13,757.54
(B) Machine Expenses
1
Depreciation = 52,000 × 10% × 400.00
13 four - week period
Repairs and maintenance (` 60 x 4 weeks) 240.00
Consumable stores (` 75 x 4 weeks) 300.00
Power (176 hours x 20 units x ` 0 .80) 2,816.00
Total machine expenses 3,756.00
(C) Total expenses (A) + (B) 17,513.54
` 17,513.54
(ii) Machine hour rate = = 99.51
176 hours
Q-13 Explain Single and Multiple Overhead Rates.
Ans. Single and Multiple Overhead Rates:
Single overhead rate: It is one single overhead absorption rate for the whole factory.
It may be computed a s follows:
Single overhead rate = Overhead costs for the entire factory
Total quantity of the base selected
The base can be total output, total labour hours, total machine hours, etc.
The single overhead rate may be applied in factories which produces only one major product on a
continuous basis. It may also be used in factories where the work performed in each department is
fairly uniform and standardized.
Multiple overhead rate: It i nvolves computation of separate rates for each production department,
service department, cost center and each product for both fixed and variable overheads. It may be
computed as follows:
Multiple overhead rate= Overhead allocated / appportioned to each department/ cost centre or product
Corresponding base
Under multiple overhead s rate, jobs or products are charged with varying amount of factory overheads
depending on the type and number of departments through which they pass.
However, the number of overheads rate which a firm may compute would depend upon two opposing
factors viz. the degree of accuracy desired and the clerical cost involved.
Q-14 In a factory, a machine is considered to work for 208 hours in a month. It includes maintenance time of
8 hours and set up time of 20 hours.
The expense data relating to the machine are as under:
Cost of the machine is Rs. 5,00,000. Life 10 years. Estimated scrap value at the end of life is Rs. 20,000.
(Rs.)
– Repairs and maintenance per annum 60,480
– Consumable stores per annum 47,520
– Rent of building per annum
(The machine under reference occupies 1/6 of the area) 72,000
– Supervisor's salary per month (Common to three machines) 6,000
– Wages of operator per month per machine 2,500
– General lighting charges per month allocated to the machine 1,000
– Power 25 units per hour at Rs. 2 per unit
Power is required for productive purposes only. Set up time, though productive, does not require
power.
The Supervisor and Operator are permanent. Repairs and maintenance and consumable stores vary
with the running of the machine.
Required
COMPUTE a two-tier machine hour rate for (a) set up time, and (b) running time.
Ans. Working Notes:
1. (i) Effective hours for standing charges (208 hours – 8 hours) = 200 hours
(ii) Effective hours for variable costs (208 hours – 28 hours) = 180 hours
2. Standing Charges per hour
Cost per month Cost per hour (Rs.)
(Rs.) (Cost per month ÷ 200 hours)
Rs. 6,000
Supervisor’s salary 2,000 10.00
3 machines
1 Rs. 72,000
Rent of building × 1,000 5.00
6 12 month
General lighting 1,000 5.00
Total Standing Charges 4,000 20.00
3. Machine running expenses per hour
Cost per month (Rs.) Cost per hour (Rs.)
Depreciation 4,000 20.00
Rs.2,500
200 hours
Repairs & Maintenance 5,040 28.00
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -105-
Rs.60,480 Rs.5,040
12 months 180 hours
Consumable stores 3,960 22.00
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -107-
Overheads:
Factory rent Floor Area
(48:20:5:7) 15,28,000 9,16,800 3,82,000 95,500 1,33,700
Factory
building Floor Area
insurance (48:20:5:7) 1,72,000 1,03,200 43,000 10,750 15,050
Plant &
Machinery Value of 1,96,000 1,22,038 55,472 5,547 12,943
insurance Plant &
Machinery
(66:30:3:7)
Plant & Machinery 2,65,000 1,65,000 75,000 7,500 17,500
Depreciation
Value of Plant
& Machinery
(66:30:3:7)
Canteen No. of 4,48,000 2,15,040 1,43,360 68,096 21,504
Subsidy employees
(60:40:19:6) ________ _________ __________ _______ _______
1,39,73,000 1,02,62,078 28,90,832 4,23,393 3,96,697
Re-distribution of Service Departments’ Expenses:
Particulars Basis of Production Service Department Departments
Apportionment Fabrication Assembly Stores Maintenance
Overheads As per Primary 1,02,62,078 28,90,832 4,23,393 3,96,697
as per Primary distribution
distribution
Maintenance Maintenance 2,01,955 1,65,891 28,851 (3,96,697)
Department Hours
Cost (28:23:4:-) _________ ________ _______
1,04,64,033 30,56,723 4,52,244 —
Stores No. of Stores 3,25,616 1,26,628 (4,52,244)
Department Requisition
(18:7:-:-) ________ _______ ___ _____
1,07,89,649 31,83,351 — —
(ii) Overhead Recovery Rate
Department Apportioned Basis of Overhead Overhead Recovery Rate (Rs.)
Overhead (Rs.) Recovery Rate
(I) (II) [(I) ÷ (II)]
Fabrication 1,07,89,649 30,00,000 Machine Hours 3.60 per Machine Hour
Assembly 31,83,351 26,00,000 Labour Hours 1.22 per Labour Hour
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -109-
No other loss of working time expected, setting up time, estimated at 100 hours, is regarded as
productive time. (Holiday to be ignored).
(ii) Electricity used by the machine during production is 16 units per hour at cost of a 9 paisa per unit.
No current is taken during maintenance or setting up.
(iii) The machine required a chemical solution which is replaced at the end of week at a cost of Rs. 20
each time.
(iv) The estimated cost of maintenance per year is Rs. 1,200.
(v) Two attendants control the operation of machine together with five other identical machines.
Their combined weekly wages, insurance and the employer's contribution to holiday pay amount
Rs. 120.
(vi) Departmental and general works overhead allocated to this machine for the current year amount
to Rs. 2,000.
You are required to CALCULATE the machine hour rate of operating the machine.
Ans. Working Notes:
(i) Total Productive hours = Estimated Working hours – Machine Maintenance hours
= 2,200 hours – 200 hours = 2,000 hours
Rs.10,000 - Rs. 1,000
(ii) Depreciation per annum = = Rs.900
10years
(iii) Chemical solution cost per annum = Rs. 20 × 50 weeks = Rs.1,000
Rs. 120 × 50 weeks
(iv) Wages of attendants (per annum) = = Rs.1, 000
6 machines
Calculation of Machine hour rate
Particulars Amount Amount
(per annum) (per hour)
A. Standing Charge
(i) Wages of attendants 1,000
(ii) Departmental and general works overheads 2,000
Total Standing Charge 3,000
3, 000
Standing Charges per hour 1.5
2, 000
B. Machine Expense
(iii) Depreciation 900 0.45
(iv) Electricity - 1.37
Q-20 A Ltd. manufactures two products- A and B. The manufacturing division consists of two production
departments P1 and P2 and two service departments S1 and S2.
Budgeted overhead rates are used in the production departments to absorb factory overheads to the
products. The rate of Department P1 is based on direct machine hours, while the rate of Department P2
is based on direct labour hours. In applying overheads, the pre-determined rates are multiplied by
actual hours.
For allocating the service department costs to production departments, the basis adopted is as follows:
(i) Cost of Department S1 to Department P1 and P2 equally, and
(ii) Cost of Department S2 to Department P1 and P2 in the ratio of 2 : 1 respectively.
The following budgeted and actual data are available:
Annual profit plan data:
Factory overheads budgeted for the year:
Departments P1 27,51,000 S1 8,00,000
P2 24,50,000 S2 6,00,000
Budgeted output in units:
Product A 50,000; B 30,000.
Budgeted raw-material cost per unit:
Product A ` 120; Product B ` 150.
Budgeted time required for production per unit:
Department P1 : Product A : 1.5 machine hours
Product B : 1.0 machine hour
Department P2 : Product A : 2 Direct labour hours
Product B : 2.5 Direct labour hours
Average wage rates budgeted in Department P2 are:
Product A - ` 72 per hour and Product B – ` 75 per hour.
All materials are used in Department P1 only.
Actual data (for the month of Jan, 2020):
Units actually produced: Product A : 4,000 units
Product B : 3,000 units
Actual direct machine hours worked in Department P1:
On Product A 6,100 hours, Product B 4,150 hours.
Actual direct labour hours worked in Department P2:
On Product A 8,200 hours, Product B 7,400 hours.
Costs actually incurred: Product A Product B
` `
Raw materials 4,89,000 4,56,000
Wages 5,91,900 5,52,000
Overheads: Department P1 2,50,000 S1 80,000
P2 2,25,000 S2 60,000
You are required to:
(i) COMPUTE the pre-determined overhead rate for each production department.
(ii) PREPARE a performance report for Jan, 2020 that will reflect the budgeted costs and actual costs
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -113-
Ans.(i) Computation of pre-determined overhead rate for each production department from budgeted data
Production Department Service Department
P1 P2 S1 S2
Budgeted factory overheads for the year (`) 27,51,000 24,50,000 8,00,000 6,00,000
Allocation of service department S1’s
costs to production departments P1 and
P2 equally (‘) 4,00,000 4,00,000 (8,00,000) —
Allocation of service department S2’s 4,00,000 2,00,000 – (6,00,000)
costs to production departments P1 and
P2 in the ratio of 2:1 (`)
Total 35,51,000 30,50,000 — —
Budgeted machine hours in department 1,05,000 —
P1 (working note-1)
Budgeted labour hours in department P2 — 1,75,000
(working note-1)
Budgeted machine/ labour hour rate (‘) 33.82 17.43
(ii) Performance report for Jan, 2020
(When 4,000 and 3,000 units of Products A and B respectively were actually produced)
Budgeted (`) Actual (`)
Raw materials used in Dept. P1:
A : 4,000 units × ` 120 4,80,000 4,89,000
B : 3,000 units × ` 150 4,50,000 4,56,000
Direct labour cost
(on the basis of labour hours worked in department P2)
A : 4,000 units × 2 hrs. × ` 72 5,76,000 5,91,900
B : 3,000 units × 2.5 hrs. × ` 75 5,62,500 5,52,000
Overhead absorbed on machine hour basis in Dept. P1:
A : 4,000 units × 1.5 hrs. × ` 33.82 2,02,920 1,96,420*
B : 3,000 units × 1 hr. × ` 33.82 1,01,460 1,33,630*
Overhead absorbed on labour hour basis in Dept. P2:
A : 4,000 units × 2 hrs. × ` 17.43 1,39,440 1,49,814**
B : 3,000 units × 2.5 hrs. × ` 17.43 1,30,725 1,35,198**
26,43,045 27,03,962
* (Refer to working note 4)
** (Refer to working note 5)
Working notes:
1.
Product A Product B Total
Budgeted output (units) 50,000 30,000
Budgeted machine hours in Dept. P1 75,000 30,000 1,05,000
(50,000×1.5 hrs.) (30,000×1 hr.)
Budgeted labour hours in Dept. P2 1,00,000 75,000 1,75,000
(50,000×2 hrs.) (30,000×2.5 hrs.)
2.
Product A Product B Total
Actual output (units) 4,000 3,000
Actual machine hours utilized in Dept. P1 6,100 4,150 10,250
Actual labour hours utilised in Dept. P2 8,200 7,400 15,600
3. Computation of actual overhead rates for each production department from actual data
Production Department Service Department
P1 P2 S1 S2
Actual factory overheads for the 2,50,000 2,25,000 80,000 60,000
month of Jan, 2020 (`)
Allocation of service Dept. S1’s costs to 40,000 40,000 (80,000) -
production Dept. P1 and P2 equally (`)
Allocation of service Dept. S2’s costs to 40,000 20,000 - (60,000)
production Dept. P1 and P2 in the ratio of 2:1 (‘)
Total 3,30,000 2,85,000 — —
Actual machine hours in Dept. P1 10,250 —
(working note 2)
Actual labour hours in Dept. P2 (working note 2) — 15,600
Actual machine/ labour hour rate (`) 32.20 18.27
4. Actual overheads absorbed (based on machine hours)
A : 6,100 hrs × ` 32.20 = (`) 1,96,420
B : 4,150 hrs × ` 32.20 = (`) 1,33,630
5. Actual overheads absorbed (based on labour hours)
A : 8,200 hrs × ` 18.27 = ` 1,49,814
B : 7,400 hrs × ` 18.27 = ` 1,35,198
Q-21 You are given the following information of the three machines of a manufacturing department of X
Ltd.:
Preliminary estimates of expenses (per annum)
Machines
Total (`)
A (`) B (`) C (`)
Depreciation 2,00,000 75,000 75,000 50,000
Spare parts 1,00,000 40,000 40,000 20,000
Power 4,00,000
Consumable stores 80,000 30,000 25,000 25,000
Insurance of machinery 80,000
Indirect labour 2,00,000
Building maintenance expenses 2,00,000
Annual interest on capital outlay 1,00,000 40,000 40,000 20,000
Monthly charge for rent and rates 20,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -115-
(B) Machine
Expenses:
Depreciation Direct 2,00,000 75,000 75,000 50,000
Spare parts Final estimates 1,32,250 46,000 57,500 28,750
Power K.W. rating 4,00,000 1,50,000 1,00,000 1,50,000
(3:2:3)
Consumable Direct 80,000 30,000 25,000 25,000
Stores
Total Machine expenses 8,12,250 3,01,000 2,57,500 2,53,750
Hourly Rate for Machine expenses 154.52 132.19 130.26
Total (A + B) 22,20,250 7,83,000 7,69,500 6,67,750
Machine Hour rate 401.95 395.02 342.79
Working Notes:
(i) Calculation of effective working hours:
No. of full off-days = No. of Sunday + No. of holidays
= 52 + 12 = 64 days
No. of half working days = 52 days – 2 holidays = 50 days
No. of full working days = 365 days – 64 days – 50 days = 251 days
Total working Hours = {(251 days × 8 hours) + (50 days × 4 hours)}
= 2,008 hours + 200= 2,208 hours.
Total effective hours = Total working hours × 90% - 2% for breakdown
= 2,208 hours × 90% - 2% (2,208 hours × 90%)
= 1,987.2 hours – 39.74 hours
= 1947.46 or Rounded up to 1948 hours.
(ii) Amount of spare parts is calculated as under:
A (`) B (`) C (`)
Preliminary estimates 40,000 40,000 20,000
Add: Increase in price @ 15% 6,000 6,000 3,000
46,000 46,000 23,000
Add: Increase in consumption “ 11,500 5,750
@ 25%
Estimated cost 46,0005 7,500 28,750
(iii) Amount of Indirect Labour is calculated as under:
(` )
Preliminary estimates 2,00,000
Add: Increase in wages @ 20% 40,000
2,40,000
(iv) Interest on capital outlay is a finance cost,therefore it has been excluded from the cost accounts.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -117-
Q-22 The following account balances and distribution of indirect charges are taken from the accounts of a
manufacturing concern for the year ending on 31st March, 2021:
Item Total Production DepartmentsService
Amount Departments
( `) X ( `) Y ( `) Z ( `) A ( `) B ( `)
Indirect Material 5,00,000 80,000 1,20,000 1,80,000 1,00,000 20,000
Indirect Labour 10,40,000 1,80,000 2,00,000 2,80,000 2,40,000 1,40,000
Supervisor’s Salary 3,84,000 - - 3,84,000 - -
Fuel & Heat 60,000
Power 7,20,000
Rent & Rates 6,00,000
Insurance of Assets 72,000
Canteen Charges 2,40,000
Depreciation 10,80,000
The following departmental data are also available:
Production Departments Service Departments
X Y Z A B
Area (Sq. ft.) 4,400 4,000 3,000 2,400 1,200
Capital Value of
Assets (‘) 40,00,000 60,00,000 50,00,000 10,00,000 20,00,000
Kilowatt Hours 3,500 4,000 3,000 1,500 -
Radiator Sections 20 40 60 50 30
No. of Employees 60 70 120 30 20
Expenses charged to the service departments are to be distributed to other departments by the
following percentages:
X Y Z A B
Department A (%) 30 30 20 - 20
Department B (%) 25 40 25 10 -
PREPARE an overhead distribution statement to show the total overheads of production departments
after re-apportioning service departments’ overhead by using simultaneous equation method. Show
all the calculations to the nearest rupee.
Ans. Primary Distribution of Overheads
Item Basis Total Production Departments Service
Amount Departments
(`) X (`) Y (`) Z (`) A (`) B (`)
Indirect Material Actual 5,00,000 80,000 1,20,000 1,80,000 1,00,000 20,000
Indirect Labour Actual 10,40,000 1,80,000 2,00,000 2,80,000 2,40,000 1,40,000
Supervisor’s Salary Actual 3,84,000 - - 3,84,000 - -
Fuel & Heat Radiator 60,000 6,000 12,000 18,000 15,000 9,000
Sections
{2:4:6:5:3}
Power Kilowatt Hours 7,20,000 2,10,000 2,40,000 1,80,000 90,000 -
{7:8:6:3:-}
Rent & Rates Area (Sq. ft.) 6,00,000 1,76,000 1,60,000 1,20,000 96,000 48,000
{22:20:15:12:6}
Insurance Capital Value 72,000 16,000 24,000 20,000 4,000 8,000
of Assets
{4:6:5:1:2}
Canteen Charges No. of 2,40,000 48,000 56,000 96,000 24,000 16,000
Employees
{6:7:12:3:2}
Depreciation Capital Value 10,80,000 2,40,000 3,60,000 3,00,000 60,000 1,20,000
of Assets
{4:6:5:1:2}
Total overheads 46,96,000 9,56,000 11,72,000 15,78,000 6,29,000 3,61,000
Re-distribution of Overheads of Service Department A and B
Total overheads of Service Departments may be distributed using simultaneous
equation method
Let, the total overheads of A = ‘a’ and the total overheads of B = ‘b’
a = 6,29,000 + 0.10 b (i)
or, 10a - b = 62,90,000 [(i) x10]
b = 3,61,000 + 0.20 a (ii)
or, -0.20a + b = 3,61,000
Solving equation (i) & (ii)
a = 6,78,673
Putting the value of ‘a’ in equation (ii), we get
b = 3,61,000 + 0.20 × 6,78,673
b = 4,96,735
Secondary Distribution of Overheads
Production Departments
X (`) Y (`) Z (`)
Total overhead as per primary distribution 9,56,000 11,72,000 15,78,000
Service Department A (80% of 6,78,673) (3:3:2) 2,03,602 2,03,602 1,35,734
Service Department B (90% of 4,96,735) (5:8:5) 1,24,184 1,98,694 1,24,184
Total 12,83,786 15,74,296 18,37,918
Q-23 A machine costing ` 10 lakhs, was purchased on 01-04-2021. The expected life of the machine is 10
years. At the end of this period its scrap value is likely to be ` 10,000. The total cost of all the machines
including new one was ` 90 lakhs.
The other information is given as follows:
(i) Working hours of the machine for the year was 4,200 including 200 non-productive hours.
(ii) Repairs and maintenance for the new machine during the year was ` 6,000.
(iii) Insurance Premium was paid for all the machine ` 9,000.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -119-
(iv) New machine consumes 8 units of electricity per hour, the rate per unit being ` 3.75
(v) The new machine occupies 1/10th area of the department. Rent of the department is ` 2,400 per
month.
(vi) Depreciation is charged on straight line basis.
COMPUTE machine hour rate for the new machine.
Ans. Computation of machine hour rate of new Machine
Total (`) Per hour (`)
A. Standing Charges
1
I. Insurance Premium ` 9,000 x 1,000
9
1
II. Rent ` 2,400 x 12 months 2,880
10
3,880 0.97*
B. Machine expenses
I. Repairs and Maintenance (` 6,000 4,000 hours) 1.50
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -121-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -123-
Q-26 PL Ltd. has three production departments P1, P2 and P3 and two service departments S1 and S2. The
following data are extracted from the records of the company for the month of October, 2020:
( `)
Rent and rates 12,50,000
General lighting 1,50,000
Indirect Wages 3,75,000
Power 5,00,000
Depreciation on machinery 10,00,000
Insurance of machinery 4,00,000
Other Information:
P1 P2 P3 S1 S2
Direct wages ( `) 7,50,000 5,00,000 7,50,000 3,75,000 1,25,000
Horse Power of Machines used 60 30 50 10 -
Cost of machinery ( `) 60,00,000 80,00,000 1,00,00,000 5,00,000 5,00,000
Floor space (Sq. ft) 2,000 2,500 3,000 2,000 500
Number of light points 10 15 20 10 5
Production hours worked 6,225 4,050 4,100 - -
Expenses of the service departments S1 and S2 are reapportioned as below:
P1 P2 P3 S1 S2
S1 20% 30% 40% - 10%
S2 40% 20% 30% 10%
Required:
(i) COMPUTE overhead absorption rate per production hour of each production department.
(ii) DETERMINE the total cost of product X which is processed for manufacture in department P1, P2
and P3 for 5 hours, 3 hours and 4 hours respectively, given that its direct material cost is ` 12,500
and direct labour cost is ` 7,500.
Ans. Primary Distribution Summary
Item of cost Basis of Total P1 P2 P3 S1 S2
apportionment ( `) ( `) ( `) ( `) ( `) ( `)
Direct wages Actual 5,00,000 — — — 3,75,000 1,25,000
Rent and Floor area 12,50,000 2,50,000 3,12,500 3,75,000 2,50,000 62,500
Rates (4 : 5 : 6 : 4 : 1)
General Light points 1,50,000 25,000 37,500 50,000 25,000 12,500
lighting (2 : 3 : 4 : 2 : 1)
Indirect wages Direct wages 3,75,000 1,12,500 75,000 1,12,500 56,250 18,750
(6 : 4 : 6 : 3 : 1)
Power Horse Power of 5,00,000 2,00,000 1,00,000 1,66,667 33,333 -
machines used
(6 : 3 : 5 : 1)
Depreciation of Value of machinery 10,00,000 2,40,000 3,20,000 4,00,000 20,000 20,000
machinery (12 : 16 : 20 : 1 : 1)
Insurance of Value of machinery 4,00,000 96,000 1,28,000 1,60,000 8,000 8,000
machinery (12 : 16 : 20 : 1 : 1)
41,75,000 9,23,500 9,73,000 12,64,167 7,67,583 2,46,750
Overheads of service cost centres
Let S1 be the overhead of service cost centre S1 and S2 be the overhead of service cost centre S2.
S1 = 7,67,583 + 0.10 S2
S2 = 2,46,750 + 0.10 S1
Substituting the value of S2 in S1 we get
S1 = 7,67,583 + 0.10 (2,46,750 + 0.10 S1)
S1 = 7,67,583 + 24,675 + 0.01 S1
0.99 S1 = 7,92,258
S1 = ` 8,00,260
S2 = 2,46,750 + 0.10 x 8,00,260
= ` 3,26,776
Secondary Distribution Summary
Particulars Total ( `) P1 ( `) P2 ( `) P3 ( `)
Allocated and Apportioned 31,60,667 9,23,500 9,73,000 12,64,167
over-heads as per primary
distribution
S1 8,00,260 1,60,052 2,40,078 3,20,104
S2 3,26,776 1,30,710 65,355 98,033
12,14,262 12,78,433 16,82,304
(i) Overhead rate per hour
P1 P2 P3
Total overheads cost ( `) 12,14,262 12,78,433 16,82,304
Production hours worked 6,225 4,050 4,100
Rate per hour ( `) 195.06 315.67 410.32
(ii) Cost of Product X
( `)
Direct material 12,500.00
Direct labour 7,500.00
Prime cost 20,000.00
Production on overheads
P1 5 hours x ` 195.06 = 975.30
P2 3 hours x ` 315.67 = 947.01
P3 4 hours x ` 410.32 = 1,641.28 3,563.59
Factory cost 23,563.59
Q-27 A manufacturing unit has purchased and installed a new machine at a cost of ` 24,90,000 to its fleet of
5 existing machines. The new machine has an estimated life of 12 years and is expected to realise ‘
90,000 as scrap value at the end of its working life.
Other relevant data are as follows:
(i) Budgeted working hours are 2,496 based on 8 hours per day for 312 days. Plant maintenance work
is carried out on weekends when production is totally halted. The estimated maintenance hours
are 416. During the production hours machine set -up and change over works are carried out.
During the set-up hours no production is done.
A total 312 hours are required for machine set-ups and change overs.
(ii) An estimated cost of maintenance of the machine is ` 2,40,000 p.a.
(iii) The machine requires a component to be replaced every week at a cost of ` 2,400.
(iv) There are three operators to control the operations of all the 6 machines. Each operator is paid `
30,000 per month plus 20% fringe benefits.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -125-
(v) Electricity: During the production hours including set -up hours, the machine consumes 60 units
per hour. During the maintenance the machine consumes only 10 units per hour. Rate of electricity
per unit of consumption is ` 6.
(vi) Departmental and general works overhead allocated to the operation during last year was `
5,00,000. During the current year it is estimated to increase by 10%.
Required:
COMPUTE the machine hour rate.
Ans. Working Note:
1. Effective machine hour:
= Budgeted working hours – Machine Set-up time
= 2,496 hours – 312 hours = 2,184 hours.
2. Operators’ salary per annum:
Salary (3 operators × ` 30,000 × 12 months) ` 10,80,000
Add: Fringe benefits (20% of ` 10,80,000) ` 2,16,000
` 12,96,000
3. Depreciation per annum
`24,900 -`90,000
= ` 2,00,000
12 years
Computation of Machine hour Rate
Amount Amount per
p.a. ( `) hour ( `)
Standing charges
Electricity:
During working hours (2,496 hours × 60 units x ‘6) 8,98,560 411.43
During maintenance hours (416 hours × 10 units x ‘6) 24,960 11.43
Component replacement cost (2,400 × 52 weeks) 1,24,800 57.14
Machine maintenance cost 2,40,000 109.89
(B) 14,88,320 681.47
Machine Hour Rate (A + B) 822.34
Q-28 Specify the types of Responsibility centres under the following situations:
(i) Purchase of bonds, stocks, or real estate property.
(ii) Ticket counter in a Railway station.
(iii) Decentralized branches of an organization.
(iv) Maharana, Navratna and Miniratna public sector undertaking (PSU) of Central Government.
(v) Sales Department of an organization.
Ans.
Particulars Types of
Responsibility Centre
(i) Purchase of bonds, stocks, or real estate property. Investment Centre
(ii) Ticket counter in a Railway station. Revenue Centre
(iii) Decentralized branches of an organization. Profit Centre
(iv) Maharatna, Navratna and Miniratna public sector
undertaking (PSU) of Central Government. Investment Centre
(v) Sales Department of an organization. Revenue Centre
Q-29 Explain Blanket Overhead Rate and Departmental Overhead Rate. How they are calculated? State the
conditions required for the application of Blanket Overhead Rate.
Ans. Blanket Overhead Rate: Blanket overhead rate refers to the computation of one single overhead rate
for the whole factory.
This overhead rate is computed as follows:
Blanket Rate = Total overheads for the factory
Total number of units of base for the factory
Departmental Overhead Rate: It refers to the computation of one single overhead rate for a particular
production unit or department.
This overhead rate is determined by the following formula:
Departmental overhead Rate = Overheads of department or cost centre
Corresponding base
Conditions required for the Application of Blanket Overhead:
A blanket rate should be applied in the following cases:
(1) Where only one major product is being produced.
(2) Where several products are produced, but
(a) All products pass through all departments; and
(b) All products are processed for the same length of time in each department.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -127-
Q-30 Pretz Ltd. is a manufacturing company having two production departments, ‘A’ & ‘B’ and two service
departments ‘X’ & ‘Y’. The following is the budget for March, 2022:
Total (`) A (`) B (`) X (`) Y (`)
Direct material 2,00,000 4,00,000 4,00,000 2,00,000
Direct wages 10,00,000 4,00,000 2,00,000 4,00,000
Factory rent 9,00,000
Power (Machine) 5,10,000
Depreciation 2,00,000
General Lighting 3,00,000
Perquisites 4,00,000
Additional information:
Area (Sq. ft.) 500 250 250 500
Capital value of assets (‘ lakhs) 40 80 20 20
Light Points 10 20 10 10
Machine hours 1,000 2,000 1,000 1,000
Horse power of machines 50 40 15 25
A technical assessment of the apportionment of expenses of service departments is as under:
A B X Y
Service Dept. ‘X’ (%) 55 25 – 20
Service Dept. ‘Y’ (%) 60 35 5 –
You are required to:
(a) PREPARE a statement showing distribution of overheads to various departments.
(b) PREPARE a statement showing re-distribution of service departments expenses to production
departments using-
(i) Simultaneous equation method
(ii) Trial and error method
(iii) Repeated Distribution Method.
Ans.
(a) Primary Distribution of Overheads
Basis Total (`) A (`) B (`) X (`) Y (`)
Direct materials Direct 6,00,000 – – 4,00,000 2,00,000
Direct wages Direct 6,00,000 – – 2,00,000 4,00,000
Factory rent Area 9,00,000 3,00,000 1,50,000 1,50,000 3,00,000
(2:1:1:2)
Power H.P. × Machine 5,10,000 1,50,000 2,40,000 45,000 75,000
(Machine) Hrs.
(10:16:3:5)*
Depreciation Capital value 2,00,000 50,000 1,00,000 25,000 25,000
(2:4:1:1)
General Light Points 3,00,000 60,000 1,20,000 60,000 60,000
Lighting
(1:2:1:1)
Perquisites Direct Wages 4,00,000 2,00,000 80,000 40,000 80,000
(5:2:1:2)
35,10,000 7,60,000 6,90,000 9,20,000 11,40,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -129-
(ii) Accounting treatment of under absorption of production overheads: It is given in the statement of the
question that 62,000 units (50,000 sold + 12,000 closing stock – 0 opening stock) were completely
finished and 20,000 units were 65% complete, 40% of the under-absorbed overheads were due to
factory inefficiency and the rest were attributable to increase in cost of indirect materials and indirect
labour.
(`)
1. (40% of `2,50,000) i.e. ` 1,00,000 of under – absorbed overheads were 1,00,000
due to factory inefficiency. This being abnormal, should be debited to the
Costing Profit and Loss A/c
2. Balance (60% of ` 2,50,000) i.e. ` 1,50,000 of under – absorbed 1,50,000
overheads should be distributed over work-in-progress, finished
goods and cost of sales by using supplementary rate
Total under-absorbed overheads 2,50,000
Apportionment of unabsorbed overheads of `1,50,000 over work-in-progress, finished goods and cost
of sales.
Equivalent (` )
Completed units
Work-in-progress (13,000 units × ` 2)
(Refer to Working Note) 20000 * 65% = 13,000 26,000
Finished goods (12,000 units × ` 2) 12,000 24,000
Cost of sales (50,000 units × ` 2) 50,000 1,00,000
75,000 1,50,000
Journal entry:
Work-in-progress control A/c Dr. ` 26,000
Finished goods control A/c Dr. ` 24,000
Cost of Sales A/c Dr. ` 1,00,000
Costing Profit & Loss A/c Dr. ` 1,00,000
To Overhead control A/c ` 2,50,000
Working Note:
`1, 50, 000
Supplementary overhead absorption rate = = ` 2 per unit
75, 000 units
Q-32 M/s Avyukt Automobile Parts has four identical machines in its factory. Cost of each machine is `
5,00,000 with expected scrap value of 10% at the end of its effective life (9 years). The expected annual
running hours of machine is expected to run for 2,200 hours. The other details in respect of the machine
shop are:
(I) Factory Rent ` 5,000 per month
(II) Lighting of Factory ` 3,000 per month
(III) Operator Wages (Two operators and each operator is in charge of two machines)
`10,000 per month (per Operator)
(IV) Fixed repairs and maintenance charges per machine ` 2,000 per quarter
(V) Insurance premium for the machine (Annual) 3% of cost
(VI) Forman’s salary (Devoted 1/6th of his time to this factory)
` 2,500 per month
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -131-
Annual Depreciation =
= ` 50,000
Q-33 PM Ltd. has three Production Departments P1, P2, P3 and two Service Departments S1 and S2 details
pertaining to which are as under:
P1 P2 P3 S1 S2
Direct wages (`) 60,000 40,000 60,000 30,000 3,900
Working hours 3,070 4,475 2,419 - -
Value of machines (`) 12,00,000 16,00,000 20,00,000 1,00,000 1,00,000
H.P. of machines 60 30 50 10 -
Light points 10 15 20 10 5
Floor space (sq. ft.) 2,000 2,500 3,000 2,000 500
The following figures extracted from the accounting records are relevant:
(` )
Rent and Rates 1,00,000
General Lighting 12,000
Indirect Wages 38,780
Power 30,000
Depreciation on Machines 2,00,000
Sundries 1,93,900
The expenses of the service departments are allocated as under:
P1 P2 P3 S1 S2
S1 20% 30% 40% - 10%
S2 40% 20% 30% 10% -
DETERMINE the total cost of product X which is processed for manufacture in Departments P1, P2 and P3
for 4, 5 and 3 hours respectively, given that its Direct Material Cost is ‘ 1,000 and Direct Labour Cost is ‘
600.
Ans. Statement Showing Distribution of Overheads of PM Ltd.
Particulars Basis Total Production Service
Departments Departments
P1 P2 P3 S1 S2
(`) (`) (`) (`) (`) (`)
Direct wages Actual 33,900 - - - 30,000 3,900
Rent & rates Area 1,00,000 20,000 25,000 30,000 20,000 5,000
General
lighting Light points 12,000 2,000 3,000 4,000 2,000 1,000
Indirect
wages Direct wages 38,780 12,000 8,000 12,000 6,000 780
Power H.P. 30,000 12,000 6,000 10,000 2,000 -
Depreciation
of machines Value of 2,00,000 48,000 64,000 80,000 4,000 4,000
machines
Sundries Direct 1,93,900 60,000 40,000 60,000 30,000 3,900
wages
6,08,580 1,54,000 1,46,000 1,96,000 94,000 18,580
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -133-
---0---0---
CHAPTER- 5
ACTIVITY BASED COSTING
Q-1 Following are the data of three product lines of a departmental store for the year 2019-20:
Soft drinks Fresh produce Packaged food
Revenues ` 39,67,500 ` 1,05,03,000 ` 60,49,500
Cost of goods sold ` 30,00,000 ` 75,00,000 ` 45,00,000
Cost of bottles returned ` 60,000 `0 `0
Number of purchase orders placed 360 840 360
Number of deliveries received 300 2,190 660
Hours of shelf-stocking time 540 5,400 2,700
Items sold 1,26,000 11,04,000 3,06,000
Additional information related with the store are as follows:
Activity Description of activity Total Cost Cost-allocation base
Bottles returns Returning of empty bottles ` 60,000 Direct tracing to soft drink line
Ordering Placing of orders for purchases ` 7,80,000 1,560 purchase orders
Delivery Physical delivery and
receipt of goods ` 12,60,000 3,150 deliveries
Shelf stocking Stocking of goods on store
shelves and on-going restocking ` 8,64,000 8,640 hours of shelf-stocking
time
Customer Assistance provided to
Support customers including check-out ` 15,36,000 15,36,000 items sold
Required:
CALCULATE the total cost and operating income using Activity Based Costing method.
Ans. Working notes:
(i) Total support cost:
(` )
Bottles returns 60,000
Ordering 7,80,000
Delivery 12,60,000
Shelf stocking 8,64,000
Customer support 15,36,000
Total support cost 45,00,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -135-
Out of total overhead costs, 30% related to machine set-ups, 30% related to customer order processing
and customer complaint management, while the balance proportion related to material ordering.
Required:
(i) COMPUTE overhead cost per unit using activity based costing method.
(ii) DETERMINE the selling price of each product based on activity-based costing withthe same profit
mark-up on cost.
Ans. Workings:
Total labour hours and overhead cost:
Particulars Product X Product Y Product Z Total
Production units 45,000 52,500 30,000 1,27,500
Hour per unit 3 5 7
Total hours 1,35,000 2,62,500 2,10,000 6,07,500
Rate per hour ` 80.00
Total overhead ` 4,86,00,000
Cost per activity and driver
Activity Machine Customer Customer Total
Set-up order complaint
processing management
Total overhead (`) 1,45,80,000 1,45,80,000 1,94,40,000 4,86,00,000
No. of drivers 600 2,400 8,000
Cost per driver (`) 24,300 6,075 2,430
(i) Computation of Overhead cost per unit:
Particulars Product X Product Y Product Z
No. of machine set-ups 40 160 400
Cost per driver (`) 24,300 24,300 24,300
Total Machine set-up cost (`) [A] 9,72,000 38,88,000 97,20,000
No. of purchase orders 400 800 1,200
Cost per driver (`) 6,075 6,075 6,075
Total order processing cost (`)[B] 24,30,000 48,60,000 72,90,000
No. of customers 1,000 2,200 4,800
Cost per driver (`) 2,430 2,430 2,430
Total customer complaint
management cost (`) [C] 24,30,000 53,46,000 1,16,64,000
Total Overhead cost (`) [A+B+C] 58,32,000 1,40,94,000 2,86,74,000
Production units 45,000 52,500 30,000
Cost per unit (`) 129.60 268.46 955.80
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -137-
Ans.
(i) Statement of Operating income and Operating income as a percentage of revenues for each product
line
(When support costs are allocated to product lines on the basis of cost of goods sold of each product)
Soft Fresh Packaged Total
Drinks Produce Foods
(`) (`) (`) (`)
Revenues: (A) 39,67,500 1,05,03,000 60,49,500 2,05,20,000
Cost of Goods sold (COGS): (B) 30,00,000 75,00,000 45,00,000 1,50,00,000
Support cost (30% of COGS): (C)
(Refer working notes) 9,00,000 22,50,000 13,50,000 45,00,000
Total cost: (D) = {(B) + (C)} 39,00,000 97,50,000 58,50,000 1,95,00,000
Operating income: E= {(A)-(D)} 67,500 7,53,000 1,99,500 10,20,000
Operating income as a percentage
of revenues: (E/A) × 100) 1.70% 7.17% 3.30% 4.97%
Working notes:
1. Total support cost:
(`)
Bottles returns 60,000
Ordering 7,80,000
Delivery 12,60,000
Shelf stocking 8,64,000
Customer support 15,36,000
Total support cost 45,00,000
2. Percentage of support cost to cost of goods sold (COGS):
` 45,00,000
100 = 30%
`1, 50,00,000
3. Cost for each activity cost driver:
Activity Total cost (`) Cost allocation base Cost driver rate
(1) (2) (3) (4) = [(2) ÷ (3)]
Ordering 7,80,000 1,560 purchase orders `500 per purchase order
Delivery 12,60,000 3,150 deliveries `400 per delivery
Shelf-stocking 8,64,000 8,640 hours `100 per stocking hour
Customer support 15,36,000 15,36,000 items sold `1 per item sold
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -139-
(ii) Statement of Operating income and Operating income as a percentage of revenues for each product
line
(When support costs are allocated to product lines using an activity-based costing system)
Soft Fresh Packaged Total
drinks (`) Produce (`) Food (`) (`)
Revenues: (A) 39,67,500 1,05,03,000 60,49,500 2,05,20,000
Cost & Goods sold 30,00,000 75,00,000 45,00,000 1,50,00,000
Bottle return costs 60,000 0 0 60,000
Ordering cost* 1,80,000 4,20,000 1,80,000 7,80,000
(360:840:360)
Delivery cost* 1,20,000 8,76,000 2,64,000 12,60,000
(300:2190:660)
Shelf stocking cost* 54,000 5,40,000 2,70,000 8,64,000
(540:5400:2700)
Customer Support cost* 1,26,000 11,04,000 3,06,000 15,36,000
(1,26,000:11,04,000:3,06,000)
Total cost: (B) 35,40,000 1,04,40,000 55,20,000 1,95,00,000
Operating income C: {(A)- (B)} 4,27,500 63,000 5,29,500 10,20,000
Operating income as a % of revenues 10.78% 0.60% 8.75% 4.97%
* Refer to working note 3
Q-4 Family Store wants information about the profitability of individual product lines: Soft drinks, Fresh
produce and Packaged food. Family store provides the following data for the year 20X7-X8 for each
product line:
Soft drinks Fresh produce Packaged food
Revenues ` 39,67,500 ` 1,05,03,000 ` 60,49,500
Cost of goods sold ` 30,00,000 ` 75,00,000 ` 45,00,000
Cost of bottles returned ` 60,000 `0 `0
Number of purchase orders placed 360 840 360
Number of deliveries received 300 2,190 660
Hours of shelf-stocking time 540 5,400 2,700
Items sold 1,26,000 11,04,000 3,06,000
Family store also provides the following information for the year 20X7-X8:
Activity Description of activity Total Cost Cost-allocation base
Bottles returns Returning of empty bottles ` 60,000 Direct tracing to soft
drink line
Ordering Placing of orders for purchases ` 7,80,000 1,560 purchase orders
Delivery Physical delivery and receipt of goods ` 12,60,000 3,150 deliveries
Shelf stocking Stocking of goods on store shelves ` 8,64,000 8,640 hours of shelf-
and on-going restocking stocking time
Customer Assistance provided to ` 15,36,000 15,36,000 items sold
Support customers including check-out
Required:
(i) Family store currently allocates support cost (all cost other than cost of goods sold) to product lines on
the basis of cost of goods sold of each product line. CALCULATE the operating income and operating
income as a % of revenues for each product line.
(ii) If Family Store allocates support costs (all costs other than cost of goods sold) to product lines using and
activity based costing system, CALCULATE the operating income and operating income as a % of revenues
for each product line.
Ans.
(i) Statement of Operating income and Operating income as a percentage of revenues for each product
line
(When support costs are allocated to product lines on the basis of cost of goods sold of each product)
Soft Fresh Packaged Total
Drinks Produce Foods
(`) (`) (`) (`)
Revenues: (A) 39,67,500 1,05,03,000 60,49,500 2,05,20,000
Cost of Goods sold (COGS): (B) 30,00,000 75,00,000 45,00,000 1,50,00,000
Support cost (30% of COGS): (C)
(Refer working notes) 9,00,000 22,50,000 13,50,000 45,00,000
Total cost: (D) = {(B) + (C)} 39,00,000 97,50,000 58,50,000 1,95,00,000
Operating income: E= {(A)-(D)} 67,500 7,53,000 1,99,500 10,20,000
Operating income as a percentage
of revenues: (E/A) × 100) 1.70% 7.17% 3.30% 4.97%
Working notes:
1. Total support cost:
(`)
Bottles returns 60,000
Ordering 7,80,000
Delivery 12,60,000
Shelf stocking 8,64,000
Customer support 15,36,000
Total support cost 45,00,000
2. Percentage of support cost to cost of goods sold (COGS):
Total support cost
= 100
Total cost of goods sold
` 45,00,000
100 = 30%
`1, 50,00,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -141-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -143-
Q-7 PQR Ltd has decided to analyse the profitability of it’s five new customers. It buys soft drink bottles in
cases at ` 45 per case and sells them to retail customers at a list price of ? 54 per case. The data
pertaining to five customers are given below :
Particulars Customers
A B C D E
Number of Cases Sold 9360 14200 62000 38000 9800
List Selling Price ` 54 54 54 54 54
Actual Selling Price ` 54 53.40 49 50.20 48.60
Number of Purchase Orders %30 50 60 50 60
Number of Customers visits 4 6 12 4 6
Number of Deliveries 20 60 120 80 40
Kilometers travelled per delivery 40 12 10 20 60
Number ofexpediate Deliveries 0 0 0 0 2
It’s five activities and their cost drivers are :
Activity Cost Driver
Order taking ` 200 per purchase order
Customer visits ` 300 per each visit
Deliveries ` 4.00 per delivery km travelled
Product Handling ` 2.00 per case sold
Expedited deliveries ` 100 per each such delivery
You are required to :
(i) Compute the customer level operating income of each of five retail customers by using the Cost
Driver rates.
(ii) Examine the results to give your comments on Customer ‘D’ in comparison with Customer ‘C and
on Customer ‘E’ in comparison with Customer ‘A’.
Ans. Working note:
Computation of revenues (at listed price), discount, cost of goods sold and customer level operating
activities costs:
Particular Customers
A B C D E
Cases sold: (a) 9,360 14,200 62,000 38,000 9,800
Revenues (at listed price)
(‘): (b) {(a) × ` 54)} 5,05,440 7,66,800 33,48,000 20,52,000 5,29,200
Discount (`): (c) {(a) × - 8,520 3,10,000 1,44,400 52,920
Discount per case} (14,200 (62,000 (38,000 (9,800
cases × ` 0.6) cases × ` 5) cases × cases ×
` 3.80) ` 5.40)
Cost of goods sold (`): (d) {(a) × ` 45} 4,21,200 6,39,000 27,90,000 17,10,000 4,41000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -145-
Q-8 MNO Ltd. manufactures two types of equipment A and B and absorbs overheads on the basis of direct
labour hours. The budgeted overheads and direct labour hours for the month of March 2019 are `
15,00,000 and 25,000 hours respectively. The information about the company’s products is as follows:
Equipment
A B
Budgeted Production Volume 3,200 units 3,850 units
Direct Material Cost ` 350 per unit ` 400 per unit
Direct Labour Cost
A: 3 hours @ ` 120 per hour ` 360
B: 4 hours @ ` 120 per hour ` 480
Overheads of ` 15,00,000 can be identified with the following three major activities:
Order Processing : ` 3,00,000
Machine Processing : ` 10,00,000
Product Inspection : ` 2,00,000
These activities are driven by the number of orders processed, machine hours worked and
inspection hours respectively. The data relevant to these activities is as follows:
Orders processed Machine hours worked Inspection hours
A 400 22,500 5,000
B 200 27,500 15,000
Total 600 50,000 20,000
Required :
(i) Prepare a statement showing the manufacturing cost per unit of each product usingthe absorption
costing method assuming the budgeted manufacturing volume isattained.
(ii) Determine cost driver rates and prepare a statement showing the manufacturing cost per unit of
each product using activity based costing, assuming the budgeted manufacturing volume is
attained.
(iii) MNO Ltd.’s selling prices are based heavily on cost. By using direct labour hours as an application
base, calculate the amount of cost distortion (under costed or over costed) for each equipment.
Ans.
(i) Overheads application base: Direct labour hours
Equipment Equipment
A (`) B (`)
Direct material cost 350 400
Direct labour cost 360 480
Overheads* 180 240
890 1120
Budgeted overheads `15,00,000
*Pre-determined rate = = = ` 60
Budgeted direct labour hours 25,000 hours
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -147-
The company has produced a batch of 15000 units and has incurred ` 26,38,700 and ` 3,75,200 on
materials and wages respectively.
The usage of activities of the said batch are as follows:
Materials orders 48 orders
Maintenance hours 810 hours
No. of set-ups 40
No. of inspections 5
You are required to:
(i) find out cost of product per unit on absorption costing basis for the said batch.
(ii) determine cost driver rate, total cost and cost per unit of output of the said batch on the basis of
activity based costing.
Ans. Working Note:
51,79,300
Overhead Absorption Rate = ×100 = 17.18%
3,01,39,000
17,30,000
Maintenance x 810 1,54,328
9,080
6,84,500
Setup 2,250 x 40 12,169
5,14,800
Quality Control x 25 4,749
2,710
Unit 15,000
Ans.
(i) Statement Showing Overhead Cost per unit “Traditional Method”
Gel Pen (`) Ball Pen (`)
Units 5,500 24,000
Overheads (`)
(Refer to W.N.) 4,80,000 10,80,000
(20 x 24,000 hrs.) (20 x 54,000 hrs.)
Overhead Rate per 87.27 45
unit (`) (` 4,80,000 / 5,500 units) (` 10,80,000 /24,000 units)
Working Notes:
Overhead Rate per Machine Hour
= Total Overhead incurred by the Company
Total Machine Hours
= 4,75,020+ 5,79,988+ 5,04,992
24,000 hours + 54,000 hours
15,60,000
=
78,000 hours
= ` 20 per machine hour
(ii) Statement Showing “Activity Based Overhead Cost”
Activity Cost Cost Driver Ratio Total Gel Pen Ball Pen
Pool Amount (` ) (` )
(` )
Volume Machine 24:54 4,75,020 1,46,160 3,28,860
Related hours
Activity Costs
Setup Related No. of Setups 30:56 5,79,988 2,02,321 3,77,667
Costs
Purchase No. of 240:448 5,04,992 1,76,160 3,28,832
Related Costs Purchase
Orders
Total Cost 5,24,641 10,35,359
Output (units) 5,500 24,000
Unit Cost (Overheads) 95.39 43.13
(iii)
Gel Pen Ball Pen
(`) (`)
Overheads Cost per unit (`) (Traditional Method) 87.27 45
Overheads Cost per unit (`) (ABC) 95.39 43.13
Difference per unit -8.12 +1.87
(Volume related activity cost, set up related costs and purchase related cost can also be calculated
under Activity Base Costing using Cost driver rate. However, there will be no changes in the final
answer.)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -151-
Q-12 Linex Limited manufactures three products P, Q and R which are similar in nature and are usually
produced in production runs of 100 units. Product P and R require both machine hours and assembly
hours, whereas product Q requires only machine hours. T he overheads incurred by the company
during the first quarter are as under:
`
Machine Department expenses…………………........................ 18,48,000
Assembly Department expenses…………………………………. 6,72,000
Setup costs…………………………………………………………. 90,000
Stores receiving cost………………………………………………. 1,20,000
Order processing and dispatch…………………………………… 1,80,000
Inspect and Quality control cost………………………………… 36,000
The date related to the three products during the period are as under:
P Q R
Units produced and sold 15,000 12,000 18,000
Machine hours worked 30,000 hrs. 48,000 hrs. 54,000 hrs.
Assembly hours worked (direct labour hours) 15,000 hrs. - 27,000 hrs.
Customers’ orders executed (in numbers) 1,250 1,000 1,500
Number of requisitions raised on the stores 40 30 50
Required
PREPARE a statement showing details of overhead costs allocated to each product type using activity based
costing.
Ans. Calculation of “Activity Rate”
Cost Pool Cost (Rs.) Cost Driver Cost Driver Rate
[A] [B] ( Rs.)
[C] = [A]÷[B]
Machine Department Expenses 18,48,000 Machine Hours (1,32,000 hrs.) 14.00
Assembly Department Expenses 6,72,000 Assembly Hours (42,000 hrs.) 16.00
Setup Cost 90,000 No. of Production Runs (450*) 200.00
Stores Receiving Cost 1,20,000 No. of Requisition s Raised on
the Stores (120) 1,000.00
Order Processing and Dispatch 1,80,000 No. of Customers Orders 48.00
Executed (3,750)
Inspectio n and Quality Control Cost 36,000 No. of Production Runs (450*) 80.00
Total (Rs.) 29,46,000
*Number of Production Run is 450 (150 + 120 + 180)
Statement Showing “Overheads Allocation”
Particulars of Cost Cost Driver P Q R Total
Machine Machine Hours 4,20,000 6,72,000 7,56,000 18,48,000
Department (30,000 × Rs.14) (48,000 × Rs.14) (54,000 × Rs.14)
Expenses
Assembly Assembly Hours 2,40,000 - -- 4,32,000 6,72,000
Department (15,000 × Rs.16) (27,000 × Rs.16)
Expenses
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -153-
(ii) If Asian Mfg. Co. allocates store support costs (all costs other than the cost of goods sold) to the
product lines on the basis of ABC system, CALCULATE the operating income and operating income
as the percentage of revenue of each product line.
(iii) SHOW a comparison statement.
Ans.(a) (i) Absorption Costing System
Operating Income-
Particulars Lemon Grapes Papaya Total
Revenue 79,350 2,10,060 1,20,990 4,10,400
Less: Cost of Goods Sold 60,000 1,50,000 90,000 3,00,000
Less: Store Support Cost 18,000 45,000 27,000 90,000
Operating Income 1,350 15,060 3,990 20,400
Operating Income (%) 1.70 7.17 3.30 4.97
(ii) ABC System
Overhead Allocation Rate-
Activity Total Costs (Rs.) Quantity of Cost Overhead
Allocation Base Allocation Rate (Rs.)
