You are on page 1of 7

Issue 93 - January 2022

Insight provides practical information on topical


issues affecting the building, engineering
and energy sectors.

Inside this issue


Contractor claims for
prolongation costs:
a comprehensive guide

www.fenwickelliott.com
01 Insight Issue 93

Contractor claims for prolongation costs:


a comprehensive guide
Claims for prolongation costs are bread and butter for those working in construction disputes.
Notwithstanding this, the basic rules governing if prolongation costs are recoverable, and how to prove the
quantum of those costs, are all too often ignored.1 Likewise, the terminology used in such claims is often
used without a proper understanding of what it means.

In this Insight, we provide a comprehensive guide to prolongation costs looking at the basic law governing
when they can be claimed, the rules under key domestic standard construction contracts and then deep
diving into specific categories of prolongation costs.

So, what are prolongation costs? When claiming prolongation costs, the It is also important to remember that
Contractor will generally need to the analysis necessary to establish a
demonstrate that it has actually Contractor’s entitlement to an
Where a construction project suffers
incurred costs/losses because of delay, extension of time is different to that
from delays, those delays cost money
and that it would not have incurred needed to establish entitlement to
for all involved. The Employer does not
those costs/losses but for the Employer prolongation costs. The differences
have use of its building on the date
Risk Event. between extension of time claims and
originally intended, and the Contractor
prolongation costs claims were
incurs time-related costs. Where
explained in Costain Limited v Charles
critical delay to the project is the Extensions of time and prolongation
Haswell & Partners Limited5:
responsibility of the Contractor, the costs
financial remedy for the Employer is
liquidated (or general) damages. “… When an extension of time of the
Prolongation costs are often
Where the critical delay to the Works is project completion date is claimed,
considered to be the financial element
the Employer’s risk, however, the the contractor needs to establish that
of a Contractor delay claim. It is
Contractor may be entitled to a delay to an activity on the critical
sometimes assumed that, where a
prolongation costs (which are also path has occurred of a certain number
Contractor is granted an extension of
known as loss and expense). of days or weeks and that that delay
time, prolongation costs should
has in fact pushed out the completion
automatically flow. This is incorrect as:
date at the end of the project by a
Prolongation costs are those time-
given number of days or weeks, after
related costs incurred by the
“… although prolongation costs are taking account of any mitigation or
Contractor as a result of critical delay
often seen as the financial side of a acceleration measures. If the
to the Works (and therefore an
“delay claim”, there is no automatic contractor establishes those facts, he
extension of the contract period) for
entitlement to loss and expense or is entitled to an extension of time for
which the Contractor is not
damages even if a right to an completion of the whole project
responsible. Keating on Construction
extension of time is established.” 4 including, of course, all those activities
Contracts defines prolongation costs
[Emphasis added] which were not in fact delayed by the
as:
delaying events at all, i.e. they were
not on the critical path.
This is because where there are other
“… costs and losses incurred as a result
non-critical Contractor delays on the
of delays to the activity in question or
project, the scale of those delays may But a claim for damages on account
the works as a whole which have led to
mean that the Employer Risk Event of delays to construction work is rather
critical delay to the contract
doesn’t cause additional costs to be different. There, in order to recover
completion date.” 2
incurred for the full period of the substantial damages, the contractor
extension of time awarded to the needs to show what losses he has
Prolongation costs are intended to Contractor. The “excusable delay”, in incurred as a result of the prolongation
compensate the Contractor for its respect of which the Contractor is of the activity in question. Those losses
time-related costs which it would not entitled to an extension of time, may will include the increased and
have incurred but for the Employer-risk be different to the “compensable additional costs of carrying out the
delay event. The SCL Delay & delay” in respect of which the delayed activity itself as well as the
Disruption Protocol puts it like this: Contractor is entitled to its additional costs caused to other site
prolongation costs. activities as a result of the delaying
event. But the contractor will not
“The objective is to put the Contractor
recover the general site overheads of
in the same financial position it would In other words, time doesn’t always
have been if the Employer Risk Event equal money.
had not occurred.” 3
02 Insight Issue 93

