You are on page 1of 7

IEEE ENGINEERING MANAGEMENT REVIEW, VOL. 46, NO.

3, THIRD QUARTER, SEPTEMBER 2018 49

Industry 4.0 Fostering Construction


Supply Chain Management: Lessons
Learned From Engineer-to-Order
Suppliers
—PATRICK DALLASEGA Abstract—Industry 4.0 will certainly transform the manufacturing industry but
Faculty of Science and Technology, Free it will also have an impact on the construction industry and its connected
 5,
University of Bolzano, Piazza Universita supply chains. However, construction faces different problems than
Bolzano 39100, Italy manufacturing. Often construction projects are highly customized, containing
a significant numbers of engineer-to-order (ETO) components. ETO
construction supplier companies consistently consist of off-site and on-site
ß 2018 IEEE. Translations and content mining production elements. On-site construction processes are prone to high
are permitted for academic research only. variability and unpredictability. This uncertainty makes supply chain
Personal use is also permitted, but
republication/redistribution requires IEEE
synchronization for maintaining construction progress difficult. As a result,
permission. See http://www.ieee.org/ construction supply chains are characterized by high levels of intermediate
publications_standards/publications/rights/ buffers and long lead-times. We propose a variety of Industry 4.0 concepts to
index.html for more information.
ameliorate these problems. Initial applications are identified from previous
works. Additionally, we present some case studies for some lessons learned
from the collaboration with ETO-companies. Seven action points in various
IEEE DOI 10.1109/EMR.2018.2861389 applications of Industry 4.0 in the construction supply chain provide a guide to
managers.

Key words: Industry 4.0, supply chain management, construction,


engineer-to-order, just-in-time

INTRODUCTION chains. Although, the construction


industry faces different concerns than
I NDUSTRY 4.0 represents the fourth the manufacturing industry when it
comes to increasing productivity.
industrial revolution after the
mechanization, electrification and Often, construction projects are
computerization of production characterized by a high number of
environments (Kagermann, et al., participating companies with
2013). It focuses on the increasing interrelated processes occurring at
digitization and automation of the different stages and in different
manufacturing industry especially locations. Construction projects are
by means of digital value chains usually unique, time limited and
between products, machines require a high degree of
and operators. According to Wang customization.
(2018), Industry 4.0 will affect the
manufacturing industry in a similar Construction Supply Chains (CSCs)
way as the smartphone technology usually consist of Make-to-Order
did for the consumer world by (MTO) supply chains, where incoming
broad behavioral and social material converges at a site where
changes. the building is assembled. CSCs are
usually characterized by temporary
Industry 4.0 is also transforming the initiatives, fragmentation, instability
construction industry and its supply and high inefficiency.
50 IEEE ENGINEERING MANAGEMENT REVIEW, VOL. 46, NO. 3, THIRD QUARTER, SEPTEMBER 2018