Ordering 15,600 156 Purchase Orders 100.00
Delivery 25,200 315 Delivering Orders 80.00
Shelf Stocking 17,280 864 Self Stocking Hours 20.00
Customer Support 30,720 1,53,600 Items Sold 0.20
Store Support Cost-
Particulars Cost Driver Lemon Grapes Papaya Total
Bottle Returns Direct 1,200 0 0 1,200
Ordering Purchase Orders 3,600 8,400 3,600 15,600
Delivery Deliveries 2,400 17,520 5,280 25,200
Self -Stocking Hours of time 1,080 10,800 5,400 17,280
Customer Support Items Sold 2,520 22,080 6,120 30,720
Grand Total 10,800 58,800 20,400 90,000
Operating Income-
Particulars Lemon Grapes Papaya Total
Revenue 79,350 2,10,060 1,20,990 410,400
Less: Cost of Goods Sold 60,000 1,50,000 90,000 300,000
Less: Store Support Cost 10,800 58,800 20,400 90,000
Operating Income 8,550 1,260 10,590 20,400
Operating Income (%) 10.78 0.60 8.75 4.97
(iii) Comparison
Particulars Lemon Grapes Papaya Total
Under Traditional Costing System 1.70% 7.17% 3.30% 4.97%
Under ABC System 10.78% 0.60% 8.75% 4.97%
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -155-
Q-15 Woolmark Ltd. manufactures three types of products namely P, Q and R. The data relating to a period
are as under:
Particulars P Q R
Machine hours per unit 10 18 14
Direct Labour hours per unit @ Rs. 20 4 12 8
Direct Material per unit (Rs.) 90 80 120
Production (units) 3,000 5,000 20,000
Currently the company uses traditional costing method and absorbs all production overheads on the
basis of machine hours. The machine hour rate of overheads is Rs. 6 per hour.
The company proposes to use activity based costing system and the activity analysis is as under:
Particulars P Q R
Batch size (units) 150 500 1,000
Number of purchase orders per batch 3 10 8
Number of inspections per batch 5 4 3
The total production overheads are analysed as under:
Machine set up costs 20%
Machine operation costs 30%
Inspection costs 40%
Material procurement related costs 10%
Required:
(i) Calculate the cost per unit of each product using traditional method of absorbing all production
overheads on the basis of machine hours.
(ii) Calculate the cost per unit of each product using activity based costing principles.
Ans.
(i) Statement Showing “Cost per unit - Traditional Method”
Particulars of Costs P Q R
(`) (`) (`)
Direct Materials 90 80 120
Direct Labour [(4, 12, 8 hours)x ` 20] 80 240 160
Production Overheads [(10, 18, 14 hours) x ` 6] 60 108 84
Cost per unit 230 428 364
(ii) Statement Showing “Cost per unit - Activity Based Costing”
Products P Q R
Production (units) 3,000 5,000 20,000
(`) (`) (`)
Direct Materials (90, 80, 120) 2,70,000 4,00,000 24,00,000
Direct Labour (80, 240, 160) 2,40,000 12,00,000 32,00,000
Machine Related Costs @ ` 1.80 per hour
(30,000, 90,000, 2,80,000) 54,000 1,62,000 5,04,000
Setup Costs @ ` 9,600 per setup (20, 10, 20) 1,92,000 96,000 1,92,000
Inspection Costs @ ` 4,800 per inspection (100, 40, 60) 4,80,000 1,92,000 2,88,000
Purchase Related Costs @ ` 750 per purchase (60, 100, 160) 45,000 75,000 1,20,000
Total Costs 12,81,000 21,25,000 67,04,000
Cost per unit(Total Cost Units) 427.00 425.00 335.20
Workings
Number of Batches, Purchase Orders, and Inspections-
Particulars P Q R Total
A. Production (units) 3,000 5,000 20,000
B. Batch Size (units) 150 500 1,000
C. Number of Batches [A B] 20 10 20 50
D. Number of Purchase Order per batch 3 10 8
E. Total Purchase Orders [C x D] 60 100 160 320
F. Number of Inspections per batch 5 4 3
G. Total Inspections [C x F] 100 40 60 200
Total Machine Hours-
Particulars P Q R
A. Machine Hours per unit 10 18 14
B. Production (units) 3,000 5,000 20,000
C. Total Machine Hours [A x B] 30,000 90,000 2,80,000
Total Machine Hours = 4,00,000
Total Production Overheads -
= 4,00,000 hrs. x Rs. 6 = ` 24,00,000
Cost Driver Rates -
Cost Pool % Overheads Cost Driver Cost Driver Rate
(`) (Units) (`)
Setup 20% 4,80,000 50 9,600 per Setup
Inspection 40% 9,60,000 200 4,800 per Inspection
Purchases 10% 2,40,000 320 750 per Purchase
Machine Hours 30% 7,20,000 4,00,000 1.80 per Machine Hour
Q-16 Discuss the requirements of implementing Activity Based Costing.
Ans. A number of distinct practical stages are required in the ABC implementation which are given as
below:
(1) Staff Training: The co-operation of the workforce is critical to the successful implementation of
ABC. Staff training should be done to create an awareness of the purpose of ABC.
(2) Process Specification: Informal, but structured, interviews with key members of personnel will
identify the different stages of the production process, the commitment of resources to each,
processing times and bottlenecks.
(3) Activity Definition: Early activity should be clearly defined the problem must be kept manageable
at this stage, despite the possibility of information overload from new data, much of which is in
need of codification.
(4) Activity Driver Selection: Cost driver for each activity shall be selected.
(5) Assigning Cost: A single representative activity driver can be used to assign costs from the activity
pools to the cost objects.
Q-17 BABYSOFT is a global brand created by Bio-organic Ltd. The company manufactures three range of
beauty soaps i.e. BABYSOFT- Gold, BABYSOFT- Pearl, and BABYSOFT- Diamond.
The budgeted costs and production for the month of December, 2019 are as follows:
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -157-
Unit Costs:
BABYSOFT- Gold BABYSOFT- Pearl BABYSOFT- Diamond
(`) (`) (`)
Direct Costs:
- Direct Labour 5.00 6.67 10.00
10 x 30 10 x 40 10 x 60
60 60 60
-
Direct Material 167.50 215.50 248.50
(Refer working note1)
Production Overhead: 16.50 22.00 33.00
33 x 30 33 x 40 33 x 30
60 60 60
60 60 60
Total unit costs 189.00 244.17 291.50
Number of units 4,000 3,000 2,000
Total costs 7,56,000 7,32,510 5,83,000
Working note-1
Calculation of Direct material cost
BABYSOFT- Gold BABYSOFT- Pearl BABYSOFT- Diamond
(`) (`) (`)
Essential oils 120.00 165.00 195.00
200 x 60 300 x 55 300 x 65
100 100 100
Cocoa Butter 40.00 40.00 40.00
200 x 20 200 x 20 200 x 20
100 100 100
Filtered water 4.50 4.50 4.50
15 x 30 15 x 30 15 x 30
100 100 100
Chemicals 3.00 6.00 9.00
30 x 10 50 x 12 60 x 15
100 100 100
Total costs 167.50 215.50 248.50
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -159-
Q-18 KD Ltd. is following Activity based costing. Budgeted overheads, cost drivers and volume are as follows:
Cost pool Budgeted Cost driver Budgeted
overheads (`) volume
Material procurement 18,42,000 No. or orders 1,200
Material handling 8,50,000 No. of movement 1,240
Maintenance 24,56,000 Maintenance hours 17,550
Set-up 9,12,000 No. of set-ups 1,450
Quality control 4,42,000 No. of inspection 1,820
The company has produced a batch of 7,600 units, its material cost was `24,62,000 and wages ` 4,68,500.
Usage activities of the said batch are as follows:
Material orders 56
Material movements 84
Maintenance hours 1,420 hours
Set-ups 60
No. of inspections 18
Required:
(i) CALCULATE cost driver rates.
(ii) CALCULATE the total and unit cost for the batch.
Ans.(i) Calculation of cost driver rate:
Cost pool Budgeted Cost driver Cost driver rate
overheads (`) (` )
Material procurement 18,42,000 1,200 1,535.00
Material handling 8,50,000 1,240 685.48
Maintenance 24,56,000 17,550 139.94
Set-up 9,12,000 1,450 628.97
Quality control 4,42,000 1,820 242.86
(ii) Calculation of cost for the batch:
Particulars Amount (`) Amount (`)
Material cost 24,62,000.00
Wages 4,68,500.00
Overheads:
- Material procurement ( `1,535×56 orders) 85,960.00
- Material handling (`685.48×84 movements) 57,580.32
- Maintenance (`139.94×1,420 hours) 1,98,714.80
- Set-up (` 628.97×60 set-ups) 37,738.20
- Quality control (` 242.86×18 inspections) 4,371.48 3,84,364.80
Total Cost 33,14,864.80
No. of units 7,600
Cost per units 436.17
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -161-
Q-19 The following budgeted information relates to B Ltd. for the year 2021:
Products
X Y Z
Production and Sales (units) 1,00,000 80,000 60,000
(`) (`) (`)
Selling price per unit 45 90 70
Direct cost per unit 25 45 50
Hours Hours Hours
Machine department
(machine hours per unit) 3 4 5
Assembly department
(direct labour hours per unit) 6 4 3
The estimated overhead expenses for the year 2021 will be as below:
Machine Department ` 36,80,000
Assembly Department ` 27,50,000
Overhead expenses are apportioned to the products on the following basis:
Machine Department On the basis of machine hours
Assembly Department On the basis of labour hours
After a detailed study of the activities the following cost pools and their respective cost drivers are
found:
Cost Pool Amount (`) Cost Driver Quantity
Machining services 32,20,000 Machine hours 9,20,000 hours
Assembly services 22,00,000 Direct labour hours 11,00,000 hours
Set-up costs 4,50,000 Machine set-ups 9,000 set-ups
Order processing 3,60,000 Customer orders 7,200 orders
Purchasing 2,00,000 Purchase orders 800 orders
As per an estimate the activities will be used by the three products:
Products
X Y Z
Machine set-ups 4,500 3,000 1,500
Customer orders 2,200 2,400 2,600
Purchase orders 300 350 150
You are required to PREPARE a product-wise profit statement using:
(i) Absorption costing method;
(ii) Activity-based method.
Ans. (i) Profit Statement using Absorption costing method:
Particulars Product Total
X Y Z
A. Sales Quantity 1,00,000 80,000 60,000 2,40,000
B. Selling price per unit (`) 45 90 70
C. Sales Value (`) [A×B] 45,00,000 72,00,000 42,00,000 1,59,00,000
D. Direct cost per unit (`) 25 45 50
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -163-
Particulars Customers
Aey Bee Cee Dee Eey
Number of Cases Sold 9,360 14,200 62,000 38,000 9,800
List Selling Price (`) 64.80 64.80 64.80 64.80 64.80
Actual Selling Price (`) 64.80 64.08 58.80 60.24 58.32
Number of Purchase Orders 30 50 60 50 60
Number of Customers visits 4 6 12 4 6
Number of Deliveries 20 60 120 80 40
Kilometers travelled per delivery 40 12 10 20 60
Number of expediate Deliveries 0 0 0 0 2
Its five activities and their cost drivers are:
Activity Cost Driver
Order taking ` 240 per purchase order
Customer visits ` 360 per each visit
Deliveries ` 4.80 per delivery km travelled
Product Handling ` 2.40 per case sold
Expedited deliveries ` 120 per such delivery
You are REQUIRED to :
(i) Compute the customer level operating income of each of five retail customers by using the Cost
Driver rates.
(ii) Examine the results to give your comments on Customer ‘Dee’ in comparison with Customer ‘Cee’
and on Customer ‘Eey’ in comparison with Customer ‘Aey’.
Ans. Working note:
Computation of revenues (at listed price), discount, cost of goods sold and customer level operating
activities costs:
Particulars Customers
Aey Bee Cee Dee Eey
Cases sold: (a) 9,360 14,200 62,000 38,000 9,800
Revenues (at listed price) 6,06,528 9,20,160 40,17,600 24,62,400 6,35,040
(`): (b) {(a) x ` 64.80)}
Discount (`): (c) {(a) x - 10,224 3,72,000 1,73,280 63,504
Discount per case} (14,200 cases x (62,000 cases x(38,000 cases x(9,800 cases x
` 0.72) ` 6) ` 4.56) ` 6.48)
Cost of goods sold (`): (d) 5,05,440 7,66,800 33,48,000 20,52,000 5,29,200
{(a) x ` 54}
Customer level operating activities costs
Order taking costs (`): 7,200 12,000 14,400 12,000 14,400
(No. of purchase x ` 240)
Customer visits costs 1,440 2,160 4,320 1,440 2,160
(`) (No. of customer visits
x ` 360)
Delivery vehicles travel 3,840 3,456 5,760 7,680 11,520
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -165-
Q-21 SNS Trading Company has three Main Departments and two Service Departments. The data for each
department is given below:
Departments Expenses Area in (Sq. Mtr) Number of
Main Department: (in `) Employees
Purchase Department 5,00,000 12 800
Packing Department 8,00,000 15 1700
Distribution Department 3,50,000 7 700
Service Departments:
Maintenance Department 6,40,000 4 200
Personnel Department 3,20,000 6 250
The cost of Maintenance Department and Personnel Department is distributed on the basis of ‘Area in
Square Metres’ and ‘Number of Employees’ respectively.
You are required to:
(i) Prepare a Statement showing the distribution of expenses of Service Departments to the Main
Departments using the “Step Ladder method” of Overhead Distribution.
(ii) Compute the Rate per hour of each Main Department, given that, the Purchase Department,
Packing Department and Distribution Department works for 12 hours a day, 24 hours a day and 8
hours a day respectively. Assume that there are 365 days in a year and there are no holidays.
Ans. (i) Schedule Showing the Distribution of Expenses of Service Departments using Step ladder method.
Main Department Service Department
Purchase Packing Distribution Maintenance Personnel
(`) (`) (`) (`) (`)
Expenses 5,00,000 8,00,000 3,50,000 6,40,000 3,20,000
Distribution of
Maintenance
Department
(12:15:7:-:6) 1,92,000 2,40,000 1,12,000 (6,40,000) 96,000
Distribution of
Personnel
Department
(800:1700:700:-:-) 1,04,000 2,21,000 91,000 - (4,16,000)
Total 7,96,000 12,61,000 5,53,000 - -
(ii) Calculation of Expenses rate per hour of Main Department
Purchase Packing Distribution
Total apportioned expenses ( `) 7,96,000 12,61,000 5,53,000
Total Hours worked 4,380 8,760 2,920
(12 x 365) (24 x 365) (8 x 365)
Expenses rate per hour (`) 181.74 143.95 189.38
Q-22 PQR Ltd. is engaged in the production of three products P, Q and R. The company calculates Activity Cost
Rates on the basis of Cost Driver capacity which is provided as below:
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -167-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -169-
Required:
1. Calculate the total cost per unit of each product using the Absorption Costing Method.
2. Calculate the total cost per unit of each product using the Activity Based Costing Method.
Ans. 1. Traditional Absorption Costing
X Y Z Total
(a) Quantity (units) 1,200 1,440 1,968 4608
(b) Direct labour per unit (`) 18 20 30 -
(c) Direct labour hours (a × b)/` 4 5,400 7,200 14,760 27,360
Overhead rate per direct labour hour:
= Budgeted overheads „iBudgeted labour hours
= (` 50,000 + ` 40,000 + ` 28,240 + ` 1,28,000) „i 27,360 hours
= ` 2,46,240 27,360 hours
= ` 9 per direct labour hour
Unit Costs:
X Y Z
Direct Costs:
- Direct Labour (`) 18.00 20.00 30.00
- Direct Material (`) 90.00 84.00 176.00
Production Overhead: (`) 40.50 45.00 67.50
9 18 9 20 9 30
4 4 4
Total cost per unit (`) 148.50 149.00 273.50
2. Calculation of Cost-Driver level under Activity Based Costing
X Y Z Total
Quantity (units) 1,200 1,440 1,968 -
No. of orders (to be 48 58 79 185
rounded off for fraction) (1200 / 25) (1440 / 25) (1968 / 25)
No. of production runs 25 30 41 96
(1200 / 48) (1440 / 48) (1968 / 48)
No. of Inspections
(done for each 25 30 41 96
production run)
Maintenance hours 1,600 1,600 3,200 6400
Calculation of Cost-Driver rate
Activity Budgeted Cost-driver Cost Driver rate
Cost (`) level (`)
(a) (b) (c) = (a) / (b)
Material procurement 50,000 185 270.27
Set-up 40,000 96 416.67
Quality control 28,240 96 294.17
Maintenance 1,28,000 6,400 20.00
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -171-
Q-26 The following budgeted information relates to N Ltd. for the year 2021:
Products
X Y Z
Production and Sales (units) 1,00,000 80,000 60,000
(` ) (` ) (` )
Selling price per unit 90 180 140
Direct cost per unit 50 90 95
Hours Hours Hours
Machine department 3 4 5
(machine hours per unit)
Assembly department 6 4 3
(direct labour hours per unit)
The estimated overhead expenses for the year 2021 will be as below:
Machine Department ` 73,60,000
Assembly Department ` 55,00,000
Overhead expenses are apportioned to the products on the following basis:
Machine Department On the basis of machine hours
Assembly Department On the basis of labour hours
After a detailed study of the activities the following cost pools and their respe ctive cost
drivers are found:
Cost Pool Amount (`) Cost Driver Quantity
Machining services 64,40,000 Machine hours 9,20,000 hours
Assembly services 44,00,000 Direct labour hours 11,00,000 hours
Set-up costs 9,00,000 Machine set-ups 9,000 set-ups
Order processing 7,20,000 Customer orders 7,200 orders
Purchasing 4,00,000 Purchase orders 800 orders
As per an estimate the activities will be used by the three products:
Products
X Y Z
Machine set-ups 4,500 3,000 1,500
Customer orders 2,200 2,400 2,600
Purchase orders 300 350 150
You are required to PREPARE a product-wise profit statement using:
(i) Absorption costing method;
(ii) Activity-based method.
Ans.(i) Profit Statement using Absorption costing method:
Particulars Product Total
X Y Z
A. Sales Quantity 1,00,000 80,000 60,000 2,40,000
B. Selling price per unit (`) 90 180 140
C. Sales Value (‘) [A×B] 90,00,000 1,44,00,000 84,00,000 3,18,00,000
D. Direct cost per unit (`) 50 90 95
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -173-
`73,60,000
Machine hour rate = =`8
9,20,000 hours
` 55,60,000
Labour hour rate = =`5
11,00,000 hours
2. Calculation of cost driver rate
Cost Pool Amount Cost Driver Quantity Driver rate
(`) (`)
Machining services 64,40,000 Machine hours 9,20,000 hours 7.00
Assembly services 44,00,000 Direct labour hours 11,00,000 hours 4.00
Set-up costs 9,00,000 Machine set-ups 9,000 set-ups 100.00
Order processing 7,20,000 Customer orders 7,200 orders 100.00
Purchasing 4,00,000 Purchase orders 800 orders 500.00
3. Calculation of activity-wise cost
Products
X Y Z Total
A. Machining hours (Refer
Working note-1) 3,00,000 3,20,000 3,00,000 9,20,000
B. Machine hour rate (`) 7 7 7
(Refer Working note-2)
C. Machining services 21,00,000 22,40,000 21,00,000 64,40,000
cost (`) [A×B]
D. Labour hours (Refer 6,00,000 3,20,000 1,80,000 11,00,000
Working note-1)
E. Labour hour rate (`) 4 4 4
(Refer Working note-2)
F. Assembly services cost (`)
[D×E] 24,00,000 12,80,000 7,20,000 44,00,000
G. Machine set-ups 4,500 3,000 1,500 9,000
H. Rate per set-up (`) 100 100 100
(Refer Working note-2)
I. Set-up cost (`) [G×H] 4,50,000 3,00,000 1,50,000 9,00,000
J. Customer orders 2,200 2,400 2,600 7,200
K. Rate per order (`) (Refer 100 100 100
Working note-2)
L. Order processing cost 2,20,000 2,40,000 2,60,000 7,20,000
(`) [J×K]
M. Purchase orders 300 350 150 800
N. Rate per order (`) (Refer
Working note-2) 500 500 500
O. Purchasing cost (`) [M×N] 1,50,000 1,75,000 75,000 4,00,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -175-
Q-27 PCP Limited belongs to the apparel industry. It specializes in the distribution of fashionable garments.
It buys from the industry and resells the same to the following two different supermarkets:
(i) Supermarket A dealing in Adults’ garments (Age group 15 - 30)
(ii) Supermarket B dealing in Kids’ garments (Age group 5 - 10)
The following data for the month of April in respect of PCP Limited has been reported:
Supermarket A (`) Supermarket B (`)
Average revenue per delivery 1,69,950 57,750
Average cost of goods sold per delivery 1,65,000 55,000
Number of deliveries 660 1,650
In the past, PCP Limited has used gross margin percentage to evaluate the relative profitability of its
supermarket segments.
The company plans to use activity –based costing for analysing the profitability of its supermarket
segments.
The April month’s operating costs (other than cost of goods sold) of PCP Limited are ‘ 16,55,995. These
operating costs are assigned to five activity areas. The cost in each area and Activity analysis including
cost driver for the month of April are as follows:
Activity Area Total costs (`) Cost Driver
Store delivery 3,90,500 Store deliveries
Cartons dispatched to store 4,15,250 Cartons dispatched to a store per delivery
Shelf-stocking at customer store 64,845 Hours of shelf-stocking
Line-item ordering 3,45,400 Line-items per purchase order
Customer purchase order processing 4,40,000 Purchase orders by customers
Other data for the month of April include the following:
Supermarket A Supermarket B
Total number of store deliveries 1,100 2,805
Average number of cartons shipped per store delivery 250 50
Average number of hours of shelf-stocking per store delivery 6 1.5
Average number of line items per order 14 12
Total number of orders 770 1,980
Required:
(i) COMPUTE gross-margin percentage for each of its supermarket segments and compute PCP
Limited’s operating income.
(ii) COMPUTE the operating income of each supermarket segments using the activity-based costing
information.
Ans.
(i) PCP Limited’s
Statement of operating income and gross margin percentage
for each of its supermarket segments
Particulars Supermarket A Supermarket B Total
Revenues: (`) 11,21,67,000 9,52,87,500 20,74,54,500
(660 × ` 1,69,950) (1,650 × ` 57,750)
Less: Cost of goods sold: (`) 10,89,00,000 9,07,50,000
(660 × ` 1,65,000) (1650 × ` 55,000) 19,96,50,000
Gross Margin: (`) 32,67,000 45,37,500 78,04,500
Less: Other operating costs: (`) 16,55,995
Operating income: (`) 61,48,505
Gross Margin 2.91% 4.76 % 3.76%
Operating income % 2.96%
(ii) Operating Income Statement of each distribution channel
in April (Using the Activity based Costing information)
Supermarket A Supermarket B
Gross margin (`) : (A) 32,67,000 45,37,500
(Refer to (i) part of the answer)
Operating cost (`): (B) 6,55,600 10,00,395
(Refer to working note)
Operating income (`): (A–B) 26,11,400 35,37,105
Operating income (in %) 2.33 3.71
(Operating income/Revenue) ×100
Working note:
Computation of rate per unit of the cost allocation base for each of the five activity
areas for the month of April
(`)
Store delivery 100 per delivery
[` 3,90,500/ (1,100 + 2,805 store deliveries)]
Cartons dispatched 1 per carton dispatch
[` 4,15,250/ {(250×1,100) +( 50×2,805)} carton dispatches]
Shelf-stocking at customer store (`) 6 per hour
[` 64,845/ {(6×1,100) + (1.5×2,805)} hours]
Line item ordering 10 per line item order
[` 3,45,400/ {(14×770) + (12×1,980)} line items]
Customer purchase order processing 160 per order
[` 4,40,000/ (770 + 1,980 orders)]
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -177-
Q-28 MG Ltd. manufactures three types of products namely A, B and C. The data relating to a period are as
under:
Particulars A B C
Machine hours per unit 10 18 14
Direct Labour hours per unit 4 12 8
Direct Material per unit (`) 1,350 1,200 1,800
Production (units) 3,000 5,000 20,000
Currently the company uses traditional costing method and absorbs all production overheads on the
basis of machine hours. The machine hour rate of overheads is ` 90 per hour. Direct labour hour rate is
` 300 per hour.
The company proposes to use activity based costing system and the activity analysis is as under:
Particulars A B C
Batch size (units) 150 500 1,000
Number of purchase orders per batch 3 10 8
Number of inspections per batch 5 4 3
The total production overheads are analysed as under:
Machine set up costs 20%
Machine operation costs 30%
Inspection costs 40%
Material procurement related costs 10%
Required:
(i) CALCULATE the cost per unit of each product using traditional method of absorbing all production
overheads on the basis of machine hours.
(ii) CALCULATE the cost per unit of each product using activity based costing principles.
Ans
(i) Statement Showing “Cost per unit - Traditional Method”
Particulars of Costs A B C
(`) (`) (`)
Direct Materials 1,350 1,200 1,800
Direct Labour [(4, 12, 8 hours) x ‘ 300] 1,200 3,600 2,400
Production Overheads [(10, 18, 14 hours) x ‘ 90] 900 1,620 1,260
Cost per unit 3,450 6,420 5,460
(ii) Statement Showing “Cost per unit - Activity Based Costing”
Products A B C
Production (units) 3,000 5,000 20,000
(`) (`) (`)
Direct Materials (1350, 1200, 1800) 40,50,000 60,00,000 3,60,00,000
Direct Labour (1200, 3600, 2400) 36,00,000 1,80,00,000 4,80,00,000
Machine Related Costs @ ` 27 per hour
(30,000, 90,000, 2,80,000) 8,10,000 24,30,000 75,60,000
Setup Costs @ ` 1,44,000 per setup (20, 10, 20) 28,80,000 14,40,000 28,80,000
Inspection Costs @ ` 72,000 per inspection (100, 40, 60) 72,00,000 28,80,000 43,20,000
Purchase Related Costs @ ` 11,250 per purchase (60, 100, 160) 6,75,000 11,25,000 18,00,000
Total Costs 1,92,15,000 3,18,75,000 10,05,60,000
Cost per unit (Total Cost Units) 6,405 6,375 5,028
Working Notes:
1. Number of Batches, Purchase Orders, and Inspections-
Particulars A B C Total
A. Production (units) 3,000 5,000 20,000
B. Batch Size (units) 150 500 1,000
C. Number of Batches [A ÷ B] 20 10 20 50
D. Number of Purchase Order per batch 3 10 8
E. Total Purchase Orders [C x D] 60 100 160 320
F. Number of Inspections per batch 5 4 3
G. Total Inspections [C x F] 100 40 60 200
2. Total Machine Hours-
Particulars A B C
A. Machine Hours per unit 10 18 14
B. Production (units) 3,000 5,000 20,000
C. Total Machine Hours [A x B] 30,000 90,000 2,80,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -179-
CHAPTER- 6
COST SHEET
Q-1 From the following data of Arnav Metallic Ltd., Calculate Cost of production :
Amount (`)
(i) Repair & maintenance paid for plant & machinery 9,80,500
(ii) Insurance premium paid for plant & machinery 96,000
(iii) Raw materials purchased 64,00,000
(iv) Opening stock of raw materials 2,88,000
(v) Closing stock of raw materials 4,46,000
(vi) Wages paid 23,20,000
(vii) Value of opening Work-in-process 4,06,000
(viii) Value of closing Work-in-process 6,02,100
(ix) Quality control cost for the products in manufacturing process 86,000
(x) Research & development cost for improvement in production process 92,600
(xi) Administrative cost for:
- Factory & production 9,00,000
- Others 11,60,000
(xii) Amount realised by selling scrap generated during the manufacturing process 9,200
(xiii) Packing cost necessary to preserve the goods for further processing 10,200
(xiv) Salary paid to Director (Technical) 8,90,000
Ans. Calculation of Cost of Production of Arnav Metallic Ltd. for the period…..
Particulars Amount (`)
Raw materials purchased 64,00,000
Add: Opening stock 2,88,000
Less: Closing stock (4,46,000)
Material consumed 62,42,000
Wages paid 23,20,000
Prime cost 85,62,000
Repair and maintenance cost of plant & machinery 9,80,500
Insurance premium paid for plant & machinery 96,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -181-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -183-
Ans. Calculation of Cost of Production and Profit for the month ended April 2018:
Particulars Amount (`) Amount (`)
Materials consumed:
- Opening stock 6,06,000
- Add: Purchases 28,57,000
34,63,000
- Less: Closing stock (7,50,000) 27,13,000
Direct wages 37,50,000
Prime cost 64,63,000
Factory expenses 21,25,000
85,88,000
Add: Opening W-I-P 12,56,000
Less: Closing W-I-P (14,22,000)
Factory cost 84,22,000
Less: Sale of scrap (26,000)
Cost of Production 83,96,000
Add: Opening stock of finished goods 6,06,000
Less: Closing stock of finished goods (3,59,000)
Cost of Goods Sold 86,43,000
Office and administration expenses 10,34,000
Selling and distribution expenses 7,50,000
Cost of Sales 1,04,27,000
Profit (balancing figure) 29,73,000
Sales 1,34,00,000
Q-5 DFG Ltd. manufactures leather bags for office and school purpose. The followinginformation is related
with the production of leather bags for the month of September 2019.
(i) Leather sheets and cotton cloths are the main inputs, and the estimated requirementper bag is
two meters of leather sheets and one meter of cotton cloth. 2,000 meter of leather sheets and
1,000 meter of cotton cloths are purchased at `3,20,000 and `15,000 respectively. Freight paid on
purchases is `8,500.
(ii) Stitching and finishing need 2,000 man hours at `80 per hour.
(iii) Other direct cost of `10 per labour hour is incurred.
(iv) DFG has 4 machines at a total cost of `22,00,000. Machine has a life of 10 years with a scrape value
of 10% of the original cost. Depreciation is charged on straight line method.
(v) The monthly cost of administrative and sales office staffs are `45,000 and `72,000respectively.
DFG pays `1,20,000 per month as rent for a 2400 sq.feet factory premises. The administrative and
sales office occupies 240 sq. feet and 200 sq. feet respectively of factory space.
(vi) Freight paid on delivery of finished bags is `18,000.
(vii) During the month 35 kg. of leather and cotton cuttings are sold at `150 per kg.
(viii) There is no opening and closing stocks for input materials. There is 100 bags in stock at the end of
the month.
Required:
PREPARE a cost sheet following functional classification for the month of September 2019.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -185-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -187-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -189-
Factory overheads:
- Fixed 90,000 2,70,000
- Variable 45,000 2,16,000
- Semi variable 27,000 36 1,51,200 29.50
Works Cost 4,63,500 103 20,41,200 94.50
Add: Administrative overheads 1,29,600 28.80 3,88,800 18
Cost of Production 5,93,100 131.80 24,30,000 112.5
Selling Overheads 36,000 8 1,72,800 8
Cost of Sales 6,29,100 139.80 26,02,800 120.5
Working Notes:
1. Calculation of Costs
Particulars 4,500 units 21,600 units
Amount (`) Amount (`)
Material 1,80,000 (` 40 × 4,500 units) 8,64,000 (` 40 × 21,600 units)
Wages 1,44,000 (Max. of ` 30 × 4,500units 6,48,000 (21600 Units × 30)
= ` 1,35,000 and ` 48,000× 3 months
= ` 1,44,000)
Variable Cost 45,000 (` 10 × 4,500 units) 2,16,000 (` 10 × 21,600 units)
` 1,08,000 ` 1,08,000
Semi-variable Cost 27,000 3 Months 1,51,200 9 Months
12 months 12 months
+ 46,800 (for 20 % increase)
+ 23,400 (for 10% increase)
Selling Overhead 36,000 (` 8 × 4,500 units) 1,72,800(` 8 × 21,600 units)
Notes:
1. Alternatively scrap of raw material can also be reduced from Work cost.
2. Administrative overhead may be treated alternatively as a part of general overhead.
In that case, Works Cost as well as Cost of Production will be same i.e. ` 4,63,500 and Cost of Sales will
remain same as ` 6,29,100.
Q-8 Following details are provided by M/s ZIA Private Limited for the quarter ending 30 September, 2018:
(i) Direct expenses ` 1,80,000
(ii) Direct wages being 175% of factory overheads ` 2,57,250
(iii) Cost of goods sold ` 18,75,000
(iv) Selling & distribution overheads ` 60,000
(v) Sales ` 22,10,000
(vi) Administration overheads are 10% of factory overheads
Stock details as per Stock Register:
Particulars 30.06.2018 30.09.2018
` `
Raw material 2,45,600 2,08,000
Work-in-progress 1,70,800 1,90,000
Finished goods 3,10,000 2,75,000
You are required to prepare a cost sheet showing:
(i) Raw material consumed
(ii) Prime cost
(iii) Factory cost
(iv) Cost of goods sold
(v) Cost of sales and profit
Ans. Cost Sheet
(for the quarter ending 30 September 2018)
Amount (`)
(i) Raw materials consumed
Opening stock of raw materials 2,45,600
Add: Purchase of materials 12,22,650*
Less: Closing stock of raw materials (2,08,000)
Raw materials consumed 12,60,250
Add: Direct wages (1,47,000×175%) 2,57,250
Direct Expenses 1,80,000
(ii) Prime cost 16,97,500
Add: Factory overheads (2,57,250/175%) 1,47,000
Gross Factory cost 18,44,500
Add: Opening work-in-process 1,70,800
Less: Closing work-in-process (1,90,000)
(iii) Factory cost 18,25,300
Add: Administration overheads (10% of factory overheads) 14,700
Add: Opening stock of finished goods 3,10,000
Less: Closing stock of finished goods (2,75,000)
(iv) Cost of goods sold 18,75,000
Add: Selling & distribution overheads 60,000
Cost of sales 19,35,000
(v) Net Profit 2,75,000
Sales 22,10,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -191-
Factory Cost = Cost of Production goods sold + Closing stock of Finished goods – Opening stock of finished
goods
Net Profit = Sales - Cost of sales.
Q-9 Following information relate to a manufacturing concern for the year ended 31st March, 2018:
`
Raw Material (opening) 2,28,000
Raw Material (closing) 3,05,000
Purchases of Raw Material 42,25,000
Freight Inwards 1,00,000
Direct wages paid 12,56,000
Direct wages-outstanding at the end of the year 1,50,000
Factory Overheads 20% of prime cost
Work-in-progress (opening) 1,92,500
Wo9rk-in-progres (closing) 1,40,700
Administrative Overheads (related to production) 1,73,000
Distribution Expenses ` 16 per unit
Finished Stock (opening)-1217 Units 6,08,500
Sale of scrap of material 8,000
The firm produced 14000 units of output during the year. The stock of finished goods at the end of the
year is valued at cost of production. The firm sold 14153 units at a price of ` 618 per unit during the year.
Prepare cost sheet of the firm.
Ans. Cost sheet for the year ended 31st March, 2018.
Units produced - 14,000 units
Units sold - 14,153 units
Particulars Amount (`)
Raw materials purchased 42,25,000
Add: Freight Inward 1,00,000
Add: Opening value of raw materials 2,28,000
Less: Closing value of raw materials (3,05,000)
42,48,000
Less: Sale of scrap of material 8,000
Materials consumed 42,40,000
Direct Wages (12,56,000 + 1,50,000) 14,06,000
Prime Cost 56,46,000
Factory overheads (20% of ` Prime Cost) 11,29,200
Add: Opening value of W-I-P 1,92,500
Less: Closing value of W-I-P (1,40,700)
Factory Cost 68,27,000
Add: Administrative overheads 1,73,000
Cost of Production 70,00,000
Add: Value of opening finished stock 6,08,500
Less: Value of closing finished stock
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -193-
[` 500(70,00,000/14,000) × 1,064)
(1,217+ 14,000 – 14,153 = 1,064 units) (5,32,000)
Cost of Goods Sold 70,76,500
Distribution expenses (` 16 × 14,153 units) 2,26,448
Cost of Sales 73,02,948
Profit (Balancing figure) 14,43,606
Sales (` 618 × 14,153 units) 87,46,554
Q-10 From the following figures, Calculate cost of production and profit for the month of March 20X9.
Amount (Rs.) Amount (Rs.)
Stock on 1st March, 20X9 Purchase of raw materials 28,57,000
- Raw materials 6,06,000 Sale of finished goods 1,34,00,000
- Finished goods 3,59,000 Direct wages 37,50,000
Stock on 31st March, 20X9 Factory expenses 21,25,000
- Raw materials 7,50,000 Office and administration expenses 10,34,000
- Finished goods 3,09,000 Selling and distribution expenses 7,50,000
Work-in-process: Sale of scrap 26,000
- On 1st March, 20X9 12,56,000
- On 31st March, 20X9 14,22,000
Ans. Calculation of Cost of Production and Profit for the month ended March, 20X9:
Particulars Amount (Rs.) Amount (Rs.)
Materials consumed:
- Opening stock 6,06,000
- Add: Purchases 28,57,000
34,63,000
- Less: Closing stock (7,50,000) 27,13,000
Direct wages 37,50,000
Prime cost 64,63,000
Factory expenses 21,25,000
85,88,000
Add: Opening W-I-P 12,56,000
Less: Closing W-I-P (14,22,000)
Factory cost 84,22,000
Less: Sale of scrap (26,000)
Cost of Production 83,96,000
Add: Opening stock of finished goods 3,59,000
Less: Closing stock of finished goods (3,09,000)
Cost of Goods Sold 84,46,000
Office and administration expenses 10,34,000
Selling and distribution expenses 7,50,000
Cost of Sales 1,02,30,000
Profit (balancing figure) 31,70,000
Sales 1,34,00,000
Ans.
Calculation of Cost of Production of A Ltd. for the period…..
Particulars Amount (Rs.)
Raw materials purchased 64,00,000
Add: Opening stock 2,88,000
Less: Closing stock (4,46,000)
Material consumed 62,42,000
Wages paid 23,20,000
Prime cost 85,62,000
Repair and maintenance cost of plant & machinery 9,80,500
Insurance premium paid for inventories 26,000
Insurance premium paid for plant & machinery 96,000
Quality control cost 86,000
Research & development cost 92,600
Administrative overheads related with factory and production 9,00,000
1,07,43,100
Add: Opening value of W-I-P 4,06,000
Less: Closing value of W-I-P (6,02,100)
1,05,47,000
Less: Amount realised by selling scrap (9,200)
Add: Primary packing cost 10,200
Cost of Production 1,05,48,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -195-
Notes:
(i) Other administrative overhead does not form part of cost of production.
(ii) Salary paid to Director (Technical) is an administrative cost.
Q-12 State the advantages of Cost-Sheets.
Ans. Advantages of Cost sheet or Cost Statements
The main advantages of a Cost Sheet are as follows:
(i) It provides the total cost figure as well as cost per unit of production.
(ii) It helps in cost comparison.
(iii) It facilitates the preparation of cost estimates required for submitting tenders.
(iv) It provides sufficient help in arriving at the figure of selling price.
(v) It facilitates cost control by disclosing operational efficiency.
Q-13 From the following data of Arnav Metallic Ltd., Calculate Cost of production:
Amount (Rs.)
(i) Repair & maintenance paid for plant & machinery 9,80,500
(ii) Insurance premium paid for inventories 26,000
(iii) Insurance premium paid for plant & machinery 96,000
(iv) Raw materials purchased 64,00,000
(v) Opening stock of raw materials 2,88,000
(vi) Closing stock of raw materials 4,46,000
(vii) Wages paid 23,20,000
(viii) Value of opening Work-in-process 4,06,000
(ix) Value of closing Work-in-process 6,02,100
(x) Quality control cost for the products in manufacturing process 86,000
(xi) Research & development cost for improvement in production process 92,600
(xii) Administrative cost for:
- Factory & production 9,00,000
- Others 11,60,000
(xiii)Amount realised by selling scrap generated during the manufacturing process 9,200
(xiv)Packing cost necessary to preserve the goods for further processing 10,200
(xv)Salary paid to Director (Technical) 8,90,000
Ans. Calculation of Cost of Production of Arnav Metallic for the period…..
Particulars Amount (Rs.)
Raw materials purchased 64,00,000
Add: Opening stock 2,88,000
Less: Closing stock (4,46,000)
Material consumed 62,42,000
Wages paid 23,20,000
Prime cost 85,62,000
Repair and maintenance cost of plant & machinery 9,80,500
Insurance premium paid for inventories 26,000
Insurance premium paid for plant & machinery 96,000
Quality control cost 86,000
Research & development cost 92,600
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -197-
Add: Fixed marketing expenses 8.00 4,80,000 4.80 4,80,000 2.40 4,80,000
Add: Variable distribution cost 30.00 18,00,000 30.00 30,00,000 30.00 60,00,000
Add: Special Costs:
- Gift items costs - - - - 30.00 60,00,000
- Customers’ prizes* - - 2.00 2,00,000 1.00 2,00,000
- Refreshments - - 2.00 2,00,000 1.00 2,00,000
- Television programme
sponsorship cost - - 20.00 20,00,000 10.00 20,00,000
Cost of sales 424.00 2,54,40,000 422.40 4,22,40,000 386.20 7,72,40,000
Profit (Bal. fig.) 176.00 1,05,60,000 137.60 1,37,60,000 113.80 2,27,60,000
Sales revenue 600.00 3,60,00,000 560.00 5,60,00,000 500.00 10,00,00,000
* Customers’ prize cost:
Particulars Amount (`)
1st Prize 60,000
2nd Prize 50,000
3rd Prize 40,000
Consolation Prizes (10 × ‘ 5,000) 50,000
Total 2,00,000
Comparison of Profit
30% capacity 50% capacity 100% capacity
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -199-
(` )
Direct Materials 12,00,000
Direct Wages 6,72,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -203-
` 12,00,000
Or, M = =`4
3,00,000
Therefore, Direct material Cost per unit of ‘Super’ = 2 x ` 4 = ` 8
(ii) Direct wages per unit for ‘Super’ =W
Direct wages per unit for ‘Normal’ = 0.6W
So, (W x 60,000) + (0.6W x 1,80,000) = ` 6,72,000
W = ` 4 per unit
` 2,88,000
(iii) Production overhead per unit = = ` 1.20
(60,000 1,80,000)
Production overhead for ‘Super’ = ` 1.20 x 60,000 units = ` 72,000
Notes:
1. Administration overhead is specific to the product as it is directly related to direct labour as
mentioned in the question and hence to be considered in cost of production only.
2. Cash discount is treated as interest and finance charges; hence, it is ignored.
3. Penalty paid against the copyright infringement case is an abnormal cost; hence, not included.
Q-18 The following data are available from the books and records of Q Ltd. for the month of April 2020:
Direct Labour Cost = ` 1,20,000 (120% of Factory Overheads)
Cost of Sales = ` 4,00,000
Sales = ` 5,00,000
Accounts show the following figures:
1st April, 2020 30th April, 2020
(` ) (` )
Inventory:
Raw material 20,000 25,000
Work-in-progress 20,000 30,000
Finished goods 50,000 60,000
Other details:
Selling expenses 22,000
General & Admin. expenses 18,000
You are required to prepare a cost sheet for the month of April 2020 showing:
(i) Prime Cost
(ii) Works Cost
(iii) Cost of Production
(iv) Cost of Goods sold
(v) Cost of Sales and Profit earned.
Ans. Cost Sheet for the Month of April 2020
Particulars (`)
Opening stock of Raw Material 20,000
Add: Purchases [Refer Working Note-2] 1,65,000
Less: Closing stock of Raw Material (25,000)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -205-
`8,00,000
Or, M = =`4
2,00,000
Therefore, Direct material Cost per unit of Super pen = 2 × ` 4 = ` 8
(ii) Direct wages per unit for Super pen = W
Direct wages per unit for Normal Pen = 0.6W
So, (W x 40,000) + (0.6W x 1,20,000) = ` 4,48,000
W = ` 4 per unit
`1,92,000
(iii) Production overhead per unit = = ‘ 1.20
(40,000+1,20,000)
Production overhead for Super pen = ` 1.20 × 40,000 units = ` 48,000
* Administration overhead is specific to the product as it is directly related to direct labour as mentioned in
the question and hence to be considered in cost of production only.
Assumption: It is assumed that in point (1) and (2) of the Question, direct materials cost and direct wages
respectively is related to per unit only.
Note: Direct Material and Direct wages can be calculated in alternative ways.
Q-20 Impact Ltd. provides you the following details of its expenditures for the year ended 31st March, 2021:
S.No. Particulars Amount (`) Amount (`)
(i) Raw materials purchased 5,00,00,000
(ii) GST paid under Composition scheme 10,00,000
(iii) Freight inwards 5,20,600
(iv) Trade discounts received 10,00,000
(v) Wages paid to factory workers 15,20,000
(vi) Contribution made towards employees’ PF & ESIS 1,90,000
(vii) Production bonus paid to factory workers 1,50,000
(viii) Fee for technical assistance 1,12,000
(ix) Amount paid for power & fuel 2,62,000
(x) Job charges paid to job workers 4,50,000
(xi) Stores and spares consumed 1,10,000
(xii) Depreciation on:
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -207-
From the above data, you are required to PREPARE Statement of cost of Impact Ltd. for the year ended
31st March, 2021, showing (i) Prime cost, (ii) Factory cost, (iii) Cost of Production, (iv) Cost of goods sold
and (v) Cost of sales.
Ans. Statement of Cost of Impact Ltd. for the year ended 31st March, 2021:
Sl.No. Particulars Amount (`) Amount (`)
(i) Material Consumed:
Raw materials purchased 5,00,00,000
GST paid under Composition scheme* 10,00,000
Freight inwards 5,20,600
Less: Trade discounts received (10,00,000)
Add: Opening stock of raw materials 9,00,000
Less: Closing stock of raw materials (5,60,000) 5,08,60,600
(ii) Direct employee (labour) cost:
Wages paid to factory workers 15,20,000
Contribution made towards employees’ PF &
ESIS 1,90,000
Production bonus paid to factory workers 1,50,000 18,60,000
(iii) Direct expenses:
Fee for technical assistance 1,12,000
Amount paid for power & fuel 2,62,000
Job charges paid to job workers 4,50,000 8,24,000
Prime Cost 5,35,44,600
(iv) Works/ Factory overheads:
Stores and spares consumed 1,10,000
Depreciation on factory building 64,000
Depreciation on plant & machinery 86,000
Repairs & Maintenance paid for plant & machinery 58,000
Insurance premium paid for plant & machinery 31,200
Insurance premium paid for factory building 28,100
Salary paid to supervisors 1,20,000 4,97,300
Gross factory cost 5,40,41,900
Add: Opening value of W-I-P 4,00,000
Less: Closing value of W-I-P (2,50,000)
Factory Cost 5,41,91,900
(v) Quality control cost:
Expenses paid for quality control check activities 25,000
(vi) Research & development cost paid for
improvement in production process 48,200
(vii) Administration cost related with production:
-Expenses paid for administration of factory work 1,38,000
-Salary paid to Production control manager 4,80,000 6,18,000
(viii) Less: Realisable value on sale of scrap and waste (66,000)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -209-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -211-
Q-22 A Ltd. produces a single product X. During the month of December 2021, the company has produced
14,560 tonnes of X. The details for the month of December 2021 are as follows:
(i) Materials consumed ` 15,00,000
(ii) Power consumed 13,000 Kwh @ ` 7 per Kwh
(iii) Diesels consumed 1,000 litres @ ` 93 per litre
(iv) Wages & salary paid – ` 64,00,000
(v) Gratuity & leave encashment paid – ` 44,20,000
(vi) Hiring charges paid for HEMM- ` 13,00,000
(vii) Hiring charges paid for cars used for official purpose – ` 80,000
(viii) Reimbursement of diesel cost for the cars – ` 20,000
(ix) The hiring of cars attracts GST under RCM @5% without credit.
(x) Maintenance cost paid for weighing bridge (used for weighing of final goods at the time of despatch)
– ` 7,000
(xi) AMC cost of CCTV installed at weighing bridge (used for weighing of final goods at the time of
despatch) and factory premises is ` 6,000 and ` 18,000 per month respectively.
-212- Chapter-6 : Cost Sheet
(xii) TA/ DA and hotel bill paid for sales manager- ` 16,000
(xiii) The company has 180 employees works for 26 days in a month.
Required:
(a) PREPARE a Cost sheet for the month of December 2021.
(b) COMPUTE Earnings per manshift (EMS) and Output per manshift (OMS) for the month of December
2021.
Ans.
(a) Cost Sheet of A Ltd. for the month of December 2021
Particulars Amount (`) Amount (`)
Materials consumed 15,00,000
Wages & Salary 64,00,000
Gratuity & leave encashment 44,20,000 1,08,20,000
Power cost (13,000 kwh × ` 7) 91,000
Diesel cost (1,000 ltr × ` 93) 93,000 1,84,000
HEMM hiring charges 13,00,000
Prime Cost 1,38,04,000
AMC cost of CCTV installed at factory premises 18,000
Cost of Production/ Cost of Goods Sold 1,38,22,000
Hiring charges of cars 80,000
Reimbursement of diesel cost 20,000
1,00,000
Add: GST @5% on RCM basis 5,000 1,05,000
Maintenance cost for weighing bridge 7,000
AMC cost of CCTV installed at weigh bridge 6,000 13,000
TA/ DA & hotel bill of sales manager 16,000
Cost of Sales 1,39,56,000
(b) Manshift = 180 employees × 26 days = 4,680 manshifts
Computation of earnings per manshift (EMS):
Total employee benefits paid
EMS =
Manshift
` 1, 08,20, 000
= = ` 2,312
4,680
Computation of Output per manshift (OMS):
Total Output / Production
Manshift
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -213-
Q-23 G Ltd. manufactures leather bags for office and school purposes.
The following information is related with the production of leather bags for the month of September,
2021.
(1) Leather sheets and cotton clothes are the main inputs and the estimated requirement per bag is
two metres of leather sheets and one metre of cotton cloth. 2,000 metre of leather sheets and
1,000 metre of cotton cloths are purchased at ` 3,20,000 and ` 15,000 respectively. Freight paid on
purchases is ` 8,500.
(2) Stitching and finishing need 2,000 man hours at ` 80 per hour.
(3) Other direct costs of ` 10 per labour hour is incurred.
(4) G Ltd. have 4 machines at a total cost of ` 22,00,000. Machines have a life of 10 years with a scrap
value of 10% of the original cost. Depreciation is charged on a straight-line method.
(5) The monthly cost of administration and sales office staffs are ` 45,000 and ` 72,000 respectively. G
Ltd. pays ` 1,20,000 per month as rent for a 2,400 sq. feet factory premises. The administrative and
sales office occupies 240 sq. feet and 200 sq. feet respectively of factory space.
(6) Freight paid on delivery of finished bags is ` 18,000.
(7) During the month, 35 kgs of scrap (cuttings of leather and cotton) are sold at ` 150 per kg.
(8) There are no opening and closing stocks of input materials. There is a finished stock of 100 bags in
stock at the end of the month.