carrying out all the activities on site as Further, task-related costs, which are remains debate as to whether this
a matter of course unless he can those costs that would have been notification requirement is a condition
establish that the delaying event to incurred in any event to complete the precedent to the Contractor’s
one activity in fact impacted on all Works (and which are not the result of entitlement to prolongation costs. As
the other site activities. Simply the increased duration of the such, the golden rule must be to
because the delaying event itself is on Contractor’s Works), are not notify prolongation costs claims
the critical path does not mean that recoverable as prolongation costs. without delay.
in point of fact it impacted on any
other site activity save for those
What do the standard form As well as notifying the claim, the
immediately following and dependent
contracts provide in respect of Contractor is obliged to provide “its
upon the activities in question.” 6
prolongation costs? initial assessment of the loss and/or
[Emphasis added]
expense incurred and any further
amounts likely to be incurred, together
JCT 2016
Claiming prolongation costs during with such information as is reasonably
the project necessary to enable the Employer to
The JCT suite of contracts provides ascertain the loss and/or expense
that, where the Contractor “incurs or incurred.” That information should be
When claiming prolongation costs,
is likely to incur any direct loss and/or provided with the Contractor’s original
the Contractor must ensure that its
expense” as a result of the regular notification “or as soon as reasonably
claim includes sufficient information
progress of the Works being practicable.” 14
to enable the amount of its incurred
“materially affected by any Relevant
loss and expense to be ascertained.
Matter”, the Contractor will be
Detailed submissions with The Contractor is also under an
entitled to be reimbursed for that loss
comprehensive supporting obligation to provide monthly updates
and/or expense.9 The event giving rise
information should be provided by the (to its initial assessment and
to the delay must, therefore, be a
Contractor, if possible. However, per information) to the Employer, “in such
Relevant Matter in order to give rise to
the TCC’s judgment in Walter Lilly & form and manner as the Employer
an entitlement on the part of the
Company Limited v Giles Patrick Cyril may reasonably require.” The
Contractor to its “direct loss and
Mackay [2012] EWHC 1773 (TCC), Contractor must do so “until all
expense.”
there is no requirement for the information reasonably necessary to
Contractor to provide “every allow ascertainment of the total
conceivable detail”, and it must be As held by the Court of Appeal in F.G. amount of such loss and expense has
borne in mind that the “Architect and Minter v WHTSO10, “direct loss and/or been supplied.” 15 It is obviously
the Quantity Surveyor are not expense” is loss and expense which sensible for both parties to engage in
strangers to the project in considering arises naturally and in the ordinary discussions as to the format of any
what needs to be provided to them.” 7 course of things. It follows that “the information required to evidence
sole question which arises in relation prolongation costs especially when
to any head of claim put forward by a delays are likely to be ongoing for a
Prolongation costs claimed by the
Contractor is whether such a claim number of months.
Contractor must be linked to the
properly falls within the first limb of
alleged Employer delay. Global claims
Hadley v Baxendale so that it may be
which assume a link between costs NEC4
said to arise naturally and in the
and the Employer risk event should be
ordinary course of things.” 11
avoided. The Contractor must
Under the NEC4 suite of contracts,
demonstrate that that overspend is
where the project has been delayed by
the direct result of the Employer risk A Contractor’s prolongation costs
the Client,16 the Contractor can claim
delay event. As stated in Walter Lilly: claim under the JCT form must be for
for additional time and money by
its actual losses and expenditure
submitting a claim for a
incurred as a direct result of the
“Ultimately, claims by contractors for compensation event. Compensation
Relevant Matter. Interest and
delay or disruption related loss and events are events which are not the
financing charges on direct loss and
expense must be proved as a matter fault of the Contractor and which
expense can be included by the
of fact. Thus, the Contractor has to have the effect of changing the cost
Contractor in its claim.12
demonstrate on a balance of of the work and/or the time needed to
probabilities that, first, events complete it. If a delay has occurred as
occurred which entitle it to loss and The JCT suite of contracts also provide a result of a compensation event, the
expense, secondly, that those events that the Contractor “shall notify the Contractor may be entitled to make
caused delay and/or disruption and Architect/Contract Administrator as changes to the prices, key dates, and/
thirdly that such delay or disruption soon as the likely effect of a Relevant or the completion date.
caused it to incur loss and/or expense Matter on regular progress …
(or loss and damage as the case may becomes (or should have become)
be).” 8 reasonably apparent to him.” 13 There
03 Insight Issue 93