A main CSC management objective execution. In the latter case, there is have been used to integrate data
is to plan and direct specific quantities additional effort for searching and from suppliers, carriers, and
of materials to the site where the final handling of components. contractors; allowing chain actors to
assembly takes place. According to share real-time information about
the type of material assembled, Early or late component delivery construction materials status (Gong
different supply chain configurations requires excessive buffers of and Azambuja, 2013). Cloud-based
can be considered: 1) Make-to-Stock components on-site and within collaboration integrates multiple
(MTS) for consumables like bolts, the supply chain, producing sources in a system and this reduces
2) Assemble-to-Order (ATO) for additional costs (Matt et al., 2014). the risk of out-of-date and incorrect
components such as doors and These wastes create construction information.
windows, 3) Make-to-Order (MTO) cost increases and budget
for cast-in-place concrete or overruns. Web services technology that
prefabricated panels and 4) Engineer- enables CSC partners to retrieve
to-Order (ETO) for highly customized EARLY INDUSTRY 4.0 up-to-date information about the
parts like design facades (Dallasega APPLICATIONS IN supply chain process (for example,
et al., 2018a). delivery of materials) to avoid delays
CONSTRUCTION SUPPLY CHAINS
and re-work also exists. Information
For ETO manufacturing companies in Industry 4.0 in the supply chain exchange among CSC partners is
the construction industry orders are produces high potential to solve some facilitated by using ontology-based
engineered, produced, and installed of the inefficiencies that cause cost web services (Das et al., 2015). They
on-site according to specific customer and delivery problems. present a distributed database
requirements (Rauch et al., 2018). architecture that allows data
Specific challenges of ETO Limited Industry 4.0 understanding in replication to improve system
companies are: 1) product the construction environment exists. reliability. Using CSC specific domain
complexity, 2) degree of customer Building Information Modeling (BIM) ontologies avoids data conflict and
product specificity, and 3) production is one of the major construction duplication.
and installation process complexity. industry digitization technologies. A
major advantage of BIM is enrichment M-internet, an Internet of Things and
In the ETO environment, activities of the digital building model providing mobile technology example, has
are partly performed on-site and a variety of information including time, been shown to improve material flow
therefore exposed to variability and cost, energy efficiency component and supply management, real-time
unplanned events, such as changing data, and field verified component on- information sharing, and
weather conditions, customer site installation data. Construction communication, coordination and
requirements and labor resources industry developments have targeted integration of CSC management.
(Dallasega and Rauch, 2017). It is the design and pre-construction Mobile terminal devices, like personal
difficult to foresee and forecast planning phase; there are few digital assistants (PDA), integrated
construction progress in this investigations on how BIM supports with global positioning systems
environment. This situation usually the construction execution (GPS) technology with RFID
requires long lead-times. It is difficult management process. technology, increase CSC and
to produce components on-demand on-site materials control (Shi et al.,
and deliver them just-in-time (JIT). Industry 4.0 concepts in the 2016).
manufacturing environment, such as
Demand-oriented production and Mobile Computing, Radio-Frequency Geographic Information System
delivery of components is a key to Identification (RFID), Cyber-Physical (GIS) have been used to
avoiding the following problems: 1) Systems, Internet of Things, Internet automatically track and localize
late deliveries that cause construction of Services, Cloud Computing, Big material throughout CSCs. Real-time
interruptions due to missing material; Data, Augmented Reality and Virtual information about the current location
and 2) early deliveries requiring on- Reality have not been fully exploited, of materials throughout the supply,
site component storage, which and have great potential, in the CSC shipping and construction process is
increases risk of component damage industry (Dallasega et al., 2018a). easily available (Majrouhi and
and costs. Both early and late Limbachiya, 2010).
deliveries create non-value adding Some Industry 4.0 concepts have
activities. In the first case, been applied to improve CSC GIS and BIM can jointly display the
rescheduling of tasks and crews is management (Dallasega et al. status of material throughout a supply
needed, hindering an efficient on-site (2018a). Cloud based platforms chain and where in a building a
INDUSTRY 4.0 FOSTERING CONSTRUCTION SUPPLY CHAIN MANAGEMENT: LESSONS LEARNED FROM ENGINEER-TO-ORDER SUPPLIERS 51

material is used. Both Industry 4.0 materials status throughout the BIM model and visualizing it in an
concepts can provide warning signals supply chain (for example, ordered, in intuitive way. How the Industry
for late deliveries. Moreover, the production or shipped) and the Foundation Classes (IFC) file format
synchronization of interfaces release of the needed material on- supports an exchange between
between GIS, BIM and mobile site. As a result, component design and construction execution
devices improves material as well as production on-demand and process information is also under
information flow among CSC partners transportation Just-in-Time (JIT) to investigation.
(Irizarry et al., 2013). BIM can be the construction site became
used to monitor CSCs. Data is possible. This situation eliminated LESSONS LEARNED FROM ETO
collected in a cloud monitoring wasteful intermediate storage; CSC COMPANIES AND
system and visualized using BIM. reducing lead times; a major OPPORTUNITIES FOR INDUSTRY
achievement for an ETO based 4.0 APPLICATIONS
RFID can be used to improve supplier.
dispatching, receiving and inventory Lessons learned from ETO
processes for technical trade and A company producing shower construction supplier companies
construction industries (Hinkka and cabinets developed a customized application of Industry 4.0
Ta€tila
€, 2013). Tasks related to service management platform that technologies are now presented.
identification and localization of runs on web-based tablets. The These lessons can be valuable
materials can be automated; reducing system allows for directly sending guidelines to managers who seek to
the probability of incorrectly identified important information from the implement Industry 4.0 capabilities in
or shipped components. RFID construction site to the company’s their supply chains. Figure 1
systems improve construction production facility. As a result shorter schematically summarizes some of
schedule performance and reduce delivery times and fewer orders of these major points.
dependency on expensive rework occurred, improving product 1) Trigger the supply chain based
intermediate storages. RFID quality. on construction progress goals
technology allows gathering (TRIGGER JIT):
information about the CSC process in Our research team currently
real time allowing for rapid response collaborates with a number of ETO The production process of first-tier
to unpredictable events. companies to investigate how the and second-tier suppliers should be
construction execution process can triggered according to meeting
be connected to BIM for improved construction goals. This requires a
CASE STUDIES scheduling and CSC monitoring. This detailed scheduling and reliable
We currently collaborate with different effort seeks data sharing from BIM monitoring of the tasks to performed
ETO supplier companies to optimize models for planning and scheduling on-site. Usually on-site personnel are
their processes using Industry 4.0 the execution process on-site. A able to predict the tasks to be
concepts. Some of these practices major Industry 4.0 research performed on-site not more than four
are outlined here. collaboration focuses on importing weeks ahead (according to our
construction progress data into the observations). Thus, there is a
An ETO building façade supplier uses
Google sheets to track in real-time
façade on-site installation progress.
Each day the crew leaders record the
completed tasks in specific
construction areas, the number of
installed components and the
required/used work amount in terms
of person-hours. Important key
performance indicator computation
occurs in real time each day. This
allows early problem identification
and timely improvement actions.