You are required to prepare a cost sheet in respect of above for the month of September 2021 showing:
(i) Cost of Raw Material Consumed
(ii) Prime Cost
(iii) Works/Factory Cost
(iv) Cost of Production
(v) Cost of Goods Sold
(vi) Cost of Sales
Ans. No. of bags manufactured = 1,000 units
Cost sheet for the month of September 2021
Particulars Total Cost Cost per unit
(` ) (` )
1. Direct materials consumed:
- Leather sheets 3,20,000 320.00
- Cotton cloths 15,000 15.00
Add: Freight paid on purchase 8,500 8.50
(i) Cost of material consumed 3,43,500 343.50
2. Direct wages (`80 × 2,000 hours) 1,60,000 160.00
3. Direct expenses (`10 × 2,000 hours) 20,000 20.00
4. (ii) Prime Cost 5,23,500 523.50
5. Factory Overheads: Depreciation on machines 16,500 16.50
{(` 22,00,000 × 90%) ÷ 120 months}
Apportioned cost of factory rent 98,000 98.00
6. (iii) Works/ Factory Cost 6,38,000 638.00
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -215-
For set-up
G Hours required per batch (Hours) 0.25 0.25 0.25 0.25
H Total hours required (Hours) [A×G] 45 56.25 60 161.25
I Power consumption per hour (Kwh) [20%×90] 18 18 18 18
J Total Power consumption (Kwh) [H×I] 810 1,012.5 1,080 2,902.5
K Per batch consumption* (Kwh) [J÷A] 4.5 4.5 4.5 4.5
* Per batch consumption can be directly calculated as [Hours required per batch x Power consumption per
hour]
Calculation of Profit/ loss per batch:
Particulars Large Medium Small Total
A Demand (bottle) 3,00,000 7,50,000 20,00,000 30,50,000
B Price per bottle (`) 150 90 50
C Sales value (`) [A×B] 4,50,00,000 6,75,00,000 10,00,00,000 21,25,00,000
Direct Material cost:
E Material-W (`)
[Qty in WN-3 × `0.50] 63,00,000 78,75,000 84,00,000 2,25,75,000
F Material-C (`)
[Qty in WN-3 × `1,000] 2,25,00,000 2,81,25,000 3,00,00,000 8,06,25,000
G [E+F] 2,88,00,000 3,60,00,000 3,84,00,000 10,32,00,000
H Direct Wages (`)
[Man-shift in WN-4 × × `880] 7,92,000 10,03,200 10,56,000 28,51,200
I Packing cost (`) [A×`3] 9,00,000 22,50,000 60,00,000 91,50,000
Power cost (`)
J For processing (`)
[WN-5 × `7] 1,98,450 2,48,062.5 2,64,600 7,11,112.5
K For set-up time (`) [WN-5 × `7] 5,670 7,087.5 7,560 20,317.5
L [J+K] 2,04,120 2,55,150 2,72,160 7,31,430
M Other variable cost (`)
[No. of batch in WN-2 × `30,000]54,00,000 67,50,000 72,00,000 1,93,50,000
N Total Variable cost per batch
[G+H+I+L+M] 3,60,96,120 4,62,58,350 5,29,28,160 13,52,82,630
O Profit/ loss before
fixed cost [C-N] 89,03,880 2,12,41,650 4,70,71,840 7,72,17,370
P Fixed Cost 4,90,00,000
Q Net Profit [O-P] 2,82,17,370
Computation of Economic Batch Quantity (EBQ):
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -217-
Q-25 The following data relates to manufacturing of a standard product during the month of February, 2022:
Particulars Amount (in `)
Stock of Raw material as on 01-02-2022 1,20,000
Work in Progress as on 01-02-2022 75,000
Purchase of Raw material 3,00,000
Carriage Inwards 30,000
Direct Wages 1,80,000
Cost of special drawing 45,000
Hire charges paid for Plant (Direct) 36,000
Return of Raw Material 60,000
Carriage on return 9,000
Expenses for participation in Industrial exhibition 12,000
Maintenance of office building 3,000
Salary to office staff 37,500
Legal charges 3,750
Depreciation on Delivery van 9,000
Warehousing charges 2,250
Stock of Raw material as on 28-02-2022 45,000
Stock of Work in Progress as on 28-02-2022 36,000
• Store overheads on materials are 10% of material consumed.
• Factory overheads are 20% of the Prime cost.
• 10% of the output was rejected and a sum of ` 7,500 was realized on sale of scrap.
• 10% of the finished product was found to be defective and the defective products were rectified
at an additional expenditure which is equivalent to 20% of proportionate direct wages.
• The total output was 8,000 units during the month.
You are required to PREPARE a Cost Sheet for the above period showing the:
(i) Cost of Raw Material consumed.
-218- Chapter-6 : Cost Sheet
Working Notes:
1. Number of Rectified units
Total Output 8,000 units
Less: Rejected 10% 800 units
Finished product 7,200 units
Rectified units (10% of finished product) 720 units
2. Proportionate additional expenditure on 720 units
= 20% of proportionate direct wages
= 0.20 x (` 1,80,000/8,000) x 720
= ` 3,240
---0---0---
CHAPTER - 7
COST ACCOUNTING SYSTEM (Integral and Non-Integral)
Q-1 The following are the balances existed in the books of JPG Ltd. for the year ended, 31st March, 2019:
Particulars Dr. Cr.
(` ) (` )
Stores Ledger Control A/c 30,00,000
WIP Control A/c 15,00,000
Finished Goods Control A/c 25,00,000
Manufacturing Overheads Control A/c 1,50,000
Cost Ledger Control A/c 68,50,000
During the year 2019-20, the following transactions took place:
Particulars Amount (`)
Finished product (at cost) 22,50,000
Manufacturing Overhead incurred 8,50,000
Raw material purchased 12,50,000
Factory wages 4,00,000
Indirect labour 2,00,000
Cost of sales 17,50,000
Materials issued to production 13,50,000
Sales returned (at cost) 90,000
Material returned to suppliers 1,30,000
Manufacturing overhead charged to production 8,50,000
Required:
PREPARE the following control accounts and Trial balance at the end of the year:
Cost Ledger, Stores Ledger, Work-in-process, Finished Stock, Manufacturing Overhead, Wages and Cost
of Sales.
Ans. Cost Ledger Control Account
Particulars (` ) Particulars (`)
To Stores Ledger control A/c 1,30,000 By Balance b/d 68,50,000
To Costing Profit & Loss A/c 17,10,000 By Stores Ledger control A/c 12,50,000
By Wages Control A/c 6,00,000
To Balance c/d 77,10,000 By Manufacturing overhead control A/c 8,50,000
95,50,000 95,50,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -221-
Trial Balance
Particulars Dr. Cr.
(` ) (` )
Stores Ledger Control A/c 27,70,000
WIP Control A/c 18,50,000
Finished Goods Control A/c 30,90,000
Cost Ledger Control A/c _______ 77,10,000
77,10,000 77,10,000
Working:
Costing P&L Account
Particulars (` ) Particulars (` )
To Cost of Sales A/c 16,60,000 By Cost Ledger control A/c 17,10,000
To Manufacturing overhead control A/c 50,000 _______
17,10,000 17,10,000
Q-2 As of 30th September, 2019, the following balances existed in a firm’s cost ledger, which is maintained
separately on a double entry basis:
Debit(`) Credit(`)
Stores Ledger Control A/c 15,00,000 _
Work-in-progress Control A/c 7,50,000 _
Finished Goods Control A/c 12,50,000 _
Manufacturing Overhead Control A/c _ 75,000
Cost Ledger Control A/c _______ 34,25,000
35,00,000 35,00,000
During the next quarter, the following items arose:
(` )
Finished Product (at cost) 11,25,000
Manufacturing overhead incurred 4,25,000
Raw material purchased 6,25,000
Factory wages 2,00,000
Indirect labour 1,00,000
Cost of sales 8,75,000
Materials issued to production 6,75,000
Sales returned (at cost) 45,000
Materials returned to suppliers 65,000
Manufacturing overhead charged to production 4,25,000
Required:
PREPARE the Cost Ledger Control A/c, Stores Ledger Control A/c, Work-in-progress Control A/c, Finished
Stock Ledger Control A/c, Manufacturing Overhead Control A/c , Wages Control A/c, Cost of Sales A/c
and the Trial Balance at the end of the quarter.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -223-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -225-
Q-4 The financial books of a company reveal the following data for the year ended 31st March, 20X8:
Opening Stock: (` )
Finished goods 625 units 53,125
Work-in-process 46,000
01.04.20X7 to 31.03.20X8
Raw materials consumed 8,40,000
Direct Labour 6,10,000
Factory overheads 4,22,000
Administration overheads (Production related) 1,98,000
Dividend paid 1,22,000
Bad Debts 18,000
Selling and Distribution Overheads 72,000
Interest received 38,000
Rent received 46,000
Sales 12,615 units 22,80,000
Closing Stock: Finished goods 415 units 45,650
Work-in-process 41,200
The cost records provide as under:
• Factory overheads are absorbed at 70% of direct wages.
• Administration overheads are recovered at 15% of factory cost.
• Selling and distribution overheads are charged at ` 3 per unit sold.
• Opening Stock of finished goods is valued at ` 120 per unit.
• The company values work-in-process at factory cost for both Financial and Cost Profit Reporting.
Required:
(i) PREPARE a statements for the year ended 31st March, 20X8. Show
• the profit as per financial records
• the profit as per costing records.
(ii) PREPARE a statement reconciling the profit as per costing records with the profit as per Financial
Records.
Ans.
(i) Statement of Profit as per Financial records
(for the year ended March 31, 20X8)
(` ) (` )
To Opening stock of Finished Goods 53,125 By Sales 22,80,000
To Work-in-process 46,000 By Closing stock of finished Goods 45,650
To Raw materials consumed 8,40,000 By Work-in-Process 41,200
To Direct labour 6,10,000 By Rent received 46,000
To Factory overheads 4,22,000 By Interest received 38,000
To Administration overheads 1,98,000 To Selling & distribution overheads 72,000
To Dividend paid 1,22,000
To Bad debts 18,000 To Profit 69,725
24,50,850 24,50,850
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -227-
2. Cost Sheet (` )
Raw materials consumed 8,40,000
Direct labour 6,10,000
Prime cost 14,50,000
Factory overheads 4,27,000
(70% of direct wages)
Factory cost 18,77,000
Add: Opening work-in-process 46,000
Less: Closing work-in-process 41,200
Factory cost of goods produced 18,81,800
Administration overheads 2,81,550
(15% of factory cost)
Cost of production of 12,405 units 21,63,350
(Refer to working note 1)
Cost of production per unit:
Total Cost of Production `21,63,350
= = = ` 174.39
No. of units produced 12,405 units
Q-5 As of 31st March, 2018, the following balances existed in a firm’s cost ledger, which is maintained
separately on a double entry basis:
Debit (`) Credit (`)
Stores Ledger Control A/c 3,20,000 -
Work-in-process Control A/c 1,52,000 -
Finished Goods Control A/c 2,56,000 -
Manufacturing Overhead Control A/c - 28,000
Cost Ledger Control A/c - 7,00,000
7,28,000 7,28,000
During the next quarter, the following items arose:
(` )
Finished Product (at cost) 2,35,500
Manufacturing overhead incurred 91,000
Raw material purchased 1,36,000
Factory wages 48,000
Indirect labour 20,600
Cost of sales 1,68,000
Materials issued to production 1,26,000
Sales returned (at cost) 8,000
Materials returned to suppliers 11,000
Manufacturing overhead charged to production 86,000
Required:
PREPARE the Cost Ledger Control A/c, Stores Ledger Control A/c, Work-in-process Control A/c, Finished
Stock Ledger Control A/c, Manufacturing Overhead Control A/c, Wages Control A/c, Cost of Sales A/c and the
Trial Balance at the end of the quarter as per costing records.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -229-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -231-
Q-9 The following balances were extracted from a Company's ledger as on 30th June, 2018:
Particulars Debit (`) Credit (`)
Raw material control a/c 2,82,450
Work-in-progress control a/c 2,38,300
Finished stock control a/c 3,92,500
General ledger adjustment a/c 9,13,250
Total 9,13,250 9,13,250
The following transactions took place during the quarter ended 30th September, 2018:
`
(i) Factory overheads - allocated to work-in-progress 1,36,350
(ii) Goods furnished - at cost 13,76,200
(iii) Raw materials purchased 12,43,810
(iv) Direct wages - allocated to work-in-progress 2,56,800
(v) Cost of goods sold 14,56,500
(vi) Raw materials - issued to production 13,60,430
(vii) Raw materials - credited by suppliers 27,200
(viii) Raw materials losses - inventory audit 6,000
(ix) Work-in-progress rejected (with no scrap value) 12,300
(x) Customer's returns (at cost) of finished goods 45,900
You are required to prepare:
(i) Raw material control a/c
(ii) Work-in-progress control a/c
(iii) Finished stock control a/c
(iv) General ledger adjustment a/c
Ans.
(i) Raw Material Control A/c
(`) (`)
To Balance b/d 2,82,450 By General Ledger Adjustment A/c 27,200
” General Ledger
Adjustment A/c 12,43,810 ” Work-in-progress Control A/c 13,60,430
Costing P & L A/c 6,000
(Loss) (OR GLA)
________ ” Balance c/d 1,32,630
15,26,260 15,26,260
(ii) Work-in-Progress Control A/c
(`) (`)
To Balance b/d 2,38,300
” Raw Material Control A/c 13,60,430 ” Finished Goods Control A/c 13,76,200
” Wages Control A/c 2,56,800 Costing P&L A/c (OR GLA) 12,300
” Factory OH Control A/c 1,36,350 ” Balance c/d 6,03,380
19,91,880 19,91,880
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -233-
Prepare a reconciliation statement reconciling losses shown by financial and cost accounts by taking costing
net loss as base.
Ans. Reconciliation Statement
Particulars ` `
Loss as per Cost Accounts (2,48,300)
Add: Works overheads over recovered 30,400
Depreciation over charged in cost accounts 35,100
Interest credited during the year in financial accounts 7,500 73,000
Less: Selling overheads under recovered 20,300
Administrative overheads under recovered 27,700
Bad debts w/off in financial accounts 15,000
Preliminary Exp. w/off in financial accounts 5,000 (68,000)
Loss as per Financial Accounts (2,43,300)
Q-11 A manufacturing company disclosed a net loss of Rs.3,47,000 as per their cost accounts for the year
ended March 31,20X8. T he financial accounts h owever disclosed a net loss of Rs. 5,10,000 for the same
period. T he following information was revealed as a result of scrutiny of the figures of both the sets of
accounts.
(Rs.)
(i) Factory Overheads under-absorbed 40,000
(ii) Administration Overheads over-absorbed 60,000
(iii) Depreciation charged in Financial Accounts 3,25,000
(iv) Depreciation charged in Cost Accounts 2,75,000
(v) Interest on investments not included in Cost Accounts 96,000
(vi) Income-tax provided 54,000
(vii) Interest on loan funds in Financial Accounts 2,45,000
(viii) Transfer fees (credit in financial books) 24,000
(ix) Stores adjustment (credit in financial books) 14,000
(x) Dividend received 32,000
PREPARE a memorandum Reconciliation Account.
Ans. Memorandum Reconciliation Accounts
Dr. Cr.
(Rs.) (Rs.)
To Net Loss as per Costing books 3,47,000 By Administration overheads over
recovered in cost accounts 60,000
To Factory overheads under 40,000 By Interest on investment not included in
absorbed in Cost Accounts Cost Accounts 96,000
To Depreciation under charged in
Cost Accounts 50,000 By Transfer fees in Financial books 24,000
To Income- Tax not provided in
Cost Accounts 54,000 By Stores adjustment
(Credit in financial books) 14,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -235-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -237-
Rs.58,87,200
Less: Closing Stock 2,000 units (2,26,431)
52,000 units
Cost of Goods Sold 56,60,769
Add: Selling expenses (Rs.10 × 50,000 units) 5,00,000
Cost of Sales 61,60,769
Profit (Balancing figure) 39,231
Sales Value 62,00,000
Costing Profit and Loss Account
Particulars Amount (Rs.) Particulars Amount (Rs.)
To Materials 26,80,000 By Sales 62,00,000
To Wages 17,80,000 By Closing stock 2,26,431
To Factory expenses 8,92,000
To Administrative expenses 5,35,200
To Selling expenses 5,00,000
To Profit (Balancing figure) 39,231 ________
64,26,431 64,26,431
Reconciliation of profit as per Cost Accounts and as per Financial Accounts
Particulars Amount (Rs.)
Profit as per Cost Accounts 39,231
Additions:
Administrative expenses (Over-absorbed) (Rs. 5,35,200 – Rs.4,80,200) 55,000
Selling expenses (Overcharged) ( Rs. 5,00,000 – Rs. 2,50,000) 2,50,000
Dividend received 20,000
3,64,231
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -239-
Deductions:
Factory expenses (Under -absorbed) (Rs. 9,50,000 – 8,92,000) 58,000
Closing stock (Over-valued) (Rs.2,26,431 – Rs. 1,50,000) 76,431
Preliminary expenses written off 50,000
1,84,431
Profit as per Financial Accounts 1,79,800
(Reconciliation statement may also be prepared by taking financial profit as base.)
Q-16 A manufacturing company has disclosed a net loss of Rs 2,25,000 as per their cost accounting records for
the year ended March 31, 2019. However, their financial accounting records disclosed a net loss of Rs
2,70,000 for the same period. A scrutiny of data of both the sets of books of accounts revealed the
following information:
(Rs)
(i) Factory overheads under-absorbed 5,000
(ii) Administration overheads over-absorbed 3,000
(iii) Depreciation charged in financial accounts 70,000
(iv) Depreciation charged in cost accounts 80,000
(v) Interest on investments not included in cost accounts 20,000
(vi) Income-tax provided in financial accounts 65,000
(vii) Transfer fees (credit in financial accounts) 2,000
(viii) Preliminary expenses written off 3,000
(ix) Over-valuation of closing stock of finished goods in cost accounts 7,000
Required:
PREPARE a Memorandum Reconciliation Account.
(d) Memorandum Reconciliation Account
Particulars (Rs.) Particulars (Rs.)
To Net loss as per Costing books 2,25,000 By Administrative overhead 3,000
over absorbed in costs
To Factory overheads under absorbed 5,000 By Depreciation over charged in
Cost books(Rs. 80,000 – Rs.70,000) 10,000
To Income tax not provided in By Interest on investments not 20,000
Cost books 65,000 included in Cost books
To Preliminary expenses written off in 3,000 By Transfer fees not considered 2,000
Financial books in Cost books
To Over-valuation of Closing Stock of By Net loss as per Financial books 2,70,000
finished goods in Cost books 7,000 ______
3,05,000 3,05,000
Q-17 The following information have been extracted from the cost records of JKL Manufacturing Company
Ltd:
Rs.
Stores:
Opening Balance 90,000
Purchases 4,80,000
Transfer from WIP 2,40,000
Issue to WIP 4,80,000
-240- Chapter-7 : Cost Accounting System
Q-20 A manufacturing company disclosed a net loss of `6,94,000 as per their cost accounts for the year ended
March 31,2020. The financial accounts however disclosed a net loss of `10,20,000 for the same period.
The following information was revealed as a result of scrutiny of the figures of both the sets of accounts.
(`)
(i) Factory Overheads under-absorbed 80,000
(ii) Administration Overheads over-absorbed 1,20,000
(iii) Depreciation charged in Financial Accounts 6,50,000
(iv) Depreciation charged in Cost Accounts 5,50,000
(v) Interest on investments not included in Cost Accounts 1,92,000
(vi) Income-tax provided 1,08,000
(vii) Interest on loan funds in Financial Accounts 4,90,000
(viii) Transfer fees (credit in financial books) 48,000
(ix) Stores adjustment (credit in financial books) 28,000
(x) Dividend received 64,000
PREPARE a memorandum Reconciliation Account.
Ans. Memorandum Reconciliation Accounts
Dr. Cr.
(` ) (` )
To Net Loss as per Costing 6,94,000 By Administration 1,20,000
books overheads over
recovered in cost
accounts
To Factory overheads under 80,000 By Interest on investment 1,92,000
absorbed in Cost not included in Cost
Accounts Accounts
To Depreciation under 1,00,000 By Transfer fees in 48,000
charged in Cost Accounts Financial books
To Income-Tax not provided 1,08,000 By Stores adjustment
in Cost Accounts (Credit in financial books) 28,000
To Interest on Loan Funds in 4,90,000 By Dividend received in 64,000
Financial Accounts financial books
By Net loss as per 10,20,000
________ Financial books ________
14,72,000 14,72,000
Q-21 XYZ Ltd. maintains a non-integrated accounting system for the purpose of management information.
The following are the data related with year 2020-21:
Particulars (` in `000)
Opening balances:
- Stores ledger control A/c 24,000
- Work-in-process control A/c 6,000
- Finished goods control A/c 1,29,000
- Building construction A/c 3,000
- Cost ledger control A/c 1,62,000
During the year following transactions took place:
Materials:
- Purchased 12,000
- Issued to production 15,000
- Issued to general maintenance 1,800
- Issued to building construction 1,200
Wages:
- Gross wages paid 45,000
- Indirect wages paid 12,000
- For building construction 3,000
Factory overheads:
- Actual amount incurred (excluding items shown above) 48,000
- Absorbed in building construction 6,000
- Under-absorbed 2,400
Royalty paid 1,500
Selling, distribution and administration overheads 7,500
Sales 1,35,000
At the end of the year, the stock of raw material and work-in-process was ` 1,65,00,000 and ` 75,00,000
respectively. The loss arising in the raw material account is treated as factory overheads. The building
under construction was completed during the year. Gross profit margin is 20% on sales.
Required:
PREPARE the relevant control accounts to record the above transactions in the cost ledger of the company
Ans. Cost Ledger Control Account
Particulars (` in `000) Particulars (` in `000)
To Costing P&L A/c 1,35,000 By Balance b/d 1,62,000
To Building Construction A/c 13,200 By Stores Ledger control A/c 12,000
To Balance c/d 1,44,900 By Wages Control A/c 45,000
By Factory overhead control A/c 48,000
By Royalty A/c 1,500
By Selling, Distribution and
Administration overheads 7,500
_______ By Costing P&L A/c 17,100
2,93,100 2,93,100
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -245-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -247-
Q-22 The financial books of a company reveal the following data for the year ended 31 st March, 2020:
(`)
Opening Stock:
Finished goods 625 units 1,06,250
Work-in-process 92,000
01.04.2019 to 31.03.2020
Raw materials consumed 16,80,000
Direct Labour 12,20,000
Factory overheads 8,44,000
Administration overheads (production related) 3,96,000
Dividend paid 2,44,000
Bad Debts 36,000
Selling and Distribution Overheads 1,44,000
Interest received 76,000
Rent received 92,000
Sales 12,615 units 45,60,000
Closing Stock: Finished goods 415 units 91,300
Work-in-process 82,400
The cost records provide as under:
Factory overheads are absorbed at 70% of direct wages.
Administration overheads are recovered at 15% of factory cost.
Selling and distribution overheads are charged at ` 6 per unit sold.
Opening Stock of finished goods is valued at ` 240 per unit.
The company values work-in-process at factory cost for both Financial and Cost Profit Reporting.
Required:
(i) PREPARE statements for the year ended 31st March, 2020 showing:
the profit as per financial records
the profit as per costing records.
(ii) PREPARE a statement reconciling the profit as per costing records with the profit as per financial
records.
Ans. (i) Statement of Profit as per financial records
(for the year ended March 31, 2020)
(` ) (` )
To Opening stock of Finished Goods 1,06,250 By Sales 45,60,000
To Work-in-process 92,000 By Closing stock of finished
Goods 91,300
To Raw materials consumed 16,80,000 By Work-in-Process 82,400
To Direct labour 12,20,000 By Rent received 92,000
To Factory overheads 8,44,000 By Interest received 76,000
To Administration overheads 3,96,000
To Selling & distribution
overheads 1,44,000
To Dividend paid 2,44,000
To Bad debts 36,000
To Profit 1,39,450 ________
49,01,700 49,01,700
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -249-
Working notes:
1. Number of units produced
Units
Sales 12,615
Add: Closing stock 415
Total 13,030
Less: Opening stock (625)
Number of units produced 12,405
2. Cost Sheet (`)
Raw materials consumed 16,80,000
Direct labour 12,20,000
Prime cost 29,00,000
Factory overheads 8,54,000
(70% of direct wages)
Factory cost 37,54,000
Add: Opening work-in-process 92,000
Less: Closing work-in-process (82,400)
Factory cost of goods produced 37,63,600
Administration overheads 5,64,540
(15% of factory cost)
Cost of production of 12,405 units 43,28,140
(Refer to working note 1)
Cost of production per unit:
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -251-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -253-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -255-
Q-26 X Ltd. maintains a non-integrated accounting system for the purpose of management information. The
following are the data related with year 2021-22:
Particulars Amount (‘000)
Opening balances:
- Stores ledger control A/c 48,000
- Work-in-process control A/c 12,000
- Finished goods control A/c 2,58,000
- Building construction A/c 6,000
- Cost ledger control A/c 3,24,000
During the year following transactions took place:
Materials:
- Purchased 24,000
- Issued to production 30,000
- Issued to general maintenance 3,600
- Issued to building construction 2,400
Wages:
- Gross wages paid 90,000
- Indirect wages paid 24,000
- For building construction 6,000
Factory overheads:
- Actual amount incurred (excluding items shown above) 96,000
- Absorbed in building construction 12,000
- Under-absorbed 4,800
Royalty paid 3,000
Selling distribution and administration overheads 15,000
Sales 2,70,000
At the end of the year, the stock of raw material and work-in-process was `3,30,00,000 and `15,00,000
respectively. The loss arising in the raw material account is treated as factory overheads. The building
under construction was completed during the year. Gross profit margin is 20% on sales.
Required:
PREPARE the relevant control accounts to record the above transactions in the cost ledger of the company.
Ans.
Cost Ledger Control Account
Particulars (` in ‘000) Particulars (` in ‘000)
To Costing P&L A/c 2,70,000 By Balance b/d 3,24,000
To Building Construction A/c 26,400 By Stores Ledger Control A/c 24,000
To Balance c/d 2,89,800 By Wages Control A/c 90,000
By Factory overhead control A/c 96,000 By Royalty A/c 3,000
By Selling, Distribution and
Administration overheads 15,000
_______ By Costing P&L A/c 34,200
5,86,200 5,86,200
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -257-
Working Note:
Cost of Goods sold = 2,70,000 × 80/100 = ` 2,16,000
---0---0---
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -259-
CHAPTER - 8
UNIT & BATCH COSTING (RECONCILIATION)
Q-1 BTL LLP. manufactures glass bottles for HDL Ltd., a pharmaceutical company, which is inayurvedic
medicines business..
BTL can produce 2,00,000 bottles in a month. Set-up cost of each production run is ` 5,200 and the cost
of holding one bottle for a year is ` 1.50.
As per an estimate HDL Ltd. can order as much as 19,00,000 bottles in a year spreading evenly throughout
the year.
At present the BTL manufactures 1,60,000 bottles in a batch.
Required:
(i) Compute the Economic Batch Quantity for bottle production.
(ii) Compute the annual cost saving to BTL by adopting the EBQ of a production.
2DS
Ans. Economic Batch Quantity (EBQ) =
C
Where, D = Annual demand for the product
S = Setting up cost per batch
C = Carrying cost per unit of production
(i) Computation of EBQ :
2 ×19,00,000 × ` 5,200
=
` 1.5
= 1,14,775 bottles
(ii) Computation of savings in cost by adopting EBQ:
Batch Size No. of Batch Set-up cost Carrying cost Total Cost
1,60,000 62,400 1,20,000
bottles 12 (` 5,200 × 12) (`1.5 ×1,20,000 ½ × 1,60,000) 1,82,400
1,14,775 88,081.25 86,081.25
bottles 17 (`5,200 × 88,40017) (`1.586,081.25 × ½ × 1,14,775) 1,74,481.25
Saving 7,918.75
Q-2 Explain ‘Job Costing’ and ‘Batch Costing’.
Ans. Job costing: In this method of costing, cost of each job is ascertained separately. It is suitable in all cases
where work is undertaken on receiving a customer’s order like a printing press, motor work shop, etc.
This method of costing is used for non- standard and non- repetitive products produced as per customer
specifications and against specific orders. Jobs are different from each other and independent of each
other. Each Job is unique.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -261-
Batch Costing: It is the extension of Job costing. Homogeneous products are produced in a continuous
production flow in lots. A batch may represent a number of small orders passed through the factory in
batch. Each batch here is treated as a unit of cost and thus separately costed. Here cost per unit is
determined by dividing the cost of the batch by number of units produced in the batch.
Q-3 Arnav Confectioners (AC) owns a bakery which is used to make bakery items like pastries, cakes and
muffins. AC use to bake at least 50 units of any item at a time. A customer has given an order for 600
cakes. To process a batch, the following cost would be incurred:
Direct materials - ` 5,000
Direct wages - ` 500 (irrespective of units)
Oven set- up cost - `750 (irrespective of units)
AC absorbs production overheads at a rate of 20% of direct wages cost. 10% is added to the total
production cost of each batch to allow for selling, distribution and administration overheads.
AC requires a profit margin of 25% of sales value.
Required:
(i) Determine the price to be charged for 600 cakes.
(ii) Calculate cost and selling price per cake.
(iii) Determine what would be selling price per unit If the order is for 605 cakes.
Ans. Statement of cost per batch and per order
No. of batch = 600 units ÷ 50 units = 12 batches
Particulars Cost per batch Total Cost
(` ) (` )
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -263-
Chargeable expenses
× Direct labour hours for batch
Direct labour hour for the month
Q-6 A Ltd. manufactures mother boards used in smart phones. A smart phone requires one mother board.
As per the study conducted by the Indian Cellular Association, there will be a demand of 180 million
smart phones in the coming year. A Ltd. is expected to have a market share of 5.5% of the total market
demand of the mother boards in the coming year. It is estimated that it costs ‘6.25 as inventory holding
cost per board per month and that the set-up cost per run of board manufacture is ‘33,500.
(i) COMPUTE the optimum run size for board manufacturing?
(ii) Assuming that the company has a policy of manufacturing 80,000 boards per run, CALCULATE how
much extra costs the company would be incurring as compared to the optimum run suggested in
(i) above?
Ans. (i) Computation of optimum run size
2×D × S
Optimum run size or Economic Batch Quantity (EBQ) =
C
Where, D= Annual demand i.e. 5.5% of 18,00,00,000 = 99,00,000 units
S= Set-up cost per run = `33,500
C= Inventory holding cost per unit per annum
= ` 6.25 × 12 months =`75
Q-7 The Profit and Loss account of ABC Ltd. for the year ended 31st March, 2021 is given below:
Profit and Loss account
(for the year ended 31st March, 2021)
To Direct Material 6,50,000 By Sales 15,00,000
(15000 units)
To Direct Wages 3,50,000 By Dividend received 9,000
To Factory overheads 2,60,000
To Administrative overheads 1,05,000
To Selling overheads 85,000
To Loss on sale of investments 2,000
To Net Profit 57,000 ________
15,09,000 15,09,000
• Factory overheads are 50% fixed and 50% variable.
• Administrative overheads are 100% fixed.
• Selling overheads are completely variable.
• Normal production capacity of ABC Ltd. is 20,000 units.
• Indirect Expenses are absorbed in the cost accounts on the basis of normal production capacity.
• Notional rent of own premises charged in Cost Accounts is amounting to ‘ 12,000.
You are required to:
(i) Prepare a Cost Sheet and ascertain the Profit as per Cost Records for the year ended 31st March,
2021.
(ii) Reconcile the Profit as per Financial Records with Profit as per Cost Records.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -265-
Q-8 Rollon Ltd. is committed to supply 96,800 bearings per annum to Racing Ltd. on steady basis. It is
estimated that it costs 25 paise as inventory carrying cost per bearing per month and the set-up cost per
run of bearing manufacture is ` 588.
(a) COMPUTE what would be the optimum run size for bearing manufacture?
(b) Assuming that the company has a policy of manufacturing 8,800 bearings per run, CALCULATE how
much extra costs the company would be incurring as compared to the optimum run suggested in
(a) above?
Ans. Optimum production run size (Q)
Q-9 The following data relates to the manufacturing project received for the budgeted output of 19,600
units. You are required to CALCULATE the selling price per unit covering a profit of 25% on the selling
price.
Direct materials: 40 sq. m. per unit @ ` 10.60 per sq. m.
Direct wages: Bonding department 48 hours per unit @ ` 25 per hour
Finishing department 30 hours per unit @ ` 19 per hour
Budgeted costs and hours per annum-
Variable overhead:
(`) Total hours
Bonding department 15,00,000 10,00,000
Finishing department 6,00,000 6,00,000
Fixed overhead-
(`)
Production 15,68,000
Selling and distribution 7,84,000
Administration (General) 3,92,000
Ans. Decision making Cost Sheet (per unit)
Particulars (Amount in `) (Amount in `)
Direct materials 40 m2 at ` 10.60 per m2 424
Direct wages:
Bonding department- 48 hours at ` 25 per hour 1,200
Finishing department- 30 hours at ` 19 per hour 570 1,770
Prime Cost 2,194
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -267-
Variable overhead:*
Bonding department- 48 hours at ` 1.50 per hour 72
Finishing department- 30 hours at ` 1.00 per hour 30 102
Variable production cost 2,296
Fixed production overhead# 80
Total production cost 2,376
Selling and distribution cost$ 40
Administration cost$ 20 60
Total Cost 2,436
Working Notes:
* Variable overhead rates-
Q-10 Brostom Ltd. manufactures ‘Stent’ that is used by hospitals in angioplasty, a procedure used to open
blocked coronary arteries without open-heart surgery. As per the estimates provided by Pharmaceutical
Industry Bureau, there will be a demand of 1 crore ‘Stents’ in the coming year. Brostom Ltd. is having a
market share of 10% of the total market demand of the Stents. It is estimated that it costs ` 3.00 as
inventory holding cost per stent per month and that the set-up cost per run of stent manufacture is `
450.
Required:
(i) WHAT would be the optimum run size for Stent manufacture?
(ii) WHAT is the minimum inventory holding cost?
Ans.
(i) Computation of Optimum Run size of ‘Stents’ or Economic Batch Quantity (EBQ)
Economic Batch Quantity (EBQ) =
Where, D = Annual demand for the Stents
= 1,00,00,000 × 10% = 10,00,000 units
S = Set- up cost per run
= ‘ 450
---0---0---
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -269-
CHAPTER - 9
JOB COSTING AND CONTRACT COSTING
Q-1 A factory uses job costing system. The following data are obtained from its books for the year ended
31st March, 2020:
Amount (`)
Direct materials 18,00,000
Direct wages 15,00,000
Selling and distribution overheads 10,50,000
Administration overheads 8,40,000
Factory overheads 9,00,000
Profit 12,18,000
(i) PREPARE a Job Cost sheet indicating the Prime cost, Cost of Production, Cost of sales and the Sales
value.
(ii) In 2019-20, the factory received an order for a job. It is estimated that direct materials required
will be `4,80,000 and direct labour will cost `3,00,000. DETERMINE what should be the price for
the job if factory intends to earn the same rate of profit on sales assuming that the selling and
distribution overheads have gone up by 15%. The factory overheads is recovered as percentage of
wages paid, whereas, other overheads as a percentage of cost of production, based on cost rates
prevailing in the previous year.
Ans. (i) Production Statement
For the year ended 31st March, 2020
Amount (`)
Direct materials 18,00,000
Direct wages 15,00,000
Prime Cost 33,00,000
Factory overheads 9,00,000
Cost of Production 42,00,000
Administration overheads 8,40,000
Selling and distribution overheads 10,50,000
Cost of Sales 60,90,000
Profit 12,18,000
Sales value 73,08,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -271-
Calculation of Rates:
` 9,00,000
1. Percentage of factory overheads to direct wages = ×100 = 60%
` 15,00,000
2. Percentage of administration overheads to Cost of production
` 8,40,000
×100 = 20%
` 42,00,000
3. Selling and distribution overheads = ` 10,50,000 × 115% = `12,07,500 Selling and distribution
overhead % to Cost of production
` 12,07,500
×100 = 28.75%
` 42,00,000
` 12,18,000
4. Percentage of profit to sales = ×100 = 16.67% or , 1/6
` 37,08,000
(ii) Calculation of price for the job received in 2019-20
Amount (`)
Direct materials 4,80,000
Direct wages 3,00,000
Prime Cost 7,80,000
Factory overheads (60% of ` 3,00,000) 1,80,000
Cost of Production 9,60,000
Administration overheads (20% of ` 9,60,000) 1,92,000
Selling and distribution overheads (28.75% of ` 9,60,000) 2,76,000
Cost of Sales 14,28,000
Profit (1/5 of ` 14,28,000) 2,85,600
Sales value 17,13,600
Q-2 Ispat Engineers Limited (IEL) undertook a plant manufacturing work for a client. It willcharge a profit
mark up of 20% on the full cost of the jobs. The following are the informationrelated to the job:
Direct materials utilised – `1,87,00,000
Direct labour utilised – 2,400 hours at `80 per hour
Budgeted production overheads are Rs. 48,00,000 for the period and are recovered on the basis of
24,000 labour hours.
Budgeted selling and administration overheads are `18,00,000 for the period and recovered on the
basis of total budgeted total production cost of `36,00,00,000.
Required:
Calculate the price to be charged for the job.
` 48,00,000
Production over heads ×2,400 hrs 4,80,000
24,000 hrs
` 18,00,000
36,00,00,000 × ` 1,93,72,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -273-
Ans. Dr. Contract Account for the year ended 31st March, 2019 Cr.
Particulars HP-1 (`) HP-2 (`) Particulars HP-1 (`) HP-2 (`)
To Balance b/d: W-I-P 7,80,000 2,80,000 By Closing material 47,000 52,000
at site
To Material purchased 6,20,000 8,10,000 By W-I-P:
To Wages: (`85,000+`12,000) 97,000 70,400 Value of work certified 20,50,000 16,10,000
(`62,000+`8,400) Cost of work not certified 1,90,000 1,40,000
To Donation to local club* 5,000 2,500
To Plant hire charges:
(`72,000x1/3) 24,000
(`57,000x1/3) 19,000
To Depreciation on concrete mixture**:
(`8,20,000x15%x180/365) 60,658
(`8,20,000x15%x100/365) 33,699
To Notional profit 7,00,342 5,86,401 _________ _________
22,87,000 18,02,000 22,87,000 18,02,000
* Assuming donation paid to local club was exclusively for the above projects, hence included in the
contract account.
** Depreciation on concrete mixture machine is charged on the basis of number of days used for the
projects, as it is clearly mentioned in the question that this machine can be used for other projects also.
(Land purchased and brokerage and registration fee paid for this purpose cannot be charged to contract
account, hence not included in the contract account)
Q-4 GVL Ltd. commenced a contract on April 1, 2018. The total contract was for ` 1,08,50,000. It was decided
to estimate the total profit and to take to the credit of Costing P & L A/c the proportion of estimated
profit on cash basis which work completed bear to the total contract. Actual expenditure in 2018-19 and
estimated expenditure in 2019-20 are given below:
2018-19 2019-20
Actual (`) Estimated (`)
Material issued 18,24,000 32,56,000
Labour : Paid: 12,20,000 15,20,000
Outstanding at end 96,000 1,50,000
Plant purchased 9,00,000 _
Expenses : Paid: 4,00,000 7,00,000
Outstanding at the end: _ 1,00,000
Prepaid at the end 90,000 _
Plant returned to stores (a historical stores) 3,00,000 6,00,000
(on Sep. 30, 2019)
Material at site 1,20,000 3,00,000
Work-in progress certified 51,00,000 Full
Work-in-progress uncertified 1,60,000 _
Cash received 40,00,000 Full
The plant is subject to annual depreciation @ 20% of WDV cost. The contract is likely to be completed
on September 30, 2019.
Required:
(i) PREPARE the Contract A/c for the year 2018-19.
(ii) ESTIMATE the profit for the contract.
Ans. GVL Ltd.
Contract A/c
(April 1, 2018 to March 31, 2019)
Particulars Amount (`) Particulars Amount (`)
To Materials Issued 18,24,000 By Plant returned to Stores
(Working Note 1) 2,40,000
To Labour 12,20,000 By Materials at Site 1,20,000
Add: Outstanding 96,000 13,16,000 By W.I.P.
To Plant Purchased 9,00,000 Certified 51,00,000
To Expenses 4,00,000 Uncertified 1,60,000 52,60,000
Less: Prepaid 90,000 3,10,000 By Plant at Site
(Working Note 2) 4,80,000
To Notional Profit 17,50,000 _________
61,00,000 61,00,000
GVL Ltd.
Contract A/c
(April 1, 2018 to September 30, 2019)
(For Computing estimated profit)
Particulars Amount (`) Particulars Amount (`)
To Materials Issued
(` 18,24,000 + ` 32,56,000) 50,80,000 By Material at Site 3,00,000
To Labour Cost
(`12,20,000 + `96,000
+`14,24,000* + `1,50,000) 28,90,000 By Plant returned to
Storeson 31.03.2019. 2,40,000
To Plant purchased 9,00,000 By Plant returned to
Storeson 30.09.2019
(Working Note3) 4,32,000
To Expenses
(`3,10,000 + `7,90,000
+ `1,00,000) 12,00,000 By Contractee A/c 1,08,50,000
To Estimated profit 17,52,000 ________
1,18,22,000 1,18,22,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -275-
Working Notes
(` )
1. Value of the Plant returned to Stores on 31.03.2019
Historical Cost of the Plant returned 3,00,000
Less: Depreciation @ 20% of WDV for one year (60,000)
2,40,000
2. Value of Plant at Site 31.03.2019
Historical Cost of Plant at Site (`9,00,000 – `3,00,000) 6,00,000
Less: Depreciation @ 20% on WDV for one year (1,20,000)
4,80,000
3. Value of Plant returned to Stores on 30.09.2019
Value of Plant (WDV) on 31.3.2019 4,80,000
Less: Depreciation @ 20% of WDV for a period of 6 months (48,000)
4,32,000
4. Expenses Paid for the year 2018-19
Total expenses paid 4,00,000
Less: Pre-paid at the end (90,000)
3,10,000
Q-5 The following data presented by the supervisor of a factory for a Job.
` per unit
Direct Material 120
Direct Wages @ ` 4 per hour
(Departments A-4 hrs,B-7 hrs,C-2 hrs & D-2 hrs)
Chargeable Expenses 20
Total 200
Analysis of the Profit and Loss Account for the year ended
31st March, 2019
` ` `
Material 2,00,000 Sales 4,30,000
Direct Wages
Dept. A 12,000
Dept.B 8,000
Dept.C 10,000
Dept.D 20,000 50,000
Special Store items 6,000
Overheads
Dept.A 12,000
Dept.B 6,000
Dept.C 9,000
Dept.D 17,000 44,000
Gross Profit c/d 1,30,000 _______
4,30,000 4,30,000
Selling Expenses 90,000 Gross Profit b/d 1,30,000
Net Profit 40,000 _______
1,30,000 1,30,000
It is also to be noted that average hourly rates for all the four departments are similar.
Required:
(i) Prepare a Job Cost Sheet.
(ii) Calculate the entire revised cost using the above figures as the base.
(iii) Ad4 20% profit on selling price to determine the selling price.
Ans. Job Cost Sheet
Customer Details _______ Job No._________________
Date of commencement ________ Date of completion _________
Particulars Amount (`)
Direct materials 120
Direct wages:
Deptt. A ` 4.00 × 4 hrs. ` 16.00
Deptt. B ` 4.00 × 7 hrs. ` 28.00
Deptt. C ` 4.00 × 2 hrs. ` 8.00
Deptt. D ` 4.00 × 2 hrs. ` 8.00 60
Chargeable expenses 20
Prime cost 200
Overheads
` 12,000
Deptt. A = ×100 = 100% of ` 16 ` 16
` 12,000
` 6,000
Deptt. B = ×100 = 75% of ` 28 ` 21
` 8,000
` 9,000
Deptt. C = ×100 = 90% of ` 8 ` 7.20
` 10,000
` 9,000
= ×100 = 90% of ` 8 = ` 7.20
` 10,000
` 17,000
Deptt. D = ×100 = 85% of ` 8 ` 6.80 51.00
` 20,000
Works cost 251.00
` 90,000
Selling expenses = ×100 = 30% of work cost 75.30
` 3,00,000
Total cost 326.30
Profit (20% profit on selling price i.e 25% of total cost) 81.58
Selling price 407.88
Q-6 A construction company undertook a contract at an estimated price of ` 108 lakhs, which includes a
budgeted profit of ` 18 lakhs. The relevant data for the year ended 31.03.20X8 are as under:
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -277-
( `000)
Materials issued to site 5,000
Direct wages paid 3,800
Plant hired 700
Site office costs 270
Materials returned from site 100
Direct expenses 500
Work certified 10,000
Work not certified 230
Progress payment received 7,200
A special plant was purchased specifically for this contract at ` 8,00,000 and after use on this contract till
the end of 31.02.20X8, it was valued at ` 5,00,000. This cost of materials at site at the end of the year was
estimated at ` 18,00,000 Direct wages accrued as on 31.03.20X8 was ` 1,10,000.
Required
PREPARE the Contract Account for the year ended 31st March, 20X8.
Ans. Contract Account for the year ended 31st March, 20X8
(`’000) (`’ 000)
To Material issued to site 5,000 By Material at site 1,800
To Direct wages 3,800 By Material returned 100
Add: Outstanding wages 110 3,910 By Work-in-progress:
To Plant hire 700 - Value of work certified 10,000
To Site office cost 270 - Work uncertified 230
To Direct expenses 500
To Depreciation (special plant) 300
To Notional profit c/d 1,450 _____
12,130 12,130
Q-7 A company has been asked to quote for a job. The company aims to make a net profit of 30% on sales.
The estimated cost for the job is as follows:
Direct materials 10 kg @`10 per kg
Direct labour 20 hours @ `5 per hour
Variable production overheads are recovered at the rate of ` 2 per labour hour.
Fixed production overheads for the company are budgeted to be `1,00,000 each year and are recovered
on the basis of labour hours.
There are 10,000 budgeted labour hours each year. Other costs in relation to selling, distribution and
administration are recovered at the rate of `50 per job.
DETERMINE quote for the job by the Company.
Ans. Determination of quotation price for the job
Cost (`)
Direct Material (10kg × `10) 100
Direct Labour (20hrs × `5) 100
Variable production overhead (20hrs × `2) 40
1,00,000
Fixed Overhead 20 hours
10,000 budgeted hours
-278- Chapter-9 : Job Costing & Contrtact Costing
Other costs 50
Total costs 490
Net profit is 30% of sales, therefore total costs represent 70% (` 490 × 100) ÷ 70 = ` 700 price to quote for
job.
To check answer is correct; profit achieved will be ` 210 (` 700 - ` 490)
= ` 210 ÷ ` 700 = 30%
Q-8 A factory uses job costing. The following data are obtained from its books for the year ended 31st
March, 2018:
Amount (`)
Direct materials 9,00,000
Direct wages 7,50,000
Selling and distribution overheads 5,25,000
Administration overheads 4,20,000
Factory overheads 4,50,000
Profit 6,09,000
Required:
(i) PREPARE a Job Cost sheet indicating the Prime cost, Cost of Production, Cost of sales and the Sales
value.
(ii) In 2018-19, the factory received an order for a job. It is estimated that direct materials required
will be ` 2,40,000 and direct labour will cost ` 1,50,000. DETERMINE what should be the price for
the job if factory intends to earn the same rate of profit on sales assuming that the selling and
distribution overheads have gone up by 15%. The factory overheads is recovered as percentage of
wages paid, whereas, other overheads as a percentage of cost of production, based on cost rates
prevailing in the previous year.
Ans.
(i) Production Statement
For the year ended 31st March, 2018
Amount (`)
Direct materials 9,00,000
Direct wages 7,50,000
Prime Cost 16,50,000
Factory overheads 4,50,000
Cost of Production 21,00,000
Administration overheads 4,20,000
Selling and distribution overheads 5,25,000
Cost of Sales 30,45,000
Profit 6,09,000
Sales value 36,54,000
Calculation of Rates:
` 4,50,000
1. Percentage of factory overheads to direct wages = x 100 = 60%
`7,50,000
2. Percentage of administration overheads to Cost of production
` 4,20,000
100 = 20%
`21,00,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -279-
` 6,09,000
4. Percentage of profit to sales = 100 = 16.67%
`36,54,000
(ii) Calculation of price for the job received in 2018 -19
Amount (`)
Direct materials 2,40,000
Direct wages 1,50,000
Prime Cost 3,90,000
Factory overheads (60% of `1,50,000) 90,000
Cost of Production 4,80,000
Administration overheads (20% of `4,80,000) 96,000
Selling and distribution overheads (28.75% of `4,80,000) 1,38,000
Cost of Sales 7,14,000
Profit (20% of `7,14,000) 1,42,800
Sales value 8,56,800
Q-9 A company processes a raw material in its Department 1 to produce three products, viz. A, B and X at the
same split-off stage. During a period 1,80,000 kgs of raw materials were processed in Department 1 at
a total cost of ` 12,88,000 and the resultant output of A, B and X were 18,000 kgs, 10,000 kgs and 54,000
kgs respectively. A and B were further processed in Department 2 at a cost of ` 1,80,000 and ` 1,50,000
respectively.
X was further processed in Department 3 at a cost of `1,08,000. There is no waste in further processing.
The details of sales affected during the period were as under:
A B X
Quantity Sold (kgs.) 17,000 5,000 44,000
Sales Value (`) 12,24,000 2,50,000 7,92,000
There were no opening stocks. If these products were sold at split-off stage, the selling prices of A, B
and X would have been ` 50, ` 40 and ` 10 per kg respectively.
Required:
(i) Prepare a statement showing the apportionment of joint costs to A, B and X.
(ii) Prepare a statement showing the cost per kg of each product indicating joint cost and further
processing cost and total cost separately.
(iii) PREPARE a statement showing the product wise and total profit for the period.
(iv) Decide with supporting calculations as to whether any or all the products should be further
processed or not.
Ans. (i) Statement showing the apportionment of joint costs to A, B and X
Products A B X Total
Output (kg) 18,000 10,000 54,000
Sales value at the point of 9,00,000 4,00,000 5,40,000 18,40,000
split off (`) (` 50 x 18,000) (` 40 x 10,000) (` 10 x 54,000)
` 12,88,000 ` 12,88,000
of sales value `18,40,000 ` 9,00,000 `18,40,000 ` 4,00,000
` 12,88,000
`18,40,000 ` 5,40,000
at the point of
split off (`)
(ii) Statement showing the cost per kg. of each product
(indicating joint cost; further processing cost and total cost separately)
Products A B X
Joint costs apportioned (`) : (I) 6,30,000 2,80,000 3,78,000
Production (kg) : (II) 18,000 10,000 54,000
Joint cost per kg (`): (I ÷ II) 35 28 7
Further processing Cost per kg. (`) 10 15 2
Products A B X Total
Closing stock (kgs.) 1,000 5,000 10,000
Cost per kg (`) 45 43 9
Closing stock value 45,000 2,15,000 90,000 3,50,000
(`) (` 45 x 1,000 kg) (` 43 x 5,000 kg) (` 9x10,000 kg)
(iv) Calculations for processing decision
Products A B X
Selling price per kg at the point of split off (`) 50 40 10
Selling price per kg after further processing (`) 72 50 18
(Refer to working Note 1)
Incremental selling price per kg (`) 22 10 8
Less: Further processing cost per kg (`) (10) (15) (2)
Incremental profit (loss) per kg (`) 12 (5) 6
Product A and X has an incremental profit per unit after further processing, hence, these two products
may be further processed. However, further processing of product B is not profitable hence, product B
shall be sold at split off point.
Q-10 A contractor prepares his accounts for the year ending 31st March each year. He commenced a contract
on 1st September, 2018. The following information relates to contract as on 31st March, 2019:
Material sent to site ` 18,75,000
Wages paid ` 9,28,500
Wages outstanding at end ` 84,800
Sundry expenses ` 33,825
Material returned to supplier ` 15,000
Plant purchased ` 3,75,000
Salary of supervisor ` 15,000 per month
(Devotes 1/3rd of his time on contract)
Material at site as on 31-03-2019 ` 2,16,800
Some of material costing ` 10,000 was found unsuitable and was sold for ` 11,200. On 31-12-2018 plant
which costs ` 25,000 was transferred to some other contract and on 31-01-2019 plant which costs `
32,000 was returned to stores. The plant is subject to annual depreciation @ 15% on written down
value method.
The contract price is ` 45,00,000. On 31st March, 2019 two-third-of the contract was completed. The
architect issued certificate covering 50% of the contract price.