In contrast to the JCT suite of instructions, is not only relevant Underlining the importance of keeping
contracts, in which time (Relevant evidence but clearly the best evidence the above detailed records, the
Events) and money (Relevant Matters) to assist the court in calculating the Contractor is also obliged under
are assessed separately, time and cost “compensation” to which the Option C to permit the Project
impacts are assessed together under consultant is entitled … Manager to inspect those records.23
the NEC4 compensation event regime.
This is all too often forgotten!
… why should I shut my eyes and Specific types of prolongation costs
grope in the dark when the material is
Notification and Assessment available to show what work they
Prolongation costs can be divided into
actually did and how much it cost
two broad categories. These are:
them?” [Emphasis added]
The NEC4 contains a time bar for
notification by the Contractor of a
(1) “on-site overheads” (sometimes
compensation event. The Contractor What is Defined Cost?
referred to as “preliminaries”); and
must notify the Project Manager of a
compensation event “within eight
Defined Cost is used to assess
weeks of becoming aware that the (2) “off-site (or “head office”)
compensation events. For Options A
event has happened.” 17 This is a overheads.”
and B, the Defined Cost is as stated in
condition precedent to the
the Short Schedule of Cost
Contractor’s entitlement to time and
Components (SSCC). For Options C, But, what do we mean when we talk
money, so the Contractor must
D, and E, it is as stated in the Schedule about “on-site” and “off-site”
comply with this requirement. A failure
of Cost Components (SCC). overheads?
to issue a notice by this deadline may
well result in any entitlement to
additional time and/or money being The SSCC and SCC set out the rules on On-site preliminaries / overheads
lost. recoverable costs and relevant rates,
including in respect of People,
On-site overheads are the
Equipment, and Plant and Materials.
The impact of compensation events is Contractor’s direct costs associated
Given that NEC4 core clause 52.1
intended to be assessed prospectively with the performance of its Works on
provides that “All the Contractor’s
based on forecasts, as evidenced by site.24 These include labour costs,
costs which are not included in the
core clause 63.1: plant and equipment costs, and
Defined Cost are treated as included
“preliminaries”:
in the Fee”,21 it is important for the
“The change to the Prices is assessed Contractor to check what is included
as the effect of the compensation in the SSCC/SCC – and what is (i) Labour costs
event upon deemed to be included in the Fee –
before submitting its compensation
event claim. Where, as a direct consequence of an
• The actual Defined Cost of the Employer-risk delay event, the
work done by the dividing date,18 Contractor’s labour resources have
• The forecast Defined Cost of the Record-keeping been required to remain on site for
work not done by the dividing longer than originally anticipated (or
date, and the Contractor has used additional
It is vital that the Contractor keeps
labour resources), the Contractor is
• The resulting fee.” 19 detailed records demonstrating the
entitled to recover its costs incurred in
Defined Costs (in respect of People,
respect of that extended or additional
Equipment, and Plant and Materials
However, all too often, compensation labour.
etc) which it has incurred. Indeed,
events end up being assessed
under Option C, the Contractor must
retrospectively. It is essential,
keep the following records: The Contractor must demonstrate
therefore, that the Contractor keeps
that the extended or additional labour
detailed and comprehensive records
• Accounts of payment of Defined was the direct result of the Employer-
demonstrating its costs. As was
Cost; risk delay event, and that the original
stated by Deeny J in Northern Ireland
labour resource levels and durations
Housing Executive v Healthy Buildings • Proof that the payments have provided for in its tender were realistic
(Ireland) Ltd20: been made; and reasonable (such that it should be
• Communications about and entitled to recover the extended/
“Evidence from time sheets and other assessments of compensation additional labour costs). In
material, of what the consultant events for Subcontractors; and circumstances where the Contractor’s
actually did in that period, particularly • Other records as stated in the labour resource is idle, the Contractor
with reference to the change in Scope.22 will be expected to mitigate its losses
04 Insight Issue 93