A web-enabled enterprise resource


planning (ERP) system was
developed allowing for visibility of Figure 1. Action points for fostering CSC management with Industry 4.0.
52 IEEE ENGINEERING MANAGEMENT REVIEW, VOL. 46, NO. 3, THIRD QUARTER, SEPTEMBER 2018

“window of predictability”, is the needed resources in terms of labor just-in-sequence rules should be
length of time for reliable prediction of and material. This situation means applied. In ETO supply chains the
tasks to be performed on-site; and that construction tasks have to be order flow should begin at
this window is usually a trigger. scheduled in detail and monitored in engineering for fabrication until
real-time; an important Industry 4.0 arriving on-site for installation. This
Two triggering strategies can be capability. A periodic forecast of requires that job orders be split into
utilized. required components on-site is small batches of work. By releasing
a) If the delivery time enters the performed. The work capacity on-site small work batches parallel process
window of predictability on-site, and within the supply chain is execution is possible. Parallel
the production start can be adjusted within a specific corridor of processing reduces overall lead-time
triggered directly; flexibility. As a practical example, and as such shortening delivery
b) If the delivery time does not enter consider working time increase or times. Lead-time reduction allows for
the window of predictability on- decrease by one day, which means staying within a window of
site, the production has to be working on a Saturday or stopping on predictability needed to trigger the
triggered in advance, according a Thursday. This decision supply chain, (see action point one).
to the construction schedule, and corresponds to a þ/- 20% capacity
6) Supply components directly to
buffered intermediately as semi- flexibility. If the construction
the place of demand (DIRECT
finished goods. As soon as the performance on-site increases or
SUPPLY)
construction site is ready for decreases, the delivery performance
installation, semi-finished of the supply chain should be
Project specific components should
components should be finalized increased or decreased. If the
be delivered directly to the place of
(for example final assembly, increase is more then the capacity
demand. If the primary or secondary
packaging) and delivered to the flexibility range, an escalation
demand of construction components
site for installation. strategy has to be implemented by
does not require prefabrication, they
the planner.
As a result, JIT-supplies to the should be delivered directly to the
construction site become possible; 4) Trigger the supply chain in one construction site. This process avoids
avoiding high levels of work-in- point (ONE POINT) wasteful intermediate storages
process stock. By triggering the throughout the supply chain.
To avoid problems such as material
supply chain according to actual Moreover, an uncoupling of the supply
delivery synchronization, the
construction progress intermediate process from manufacturing allows to
customer order should trigger the
buffers are not created or overfilled. parallelize processes and again to
process chain only in one point. The
reduce the overall delivery time.
2) Supply material to the site order penetration point (OPP) defines
according to customer demand the point in a manufacturing process 7) Move the OPP upstream the
(PULL from site) where customer neutral production supply chain (OPP UPSTREAM)
orders transition to customer related
Based on the pace of the scheduled production orders (Schweizer, 2013). The OPP should be moved upstream
tasks on-site, their primary-, The placement of the OPP depends the supply chain (first-tier, second-tier
secondary- and tertiary demand on the specific market interaction and so on), until the overall delivery
should be defined. This activity can strategy. In MTS supply chains it is time enters the window of
be completed by coupling placed at the inventory of finished predictability on-site. This process
construction schedules with bill of goods, in ATO at the final assembly allows for agile reaction to on-site
materials (BOM) of first- and second process, in MTO at the first changes; preventing to build up
tier suppliers. A common strategy is production process, and in ETO at the excessive amounts of buffer or
to increase the labor resources on- product engineering process. delaying construction.
site if construction has to be
expedited. As such, more tasks have 5) Let the customer order flow
A practical implementation requires
to be scheduled and completed, and (FLOW)
reorganizing processes; preferably
this leads automatically to an Downstream of the OPP, the order through lean management principles.
increased request of material. should flow in a continuous way to the Industry 4.0 concepts can support
3) Follow the customer demand customer. This means that and foster the reorganization of
(SELF-REGULATION) intermediate interruptions and buffers processes. Currently, we are
should be avoided. In cases where collaborating with ETO companies to
The customer process, in this case this is not possible, work-in-process develop a tool based on mobile
the construction site, controls the levels should be limited and computing and connected with BIM
INDUSTRY 4.0 FOSTERING CONSTRUCTION SUPPLY CHAIN MANAGEMENT: LESSONS LEARNED FROM ENGINEER-TO-ORDER SUPPLIERS 53