Prepare Contract A/c and show the notional profit or loss as on 31st March, 2019.
Ans. Contract Account as on 31-03-2019
Particulars (`) Particulars (`)
To Materials sent to site 18,75,000 By Material returned toSupplier 15,000
To Wages paid 9,28,500 By Material sold 11,200
Add: Outstanding 84,800 10,13,300 By Plant transferred toot her contract 23,750
To Plant purchased 3,75,000 By Plant returned tostores 30,000
-282- Chapter-9 : Job Costing & Contrtact Costing
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -283-
A plant was purchased for ` 12,00,000 on 1st November, 2017 and was in use at the site upto 31st March, 2018.
Depreciation is to be charged on plant @ 15% per annum on straight line basis. Material costing ` 50,000 was
stolen from the site.
You are required to:
(i) Prepare contract account for the year ended 31st March, 2018 showing the profit to be taken to Profit &
Loss Account.
(ii) Prepare Balance Sheet showing the relevant items.
Ans.
(i) Contract Account
Particulars (`’000) (`’000) Particulars (`’000) (`’000)
To Material purchased 6,800 By Material returned 150
” Direct wages 3,450 “ Work-in-progress:
Less: Prepaid wages (50) 3,400 Value of work certified 11,800
(`9,440 ÷ 0.8)
” Salaries 200 Cost of work uncertified 500
Add: Outstanding 100 12,300
300 “ Material stolen at Site 50
” Depreciation on Plant 75 ” Material at site 175
{(`1,200× 15%) × (5÷12)}
” Costing P&L A/c 2,100
(Notional profit)
(bal. figure) ______ ______
12,675 12,675
(ii) Balance Sheet (extract) as on 31st March, 2018
Liabilities (`’000) Assets (`’000)
Capital Plant at site 1,125
Add: Notional Profit 2,100 Work in Progress
Outstanding Salary 100 Work certified 11,800
Work uncertified 500
12,300
Cash & Bank (in transit) 9,440 2,860
Prepaid Direct wages 50
Material at site 175
Q-13 M/s. Bansals Construction Company Ltd. took a contract for Rs. 60,00,000 expected to be completed in
three years. T he following particulars relating to the contract are available:
20X7 (Rs.) 20X8 (Rs.) 20X9 (Rs.)
Materials 6,75,000 10,50,000 9,00,000
Wages 6,20,000 9,00,000 7,50,000
T ransportation cost 30,000 90,000 75,000
Other expenses 30,000 75,000 24,000
Cumulative work certified 13,50,000 45,00,000 60,00,000
Cumulative work uncertified 15,000 75,000 —
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -285-
Plant costing Rs. 3,00,000 was bought at the commencement of the contract. Depreciation was to be
charged at 25% per annum, on the written down value method. T he contractee pays 75% of the value
of work certified as and when certified, and makes the final payment on completion of the contract.
You are required to PREPARE a contract account for th ree years .
Ans. Contract Account (For the year ended 20X7)
Particulars (Rs.) Particulars (Rs.)
To Materials 6,75,000 By Plant at site c/d 2,25,000
(75% of Rs.3,00,000)
” Wages 6,20,000 ” Work-in-progress c/d:
” Transportation cost 30,000 - Work certified 13,50,000
” Other expenses 30,000 - Work uncertified 15,000 13,65,000
” Plant 3,00,000 ” Costing P & L A/c 65,000
(Loss for the year)
16,55,000 16,55,000
Contract Account (For the year ended 20X8)
Particulars (Rs.) Particulars (Rs.)
To Plant at site b/d 2,25,000 By Plant at site c/d 1,68,750
(75% of Rs.2,25,000)
” Work-in-progress b/d: ” Work-in-progress c/d:
- Work certified 13,50,000 - Work certified 45,00,000
-Work uncertified 15,000
13,65,000 - Work uncertified 75,000 45,75,000
” Materials 10,50,000
” Wages 9,00,000
” Transportation cost 90,000
” Other expenses 75,000
” Costing P&L A/c 10,38,750
(Notional Profit for the year) ________ _________
47,43,750 47,43,750
Contract Account (For the year ended 20X9)
Particulars (Rs.) Particulars (Rs.)
To Plant at site b/d 1,68,750 By Plant at site c/d 1,26,563
(75% of Rs.1,68,750)
” Work-in-progress b/d: ” Contractee A/c 60,00,000
- Work certified 45,00,000 ” Costing P&L A/c 3,66,187
(Notional Loss for the year)
-Work uncertified 75,000 45,75,000
” Materials 9,00,000
” Wages 7,50,000
” Transportation cost 75,000
” Other expenses 24,000 ________
64,92,750 64,92,750
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -287-
Labour:
L1 60,000 15 18 +3 +1,80,000
L2 40,000 30 35 +5 +2,00,000
Labour escalation claim 3,80,000
Statement showing Final Contract Price
(Rs.) (Rs.)
Agreed contract price 1,50,00,000
Add: Agreed escalation claim:
Material Cost 1,60,000
Labour Cost 3,80,000 5,40,000
Final Contract Price 1,55,40,000
(ii) Contract Account
Dr Cr.
Particulars (Rs.) Particulars (Rs.)
To Material: By Contractee’s A/c 1,55,40,000
A – (3,400 × Rs. 1,100) 37,40,000
B – (2,300 × Rs. 700) 16,10,000
C – (600 × Rs. 3,900) 23,40,000
D – (90 × Rs. 31,500) 28,35,000 1,05,25,000
To Labour:
L1 – (56,000 × Rs.18) 10,08,000
L2 – (38,000 × Rs.35) 13,30,000 23,38,000
To Other expenses 13,45,000
To Estimated Profit 13,32,000 __________
1,55,40,000 1,55,40,000
Q-16 XYZ LLP, contractors and civil engineers, are building a new wing to a school. T he quoted fixed price for
the contract is Rs.30,00,000. Work commenced on 1st January 20X8 and is expected to be completed on
schedule by 30 June 20X9.
Data relating to the contract at the year ended 31st March 20X9 is as follows.
Amount (Rs.)
Plant sent to site at commencement of contract 2,40,000
Hire of plant and equipment 77,000
Materials sent to site 6,62,000
Materials returned from site 47,000
Direct wages paid 9,60,000
Wage related costs 1,32,000
Direct expenses incurred 34,000
Supervisory staff salaries - Direct 90,000
- Indirect 20,000
Regional office expenses apportioned to contract 50,000
Head office expenses apportioned to contract 30,000
Surveyor’s fees 27,000
Progress payments received from school 18,00,000
Additional information:
1. Plant is to be depreciated at the rate of 25% per annum following straight line method, with no residual
value.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -289-
210
= x 100 = 16.36%
1,284
(b) Labour Turnover under Flux Method
= No.of employees (Joined Separated) during the year x 10
Average no.of employees onroll
= No.of employees (Re placed New recruited Separated) during the year x 100
Average no.of employees onroll
1,234 + 210
x 10 = 112.46%
1,284
Labour Turnover calculated by the executive trainee of the Personnel department is incorrect as it has
not taken the No. of new recruitment while calculating the labour turnover under Flux method.
Q-19 APFL Ltd. deals in plumbing materials and also provides plumbing services to its customers. On 12th
August, 2019, APFL received a job order for a students’ hostel to supply and fitting of plumbing materials.
The work is to be done on the basis of specification provided by the hostel owner. Hostel will be
inaugurated on 5th September, 2019 and the work is to be completed by 3rd September, 2019. Following
are the details related with the job work:
Direct Materials
APFL uses a weighted average method for the pricing of materials issues.
Opening stock of materials as on 12th August 2019:
• 15mm GI Pipe, 12 units of 15 feet size @ Rs.600 each
• 20mm GI Pipe, 10 units of 15 feet size @ Rs.660 each
• Other fitting materials, 60 units @ Rs. 26 each
• Stainless Steel Faucet, 6 units @ Rs. 204 each
• Valve, 8 units @ Rs. 404 each
Purchases:
On 16th August 2019:
• 20mm GI Pipe, 30 units of 15 feet size @ Rs. 610 each
• 10 units of Valve @ Rs. 402 each
On 18th August 2019:
• Other fitting materials, 150 units @ Rs. 28 each
• Stainless Steel Faucet, 15 units @ Rs. 209 each
On 27th August 2019:
• 15mm GI Pipe, 35 units of 15 feet size @ Rs.628 each
• 20mm GI Pipe, 20 units of 15 feet size @ Rs.660 each
• Valve, 14 units @ Rs. 424 each
Issues for the hostel job:
On 12th August 2019:
• 20mm GI Pipe, 2 units of 15 feet size
• Other fitting materials, 18 units
-292- Chapter-9 : Job Costing & Contrtact Costing
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -293-
The following balances relating to the contract No. 999 for the year ended on March 31, 20X7 and March
31, 20X8 are available:
as on 31st March, 20X7 as on 31st March, 20X8
Work certified 12,00,000 35,00,000
Work uncertified 20,000 40,000
Materials at site 15,000 30,000
Wages outstanding 10,000 20,000
The contractor receives 75% of work certified in cash.
PREPARE Contract Account and Contractee's Account.
Ans. Contract No. 999 Account for the year ended 31st March, 20X8
Dr. Cr.
Particulars Amount(Rs.) Particulars Amount(Rs.)
To Work in progress b/d: By Material returned to store 30,000
- Work certified 12,00,000 By Material returned tosuppliers 20,000
- Work uncertified 20,000 By Stock (Material) c/d 30,000
To Stock (Materials) b/d 15,000 By Work in progress c/d:
To Material purchased 1,60,000 - Work certified 35,00,000
To Material issued 5,00,000 - Work uncertified 40,000
To Wages paid 7,00,000
Less: Opening O/s (10,000)
Add: Closing O/s 20,000 7,10,000
To Drawing and maps* 60,000
To Sundry expenses 15,000
To Electricity charges 25,000
To Plant hire expenses 60,000
To Sub- contract cost 20,000
To Notional profit c/d
(balancing figure) 8,35,000 _______-
36,20,000 36,20,000
*Assumed that expenses incurred for drawing and maps are used exclusively for this contract only.
Dr. Contractee’s Account Cr.
Particulars Amount(Rs.) Particulars Amount(Rs.)
To Balance c/d
(Rs. 35,00,000 × 75%) 26,25,000 By Balance b/d
(75% of Rs. 12,00,000) 9,00,000
________ By Bank A/c 17,25,000
26,25,000 26,25,000
Q-21 AP Ltd. received a job order for supply and fitting of plumbing materials. Following are the details
related with the job work:
Direct Materials
AP Ltd. uses a weighted average method for the pricing of materials issues.
Opening stock of materials as on 12th August 2020:
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -295-
6 × `204 + 15 × `209
15 units × 3,113.57
75%
- Valve
65, 643, 95
Add: 25% Profit on Job Price × 25% 21,881.32
75%
87,525.27
Working Note:
1. Cost of 15mm GI Pipe
Date Amount (`)
17-08-2020 8 units × ` 600 4,800.00
4 x 600 + 35 x 628
28-08-2020 10 units × 6,251.28
39 units
11,051.28
2. Cost of 20mm GI Pipe
Date Amount (`)
12-08-2020 2 units × ` 660 1,320.00
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -297-
12 x 26 + 150 x 28
28-08-2020 34 units × 946.96
162 units
12 x 26 + 150 x 28
30-08-2020 60 units × 1,671.11
162 units
3,866.07
Q-22 A contractor has entered into a long term contract at an agreed price of `18,70,000 subject to an
escalation clause for materials and wages as spelt out in the contract and corresponding actuals are as
follows:
Standard Actual
Materials Qty (tons) Rate (`) Qty (tons) Rate (`)
A 6,000 50.00 6,050 48.00
B 3,000 80.00 2,950 79.00
C 2,500 60.00 2,600 66.00
Wages Hours Hourly Rate (`) Hours Hourly Rate (`)
X 3,000 70.00 3,100 72.00
Y 2,500 75.00 2,450 75.00
Z 3,000 65.00 3,100 66.00
Reckoning the full actual consumption of material and wages, the company has claimed a final price
of ` 18,94,100. Give your ANALYSIS of admissible escalation claim and indicate the final price payable.
Ans.
Standard Standard Actual Rate Variation in Rate Escalation
Qty/Hrs. Rate (`) (` ) (` ) Claim (`)
(a) (b) (c) (d) = (c)–(b) (e) =(a) × (d)
Materials
A 6,000 50.00 48.00 (–) 2.00 (–) 12,000
B 3,000 80.00 79.00 (–) 1.00 (–) 3,000
C 2,500 60.00 66.00 (+) 6.00 15,000
Materials escalation claim: (A) 0
Wages
X 3,000 70.00 72.00 (+) 2.00 6,000
Y 2,500 75.00 75.00 - -
Z 3,000 65.00 66.00 (+) 1.00 3,000
Wages escalation claim: (B) 9,000
Final claim: (A + B) 9,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -299-
(ii) These contracts are preferred when the cost of material and labour is not steady and the contract
completion may take number of years.
(iii) The different costs to be included in the execution of the contract are mutually agreed, so that no
dispute may arise in future in this respect. Under such type of contracts, contractee is allowed to
check or scrutinize the concerned books, documents and accounts.
(iv) Such a contract offers a fair price to the contractee and also a reasonable profit to the contractor.
The contract price here is ascertained by adding a fixed and mutually pre-decided component of profit
to the total cost of the work.
Q-24 From the following particulars, COMPUTE Notional profit and estimated profit on a contract (which has
been 80% complete):
(`)
Total expenditure to date 4,00,000
Estimated further expenditure to complete the contract
(including contingencies) 22,000
Contract price 5,44,000
Work certified 4,89,600
Work uncertified 30,200
Cash received 3,91,680
Ans.
Computation of Notional Profit (`)
Value of work certified 4,89,600
Less: Cost of work certified
(` 4,00,000 - ` 30,200) 3,69,800
Notional profit 1,19,800
Computation of Estimated Profit (`)
Contract price 5,44,000
Less: Estimated total cost
Cost of work to date 4,00,000
Estimated further expenditure to complete the contract 22,000 4,22,000
Estimated profit 1,22,000
Q-25 Brick Constructions Ltd. commenced a contract on April 1,2020. The contract was for ` 10,00,000. The
following information relates to the Contract as on 31st March, 2021:
• The value of work completed up to Feb. 28, 2021 was certified by the architect and as a matter of
policy, the Contractee has retained ` 1,30,000 as retention money which is 20% of the certified
work and paid the balance amount.
• The cost of work completed subsequent to the architect’s certificate was of ` 30,000.
• The expenditure incurred related to material purchase, wages and other chargeable expenses
were ` 5,10,000
• Materials of the value of ` 20,000 were lying on the site.
• A special plant was purchased specifically for this contract at ` 40,000 and after use on this contract
till 31st March, 2021, it was valued at ` 25,000.
You are required to compute the value of Work Certified, Cash received for certified work and Notional
profit of the contract for the year ended on 31st March, 2021.
Price of materials and wages has been increased by 25%, the value before price increase is:
Cash received on account to date was ` 70,00,000, representing 80% of the work certified.
The contract would be completed by 31st December, 2020 and the contractor estimated further expenditure
that would be incurred in completion of the contract:
A sum of ` 12,50,000 would have to be spent on the plant and the residual value of the plant on the
completion of the contract would be ` 1,50,000.
Establishment charges would cost the same amount per month as in the previous year.
` 4,32,000 would be sufficient to provide for contingencies.
Required:
PREPARE a Contract Account for the year ended 31st March, 2020, and CALCULATE estimated total profit on
this contract.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -303-
Working Note:
Calculation of Factory Cost in 2019-20
Particulars Amount (`)
Opening Stock of Material 15,00,000
Add: Purchase of Material 1,80,50,000
Less: Closing Stock of Material (20,00,000)
Material Consumed 1,75,50,000
Direct Labour 90,50,000
Prime Cost 2,66,00,000
Factory Overhead 30,80,000
Factory Cost 2,96,80,000
(ii) Job Cost Sheet for the order received in 2020-21
Particulars Amount (`)
Materia 80,00,000
Labour 40,50,000
Factory Overhead (34% of ` 40,50,000) 13,77,000
Factory Cost 1,34,27,000
Administrative Overhead (6.91% of ` 1,34,27,000) 9,27,806
Cost of delivery 4,50,000
Total Cost 1,48,04,806
Add: Profit @ 25% of Sales or 33.33% of cost 49,34,935
Sales value (Price to be quoted for the order) 1,97,39,741
Hence the price to be quoted is ` 1,97,39,741
Q-29 KJ Motors Ltd. is a manufacturer of auto components. Following are the details of expenses for the year
2020-21:
(`)
(i) Opening Stock of Material 15,00,000
(ii) Closing Stock of Material 20,00,000
(iii) Purchase of Material 1,80,50,000
(iv) Direct Labour 90,50,000
(v) Factory Overhead 30,80,000
(vi) Administrative Overhead 20,50,400
During the FY 2021-22, the company has received an order from a car manufacturer where it estimates
that the cost of material and labour will be ` 80,00,000 and ` 40,50,000 respectively. The company
charges factory overhead as a percentage of direct labour and administrative overheads as a percentage
of factory cost based on previous year’s cost.
Cost of delivery of the components at customer’s premises is estimated at ` 9,50,000.
You are required to:
(i) CALCULATE the overhead recovery rates based on actual costs for 2020-21.
(ii) PREPARE a Job cost sheet for the order received and the price to be quoted if the desired profit is
25% on sales.
Ans.
(i) Calculation of Overhead Recovery Rate:
Factory Overhead in 2020 - 21
Factory Overhead Recovery Rate = = × 100
Direct labour cost in 2020 - 21
30,80, 000
== × 100 = 34% of Direct labour
90, 50, 000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -305-
90,000
18,52,000 18,52,000
To works cost 17,02,000 By work in progress:
To Costing P& L (Notional profit) 6,10,750 Work certified 21,00,000
________ Work uncertified 2,12,750 23,12,750
23,12,750 23,12,750
Working Note:
Calculation of Value of work uncertifiedCost incurred till date 17,02,000
Estimate total cost [17,02,000/80%] 21,27,500
Cost of work certified till date (21,27,500 ×70%) 14,89,250
Cost of uncertified work (17,02,000 –14,89,250) 2,12,750
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -307-
Q-31 A contractor prepares his accounts for the year ending 31st March each year. He commenced a contract
on 1st July, 2021.
The following information relates to the contract as on 31st March, 2022:
(`)
Material issued 7,53,000
Wages 16,96,800
Salary to Foreman 2,43,900
A machine costing ` 7,80,000 has been on the site for 146 days, its working life is estimated at 7 years
and its final scrap value at ` 45,000.
A supervisor, who is paid ` 24,000 p.m. has devoted one-half of his time to this contract.
All other expenses and administration charges amount to ` 4,09,500.
Material in hand at site costs ` 1,06,200 on 31st March, 2022.
The contract price is ` 60,00,000. On 31st March, 2022 two-third of the contract was completed. The
architect issued certificates covering 50% of the contract price, and the contractor had been paid `
22,50,000 on account.
PREPARE Contract A/c and show the notional profit or loss as on 31st March, 2022.
Ans. Contract Account
Particulars (`) Particulars (`)
To Material issued 7,53,000 By Machine (Working note 1) 7,38,000
” Wages 16,96,800 ” Material (in hand) 1,06,200
” Foreman’s salary 2,43,900 ” Works cost (balancing figure) 31,47,000
” Machine 7,80,000
” Supervisor’s salary (` 24,000 × 9)/2 1,08,000
” Administrative charges 4,09,500
39,91,200 39,91,200
” Works cost 31,47,000 ” Value of work certified 30,00,000
” Costing P&L A/c 6,39,750 ” Cost of work uncertified
(Notional profit) (Working Note 2) 7,86,750
37,86,750 37,86,750
Working notes:
1. Written down value of Machine:
Hence, the value of machine after the period of 146 days = ` 7,80,000 – ` 42,000 = ` 7,38,000
2. The cost of 2/3rd of the contract is ` 31,47,000
Cost of 50% of the contract which has been certified by the architect is ` 23,60,250. Also, the cost of the
contract, which has been completed but not certified by the architect is ` 7,86,750.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -309-
Required:
Prepare a reconciliation statement showing the profit as per financial records.
Ans. Statement of Reconciliation
(Reconciling the profit as per costing records with the profit as per financial records)
(` ) (` )
Net Profit as per Cost Accounts 3,60,740
Add:
Over recovery of selling overheads in cost accounts 10,250
Rent received credited in financial accounts 5,450 15,700
376,440
Less:
Over valuation of closing stock in cost accounts 7,300
Bad debts provided in financial accounts 3,250
Income tax provided in financial accounts 15,900
Loss on sale of capital asset debited in financial accounts 5,800
Under recovery of administration overheads in cost accounts 3,600 35,850
Profit as per Financial Accounts 3,40,590
---0---0---
CHAPTER- 10
PROCESS & OPERATION COSTING
Q-1 Star Ltd. manufactures chemical solutions for the food processing industry. The manufacturing takes
place in a number of processes and the company uses FIFO method to value work-in-process and
finished goods. At the end of the last month, a fire occurred in the factory and destroyed some of
papers containing records of the process operations for the month.
Star Ltd. needs your help to prepare the process accounts for the month during which the fire occurred.
You have been able to gather some information about the month’s operating activities but some of the
information could not be retrieved due to the damage. The following information was salvaged:
• Opening work-in-process at the beginning of the month was 1,600 litres, 70% complete for labour
and 60% complete for overheads. Opening work-in-process was valued at ` 1,06,560.
• Closing work-in-process at the end of the month was 320 litres, 30% complete for labour and 20%
complete for overheads.
• Normal loss is 10% of input and total losses during the month were 1,200 litres partly due to the
fire damage.
• Output sent to finished goods warehouse was 8,400 litres.
• Losses have a scrap value of ` 15 per litre.
• All raw materials are added at the commencement of the process.
• The cost per equivalent unit (litre) is ` 78 for the month made up as follows:
(`)
Raw Material 46
Labour 14
Overheads 18
78
Required:
(i) CALCULATE the quantity (in litres) of raw material inputs during the month.
(ii) CALCULATE the quantity (in litres) of normal loss expected from the process and the quantity (in
litres) of abnormal loss / gain experienced in the month.
(iii) CALCULATE the values of raw material, labour and overheads added to the process during the
month.
(iv) PREPARE the process account for the month.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -311-
Q-2 Following information is available regarding process A for the month of February, 20X9:
Production Record:
Units in process as on 01.02.20X9 4,000
(All materials used, 25% complete for labour and overhead)
New units introduced 16,000
Units completed 14,000
Units in process as on 28.02.20X9 6,000
(All materials used, 33-1/3% complete for labour and overhead)
Cost Records:
Work-in-process as on 01.02.20X9 (`)
Materials 6,00,000
Labour 1,00,000
Overhead 1,00,000
8,00,000
Cost during the month
Materials 25,60,000
Labour 15,00,000
Overhead 15,00,000
55,60,000
Presuming that average method of inventory is used, PREPARE:
(i) Statement of Equivalent Production.
(ii) Statement showing Cost for each element.
(iii) Statement of Apportionment of cost.
(iv) Process Cost Account for Process A.
Ans.
(i) Statement of Equivalent Production (Average cost method)
Input Particulars Output Units Equivalent Production
(Units) Materials Labour Overheads
(%*) Units** (% )* Units** (%)* Units**
20,000 Completed 14,000 100 14,000 100 14,000 100 14,000
WIP 6,000 100 6,000 33-1/3 2,000 33-1/3 2,000
20,000 20,000 20,000 16,000 16,000
*Percentage of completion ** Equivalent units
(ii) Statement showing Cost for each element
Particulars Materials Labour Overhead Total
Cost of opening work-in- 6,00,000 1,00,000 1,00,000 8,00,000
progress (`)
Cost incurred during the month (`) 25,60,000 15,00,000 15,00,000 55,60,000
Total cost (`) : (A) 31,60,000 16,00,000 16,00,000 63,60,000
Equivalent units : (B) 20,000 16,000 16,000
Cost per equivalent unit (`) : C= (A ÷ B) 158 100 100 358
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -313-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -315-
Working note:
Production units = Opening units + Units transferred from Process-II – Closing Units
= 1,600 units + 55,400 units – 4,200 units = 52,800 units
Statement of Cost
Cost (`) Equivalent Cost per
units equivalent
units (`)
Material A (Transferred from previous process) 6,23,250
Less: Scrap value of normal loss (2,640 units × ` 5) (13,200)
6,10,050 52,760 11.5627
Material B 2,12,400 51,820 4.0988
Labour 96,420 51,300 1.8795
Overheads 56,400 51,300 1.0994
9,75,270 18.6404
Statement of apportionment of Process Cost
Amount (`) Amount (`)
Opening WIP Material A 24,000
Completed opening Material B (320 units × ` 4.0988) 1311.62
WIP units-1600
Wages (640 units × ` 1.8795) 1202.88
Overheads (640 units × ` 1.0994) 703.62 3,218.12
Introduced & 50,600 units × ` 18.6404 9,43,204.24
Completed-50,600 units
Total cost of 52,200 9,70,422.36
finished goods units
Closing WIP units- 4,200 Material A (4,200 units × ` 11.5627) 48,563.34
Material B (2,940 units × ` 4.0988) 12,050.47
Wages (2,100 units × ` 1.8795) 3,946.95
Overheads (2,100 units × ` 1.0994) 2,308.74
66,869.50
Abnormal gain units - 2,040 (2,040 units × ` 18.6404) 38026.42
Process III A/c
Particulars Units Amount (`) Particulars Units Amount (`)
To Balance b/d 1,600 24,000 By Normal loss 2,640 13,200
To Process II A/c 55,400 6,23,250 By Finished goods 52,200 9,70,422.36
To Direct material 2,12,400 By Closing WIP 4,200 66,874.06*
To Direct wages 96,420
To Production overheads 56,400
To Abnormal gain 2,040 38,026.42 ______ ___________
59,040 10,50,496.42 59,040 10,50,496.42
* Difference in figure due to rounding off has been adjusted with closing WIP.
Q-5 Star Ltd. manufactures chemical solutions for the food processing industry. The manufacturing takes
place in a number of processes and the company uses FIFO method to value work-in-process and
finished goods. At the end of the last month, a fire occurred in the factory and destroyed some of paper
containing records of the process operations for the month.
Star Ltd. needs your help to prepare the process accounts for the month during which the fire occurred.
You have been able to gather some information about the month’s operating activities but some of the
information could not be retrieved due to the damage. The following information was salvaged:
• Opening work-in-process at the beginning of the month was 800 litres, 70% complete for labour and
60% complete for overheads. Opening work-in-process was valued at ` 26,640.
• Closing work-in-process at the end of the month was 160 litres, 30% complete for labour and 20%
complete for overheads.
• Normal loss is 10% of input and total losses during the month were 1,800 litres partly due to the fire
damage.
• Output sent to finished goods warehouse was 4,200 litres.
• Losses have a scrap value of `15 per litre.
• All raw materials are added at the commencement of the process.
• The cost per equivalent unit (litre) is `39 for the month made up as follows:
(` )
Raw Material 23
Labour 7
Overheads 9
39
Required:
(i) Calculate the quantity (in litres) of raw material inputs during the month.
(ii) Calculate the quantity (in litres) of normal loss expected from the process and the quantity (in
litres) of abnormal loss / gain experienced in the month.
(iii) Calculate the values of raw material, labour and overheads added to the process during the
month.
(v) PREPARE the process account for the month.
Ans.
(i) Calculation of Raw Material inputs during the month:
Quantities Entering Litres Quantities Leaving Process Litres
Process
Opening WIP 800 Transfer to Finished Goods 4,200
Raw material input 5,360 Process Losses 1,800
(balancing figure)
_____ Closing WIP 160
6,160 6,160
(ii) Calculation of Normal Loss and Abnormal Loss/Gain
Litres
Total process losses for month 1,800
Normal Loss (10% input) 536
Abnormal Loss (balancing figure) 1,264
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -317-
(iii) Calculation of values of Raw Material, Labour and Overheads added to the process:
Material Labour Overheads
Cost per equivalent unit ` 23.00 ` 7.00 ` 9.00
Equivalent units (litre) 4,824 4,952 5,016
(refer the working note)
Cost of equivalent units ` 1,10,952 ` 34,664 ` 45,144
Add: Scrap value of normal loss
(536 units × ` 15) ` 8,040 -- --
Total value added ` 1,18,992 `34,664 ` 45,144
Workings:
Statement of Equivalent Units (litre):
Equivalent Production
Input Units Output details Units Material Labour Overheads
Details Units (%) Units (%) Units (%)
Opening 800 Units completed:
WIP 5,360 - Opening 800 -- -- 240 30 320 40
Units WIP
introduced - Fresh inputs 3,400 3,400 100 3,400 100 3,400 100
Normal loss 536 -- -- -- -- -- --
Abnormal loss 1,264 1,264 100 1,264 100 1,264 100
______ Closing WIP 160 160 100 48 30 32 20
6,160 6,160 4,824 4,952 5,016
(iv) Process Account for Month
Litres Amount Litres Amount
(` ) (` )
To Opening WIP 800 26,640 By Finished goods 4,200 1,63,800
To Raw Materials 5,360 1,18,992 By Normal loss 536 8,040
To Wages -- 34,664 By Abnormal loss 1,264 49,296
To Overheads -- 45,144 By Closing WIP 160 4,304
6,160 2,25,440 6,160 2,25,440
Q-6 A product passes through two distinct processes before completion. Following information are available
in this respect:
Process-1 Process 2
Raw materials used 10000 units -
Raw material cost (per unit) ` 75 -
Transfer to next process/Finished good 9000 units 8200 units
Normal loss (on inputs) 5% 10%
Direct wages ` 3,00,000 ` 5,60,000
Direct expenses 50% of direct wages 65% of direct wages
Manufacturing overheads 25% of direct wages 15% of direct wages
Realisable value of scrap (per unit) ` 13.50 ` 145
8000 units of finished goods were sold at a profit of 15% on cost. There was no opening and closing
stock of work-in-progress.
Prepare:
(i) Process-1 and Process-2 Account
(ii) Finished goods Account
(iii) Normal Loss Account
(iv) Abnormal Loss Account
(v) Abnormal Gain Account
Ans. (i)
Dr. Process-1 Account Cr.
Particulars Units Total (`) Particulars Units Total (`)
To Raw Material 10,000 7,50,000 By Normal Loss A/c
Consumed @ 13.5 500 6,750
” Direct Wages — 3,00,000 ” Process 2 @ 133.5 9,000 12,01,500
” Direct — 1,50,000 ” By Abnormal 500 66,750
Expenses Loss @ 133.5
“ Manufacturing
Overheads _____ 75,000 _____ ________
10,000 12,75,000 10,000 12,75,000
Cost per unit of completed units and abnormal loss:
` 12,75,00 - ` 6,750
= = ` 133.5
10,000 units - 50 units
(ii)
Dr. Process-2 Account Cr.
Particulars Units Total (`) Particulars Units Total (`)
To Process-I A/c 9,000 12,01500 By Normal Loss A/c @ 145 900 1,30,500
” To Direct Wages — 5,60,000 ” By Finished Stock A/c
[bal fig] 8,200 21,04,667
” Direct Expenses — 3,64,000
” Manufacturing
Overheads — 84,000
” To Abnormal gain
(` 256.67 × 100 units) 100 25,667 _____ ________
9,100 22,35,167 9,100 22,35,167
Cost per unit of completed units and abnormal gain:
` 22,09,500 - ` 130500
= ` 256.67
8,100 units
Dr. Finished Goods A/c Cr.
Particulars Units Total (`) Particulars Units Total (`)
To Process II A/c 8,200 21,04,667 By By Cost of Sales 8,000 20,53,333
” By Balance c/d 200 51,334 _____ ______
8,200 21,04,667 8,200 21,04,667
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -319-
19,000 19,000 _
Less: Closingstock (2,000) (2,000) _
Prime Cost 17,000 17,000 _
Overheads 4,600 4,600 _
Process Cost 21,600 21,600 _
Profit (33.33%
of total cost) 7,200 - 7,200
28,800 21,600 7,200 28,800 21,600 7,200
Process-B A/c
Particulars Total(`) Cost(`) Profit(`) Particulars Total(`) Cost(`) Profit(`)
Opening stock 5,500 4,500 1,000 Finished
stock A/c 61,675 41,550 20,125
Process A A/c 28,800 21,600 7,200
Direct materials 9,500 9,500 _
Direct wages 6,000 6,000 _
49,800 41,600 8,200
Less: Closing stock (2,490) (2,080) (410)
Prime Cost 47,310 39,520 7,790
Overheads 2,030 2,030 _
Process Cost 49,340 41,550 7,790
Profit (25%
of total cost) 12,335 - 12,335
61,675 41,550 20,125 61,675 41,550 20,125
Finished Stock A/c
Particulars Total(`) Cost(`) Profit(`) Particulars Total(`) Cost(`) Profit(`)
Opening stock 10,000 6,000 4,000 Costing
P & L A/c 75,000 44,181 30,819
Process B A/c 61,675 41,550 20,125
71,675 47,550 24,125
Less: Closing stock (5,000) (3,369) (1,631)
COGS 66,675 44,181 22,494
Profit 8,325 - 8,325
75,000 44,181 30,819 75,000 44,181 30,819
Q-8 Following details have been provided by M/s AR Enterprises:
(i) Opening works-in-progress - 3000 units (70% complete)
(ii) Units introduced during the year - 17000 units
(iii) Cost of the process (for the period) - ` 33,12,720
(iv) Transferred to next process - 15000 units
(v) Closing works-in-progress - 2200 units (80% complete)
(vi) Normal loss is estimated at 12% of total input (including units in process in the beginning). Scraps
realise ` 50 per unit. Scraps are 100% complete.
Using FIFO method, compute:
(i) Equivalent production
(ii) Cost per equivalent unit
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -321-
Ans.
Statement of Equivalent Production Units (Under FIFO Method)
Particulars Input Particulars Output Equivalent
units units Production
(%) Equivalent
units
Opening W-I-P 3,000 From opening W-I-P 3,000 30 900
Units introduced 17,000 From fresh inputs 12,000 100 12,000
Units completed
(Transferred to next process) 15,000
Normal Loss
{12% (3,000 + 17,000 units)} 2,400 -- --
Closing W-I-P 2,200 80 1760
_____ Abnormal loss (Balancing figure) 400 100 400
20,000 11,000 15,060
Computation of cost per equivalent production unit :
Cost of the Process (for the period) ` 33,12,720
Less: Scrap value of normal loss (` 50 × 2,400 units) (` 1,20,000)
Total process cost ` 31,92,720
Q-9 Alpha Ltd. is engaged in the production of a product A which passes through 3 different process -
Process P, Process Q and Process R. The following data relating to cost and output is obtained from the
books of accounts for the month of April 2017:
Particulars Process P Process Q Process R
Direct Material 38,000 42,500 42,880
Direct Labour 30,000 40,000 50,000
Production overheads of ` 90,000 were recovered as percentage of direct labour.
10,000 kg of raw material @ ` 5 per kg. was issued to Process P. There was no stock of materials or work
in process. The entire output of each process passes directly to the next process and finally to warehouse.
There is normal wastage, in processing, of 10 %.
The scrap value of wastage is ` 1 per kg. The output of each process transferred to next process and
finally to warehouse are as under:
Process P = 9,000 kg
Process Q = 8,200 kg
Process R = 7,300 kg
The company fixes selling price of the end product in such a way so as to yield a profit of 25% selling
price.
Prepare Process P, Q and R accounts. Also calculate selling price per unit of end product.
` 1,40,500 - ` 1,000
Cost per unit = = ` 15.50
10,000 kg. - 1,000 kg.
Process- Q Account
Particulars Kg. Amount Particulars Kg. Amount
(` ) (` )
To Process-P A/c 9,000 1,39,500 By Normal wastage
(900 kg. × ` 1) 900 900
To Direct Material — 42,500 By Process- Q 8,200 2,54,200
(8,200 kg. × ` 31)
To Direct Labour — 40,000
To Production OH — 30,000
(` 90,000 × 4/12)
To Abnormal Gain 100 3,100
(100 kg. × ` 31) _____ _______ _____ _______
9,100 2,55,100 9,100 2,55,100
` 2,52,000 - ` 900
Cost per unit =
9,000 kg. - 900 kg.
Process- R Account
Particulars Kg. Amount Particulars Kg. Amount
(` ) (` )
To Process-Q A/c 8,200 2,54,200 By Normal wastage 820 820
(820 kg. × Re.1)
To Direct Material — 42,880 By Abnormal loss 80 4,160
(80 kg. × ` 52)
To Direct Labour — 50,000 By Finished Goods 7,300 3,79,600
(7,300 kg. × `52)
To Production OH
(` 90,000 × 5/12) — 37,500 _____ _______
8,200 3,84,580 8,200 3,84,580
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -323-
` 3,84,580 -` 820
Cost per unit = ` 52
8,200 kg. - 820 kg.
Calculation of Selling price per unit of end product:
Cost per unit ` 52.00
Add: Profit 25% on selling price i.e. 1/3rd of cost ` 17.33
Selling price per unit ` 69.33
Q-10 A ditya Agro Ltd. mixes powdered ingredients in two different processes to produce one product.
The output of Process- I becomes the input of Process -II and the output of Process-II is transferred to
the Packing department.
From the information given below, you are required to PREPARE accounts for Process-I , Process-II and
A bnormal loss/ gain A/c to record the transactions for the month of February 20X9.
Process-I
Input:
Material A 6,000 kilograms at Rs. 50 per kilogram
Material B 4,000 kilograms at Rs. 100 per kilogram
Labour 430 hours at Rs. 50 per hour
Normal loss 5% of inputs. Scrap are disposed off at Rs.16 per kilogram
Output 9,200 kilograms.
There is no work- in- process at the beginning or end of the month.
Process-II
Input:
Material C 6,600 kilograms at Rs. 125 per kilogram
Material D 4,200 kilograms at Rs. 75 per kilogram
Flavouring Essence Rs. 3, 300
Labour 370 hours at Rs.50 per hour
Normal loss 5% of input s with no disposal value
Output 18,000 kilograms.
There is no work-in-process at the beginning of the month but 1,000 kilograms in process at the end of
the month and estimated to be only 50% complete so far as labour and overhead were concerned.
Overhead of Rs. 92 ,000 incurred to be abso rbed on the basis of labour hours.
Ans.
Process-I A/c
Particulars Qty. Amount Particulars Qty. Amount
(kgs) (kgs) ( Rs.)
To Material A 6,000 3,00,000 By Normal loss 500 8,000
To Material B 4,000 4,00,000 By Process-II A/c 9,200 7,38,857
To Labour - 21,500 By Abnormal loss A/c 300 24,093
To Overhead -- 49,450
Rs. 92,000 430 hrs
______ _______ _____ _______
800 hrs
10,000 7,70,950 10,000 7,70,950
{(` 3,00, 000 + ` 4, 00, 000 + `21,500 + ` 49,450) - ` 8,000} ` 7,70,950 - ` 8, 000
* = = Rs.80.3105
(10,000 - 500)units 9,500 units
Process-II A/c
Particulars Qty. Amount Particulars Qty. (kgs) Amount
(kgs) ( Rs.) ( Rs.)
To Process-I A/c 9,200 7,38,857 By Normal loss 1,000 --
To Material C 6,600 8,25,000 By Packing 18,000 18,42,496
Dept. A/c
(See the working notes)
To Material D 4,200 3,15,000 By WIP A/c 1,000 1,00,711
(See the working notes)
To Flavouring essence -- 3,300
To Labour -- 18,500
To Overheads -- 42,550
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -325-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -327-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -333-
***
8,05, 406 - 2,600 - 21,000 =` 180.1396
(5,200 - 260 - 600) Units
# Realisable value = `135 – (85+15) = `35
(ii) By-Product Process A/c
Particulars Units Amt.(`) Particulars Units Amt.(`)
To Process-III A/c 600 21,000 By Product-Z 600 81,000
To Processing cost - 51,000
To Selling expenses - 9,000
600 81,000 600 81,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -335-
Q-18 Following information is available regarding process A for the month of October, 2021:
Production Record:
Units in process as on 01.10.2021 8,000
(All materials used, 25% complete for labour and overhead)
New units introduced 32,000
Units completed 28,000
Units in process as on 31.10.2021 12,000
(All materials used, 33-1/3% complete for labour and overhead)
Cost Records:
Work-in-process as on 01.10.2021 (`)
Materials 12,00,000
Labour 2,00,000
Overhead 2,00,000
16,00,000
Cost during the month
Materials 51,20,000
Labour 30,00,000
Overhead 30,00,000
1,11,20,000
Presuming that average method of inventory is used, PREPARE:
(i) Statement of Equivalent Production.
(ii) Statement showing Cost for each element.
(iii) Statement of Apportionment of cost.
(iv) Process Cost Account for Process A.
Ans.(i) Statement of Equivalent Production (Average cost method)
Input Particulars Output Equivalent Production
(Units) Units
Materials Labour Overheads
(%*) Units** (% )* Units** (%)* Units**
40,000 Completed 28,000 100 28,000 100 28,000 100 28,000
WIP 12,000 100 12,000 33-1/3 4,000 33-1/3 4,000
40,000 40,000 40,000 32,000 32,000
*Percentage of completion ** Equivalent units
(ii) Statement showing Cost for each element
Particulars Materials Labour Overhead Total
Cost of opening work-in-progress (`) 12,00,000 2,00,000 2,00,000 16,00,000
Cost incurred during the month (`) 51,20,000 30,00,000 30,00,000 1,11,20,000
Total cost (`) : (a) 63,20,000 32,00,000 32,00,000 1,27,20,000
Equivalent units : (B) 40,000 32,000 32,000
Cost per equivalent unit (`) : C= (A ÷B) 158 100 100 358
-336- Chapter-10 : Process & Operation Costing
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -337-
(iii) Calculate the values of raw material, labour and overheads added to the process during the month.
(iv) Prepare the process account for the month.
Ans. (i) Calculation of Raw Material inputs during the month:
Quantities Entering Process Litres Quantities Leaving Process Litres
Opening WIP 900 Transfer to Finished Goods 4,200
Raw material input (balancing figure) 5,260 Process Losses 1,800
Closing WIP 160
6,160 6,160
(ii) Calculation of Normal Loss and Abnormal Loss/Gain
Particulars Litres
Total process losses for month 1,800
Normal Loss (10% input) 526
Abnormal Loss (balancing figure) 1,274
(iii) Calculation of values of Raw Material, Labour and Overheads added to the process:
Material Labour Overheads
Cost per equivalent unit ` 23.00 ` 7.00 ` 9.00
Equivalent units (litre) (refer the
working note) 4,734 4,892 4,966
Cost of equivalent units ` 1,08,882 ` 34,244 ` 44,694
Add: Scrap value of normal loss (526
units x ` 20) ` 10,520 -- --
Total value added ` 1,19,402 ` 34,244 ` 44,694
Workings:
Statement of Equivalent Units (litre):
Input Units Output details Units Equivalent Production
Details Material Labour Overheads
Units (%) Units (%) Units (%)
Opening WIP 900 Units completed:
Units introduced 5,260 - Opening WIP 900 -- -- 270 30 360 40
- Fresh inputs 3,300 3,300 100 3,300 100 3,300 100
Normal loss 526 - - -- -- -- -- --
Abnormal loss 1,274 1,274 100 1,274 100 1,274 100
Closing WIP 160 160 100 48 30 32 20
6,160 6,160 4,734 4,892 4,966
(iv) Process Account for Month
Litres Amount (`) Litres Amount (`)
To Opening WIP 900 29,970 By Finished goods 4,200 1,63,800
To Raw Materials 5,260 1,19,402 By Normal loss 526 10,520
To Wages -- 34,244 By Abnormal loss 1,274 49,686
To Overheads -- 44,694 By Closing WIP 160 4,304
6,160 2,28,310 6,160 2,28,310
Q-20 A Manufacturing unit manufactures a product ‘XYZ’ which passes through three distinct Processes - X,
Y and Z. The following data is given:
Process X Process Y Process Z
Material consumed (in `) 2,600 2,250 2,000
Direct wages (in `) 4,000 3,500 3,000
• The total Production Overhead of ` 15,750 was recovered @ 150% of Direct wages.
• 15,000 units at ` 2 each were introduced to Process ‘X’.
• The output of each process passes to the next process and finally, 12,000 units were transferred to
Finished Stock Account from Process ‘Z’.
• No stock of materials or work in progress was left at the end.
The following additional information is given:
Process % of wastage to normal input Value of Scrap per unit (`)
X 6% 1.10
Y ? 2.00
Z 5% 1.00
You are required to:
(i) Find out the percentage of wastage in process ‘Y’, given that the output of Process ‘Y’ is transferred
to Process ‘Z’ at ` 4 per unit.
(ii) Prepare Process accounts for all the three processes X, Y and Z.
Ans. Dr. Process-X Account Cr.
Particulars Units (`) Particulars Units (`)
To Material 15,000 30,000 By Normal Loss A/c 900 990
introduced [(6% of 15,000 units)
x ` 1.1]
” Additional — 2,600 ” Process-Y A/c 14,100 41,610
material (` 2.951* × 14,100
units)
” Direct wages — 4,000
” Production OH — 6,000 ______ ______
15,000 42,600 15,000 42,600
*Cost per unit of completed units
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -339-
Alternative Solution
Dr. Process-X Account Cr.
Particulars Units (`) Particulars Units (`)
To Material 15,000 30,000 By Normal Loss A/c 900 990
introduced [(6% of 15,000 units) x
` 1.1]
” Additional — 2,600 ” Process-Y A/c 14,100 41,610
material (` 2.951* × 14,100 units)
” Direct wages — 4,000
” Production OH — 6,000
15,000 42,600 15,000 42,600
*Cost per unit of completed units
Q-21 MRSL Healthcare Ltd. has incurred the following expenditure during the last year for its newly launched
‘COVID-19’ Insurance policy:
Office administration cost 48,00,000
Claim management cost 3,80,000
Employees cost 16,20,000
Postage and logistics 32,40,000
Policy issuance cost 29,50,000
Facilities cost 46,75,000
Cost of marketing of the policy 1,38,90,000
Policy development cost 35,00,000
Policy servicing cost 96,45,000
Sales support expenses 32,00,000
I.T. Cost ?
Number of Policy sold: 2,800
Total insured value of policies - ` 3,500 Crores
Cost per rupee of insured value - ` 0.002
You are required to:
(i) Calculate Total Cost for “COVID-19” Insurance policy segregating the costs into four main activities
namely (a) Marketing and Sales suppor t (b) Operations (c) I.T. Cost and (d) Support functions.
(ii) Calculate Cost Per Policy
Ans. (i)Calculation of total cost for ‘COVID-19’ Insurance policy
Particulars Amount (`) Amount (`)
a. Marketing and Sales support:
- Policy development cost 35,00,000
- Cost of marketing 1,38,90,000
- Sales support expenses 32,00,000 2,05,90,000
b. Operations:
- Policy issuance cost 29,50,000
- Policy servicing cost 96,45,000
- Claim management cost 3,80,000 1,29,75,000
c. IT Cost* 2,21,00,000
d. Support functions
- Postage and logistics 32,40,000
- Facilities cost 46,75,000
- Employees cost 16,20,000
- Office administration cost 48,00,000 1,43,35,000
Total Cost 7,00,00,000
*IT cost
= (` 3,500 crores x 0.002) – ` 4,79,00,000 = ` 2,21,00,000
(ii) Calculation of cost per policy = Total cost / No.of policies = ` 7,00,00,000 / 2,800 = ` 25,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -343-
Working Notes:
1. Computation of Cost per unit
Particulars Materials Labour Overhead
(`) (`) (`)
Input costs 2,20,000 26,500 61,500
Less: Realisable value of normal (27,625) — —
scrap (3,250 units x ` 8.5)
Net cost 1,92,375 26,500 61,500
Equivalent Units 51,750 51,050 51,050
Cost Per Unit 3.7174 0.5191 1.2047
Total cost per unit = ` (3.7174 + 0.5191 + 1.2047) = ` 5.4412
2. Valuation of Abnormal Loss
(`)
Materials (6,250 units × ` 3.7174) 23,233.75
Labour (3,750 units × ` 0.5191) 1,946.63
Overheads (3,750 units × ` 1.2047) 4,517.62
29,698
Q-23 ABC Health care runs an Intensive Medical Care Unit. For this purpose, it has hired a building at a rent of
`50,000 per month with the agreement to bear the repairs and maintenance charges also.
The unit consists of 100 beds and 5 more beds can comfortably be accommodated when the situation
demands. Though the unit is open for patients all the 365 days in a year, scrutiny of accounts for the
year 2020 reveals that only for 120 days in the year, the unit had the full capacity of 100 patients per day
and for another 80 days, it had, on an average only 40 beds occupied per day. But, there were occasions
when the beds were full, extra beds were hired at a charge of ‘ 50 per bed per day. This did not come to
more than 5 beds above the normal capacity on any one day. The total hire charges for the extra beds
incurred for the whole year amounted to ` 20,000.
The unit engaged expert doctors from outside to attend on the patients and the fees were paid on the
basis of the number of patients attended and time spent by them which on an average worked out to
` 30,000 per month in the year 2020.
The permanent staff expenses and other expenses of the unit were as follows:
`
2 Supervisors each at a per month salary of 5,000
4 Nurses each at a per month salary of 3,000
2 Ward boys each at a per month salary of 1,500
Other Expenses for the year were as under:
Repairs and Maintenance 28,000
Food supplied to patients 4,40,000
Caretaker and Other services for patients 1,25,000
Laundry charges for bed linen 1,40,000
Medicines supplied 2,80,000
Cost of Oxygen etc. other than directly borne for treatment of patients 75,000
General Administration Charges allocated to the unit 71,000
Required:
(i) What is the profit per patient day made by the unit in the year 2020, if the unit recovered an overall
amount of ` 200 per day on an average from each patient.
(ii) The unit wants to work on a budget for the year 2021, but the number of patients requiring medical care
is a very uncertain factor. Assuming that same revenue and expenses prevail in the year 2021 in the first
instance, work out the number of patient days required by the unit to break even.
Ans. Workings:
Calculation of number of Patient days
100 Beds × 120 days = 12000
40 Beds × 80 days = 3,200
Extra beds = 400
Total = 15,600
(i) Statement of Profitability
Particulars Amount (`) Amount (`)
Income for the year (` 200 per patient per day ×
15,600 patient days) 31,20,000
Variable Costs:
Doctor Fees (` 30,000 per month × 12) 3,60,000
Food to Patients (Variable) 4,40,000
Caretaker Other services to patients (Variable) 1,25,000
Laundry charges (Variable) 1,40,000
Medicines (Variable) 2,80,000
Bed Hire Charges (` 50 × 400 Beds) 20,000
Total Variable costs (13,65,000)
Contribution 17,55,000
Fixed Costs:
Rent (` 50,000 per month × 12) 6,00,000
Supervisor (2 persons × ` 5,000 × 12) 1,20,000
Nurses (4 persons × ` 3,000 × 12) 1,44,000
Ward Boys (2 persons x ` 1500 x12) 36,000
Repairs (Fixed) 28,000
Cost of Oxygen 75,000
Administration expenses allocated 71,000
Total Fixed Costs (10,74,000)
Profit 6,81,000
Calculation of Contribution and profit per Patient day
Total Contribution = ` 17,55,000
Total Patient days = 15,600 days
Contribution per Patient day = ` 17,55,000 / 15,600 days = ` 112.50
Total Profit = ` 6,81,000
Total Patient days = 15,600 days
Profit per Patient day = ` 6,81,000 / 15,600 days = ` 43.65
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -345-
`900 crore 1
A. Apportionment of capital cost 10 years 12 months 7,50,00,000
B. Other Costs
Salary to Collection Personnel (3 Shifts × 5 persons per shift × 30 days × ` 200 per day) 90,000
Salary to Supervisor (3 Shifts × 2 persons per shift × 30 days × ` 350 per day) 63,000
Salary to Security Personnel (2 Shifts × 2 persons per shift × 30 days × ` 200 per day) 24,000
Salary to Toll Booth Manager (3 Shifts × 1 person per shift × 30 days × ` 500 per day) 45,000
Electricity 1,50,000
Telephone 1,00,000
4,72,000
C. Maintenance cost 50,00,000
Total (A + B + C) 8,04,72,000
Working:
Q-26 Following information is available regarding Process-I of a manufacturing company for themonth of
February:
Production Record:
Units in process as on 1st February
(All materials used, 1/4th complete for labour and overhead) 8,000
New units introduced 32,000
Units completed 28,000
Units in process as on 28th February 12,000
(All materials used, 1/3rd complete for labour and overhead)
Cost Records: (` )
Work-in-process as on 1st February
Materials 1,20,000
Labour 20,000
Overhead 20,000
1,60,000
Cost during the month:
Materials 5,12,000
Labour 3,00,000
Overhead 3,00,000
11,12,000
Presuming that average method of inventory is used, PREPARE the following:
(i) Statement of equivalent production.
