You are on page 1of 3

DAILY REPORT KERJA EXCAVATOR KOMATSU

Jln cicereme karang papak,kec.cisolok,kab Sukabumi jawa barat 43366

Bulan : Juli 2022


Tgl Jam Kerja Keterangan
13 8 Cetak tandon 1
14 8 Cetak tandon 1
15 7 Cetak tandon 1
16 8 Cetak tandon 1
17 8 Cetak tandon 1
18 8 Cetak tandon 1
19 8 Cetak tandon 1
20 4 Cetak tandon 1
21 7 Cetak tandon 1
22 0 Problem hose hidrolik
23 0 Problem hose hidrolik
24 4 Cetak tandon 1
25 0 Problem Engine
26 0 Problem Engine
27 0 Problem Engine
28 0 Problem Engine
29 0 Problem Engine
30 0 Problem Engine
31 0 Problem Engine
Jlh : 70

Bulan : Agustus 2022


Tgl Jam Kerja Keterangan
1 0 Problem Engine
2 0 Problem Engine
3 0 Problem Engine
4 0 Problem Engine
5 0 Problem Engine
6 0 Problem Engine
7 0 Problem Engine
8 0 Problem Engine
9 0 Problem Engine
10 0 Problem Engine
11 0 Problem Engine
12 0 Problem Engine
13 0 Problem Engine
14 0 Problem Engine
15 0 Problem Engine
16 6 Cetak tandon 2
17 5 Cetak tandon 2 ( 17 an )
18 8 Cetak tandon 2
19 7 Cetak tandon 2
20 8 Cetak kasar CP 6
21 7 Cetak kasar
22 8 Cetak kasar
23 8 Cetak kasar
24 8 Cetak kasar
25 8 Cetak kasar
26 5 Selang pc bocor
27 7 Problem selang pc & handle
28 0 Nunggu selang hidrolik
29 7 Finishing
30 0 Suplay solar terhambat
31 0 Suplay solar terhambat
Jlh : 92

Bulan : September 2022


Tgl Jam Kerja Keterangan
1 0 Suplay solar terhambat
2 0 Suplay solar terhambat
3 0 Suplay solar terhambat
4 0 Suplay solar terhambat
5 0 Suplay solar terhambat
6 8 Finishing cp 5
7 8 Finishing cp 2
8 8 Finishing
9 4 Finishing
10 7 Finishing / buat saluran irigasi
11 0 Suplay solar terhambat
12 0 Suplay solar terhambat
13 8 Finishing
14 0 Solar telat
15 8 Pasang pipa outlet
16 7 Pasang pipa outlet ( jum'at )
17 7 Nglantai & pasang pipa central,side & subsoil
18 8 Nglantai & pasang pipa central,side & subsoil
19 8 Nglantai & pasang pipa central,side & subsoil
20 8 Pasang paralon central
21 0 Selang bocor,press di cibadak
22 7 Jum'at, nglantai
23 5 Hujan petir
24 8 Finishing ipal
25 8 Finishing ipal
26 8 Nglantai kolam & finishing
27 8 Pasang pipa penghubung box kontrol
28 8 Pasang pipa penghubung box kontrol
29 7 Pasang pipa penghubung box kontrol
30 6 Pasang pipa penghubung box kontrol
Jlh : 154

Bulan : Oktober 2022


Tgl Jam Kerja Keterangan
1 7 Pasang pipa penghubung bak kontrol
2 7 Pasang pipa penghubung bak kontrol
3 2 Pasang pipa penghubung bak kontrol
16 2 Pasang pipa penghubung bak kontrol
17 7 Pasang pipa penghubung bak kontrol
18 7 Pasang pipa penghubung bak kontrol
19 7 Pasang pipa penghubung bak kontrol
20 6 Pasang pipa penghubung bak kontrol
Jlh : 45
TOTAL HM : 361

You might also like