that implements this action point new technology (like BIM or monitoring of construction progress,
process model. M-internet), with existing technology requiring flexible transportation
(like ERP systems). All these costs schedules and short delivery times.
ISSUES AND LIMITATIONS may increase the time new Reliable planning and measurement
technology pays back and influence of construction progress is a
When following the seven guidelines the decision whether or not to invest prerequisite for economic and
proposed here, managers should be in Industry 4.0. ecological production and delivery of
aware of the following issues and components.
limitations.
FURTHER CONSIDERATIONS AND Defining sustainable supply cycles
The tradeoff between low levels of CONCLUSION in the construction, infrastructure
stock throughout the supply chain,
Usually construction projects are and plant building industry are all
reached by JIT deliveries, and the
unique, time limited and require a needed. Different intermodal freight
potential increase of deliveries can
high degree of customization. ETO transport systems with the final aim to
raise transportation costs and
construction supplier companies reduce CO2 emissions and foster
environmental impact (CO2
consist of off-site and on-site environmentally friendly freight
emissions).
production processes. transports will be required. Questions
Similar to most traditional mature Construction sites are usually on what extent a delivery of
industries, there is an adverse cultural characterized by high variability and construction components can be
attitude within the construction unpredictability. This characteristic completed by rail, using distribution
industry to accept new processes and makes the synchronization of supply centers and supplying the last mile
technologies. Here, the stepwise chains to the construction progress by alternative energy vehicles with
qualification of employees should not difficult. As a result, expensive environmental-friendly fuels needs
be forgotten. In our experience, when construction stops due to missing evaluation. Consideration of new
implementing innovative tools in materials and other types of waste distribution center designs, Industry
practice, a good course of action is to like searching, excessive moving and 4.0 technology and construction
assure that the reorganization of handling of material are frequent in site locations require further
processes goes hand-in-hand with CSCs. developments.
the introduction of new technology.
This assures that the company is Industry 4.0 concepts seem to be How to further increase flexibility of
ready to adopt the new technology. very promising in addressing the the supply chain through: a) space
As a practical example, providing various ETO construction supply saving at the place of consumption
foremen with assistants having chain deficiencies. (on-site) and b) increasing supply
knowledge of information technology chain reaction to meet high
may be necessary to build It has been shown that Industry 4.0 variability of construction processes
organizational expertise and concepts can help address these is still needed. Further technological
acceptance. This approach allows for deficiencies and synchronize the forecasting, maturity mapping,
shortening the initial learning phase supply chain to construction requirement analyses and
and at the same time it assures that progress. Seven action points are specification of construction
the system is fed with valuable data; proposed as guidelines for managers logistics IT-platform are all needed.
and management is strongly to improve CSC processes. These These Industry 4.0 platforms need to
supportive by supply needed processes can be supported through support configuration and plans for
resources. Industry 4.0 technologies and CSC. Economic as well as
systems. ecological key performance
Managers should not forget the costs indicators need further development
that may incur due to the Future issues include more broadly and monitoring.
reorganization of processes. Initial encompassing sustainability aspects,
increased effort to handle new beyond the business aspects. CSCs Further case studies to evaluate the
technology and needed qualification have not been very efficient from an feasibility of these concepts and the
to increase the acceptance degree of ecological perspective. For example, Industry 4.0 tools as they evolve,
employees; basic change a significant delivery and along with the necessary incentives
management concerns. transportation in the construction and support from public policy, for a
industry is been performed by trucks long term technological road mapping
Investment decisions should also (Akan et al., 2017). This partice could can greatly benefit the CSC and other
consider the compatibility degree of be explained by weak planning and industries.
54 IEEE ENGINEERING MANAGEMENT REVIEW, VOL. 46, NO. 3, THIRD QUARTER, SEPTEMBER 2018

ACKNOWLEDGMENT This paper is part of research 2020 research and innovation


activities in the project “SME program under the Marie
The author would like to thank the
4.0 - Industry 4.0 for SMEs”. The Sk»odowska-Curie grant agreement
Editor-in-Chief Prof. J. Sarkis for his
project has received funding from No. 734713.
kind invitation and comments for the
the European Union’s Horizon
development of this paper.