(ii) Statement showing cost for each element.
(iii) Statement of apportionment of cost.
(iv) Process cost account for Process-I.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -349-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -351-
Q-28 A company produces a component, which passes through two processes. During the month of December,
2021, materials for 40,000 components were put into Process-I of which 30,000 were completed and
transferred to Process-II. Those not transferred to Process- II were 100% complete as to materials cost
and 50% complete as to labour and overheads cost. The Process- I costs incurred were as follows:
Direct Materials ` 6,00,000
Direct Wages ` 7,00,000
Factory Overheads ` 4,90,000
Of those transferred to Process II, 28,000 units were completed and transferred to finished goods
stores. There was a normal loss with no salvage value of 200 units in Process II. There were 1,800 units,
remained unfinished in the process with 100% complete as to materials and 25% complete as regard to
wages and overheads.
Costs incurred in Process-II are as follows:
Packing Materials ` 1,60,000
Direct Wages ` 1,42,250
Factory Overheads ` 1,70,700
Packing material cost is incurred at the end of the second process as protective packing to the completed
units of production.
Required:
(i) PREPARE Statement of Equivalent Production, Cost per unit and Process I A/c.
(ii) PREPARE statement of Equivalent Production, Cost per unit and Process II A/c.
Ans.
(i) Process I
Statement of Equivalent Production and Cost
Input Particulars Output Equivalent Production
Units (Units) Materials Labour Overheads
(%) Units (%) Units (%) Units
40,000 Completed 30,000 100 30,000 100 30,000 100 30,000
Closing WIP 10,000 100 10,000 50 5,000 50 5,000
40,000 40,000 40,000 35,000 35,000
Particulars Materials Labour Overhead Total
Cost incurred (`) 6,00,000 7,00,000 4,90,000 17,90,000
Equivalent units 40,000 35,000 35,000
Cost per equivalent unit (`) 15 20 14 49
Process-I Account
Particulars Units (`) Particulars Units (`)
To Materials 40,000 6,00,000 By Process-II A/c 30,000 14,70,000
(30,000 units × ‘49)
To Labour 7,00,000 By Closing WIP* 10,000 3,20,000
To Overhead 4,90,000
40,000 17,90,000 40,000 17,90,000
* (Material 10,000 units × ` 15) + (Labour 5,000 units × ` 20) + (Overheads 5,000 units × ` 14)
= ` 1,50,000 + ` 1,00,000 + ` 70,000 = ` 3,20,000
(ii) Process II
Statement of Equivalent Production and Cost
Input Particulars Output Equivalent Production
Units (Units) Materials Labour Overheads
(%) Units (%) Units (%) Units
30,000 Completed 28,000 100 28,000 100 28,000 100 28,000
Normal loss 200 — — —
Closing WIP 1,800 100 1,800 25 450 25 450
30,000 30,000 29,800 28,450 28,450
Particulars Materials Labour Overhead Total
Process-I Cost 14,70,000 — — 14,70,000
Cost incurred (`) — 1,42,250 1,70,700 3,12,950
Equivalent units 29,800 28,450 28,450 —
Cost per equivalent unit (`) 49.3289 5.00 6.00 60.3289
Process-II Account
Particulars Units (`) Particulars Units (`)
To Process-I A/c 30,000 14,70,000 By Normal loss A/c 200 —
To Packing Material — 1,60,000 By Finished Goods
Stock A/c 28,000* 18,49,209
To Direct Wages — 1,42,250 By Closing WIP 1,800** 93,741
To Factory Overhead — 1,70,700 ______ ______
30,000 19,42,950 30,000 19,42,950
* 28,000 × ‘ 60.3289 = ` 16,89,209 + ` 1,60,000 (Packing Material Cost) = ` 18,49,209
** 1,800 units × ` 49.3289 + 450 units × (` 5 + `6) = ` 93,741
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -353-
% of wastage = = 13.44%
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -355-
Q-31 Chill Ltd. uses process costing to manufacture water density sensor for hydro sector. The following
information pertains to operations for the month of February:
Particulars Units
Beginning WIP, February 1 22,400
Started in production during February 1,40,000
Completed production during February 1,28,800
Ending work in progress, February 28 33,600
The beginning work in progress was 50% complete for materials and 30% complete for conversion
costs. The ending inventory was 80% complete for material and 30% complete for conversion costs.
Costs pertaining to the month of February are as follows:
Beginning inventory costs are material ` 1,38,350, direct labour ` 1,50,600 and factory overhead `63,600
Cost incurred during February are material ` 23,95,000, direct labour ` 9,14,400, factory overheads
`19,55,800.
CALCULATE:
(i) Using the FIFO method, the equivalent units of production for material.
(ii) Cost per equivalent unit for conversion cost.
Ans.
(i) Calculation of equivalent units of production:
Input Details Units Output Particulars Units Equivalent Units
Material Conversion cost
% Units % Units
Beginning WIP 22,400 From beginning WIP 22,400 50 11,200 70 15,680
Unit Introduced 1,40,000 Completed output 1,06,400 100 1,06,400 100 1,06,400
Closing W-I-P 33,600 80 26,880 30 10,080
Total 1,62,400 Total 1,62,400 1,44,480 1,32,160
-356- Chapter-10 : Process & Operation Costing
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -357-
Ans.
(i) Statement of Expenses of operating a mini bus in a year
Particulars Rate (`) Per Bus per
annum (`)
(A) Standing Charges:
Driver’s salary 20,000 p.m 2,40,000
Lady attendant’s salary 10,000 p.m 1,20,000
Average Cleaner’s salary (50%) 15,000 p.m 90,000
Insurance charge 30,000 p.a. 30,000
License fee, taxes etc. 5,080 p.m. 60,960
Average Garage Rent 24,000 p.m 36,000
Depreciation {(15,00,000 – 3,00,000) ÷ 8} 1,50,000 p.a. 1,50,000
(B) Maintenance Charges:
Repairs & maintenance including engine oil and
lubricants (Working Note 1) 28,560 p.a.
(C) Operating Charges:
Diesel (Working Note 2) 5,76,000
Total Cost (A + B + C) 13,31,520
Cost per month 1,10,960
= ×` 80
= 5,76,000
3. Calculation of equivalent number of employees per bus:
Seating capacity of a bus 30 employees
Occupancy (80% of capacity) 24 employees
Half fare employees (50% of 24 employees) 12 employees
Full fare employees (50% of 24 employees) 12 employee
Note: Total Equivalent number of employees per month (morning + afternoon shift of company can also be
calculated considering full fare employees as a base. In that case the number will be 36. Then fare for
employees coming from distance beyond 15km will be = ` 3,082.22 and employees coming from
distance upto 15 km will be 3,082.22 / 2 = ` 1,541.11].
Q-33 A Drug Store is presently selling three types of drugs namely ‘sDrug A’, ‘Drug B’ and ‘Drug C’. Due to
some constraints, it has decided to go for only one product line of drugs. It has provided the following
data for year 2020-21 for each product line:
Drugs Types
A B C
Revenues (in `) 74,50,000 1,11,75,000 1,86,25,000
Cost of goods sold (in `) 41,44,500 68,16,750 1,20,63,750
Number of purchase orders placed (in nos.) 560 810 630
Number of deliveries received 950 1,000 850
Hours of shelf-stocking time 900 1,250 2,350
Units sold (in Nos.) 1,75,200 1,50,300 1,44,500
Following additional information is also provided:
Activity Description of activity Total Cost Cost-allocation base
(` )
Drug Licence fee Drug Licence fee 5,00,000 To be distributed in ratio
2:3:5 between A, B and C
Ordering Placing of orders for purchases 8,30,000 2,000 purchase orders
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -359-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -361-
Depreciation 16,00,000
Working Notes:
1. Let total takings be X then Passenger tax and profit will be as follows:
X = ` 1,17,57,540 + 0.15X + 0.25X
X – 0.40X = ` 1,17,57,540
X= = ` 1,95,95,900
---0---0---
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -363-
CHAPTER - 11
JOINT PRODUCT AND BY PRODUCT
Q-1 In an Oil Mill four products emerge from a refining process. The total cost of input during the quarter
ending March 20X8 is `1,48,000. The output, sales and additional processing costs are as under:
Products Output in Litres Additional processing Sales value (`)
cost after split off (`)
ACH 8,000 43,000 1,72,500
BCH 4,000 9,000 15,000
CSH 2,000 - 6,000
DSH 4,000 1,500 45,000
In case these products were disposed-off at the split off point that is before further processing, the
selling price per litre would have been:
ACH (`) BCH (`) CSH (`) DSH (`)
15.00 6.00 3.00 7.50
PRODUCE a statement of profitability based on:
(i) If the products are sold after further processing is carried out in the mill.
(ii) If they are sold at the split off point.
Ans. (i) Statement of profitability of the Oil Mill (after carrying out further processing) for the quarter
ending 31st March 20X8.
Products Sales Value Share of Additional Total cost Profit (loss)
after further Joint cost processing after
processing cost processing
ACH 1,72,500 98,667 43,000 1,41,667 30,833
BCH 15,000 19,733 9,000 28,733 (13,733)
CSH 6,000 4,933 — 4,933 1,067
DSH 45,000 24,667 1,500 26,167 18,833
2,38,500 1,48,000 53,500 2,01,500 37,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -365-
` 83.600 ` 83.600
on the basis of ‘Physical Quantity’ ×100 ×120
100 + 120 units 100 + 120 units
(ii) Apportionment of Joint Cost on the
basis of ‘Contribution Margin
Method’:
` 51.600 ` 51.600
physical units) ×100 ×120
100 + 120 units 100 + 120 units
Contribution Margin 36,545 ) -4,145
(` 600×100 – 23,455 (` 200×120 – 28,145)
Fixed Costs* ` 32,000
Total apportioned cost ` 55,455 ` 28,145
II. (iii) Profit or Loss:
When Joint cost apportioned on basis of physical units
A. Sales Value ` 60,000 ` 24,000
B. Apportioned joint cost on basis of
‘Physical Quantity’: ` 38,000 ` 45,600
A-B Profit or (Loss) 22,000 (21,600)
When Joint cost apportioned on basis of ‘Contribution Margin Method’
C Apportioned joint cost on basis of
‘Contribution Margin Method’ ` 55,455 ` 28,145
A-C Profit or (Loss) ` 4,545 ` (4,145)
* The fixed cost of ` 32,000 is to be apportioned over the joint products A and B in the ratio of their
contribution margin but contribution margin of Product B is Negative so fixed cost will be charged to
Product A only.
Q-3 A Factory is engaged in the production of chemical Bomex and in the course of its manufacture a by-
product Cromex is produced which after further processing has a commercial value. For the month of
April 2019 the following are the summarised cost data:
Joint Expenses Separate
(` ) Expenses (`)
Bomex Cromex
Materials 1,00,000 6,000 4,000
Labour 50,000 20,000 18,000
Overheads 30,000 10,000 6,000
Selling Price per unit 100 40
Estimated profit per unit on sale of Cromex 5
Number of units produced 2,000 2,000
Units Units
The factory uses net realisable value method for apportionment of joint cost to by-products.
You are required to prepare statements showing :
(i) Joint cost allocable to Cromex
(ii) Product wise and overall profitability of the factory for April 2019.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -367-
Ans.
(i) Statement Showing Joint Cost Allocation to ‘Cromex’
Particulars Cromex (`)
Sales (` 40 × 2,000 units) 80,000
Less: Post Split Off Costs (4,000 + 18,000 + 6,000) (28,000)
Less: Estimated Profit (` 5 × 2,000 units) (10,000)
Joint cost allocable 42,000
(ii) Statement Showing Product Wise and Overall Profitability
Particulars Bomex (`) Cromex (`) Total (`)
Sales 2,00,000 80,000 2,80,000
Less: Share in Joint Expenses (1,38,000)* (42,000) (1,80,000)
Less: Post Split Off Costs (36,000) (28,000) (64,000)
Profit 26,000 10,000 36,000
(*) 1,80,000 – 42,000
Q-4 How are By-products treated in Costing?
Ans. Treatment of by-product cost in Cost Accounting:
By-product cost can be dealt in cost accounting in the following ways:
(a) When they are of small total value: When the by-products are of small total value, the amount
realised from their sale may be dealt in any one the following two ways:
1. The sales value of the by-products may be credited to the Costing Profit and Loss Account
and no credit be given in the Cost Accounts. The credit to the Costing Profit and Loss Account
here is treated either as miscellaneous income or as additional sales revenue.
2. The sale proceeds of the by-product may be treated as deductions from the total costs. The
sale proceeds in fact should be deducted either from the production cost or from the cost of
sales.
(b) When the by-products are of considerable total value: Where by-products are of considerable
total value, they may be regarded as joint products rather than as by-products. To determine
exact cost of by-products the costs incurred upto the point of separation, should be apportioned
over by-products and joint products by using a logical basis.
(c) Where they require further processing: In this case, the net realisable value of the by-product at
the split-off point may be arrived at by subtracting the further processing cost from the realisable
value of by-products.
Q-5 Three products X,Y and Z alongwith a byproduct B are obtained again in a crude state which require
further processing at a cost of Rs. 5 for X; Rs. 4 for Y; and Rs. 2.50 for Z per unit before sale. The byproduct
is however saleable as such to a nearby factory. The selling prices for the three main products and
byproduct, assuming they should yield a net margin of 25 percent of cost, are fixed at Rs. 13.75 Rs. 8.75
and Rs. 7.50 and Re. 1.00 respectively – all per unit quantity sold.
During a period, the joint input cost including the material cost was Rs. 90,800 and the respective
outputs were:
X 8,000 units
Y 6,000 units
Z 4,000 units
B 1,000 units
By product should be credited to the joint cost and only the net joint costs are to be allocated to the
main products.
Calculate the joint cost per unit of each product and the margin available as a percentage on cost.
Ans. Machine running expenses per hour
Cost per month (Rs.) Cost per hour (Rs.)
Depreciation 4,000 20.00
Rs.2,500
200 hours
Repairs & Maintenance 5,040 28.00
Rs.60,480 Rs.5,040
12 months 180 hours
Consumable stores 3,960 22.00
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -369-
Q-6 Describe net realizable value method of apportioning joint costs to by-products.
Ans. Net Realisable Value method : The realisation on the disposal of the by-product may be deducted from
the total cost of production so as to arrive at the cost of the main product. For example, the amount
realised by the sale of molasses in a sugar factory goes to reduce the cost of sugar produced in the
factory.
When the by-product requires some additional processing and expenses are incurred in making it
saleable to the best advantage of the concern, the expenses so incurred should be deducted from the
total value realised from the sale of the by -product and only the net realisations should be deducted
from the total cost of production to arrive at the cost of production of the main product.
Separate accounts should be maintained for collecting addit ional expenses incurred on:
(i) further processing of the by -product, and
(ii) selling, distribution and administration expenses attributable to the by -product.
Q-7 A company processes a raw material in its Department 1 to produce three products, viz. A, B and X at the
same split-off stage. During a period 1,80,000 kgs of raw materials were processed in Department 1 at
a total cost of ` 12,88,000 and the resultant output of A, B and X were 18,000 kgs, 10,000 kgs and 54,000
kgs respectively. A and B were further processed in Department 2 at a cost of `1,80,000 and `1,50,000
respectively.
X was further processed in Department 3 at a cost of `1,08,000. There is no waste in further processing.
The details of sales affected during the period were as under:
A B X
Quantity Sold (kgs.) 17,000 5,000 44,000
Sales Value (`) 12,24,000 2,50,000 7,92,000
There were no opening stocks. If these products were sold at split-off stage, the selling prices of A, B
and X would have been ` 50, ` 40 and ` 10 per kg respectively.
Required:
(i) Prepare a statement showing the apportionment of joint costs to A, B and X.
(ii) Present a statement showing the cost per kg of each product indicating joint cost and further processing
cost and total cost separately.
(iii) Prepare a statement showing the product wise and total profit for the period.
(iv) State with supporting calculations as to whether any or all the products should be further processed or
not.
Ans.
(i) Statement showing the apportionment of joint costs to A, B and X
Products A B X Total
Output (kg) 18,000 10,000 54,000 18,40,000
Sales value 9,00,000 4,00,000 5,40,000
at the point of (` 50 x 18,000) (` 40 x 10,000) (` 10 x 54,000)
split off (`)
Joint cost 6,30,000 2,80,000 3,78,000 12,88,000
apportionment
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -371-
Products A B X Total
Closing stock 1,000 5,000 10,000
(kgs.)
Cost per kg (`) 45 43 9
Closing stock value (`) 45,000 2,15,000 90,000 3,50,000
(` 45 x 1,000 kg) (` 43 x 5,000 kg) (`9x10,000 kg)
(iv) Calculations for processing decision
Products A B X
Selling price per kg at the point of split off (`) 50 40 10
Selling price per kg after further processing (`)
(Refer to working Note 1) 72 50 18
Incremental selling price per kg (`) 22 10 8
Less: Further processing cost per kg (`) (10) (15) (2)
Incremental profit (loss) per kg (`) 12 (5) 6
Product A and X has an incremental profit per unit after further processing, hence, these two products
may be further processed. However, further processing of product B is not profitable hence, product B
shall be sold at split off point.
Q-8 In an Oil Mill, four products emerge from a refining process. The total cost of input during the quarter
ending March 2019 is Rs.22,20,000. The output, sales and additional processing costs are as under:
Products Output in Additional processing Sales value (Rs.)
Litres cost after split off (Rs.)
A 8,000 6,45,000 25,87,500
B 4,000 1,35,000 2,25,000
C 2,000 - 90,000
D 4,000 22,500 6,75,000
In case these products were disposed-off at the split off point that is before further processing, the
selling price per litre would have been:
A (Rs.) B (Rs.) C (Rs.) D (Rs.)
225.00 90.00 45.00 112.50
PREPARE a statement of profitability based on:
(i) If the products are sold after further processing is carried out in the mill.
(ii) If they are sold at the split off point.
Ans. Statement of profitability of an Oil Mill (after carrying out further processing) for the quarter ending
31st March 2019.
Products Sales Value after Share of Joint Additional Total cost Profit (loss)
further cost processing after
processing cost processing
A 25,87,500 14,80,000 6,45,000 21,25,000 4,62,500
B 2,25,000 2,96,000 1,35,000 4,31,000 (2,06,000)
C 90,000 74,000 - 74,000 16,000
D 6,75,000 3,70,000 22,500 3,92,500 2,82,500
35,77,500 22,20,000 8,02,500 30,22,500 5,55,000
-372- Chapter-11 : Joint Product & By Product
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -373-
12, 50,000
Total cost of Product X = × ` 10,98,000 - ` 4,66,797
` 29, 40,250
12, 50,000
Total cost of Product Y = × ` 13,20,750 - `5,61,496
` 29,40,250
12,50, 000
Total cost of Product Z = × ` 5,21, 500 - `2,21,707
` 29, 40,250
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -375-
Q-11 How apportionment of joint costs up-to the point of separation amongst the joint products using
market value at the point of separation and net realizable value method is done?
Ans. Apportionment of Joint Cost amongst Joint Products using:
Market value at the point of separation: This method is used for apportionment of joint costs to joint
products upto the split off point. It is difficult to apply if the market value of the product at the point of
separation is not available. It is useful method where further processing costs are incurred
disproportionately.
Net realizable value Method: From the sales value of joint products (at finished stage) the followings
are deducted:
- Estimated profit margins
- Selling & distribution expenses, if any
- Post- split off costs.
The resultant figure so obtained is known as net realizable value of joint products. Joint costs are
apportioned in the ratio of net realizable value.
Q-12 Answer the following:
A factory produces two products, `Ghee’ and `Cream’ from a single process. The joint processing costs
during a particular month are:
Direct Material ` 60,000
Direct Labour ` 19,200
Variable Overheads ` 24,000
Fixed Overheads ` 64,000
Sales: Ghee - 200 litre @ ` 600 per litre; Cream – 240 litre @ ` 200 per litre.
REQUIRED:
I. Apportion joints costs on the basis of:
(i) Physical Quantity of each product.
(ii) Contribution Margin method, and
II. Determine Profit or Loss under both the methods.
Ans. Total Joint Cost
Particulars Amount (`)
Direct Material 60,000
Direct Labour 19,200
Variable Overheads 24,000
Total Variable Cost 1,03,200
Fixed Overheads 64,000
Total joint cost 1,67,200
Apportionment of Joint Costs:
Product-Ghee Product-Cream
I. (i) Apportionment of Joint `76,000 `91,200
`Physical Quantity’
(ii) Apportionment of Joint
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -377-
` 40,000
Share of P in joint cost = x ` 12,000 = ` 6,000
`80,000
` 40,000
Share of N in joint cost = x ` 28,000 = ` 14,000
`80,000
` 40,000
Share of A in joint cost = x ` 20,000 = ` 10,000
`80,000
Alternative Solution
Decision for further processing of Product S, P and N
Products S (`) P (`) N (`)
Sales revenue after further processing 1,20,000 40,000 48,000
Less: sales value at split-off point 20,000 12,000 28,000
Incremental Sales Revenue 1,00,000 28,000 20,000
Less: Further Processing cost 80,000 32,000 36,000
Profit/ loss arising due to further processing 20,000 (-)4,000 (-)16,000
Suggested Product to be further processed for maximising profits:
On comparing the figures of “Profit if no further processing” and “Profits if further processing”, one
observes that OPR Ltd. is earning more after further processing of Product S only i.e. ` 20,000. Hence,
for maximizing profits, only Product S should be further processed and Product P, N and A should be
sold at split -off point.
Q-14 Mayura Chemicals Ltd buys a particular raw material at ` 8 per litre. At the end of the processing in
Department- I, this raw material splits-off into products X, Y and Z. Product X is sold at the split-off
point, with no further processing. Products Y and Z require further processing before they can be sold.
Product Y is processed in Department-2, and Product Z is processed in Department-3. Following is a
summary of the costs and other related data for the year 2019-20:
Particulars Department
1 2 3
Cost of Raw Material ` 4,80,000 - -
Direct Labour ` 70,000 ` 4,50,000 ` 6,50,000
Manufacturing Overhead ` 48,000 ` 2,10,000 ` 4,50,000
Products
X Y Z
Sales (litres) 10,000 15,000 22,500
Closing inventory (litres) 5,000 - 7,500
Sale price per litre (`) 30 64 50
There were no opening and closing inventories of basic raw materials at the beginning as well as at the
end of the year. All finished goods inventory in litres was complete as to processing. The company uses
the Net-realisable value method of allocating joint costs.
You are required to prepare:
(i) Schedule showing the allocation of joint costs.
(ii) Calculate the Cost of goods sold of each product and the cost of each item in Inventory.
(iii) A comparative statement of Gross profit.
Ans. (i) Statement of Joint Cost allocation of inventories of X, Y and Z
Products Total
X (`) Y (`) Z (`) (`)
Final sales value of 4,50,000 9,60,000 15,00,000 29,10,000
total production (15,000 x ` 30) (15,000 x ` 64) (30,000 x ` 50)
(Working Note 1)
Less: Additional cost — 6,60,000 11,00,000 17,60,000
Net realisable value 4,50,000 3,00,000 4,00,000 11,50,000
(at split-off point)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -379-
Q-15 A company’s plant processes 6,750 units of a raw material in a month to produce two products `M’ and
`N’.
The process yield is as under:
Product M 80%
Product N 12%
Process Loss 8%
The cost of raw material is ` 80 per unit.
Processing cost is ` 2,25,000 of which labour cost is accounted for 66%. Labour is
chargeable to products `M’ and `N’ in the ratio of 100:80.
Prepare a Comprehensive Cost Statement for each product showing:
(i) Apportionment of joint cost among products `M’ and `N’ and
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -381-
---0---0---
CHAPTER- 12
SERVICE COSTING
Q-1 AD Higher Secondary School (AHSS) offers courses for 11th & 12th standard in three streams i.e. Arts,
Commerce and Science. AHSS runs higher secondary classes alongwith primary and secondary classes
but for accounting purpose it treats higher secondary as a separate responsibility centre. The Managing
committee of the school wants to revise its fee structure for higher secondary students. The accountant
of the school has provided the following details for a year:
Amount (`)
Teachers’ salary (15 teachers × `35,000 × 12 months) 63,00,000
Principal’s salary 14,40,000
Lab attendants’ salary (2 attendants × `15,000 × 12 months) 3,60,000
Salary to library staff 1,44,000
Salary to peons (4 peons × ` 10,000 × 12 months) 4,80,000
Salary to other staffs 4,80,000
Examinations expenditure 10,80,000
Office & Administration cost 15,20,000
Annual day expenses 4,50,000
Sports expenses 1,20,000
Other information:
(i)
Standard 11 & 12 Primary & Secondary
Arts Commerce Science
No. of students 120 360 180 840
Lab classes in a year 0 0 144 156
No. of examinations in a year 2 2 2 2
Time spent at library per student
per year 180 hours 120 hours 240 hours 60 hours
Time spent by principal for
administration 208 hours 312 hours 480 hours 1,400 hours
Teachers for 11 & 12 standard 4 5 6 -
(ii) One teacher who teaches economics for Arts stream students also teaches commerce stream students.
The teacher takes 1,040 classes in a year, it includes 208 classes for commerce students.
(iii) There is another teacher who teaches mathematics for Science stream students also teaches business
mathematics to commerce stream students. She takes 1,100 classes a year, it includes 160 classes for
commerce students.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -385-
(iv) One peon is fully dedicated for higher secondary section. Other peons dedicate their 15% time for
higher secondary section.
(v) All school students irrespective of section and age participate in annual functions and sports activities.
Requirement:
(a) CALCULATE cost per student per annum for all three streams.
(b) If the management decides to take uniform fee of ` 1,000 per month from all higher secondary
students, CALCULATE stream wise profitability.
(c) If management decides to take 10% profit on cost, COMPUTE fee to be charged from the students
of all three streams respectively.
Ans. Calculation of Cost per annum
Particulars Arts (`) Commerce (`) Science (`) Total (`)
Teachers’ salary (W.N-1) 16,80,000 21,00,000 25,20,000 63,00,000
Re-apportionment of
Economics & Mathematics
teachers’ salary (W.N- 2) (84,000) 1,45,091 (61,091) -
Principal’s salary (W.N-3) 1,24,800 1,87,200 2,88,000 6,00,000
Lab assistants’ salary (W.N-4) - - 1,72,800 1,72,800
Salary to library staff (W.N-5) 43,200 28,800 57,600 1,29,600
Salary to peons (W.N-6) 31,636 94,909 47,455 1,74,000
Salary to other staffs (W.N-7) 38,400 1,15,200 57,600 2,11,200
Examination expenses (W.N- 8) 86,400 2,59,200 1,29,600 4,75,200
Office & Administration
expenses (W.N- 7) 1,21,600 3,64,800 1,82,400 6,68,800
Annual Day expenses (W.N-7) 36,000 1,08,000 54,000 1,98,000
Sports expenses (W.N- 7) 9,600 28,800 14,400 52,800
Total Cost per annum 20,87,636 34,32,000 34,62,764 89,82,400
(a) Calculation of cost per student per annum
Particulars Arts (`) Commerce (`) Science (`) Total (`)
Total Cost per annum 20,87,636 34,32,000 34,62,764 89,82,400
No. of students 120 360 180 660
Cost per student per annum 17,397 9,533 19,238 13,610
(b) Calculation of profitability
Particulars Arts (`) Commerce (`) Science (`) Total (`)
Total Fees per annum 12,000 12,000 12,000
Cost per student per annum 17,397 9,533 19,238
Profit/ (Loss) per student per annum (5,397) 2,467 (7,238)
No. of students 120 360 180
Total Profit/ (Loss) (6,47,640) 8,88,120 (13,02,840) (10,62,360)
` 4,20,000 ` 4,20,000
1,040 ×208 1,00 ×160
Total addition to Commerce stream = ` 84,000 + ` 61,091 = ` 1,45,091
(3) Principal’s salary has been apportioned on the basis of time spent by him for administration of
classes.
(4) Lab attendants’ salary has been apportioned on the basis of lab classes attended by the students.
(5) Salary of library staffs are apportioned on the basis of time spent by the students in library.
(6) Salary of Peons are apportioned on the basis of number of students. The peons’ salary allocable to
higher secondary classes is calculated as below:
Amount ( `)
Peon dedicated for higher secondary (1 peon × `10,000 × 12 months) 1,20,000
Add: 15% of other peons’ salary {15% of (3 peons × `10,000 × 12 months)} 54,000
1,74,000
(7) Salary to other staffs, office & administration cost, Annual day expenses and sports expenses are
apportioned on the basis of number of students.
(8) Examination Expenses has been apportioned taking number of students and number of examinations
into account.
Q-2 A transport company has a fleet of four trucks of 10 tonne capacity each plying in different directions
for transport of customer’s goods. The trucks run loaded with goods and return empty. The distance
travelled, number of trips made and the load carried per day by each truck are as under:
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -387-
` 1,13,39,112
= ` 26.89
4,21,632 kms
(iii) Freight rate per tonne km (to yield a profit of 30% on freight)
` 1,13,39,112
= = ` 7.04
16,10,496 kms
` 7.04
= Freight rate per tonne km. × 1 = ` 10.06
0.7
Working Notes:
1. Total kilometre travelled and tonnes kilometre (load carried) by four trucks in one year
Truck One way No. of Total distance Load carried Total
number distance trips covered in km per trip / day effective
in kms per day in tonnes tonnes km
1 48 4 384 6 1,152
2 120 1 240 9 1,080
3 90 2 360 8 1,440
4 60 4 480 8 1,920
Total 1,464 5,592
Total kilometre travelled by four trucks in one year
(1,464 km. × 24 days × 12 months) = 4,21,632
Total effective tonnes kilometre of load carried by four trucks during one year
(5,592 tonnes km. × 24 days × 12 months) = 16,10,496
2. Fixed and variable component of maintenance cost:
` 1,38,150 - ` 1,35,525
=
1,60,200 kms -1,56,700 kms
= ` 0.75
Fixed maintenance cost = Total maintenance cost–Variable maintenance cost
= ` 1,38,150 – 1,60,200 kms × ` 0.75 = ` 18,000
Q-3 A company runs a holiday home. For this purpose, it has hired a building at a rent of `10,00,000 per
month alongwith 5% of total taking. It has three types of suites for its customers, viz., single room,
double rooms and triple rooms.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -389-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -391-
Ans.
(i) Calculation of total cost for ‘Professionals Protect Plus’ policy
Particulars Amount (`) Amount (`)
1. Marketing and Sales support:
- Policy development cost 11,25,000
- Cost of marketing 45,20,000
- Sales support expenses 11,45,000 67,90,000
2. Operations:
- Policy issuance cost 10,05,900
- Policy servicing cost 35,20,700
- Claims management cost 1,25,600 46,52,200
3. IT Cost 74,32,000
4. Support functions
- Postage and logistics 10,25,000
- Facilities cost 15,24,000
- Employees cost 5,60,000
- Office administration cost 16,20,400 47,29,400
Total Cost 2,36,03,600
Total cost ` 2,36,03,600
(ii) Calculation of cost per policy = = = `44,703.79
No. of policies 528
Q-5 AD Higher Secondary School (AHSS) offers courses for 11th & 12th standard in three streams i.e. Arts,
Commerce and Science. AHSS runs higher secondary classes along with primary and secondary classes
but for accounting purpose it treats higher secondary as a separate responsibility centre. The Managing
committee of the school wants to revise its fee structure for higher secondary students. The accountant
of the school has provided the following details for a year:
Amount (`)
Teachers’ salary (15 teachers × `35,000 × 12 months) 63,00,000
Principal’s salary 14,40,000
Lab attendants’ salary (2 attendants × `15,000 × 12 months) 3,60,000
Salary to library staff 1,44,000
Salary to peons (4 peons × `10,000 × 12 months) 4,80,000
Salary to other staffs 4,80,000
Examinations expenditure 10,80,000
Office & Administration cost 15,20,000
Annual day expenses 4,50,000
Sports expenses 1,20,000
-392- Chapter-12 : Service Costing
Other information:
(i)
Standard 11 & 12 Primary
Arts Commerce Science & Secondary
No. of students 120 360 180 840
Lab classes in a year 0 0 144 156
No. of examinations in a year 2 2 2 2
Time spent at library per student per year 180 hours 120 hours 240 hours 60 hours
Time spent by principal for administration 208 hours 312 hours 480 hours 1,400 hours
Teachers for 11 & 12 standard 4 5 6 -
(ii) One teacher who teaches economics for Arts stream students also teaches commerce stream students.
The teacher takes 1,040 classes in a year, it includes 208 classes for commerce students.
(iii) There is another teacher who teaches mathematics for Science stream students also teaches business
mathematics to commerce stream students. She takes 1,100 classes a year, it includes 160 classes for
commerce students.
(iv) One peon is fully dedicated for higher secondary section. Other peons dedicate their 15% time for
higher secondary section.
(v) All school students irrespective of section and age participates in annual functions and sports activities.
Required:
(i) CALCULATE cost per student per annum for all three streams.
(ii) If the management decides to take uniform fee of ` 1,000 per month from all higher secondary students,
CALCULATE stream wise profitability.
(iii) If management decides to take 10% profit on cost, COMPUTE fee to be charged from the students of all
three streams respectively.
Ans. Calculation of Cost per annum
Particulars Arts (`) Commerce Science Total (`)
(` ) (` )
Teachers’ salary (W.N-1) 16,80,000 21,00,000 25,20,000 63,00,000
R-apportionment of Economics (84,000) 1,45,091 (61,091) -
& Mathematics teachers’ salary
(W.N- 2)
Principal’s salary (W.N-3) 1,24,800 1,87,200 2,88,000 6,00,000
Lab assistants’ salary (W.N-4) - - 1,72,800 1,72,800
Salary to library staff (W.N-5) 43,200 28,800 57,600 1,29,600
Salary to peons (W.N-6) 31,636 94,909 47,455 1,74,000
Salary to other staffs (W.N-7) 38,400 1,15,200 57,600 2,11,200
Examination expenses (W.N- 8) 86,400 2,59,200 1,29,600 4,75,200
Office & Administration
expenses (W.N- 7) 1,21,600 3,64,800 1,82,400 6,68,800
Annual Day expenses (W.N-7) 36,000 1,08,000 54,000 1,98,000
Sports expenses (W.N- 7) 9,600 28,800 14,400 52,800
Total Cost per annum 20,87,636 34,32,000 34,62,764 89,82,400
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -393-
` 4,20,000 ` 4,20,000
1,040 208 1,040 160
(3) Principal’s salary has been apportioned on the basis of time spent by him for administration of classes.
(4) Lab attendants’ salary has been apportioned on the basis of lab classes attended by the students.
(5) Salary of library staffs are apportioned on the basis of time spent by the students in library.
(6) Salary of Peons are apportioned on the basis of number of students. The peons’ salary allocable to
higher secondary classes is calculated as below:
Amount (`)
Peon dedicated for higher secondary 1,20,000
(1 peon × `10,000 × 12 months)
Add: 15% of other peons’ salary 54,000
{15% of (3 peons × `10,000 × 12 months)} 1,74,000
(7) Salary to other staffs, office & administration cost, Annual day expenses and sports expenses are
apportioned on the basis of number of students.
(8) Examination Expenses has been apportion taking number of students and number examinations into
account.
Q-6 A hotel is being run in a Hill station with 200 single rooms. The hotel offers concessional rates during six
off-season months in a year. During this period, half of the full room rent is charged. The management’s
profit margin is targeted at 20% of the room rent. The following are the cost estimates and other details
for the year ending 31stMarch,2019:
(i) Occupancy during the season is 80% while in the off-season it is 40%.
(ii) Total investment in the hotel is ` 300 lakhs of which 80% relates to Buildings and the balance to
Furniture and other Equipment.
(iii) Room attendants are paid ` 15 per room per day on the basis of occupancy of rooms in a month.
(iv) Expenses:
• Staff salary (excluding that of room attendants) ` 8,00,000
• Repairs to Buildings ` 3,00,000
• Laundry Charges ` 1,40,000
• Interior Charges ` 2,50,000
• Miscellaneous Expenses ` 2,00,200
(v) Annual Depreciation is to be provided on Buildings @ 5% and 15% on Furniture and other
Equipments on straight line method.
(vi) Monthly lighting charges are ` 110, except in four months in % winter when it is ` 30 per room and
this cost is on the basis of full occupancy for a month.
You are required to workout the room rent chargeable per day both during the season and the off-
season months using the foregoing information.
(Assume a month to be of 30days and winter season to be considered as part of off-season).
Ans. Working Notes:
(i) Total Room days in a year
Season Occupancy (Room-days) Equivalent Full Room charge days
Season – 80% Occupancy 200 Rooms × 80% × 6 28,800 Room Days × 100%
months × 30 days in a = 28,800
month = 28,800 Room Days
Off-season – 40% 200 Rooms × 40% × 6 14,400 Room Days × 50%
Occupancy months × 30 days in a = 7,200
month = 14,400 Room Days 36,000 Full Room days
Total Room Days 28,800 + 14,400 = 43,200
Room Days
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -395-
(i) Weighted Average or Absolute basis – It is summation of the products of qualitative and
quantitative factors. For example, to calculate absolute Ton-Km for a goods transport is
calculated as follows.:
(Weight Carried × Distance)1 + (Weight Carried × Distance)2 + ..... + (Weight Carried × Distance)n
Similarly, in case of Cinema theatres, price for various classes of seats are fixed differently.
For example–
First class seat may be provided with higher quality service and hence charged at a higher
rate, whereas Second Class seat may be priced less. In this case, appropriate weight to be
given effect for First Class seat and Second Class seat – to ensure proper cost per composite
unit.
(ii) Simple Average or Commercial basis – It is the product of average qualitative and total
quantitative factors. For example, in case of goods transport, Commercial Ton-Km is arrived
at by multiplying total distance km., by average load quantitTy.
w + W2 +.......Wn
(Distance1 + Distance2 + .......... & + Distancen ) × 1
n
In both the example, variable cost is dependent of distance and is a quantitative factor.
Since, the weight carried does not affect the variable cost hence and is a qualitative factor.
Q-8 X Ltd. distributes’ its goods to a regional dealer using single lorry. The dealer premises are 40 kms away
by road. The capacity of the lorry is 10 tonnes. The lorry makes the journey twice a day fully loaded on
the outward journey and empty on return journey. The following information is available:
Diesel Consumption 8 km per litre
Diesel Cost ` 60 per litre
Engine Oil ` 200 per week
Driver’s Wages (fixed) ` 2,500 per week
Repairs ` 600 per week
Garage Rent ` 800 per week
Cost of Lorry (excluding cost of tyres) ` 9,50,000
Life of Lorry 1,60,000 kms
Insurance ` 18,200 per annum
Cost of Tyres ` 52,500
Life of Tyres 25,000 kms
Estimated sale value of the lorry at end of its life is ` 1,50,000
Vehicle License Cost ` 7,800 per annum
Other Overhead Cost ` 41,600 per annum
The lorry operates on a 5 day week.
Required :
(i) A statement to show the total cost of operating the vehicle for the four week period analysed into
Running cost and Fixed cost.
(ii) Calculate the vehicle operating cost per km and per tonne km. (Assume 52 weeks in a year)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -397-
` 9,50,000 -` 1,50,000
3,200km
1,60,000 km
` 52,500
Depreciation on tyres 3,200km 6,720 1,680
25,000km
Total (B) 49,920 12,480
C. Total Cost (A + B) 68,320 17,080
*Cost of engine oil & repairs may also be treated as fixed cost, as the question relates these with time
i.e. in weeks instead of running of vehicle.
(ii) Calculation of vehicle operating cost :
Operating cost per k.m. = ` 68,320 or ` 17,080 = ` 21.35
3,200 kms 800 Kms
Operating cost per Tonne-k.m. = ` 68,320 or ` 17,080 = ` 4.27
16,000 4,000
Q-9 M/s XY Travels has been given a 25 km. long route to run an air- conditioned Mini Bus.
The cost of bus is ` 20,00,000. It has been insured @3% premium per annum while annual road tax
amounts to ` 36,000. Annual repairs will be ` 50,000 and the bus is likely to last for 5 years. The driver's
salary will be `2,40,000 per annum and the conductor's salary will be ` 1,80,000 per annum in addition
to 10% of the takings as commission (to be shared by the driver and the conductor equally). Office and
administration overheads will be ` 18,000 per annum. Diesel and oil will be ` 1,500 per 100 km. The bus
will make 4 round trips carrying on an average 40 passengers on each trip.
Assuming 25% profit on takings and considering that the bus will run on an average 25 days in a month,
you are required to:
(i) prepare operating cost sheet (for the month).
(ii) calculate fare to be charged per passenger km.
Ans.
(i) Statement showing the Operating Cost per Passenger-km.
Yearly (`) Monthly (`)
(A) Standing Charges:
Insurance Charge ` 20,00,000 × 3% 60,000 5,000
Road Tax 36,000 3,000
Depreciation (20,00,000/5) 4,00,000 33,333.33
Total 4,96,000 41,333.33
(B) Maintenance Charges:
Annual Repairs 50,000 4166.67
Office and administration overheads 3,18,000 26,500
Total 3,68,000 30666.67
(C) Running Cost/Charges:
Driver’s Salary 2,40,000 20,000
Conductor’s Salary 1,80,000 15,000
1,500
Diesel & Oil 60,000 9,00,000 75,000
100
Total 13,20,000 41,333.33
Total (A+B+C) Cost before commission and profit 21,84,000 1,82,000
Commission (33,60,000 × 10%) (working note 2) 3,36,000 28,000
Profit (33,60,000 × 25% ) (working note 2) 8,40,000 70,000
Takings (working note 1) 33,60,000 2,80,000
Total Collection / Takings
(ii) Fare per Passenger-km. =
Total Passenger - km (Working note 3)
33,60,000
= ` 1.40
24,00,000
OR
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -399-
2,80,000
Fare per Passenger-km. (monthly) = = ` 1.40
2,00,000
Working note :
1. Cost before commission (10%) and profit (25%) is 21,84,000 which is 65% of total takings. So total
takings is (21,84000÷65) ×100 = ` 33,60,000
2. Commission is 10% of ` 33,60,000 = ` 3,36,000 and Profit is 25% of ` 33,60,000= ` 8,40,000
3. Total Km is (4 Round Trips × Days in a month × Month = (4×2×25 ×25×12 ) = 60,000 km
Passenger km is 60,000 km×40 passenger= 24,00,000.
Q-10 A group of ‘Health Care Services’ has decided to establish a Critical Care Unit in a metro city with an
investment of ` 85 lakhs in hospital equipments. The unit’s capacity shall be of 50 beds and 10 more
beds, if required, can be added. Other information for a year are as under:
(`)
Building Rent 2,25,000 per month
Manager Salary (Number of Manager-03) 50,000 per month to each one
Nurses Salary (Number of Nurses-24) 18,000 per month to each Nurse
Ward boy’s Salary (Number of ward boys’ -24) 9,000 per month per person
Doctor’s payment (Paid on the basis of number 5,50,000 per month
of patients attended and time spent by them)
Food and laundry services (variable) 39,53,000
Medicines to patients (variable) 22,75,000 per year
Administrative Overheads 28,00,000 per year
Depreciation on equipments 15% per annum on original cost
It was reported that for 200 days in a year 50 beds were occupied, for 105 days 30 beds were occupied
and for 60 days 20 beds were occupied.
The hospital hired 250 beds at a charge of ` 950 per bed to accommodate the flow of patients. However,
this never exceeded the normal capacity of 50 beds on any day. Find out: (i) Profit per patient day, if
hospital charges on an average ` 2,500 per day from each patient. (ii) Break even point per patient day
(Make calculation on annual basis)
Ans Number of Patient Days = (200x50) + (105x30) + (60x20)
=14,350 patient days + 250 = 14,600
Statement Showing Profit
Elements of Cost and Revenue Total (`)
A. Revenue (14,600 x ` 2,500) 3,65,00,000
B. Variable Costs
Food and Laundry Service 39,53,000
Medicines to Patients 22,75,000
Doctor’s Payment 66,00,000
Hire Charges of Bed (250 x ` 950) 2,37,500
Total Variable Cost 1,30,65,500
C. Fixed Costs
Building Rent 27,00,000
Manager’s Salary (` 50,000 x 3 x 12) 18,00,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -401-
Rs.7.48
Freight rate per tonne km. x 1 = Rs. 8.31
0.9
Working Notes:
1. Total kilometer travelled and Commercial tonnes kilometer (load carried) by three trucks in one year
Truck One way No. of Total Total Load Total
distance in kms trips distance distance carried effective
covered in covered in per trip / tonnes km
km per day km per day day in
(with load) (up & down) tonnes
a b c=a ×b d=c× 2 e f = 27/3 × c
1 16 4 64 128 6 576
2 40 2 80 160 9 720
3 30 3 90 180 12 810
Total 234 468 27 2,106
Total kilometre travelled by three trucks in one year
(468 km . × 24 days × 12 months) = 1,34,784
Total effective tonnes kilometre of load carri ed by three trucks during one year
Sundries 30.28
Depreciation (refer W.N- 4):
- Building 45.00
- Furniture & Fixture 9.00
- Air Conditioners 7.50
Total cost for the year 1,666.98
Computation of profit:
Let ` x be the rent for deluxe from.
Equivalent deluxe room days are 90,720 (refer W.N- 2)
Total takings = ` 90,720x
Profit is 25% of total takings.
Profit = 25% of ` 90,720x = ` 22,680x
Total takings = Total Cost + Profit
` 90,720x = ` 16,66,98,000 + ` 22,680x
` 90,720x - ` 22,680x = ` 16,66,98,000
` 68,040x = ` 16,66,98,000
` 116,66,98,000
X= ` 68,040 = 2,450
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -405-
Running expenses:
Repair and maintenance 15,000 1,250
Replacement of tyre-tube 3,600 300
Diesel and oil cost (9,000 km × Rs. 5) - 45,000
Driver and conductor’s salary - 5,000
Total cost (per month) 61,550.00
Add: Profit 20% of total revenue cost or 25% of total cost 15,387.50
Total revenue 76,937.50
Rate per passenger-km Rs. 76,937.50/1,80,000 passenger km = 0.42743 i.e., = 0.43 i.e., 43 paise.
Q-14 SLS Infrastructure builts and operates a 110 k.m. long highway on the basis of Built-Operate-Transfer
(BOT) model for a period of 25 years. A traffic assessment has been carried out to estimate the traffic
flow per day. The details are as below:
Sl. No. Type of vehicle Daily traffic volume
1. Two wheelers 44,500
2. Car and SUVs 3,450
3. Bus and LCV 1,800
4. Heavy commercial vehicles 816
The following is the estimated cost of the project:
Sl. no. Activities Amount (Rs. in lakh)
1 Site clearance 170.70
2 Land development and filling work 9,080.35
3 Sub base and base courses 10,260.70
4 Bituminous work 35,070.80
5 Bridge, flyovers, underpasses, Pedestrian subway, footbridge, etc. 29,055.60
6 Drainage and protection work 9,040.50
7 Traffic sign, marking and road appurtenance 8,405.00
8 Maintenance, repairing and rehabilitation 12,429.60
9 Environmental management 982.00
Total Project cost 1,14,495.25
An average cost of Rs.1,120 lakh has to be incurred on administration and toll plaza operation.
On the basis of the vehicle specifications (i.e. weight, size, time saving etc.), the following weights has
been assigned to the passing vehicles:
Sl. No. Type of vehicle
1. Two wheelers 5%
2. Car and SUVs 20%
3. Bus and LCV 30%
4. Heavy commercial vehicles 45%
Required:
(i) Calculate the total project cost per day of concession period.
(ii) Compute toll fee to be charged for per vehicle of each type, if the company wants to earn a profit
of 15% on total cost.
[Note: Concession period is a period for which an infrastructure is allowed to operate and recovers its
investment]
-406- Chapter-12 : Service Costing
Ans.(a) (i) Calculation of total project cost per day of concession period:
Activities Amount (Rs. in lakh)
Site clearance 170.70
Land development and filling work 9,080.35
Sub base and base courses 10,260.70
Bituminous work 35,070.80
Bridge, flyovers, underpasses, Pedestrian subway, footbridge, etc 29,055.60
Drainage and protection work 9,040.50
Traffic sign, marking and road appurtenance 8,405.00
Maintenance, repairing and rehabilitation 12,429.60
Environmental management 982.00
Total Project cost 1,14,495.25
Administration and toll plaza operation cost 1,120.00
Total Cost 1,15,615.25
Concession period in days (25 years × 365 days) 9,125
Cost per day of concession period (Rs. in lakh) 12.67
(ii) Computation of toll fee:
Cost to be recovered per day = Cost per day of concession period + 15% profit on cost
= Rs.12,67,000 + Rs.1,90,050 = Rs.14,57,050
` 14,57,050
Cost per equivalent vehicle = 76,444 units Refer working note
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -407-
Q-15 DKG Airlines owns single passenger aircraft and operates between Melbourne and Delhi only. Flight
leaves Melbourne on Monday and Thursday and departs from Delhi on Wednesday and Saturday. DKG
Airlines cannot afford any more flight between Melbourne and Delhi. Only economical class seats are
available on its flight and all tickets are booked by travel agents. The following information are collected.
Seating capacity per plane 360
Average passengers per flight 250
Flights per week 4
Flights per year 208
Average one-way fare Rs.50,000
Variable fuel cost Rs.28,00,000 per flight
Food service to passengers (not charged to Passengers) Rs.2,600 per passenger
Commission to travel agents 15% of fare
Fixed annual lease cost allocated to each flight Rs. 15,30,000 per flight
Fixed ground services (maintenance, check in,
Baggage handling cost) allocated to each flight Rs.1,70,000 per flight
Fixed salaries of flight crew allocated to each flight Rs.6,50,000 per flight
For the sake of simplicity assume that fuel cost is unaffected by the actual number of passengers on a
flight.
Required:
(i) Calculate the operating income that DKG Airlines makes on each way flight between Melbourne
and Delhi?
(ii) The market research department of DKG Airlines indicates that lowering the average one-way
fare to Rs. 48,000 and increase in agents’ commission to 17.5% will increase the average number
of passenger per flight to 275. DECIDE whether DKG Airlines should lower its fare or not?
Ans.(i) Statement of operating income of DKG Airlines for Melbourne-Delhi flight (one way)
Particulars Amount(`) Amount(`)
Fare received (per flight): 250 passengers × ` 50,000 1,25,00,000
Variable costs (per flight):
- Fuel cost 28,00,000
- Food (250 × ` 2,600) 6,50,000
- Commission to Travel Agents (15% of ` 1,25,00,000) 18,75,000 (53,25,000)
Contribution per flight 71,75,000
Fixed cost (per flight):
Annual lease cost 15,30,000
Fixed ground service costs 1,70,000
Salaries of flight crew 6,50,000 (23,50,000)
Operating income per flight 48,25,000
(ii) Operating income of DKG Airlines per Melbourne-Delhi flight (one way) after reduction in fare
Fare received (per flight): 275 passengers × ` 48,000 1,32,00,000
Variable costs (per flight):
Fuel cost 28,00,000
Food (275 × `2,600) 7,15,000
Commission to Travel Agents (17.5% of `1,32,00,000) 23,10,000 (58,25,000)
Contribution per flight 73,75,000
-408- Chapter-12 : Service Costing
Excess contribution due to lowering of fare (` 73,75,000 – ` 71,75,000) = `2,00,000. DKG Airlines should
lower its fare as it would increase its contribution by ` 2,00,000.