by redeploying that resource to other, effect of the Employer Risk Event was (ii) Lost contribution to head office
productive work. They will not be felt, not by reference to the extended overheads
entitled to the costs of idle labour if period at the end of the contract.” 30
they don’t take steps to mitigate their
Overheads are normally recovered
losses.25
Head office (off-site) overheads from the income of the Contractor’s
business as a whole. Where a
(ii) Plant and equipment particular project is delayed, there
Head office, or off-site, overheads are
may then be a reduction in the
the costs incurred by the Contractor
Contractor’s income from that
If the Contractor has hired plant and as part of its normal business
particular project. The Contractor’s
equipment which has sat idle as a operations. Head office overheads
overall turnover reduces, whilst its
result of the Employer-risk delay event, include the costs of the Contractor’s
expenditure on overheads – which it
then the Contactor may be entitled to head office staff, head office utilities
cannot avoid or reduce – continues.
recover the hire charges which it has (electricity, water, etc.), lease
However, had the particular project
incurred in respect of that plant and payments on the head office, and
not been delayed as a result of the
machinery during the idle period.26 insurance.31 Head office overheads
Employer-risk delay event, the
are distinguishable from the
Contractor would have had the
Contractor’s on-site overheads
Alternatively, if the plant and opportunity to deploy its labour on
incurred on the project.
equipment is owned by the another project. This would have had
Contractor, the Contractor may be the effect of contributing to the
able to recover costs in respect of the Where the Contractor’s works are Contractor’s overheads during the
loss of opportunity to hire out the delayed as a direct result of an period of overrun.34
plant to others during the period of Employer-risk delay event, the
delay.27 If the Contractor cannot Contractor may be entitled to recover
As was stated in JF Finnegan Ltd v
demonstrate such a loss of its head office overheads attributable
Sheffield City Council35:
opportunity, then it may still be able to that delay.32 There are two
to recover depreciation and categories of head office overhead
maintenance costs in respect of the claim: “It is generally accepted that, on
plant and equipment. principle, a contractor who is delayed
in completing a contract due to the
(i) Increased head office overheads
default of his employer, may properly
(iii) “Preliminaries”
have a claim for head office or off-site
Where particular head office costs of overheads during the period of delay,
These are the Contractor’s costs of the Contractor have increased as a on the basis that the work-force, but
maintaining its site establishment, result of the Employer-risk delay event, for the delay, might have had the
and include fencing and hoarding for the Contractor is entitled to recover opportunity of being employed on
the site, cabins or site huts, and these additional costs. One example another contract which would have
utilities.28 Where the project duration of such a cost is the cost of additional had the effect of funding the
has been extended as a result of an staff recruited by the Contractor overheads during the overrun period.”
Employer-risk delay event, these because the project was in difficulties.
time-related preliminaries may
In order to be successful in a claim for
increase. The Contractor is entitled to
When claiming for increased head lost contribution to overheads,
recover its additional costs in respect
office overheads, the Contractor will however, the Contractor will need to
of these extended preliminaries.
need to demonstrate cause and establish that other work was
However, in order to do so, it will need
effect. In other words, they need to available which it would have secured
to prove its actual additional costs
show that, as a direct result of the but for the delay. The Contractor
incurred as a result of the
Employer-risk delay event, the might do this by demonstrating that
prolongation.
Contractor had to (for example) it declined invitations to tender
recruit the additional staff to deal because its resources were tied up on
Costs should be calculated by with the project, and that its the delayed project (and so it had
reference to the period of delay rather increased overheads were therefore insufficient capacity to take on the
than the period of overrun at the end incurred (necessarily) as a direct result new work), or by demonstrating a
of the project.29 As explained in the of the Employer-risk delay event. reduction in its turnover (by reference
SCL Delay and Disruption Protocol: to its accounts).36
Claims for increased head office
“Once it is established that overheads are relatively unusual
compensation for prolongation is due, compared to claims for lost
the evaluation of the sum due is made contributions to head office
by reference to the period when the overheads.33
05 Insight Issue 93