REFERENCES
Akan, M. O. € A., Dhavale, D. G., Sarkis, J. “Greenhouse gas emissions in the
construction industry: An analysis and evaluation of a concrete supply chain,”
Journal of Cleaner Production, vol. 167, pp. 1195–1207, 2017.
Choi, T. M. “A system of systems approach for global supply chain management
in the big data era,” IEEE Engineering Management Review, vol. 46, no. 1,
First Quarter, March, pp. 91–97, 2018.
Dallasega, P. and Rauch, E. “Sustainable construction supply chains through
synchronized production planning and control in engineer-to-order enterprises,”
Sustainability, vol. 9, no. 10, pp. 1–25, 2017.
Dallasega, P., Rauch, E., Linder, C. “Industry 4.0 as an enabler of proximity for
construction supply chains: A systematic literature review,” Computers in
Industry, vol. 99, pp. 205–225, 2018.
Dallasega, P., Rauch, E., Frosolini, M. “A lean approach for real-time planning and
monitoring in engineer-to-order construction projects,” Buildings, vol. 8, no. 38,
pp. 1–22, 2018.
Das, M., Cheng, J. C., Law, K. H. “An ontology-based web service framework for
construction supply chain collaboration and management,” Engineering
Construction and Architectural Management, vol. 22, pp. 551–572, 2015.
Gong, J. and Azambuja, M. “Visualizing construction supply chains with google
cloud computing tools,” in Proceeding of International Conference on Sustainable
Design, Engineering, and Construction, pp. 671–678, 2013.
Hinkka, V. and Ta €tila
€, J. “RFID tracking implementation model for the technical trade
and construction supply chains,” Automation in Construction, vol. 35, pp. 405–
414, 2013.
Irizarry, J., Karan, E. P., Jalaei, F. “Integrating BIM and GIS to improve the visual
monitoring of construction supply chain management,” Automation in
Construction, vol. 31, pp. 241–254, 2013.
Kagermann, H., Helbig, J., Hellinger, A., Wahlster, W. Recommendations for
implementing the strategic initiative INDUSTRIE 4.0: Securing the future of
german manufacturing industry. Munich, Germany: Acatech, 2013.
Li, J. and Yang, H. “A research on development of construction industrialization
based on BIM technology under the background of Industry 4.0,” in Proceeding of
MATEC Web of Conferences, vol. 100, pp. 1–8, 2017.
Majrouhi, J. S. and Limbachiya, M. C. “Integrated advance data storage technology
for effective construction logistics management,” in Proceedings of the 27th
International Symposium on Automation and Robotics in Construction, pp. 89–
98, 2010.
Matt, D. T., Dallasega, P., Rauch, E. “Synchronization of the manufacturing process
and on-site installation in ETO companies,” Procedia CIRP, vol. 17, pp. 457–462,
2014.
Rauch, E., Dallasega, P., Matt, D. T. “Complexity reduction in engineer-to-order
industry through real-time capable production planning and control,” Production
Engineering, vol. 12, no. 3/4, pp. 341–352, 2018.
Schweizer, W. Wertstrom Engineering—Typen- und variantenreiche Produktion.
Berlin, Germany: epubli GmbH, 2013.
INDUSTRY 4.0 FOSTERING CONSTRUCTION SUPPLY CHAIN MANAGEMENT: LESSONS LEARNED FROM ENGINEER-TO-ORDER SUPPLIERS 55

Shi, Q., Ding, X., Zuo, J., Zillante, G. “Mobile internet based construction supply
chain management: A critical review,” Automation in Construction, vol. 72,
pp. 143–154, 2016.
Wang, D. “Building value in a world of technological change: Data analytics
and industry 4.0,” IEEE Engineering Management Review, vol. 46, no. 1,
First Quarter, March, pp. 32–33, 2018.

Patrick Dallasega received the degree(s) from the Free University of Bolzano, Bolzano, Italy,
the Polytechnic University of Turin, Turin, Italy, and the Ph.D. degree from the University of
Stuttgart, Stuttgart, Germany. He is an Assistant Professor of project management and industrial
plants design with the Faculty of Science and Technology, the Free University of Bolzano. He
was a Visiting Scholar with the Excellence Center in Logistics and Supply Chain Management
Chiang Mai University, Chiang Mai, Thailand, and the Worcester Polytechnic Institute in
Massachusetts, Worcester, MA, USA. His main research interests are supply chain
management, Industry 4.0, lean construction, lean manufacturing and production planning, and
control in MTO and ETO enterprises.

You might also like