Q-16 Happy Transport Service is a Delhi based national goods transport service provider, owning four trucks
for this purpose. The cost of running and maintaining these trucks are as follows:
Particulars Amount
Diesel cost Rs.13.75 per km.
Engine oil Rs.4,200 for every 13,000 km.
Repair and maintenance Rs.12,000 for every 10,000 km.
Driver’s salary Rs.18,000 per truck per month
Cleaner’s salary Rs.7,500 per truck per month
Supervision and other general expenses Rs.12,000 per month
Cost of loading of goods Rs.150 per Metric Ton (MT)
Each trucks were purchased for Rs. 20 lakhs with an estimated life of 7,20,000 km.
During the next month, it is expecting 6 bookings, the details are as follows:
Sl. No. Journey Distance in km Weight- Up (in MT) Weight- Down (in MT)
1. Delhi to Kochi 2,700 14 6
2. Delhi to Guwahati 1,890 12 0
3. Delhi to Vijayawada 1,840 15 0
4. Delhi to Varanasi 815 10 0
5. Delhi to Asansol 1,280 12 4
6. Delhi to Chennai 2,185 10 8
Total 10,710 73 18
Required
(i) Calculate the total absolute Ton-km for the vehicles.
(ii) Calculate the cost per ton-km.
Ans.
(i) Calculation of Absolute Ton-km for the next month:
Journey Distance Weight-Up Ton-km WeightDown Ton-km Total
in km (in MT) (in MT)
(a) (b) (c)=(a)×(b) (d) (e) =(a)×(d) (c) + (e)
Delhi to Kochi 2,700 14 37,800 6 16,200 54,000
Delhi to Guwahati 1,890 12 22,680 0 0 22,680
Delhi to Vijayawada 1,840 15 27,600 0 0 27,600
Delhi to Varanasi 815 10 8,150 0 0 8,150
Delhi to Asansol 1,280 12 15,360 4 5,120 20,480
Delhi to Chennai 2,185 10 21,850 8 17,480 39,330
Total 10,710 73 1,33,440 18 38,800 1,72,240
Total Ton-Km = 1,72,240 ton-km
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -409-
Rs.4,200
- Engine oil cost × 21, 420km 6,920.31
13, 000km
- Cost of loading of goods {Rs.150 × (73+18)} 13,650.00
Rs.12, 000
B. Repairs & Maintenance Cost × 21, 420km 25,704
10, 000km
C. Standing Charges
- Drivers’ salary (Rs.18,000 × 4 trucks) 72,000
- Cleaners’ salary (Rs.7,500 × 4 trucks) 30,000
- Supervision and other general exp. 12,000 1,14,000
Total Cost (A + B + C) 5,14,299.31
Total ton-km 1,72,240
Cost per ton-km 2.99
Q-17 A transport company has 20 vehicles, the capacities are as follows:
No. of Vehicles Capacity per vehicle
5 9 MT
6 12 MT
7 15 MT
2 20 MT
The company provides the goods transport service between stations ‘A’ to station ‘B’. Distance between
these stations is 100 kilometers. Each vehicle makes one round trip per day on an average. Vehicles are
loaded with an average of 90 per cent of capacity at the time of departure from station ‘A’ to station ‘B’
and at the time of return back loaded with 70 per cent of capacity. 10 per cent of vehicles are laid up for
repairs every day. The following information is related to the month of August, 2020:
Salary of Transport Manager ` 60,000
Salary of 30 drivers `20,000 each driver
Wages of 25 Helpers `12,000 each helper
Loading and unloading charges ` 850 each trip
Consumable stores (depends on running of vehicles) ` 1,35,000
Insurance (Annual) ` 8,40,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -411-
(90% + 70%)
= [(5 x 9 MT) + (6 x 12MT) + (7 x 15 MT) + (2 x 20 MT)] x 4, 500 k.m. x
2
= (45 + 72 + 105 + 40) x 4,500 k.m. x 80%
= 262 x 4,500 x 80%.
= 9,43,200 ton-km.
Q-18 MKL Infrastructure built and operates 110 k.m. highway on the basis of Built-Operate-Transfer (BOT)
for a period of 21 years. A traffic assessment has been carried out to estimate the traffic flow per day
which shows the following figures:
Sl. No. Type of vehicle Daily traffic volume
1. Two wheelers 44,500
2. Car and SUVs 3,450
3. Bus and LCV 1,800
4. Heavy commercial vehicles 816
The following is the estimated cost of the project:
Sl. no. Activities Amount
(` in lakh)
1 Site clearance 341.00
2 Land development and filling work 9,160.00
3 Sub base and base courses 10,520.00
4 Bituminous work 32,140.00
5 Bridge, flyovers, underpasses, Pedestrian subway, footbridge, etc 28,110.00
6 Drainage and protection work ,080.00
7 Traffic sign, marking and road appurtenance 8,810.00
8 Maintenance, repairing and rehabilitation 12,850.00
9 Environmental management 1,964.00
Total Project cost 1,12,975.00
An average cost of ` 1,200 lakh has to be incurred on administration and toll plaza operation.
On the basis of the vehicle specifications (i.e. weight, size, time saving etc.), the following weights has
been assigned to the passing vehicles:
Sl. No. Type of vehicle
1. Two wheelers 5%
2. Car and SUVs 20%
3. Bus and LCV 30%
4. Heavy commercial vehicles 45%
Required:
(i) CACULATE the total project cost per day of concession period.
(ii) COMPUTE toll fee to be charged for per vehicle of each type, if the company wants earn a profit of
15% on total cost.
[Note: Concession period is a period for which an infrastructure is allowed to operate and recover its
investment]
Ans. (i) Calculation of total project cost per day of concession period:
Activities Amount (` in lakh)
Site clearance 341.00
Land development and filling work 9,160.00
Sub base and base courses 10,520.00
Bituminous work 32,140.00
Bridge, flyovers, underpasses, Pedestrian subway, footbridge, etc 28,110.00
Drainage and protection work 9,080.00
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -413-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -415-
The distance travelled by each bus, one way is 8 km. The school works 22 days in a month and remains
closed for vacation in May and June. The bus fee, however, is payable by the students for all the 12
months in a year.
The details of expenses for a year are as under:
Driver’s salary – payable for all the 12 in months ` 12,000 per month per driver
Cleaner’s salary payable for all the 12 months ` 8,000 per month per cleaner
License fees, taxes etc. ` 8,400 per bus per annum
Insurance Premium ` 15,600 per bus per annum
Repairs and Maintenance ` 20,500 per bus per annum
Purchase price of the bus ` 20,00,000 each
Life of the bus 16 years
Scrap value ` 1,60,000
Diesel Cost ` 78.50 per litre
Each bus gives an average of 5 km. per litre of diesel. The seating capacity of each bus is 40 students.
The school follows differential transportation fees based on distance travelled as under:
Students picked up and dropped within Transportation Percentage of students
the range of distance from the school fee availing this facility
2 km. 25% of Full 15%
4 km. 50% of Full 30%
8 km. Full 55%
Due to a pandemic, lockdown imposed on schools and the school remained closed from April 2020 to
December 2020. Drivers and cleaners were paid 75% of their salary during the lockdown period.
Repairing cost reduced to 75% for the year 2020.
Ignore the interest cost.
Required:
(i) PREPARE a statement showing the expenses of operating a single bus and the fleet of 25 buses for
a year.
(ii) FIND OUT transportation fee per student per month in respect of:
(a) Students coming from a distance of upto 2 km. from the school.
(b) Students coming from a distance of upto 4 km. from the school; and
(c) Students coming from a distance of upto 8 km. from the school.
(iii) CALCULATE the minimum bus fare that has to be recovered from the students for the year 2020.
Ans. (i) Statement showing the expenses of operating a single bus and
the fleet of 25 buses for a year
Particulars Per bus Fleet of 25
per annum buses
(` ) per annum
(` )
Running costs : (A)
Diesel (Refer to working note 1) 2,21,056 55,26,400
Repairs & maintenance costs: (B) 20,500 5,12,500
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -417-
Fixed charges:
Driver’s salary
(` 12,000 × 12 months) 1,44,000 36,00,000
Cleaners salary
(` 8,000 × 12 months) 96,000 24,00,000
Licence fee, taxes etc. 8,400 2,10,000
Insurance 15,600 3,90,000
`20,00,000 -`1,60,000
Depreciation 16 years 1,15,000 28,75,000
Total fixed charges: (C) 3,79,000 94,75,000
Total expenses: (A+B+C) 6,20,556 1,55,13,900
(ii) Average cost per student per month in respect of students coming from a distance of:
(a) 2 km. from the school {` 6,20,556 / (236 students × 12 months)}
(Refer to Working Note 2) ` 219.12
(b) 4 km. from the school (` 219.12 × 2) ` 438.24
(c) 8 km. from the school (` 219.12 × 4) ` 876.48
(iii) Calculation of minimum bus fare to be recovered from the students during the year 2020:
Statement showing the expenses of operating a single bus in year 2020
Particulars Per bus
per annum
(`)
Running costs : (A)
Diesel (Refer to working note 3) 66,316.80
Repairs & maintenance costs: (B)
(` 20,500 x 0.75) 15,375
Fixed charges:
Driver’s salary 1,17,000
{` 12,000 × 3 months + (75% of ` 12,000 × 9 months)}
Cleaners salary 78,000
{` 8,000 × 3 months + (75% of ` 8,000 × 9 months)}
Licence fee, taxes etc. 8,400
Insurance 15,600
`20,00,000 -`1,60,000
Depreciation 16 years 1,15,000
Total fixed charges: (C) 3,34,000
Total expenses: (A+B+C) 4,15,691.80
Toll Rate: In general, the toll rate should have a direct relation with the benefits that the road users
would gain from its improvements. The benefits to road users are likely to be in terms of fuel savings,
improvement in travel time and good riding quality.
To compute the toll rate, following formula may be used
= Total Cost + Profit / Number of Vehicles
Or, to compute the toll rate following formula with rounding off to nearest multiple of five has been
adopted: User fee = Total distance x Toll rate per km.
Q-22 Navya LMV Pvt. Ltd, operates cab/ car rental service in Delhi/NCR. It provides its service to the offices
of Noida, Gurugram and Faridabad. At present it operates CNG fuelled cars but it is also considering to
upgrade these into Electric vehicle (EV). The details related with the owning of CNG & EV propelled
cars are as tabulated below:
Particulars CNG Car EV Car
Car purchase price (`) 9,20,000 15,20,000
Govt. subsidy on purchase of car (`) — 1,50,000
Life of the car 15 years 10 years
Residual value (`) 95,000 1,70,000
Mileage 20 km/kg 240 km per charge
Electricity consumption per full charge — 30 Kwh
CNG cost per Kg (`) 60 —
Power cost per Kwh (`) — 7.60
Annual Maintenance cost (`) 8,000 5,200
Annual insurance cost (`) 7,600 14,600
Tyre replacement cost in every 5 -year (`) 16,000 16,000
Battery replacement cost in every 8- year (`) 12,000 5,40,000
Apart from the above, the following are the additional information:
Particulars
Average distance covered by a car in a month 1,500 km
Driver’s salary (`) 20,000 p.m
Garage rent per car (`) 4,500 p.m
Share of Office & Administration cost per car (`) 1,500 p.m
Required:
CALCULATE the operating cost of vehicle per month per car for both CNG & EV options.
Ans. Working Notes:
1. Calculation of Depreciation per month:
Particulars CNG Car EV Car
A Car purchase price (`) 9,20,000 15,20,000
B Less: Govt. subsidy (`) — (1,50,000)
C Less: Residual value (`) (95,000) (1,70,000)
D Depreciable value of car (`) [A-B-C] 8,25,000 12,00,000
E Life of the car 15 years 10 years
F Annual depreciation (`) [D÷E] 55,000 1,20,000
G Depreciation per month (`) [F÷12] 4,583.33 10,000
CHAPTER- 13
STANDARD COSTING
Q-1 ABC Ltd. had prepared the following estimation for the month of January:
Quantity Rate (`) Amount (`)
Material-A 800 kg. 90.00 72,000
Material-B 600 kg. 60.00 36,000
Skilled labour 1,000 hours 75.00 75,000
Unskilled labour 800 hours 44.00 35,200
Normal loss was expected to be 10% of total input materials and an idle labour time of 5% of expected
labour hours was also estimated.
At the end of the month the following information has been collected from the cost accounting
department:
The company has produced 1,480 kg. finished product by using the followings:
Quantity Rate (`) Amount (`)
Material-A 900 kg. 86.00 77,400
Material-B 650 kg. 65.00 42,250
Skilled labour 1,200 hours 71.00 85,200
Unskilled labour 860 hours 46.00 39,560
You are required to CALCULATE:
(a) Material Cost Variance;
(b) Material Price Variance;
(c) Material Mix Variance;
(d) Material Yield Variance;
(e) Labour Cost Variance;
(f) Labour Efficiency Variance and
(g) Labour Yield Variance.
Ans. Material Variances:
Material SQ SP SQ × SP RSQ RSQ × SP AQ AQ × SP AP AQ × AP
(WN-1) (` ) (`) (WN-2) (`) (`) (` ) (`)
A 940 kg. 90.00 84,600 886 kg. 79,740 900 kg. 81,000 86.00 77,400
B 705 kg. 60.00 42,300 664 kg. 39,840 650 kg. 39,000 65.00 42,250
1645 kg 1,26,900 1550 kg 1,19,580 1550 kg 1,20,000 1,19,650
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -423-
800 kg
Material A- ×1,480 kg. = 939.68 or 940 kg.
0.9 ×1,400kg
600 kg
Material B- ×1,480 kg. = 704.76 or 705 kg.
0.9 ×1,400kg
WN- 2: Revised Standard Quantity (RSQ):
800 kg
Material A- ×1,550 kg. = 885.71 or 886 kg.
1,400kg
600 kg
Material B- ×1,550 kg. = 664.28 or 664 kg.
1,400kg
(a) Material Cost Variance (A + B) = {(SQ × SP) – (AQ × AP)}
= {1,26,900 – 1,19,650} = 7,250 (F)
(b) Material Price Variance (A + B) = {(AQ × SP) – (AQ × AP)
= {1,20,000 – 1,19,650} = 350 (F)
(c) Material Mix Variance (A + B) = {(RSQ × SP) – (AQ × SP)}
= {1,19,580 – 1,20,000} = 420 (A)
(d) Material Yield Variance (A + B) = {(SQ × SP) – (RSQ × SP)}
= {1,26,900 – 1,19,580} = 7,320 (F)
Labour Variances: Labour
Labour SH SR SH × SR RSH RSH × SR AH AH × SR AR AH × AR
(WN-3) (`) (` ) (WN-4) (` ) (`) (`) (` )
Skilled 1,116 hrs 75.00 83,700 1144 85,800 1,200 90,000 71.00 85,200
Unskilled 893 hrs 44.00 39,292 916 40,304 860 37,840 46.00 39,560
2,009 hrs 1,22,992 2,060 1,26,104 2,060 1,27,840 1,24,760
WN- 3: Standard Hours (SH):
0.95 ×1,000hr
Skilled labour- ×1,480 kg. = 1,115.87 or 1,116 hrs.
0.90 × 1,400kg
0.95 × 8,00hr
Unskilled labour- ×1,480 kg. = 892.69 or 893 hrs.
0.90 × 1,400kg
WN- 4: Revised Standard Hours (RSH):
1,000 hr.
Skilled labour- × 2,060 hr. = 1.144.44 or 1,144 hrs.
1,800hr.
8,00 hr.
Unskilled labour- ×2,060 hr. = 915.56 or 916 hrs.
1,800hr.
(e) Labour Cost Variance (Skilled + Unskilled) = {(SH × SR) – (AH × AR)}
= {1,22,992 – 1,24,760} = 1,768 (A)
(f) Labour Efficiency Variance (Skilled + Unskilled) = {(SH × SR) – (AH × SR)}
= {1,22,992 – 1,27,840} = 4,848 (A)
(g) Labour Yield Variance (Skilled + Unskilled) = {(SH × SR) – (RSH × SR)}
= {1,22,992 – 1,26,104} = 3,112 (A)
Q-2 JVG Ltd. produces a product and operates a standard costing system and value material and finished
goods inventories at standard cost. The information related with the product is as follows:
Particulars Cost per unit (`)
Direct materials (30 kg at `350 per kg) 10,500
Direct labour (5 hours at `80 per hour) 400
The actual information for the month just ended is as follows:
(a) The budgeted and actual production for the month of September 2019 is 1,000 units.
(b) Direct materials –5,000 kg at the beginning of the month. The closing balance of directmaterials
for the month was 10,000 kg. Purchases during the month were made at‘ 365 per kg. The actual
utilization of direct materials was 7,200 kg more than thebudgeted quantity.
(c) Direct labour – 5,300 hours were utilised at a cost of ` 4,34,600.
Required:
Calculate (i) Direct material price and usage variances (ii) Direct labour rate and efficiency variances.
Ans. Working:
Quantity of material purchased and used.
No. of units produced 1,000 units
Std. input per unit 30kg.
Std. quantity (Kg.) 30,000 kg.
Add: Excess usage 7,200 kg.
Actual Quantity 37,200 kg.
Add: Closing Stock 10,000 kg.
Less: Opening stock 5,000 kg.
Quantity of Material purchased 42,200 kg.
(i) Direct Material Price Variance:
= Actual Quantity purchased (Std. Price – Actual Price)
= 42,200 kg.(`350 – `365) = 6,33,000 (Adverse)
Direct Material Usage Variance:
= Std. Price (Std. Quantity – Actual Quantity)
= ` 350 (30,000 kg. – 37,200 kg.) = ` 25,20,000 (Adverse)
(ii) Direct Labour Rate Variance:
= Actual hours (Std. Rate – Actual Rate)
= 5,300 hours (`80 – ` 82) = ` 10,600 (Adverse)
Direct Labour Efficiency Variance:
= Std. Rate (Std. hours – Actual hours)
= ` 80 (1,000 units × 5 hours – 5,300 hours) = ` 24,000 (Adverse)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -425-
Q-3 ABC Ltd. had prepared the following estimation for the month of April:
Quantity Rate (`) Amount (`)
Material-A 800 kg. 45.00 36,000
Material-B 600 kg. 30.00 18,000
Skilled labour 1,000 hours 37.50 37,500
Unskilled labour 800 hours 22.00 17,600
Normal loss was expected to be 10% of total input materials and an idle labour time of 5% of expected
labour hours was also estimated.
At the end of the month the following information has been collected from the cost accounting
department:
The company has produced 1,480 kg. finished product by using the followings:
Quantity Rate (`) Amount (`)
Material-A 900 kg. 43.00 38,700
Material-B 650 kg. 32.50 21,125
Skilled labour 1,200 hours 35.50 42,600
Unskilled labour 860 hours 23.00 19,780
You are required to CALCULATE:
(a) Material Cost Variance; (b) Material Price Variance;
(c) Material Mix Variance; (d) Material Yield Variance;
(e) Labour Cost Variance; (f) Labour Efficiency Variance and
(g) Labour Yield Variance.
Ans. Material Variances:
Material SQ SP SQ × SP RSQ RSQ × SP AQ AQ × SP AP AQ × AP
(WN-1) (`) (`) (WN-2) (`) (`) (`) (`)
A 940 kg. 45.00 42,300 886 kg. 39,870 900 kg. 40,500 43.00 38,700
B 705 kg. 30.00 21,150 664 kg. 19,920 650 kg. 19,500 32.50 21,125
1645 kg 63,450 1550 kg 59,790 1550 kg 60,000 59,825
800 kg.
Material A- 1,480 kg. 939.68 or 940kg.
0.9 1,400 kg.
600 kg.
Material B- 1,480 kg. = 704.76 or 705 kg.
0.9 1,400 kg.
WN- 2: Revised Standard Quantity (RSQ):
800 kg.
Material A- 1,550 kg. = 664.28 or 664 kg. = 885.71 or 886 kg.
1,400 kg.
600 kg.
Material B- 1,550 kg. = 664.28 or 664 kg. = 664.28 or 664 kg.
1,400 kg.
(a) Material Cost Variance (A + B) = {(SQ × SP) – (AQ × AP)}
= {63,450 – 59,825} = 3,625 (F)
(b) Material Price Variance (A + B) = {(AQ × SP) – (AQ × AP)
= {60,000 – 59,825} = 175 (F)
(c) Material Mix Variance (A + B) = {(RSQ × SP) – (AQ × SP)}
= {59,790 – 60,000} = 210 (A)
(d) Material Yield Variance (A + B) = {(SQ × SP) – (RSQ × SP)}
= {63,450 – 59,790} = 3,660 (F)
Labour Variances:
Labour SH SR SH × SR RSH RSH × SR AH AH × SR AR AH × AR
(WN-3) (`) (`) (WN-4) (`) (`) (`) (`)
Skilled 1,116 hrs 37.50 41,850 1144 42,900 1,200 45,000 35.50 42,600
Unskilled 893 hrs 22.00 19,646 916 20,152 860 18,920 23.00 19,780
2,009 hrs 61,496 2,060 63,052 2,060 63,920 62,380
WN- 3: Standard Hours (SH):
0.95 1,000hr.
Skilled labour- × 1,480 kg. = 1,115,87 or 1,116 hrs.
0.90 1,400kg.
1,000 hr.
Skilled labour- × 2,060 kg. = 1,144.44 or 1,144 hrs.
1,800 hr.
800 hr.
Unskilled labour- × 2,060 hr. = 915.56 or 916 hrs.
1,800 hr.
(e) Labour Cost Variance (Skilled + Unskilled) = {(SH × SR) – (AH × AR)}
= {61,496 – 62,380} = 884 (A)
(f) Labour Efficiency Variance (Skilled + Unskilled) = {(SH × SR) – (AH × SR)}
= {61,496 – 63,920} = 2,424 (A)
(g) Labour Yield Variance (Skilled + Unskilled) = {(SH × SR) – (RSH × SR)}
= {61,496 – 63,052} = 1,556 (A)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -427-
Q-4 Aaradhya Ltd.manufactures a commercial product for which the standard cost per unit is as follows:
(` )
Material:
5 kg. @ ` 4 per kg. 20.00
Labour:
3 hours @ `10 per hour 30.00
Overhead
Variable: 3 hours @ `1 3.00
Fixed: 3 hours @ `0.50 1.50
Total 54.50
During Jan. 20X8, 600 units of the product were manufactured at the cost shown below:
(` )
Materials purchased:
5,000 kg. @ `4.10 per kg. 20,500
Materials used:
3,500 kg.
Direct Labour:
1,700 hours @ ` 9 15,300
Variable overhead 1,900
Fixed overhead 900
Total 38,600
The flexible budget required 1,800 direct labour hours for operation at the monthly activity level used to set
the fixed overhead rate.
Compute :
(a) Material price variance, (b) Material Usage variance; (c) Labour rate variance; (d) Labour efficiency variance;
(e) Variable overhead expenditure variance; (f) Variable overhead efficiency variance; (g) Fixed overhead
expenditure variance; (h) Fixed overhead volume variance; (i) Fixed overhead capacity variance; and (j)
Fixed overhead efficiency variance.
Also RECONCILE the standard and actual cost of production.
Ans.
(a) Material price variance:
= (Standard price – Actual Price) × Actual quantity
= (` 4 – ` 4.10) × 5,000 = ` 500 Adv.
(b) Material usage variance:
= (Std. quantity for actual output – Actual qtty.) × Std. price
= (600 × 5 – 3,500) × 4 = ` 2,000 Adv.
(c) Labour Rate Variance:
= (Standard rate – Actual rate) × Actual hours
= (`10 – `9) × 1,700 = ` 1,700 Fav.
(d) Labour Efficiency Variance:
= (Standard hours for actual output – Actual hours) × Standard rate
= (600 × 3 – 1,700) × `10
= ` 1,000 Fav.
-428- Chapter-13 : Standard Costing
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -429-
Q-5 ABC Ltd. had prepared the following estimation for the month of April:
Quantity Rate (`) Amount (`)
Material-A 800 kg. 45.00 36,000
Material-B 600 kg. 30.00 18,000
Skilled labour 1,000 hours 37.50 37,500
Unskilled labour 800 hours 22.00 17,600
Normal loss was expected to be 10% of total input materials and an idle labour time of 5% of expected
labour hours was also estimated.
At the end of the month the following information has been collected from the cost accounting
department:
The company has produced 1,480 kg. finished product by using the followings:
Quantity Rate (`) Amount (`)
Material-A 900 kg. 43.00 38,700
Material-B 650 kg. 32.50 21,125
Skilled labour 1,200 hours 35.50 42,600
Unskilled labour 860 hours 23.00 19,780
Required:
CALCULATE:
(i) Material Cost Variance;
(ii) Material Price Variance;
(iii) Material Mix Variance;
(iv) Material Yield Variance;
(v) Labour Cost Variance;
(vi) Labour Efficiency Variance and
(vii) Labour Yield Variance.
Ans. Material Variances:
Material SQ SP SQ × SP RSQ RSQ × SP AQ AQ x SP AP AQxAP
(WN-1) (`) (`) (WN-2) (`) (`) (`) (`)
A 940 kg. 45.00 42,300 886 kg. 39,870 900 kg. 40,500 43.00 38,700
B 705 kg. 30.00 21,150 664 kg. 19,920 650 kg. 19,500 32.50 21,125
1645 kg 63,450 1550 kg 59,790 1550 kg 60,000 59,825
800 kg.
Material A- 1,480 kg. = 939.68 or 940 kg.
0.9 1,400 kg.
600 kg.
Material B- 1,480 kg. = 704.76 or 705 kg.
0.9 1,400 kg.
800 kg.
Material A- 1,550 kg. = 885.71 or 886 kg.
1,400 kg.
600 kg.
Material B- 1,550 kg. = 664.28 or 664 kg.
1,400 kg.
(i) Material Cost Variance (A + B) = {(SQ × SP) – (AQ × AP)}
= {63,450 – 59,825} = 3,625 (F)
(ii) Material Price Variance (A + B) = {(AQ × SP) – (AQ × AP)
= {60,000 – 59,825} = 175 (F)
(iii) Material Mix Variance (A + B) = {(RSQ × SP) – (AQ × SP)}
= {59,790 – 60,000} = 210 (A)
(iv ) Material Yield Variance (A + B) = {(SQ × SP) – (RSQ × SP)}
= {63,450 – 59,790} = 3,660 (F)
Labour Variances:
Labour SH SR SH × SR RSH RSH × SR AH AH × SR AR AH × AR
(WN-3) (`) (`) (WN-4) (`) (`) (`) (`)
Skilled 1,116 hrs 37.50 41,850 1144 42,900 1,200 45,000 35.50 42,600
Unskilled 893 hrs 22.00 19,646 916 20,152 860 18,920 23.00 19,780
2,009 hrs 61,496 2,060 63,052 2,060 63,920 62,380
WN- 3: Standard Hours (SH):
1,000 hr.
Skilled labour- 2,060 hr. = 1,144.44 or 1,144 hrs.
1,800 kg.
800 hr.
Unskilled labour- 2,060 hr. = 915.56 or 916 hrs.
1,800 hr.
(v) Labour Cost Variance (Skilled + Unskilled) = {(SH × SR) – (AH × AR)}
= {61,496 – 62,380} = 884 (A)
(vi) Labour Efficiency Variance (Skilled + Unskilled) = {(SH × SR) – (AH × SR)}
= {61,496 – 63,920} = 2,424 (A)
(vii) Labour Yield Variance (Skilled + Unskilled) = {(SH × SR) – (RSH × SR)}
= {61,496 – 63,052} = 1,556 (A)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -431-
Q-6 The standard cost of a chemical mixture is as follows : 60% of Material A @ ` 50 per kg 40% Material B @
` 60 per kg .
A standard loss of 25% on output is expected in production. The cost records for a period has shown the
following usage.
540 kg of Material A @ ` 60 per kg
260 kg of Material B @ ` 50 per kg
The quantity processed was 680 kilograms of good product. From the above given information
Calculate:
(i) Material Cost Variance (ii) Material Price Variance
(iii) Material Usage Variance (iv) Material Mix Variance
(v) Material Yield Variance
Ans.
Basic Calculation
Material Standard for 640 kg. output Actual for 680 kg. output
Qty. Rate Amount Qty Rate Amount
Kg. (`) (`) Kg. (`) (`)
A 480 50 24,000 540 60 32,400
B 320 60 19,200 260 50 13,000
Total 800 43,200 800 45,400
Less: Loss 160 - - 120 - -
640 43,200 680 45,400
Std. cost of actual output = ` 43,200 × 680/640 = ` 45,900
Calculation of Variances
(i) Material Cost Variance = (Std. cost of actual output – Actual cost)
= (45,900– 45,400)
= ` 500 (F)
(ii) Material Price Variance = (SP – AP) × AQ
Material A = (50 – 60) × 540 = ` 5400 (A)
Material B = (60 – 50)) × 260 = ` 2600 (F)
MPV = ` 2800 (A)
(iii) Material Usage Variance (MUV) = (Std. Quantity for actual output – Actual Quantity) × Std. Price
480 ×680
Material A = - 540 × 50 = ` 1,500 (A)
640
320 × 680
Material B = -260 × 60 = ` 4,800 (F)
640
MUV = ` 3,300 (F)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -433-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -435-
Q-9 (i) The following details are provided by M/s. SKU Enterprises for the year ended 31st March, 2018:
Particulars Material-M (`) Material-N (`) Stock as on 01-04-2017 6,00,000 10,00,000 Stock as on 31-03-
2018 4,50,000 7,25,000 Purchases during the year 9,50,000 18,40,000 You are required to: (i) Calculate
Turnover Ratio of both the materials. (ii) Advise which of the two materials is fast moving. (Assume 360
days in a year). (5 Marks) (ii) Beta Ltd. is manufacturing Product N. This is manufactured by mixing two
materials namely Material P and Material Q. The Standard Cost of Mixture is as under: Material P 150
ltrs. @ ` 40 per ltr. Material Q 100 ltrs. @ ` 60 per ltr. Standard loss @ 20 of total input is expected during
production. The cost records for the period exhibit following consumption: Material P 140 ltrs. @ ` 42
per ltr, Material Q 110 ltrs. @ ` 56 per ltr, Quantity produced was 195 ltrs. Calculate: (i) Material Cost
Variance (ii) Material Usage Variance. (iii) Material Price Variance.
Ans.
(i) Material M Material N
Turnover ratio Turnover ratio
= Cost of stock of raw material consumed = Cost of stock of raw material consumed
Average stock of raw material Average stock of raw material
= ` 6,00,000 + ` 9,50,000- ` 4,50,000 = 2.09 = ` 10,00,000 + ` 18,40,000- ` 7,25,000.
(6,00,000+ 4,50,000) / 2 (10,00,000+ 7,25,000) / 2
Average number of days for which the =2.45
average inventory is held Average number of days for which the
= 360 average inventory is held
Inventory turnover ratio
= 360 days = 360 / Inventory turnover ratio
2.09
= 172.25 days = 360 days / 2.45
= 146.94 days
(ii) Advice
Comparatively Material M is slower than Material N since Inventory holding period of ‘M’ is 172.25
days in Comparison to ‘N’ i.e. 146.94 days. Infact, both materials have slow inventory turnover. Though,
different business has their own expected rates for inventory turnover like food shops have fast
inventory turnover, shop selling furniture etc. will have slower inventory turnover while manufacturers
of large items of plant will have very long inventory turnover.
If it is not as per the Industry Standard, then a slow turnover may indicate that excessive inventory is
held and risk of obsolete or spoiled inventory will increase.
Large quantity of slow moving material means that capital is locked up in business and not earning
revenue. It is advisable to make proper investigations into slow moving materials and take steps to
minimize the loss arises therefrom as it may impact overall financial health of the organisation.
Q-10 The following standards have been set to manufacture a product:
Direct Materials: (Rs.)
2 units of X at Rs.40 per unit 80.00
3 units of Y at Rs. 30 per unit 90.00
15 units of Z at Rs.10 per unit 150.00
320.00
Direct labour 3 hours @ Rs. 55 per hour 165.00
Total standard prime cost 485.00
The company manufactured and sold 6,000 units of the product during the year 20X8.
Direct material costs were as follows:
12,500 units of X at Rs. 44 per unit.
18,000 units of Y at Rs. 28 per unit.
88,500 units of Z at Rs.12 per unit.
The company worked 17,500 direct labour hours during the year 20X8. For 2,500 of these hours the
company paid at Rs. 58 per hour while for the remaining hours the wages were paid at the standard
rate.
Required:
COMPUT E the following variances:
Material Price, Material Usage, Material Mix, Material Yield, Labour Rate and Labour Efficiency.
Ans. Material Price Variance = Actual Quantity (Std. Price – Actual Price)
X = 12,500 units (Rs.40 – Rs.44) = 50,000 (A)
Y = 18,000 units (Rs.30 – Rs.28) = 36,000 (F)
Z = 88,500 units (Rs.10 – Rs.12) = 1,77,000 (A) 1,91,000 (A)
Material Usage Variance = Std. Price (Std. Qty – Actual Qty.)
X = Rs.40 (6,000 × 2 – 12,500) = 20,000 (A)
Y = Rs.30 (6,000 × 3 – 18,000) = Nil
Z = Rs.10 (6,000 × 15 – 88,500) = 15,000 (F) 5,000 (A)
Material Mix Variance = Std. Price (Revised Std. Qty. – Actual Qty.)
1,19,000 × 2
X = Rs.40 12,500 = 24,000 (A)
20
1,19,000 × 3
Y = Rs.30 18,000 = 4,500 (A)
20
1,19,000 × 15
Z = Rs.10 88,500 = 7,500 (F) 21,000 (A )
20
Material Yield Variance = Std. Price (Std. Qty. – Revised Std. Qty.)
1,19, 000 2
X = Rs.40 (6,000 × 2 - ) = 4,000 (F)
20
1,19, 000 3
Y = Rs.30 (6,000 × 3 - )= 4,500 (F)
20
1,19, 000 15
Z = Rs.10 (6,000 × 15 - ) = 7,500 (F) 16,000 (F)
20
Labour Rate Variance = Actual Hours (Std. Rate – Actual Rate)
= 2,500 hours (Rs.55 – Rs.58) = 7,500 (A)
Labour Efficiency Variance = Std. Rate (Std. Hours – Actual Hours)
= Rs.55 (6,000 × 3 – 17,500) = 27,500 (F)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -437-
Q-11 BBC Ltd. manufactures Ordinary Portland Cement (OPC). T he standard data for the raw materials that
are used to manufacture OPC are as follows:
Raw Material Composition (%) Rate per Metric Ton (Rs.)
Limestone 65 565
Silica 20 4,800
Alumina 5 32,100
Iron ore 5 1,800
Others 5 2,400
During the month of February 20X8, A Ltd. produced 500 MT OPC. Actual data related with the
consumption and costs are as follows:
Raw Material Quantity (MT) Total Cost (Rs.)
Limestone 340 1,90,400
Silica 105 5,09,250
Alumina 25 8,12,500
Iron ore 30 53,400
Others 23 51,750
You are required to COMPUTE the following variances related with the production of OPC for the
month of February 20X8:
(i) Material Price Variance
(ii) Material Mix Variance
(iii) Material Yield Variance
(iv) Material Cost Variance.
Ans. (i) Material Price Variance = Actual Quantity (Std. Price – Actual Price)
Rs.1,90,400
Limestone = 340 Rs.565 -
340
= 340 (Rs. 565 - Rs. 560) = 1,700 (F)
Rs.5,09,250
Silica = 105 Rs.4,800 -
150
= 105 (Rs. 4,800 - Rs. 4,850) = 5,250 (A)
Rs.8,12,500
Alumina = 25 Rs.32,100 -
25
= 25 (Rs. 32,100 - Rs. 32,500) = 10,000 (A)
Rs.53,400
Iron ore = 30 Rs.1,800 -
30
= 30 (Rs. 1,800 - Rs. 1,780) = 600 (F)
Rs.51,750
Others = 23 Rs.2,400 -
23
= 23 (Rs. 2,400 - Rs. 2,250) = 3,450 (F)
9,500 (A)
(ii) Material Mix Variance = Std. Price (Revised Std. Quantity – Actual Quantity)
Limestone = Rs. 565 (523 × 65% - 340)
= Rs. 565 (339.95 - 340) = 28.25 (A)
Silica = Rs. 4,800 (523 × 20% - 105)
= Rs. 4,800 (104.6 - 105) = 1,920 (A)
Alumina = Rs. 32,100 (523 × 5% - 25)
= Rs. 32,100 (26.15 - 25) = 36,915 (F)
Iron ore = Rs. 1,800 (523 × 5% - 30)
= Rs. 1,800 (26.15 - 30) = 6,930 (A)
Others = Rs. 2,400 (523 × 5% - 23)
= Rs. 2,400 (26.15 - 23) = 7,560 (F)
35,596.75 (F)
(iii) Material Yield Variance = Std. Price (Standard Quantity – Revised Std. Quantity)
Limestone = Rs. 565 (500 × 65% - 523 × 65%)
= Rs. 565 (325 - 339.95) = 8,446.75 (A)
Silica = Rs. 4,800 (500 × 20% - 523 × 20%)
= Rs. 4,800 (100 - 104.6) = 22,080 (A)
Alumina = Rs. 32,100 (500 × 5% - 523 × 5%)
= Rs. 32,100 (25 - 26.15) = 36,915 (A)
Iron ore = Rs. 1,800 (500 × 5% - 523 × 5%)
= Rs. 1,800 (25 - 26.15) = 2,070 (A)
Others = Rs. 2,400 (500 × 5% - 523 × 5%)
= Rs. 2,400 (25 - 26.15) = 2,760 (A)
72,271.75 (A)
(iv) Material Cost Variance = (Std. Quantity × Std. Price) – (Actual Quantity × Actual Price)
Limestone = Rs. 565 × (500 × 65%) - Rs. 1,90,400
= Rs. 1,83,625 - Rs. 1,90,400 = 6,775 (A)
Silica = Rs. 4,800 × (500 × 20%) - Rs. 5,09,250
= Rs. 4,80,000 – Rs. 5,09,250 = 29,250 (A)
Alumina = Rs. 32,100 (500 × 5%) – Rs. 8,12,500
= Rs. 8,02,500 – Rs. 8,12,500 = 10,000 (A)
Iron ore = Rs. 1,800 (500 × 5%) – Rs. 53,400
= Rs. 45,000 – Rs. 53,400 = 8,400 (A)
Others = Rs. 2,400 (500 × 5%) – Rs. 51,750
= Rs. 60,000 – Rs. 51,750 = 8,250 (F)
46,175 (A)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -439-
Q-12 The standard labour component and the actual labour component engaged in a week for a job are as
follows:
Skilled Semi-skilled Un-Skilled
Workers Workers workers
Standard number of workers in the gang 32 12 6
Standard wage rate per hour (`) 30 20 10
Actual number of workers employed in the gang
during the week 28 18 4
Actual wages rate per hour (`) 34 23 12
During the 40 hours working week the gang produced 1,800 standard labour hours of work.
CALCULATE:
(i) Total labour cost variance;
(ii) Labour yield variance;
(iii) Labour mix variance; and
(iv) Labour wage rate variance.
Ans. Work produced by the gang 1,800 standard labour hours, i.e.,
1, 800
or 36 gang hours
32 + 12 + 6
Standard hours of Skilled Labour (36 x 32) 1,152 hours
Standard hours of Semi-skilled Labour (36 x 12) 432 hours
Standard hours of Un-skilled Labour (36 x 6) 216 hours
Total 1,800 hours
Actual hours of Skilled Labour (40 x 28) 1,120 hours
Actual hours of Semi-skilled Labour (40 x 18) 720 hours
Actual hours of Un-skilled Labour (40 x 4) 160 hours
Total 2,000 hours
Revised Standard hours (actual hours worked expressed in standard ratio)
1,152
Skilled Labour × 2,000 1,280 hours
1,800
432
Semi-skilled Labour × 2,000 480 hours
1,800
216
Unskilled Labour × 2,000 240 hours
1,800
2,000 hours
Standard Cost for Actual Output: `
Skilled Labour 1,152 hours @ ` 30 34,560
Semi-skilled Labour 432 hours @ ` 20 8,640
Unskilled Labour 216 hours @ ` 10 2,160
1,800 hours 45,360
-440- Chapter-13 : Standard Costing
Actual Cost:
Skilled Labour 1,120 hours @ ` 34 38,080
Semi-skilled Labour 720 hours @ ` 23 16,560
Unskilled Labour 160 hours @ ` 12 1,920
2,000 hours 56,560
(i) Total Labour Cost Variance
Standard Cost- Actual Cost `
` 45,360 - ` 56,560 11,200 (A)
The variable overhead efficiency variance is Rs. 1,500 adverse. Variable overheads are based on direct
labour hours. There was no stock of the material in the beginning
You are required to DETERMINE the missing figures and work out all the relevant variances.
Ans. Working Notes
Standard Costs
Rs.
Direct materials (6,000 × Rs. 12) 72,000
Direct labour (6,000 × Rs. 4.40) 26,400
Variable overheads (6,000 × Rs. 3) 18,000
Total 1,16,400
Actual Cost
Direct Materials (12,670 × 5.70) 72,219
Direct wages 27,950
Variable overhead incurred 20,475
Total 1,20,644
Total Variance = SC- AC = 1,16,400 –1,20,644 = Rs. 4,244 (A)
Missing Figures
1. Actual Direct Labour Hours (DLH)
We can find out this through Variable overhead efficiency variance of Rs. 1,500 adverse
VOH Efficiency Variance= SR (SH – AH)
1,500 A = 3(6,000 – AH)
-1,500 = 18,000 – 3 AH
3AH = 18,000 + 1,500 = 19,500
AH = 19,500/3 = 6,500 Actual Hours i.e. Actual DLH.
Rs.27,950
2. Actual Labour Rate per hour = = Rs. 4.30
6,500 DLH
Relevant Variances:
1 Material Variances:
(a) MCV = SC – AC = 72,000 – 72,219 = Rs. 219 (A)
(b) MPV = AQ (SR – AR) = 12,670 (6 – 5.70) = Rs. 3,801 (F)
or = 19,000 (6 – 5.70) = Rs. 5,700(F)
(c) MUV = SR (SQ – AQ) = 6 (6,000 × 2 – 12,670)
= 6 (12,000 – 12,670) = Rs. 4,020 (A)
2. Labour Variances:
(a) LCV = SC – AC = 26,400 – 27,950 = Rs. 1,550 (A)
(b) LRV = AHP (SR – AR) = 6,500 (4.40 – 4.30) = Rs. 650 (F)
(c) LEV = SR (SH – AHP) = 4.40 (6,000 – 6,500) = Rs. 2,200 (A)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -443-
Rs. 1,09,000
20 Days ×19Days
Actual Fixed Overheads (Rs.1,10,000 + 60% of Rs. 19,200) Rs.1,21,520
Actual Variable Overheads (Rs.48,000 + 40% of Rs.19,200) Rs. 55,680
Q-15 Arnav Ltd. manufactures a product Q, the standard cost of which is as follows:
Standard Cost per unit (Rs.)
Direct Material 600
Direct labour:
- Skilled @ Rs.80 per hour 120
- Unskilled @ Rs.60 per hour 90
Variable overheads 75
Fixed overheads 30
915
During the month just ended 4,000 units of Q were produced. The actual labour cost was as follows.
Rate per hour (Rs.) Cost (Rs.)
Skilled 87.50 5,77,500
Unskilled 55.00 2,97,000
10% of the labour time was lost due to idle time. The standard idle time was 7.5% of labour time. Arnav
Ltd. has budgeted to produce 4,200 units of Q. Arnav Ltd. absorbs its overheads on direct labour hour
(effective hours) basis. Actual fixed and variable overheads incurred were Rs.1,55,000 and Rs.2,85,000
respectively.
CALCULATE:
(i) Labour rate variance;
(ii) Labour efficiency variance;
(iii) Labour mix variance;
(iv) Labour yield variance;
(v) Labour idle time variance;
(vi) Variable overhead expenditure variance and
(vii) Variable overhead efficiency variance.
Ans. Workings:
Skilled Unskilled
Standard Rate per hour 80 60
Standard time for producingone unit 1.5 hours(` 120 ÷ ` 80) 1.5 hours(` 90 ÷ ` 60)
Actual hours paid (AHPaid) 6,600 hours 5,400 hours
Standard hours required toproduce 6,000 hours 6,000 hours
4,000 units (SH) (1.5 hours× 4,000 units) (1.5 hours× 4,000 units)
6, 600 5, 400
Actual hours worked × 97.5 × 97.5
100 100
(AH Worked) = 6,435 hours = 5,265 hours
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -445-
` 75 ` 2,85, 000
= 11,700 hours = -
2 1.5 hours 11,700hours
= 11,700 hours (` 25 – ` 24.36) = ` 7,488 (F)
(vii) Variable Overhead Efficiency Variance
= Std. Rate (SH – AHWorked)
= ` 25 (12,000 – 11,700) = ` 7,500 (F)
Q-16 The following information has been provided by a company:
Number of units produced and sold 6,000
Standard labour rate per hour Rs. 8
Standard hours required for 6,000 units -
Actual hours required 17094 hours
Labour efficiency 105.3%
Labour rate variance Rs. 68,376 (A)
You are required to CALCULATE:
(i) Actual labour rate per hour
(ii) Standard hours required for 6,000 units
(iii) Labour Efficiency variance
17, 094 × 12
(v) Actual Labour Cost Per Unit = = = Rs.34.19
6,000
Q-17 Following data is extracted from the books of XYZ Ltd. for the month of January, 2020:
(i) Estimation
Particulars Quantity (kg.) Price (`) Amount (`)
Material - A 800 ? --
Material-B 600 30.00 18,000
--
Normal loss was expected to be 10% of total input materials.
(ii) Actuals-
1480 kg of output produced.
Particulars Quantity (kg.) Price (`) Amount (`)
Material-A 900 ? - -
Material-B ? 32.50 --
59,825
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -447-
1, 480kg
= = 1,645 kg
90%
800kg
SQA x 1,645kg. = 940 kg
(800 + 600)
600kg
SQB = x 1,645kg. = 705 kg
(800 + 600)
19, 500
AQB = = 650 kg
30
-448- Chapter-13 : Standard Costing
38, 700
APA = = 43
900
Actual Price of Material-A = ` 43
(iv) Total Actual Quantity of Material-A and Material-B
= AQA + AQB
= 900 kg + 650 kg (from (ii) above)
= 1,550 kg
Now,
800kg
Revised SQA = x 1,550kg. = 886 kg
(800 + 600)
600kg
Revised SQB = x 1,550kg. = 664 kg
(800 + 600)
(v) Material Mix Variance (A + B) = {(RSQ × SP) – (AQ × SP)}
= {(RSQA × SPA) + (RSQB × SPB) – 60,000}
= (886 kg (from (iv) above) × ` 45 (from (i) above))
+ (664 kg (from (iv) above) × ` 30) - `60,000
= (39,870 + 19,920) – 60,000 = ` 210 (A)
Q-18 Following are the standard cost for a product-X:
(`)
Direct materials 10 kg @ ` 90 per kg 900
Direct labour 8 hours @ `100 per hour 800
Variable Overhead 8 hours @ `15 per hour 120
Fixed Overhead 400
2,220
Budgeted output for the year was 2,000 units. Actual output is 1,800 units.
Actual cost for year is as follows:
(`)
Direct Materials 17,800 Kg @ ` 92 per Kg. 16,37,600
Direct Labour 14,000 hours @ ` 104 per hour 14,56,000
Variable Overhead incurred 2,17,500
Fixed Overhead incurred 7,68,000
You are required to CALCULATE:
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -449-
Q-19 JK Ltd. has furnished the following standard cost data per unit of production:
Material 10 kg @ ` 200 per kg.
Labour 6 hours @ ` 110 per hour
Variable overhead 6 hours @ ` 200 per hour.
Fixed overhead ` 90,00,000 per month (Based on a normal volume of 30,000
labour hours.)
The actual cost data for the month of September 2021 are as follows:
Material used 50,000 kg at a cost of ` 1,05,00,000.
Labour paid ` 31,00,000 for 31,000 hours
Variable overheads ` 58,60,000
Fixed overheads ` 94,00,000
Actual production 4,800 units.
CALCULATE:
(i) Material Cost Variance.
(ii) Labour Cost Variance.
(iii) Fixed Overhead Cost Variance.
(iv) Variable Overhead Cost Variance.
Ans. Budgeted Production 30,000 hours ÷ 6 hours per unit = 5,000 units
Budgeted Fixed Overhead Rate = ` 90,00,000 ÷ 5,000 units = ` 1,800 per unit
= ` 90,00,000 ÷ 30,000 hours = ` 300 per hour.
(i) Material Cost Variance = (Std. Qty. × Std. Price) – (Actual Qty. × Actual Price)
= (4,800 units × 10 kg. × ` 200) - ` 1,05,00,000
= ` 96,00,000 –` 1,05,00,000
= ` 9,00,000 (A)
(ii) Labour Cost Variance = (Std. Hours × Std. Rate) – (Actual Hours × Actual rate)
= (4,800 units × 6 hours × ` 110) – ` 31,00,000
= ` 31,68,000 – ` 31,00,000
= ` 68,000 (F)
(iii) Fixed Overhead Cost Variance = (Budgeted Rate × Actual Qty) – Actual Overhead
= (` 1,800 × 4,800 units) – ` 94,00,000
= ` 7,60,000 (A)
OR = (Budgeted Rate × Std. Hours) – Actual Overhead
= (` 300 × 4,800 units × 6 hours) – ` 94,00,000
= ` 7,60,000 (A)
(iv) Variable Overhead Cost Variance = (Std. Rate × Std. Hours) – Actual Overhead
= (4,800 units × 6 hours × ` 200) - ` 58,60,000
= ` 57,60,000 - ` 58,60,000
= ` 1,00,000 (A)
Q-20 Following information has been provided by a company:
Number of units produced and sold 9,000
Standard labour rate per hour ` 12
Standard hours required for 9,000 units -
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -451-
SH =
= SH = 26,999.973
SH = 27,000 hours
(iii) Labour Efficiency Variance = SR (SH - AH)
= 12 (27,000 - 25,641)
= ` 16,308 (F)
27,000 12
(iv) Standard Labour Cost per Unit = = ` 36
9,000
25,641 18
(v) Actual Labour Cost Per Unit = = ` 51.282
2
9,000
Q-21 The standard output of a Product ‘DJ’ is 25 units per hour in manufacturing department of a Company
employing 100 workers. In a 40 hours week, the department produced 960 units of product ‘DJ’ despite
5% of the time paid was lost due to an abnormal reason. The hourly wage rates actually paid were `
6.20, ` 6.00 and ` 5.70 respectively to Group ‘A’ consisting 10 workers, Group ‘B’ consisting 30 workers
and Group ‘C’ consisting 60 workers. The standard wage rate per labour is same for all the workers.
Labour Efficiency Variance is given ` 240 (F).
You are required to compute:
(i) Total Labour Cost Variance.
(ii) Total Labour Rate Variance.
(iii) Total Labour Gang Variance.
(iv) Total Labour Yield Variance, and
(v) Total Labour Idle Time Variance.