Loss of profit Crucially, these formulae do not in 4. The Contractor should seek to
themselves prove the Contractor’s establish its actual costs and
losses. The formulae are only of losses incurred. Where it cannot
A further category of cost/loss which
assistance in quantifying the do so for its off-site overhead and
can be included in a Contractor’s
Contractor’s losses where the profit losses, formulae can be
prolongation claim, and which is often
Contractor has proved causation, i.e. used – but this should be done
categorised alongside “off-site
that it has suffered loss as a result of with caution. Formulae provide an
overheads”, is loss of profit. It is open
the prolonging Employer-risk delay approximation of the Contractor’s
to the Contractor to claim a loss of
event. As was stated in Alfred losses, rather than a calculation
profit arising from its reduced turnover
McAlpine Homes North Ltd v Property of its actual losses. If the
as a result of the delayed project.
and Land Contractors Ltd (1995) 76 Contractor is able to provide
B.L.R.: better proof of its actual losses
As with a claim for lost contribution to but instead chooses to use a
head office overheads, the Contractor formula, it risks having its claim
“… such formulae are likely only to be
will need to establish that it was for loss of off-site overheads and
of value if the event causing delay is
unable to tender for, and work on, profit rejected by the courts. The
(or has the characteristics of) a
other projects as a result of the delays Contractor should also bear in
breach of contract …”
on the particular project. The mind that formulae assist only in
Contractor should, therefore, keep quantifying losses – they do not
detailed records of all tender Practical tips for the Contractor prove causation.
opportunities it has received and been preparing a prolongation claim
forced to decline. As was noted in
For Employers seeking to resist such
Walter Lilly:
For a Contractor seeking to advance a claims, a failure to follow the rules set
claim for prolongation costs, the out above makes life much easier.
“… During that period, WLC had to following golden rules should be
and did decline a number of tendering obeyed:
opportunities: that was not said
vaguely, or in a vacuum of support: Claire King & Matthew Simson
1. The rules of the contract must Fenwick Elliott
the opportunities received and
be followed! As discussed above, 5 January 2022
declined were precisely detailed on a
the JCT and NEC standard forms
comprehensive schedule …” 37
have different requirements for
the claiming of time-related
The Contractor will also need to show, prolongation costs. The
on the balance of probabilities, that Contractor must ensure that it
“at the time of the delay, it could have complies with the requirements of
used the lost turnover profitably.” 38 its particular contract when
Contemporaneous evidence as to preparing and submitting its
these lost opportunities is therefore claim.
key.
2. Causation must be established.
Formulae for calculating loss of A global-type claim which simply
off-site overheads and profit assumes that the Contractor’s
overspend results from Employer
delays will not be successful. The
There are three alternative formulae
Contractor must prove (on the
which can be used to calculate claims
balance of probabilities) that the
for loss of off-site overheads and
Employer-risk delay event
profit. These are the Hudson, Emden,
occurred, it caused delay to the
and Eichleay formulae.39 These
Contractor, and the Contractor
formulae are not assessments of the
suffered loss and expense as a
Contractor’s actual costs, but instead
direct result.
produce an approximation of the
Contractor’s losses. Whilst these
formulae can be used where 3. Evidence is key. It is essential
necessary, therefore,40 if the that comprehensive
Contractor is able to provide better contemporaneous records (both
proof of its actual losses incurred, it in respect of causation and
should do so.41 quantum) are kept and provided
by the Contractor with its claim
– “records, records, records.”
06 Insight Issue 93

