Professional Documents
Culture Documents
PS.17
any times I have been asked to review a sched- Additional codes can be added at any time directly into the “col-
PS.17.1
2007 AACE International Transactions
(resource) at the top and a graph selected by resource on the • Use VIEW to enter, change and review allocations
bottom. instantaneously.
The resultant view should look like Figure 1. • Use results to commence dialogue with the schedule
Now, by reviewing the task descriptions, the task durations originator.
and the number of crews assigned, educated changes can be
made to the crew assignments. This will create a more realistic
graph. Any changes can be seen instantaneously on the graph USING THIS METHOD
below, WITH MICROSOFT PROJECT (3000)
The final step is to present this information the schedule orig-
inator. (Please note that so far no logic or task duration has been As with any software application or version, the problem is
changed.) The questions for the originator are: finding out how to accomplish the same results you had with the
initial software (P3) using the features of the new software (MS
• Does this curve reflect the originators plan? Project). There is some give and take; however, the time need-
a. Accurately? ed to produce meaningful results is about the same.
b. Somewhat? As with P3, the process begins with copying the submittal file
c. Not at all? into a test file.
In MS Project, go to the “resource sheet” view. Enter each
• If not at all, Why? resource crew that is to be monitored.
a. This curve is directly proportional to the layout of Then set up a “table” with the columnar information needed.
the schedule. (Remember at the beginning, it was This should include; ID, NAME, DURATION, START, and
noted that the schedule planner should lay out the FINISH.
schedule with resources considered, whether or not Name this table: artificial resource loading” (or some other
resource loading was required by contract specifica- unique description).
tion.) Next, set up a “view” with the same name. The view will
include; the bar chart screen (usually the Gantt), the table (with
• Can the originator fine tune the submitted schedule by the same name), “no group”, and “all tasks.” (Filtering is option-
using this method? al.)
Eliminate summary tasks by removing the “check” on the
• If so, supply the method, not the data, so the originator is view screen of the “OPTIONS” menu.
responsible for the results. Sorting the file by “NAME” (Important: do not keep the “out-
line structure”) will give the data ready for resource loading,
Points to remember for using this method with P3: The drop down menu in the resource field will give the selec-
tions available. Assign the correct resource and use the “fill
• Use TASK coding to set up the global resource ADD. down” feature of MS Project to assign the same resource to the
• Use CREWS as resource unit. other similar tasks.
PS.17.2
2007 AACE International Transactions
After completing the resource assignments, go to the resource a. This curve is directly proportional to the layout of
graph view and select the resource to review. the schedule.
Adjusting the resource allocation is a two step process in MS
Project. The addition or subtraction of crews is done by “split- • Can the originator fine tune the submitted schedule by
ting” the screen onto the bar chart at the top and the resource using this method?
table at the bottom. By adjusting the “percentage units” in the
table, you can add or subtracts crews in one half ½ intervals. • If so, supply the method, not the data, so the originator is
While there are other methods such as the “Task Usage” view responsible for the results.
or the “resource usage” view which can be used, the “split
screen method” is considered more efficient.
You can then switch the bottom screen to the resource graph
view to see the results.
Note that the P3 (figure 1) and MS Project (figure 2) views
are very similar.
Note: Before discussing the results with the schedule origi- Albert Joseph Kuhn PSP
nator, you may want to export your resource curve informa- Principal
tion to Excel to use the graphic options of that program. Kuhn Consulting
Using the same criteria as with P3 above, discuss the results 149 Stonegate Lane
with the schedule originator and attempt to get their input. Hanover, MA 02339, US
The questions for the originator are: Phone: +1.781.826.9517
Email: al.kuhn@kuhnconsult.com
• Does this curve reflect the originators plan?
a. Accurately?
b. Somewhat?
c. Not at all?
PS.17.3