=0
(iv) Total Labour Yield Variance
= Average Standard Rate per hour of Standard Gang × {Total Standard Time
(hours) - Total Actual Time worked (hours)}
= 6 x (3,840 – 3,800)
= 240F
(v) Total Labour idle time variance
= Total Idle hours x standard rate per hour
= 200 hours x 6
= 1,200A
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -453-
Q-22 ABC Ltd. has furnished the following information regarding the overheads for the month of June 2020:
(i) Fixed Overhead Cost Variance ` 2,800 (Adverse)
(ii) Fixed Overhead Volume Variance ` 2,000 (Adverse)
(iii) Budgeted Hours for June, 2020 2,400 hours
(iv) Budgeted Overheads for June,2020 ` 12,000
(v) Actual rate of recovery of overheads ` 8 Per Hour
From the above given information
Calculate:
(1) Fixed Overhead Expenditure Variance
(2) Actual Overheads Incurred
(3) Actual Hours for Actual Production
(4) Fixed Overhead Capacity Variance
(5) Standard hours for Actual Production
(6) Fixed Overhead Efficiency Variance
Ans. (1)Fixed Overhead Expenditure Variance
= Budgeted Fixed Overheads – Actual Fixed Overheads
= ` 12,000 – ` 12,800 (as calculated below) = ` 800 (A)
(2) Fixed Overhead Cost Variance= Absorbed Fixed Overheads – Actual Fixed Overheads
2,800 (A) = ` 10,000 – Actual Overheads
Actual Overheads = ` 12,800
(3) Actual Hours for Actual Production = ` 12,800/ `8 = 1,600 hrs.
(4) Fixed Overhead capacity Variance
= Budgeted Fixed Overheads for Actual Hours– Budgeted Fixed Overheads
= ` 5 x 1600 hrs. – ` 12,000 = ` 4,000 (A)
(5) Standard Hours for Actual Production
= Absorbed Overheads/ Std. Rate
= ` 10,000/ ‘ 5 = 2,000 hrs.
(6) Fixed Overhead Efficiency Variance
= Absorbed Fixed Overheads – Budgeted Fixed Overheads for Actual Hours
= ` 10,000 – ` 5 x 1,600 hrs. = ` 2,000 (F)
Working Note:
(i) Fixed Overhead Volume Variance = Absorbed Fixed Overheads – Budgeted Fixed Overheads
2,000 (A) = Absorbed Fixed Overheads – ` 12,000
Absorbed Fixed Overheads = ` 10,000
(ii) Standard Rate/ Hour = ` 5 (` 12,000/2,400 hrs.)
Q-23 Baby Moon Ltd. uses standard costing system in manufacturing one of its product `Baby Cap’. The
details are as follows:
Direct Material 1 Meter @ ` 60 per meter ` 60
Direct Labour 2 hour @ ` 20 per hour ` 40
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -455-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -457-
You are required to calculate the following variances for the month of April 2021:
i. Overhead Cost variance
ii. Fixed Overhead Cost variance
iii. Variable Overhead Cost variance
iv. Fixed Overhead Volume variance
v. Fixed Overhead Expenditure Variance
vi. Calendar Variance
Ans. Working Notes
Fixed Overheads = ` 10
Standard Rate of Absorption of Fixed Overheads per unit (`10 + `0.90) ` 10.90
Fixed Overheads Absorbed on 8,000 units @ ` 10.90 ` 87,200
Budgeted Variable Overheads ` 6,00,000
Add: Variable element in Semi-Variable Overheads 40% of ` 1,80,000 ` 72,000
Total Budgeted Variable Overheads ` 6,72,000
= ` 34,320 (A)
iii. Variable Overhead Cost Variance = Standard Variable Overheads for Production–
Actual Variable Overheads
= ` 44,800 – ` 55,680
= ` 10,880 (A)
iv. Fixed Overhead Volume Variance = Absorbed Fixed Overheads – Budgeted Fixed Overheads
= ` 87,200 – `1,09,000
= ` 21,800 (A)
v. Fixed Overhead Expenditure Variance = Budgeted Fixed Overheads – Actual Fixed Overheads
= ` 10.90 × 10,000 units – ` 1,21,520
= ` 12,520 (A)
vi. Calendar Variance = Possible Fixed Overheads – Budgeted Fixed Overheads
= ` 1,03,550 – ` 1,09,000
= ` 5,450 (A)
OR
Calendar Variance = (Actual days – Budgeted days) x Standard fixed overhead rate per day
Standard fixed overhead rate per day = 1308000/20*12 = ` 5450
Fixed Overhead Calendar Variance = (19-20) x 5450 = 5450(A)
Q-27 Rounak Minerals Ltd. operates in iron ore mining through open cast mining method. Explosives and
detonators are used for excavation of iron ores from the mines. The following are the details of standard
quantity of explosives materials used for mining:
Particulars Rate (`) Standard Qty. for Standard Qty. for
Iron ore Overburden (OB)
SME 40.00 per kg. 2.4 kg per tonne 1.9 kg per cubic- meter
Detonators 20.00 per piece 2 pcs per tonne 2 pcs per cubic-meter
The standard stripping ratio is 3:1 (means 3 cubic- meter of overburden soil to be removed to get one
tonne of iron ore).
During the month of December 2021, the company produced 20,000 tonnes of iron ore and removed
58,000 cubic- meter of OB. The quantity of explosive materials used and paid for the month is as below:
Material Quantity Amount (`)
SME 1,67,200 kg. 63,53,600
Detonators 1,18,400 pcs 24,27,200
You are required to COMPUTE:
(i) Material price variance
(ii) Material quantity variance
(iii) Material cost variance.
Ans.
Workings:
1. Calculation of Standard Qty. of Explosives and Detonators for actual output:
Particulars Iron ore Overburden (OB) Total
SME:
A Actual Output 20,000 tonne 58,000 M3
B Standard Qty per unit 2.4 kg./tonne 1.9 kg./M3
C Standard Qty. for actual
production [A×B] 48,000 kg. 1,10,200 kg. 1,58,200 kg.
Detonators:
D Standard Qty per unit 2 pcs/ tonne 2 pcs/ M3
E Standard Qty. for actual
production [A×D] 40,000 pcs. 1,16,000 pcs 1,56,000 pcs
2. Calculation of Actual Price per unit of materials:
Material Quantity [A] Amount (`) [B] Rate (`) [C = B÷A]
SME 1,67,200 kg. 63,53,600 38.00
Detonators 1,18,400 pcs 24,27,200 20.50
(i) Computation of material price variance:
Material Price Variance = Actual Qty. × (Std. Price - Actual Price)
SME = 1,67,200 kg. × (`40 – `38) = ` 3,34,400 (F)
Detonators = 1,18,400 pcs × (`20 – `20.5) = ` 59,200 (A)
Total = ` 2,75,200 (F)
(ii) Computation of material quantity variance:
Material Qty. Variance = Std. Price × (Std. Qty for actual output - Actual Qty.)
SME = `40 × (1,58,200 kg. - 1,67,200 kg.) = ` 3,60,000 (A)
Detonators = `20 × (1,56,000 pcs -1,18,400 pcs) = ` 7,52,000 (F)
Total = ` 3,92,000 (F)
(iii) Computation of material cost variance:
Material cost variance = Std. cost – Actual Cost
Or, (Std. Price × Std. Qty) – (Actual Price × Actual Qty.)
SME = (`40 × 1,58,200 kg) – (`38 × 1,67,200 kg.)
= `63,28,000 – `63,53,600 = ` 25,600 (A)
Detonators = (`20 × 1,56,000 pcs) – (`20.50 × 1,18,400 pcs)
= `31,20,000 – `24,27,200 = ` 6,92,800 (F)
Total = ` 6,67,200 (F)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -461-
(vi) Fixed overheads capacity variance = (Budgeted Hours for Actual Days – Actual Hours)
x Budgeted Rate per Hour
---0---0---
-462- Chapter-13 : Standard Costing
CHAPTER - 14
MARGINAL COSTING
Q-1 A Ltd. manufacture and sales its product R-9. The following figures have been collected from cost
records of last year for the product R-9:
Elements of Cost Variable Cost portion Fixed Cost
Direct Material 30% of Cost of Goods Sold —
Direct Labour 15% of Cost of Goods Sold —
Factory Overhead 10% of Cost of Goods Sold ` 2,30,000
Administration Overhead 2% of Cost of Goods Sold ` 71,000
Selling & Distribution Overhead 4% of Cost of Sales ` 68,000
Last Year 5,000 units were sold at ` 185 per unit. From the given DETERMINE the followings:
(i) Break-even Sales (in rupees)
(ii) Profit earned during last year
(iii) Margin of safety (in %)
(iv) Profit if the sales were 10% less than the actual sales.
(Assume that Administration Overhead is related with production activity)
Ans. Working Notes:
(1) Calculation of Cost of Goods Sold (COGS):
COGS = DM + DL + FOH + AOH
COGS = {0.3 COGS + 0.15 COGS + (0.10 COGS + ` 2,30,000) + (0.02 COGS + ` 71,000)}
Or, COGS = 0.57 COGS + ` 3,01,000
` 3,01,000
Or, COGS = =`7,00,000
0.43
(2) Calculation of Cost of Sales (COS):
COS = COGS + S&DOH
COS = COGS + (0.04 COS + ` 68,000)
Or, COS = `7,00,000 + (0.04 COS + ` 68,000)
` 7,68,000
Or, COS = = ` 8,00,000
0.96
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -463-
` 9.25,000 - 6,90,882
= ×100 = 25.31%
` 9,25,000
(iv) Profit if the sales were 10% less than the actual sales:
Profit = 90% (` 9,25,000 - ` 4,31,000) - ` 3,69,000
= ` 4,44,600 - ` 3,69,000 = ` 75,600
Q-2 PVC Ltd sold 55,000 units of its product at `375 per unit. Variable costs are `175 per unit (manufacturing
costs of `140 and selling cost `35 per unit). Fixed costs are incurred uniformly throughout the year and
amount to `65,00,000 (including depreciation of `15,00,000). There is no beginning or ending
inventories.
Required:
(i) Compute breakeven sales level quantity and cash breakeven sales level quantity.
(ii) Compute the P/V ratio.
(iii) Compute the number of units that must be sold to earn an income (EBIT) of `5,00,000.
(iv) Compute the sales level achieve an after-tax income (PAT) of `5,00,000, assume 40% corporate
tax rate.
Ans. (i) Contribution = `375 - `175 = `200 per unit.
` 65,00,000 + ` 8,33,333
= ` 1,37,50,859
53.33%
Q-3 MNP Ltd sold 2,75,000 units of its product at ` 375 per unit. Variable costs are ` 175 per unit (manufacturing
costs of `140 and selling cost `35 per unit). Fixed costs are incurred uniformly throughout the year and
amount to `3,50,00,000 (including depreciation of ` 1,50,00,000). there are no beginning or ending
inventories.
Required:
(i) Compute breakeven sales level quantity and cash breakeven sales level quantity.
(ii) Compute the P/V ratio.
(iii) Compute the number of units that must be sold to earn an income (EBIT) of ` 25,00,000.
(iv) Compute the sales level achieve an after-tax income (PAT) of ` 25,00,000. Assume 40% corporate
Income Tax rate.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -465-
S - V 15 - 5 200 2
P/V ratio = = 100 = = 66 %
S 15 3 3
Suppose break-even sales = x
15x – 5x = 1,20,000 (at BEP, contribution will be equal to fixed cost)
x = 12,000 units.
Or Break-even sales in units = 12,000
Break-even sales in rupees = 12,000 x ` 15 = ` 1,80,000
Q-5 A company manufactures two types of herbal product, A and B. Its budget shows profit figures after
apportioning the fixed joint cost of `15 lacs in the proportion of the numbers of units sold. The budget
for 2018, indicates:
A B
Profit (`) 1,50,000 30,000
Selling Price / unit (`) 200 120
P/V Ratio (%) 40 50
Required:
Compute the best option among the following, if the company expects that the number of units to be sold
would be equal.
(i) Due to exchange in a manufacturing process, the joint fixed cost would be reduced by 15% and the
variables would be increased by 7½ %.
(ii) Price of A could be increased by 20% as it is expected that the price elasticity of demand would be unity
over the range of price.
(iii) Simultaneous introduction of both the option, viz, (i) and (ii) above.
Ans. Option (i)
Increase in profit when due to change in a manufacturing process there is reduction in joint fixed cost
and increase in variable costs.
(` )
Revised Contribution from 12,000 units of A due to 7.5% increase in
Variable Cost {12,000 units × (`200 – `129)} 8,52,000
Revised Contribution from 12,000 units of B due to 7.5% increase in
Variable Cost {12,000 units × (`120 – `64.50)} 6,66,000
Total Revised Contribution 15,18,000
Less: Fixed Cost (`15,00,000 – 15% × `15,00,000) 12,75,000
Revised Profit 2,43,000
Less: Existing Profit 1,80,000
Increase in Profit 63,000
Option (ii)
Increase in profit when the price of product A increased by 20% and the price elasticity of its demand would
be unity over the range of price.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -467-
(` )
Budgeted Revenue from Product A (12,000 units × `200) 24,00,000
Revised Demand (in units) (`24,00,000 / `240) 10,000
Revised Contribution (in `) [10,000 units × ( `240 – `120)] 12,00,000
Less: Existing Contribution (12,000 units × `80) 9,60,000
Increase in Profit (Contribution) 2,40,000
*Note: Since Price Elasticity of Demand is 1, therefore the Revenue in respect of Products will remain same.
Option (iii)
Increase in profit on the simultaneous introduction of above two options.
(`)
Revised Contribution from Product A [10,000 units × (`240 – `129)] 11,10,000
Revised Contribution from Product B [12,000 units × (`120 – `64.50)] 6,66,000
Total Revised Contribution 17,76,000
Less: Revised Fixed Cost 12,75,000
Revised Profit 5,01,000
Less: Existing Profit 1,80,000
Increase in Profit 3,21,000
A comparison of increase in profit figures under above three options clearly indicates that the option (iii) is
the best as it increases the profit of the concern by ` 3,21,000.
Note: The budgeted profit / (loss) for 201 8 in respect of products A and B should be ` 2,10,000 and (`30,000)
respectively instead of ` 1,50,000 and ` 30,000.
Workings
1. Contribution per unit of each product:
Product
A (`) B (`)
Contribution per unit 80 60
(Sales × P/V Ratio) (`200 × 40%) (`120 × 50%)
2. Number of units to be sold:
Total Contribution – Fixed Cost = Profit
Let x be the number of units of each product sold, therefore:
(80x + 60x) – `15,00,000 = `1,50,000 + `30,000
Or x = 12,000 units
Q-6 When volume is 4000 units, average cost is ? 3.75 per unit. When volume is 5000 units, average cost is
` 3.50 per unit. The Break-Even point is 6000 units.
Calculate:- (i) Variable Cost per unit (ii) Fixed Cost and (iii) Profit Volume Ratio.
` 17,500 - ` 15,000
= = ` 2,500/1000 = ` 2.5
1,000
(ii) Fixed cost = Total Cost – Variable cost (at 5,000 units level)
= ` 17,500 – ` 2.5 × 5,000 = ` 5,000
(iii) Contribution
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -469-
(ii) Dependence on key factors: Contribution of a product itself is not a guide foroptimum profitability
unless it is linked with the key factor.
(iii) Scope for Low Profitability: Sales staff may mistake marginal cost for total cost and sell at a price;
which will result in loss or low profits. Hence, sales staff should be cautioned while giving marginal
cost.
(iv) Faulty valuation: Overheads of fixed nature cannot altogether be excluded particularly in large
contracts, while valuing the work-in- progress. In order to show the correct position fixed overheads
have to be included in work-in-progress.
(v) Unpredictable nature of Cost: Some of the assumptions regarding the behaviour of various costs
are not necessarily true in a realistic situation. For example, the assumption that fixed cost will
remain static throughout is not correct. Fixed cost may change from one period to another. For
example, salaries bill may go up because of annual increments or due to change in pay rate etc.
The variable costs do not remain constant per unit of output. There may be changes in the prices
of raw materials, wage rates etc. after a certain level of output has been reached due to shortage
of material, shortage of skilled labour, concessions of bulk purchases etc.
(vi) Marginal costing ignores time factor and investment: The marginal cost of two jobs may be the
same but the time taken for their completion and the cost of machines used may differ. The true
cost of a job which takes longer time and uses costlier machine would be higher. This fact is not
disclosed by marginal costing.
(vii) Understating of W-I-P: Under marginal costing stocks and work in progress are understated.
Q-10 A manufacturing company is producing a product 'A' which is sold in the market at `45 per unit. The
company has the capacity to produce 40000 units per year. The budget for the year 2018-19 projects a
sale of 30000 units.
The costs of each unit are expected as under:
`
Materials 12
Wages 9
Overheads 6
Margin of safety is ` 4,12,500.
You are required to:
(i) calculate fixed cost and break-even point.
(ii) calculate the volume of sales to earn profit of 20% on sales.
(iii) if management is willing to invest ` 10,00,000 with an expected return of 20%, calculate units to
be sold to earn this profit.
(iv) Management expects additional sales if the selling price is reduced to ` 44. Calculate units to be
sold to achieve the same profit as desired in above (iii).
Ans.
Profit
Margin of Safety = = ` 4,12,500
P / V ratio
Profit
= 45 - (2 + 9 + 6) = ` 4,12,500
45
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -471-
Profit
18 = 4,12,500
45
Profit = 1,65,000 OR P/V = (18/45) x 100 =40%
(i) Fixed Cost
Profit = (Sales × P/V Ratio) – Fixed Cost
18
1,65,000 = 30,000 x 45 x - Fixed Cost
45
Or Fixed Cost = 5,40,000 – 1,65,000
= ` 3,75,000
OR
Profit = Contribution – Fixed Cost = ` 5,40,000 - ` 3,75,000 = ` 1,65,000
18
P/V Ratio= = 40%
45
Break-even Point = Total Sales – Margin of Safety
= ` (30,000 × 45) – 4,12,500
= 13,50,000 – 4,12,500 = ` 9,37,500
Or
3,75,000
So, S = Unitss
9
3,75,000 - 45
Volume of sales= = ` 18,75,000 OR 41666.67 Unitss
9
So, ` 18,75,000 sales are required to earn profit on 20% of sales
(iii) Contribution = Fixed Cost + Desired Profit
18S = 3,75,000 + Return on Investment
18S = 3,75,000 + 2,00,000
5,75,000
S = Units = 31,945 Units(approx.)
18
-472- Chapter-14 : Marginal Costing
5,75,000
S = Unitss
17
S = 33,824 units (approx.)
Additional Sales to be sold to achieve the same profit is 33,824 Units.
Q-11 Following figures have been extracted from the books of M/s. RST Private Limited:
Financial Year Sales (`) Profit/Loss (`)
2016-17 4,00,000 15,000(loss)
2017-18 5,00,000 15,000 (Profit)
You are required to calculate:
(i) Profit Volume Ratio
(ii) Fixed Costs
(iii) Break Even Point
(iv) Sales required to earn a profit of ` 45,000.
(v) Margin of Safety in Financial Year 2017-18.
Ans.
Sales (`) Profit (`)
Year 2016 4,00,000 15,000 (loss)
Year 2017 5,00,000 15,000 (profit)
Difference 1,00,000 30,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -473-
` 5,94,200
Less: Direct Material 1,200 4,75,360
1,500 units
` 4,42,600
Direct Labour 1,200 3,54,080
1,500 units
` 11,97,000 x 60%
Variable Overhead 1,200 5,74,560
1,500 units
Contribution 9,96,000
Less: Fixed cost (Rs. 11,97,000x40%) 4,78,800
Profit 5,17,200
If price has been increased by 11.11% (increases by 200 on 1,800) sales goes down by 20% (decreased by
300 on 1,500). Change in demand is greater than change in price. Since the variable costs are still same
profit has been arose to ` 5,17,200 in-spite of high elasticity of demand. PH gems would not be able to
sustain this policy on account of change if any in variable costs.
(ii) Evaluation of Option (ii)
(`)
Sales 1,800.00
` 5,94,200
Less: Direct Material 396.13
1,500
Cost of Tie PIN 18.00
-474- Chapter-14 : Marginal Costing
` 4,42,600
Direct Labour 295.07
1,500
` 11,97,000 60%
Variable Overheads 478.80
1,500
Contribution 612.00
P/V Ratio (` 612/1800x100) 34.0%
Sales to required earn a profit of 20%
Sales = ` 4,78,800 + 0.20 of Sales
34.00%
Sales = ` 34,20,000 or 1,900 units (` 34,20,000/1800)
To earn profit 20% on sales of readymade suit (along with TIE PIN) company has to sold 1,900 units i.e. 95%
of the full capacity. This sales level of 1,900 units is justified only if variable cost is constant. Any upside in
variable cost would impact profitability, to achieve the desired profitability. Production has to be increased
but the scope is limited to 5% only.
Q-13 Why is ‘Zero Base Budgeting’ (ZBB) considered superior to ‘Traditional Budgeting’? Explain.
Ans. Zero based budgeting is superior to traditional budgeting: Zero based budgeting is superior to traditional
budgeting in the following manner:
• It provides a systematic approach for evaluation of different activities.
• It ensures that the function undertaken are critical for the achievement of the objectives.
• It provides an opportunity for management to allocate resources to various activities after a
thorough – cost benefit analysis.
• It helps in the identification of wasteful expenditure and then their elimination. If facilitates the
close linkage of departmental budgets with corporate objectives.
• It helps in the introduction of a system of Management by Objectives.
Q-14 M Ltd. has an annual fixed cost of Rs. 98,50,000. In the year 20X8-X9, sales amounted to Rs.7,80,60,000
as compared to Rs.5,93,10,000 in the preceding year 20X7-X8. Profit in the year 20X8-X9 is Rs.37,50,000
more than that in 20X7-X8.
Required:
(i) CALCULAT E Break-even sales of the company ;
(ii) DET ERMINE profit/ loss on a forecasted sales volume of Rs.8, 20,00,000.
(iii) If there is a reduction in selling price by 10% in the financial year 20X8-X9 and company desires to
earn the same amount of profit as in 20X7-X8, COMPUT E the required sales amount?
Fiexd cost
Ans. (i) Break-even sales =
P / V Ratio
Change in Profit
Or, x 100 or, 20%
Change in Sales
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -475-
2,000
P/V Ratio = x 100 = 58.82%
3,400
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -479-
Q-18
Fixed Cost Rs. 1,20,000
Variable costs Rs. 3 per unit
Selling price Rs. 7 per unit
Output Rs. 50,000 units
CALCULATE the profit for each of the following situation with the above data:
(i) with the data above
(ii) with a 10% increase in output & sales.
(iii) with a 10% increase in fixed costs.
(iv) with a 10% increase in variable costs.
(v) with a 10% increase in selling price.
(vi) taking all the above situations.
Ans. (i)
Rs.
Sales 50,000 units at Rs. 7 3,50,000
Variable cost 50,000 × 3 1,50,000
Contribution 50,000 × 4 2,00,000
Fixed costs 1,20,000
Profit 80,000
S- V 7-3 4
P/V ratio = ×100 = × 100 = × 100 = 57.14%
S 7 7
F 1,20,000
BEP (units) = = =30,000 Unitss
contribution per unit 4
BEP (Value) = 30,000 Units × 7 = Rs. 2,10,000
Profit Rs. 80,000 (as calculated above)
(ii) with a 10% increase in output & sales
i.e., 50,000+ 5,000 = 55,000 units
Contribution 55,000 × Rs. 4 per unit Rs. 2,20,000
Fixed costs Rs. 1,20,000
Profit Rs. 1,00,000
(iii) with a 10% increase in Fixed Cost
Contribution (50,000 ×Rs. 4 per unit) Rs. 2,00,000
Fixed cost (1,20,000+ 12,000 ) Rs. 1,32,000
Profit Rs. 68,000
(iv) with a 10% increase in variable costs
Selling price per unit 7.00
Less: variable cost (3+0.30) 3.30
Contribution per unit 3.70
Total contribution 50,000 × 3.70 1,85,000
Fixed costs 1,20,000
Profit 65,000
Rs.21,60,000
Rate of Net Return on Sales = 14.40% ×100
Rs.1,50,00,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -481-
(ii) Products
X (Rs.) Y (Rs.)
Selling Price per unit 100 150
Variable Cost per unit 60 100
Contribution per unit 40 50
Composite contribution will be as follows:
40 50
Contribution per unit = × 5 + × 3
8 8
= 25 + 18.75 = Rs.43.75
Rs.28,00,000
Break-even Sale = 64,000 units
Rs.43.75
Break-even Sales Mix:
X (64,000 units × 5/8) = 40,000 units
Y (64,000 units × 3/8) = 24,000 units
Q-20 Arnav Ltd. is producing a single product, has the profit-volume ratio of 40%. The company wishes to
increase the selling price by 10% which will increase the variable cost by 5%. The fixed overheads will
increase from its present level of Rs.20,00,000 to Rs.30,00,000.
Required:
(i) Compute the company’s original break-even point sales and the break-even point sales after the
increase.
(ii) Estimate the sales value for the firm to make a profit of Rs. 4,50,000 after the increase.
Ans. Workings:
Let us assume that the selling price before increment is ` 100, the other relevant details are as follows:
Particulars Before increase After increase
Selling Price 100 110
Variable Cost 60 63
Contribution 40 47
P/V Ratio 40% 42.73%
(i) Computation of Break-even point sales:
FixedOverheads
Break-even point sales =
P / Vratio
Q-21 A Ltd. manufacture and sales its product R-9. The following figures have been collected from cost
records of last year for the product R-9:
Elements of Cost Variable Cost portion Fixed Cost
Direct Material 30% of Cost of Goods Sold --
Direct Labour 15% of Cost of Goods Sold --
Factory Overhead 10% of Cost of Goods Sold Rs. 2,30,000
Administration Overhead 2% of Cost of Goods Sold Rs. 71,000
Selling & Distribution Overhead 4% of Cost of Sales Rs. 68,000
Last Year 5,000 units were sold at Rs.185 per unit. From the given DETERMINE the followings:
(i) Break-even Sales (in rupees)
(ii) Profit earned during last year
(iii) Margin of safety (in %)
(iv) Profit if the sales were 10% less than the actual sales.
(Assume that Administration Overhead is related with production activity).
Ans. Working Notes:
(1) Calculation of Cost of Goods Sold (COGS):
COGS = {(DM- 0.3 COGS) + (DL- 0.15 COGS) + (FOH- 0.10 COGS +
Rs. 2,30,000) + (AOH- 0.02 COGS + Rs. 71,000)}0.57 COGS + Rs. 3,01,000
Or, COGS = 0.57 COGS + Rs. 3,01,000
Rs.3, 01, 000
Or COGS = = Rs.7, 00, 000
0.43
(2) Calculation of Cost of Sales (COS):
COS = COGS + (S&DOH- 0.04 COS + Rs. 68,000)
Or COS = Rs. 7,00,000 + (0.04 COS + Rs. 68,000)
Rs.7, 68, 000
Or, COS = = Rs.8, 00, 000
0.96
(3) Calculation of Variable Costs:
Direct Material- (0.30 × Rs. 7,00,000) Rs. 2,10,000
Direct Labour- (0.15 × Rs. 7,00,000) Rs. 1,05,000
Factory Overhead- (0.10 × Rs. 7,00,000) Rs. 70,000
Administration OH- (0.02 × Rs. 7,00,000) Rs. 14,000
Selling & Distribution OH (0.04 × Rs. 8,00,000) Rs. 32,000
Rs. 4,31,000
(4) Calculation of total Fixed Costs:
Factory Overhead- Rs. 2,30,000
Administration OH- Rs. 71,000
Selling & Distribution OH Rs. 68,000
Rs. 3,69,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -483-
=
Rs.185 × 5, 000 units - Rs.4, 31, 000 × 100 = 53.41%
Rs.185 × 5, 000 units
Rs.9,25,000 - Rs.6,90,882
(iii) Margin of Safety (%) = × 100 = 25.31%
Rs.9,25,000
Rs.9,25,000 - Rs.6,90,882
= × 100 = 25.31%
Rs.9,25,000
(iv) Profit if the sales were 10% less than the actual sales:
Profit = 90% (Rs.9,25,000 - Rs.4,31,000) - Rs.3,69,000
= Rs.4,44,600 - Rs.3,69,000 = Rs.75,600
Q-22 Can Cola, a zero sugar cold drink manufacturing Indian company, is planning to establish a subsidiary
company in Nepal to produce coconut flavoured juice. Based on the estimated annual sales of 60,000
bottles of the juice, cost studies produced the following estimates for the Nepalese subsidiary:
Total Annual Costs Percent of Total Annual Cost
(`) which is variable
Material 2,70,000 100%
Labour 1,97,000 80%
Factory Overheads 1,20,000 60%
Administration Expenses 52,000 35%
The Nepalese production will be sold by manufacturer’s representatives who will receive a
commission of 9% of the sale price. No portion of the Indian office expenses is to be allocated to the
Nepalese subsidiary. You are required to-
(i) COMPUTE the sale price per bottle to enable the management to realize an estimated 20% profit
on sale proceeds in Nepal.
(ii) CALCULATE the break-even point in rupees value sales and also in number of bottles for the
Nepalese subsidiary on the assumption that the sale price is ` 14 per bottle.
Ans.(i) Computation of Sale Price Per Bottle
(`)
Variable Cost:
Material 2,70,000
Labour (` 1,97,000 × 80%) 1,57,600
Factory Overheads (`1,20,000 × 60%) 72,000
Administrative Overheads (` 52,000 × 35%) 18,200
Commission (9% on ‘9,00,000 (Working Note -1)) 81,000
Fixed Cost:
Labour (` 1,97,000 × 20%) 39,400
Factory Overheads (` 1,20,000 × 40%) 48,000
Administrative Overheads (` 52,000 × 65%) 33,800
Total Cost 7,20,000
Profit (20% of ` 9,00,000) 1,80,000
Sales Proceeds 9,00,000
Sales Price per bottle Rs.9,00,000 15
60,000
(ii) Calculation of Break-even Point
Sales Price per Bottle = ` 14
Variable Cost per Bottle = Rs.5,93,400(workingnote 2) = `9.89
60,000bottles
Contribution per Bottle = ` 14 x ` 9.89 = ` 4.11
Break -even Point (in number of Bottles) = Fixedcost Contributionper bottle
= Rs.1,21,200 = 29,489
Rs.4.11
Break- even Point (in Sales Value) = 29,489 Bottles × ` 14
= ` 4,12,846
Working Note
(1) Let the Sales Price be ‘X’
9X
Commission =
100
20X
Profit =
100
X =`2,70,000 + `1,57,600 + ` 72,000 + ` 18,200 + ` 39,400 + ` 48,000 +
9X 20X
`33,800 + +
100 100
9X 20X
X = ` 6,39,000 + +
100 100
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -485-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -487-
Q-24 A Limited manufactures three different products and the following information has been collected
from the books of accounts:
Products
S T U
Sales Mix 25% 35% 40%
Selling Price ` 600 ` 800 ` 400
Variable Cost ` 300 ` 400 ` 240
Total Fixed Costs ` 36,00,000
Total Sales ` 1,20,00,000
The company has currently under discussion, a proposal to discontinue the manufacture of Product U
and replace it with Product M, when the following results are anticipated:
Products
S T U
Sales Mix 40% 35% 25%
Selling Price ` 600 ` 800 ` 600
Variable Cost ` 300 ` 400 ` 300
Total Fixed Costs ` 36,00,000
Total Sales ` 1,28,00,000
Required
(i) Compute the PV ratio, total contribution, profit and Break-even sales for the existing product mix.
(ii) Compute the PV ratio, total contribution, profit and Break-even sales for the proposed product
mix.
Ans. (i) Computation of PV ratio, contribution and break-even sales for existing product mix
Products Total
S T U
Selling Price (`) 600 800 400
Less: Variable Cost (`) 300 400 240
Contribution per unit (`) 300 400 160
P/V Ratio (Contribution/Selling price) 50% 50% 40%
Sales Mix 25% 35% 40%
Contribution per rupee of sales
(P/V Ratio × Sales Mix) 12.5% 17.5% 16% 46%
Present Total Contribution (` 1,20,00,000 × 46%) ` 55,20,000
Less: Fixed Costs ` 36,00,000
Present Profit ` 19,20,000
Present Break Even Sales (` 36,00,000/0.46) ` 78,26,087
(ii) Computation of PV ratio, contribution and break-even sale for proposed product mix
Products Total
S T U
Selling Price (`) 600 800 600
Less: Variable Cost (`) 300 400 300
Contribution per unit (`) 300 400 300
P/V Ratio (Contribution/Selling price) 50% 50% 50%
Sales Mix 40% 35% 25%
Contribution per rupee of sales
(P/V Ratio x Sales Mix) 20% 17.5% 12.5% 50%
Proposed Total Contribution (` 1,28,00,000 x 50%) ` 64,00,000
Less: Fixed Costs `36,00,000
Proposed Profit ` 28,00,000
Proposed Break Even Sales (` 36,00,000/0.50) ` 72 ,00,000
Q-25 Amy Ltd. manufacture and sales its product RM. The following figures have been collected from cost
records of last year for the product RM:
Elements of Cost Variable Cost portion Fixed Cost
Direct Material 30% of Cost of Goods Sold —
Direct Labour 15% of Cost of Goods Sold —
Factory Overhead 10% of Cost of Goods Sold ` 3,45,000
Administration Overhead 2% of Cost of Goods Sold ` 1,06,500
Selling & Distribution Overhead 4% of Cost of Sales ` 1,02,000
Last Year, 7,500 units were sold at ` 185 per unit. From the given information, DETERMINE the followings:
(i) Break-even Sales (in rupees)
(ii) Profit earned during last year
(iii) Margin of safety (in %)
(iv) Profit if the sales were 10% less than the actual sales.
(Assume that Administration Overhead is related with production activity)
Ans. Working Notes:
(1) Calculation of Cost of Goods Sold (COGS):
COGS = DM + DL + FOH + AOH
COGS = {0.3 COGS + 0.15 COGS + (0.10 COGS + ` 3,45,000) + (0.02 COGS + ` 1,06,500)}
Or, COGS = 0.57 COGS + ` 4,51,500
Or = COGS = = ` 10,50,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -489-
(iv) Profit if the sales were 10% less than the actual sales:
Profit = 90% (` 13,87,500 -` 6,46,500) - ` 5,53,500
= ` 1,13,400
Q-26 LR Ltd. is considering two alternative methods to manufacture a new product it intends to market. The
two methods have a maximum output of 50,000 units each and produce identical items with a selling
price of ` 25 each. The costs are:
Method-1 Method-2
Semi-Automatic Fully-Automatic
(`) (`)
Variable cost per unit 15 10
Fixed costs 1,00,000 3,00,000
You are required to calculate:
(1) Cost Indifference Point in units. Interpret your results.
(2) The Break-even Point of each method in terms of units.
Ans. (i) Cost Indifference Point
Method-1 and Method-2
(`)
Differential Fixed Cost (I) ` 2,00,000
(` 3,00,000 – ` 1,00,000)
Differential Variable Costs (II) `5
(` 15 – ` 10)
Cost Indifference Point (I/II) 40,000
(Differential Fixed Cost / Differential Variable Costs per unit)
Interpretation of Results
At activity level below the indifference points, the alternative with lower fixed costs and higher variable
costs should be used. At activity level above the indifference
point, alternative with higher fixed costs and lower variable costs should be used.
No. of Product Alternative to be Chosen
Product d” 40,000 units Method-1, Semi-Automatic
Product e” 40,000 units Method-2, Automatic
(ii) Break Even point (in units)
Method-1 Method-2
BEP (in units) = Fixed cost / Contribution per unit 1,00,000 / (25-15) 3,00,000/(25-10)
= 10,000 = 20,000
Q-27 Answer the following:
During a particular period ABC Ltd has furnished the following data:
Sales ` 10,00,000
Contribution to sales ratio 37% and
Margin of safety is 25% of sales.
A decrease in selling price and decrease in the fixed cost could change the “contribution to sales ratio”
to 30% and “margin of safety” to 40% of the revised sales. Calculate:
(i) Revised Fixed Cost.
(ii) Revised Sales and
(iii) New Break-Even Point.
Ans. Contribution to sales ratio (P/V ratio) = 37%
Variable cost ratio = 100% - 37% = 63%
Variable cost = ` 10,00,000 x 63% = ` 6,30,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -491-
After decrease in selling price and fixed cost, sales quantity has not changed. Thus, variable cost is `
6,30,000.
Revised Contribution to sales = 30%
Thus, Variable cost ratio = 100% ƒ{ 30% = 70%
6,30,000
Thus, Revised sales = = ` 9,00,000
70%
Revised, Break-even sales ratio = 100% - 40% (revised Margin of safety) = 60%
(i) Revised fixed cost = revised breakeven sales x revised contribution to
sales ratio
= ` 5,40,000 (` 9,00,000 x 60%) x 30%
= ` 1,62,000
(ii) Revised sales = ` 9,00,000 (as calculated above)
(iii) Revised Break-even point = Revised sales x Revised break-even sales ratio
= ` 9,00,000 x 60%
= ` 5,40,000
Q-28 Two manufacturing companies A and B are planning to merge. The details are as follows:
A B
Capacity utilisation (%) 90 60
Sales (`) 63,00,000 48,00,000
Variable Cost (`) 39,60,000 22,50,000
Fixed Cost (`) 13,00,000 15,00,000
Assuming that the proposal is implemented, calculate:
(i) Break-Even sales of the merged plant and the capacity utilization at that stage.
(ii) Profitability of the merged plant at 80% capacity utilization.
(iii) Sales Turnover of the merged plant to earn a profit of ` 60,00,000.
(iv) When the merged plant is working at a capacity to earn a profit of ` 60,00,000, what percentage of
increase in selling price is required to sustain an increase of 5% in fixed overheads.
Ans. Workings:
1. Statement showing computation of Breakeven of merged plant and other required information
S.No. Particulars Plan A Plant B Merged
Before After Before After Plant
(90%) (100%) (60%) (100%) (100%)
(`) (`) (`) (`) (`)
(i) Sales 63,00,000 70,00,000 48,00,000 80,00,000 1,50,00,000
(ii) Variable cost 39,60,000 44,00,000 22,50,000 37,50,000 81,50,000
(iii) Contribution (i - ii) 23,40,000 26,00,000 25,50,000 42,50,000 68,50,000
(iv) Fixed Cost 13,00,000 13,00,000 15,00,000 15,00,000 28,00,000
(v) Profit (iii - iv) 10,40,000 13,00,000 10,50,000 27,50,000 40,50,000
Contribution
2. PV ratio of merged plant = x 100
Sales
492- Chapter-14 : Marginal Costing
`68,50,000
= x 100 = 45.67 %
`1,50,00,000
Fixed Cost
(i) Break even sales of merged plant =
P/V Ratio
28,00,000
=
45.67%
= ` 61,30,939.34 (approx.)
`61,30,939.34
Capacity utilisation = x 100 = 40.88%
`1,50,00,000
(ii) Profitability of the merged plant at 80% capacity utilisation
= (` 1,50,00,000 x 80%) x P/v ratio – fixed cost
= ` 1,20,00,000 x 45.67% – ` 28,00,000
= ` 26,80,400
(iii) Sales to earn a profit of ` 60,00,000
`28,00,000 + `60,00,000
=
45.67%
= ` 1,92,68,666 (approx.)
(iv) Increase in fixed cost
= ` 28,00,000 x 5% = ` 1,40,000
Therefore, percentage increase in sales price
` 1,40,000
= x 100 = 0.726% (approx.)
` 1,92,68,666
Q-29 XYZ Ltd. is engaged in the manufacturing of toys. It can produce 4,20,000 toys at its 70% capacity on per
annum basis. Company is in the process of determining sales price for the financial year 2020-21. It has
provided the following information:
Direct Material ` 60 per unit
Direct Labour ` 30 per unit
Indirect Overheads:
Fixed ` 65,50,000 per annum
Variable ` 15 per unit
Semi-variable ` 5,00,000 per annum up to 60% capacity and ` 50,000 for every
5% increase in capacity or part thereof up to 80% capacity and
thereafter ` 75,000 for every 10% increase in capacity or part
thereof.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -493-
Company desires to earn a profit of ` 25,00,000 for the year. Company has planned that the factory will
operate at 50% of capacity for first six months of the year and at 75% of capacity for further three
months and for the balance three months, factory will operate at full capacity.
You are required to :
(1) Determine the average selling price at which each of the toy should be sold to earn the desired
profit.
(2) Given the above scenario, advise whether company should accept an offer to sell each Toy at:
(a) ` 130 per Toy
(b) ` 129 per Toy
Ans.(1) Statement of Cost
For For For Total
first 6 further 3 remaining 3
months months months
6,00,000 x 6,00,000 x 6,00,000 x
6/12 x 50% 3/12 x 75% 3/12
= 1,50,000 = 1,12,500 = 1,50,000 4,12,500
units units units units
Direct Material 90,00,000 67,50,000 90,00,000 2,47,50,000
Direct labour 45,00,000 33,75,000 45,00,000 1,23,75,000
Indirect – Variable Expenses 22,50,000 16,87,500 22,50,000 61,87,500
Indirect – Fixed Expenses 32,75,000 16,37,500 16,37,500 65,50,000
Indirect Semi-variable
expenses
- For first six months @ 2,50,000
5,00,000 per annum
- For further three months 1,62,500
@ 6,50,000* per annum
- For further three months 2,12,500 6,25,000
@ 8,50,000** per annum
Total Cost 1,92,75,000 1,36,12,500 1,76,00,000 5,04,87,500
Desired Profit 25,00,000
Sales value 5,29,87,500
Average Sales price per Toy 128.45
* ` 5,00,000+ [3 times (from 60% to 75%) x 50,000] = ` 6,50,000
** ` 6,50,000+ [1 time (from 75% to 80%) x 50,000] + [2 times (from 80% to 100%)
× 75,000] = ‘ 8,50,000
(2) (a) Company Should accept the offer as it is above its targeted sales price of ` 128.45 per toy.
(b) Company Should accept the offer as it is above its targeted sales price of ` 128.45 per toy.
Q-30 Moon Ltd. produces products ‘X’, ‘Y’ and ‘Z’ and has decided to analyse it’s production mix in respect of
these three products - ‘X’, ‘Y’ and ‘Z’.
Fixed Cost
Break-even Sales (Company as Whole) =
Composite P / V Ratio *
`13,50,000
=
54%
= ` 25,00,000
Total Contribution 2,025
*Composite P/V Ratio = = = 54%
Total Actual sales 3,750
Q-32 Aditya Limited manufactures three different products and the following information has been collected
from the books of accounts:
Products
S T U
Sales Mix 35% 35% 30%
Selling Price ` 300 ` 400 ` 200
Variable Cost ` 150 ` 200 ` 120
Total Fixed Costs ` 18,00,000
Total Sales ` 60,00,000
The company has currently under discussion, a proposal to discontinue the manufacture of Product U
and replace it with Product M, when the following results are anticipated:
Products
S T M
Sales Mix 50% 25% 25%
Selling Price ` 300 ` 400 ` 300
Variable Cost ` 150 ` 200 ` 150
Total Fixed Cost ` 18,00,000
Total Sales ` 64,00,000
Required
(i) COMPUTE the PV ratio, total contribution, profit and Break-even sales for the existing product mix.
(ii) COMPUTE the PV ratio, total contribution, profit and Break-even sales for the proposed product mix.
Ans. (i) Computation of PV ratio, contribution and break-even sales for existing product mix
Products
Total
S T U
Selling Price (`) 300 400 200
Less: Variable Cost (`) 150 200 120
Contribution per unit (`) 150 200 80
P/V Ratio (Contribution/Selling price) 50% 50% 40%
Sales Mix 35% 35% 30%
Contribution per rupee of sales
(P/V Ratio × Sales Mix) 17.5% 17.5% 12% 47%
Present Total Contribution (`60,00,000 × 47%) ` 28,20,000
Less: Fixed Costs ` 18,00,000
Present Profit ` 10,20,000
Present Break Even Sales (`18,00,000/0.47) ` 38,29,787
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -497-
Join Us on Telegram http://t.me/canotes_ipcc
Downloaded From www.castudynotes.com
(ii) Computation of PV ratio, contribution and break-even sale for proposed product mix
Products
S T M Total
Selling Price (`) 300 400 300
Less: Variable Cost (`) 150 200 150
Contribution per unit (`) 150 200 150
P/V Ratio (Contribution/Selling price) 50% 50% 50%
Sales Mix 50% 25% 25%
Contribution per rupee of sales
(P/V Ratio x Sales Mix) 25% 12.5% 12.5% 50%
Proposed Total Contribution (`64,00,000 x 50%) ` 32,00,000
Less: Fixed Costs `18,00,000
Proposed Profit ` 14,00,000
Proposed Break Even Sales (`18,00,000/0.50) ` 36,00,000
Q-33 What is Margin of Safety? What does a large Margin of Safety indicates? How can you calculate Margin
of Safety?
Ans. Margin of Safety: The margin of safety can be defined as the difference between the expected level of
sale and the breakeven sales.
The larger the margin of safety, the higher is the chances of making profits.
The Margin of Safety can be calculated by identifying the difference between the projected sales and
breakeven sales in units multiplied by the contribution per unit. This is possible because, at the
breakeven point all the fixed costs are recovered and any further contribution goes into the making of
profits.
Margin of Safety = (Projected sales – Breakeven sales) in units x contribution per unit
It also can be calculated as:
Profit
Margin of Safety =
P/V Ratio
Q-34 Difference between Cost Accounting and Management Accounting
Ans.
Basis Cost Accounting Management Accounting
(i) Nature It records the quantitative It records both qualitative and
aspect only. quantitative aspect.
(ii) Objective It records the cost of It Provides information to
producing a product and management for planning and
providing a service. co-ordination.
(iii) Area It only deals with cost It is wider in scope as it includes
Ascertainment. financial accounting, budgeting,
taxation, planning etc.
(iv) Recording of data It uses both past and It is focused with the projection
present figures. of figures for future.
(v) Development Its development is related It develops in accordance to the
to industrial revolution. need of modern business world.
(vi) Rules and It follows certain principles It does not follow any specific
Regulation and procedures for rules and regulations.
recording costs of different
products.
Q-35 A Limited manufactures three different products and the following information has been collected
from the books of accounts:
Products S T U
Sales Mix 25% 35% 40%
Selling Price ` 600 ‘800 ` 400
Variable Cost ` 300 ‘400 `240
Total Fixed Costs ` 36,00,000
Total Sales ` 1,20,00,000
The company has currently under discussion, a proposal to discontinue the manufacture of Product U
and replace it with Product M, when the following results are anticipated:
Products
S T M
Sales Mix 40% 35% 25%
Selling Price ` 600 ` 800 ` 600
Variable Cost ` 300 ` 400 ` 300
Total Fixed Costs ` 36,00,000
Total Sales ` 1,28,00,000
Required:
(i) COMPUTE the PV ratio, total contribution, profit and Break-even sales for the existing product mix.
(ii) COMPUTE the PV ratio, total contribution, profit and Break-even sales for the proposed product
mix.
Ans.
(i) Computation of PV ratio, contribution, profit and break-even sales for existing product mix
Products
S T U Total
Selling Price (`) 600 800 400
Less: Variable Cost (`) 300 400 240
Contribution per unit (`) 300 400 160
P/V Ratio (Contribution/Selling price) 50% 50% 40%
Sales Mix 25% 35% 40%
Contribution per rupee of sales 12.5% 17.5% 16% 46%
(P/V Ratio × Sales Mix)
Present Total Contribution (`1,20,00,000 × 46%) ` 55,20,000
Less: Fixed Costs ` 36,00,000
Present Profit ` 19,20,000
Present Break Even Sales (` 36,00,000/0.46) ` 78,26,087
(ii) Computation of PV ratio, contribution, profit and break-even sale for proposed product mix
Products
S T M Total
Selling Price (`) 600 800 600
Less: Variable Cost (`) 300 400 300
Contribution per unit (`) 300 400 300
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -499-
= 1,00,000 units
Present Break-even Sales (`) = 1,00,000 units „e` 24 = ` 24,00,000
(ii) Present P/V Ratio = 8/24 x 100 = 33.33%
(iii) Revised Selling Price per Unit = ` 24 – 10% of ` 24 = ` 21.60
Revised Contribution per Unit=` 21.60-` 16 = ` 5.60
Revised P/V Ratio = 5.60/ 21.60 x 100 = 25.926%
Or
units
Revised Break-even point (`) = 1,42,857 units x ` 21.60 = ` 30,85,711
(iv) Present profit =` 8,00,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -501-
X7 (3,000 x 3,000)
Wireless Charger (15,000 x 300) 3,35,00,000
Labour:
X5 (5,000 x 1,000)
X6 (4,000 x 1,500)
X7 (3,000 x 2,000)
Wireless Charger (15,000 x 200)
Overtime (5,000 x 1,000) 2,50,00,000
Other variable overheads 1,25,00,000 7,10,00,000
Contribution 6,17,00,000
Less: Fixed Cost 1,00,00,000
Profit 5,17,00,000
Q-37 At budget activity of 80% of total capacity, a company earns a P/V ratio of 30% and a profit of 15% of total
sales. Due to covid pandemic resulting in poor demand, the company has to reduce its selling price by
10%. The company was able to achieve a production and sales volume for the year equivalent to 50% of
total capacity. The sales value at this level was ` 27,00,000 at a reduced price of ` 18 per unit. Due to
reduction in production, the actual variable cost went up by 5% of the budget.
You are required to:
(i) PREPARE statement of profitability at budget and actual activity.
(ii) FIND P/V ratio and BES (in ‘ and unit of the actual sales activity).
Ans.
Actual Sales ‘ 27,00,000
Actual Selling Price per unit 18
---0---0---
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -503-
CHAPTER - 15
BUDGET & BUDGETARY CONTROL
Q-1 A Vehicle manufacturer has prepared sales budget for the next few months, and the following draft
figures are available:
Month No. of vehicles
October 40,000
November 35,000
December 45,000
January 60,000
February 65,000
To manufacture a vehicle a standard cost of `11,42,800 is incurred and sold through dealers at a uniform
selling price of `17,14,200 to customers. Dealers are paid 15% commission on selling price on sale of a
vehicle.
Apart from other materials, four units of Part - X are required to manufacture a vehicle. It is a policy of
the company to hold stocks of Part-X at the end of each month to cover 40% of next month’s production.
48,000 units of Part-X are in stock as on 1st October.
There are 9,500 nos. of completed vehicles in stock as on 1st October and it is policy to have stocks at
the end of each month to cover 20% of the next month’s sales.
You are required to -
(i) PREPARE Production budget (in nos.) for the month of October, November, December and January.
(ii) PREPARE a Purchase budget for Part-X (in units) for the months of October, November and
December.
(iii) CALCULATE the budgeted gross profit for the quarter October to December.
Ans.(i) Preparation of Production Budget (in units)
October November December January
Demand for the month (Nos.) 40,000 35,000 45,000 60,000
Add: 20% of next month’s demand 7,000 9,000 12,000 13,000
Less: Opening Stock (9,500) (7,000) (9,000) (12,000)
Vehicles to be produced 37,500 37,000 48,000 61,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -505-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -507-
Q-5 G Ltd. manufactures two products called ‘M’ and ‘N’. Both products use a common raw material Z. The
raw material Z is purchased @ ` 36 per kg from the market. The company has decided to review
inventory management policies for the forthcoming year.
The following information has been extracted from departmental estimates for the year ended 31st
March 2018 (the budget period):
Product M Product N
Sales (units) 28,000 13,000
Finished goods stock increase by year-end 320 160
Post-production rejection rate (%) 4 6
Material Z usage (per completed unit, net of wastage) 5 kg 6 kg
Material Z wastage (%) 10 5
Additional information:
- Usage of raw material Z is expected to be at a constant rate over the period.
- Annual cost of holding one unit of raw material in stock is 11% of the material cost.
- The cost of placing an orders is ` 320 per order.
- The management of G Ltd. has decided that there should not be more than 40 orders in a year for the
raw material Z.
Required:
(i) PREPARE functional budgets for the year ended 31st March 2018 under the following headings:
(a) Production budget for Products M and N (in units).