Footnotes

1. By Claire King and Matthew Simson. 18. For compensation events other than 40. See Walter Lilly & Company Limited v
With thanks to Sanjay Patel from 4 those arising from a Project Manager’s Giles Patrick Cyril Mackay [2012] EWHC
Pump Court for his input into our instruction, notification, issuing of a 1773 (TCC) at 543(c) – “The use of a
Fenwick Elliott webinar on this topic certificate, or changing of an earlier formula, such as Emden or Hudson, is a
which can be downloaded at https:// decision, the dividing date is the date of legitimate and indeed helpful way of
www.fenwickelliott.com/research- notification of the compensation event. ascertaining, on the balance of
insight/webinars-podcasts/ 19. NEC4 Engineering & Construction probabilities, what that return can be
prolongation-costs-construction- Contract, clause 63.1. calculated to be.”
projects. 41. See Keating on Construction Contracts,
20. [2017] NIQB 43.
2. Keating on Construction Contracts, 11th 11th Ed., para. 9.055 and Tate & Lyle v
21. NEC4 Engineering & Construction
Ed., para. 9-046. GLC [1982] 1 W.L.R. 149 at 152.
Contract, clause 52.1.
3. Society of Construction Law Delay and
22. NEC4 Engineering & Construction
Disruption Protocol, 2nd Ed (February
Contract, Option C, clause 52.2.
2017), “Core Principles”, para. 20.
23. NEC4 Engineering & Construction
4. Keating on Construction Contracts, 11th
Contract, Option C, clause 52.3.
Ed., para. 9-048.
24. Construction Law, 3rd Ed., Julian Bailey,
5. [2009] EWHC 3140 (TCC).
Vol. II, para. 11.139.
6. Costain Limited v Charles Haswell &
25. Construction Law, 3rd Ed., Julian Bailey,
Partners Limited [2009] EWHC 3140
Vol. II, para. 11.140.
(TCC) at 183-184.
26. Shore & Horwitz Construction Co Ltd v
7. Walter Lilly & Company Limited v Giles
Franki of Canada Ltd [1964] S.C.R. 589
Patrick Cyril Mackay [2012] EWHC 1773
(Canada SC).
(TCC) at 467.
27. Alfred McAlpine Homes North Ltd v
8. Walter Lilly & Company Limited v Giles
Property and Land Contractors Ltd
Patrick Cyril Mackay [2012] EWHC 1773
(1995) 76 B.L.R. 59.
(TCC) at 486.
28. Construction Law, 3rd Ed., Julian Bailey,
9. Standard Building Contract 2016 clauses
Vol. II, para. 11.145.
4.19.1 (Without Quantities) / 4.20.1 (With
Quantities / With Approximate 29. Keating on Construction Contracts, 11th
Quantities); and Design & Build Ed., para. 9.050; Ascon Contracting Ltd
Contract 2016 clause 4.19.1. v Alfred McAlpine Construction Isle of
Man Ltd (1999) 66 Con. L.R. 119 (TCC) at
10. (1980) 13 B.L.R. 1 CA.
43.
11. Keating on Construction Contracts,
30. Society of Construction Law Delay and
10th Ed., para. 20-353. Importantly, the
Disruption Protocol, 2nd Ed (February
use by the Contractor of formulae (such
2017), “Core Principles”, para. 22.
as Hudson and Emden) does not
detract from this principle. 31. Construction Law, 3rd Ed., Julian Bailey,
Vol. II, para. 11.146.
12. These were held to be recoverable in
F.G. Minter v WHTSO (1980) 13 B.L.R. 1 32. Construction Law, 3rd Ed., Julian Bailey,
CA. Vol. II, para. 11.146.
13. Standard Building Contract 2016 clauses 33. Keating on Construction Contracts, 11th
4.20.1 (Without Quantities) / 4.21.1 Ed., para. 9.052.
(With Quantities / With Approximate 34. Keating on Construction Contracts, 11th
Quantities); and Design & Build Ed., para. 9.053.
Contract 2016 clause 4.20.1. 35. (1988) 43 B.L.R. 124.
14. Standard Building Contract 2016 clauses 36. Keating on Construction Contracts, 11th
4.20.2 (Without Quantities) / 4.21.2 Ed., para. 9.053.
(With Quantities / With Approximate
37. Walter Lilly & Company Limited v Giles
Quantities); and Design & Build
Patrick Cyril Mackay [2012] EWHC 1773
Contract 2016 clause 4.20.2.
(TCC) at 543.
15. Standard Building Contract 2016 clauses
38. Keating on Construction Contracts, 11th
4.20.3 (Without Quantities) / 4.21.3
Ed., para. 9.054; B Sunley & Co Ltd v
(With Quantities / With Approximate
Cunard White Star Ltd [1940] 1 K.B. 740
Quantities); and Design & Build
CA.
Contract 2016 clause 4.20.3.
39. The Hudson and Emden formulae are
16. In the NEC4 suite of contracts, the
used to calculate loss of head office
Employer is referred to as the Client.
overheads and profit taken together,
17. NEC4 Engineering & Construction whereas the Eichleay formula is used
Contract, clause 61.3. only for the calculation of head office
overheads.

You might also like