(b) Purchases budget for Material Z (in kgs and value).
(ii) CALCULATE the Economic Order Quantity for Material Z (in kgs).
(iii) If there is a sole supplier for the raw material Z in the market and the supplier do not sale more than
4,000 kg. of material Z at a time. Keeping the management purchase policy and production quantity mix
into consideration, CALCULATE the maximum number of units of Product M and N that could be produced.
Ans.
(i) (a) Production Budget (in units) for the year ended 31st March 2016
Product M Product N
Budgeted sales (units) 28,000 13,000
Add: Increase in closing stock 320 160
No. good units to be produced 28,320 13,160
Post production rejection rate 4% 6%
No. of units to be produced 29,500 14,000
28,320 13,160
0.96 0.94
(b) Purchase budget (in kgs and value) for Material Z
Product M Product N
No. of units to be produced 29,500 14,000
Usage of Material Z per unit of production 5 kg. 6 kg.
Material needed for production 1,47,500 kg. 84,000 kg.
Materials to be purchased 1,63,889 kg. 88,421 kg.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -509-
1,47,500 84,000
0.90 0.95
(iii) Since, the maximum number of order per year can not be more than 40 orders and the maximum
quantity per order that can be purchased is 4,000 kg. Hence, the total quantity of Material Z that can be
available for production:
= 4,000 kg. × 40 orders = 1,60,000 kg.
Product M Product N
Material needed for production to maintain the 1,03,929 kg. 56,071 kg.
1,63,889 88,421
same production mix 1,60,000 1,60,000
2,52,310 2,52,310
Less: Process wastage 10,393 kg. 2,804 kg.
Net Material available for
production 93,536 kg. 53,267 kg.
Units to be produced 18,707 units 8,878 units
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -511-
Q-8 What are the cases when a flexible budget is found suitable?
Ans. Flexible budgeting may be resorted to under following situations:
(i) In the case of new business venture due to its typical nature it may be difficult toforecast the
demand of a product accurately.
(ii) Where the business is dependent upon the mercy of nature e.g., a person dealing inwool trade
may have enough market if temperature goes below the freezing point.
(iii) In the case of labour-intensive industry where the production of the concern is dependent upon
the availability of labour.
Suitability for flexible budget:
1. Seasonal fluctuations in sales and/or production, for example in soft drinks industry;
2. a company which keeps on introducing new products or makes changes in the design of its products
frequently;
3. industries engaged in make-to-order business like ship building;
4. an industry which is influenced by changes in fashion; and
5. General changes in sales.
Q-9 An electronic gadget manufacturer has prepared sales budget for the next few months. In this respect,
following figures are available:
Months Electronic gadgets' sales
January 5000 units
February 6000 units
March 7000 units
April 7500 units
May 8000 units
To manufacture an electronic gadget, a standard cost of ` 1,500 is incurred and it is sold through dealers
at an uniform price of ` 2,000 per gadget to customers. Dealers are given a discount of 15% on selling
price.
Apart from other materials, two units of batteries are required to manufacture a gadget.
The company wants to hold stock of batteries at the end of each month to cover 30% of next month's
production and to hold stock of manufactured gadgets to cover 25% of the next month's sale.
3250 units of batteries and 1200 units of manufactured gadgets were in stock on 1st January.
Required:
(i) Prepare production budget (in units) for the month of January, February, March and April.
(ii) Prepare purchase budget for batteries (in units) for the month of January, February and March and
calculate profit for the quarter ending on March.
Ans. (i) Preparation of Production Budget (in Units)
January February March April May
Sales 5,000 6,000 7,000 7,500 8,000
Add: Closing stock (25% 1,500 1,750 1,875 2,000
of next month’s sales)
Less: Opening Stock (1200) (1500) (1750) (1875)
Production of electronic Gadgets 5,300 6,250 7,125 7,625
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -515-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -517-
Q-15 Explain the difference between fixed budget and flexible budget.
Ans. Difference between Fixed and Flexible Budgets:
Sl. No. Fixed Budget Flexible Budget
1. It does not change with actual volume of It can be re-casted on the basis of activity
activity achieved. Thus it is known as level to be achieved. Thus it is not rigid.
rigid or inflexible budget
2. It operates on one level of activity and It consists of various budgets for different
under one set of conditions. It assumes levels of activity
that there will be no change in the
prevailing conditions, which is
unrealistic.
3. Here as all costs like - fixed, variable and Here analysis of variance provides useful
semi-variable are related to only one information as each cost is analysed
level of activity so variance analysis according to its behaviour.
does not give useful information.
4. If the budgeted and actual activi ty levels Flexible budgeting at different levels of
differ significantly, then the aspects like activity facilitates the ascertainment of cost,
cost ascertainment and price fixation do fixation of selling price and tendering of
not give a correct picture. quotations.
5. Comparison of actual performance with It provides a mean ingful basis of comparison
budgeted targets will be meaningless of the actual performance with the budgeted
specially when there is a difference targets.
between the two activity levels.
Q-16 Calculate from the following figures:
(i) Efficiency ratio,
(ii) Activity, Ratio and
(iii) Capacity Ratio:
Budgeted Production 88,000 units
Standard Hours per unit 10
Actual Production75,000 units
Actual Working Hours 6,00,000
6,00,000 hrs.
= ×100
88,000 units × 10 hrs.
= 68.18%
Q-17 V Ltd. produces and markets a very popular product called ‘X’. The company is interested in presenting
its budget for the second quarter of 2019.
The following information are made available for this purpose:
(i) It expects to sell 50,000 bags of ‘X’ during the second quarter of 2019 at the selling price of Rs. 900
per bag.
(ii) Each bag of ‘X’ requires 2.5 kgs. of a raw – material called ‘Y’ and 7.5 kgs. of raw – material called ‘Z’.
(iii) Stock levels are planned as follows:
Particulars Beginning of Quarter End of Quarter
Finished Bags of ‘X’ (Nos.) 15,000 11,000
Raw – Material ‘Y’ (Kgs.) 32,000 26,000
Raw – Material ‘Z’ (Kgs.) 57,000 47,000
Empty Bag (Nos.) 37,000 28,000
(iv) ‘Y’ cost Rs.120 per Kg., ‘Z’ costs Rs.20 per Kg. and ‘Empty Bag’ costs Rs.80 each.
(v) It requires 9 minutes of direct labour to produce and fill one bag of ‘X’. Labour cost is Rs.50 per
hour.
(vi) Variable manufacturing costs are Rs.45 per bag. Fixed manufacturing costs Rs.30,00,000 per quarter.
(vii) Variable selling and administration expenses are 5% of sales and fixed administration and selling
expenses are Rs.20,50,000 per quarter.
Required
(i) PREPARE a production budget for the said quarter.
(ii) PREPARE a raw – material purchase budget for ‘Y’, ‘Z’ and ‘Empty Bags’ for the said quarter in
quantity as well as in rupees.
(iii) COMPUTE the budgeted variable cost to produce one bag of ‘X’.
(iv) PREPARE a statement of budgeted net income for the said quarter and show both per unit and
total cost data.
Ans.(i) Production Budget of ‘X’ for the Second Quarter
Particulars Bags (Nos.)
Budgeted Sales 50,000
Add: Desired Closing stock 11,000
Total Requirements 61,000
Less: Opening stock 15,000
Required Production 46,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -519-
(ii) Raw–Materials Purchase Budget in Quantity as well as in Rs. for 46,000 Bags of ‘X’
Particulars ‘Y’ ‘Z’ Empty Bags
Kgs. Kgs. Nos.
Production Requirements 2.5 7.5 1.0
Per bag of ‘X’
Requirement for Production 1,15,000 3,45,000 46,000
(46,000 × 2.5) (46,000 × 7.5) (46,000 × 1)
Add: Desired Closing Stock 26,000 47,000 28,000
Total Requirements 1,41,000 3,92,000 74,000
Less: Opening Stock 32,000 57,000 37,000
Quantity to be purchased 1,09,000 3,35,000 37,000
Cost per Kg./Bag Rs.120 Rs.20 Rs.80
Cost of Purchase (Rs.) 1,30,80,000 67,00,000 29,60,000
(iii) Computation of Budgeted Variable Cost of Production of 1 Bag of ‘X’
Particulars (Rs.)
Raw – Material
Y 2.5 Kg @120 300.00
Z 7.5 Kg. @20 150.00
Empty Bag 80.00
Direct Labour(Rs.50× 9 minutes / 60 minutes) 7.50
Variable Manufacturing Overheads 45.00
Variable Cost of Production per bag 582.50
(iv) Budgeted Net Income for the Second Quarter
Particulars Per Bag (Rs.) Total (Rs.)
Sales Value (50,000 Bags) 900.00 4,50,00,000
Less: Variable Cost:
Production Cost 582.50 2,91,25,000
Admn. & Selling Expenses (5% of Sales Price) 45.00 22,50,000
Budgeted Contribution 272.50 1,36,25,000
Less: Fixed Expenses:
Manufacturing 30,00,000
Admn. & Selling 20,50,000
Budgeted Net Income 85,75,000
Q-18 C Ltd. manufactures two products using two types of materials and one grade of labour. Shown below
is an extract from the company’s working papers for the next month’s budget:
Product-A Product-B
Budgeted sales (in units) 2,400 3,600
Budgeted material consumption per unit (in kg):
Material-X 5 3
Material-Y 4 6
Standard labour hours allowed per unit of product 3 5
Material-X and Material-Y cost Rs. 4 and Rs. 6 per kg and labours are paid Rs. 25 per hour. Overtime
premium is 50% and is paid, if a worker works for more than 40 hours a week. There are 180 direct
workers.
The target productivity ratio (or efficiency ratio) for the productive hours worked by the direct workers
in actually manufacturing the products is 80%. In addition, the non-productive down-time is budgeted
at 20% of the productive hours worked.
There are four 5-days weeks in the budgeted period and it is anticipated that sales and production will
occur evenly throughout the whole period.
It is anticipated that stock at the beginning of the period will be:
Product-A 400 units
Product-B 200 units
Material-X 1,000 kg.
Material-Y 500 kg.
The anticipated closing stocks for budget period are as below:
Product-A 4 days sales
Product-B 5 days sales
Material-X 10 days consumption
Material-Y 6 days consumption
Required:
CALCULATE the Material Purchase Budget and the Wages Budget for the direct workers, showing the
quantities and values, for the next month.
Ans. Number of days in budget period = 4 weeks × 5 days = 20 days
Number of units to be produced
Product-A (units) Product-B (units)
Budgeted Sales 2,400 3,600
Add: Closing stock 480 900
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -521-
Sales:
Acrylic finish wooden sheets ` 70,00,000
Lacquer finish wooden sheets ` 30,00,000
Direct material cost 65% of sales
Direct wages 25 workers @ ` 1,500 per month
Factory overheads:
Indirect labour –
Works manager ` 5,500 per month
Foreman ` 4,500 per month
Stores and spares 2.5% on sales
Depreciation on machinery ` 1,26,000
Light and power (fixed) `30,000
Repairs and maintenance ` 80,000
Others sundries 10% on direct wages
Administration, selling and distribution expenses ` 3,99,000 p.a.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -523-
Q-21 A factory can produce 1,80,000 units per annum at its 60% capacity. The estimated costs of production
are as under:
Direct material ` 50 per unit
Direct employee cost ` 16 per unit
Indirect expenses:
- Fixed ` 32,50,000 per annum
- Variable ` 10 per unit
- Semi-variable ` 40,000 per month up to 50% capacity and ` 15,000 for
every 20% increase in the capacity or part thereof.
If production program of the factory is as indicated below and the management desires to ensure a
profit of ` 10,00,000 for the year, DETERMINE the average selling price at which each unit should be
quoted:
First three months of the year- 50% of capacity;
Remaining nine months of the year- 75% of capacity.
Ans. Statement of Cost
First three Remaining nine Total (`)
months (`) months (`)
37,500 1,68,750 units 2,06,250 units
units
Direct material 18,75,000 84,37,500 1,03,12,500
Direct employee cost 6,00,000 27,00,000 33,00,000
Indirect- variable expenses 3,75,000 16,87,500 20,62,500
Indirect – fixed expenses 8,12,500 24,37,500 32,50,000
Indirect- semi-variable expenses
- For first three months @ ` 1,20,000 1,20,000
40,000 p.m.
- For remaining nine months @ 6,30,000 6,30,000
` 70,000* p.m.
Total cost 37,82,500 1,58,92,500 1,96,75,000
Desired profit - - 10,00,000
Sales value - - 2,06,75,000
Average selling price per unit 100.24
* ` 40,000 for 50% capacity + `15,000 for 20% increase in capacity + ` 15,000 for 5% increase in capacity
(because cost is increased for every 20% increase in capacity or part thereof)
Q-22 T Ltd manufactures and sells a single product and has estimated sales revenue of ` 1,51,20,000 during
the year based on 20% profit on selling price. Each unit of product requires 6 kg of material A and 3 kg
of material B and processing time of 4 hours in machine shop and 2 hours in assembly shop. Factory
overheads are absorbed at a blanket rate of 20% of direct labour. Variable selling & distribution overheads
are ` 30 per unit sold and fixed selling & distribution overheads are estimated to be ` 34,56,000.
The other relevant details are as under:
Purchase Price: Material A ` 80 per kg
Materials B ` 50 per kg
Labour Rate: Machine Shop ` 70 per hour
Assembly Shop ` 35 per hour
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -525-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -527-
= 4800 A
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -529-
= 8400 F
(ii) Fixed overhead variances
(a) Fixed overhead budget variance
= Budgeted overhead – Actual overhead
= ` 2,21,000 – ` 2,00,000
= 21,000 F
(b) Fixed overhead capacity variance
= Std rate x (Actual hours – budgeted hours)
= x (8,100 – 8,840)
= 18,500 A
(c) Fixed overhead efficiency variance
= Std rate x (Std hours for actual production – Actual hours)
= x (8,800 – 8,100)
= 17,500 F
(iii) Control Ratios
(a) Capacity Ratio
= Actual hours x 100
Budgeted hours
= 8,100 x 100 = 91.63%
8,840
(b) Efficiency Ratio
= Standard hours x 100
Actual hours
= 8,800 x 100 = 108.64 %
8,100
(c) Activity Ratio
= Standard hours x 100
Budgted hours
= 8,800 x 100 = 99.55%
8,840
Q-27 The accountant of manufacturing company provides you the following details for year 2019-20:
Particulars (`)
Direct materials 28,00,000
Direct Wages 16,00,000
Fixed factory overheads 16,00,000
Variable factory overheads 16,00,000
Other variable costs 12,80,000
Other fixed costs 12,80,000
Profit 18,40,000
Sales 1,20,00,000
During the year, the company manufactured two products A and B and the output and costs were:
Particulars A B
Output (units) 2,00,000 1,00,000
Selling price per unit ` 32.00 ` 56.00
Direct materials per unit ` 8.00 ` 12.00
Direct wages per unit ` 4.00 ` 8.00
Variable factory overhead is absorbed as a percentage of direct wages. Other variable costs have been
computed as: Product A ` 4.00 per unit; and B ` 4.80 per unit.
During 2020-21, it is expected that the demand for product A will fall by 25% and for B by 50%. It is
decided to manufacture a new product C, the cost for which is estimated as follows:
Particulars Product C
Output (units) 2,00,000
Selling price per unit ` 28.00
Direct materials per unit ` 6.40
Direct wages per unit ` 4.00
It is anticipated that the other variable costs per unit of Product C will be same as for product A.
PREPARE a budget to present to the management, showing the current position and the position for
2020-21. COMMENT on the comparative results.
Ans. Budget Showing Current Position and Position for 2020-21
Position for 2019-20 Position for 2020-21
A B Total A B C Total
(A+B) (A+B+C)
Sales (units) 2,00,000 1,00,000 – 1,50,000 50,000 2,00,000 –
(`) (`) (`) (`) (`) (`) (`)
(A) Sales 64,00,000 56,00,000 1,20,00,000 48,00,000 28,00,000 56,00,000 1,32,00,000
Direct Material 16,00,000 12,00,000 28,00,000 12,00,000 6,00,000 12,80,000 30,80,000
Direct wages 8,00,000 8,00,000 16,00,000 6,00,000 4,00,000 8,00,000 18,00,000
Factory overhead
(variable) 8,00,000 8,00,000 16,00,000 6,00,000 4,00,000 8,00,000 18,00,000
Other variable costs 800,000 4,80,000 12,80,000 6,00,000 240,000 8,00,000 16,40,000
(B) Marginal Cost 40,00,000 32,80,000 72,80,000 30,00,000 16,40,000 36,80,000 83,20,000
(C) Contribution (AB)
24,00,000 23,20,000 47,20,000 18,00,000 11,60,000 19,20,000 48,80,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -531-
Fixed costs
– Factory 16,00,000 16,00,000
– Others 12,80,000 12,80,000
(D) Total fixed cost 28,80,000 28,80,000
Profit (C – D) 18,40,000 20,00,000
Comments: Introduction of Product C is likely to increase profit by ` 1,60,000 (i.e. from ` 18,40,000 to
` 20,00,000) in 2020-21 as compared to 2019-20 even if the demand for Product A & B falls. Therefore,
introduction of product C is recommended.
Q-28 RS Ltd manufactures and sells a single product and has estimated sales revenue of ` 302.4 lakh during
the year based on 20% profit on selling price. Each unit of product requires 6 kg of material A and 3 kg
of material B and processing time of 4 hours in machine shop and 2 hours in assembly shop. Factory
overheads are absorbed at a blanket rate of 20% of direct labour. Variable selling & distribution overheads
are ` 60 per unit sold and fixed selling & distribution overheads are estimated to be ` 69,12,000.
The other relevant details are as under:
Purchase Price: Material A ` 160 per kg
Materials B ` 100 per kg
Labour Rate: Machine Shop ` 140 per hour
Assembly Shop ` 70 per hour
Finished Stock Material A Material B
Opening Stock 2,500 units 7,500 kg 4,000 kg
Closing Stock 3,000 units 8,000 kg 5,500 kg
Required:
(i) CALCULATE number of units of product proposed to be sold and selling price per unit,
(ii) PREPARE Production Budget in units, and
(iii) PREPARE Material Purchase Budget in units.
Ans. Workings:
Statement Showing “Total Variable Cost for the year”
Particulars Amount
(` )
Estimated Sales Revenue 3,02,40,000
Less: Desired Profit Margin on Sale @ 20% 60,48,000
Estimated Total Cost 2,41,92,000
Less: Fixed Selling and Distribution Overheads 69,12,000
Total Variable Cost 1,72,80,000
Statement Showing “Variable Cost per unit”
Particulars Variable Cost
p.u. (`)
Direct Materials:
A: 6 Kg. @ ` 160 per kg. 960
B: 3 Kg. @ ` 100 per kg. 300
Labour Cost:
Machine Shop: 4 hrs. @ ` 140 per hour 560
Assembly Shop: 2 hrs. @ ` 70 per hour 140
Factory Overheads: 20% of (` 560 + ` 140) 140
Variable Selling & Distribution Expenses 60
Total Variable Cost per unit 2,160
(i) Calculation of number of units of product proposed to be sold and selling price per unit:
Number of Units Sold = Total Variable Cost / Variable Cost per unit
= ` 1,72,80,000 / ` 2,160
= 8,000 units
Selling Price per unit = Total Sales Value / Number of Units Sold
= ` 3,02,40,000 / 8,000 units
= ` 3,780
(ii) Production Budget (units)
Particulars Units
Budgeted Sales 8,000
Add: Closing Stock 3,000
Total Requirements 11,000
Less: Opening Stock (2,500)
Required Production 8,500
(iii) Materials Purchase Budget (Kg.)
Particulars Material Material
A B
Requirement for Production 51,000 25,500
(8,500 units × 6 Kg.) (8,500 units × 3 Kg.)
Add: Desired Closing Stock 8,000 5,500
Total Requirements 59,000 31,000
Less: Opening Stock (7,500) (4,000)
Quantity to be purchased 51,500 27,000
Q-29 G Ltd. manufactures a single product for which market demand exists for additional quantity. Present
sales of ` 6,00,000 utilises only 60% capacity of the plant. The following data are available:
(1) Selling price : ` 100 per unit
(2) Variable cost : ` 30 per unit
(3) Semi-variable expenses : ` 60,000 fixed + ` 5 per unit
(4) Fixed expenses : ` 1,00,000 at present level,
estimated to increase by 25% at
and above 80% capacity.
You are required to prepare a flexible budget so as to arrive at the operating profit at 60%, 80% and
100% levels.
Ans. Flexible Budget
Activity Level 60% 80% 100%
Production (units) 6,000 8,000 10,000
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -533-
(` ) (` ) (` )
Sales @ ` 100 per unit 6,00,000 8,00,000 10,00,000
Variable Cost
(@ ` 35 (` 30 + ` 5) per unit) 2,10,000 2,80,000 3,50,000
Contribution (A) 3,90,000 5,20,000 6,50,000
Fixed Cost (part of semi-variable cost) 60,000 60,000 60,000
Other Fixed Cost 1,00,000 1,25,000 1,25,000
Total Fixed Cost (B) 1,60,000 1,85,000 1,85,000
Operating Profit (A – B) 2,30,000 3,35,000 4,65,000
Q-30 State the limitations of Budgetary Control System.
Ans. Limitations of Budgetary Control System
Points Description
1. Based on Estimates Budgets are based on a series of estimates, which are
based on the conditions prevalent or expected at the
time budget is established. It requires revision in plan
if conditions change.
2. Time factor Budgets cannot be executed automatically. Some
preliminary steps are required to be accomplished
before budgets are implemented. It requires proper
attention and time of management. Management must
not expect too much during the initial development
period.
3. Co-operation Required Staff co-operation is usually not available during the
initial budgetary control exercise. In a decentralised
organisation, each unit has its own objective and
these units enjoy some degree of discretion. In this
type of organisation structure, coordination among
different units is required. The success of the
budgetary control depends upon willing co-operation
and teamwork,
4. Expensive The implementation of budget is somewhat expensive.
For successful implementation of the budgetary
control, proper organisation structure with
responsibility is prerequisite. Budgeting process start
from the collection of information to for preparing the
budget and performance analysis. It consumes
valuable resources (in terms of qualified manpower,
equipment, etc.) for this purpose; hence, it is an
expensive process.
Q-31 What are the important points an organization should consider if it wants to adopt Performance
Budgeting?
Ans. For an enterprise that wants to adopt Performance Budgeting, it is thus imperative that:
• the objectives of the enterprise are spelt out in concrete terms.
• the objectives are then translated into specific functions, programmes, activities and tasks for
different levels of management within the realities of fiscal constraints.
• realistic and acceptable norms, yardsticks or standards and performance indicators should be
evolved and expressed in quantifiable physical units.
• a style of management based upon decentralised responsibility structure should be adopted, and
• an accounting and reporting system should be developed to facilities monitoring, analysis and
review of actual performance in relation to budgets.
Q-32 Maharatna Ltd., a public sector undertaking (PSU), produces product A. The company is in process of
preparing its revenue budget for the year 2022. The company has the following information which can
be useful in preparing the budget:
(i) It has anticipated 12% growth in sales volume from the year 2021 of 4,20,000 tonnes.
(ii) The sales price of `23,000 per tonne will be increased by 10% provided Wholesale Price Index
(WPI) increases by 5%.
(iii) To produce one tonne of product A, 2.3 tonnes of raw material are required. The raw material cost
is `4,500 per tonne. The price of raw material will also increase by 10% if WPI increase by 5%.
(iv) The projected increase in WPI for 2022 is 4%
(v) A total of 6,000 employees works for the company. The company works 26 days in a month.
(vi) 85% of employees of the company are permanent and getting salary as per 5- year wage agreement.
The earnings per manshift (means an employee cost for a shift of 8 hours) is ` 3,000 (excluding
terminal benefits). The new wage agreement will be implemented from 1st July 2022 and it is
expected that a 15% increase in pay will be given.
(vii) The casual employees are getting a daily wage of ` 850. The wages in linked to Consumer Price
Index (CPI). The present CPI is 165.17 points and it is expected to be 173.59 points in year 2022.
(viii) Power cost for the year 2021 is ` 42,00,000 for 7,00,000 units (1 unit = 1 Kwh). 60% of power is used
for production purpose (directly related to production volume) and remaining are for employee
quarters and administrative offices.
(ix) During the year 2021, the company has paid ` 60,00,000 for safety and maintenance works. The
amount will increase in proportion to the volume of production.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -535-
(x) During the year 2021, the company has paid ` 1,20,000 for the purchase of diesel to be used in car
hired for administrative purposes. The cost of diesel will increase by 15% in year 2022.
(xi) During the year 2021, the company has paid ` 6,00,000 for car hire charges (excluding fuel cost). In
year 2022, the company has decided to reimburse the diesel cost to the car rental company. Doing
this will attract 5% GST on Reverse Charge Mechanism (RCM) basis on which the company will not
get GST input credit.
(xii) Depreciation on fixed assets for the year 2021 is ` 80,40,00,000 and it will be 15% lower in 2022.
Required:
From the above information PREPARE Revenue (Flexible) budget for the year 2022 and also show the
budgeted profit/ loss for the year.
Ans. Revenue Budget (Flexible Budget) of Maharatna Ltd. for the Year 2022
Particulars PY 2021 CY 2022
A Sales Volume (Tonnes) 4,20,000 4,70,400
[112%×4,20,000]
B Selling Price per tonne (`) 23,000 23,000
(` in lakh) (` in lakh)
C Sales value [A×B] 96,600 1,08,192
D Raw material Cost:
(i) Qty. of Material 9,66,000 10,81,920
[2.3 tonnes × A] (tonnes)
(ii) Price per tonne (`) 4,500 4,500
(iii) Total raw material cost (` in lakh) [(i)×(ii)] 43,470 48,686.40
E Wages & Salary Cost:
(i) Wages to casual employees
(15% × 6,000 = 900 employees) 2,386.80 2,508.47
[900 × 26 × 12 × ` 850] [900 × 26 × 12 × ` 893.33]
(ii) Salary to permanent employees 47,736 51,316.20
(85% × 6,000 = 5,100 employees) [5100 × 26 × 12 × [(5100 × 26 × 6 ×
` 3,000] ` 3,000) +
(5100 × 26 × 6
× ` 3,450)]
(iii) Total wages & salary [(i)+(ii)] 50,122.80 53,824.67
F Power cost:
(i) For production (units) 4,20,000 4,70,400
[60% × 7,00,000] [112% × 4,20,000]
(ii) For employees & offices (units)
[40% × 7,00.000] 2,80,000 2,80,000
Q-33 The Accountant of KPMR Ltd. has prepared the following budget for the coming year 2022 for its two
products ‘AYE’ and ‘ZYE’:
Particulars Product ‘AYE’ Product ‘ZYE’
Production and Sales (in Units) 4,000 3,000
Amount (in `) Amount (in `)
Selling Price per unit 200 180
Direct Material per unit 80 70
Direct Labour per unit 40 35
Variable Overhead per unit 20 25
Fixed Overhead per unit 10 10
After reviewing the above budget, the management has called the marketing team for suggesting
some measures for increasing the sales. The marketing team has suggested that by promoting the
products on social media, the sales quantity of both the products can be increased by 5%. Also, the
selling price per unit will go up by 10%. But this will result in increase in expenditure on variable
overhead and fixed overhead by 20% and 5% respectively for both the products.
You are required to prepare flexible budget for both the products:
(i) Before promotion on social media,
(ii) After promotion on social media.
Ans.(i) Flexible Budget (before promotion)
Particulars Product ‘AYE’ Product ‘ZYE’ Total
Production & Sales (units) 4,000 3,000
Amount (`) Amount (`) Amount (`)
A. Sales Value 8,00,000 5,40,000 13,40,000
(` 200×4,000) (` 180×3,000)
B. Direct Materials 3,20,000 2,10,000 5,30,000
(` 80 × 4,000) (`70 × 3,000)
C. Direct labour 1,60,000 1,05,000 2,65,000
(` 40 × 4,000) (` 35 × 3,000)
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -537-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -539-
PREPARE a cost sheet for the month showing total cost and profit at 30% and 100% capacity level.
Ans. Cost Sheet (For the month)
Level of Capacity 30% 100%
30,000 units 1,00,000 units
Per unit (`) Total (`) Per unit (`) Total (`)
Works Cost 1,900.00 5,70,00,000 1,550.00 15,50,00,000
Add: Fixed general administration
expenses 25.00 7,50,000 7.50 7,50,000
Add: Fixed marketing expenses 41.67 12,50,000 12.50 12,50,000
Add: Variable distribution cost 150.00 45,00,000 150.00 1,50,00,000
Add: Special Costs:
- Refreshments - - 5.00 5,00,000
- Gift items costs - - 150.00 1,50,00,000
- Television programme
sponsorship cost - - 100.00 1,00,00,000
- Customers’ prizes* - - 5.00 5,00,000
Cost of sales 2,116.67 6,35,00,000 1,980.00 19,80,00,000
Profit (Balancing figure) 633.33 1,90,00,000 520.00 5,20,00,000
Sales revenue2,750.00 8,25,00,000 2,500.00 25,00,00,000
*Customers’ prize cost: Amount (`)
1st Prize 2,50,000
2nd Prize 1,25,000
3rd Prize 50,000
Consolation Prizes (3 × ` 25,000) 75,000
Total 5,00,000
---0---0---
CHAPTER-16
MISCELLANEOUS TOPICS
Q-1
(a) DIFFERENTIATE between Cost Accounting and Management Accounting.
(b) DISCUSS the impact of Information Technology (IT) on cost accounting system.
(c) DISCUSS the Escalation Clause in a Contract.
(d) DISCUSS the treatment of by-product cost in cost accounting.
Ans.(a) Difference between Cost Accounting and Management Accounting
Basis Cost Accounting Management Accounting
(i) Nature It records the quantitative It records both qualitative and
aspect only. quantitative aspect.
(ii) Objective It records the cost of It Provides information to management
producing a product and for planning and co-ordination.
providing a service.
(iii) Area It only deals with cost It is wider in scope as it includes financial
Ascertainment. accounting,budgeting,taxation, planning etc.
(iv) Recording It uses both past and It is focused with the projection of figures
of data present figures. for future.
(v) Development Its development is related to It develops in accordance to the need of
industrial revolution. modern business world.
(vi) Rules and It follows certain principles It does not follow any specific rules and
Regulation and procedures for recording regulations.
costs of different products.
(b) The impact of IT in cost accounting system may include the following:
(i) After the introduction of ERPs, different functional activities get integrated and as a consequence
a single entry into the accounting system provides custom made reports for every purpose and
saves an organisation from preparing different sets of documents. Reconciliation process of results
of both cost and financial accounting systems become simpler and less sophisticated.
(ii) A move towards paperless environment can be seen where documents like Bill of Material,
Material Requisition Note, Goods Received Note, labour utilisation report etc. are no longer
required to be prepared in multiple copies, the related department can get e-copy from the
system.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -541-
(iii) Information Technology with the help of internet (including intranet and extranet) helps in
resource procurement and mobilisation. For example, production department can get materials
from the stores without issuing material requisition note physically. Similarly, purchase orders
can be initiated to the suppliers with the help of extranet. This enables an entity to shift towards
Just-in-Time (JIT) approach of inventory management and production.
(iv) Cost information for a cost centre or cost object is ascertained with accuracy in timely manner.
Each cost centre and cost object is codified and all related costs are assigned to the cost object or
cost centre. This process automates the cost accumulation and ascertainment process. The cost
information can be customised as per the requirement. For example, when an entity manufacture
or provide services, it can know information job-wise, batch-wise, process-wise, cost centre wise
etc.
(v) Uniformity in preparation of report, budgets and standards can be achieved with the help of IT.
ERP software plays an important role in bringing uniformity irrespective of location, currency,
language and regulations.
(vi) Cost and revenue variance reports are generated in real time basis which enables the management
to take control measures immediately.
(vii) IT enables an entity to monitor and analyse each process of manufacturing or service activity
closely to eliminate non value added activities.
The above are examples of few areas where Cost Accounting is done with the help of IT.
(c) Escalation clause in a contract empowers a contractor to revise the price of the contract in case of
increase in the prices of inputs due to some macro-economic or other agreed reasons. A contract takes
longer period to complete and the factors based on which price negotiation is done at the time of
entering into the contract may change till the contract completes. This protect the contractor from
adverse financial impacts and empowers the contractor to recover the increased prices. As per this
clause, the contractor increases the contract price if the cost of materials, employees and other expenses
increase beyond a certain limit. Inclusion of such a clause in a contract deed is called an “Escalation
Clause”.
(d) By-product cost can be dealt in cost accounting in the following ways:
(i) When they are of small total value: When the by-products are of small total value, the amount
realised from their sale may be dealt in any one the following two ways:
1. The sales value of the by-products may be credited to the Costing Profit and Loss Account
and no credit be given in the Cost Accounts. The credit to the Costing Profit and Loss Account
here is treated either as miscellaneous income or as additional sales revenue.
2. The sale proceeds of the by-product may be treated as deductions from the total costs. The
sale proceeds in fact should be deducted either from the production cost or from the cost of
sales.
(ii) When the by-products are of considerable total value: Where by-products are of considerable
total value, they may be regarded as joint products rather than as by-products. To determine
exact cost of by-products the costs incurred upto the point of separation, should be apportioned
over by-products and joint products by using a logical basis. In this case, the joint costs may be
divided over joint products and by-products by using relative market values; physical output
method (at the point of split off) or ultimate selling prices (if sold).
(iii) Where they require further processing: In this case, the net realisable value of the by-product at
the split-off point may be arrived at by subtracting the further processing cost from the realisable
value of by-products.
If total sales value of by-products at split-off point is small, it may be treated as per the provisions
discussed above under (i).
In the contrary case, the amount realised from the sale of by-products will be considerable and
thus it may be treated as discussed under (ii).
Q-2
(i) DIFFERENTIATE between Cost Accounting and Management Accounting.
(ii) EXPLAIN the meaning of Budget Manual.
(iii) EXPLAIN the term Equivalent units used in process industries.
Ans. (i) Difference between Cost Accounting and Management Accounting
Basis Cost Accounting Management Accounting
(i) Nature It records the It records both qualitativeand
quantitativeaspect only. quantitative aspect.
(ii) Objective It records the cost ofproducing It Provides information
a product andproviding a service. tomanagement for planningand co-
ordination.
(iii) Area It only deals with cost Ascertainment. It is wider in scope as itincludes
financialaccounting, budgeting,
taxation, planning etc.
(iv) Recording It uses both past andpresent figures. It is focused with theprojection of
of data figures forfuture.
(v) Development Its development is relatedto industrial It develops in accordanceto the need
revolution. of modernbusiness world.
(vi) Rules and It follows certain principlesand It does not follow anyspecific
Regulation procedures forrecording costs of rules andregulations.
differentproducts.
(ii) Budget Manual: A budget manual is a collection of documents that contains key information for those
involved in the planning process. Typical contents could include the following:
• An introductory explanation of the budgetary planning and control process, including a statement of
the budgetary objective and desired results.
• A form of organisation chart to show who is responsible for the preparation of each functional budget
and the way in which the budgets are interrelated.
• A timetable for the preparation of each budget. This will prevent the formation of a ‘bottleneck’ with
the late preparation of one budget holding up the preparation of all others.
• Copies of all forms to be completed by those responsible for preparing budgets, with explanations
concerning their completion.
• A list of the organization’s account codes, with full explanations of how to use them.
• Information concerning key assumptions to be made by managers in their budgets, for example the
rate of inflation, key exchange rates, etc.
(iii) Equivalent Units: Equivalent units or equivalent production units, means converting the incomplete
production units into their equivalent completed units. Under each process, an estimate is made of the
percentage completion of work-in-process with regard to different elements of costs, viz., material,
labour and overheads. It is important that the estimate of percentage of completion should be as
accurate as possible. The formula for computing equivalent completed units is:
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -543-
For instance, if 25% of work has been done on the average of units still under process, then 200 such
units will be equal to 50 completed units and the cost of work-inprocess will be equal to the cost of 50
finished units.
Q-3 (a) DISTINGUISH between Cost Control and Cost Reduction.
(b) DISCUSS the accounting treatment of Idle time and overtime wages.
(c) DISCUSS cost classification based on variability and controllability.
Ans.
(a) Difference between Cost Control and Cost Reduction
Cost Control Cost Reduction
1. Cost control aims at maintaining the 1. Cost reduction is concerned with reducing costs.
costs in accordance with the It challenges all standards and endeavours
established standards. to better them continuously
2. Cost control seeks to attain lowest 2. Cost reduction recognises no condition as
possible cost under existing conditions. permanent, since a change will result in lower cost.
3. In case of cost control, emphasis is 3. In case of cost reduction, it is on present and future.
on past and present
4. Cost control is a preventive function 4. Cost reduction is a corrective function.
It operates even when an efficient cost control
system exists.
5. Cost control ends when targets are achieved. 5. Cost reduction has no visible end.
(b) Accounting treatment of idle time wages & overtime wages in cost accounts: Normal idle time is
treated as a part of the cost of production. Thus, in the case of direct workers, an allowance for normal
idle time is built into the labour cost rates. In the case of indirect workers, normal idle time is spread
over all the products or jobs through the process of absorption of factory overheads.
Under Cost Accounting, the overtime premium is treated as follows:
• If overtime is resorted to at the desire of the customer, then the overtime premium may be charged to
the job directly.
• If overtime is required to cope with general production program or for meeting urgent orders, the
overtime premium should be treated as overhead cost of particular department or cost center which
works overtime.
• Overtime worked on account of abnormal conditions should be charged to costing Profit & Loss Account.
• If overtime is worked in a department due to the fault of another department the overtime premium
should be charged to the latter department.
(c) Cost classification based on variability
(a) Fixed Costs – These are the costs which are incurred for a period, and which, within certain output
and turnover limits, tend to be unaffected by fluctuations in the levels of activity (output or
turnover). They do not tend to increase or decrease with the changes in output. For example,
rent, insurance of factory building etc., remain the same for different levels of production.
(b) Variable Costs – These costs tend to vary with the volume of activity. Any increase in the activity
results in an increase in the variable cost and vice-versa. For example, cost of direct labour, etc.
(c) Semi-variable Costs – These costs contain both fixed and variable components and are thus partly
affected by fluctuations in the level of activity. Examples of semi variable costs are telephone
bills, gas and electricity etc.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -545-
3. In case of cost control, emphasis is 3. In case of cost reduction, it is on present and future.
on past and present
4. Cost control is a preventive function 4. Cost reduction is a corrective function.
It operates even when an efficient cost control
system exists.
5. Cost control ends when targets 5. Cost reduction has no visible end.
are achieved.
(c) (i) Controllable Costs: - Cost that can be controlled, typically by a cost, profit or investment centre
manager is called controllable cost. Controllable costs incurred in a particular responsibility centre can
be influenced by the action of the executive heading that responsibility centre. For example, direct
costs comprising direct labour, direct material, direct expenses and some of the overheads are generally
controllable by the shop level management.
(ii) Uncontrollable Costs - Costs which cannot be influenced by the action of a specified member of an
undertaking are known as uncontrollable costs. For example, expenditure incurred by, say, the tool
room is controllable by the foreman in-charge of that section but the share of the tool-room expenditure
which is apportioned to a machine shop is not to be controlled by the machine shop foreman.
(d) Distinction between Job and Batch Costing:
Sr. No Job Costing Batch Costing
1 Method of costing used for non- standard Homogeneous products produced in a
and non- repetitive products produced continuous production flow in lots.
as per customer specifications and against
specific orders.
2 Cost determined for each Job Cost determined in aggregate for the entire Batch
and then arrived at on per unit basis.
3 Jobs are different from each other and Products produced in a batch are homogeneous
independent of each other. and lack of individuality
Each Job is unique.
Q-5
(i) Discuss on (a) Discretionary Cost Centre and (b) Investment Centre
(ii) Describe the three advantages of Cost-plus contract.
(iii) State the advantages of Zero-based budgeting.
(iv) Describe Operation costing with two examples of industries where operation costing is applied.
15. (i) (a) Discretionary Cost Centre: The cost centre whose output cannot be measured in financial terms,
thus input -output ratio cannot be defined. The cost of input is compared with allocated budget for the
activity. Example of discretionary cost centres are Research & Development department, Advertisement
department where output of these department cannot be measured with certainty and co -related
with cost incurred on inputs.
(b) Investment Centres: These are the responsibility centres which are not only responsible for profitability
but also has the authority to make capital investment decisions. The performance of these responsibility
centres are measured on the basis of Return on Investment (ROI) besides profit. Examples of
investment centres are Maharatna, Navratna and Miniratna companies of Public Sector Undertakings
of Central Government.
(iii) Comparison of actual performance with set standard or target: The actual performance so
measured is compared against the set standard and desired target. Any deviation (variance)
between the two is noted and reported to the appropriate person or authority.
(iv) Analysis of variance and action: The variance in results so noted are further analysed to know the
reasons for variance and appropriate action is taken to ensure compliance in future. If necessary,
the standards are further amended to take developments into account.
(b) Bill of Materials Material Requisition Note
1. It is the document prepared by the 1. It is prepared by the production or
engineering or planning department. other consuming department.
2. It is a complete schedule of component 2. It is a document authorizing Storekeeper
parts and raw materials required for a to issue materials to the consuming
particular job or work order. department.
3. It often serves the purpose of a material 3. It cannot replace a bill of materials.
requisition as it shows the complete
schedule of materials required for a
particular job i.e. it can replace material
requisition.
4. It can be used for the purpose of 4. It is useful in arriving historical cost only.
quotations.
5. It helps in keeping a quantitative control 5. It shows the material actually drawn
on materials drawn through material from stores.
requisition.
(c) Financial expenses causing differences in Financial and Cost Accounts:
(i) Interest on loans or bank mortgages.
(ii) Expenses and discounts on issue of shares, debentures etc.
(iii) Other capital losses i.e., loss by fire not covered by insurance etc.
(iv) Losses on the sales of fixed assets and investments.
(v) Goodwill written off.
(vi) Preliminary expenses written off.
(vii) Income tax, donations, subscriptions.
(viii) Expenses of the company’s share transfer office, if any.
(d) Standing Charges: These are the fixed costs that remain constant irrespective of the distance travelled.
These costs include the following-
- Insurance
- License fees
- Salary to Driver, Conductor, Cleaners, etc. if paid on monthly basis
- Garage costs, including garage rent
- Depreciation (if related to efflux of time)
- Taxes
- Administration expenses, etc.
Running Charges: These costs are generally associated with the distance travelled. These costs include
the following-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -549-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -551-
Direct costing Direct costing is a specialized form of cost analysis that only uses
variable costs to make decisions. It does not consider fixed costs,
which are assumed to be associated with the time periods in which
they are incurred.
(b) (i) Joint Products - Joint products represent “two or more products separated in the course of the same
processing operation usually requiring further processing, each product being in such proportion that
no single product can be designated as a major product”.
In other words, two or more products of equal importance, produced, simultaneously from the same
process, with each having a significant relative sale value are known as joint products.
For example, in the oil industry, gasoline, fuel oil, lubricants, paraffin, coal tar, asphalt and kerosene
are all produced from crude petroleum. These are known as joint products.
(ii) By-Products - These are defined as “products recovered from material discarded in a main process, or
from the production of some major products, where the material value is to be considered at the time
of severance from the main product.” Thus, by-products emerge as a result of processing operation of
another product or they are produced from the scrap or waste of materials of a process. In short, a by-
product is a secondary or subsidiary product which emanates as a result of manufacture of the main
product.
The point at which they are separated from the main product or products is known as split-off point.
The expenses of processing are joint till the split –off point.
Examples of by-products are molasses in the manufacture of sugar, tar, ammonia and benzole obtained
on carbonisation of coal and glycerine obtained in the manufacture of soap.
(c) Procedure of Setting Labour Time Standards
The following are the steps involved in setting labour standards:
(a) Standardisation: Products to be produced are decided based on production plan and customer’s
order.
(b) Labour specification: Types of labour and labour time is specified. Labour time specification is
based on past records and it takes into account normal wastage of time.
(c) Standardisation of methods: Selection of proper machines to use proper sequence and method of
operations.
(d) Manufacturing layout: A plan of operation for each product listing the operations to be performed
is prepared.
(e) Time and motion study: It is conducted for selecting the best way of completing the job or motions
to be performed by workers and the standard time which an average worker will take for each job.
This also takes into account the learning efficiency and learning effect.
(f) Training and trial: Workers are trained to do the work and time spent at the time of trial run is
noted down.
(d) Budgetary Control System: It is the system of management control and accounting in which all the
operations are forecasted and planned in advance to the extent possible and the actual results
compared with the forecasted and planned results.
Components of Budgetary Control System: The policy of a business for a defined period is represented
by the master budget, the detailed components of which are given in a number of individual budgets
called functional budgets. These functional budgets are broadly grouped under the following heads:
1. Physical budgets: Those budgets which contain information in quantitative terms such as the
physical units of sales, production etc. This may include quantity of sales, quantity of production,
inventories, and manpower budgets are physical budgets.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -553-
2. Cost budgets: Budgets which provides cost information in respect of manufacturing, administration,
selling and distribution, etc. for example, manufacturing costs, selling costs, administration cost,
and research and development cost budgets are cost budgets.
3. Profit budgets: A budget which enables the ascertainment of profit. For example, sales budget,
profit and loss budget, etc.
4. Financial budgets: A budget which facilitates in ascertaining the financial position of a concern, for
example, cash budgets, capital expenditure budget, budgeted balance sheet etc.
Q-10 Difference between Cost Control and Cost Reduction
Ans.
Cost Control Cost Reduction
1. Cost control aims at maintaining 1. Cost reduction is concerned with
the costs in accordance with the reducing costs. It challenges all standards
established standards. and endeavours to improvise them continuously
2. Cost control seeks to attain lowest 2. Cost reduction recognises no condition
possible cost under existing conditions. as permanent, since a change will result in lower
cost.
3. In case of cost control, emphasis 3. In case of cost reduction, it is on
is on past and present present and future.
4. Cost control is a preventive function 4. Cost reduction is a corrective function.
It operates even when an efficient cost control
system exists.
5. Cost control ends when targets are 5. Cost reduction has no visible end and
achieved. is a continuous process.
Q-11 BRIEF OUT advantages and disadvantages of Halsey Premium Plan.
Ans.
Advantages Disadvantages
1. Time rate is guaranteed while there is 1. Incentive is not so strong as
opportunity for increasing earnings by with piece rate system. In fact
increasing production. the harder the worker works,
the lesser he gets per piece.
2. The system is equitable in as much as the 2. The sharing principle may not
employer gets a direct return for his efforts be liked by employees.
in improving production methods and providing
better equipment.
Q-12 STATE the method of costing for the following industries:
(i) Sugar manufacturing
(ii) Bridge Construction
(iii) Advertising
(iv) Car Assembly
Ans.
S. No. Industry Method of costing
(i) Sugar manufacturing Process costing
(ii) Bridge Construction Contract Costing
(iii) Advertising Job costing
(iv) Car Assembly Multiple Costing (Combination of any method)
Q-13 STATE the unit of cost for the following service industries:
(i) Electricity Supply service
(ii) Hospital
(iii) Cinema
(iv) Hotels
Ans.
S. No. Service industry Unit of cost
(i) Electricity Supply service Kilowatt- hour (kWh)
(ii) Hospital Patient per day, room per day or per bed,
per operation etc.
(iii) Cinema Per ticket.
(iv) Hotels Guest Days or Room Days
Q-14 BRIEF OUT advantages of Integrated Accounts.
Ans. Advantages of Integrated Accounts are as follows:
(i) No need for Reconciliation- The question of reconciling costing profit and financial profit does not
arise, as there is only one figure of profit.
(ii) Less efforts- Due to use of one set of books, there is a significant saving in efforts made.
(iii) Less time consuming- No delay is caused in obtaining information as it is provided from books of
original entry.
(iv) Economical process- It is economical also as it is based on the concept of “Centralisation of
Accounting function”.
Q-15 BRIEF OUT difference between Fixed and Flexible Budget.
Ans.
S. No. Fixed Budget Flexible Budget
1. It does not change with actual volume of It can be re-casted on the basis of
activity achieved. Thus it is known as rigid activity level to be achieved. Thus it
or inflexible budget. is not rigid.
2. It operates on one level of activity and under It consists of various budgets for
one set of conditions. It assumes that there different levels of activity.
will be no change in the prevailing conditions,
which is unrealistic.
3. Here as all costs like - fixed, variable and Here analysis of variance provides
semi-variable are related to only one level useful information as each cost is
of activity so variance analysis does not analysed according to its behaviour.
give useful information.
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -555-
4. If the budgeted and actual activity levels Flexible budgeting at different levels of
differ significantly, then the aspects like activity facilitates the ascertainment of cost,
cost ascertainment and price fixation do not fixation of selling price and tendering
give a correct picture. of quotations.
5. Comparison of actual performance with It provides a meaningful basis of
budgeted targets will be meaningless specially comparison of the actual performance with
when there is a difference between the the budgeted targets.
two activity levels.
Q-16 DISTINGUISH clearly between Bin cards and Stores Ledger.
Ans.
Bin Card Stores Ledger
It is maintained by the storekeeper in the store. It is maintained in cost accounting department.
It contains only quantitative details of
material received, issued and returned to stores. It contains information both in quantity and value.
Entries are made when transaction takes place. It is always posted after the transaction.
Each transaction is individually posted. Transactions may be summarized and then posted.
Inter-department transfers do not appear
in Bin Card. Material transfers from one job to another job are
recorded for costing purposes.
Q-17 Some of the items of PR Company, a manufacturer of corporate office furniture, are provided below. As
the company is in the process of developing a formal cost accounting system, you are required to
CLASSIFY the items into three categories namely: (i) Cost tracing (ii) Cost allocation (iii) Non-
manufacturing item.
Carpenter wages, Depreciation - office building, Glue for assembly, Lathe department supervisor, Metal
brackets for drawers, Factory washroom supplies, Lumber, Samples for trade shows, Lathe depreciation,
Lathe operator wages.
Ans.
Item Cost Tracing Cost Allocation Non-manufacturing
Carpenter wages
Depreciation - office building
Glue for assembly
Lathe department supervisor
Metal brackets for drawers
Factory washroom supplies
Lumber
Samples for trade shows
Lathe depreciation
Lathe operator wages
Where,
D = Annual demand for the product
S =Setting up cost per batch
C=Carrying cost per unit of production
Q-19 EXPLAIN what are the essential pre-requisites of Integrated accounting system?
Ans. Essential pre-requisites for Integrated Accounts: The essential pre-requisites for integrated accounts
include the following steps-
1. The management’s decision about the extent of integra tion of the two sets of books. Some
concerns find it useful to integrate up to the stage of prime cost or factory cost while other prefers
full integration of the entire accounting records.
2. A suitable coding system must be made available so as to serve the accounting purposes of financial
and cost accounts.
3. An agreed routine, with regard to the treatment of provision for accruals, prepaid expenses, other
adjustment necessary for preparation of interim accounts.
4. Perfect coordination should exist between the staff responsible for the financial and cost aspects
of the accounts and an efficient processing of accounting documents should be ensured.
Q-20 WHAT is inter-process profit? STATE its advantages and disadvantages.
Ans.
Inter-Process Profit: To control cost and to measure performance, different processes within an organization
are designated as separate profit centres. In this type of organizational structure, the output of one process
is transferred to the next process not at cost but at market value or cost plus a percentage of profit. The
difference between cost and the transfer price is known as inter - process profits.
The advantages and disadvantages of using inter-process profit, in the case of process type industries are as
follows:
Advantages:
1. Comparison between the cost of output and its market price at the stage of completion is facilitated.
2. Each process is made to stand by itself as to the profitability.
Disadvantages:
1. The use of inter-process profits involves complication.
2. The system shows profits which are not realised because of stock not sold out.
---0---0---
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -557-
Navkar Digital Institute | Paper 3 : Compiler | Most Imp collection of Chapterwise Que. & Ans. -559-