Professional Documents
Culture Documents
7.1 INTRODUCTION
Many strengthening techniques are available depending on the purpose
needed from strengthening. Some of those techniques are explained in
details in the following sections.
Why do we strengthen or retrofit buildings?
Increase in the applied loads.
Mistakes or unsafe design.
R. Steel corrosion or insufficient number of bars.
Cracks in concrete or stress less than design stress.
The settlement in the foundation is more than the allowable.
This solution is carried out when the reinforcing steel bars are not capable to
carry the stresses applied to the beam. The following steps should be
followed:
1. The concrete cover is removed for both the upper and lower steel bars.
2. The steel bars are well cleaned and coated with an appropriate
material that would prevent corrosion.
3. Holes are made, in the whole span of the beam under the slab, as
shown in Fig 7-3, 15-25cm apart, a diameter of 1.3cm and extend to
the total width of the beam.
4. The holes are filled with an epoxy material with low viscosity and
installing steel connectors for fastening the new stirrups.
5. Steel connectors are installed into the columns in order to fasten the
steel bars added to the beam.
6. The added stirrups are closed using steel wires and the new steel is
installed into these stirrups.
7. The surface is then coated with a bonding epoxy material.
8. The concrete cover is poured over the new steel and the new stirrups.
The previous steps are illustrated in Fig 7.4.
II-INCREASING BOTH THE REINFORCING STEEL BARS AND THE CROSS
SECTIONAL AREA OF CONCRETE
This solution is chosen when both the steel and concrete are not able to carry
the additional loads applied to the beam. In such cases the following steps
should be followed as in Fig 7.5.
In some cases, it is needed to reduce the load on the beam that needs
strengthening before implementing the previous steps, either partial or
complete unloading.
This is made by putting steel beams on top or below the concrete beams, as
shown in Fig 7-7.
The following photos (8-11) were taken during strengthening an existing
building; they present the practical method of implementing some
strengthening techniques.
7.4 STRENGTHENING OF R.C.COLUMNS
Strengthening of reinforced concrete columns is needed when:
1. The load carried by the column is increased due to either increasing
the number of floors or due to mistakes in the design.
2. The compressive strength of the concrete or the percent and type of
reinforcement are not according to the codes’ requirements.
3. The inclination of the column is more than the allowable.
4. The settlement in the foundation is more than the allowable.
There are two major techniques for strengthening reinforced concrete
columns:
In some cases, where the column is needed to carry bending moment and
transfer it successfully through the floors, one should install a steel collar at
the neck of the column by means of bolts or a suitable bonding material.
7.5 STRENGTHENING OF R.C.WALLS
The dimensions of the wall and its reinforcement are increased by the
following steps:
1. Roughing the total area of the concrete surface.
2. Installing steel connectors for the whole surface at 25-30cm spaces in
both directions. The diameter of the steel connectors is determined
according to the design and their depth should be 5-7 times their
diameter.
3. Installing steel connectors into the wall footings, with the same
number and diameter of the main vertical steel bars, using an epoxy
material.
4. Installing the steel mesh and fasten it by steel wires to the steel
connectors.
5. Coating the surface of the wall with an appropriate epoxy material.
6. Pouring the concrete jacket using low shrinkage concrete before
drying of the epoxy material.
The previous steps are illustrated in Fig 7-10.
7.6 STRENGTHENING OF FOUNDATIONS
Columns foundations need strengthening in the case of applying additional
loads. Widening and strengthening of existing foundations may be carried
out by constructing a concrete jacket to the existing footings. The new jacket
should be properly anchored to the existing footing and column neck in
order to guarantee proper transfer of loads. The size of the "jacket" shall be
selected such that the average maximum foundation pressure does not
exceed the recommended allowable value. Attention shall be given during
construction in order that the excavations for the new "jackets" do not affect
the existing adjacent foundations.
7.7.1.2 INTRODUCTION
Nowadays, strengthening by post casting concrete, steel plate jacketing,
fiber reinforcements such as carbon, armed, and glass are utilized as seismic
strengthening methods for concrete structures. Recently, a seismic
strengthening method by wrapping continuous fiber sheets has often been
used, since the constructability and durability is superior. However,
materials using continuous fibers are expensive.
On the spread of seismic strengthening for buildings and infrastructures in
future, simple methods of strengthening with low cost should not only be
suggested, but also seismic behaviors should be cleared.
In this study, a new, inexpensive, and simple strengthening method for
concrete structures is discussed and suggested in order to improve future
seismic strengthening. This method using short fibers with vinyl ester is a
new combination of materials as seismic strengthening. Chopped short fibers
of carbon and glass with vinyl ester resin are sprayed in place on the
concrete structures. It is called “Sprayed-Up FRP (Fiber Reinforced
Polymer)”. Benefits of using vinyl ester resin in this strengthening method
are that it takes shorter time to harden the resin than epoxy resin. In addition,
the mechanical properties of vinyl ester resin are the same as the one of
epoxy resin. In the following sections, the outlines of this method and the
results of column test under the anti-symmetrical loading are reported. In
addition, the bond behavior between FRP and concrete, and anchoring
behavior using slit (groove) are reported.
SEISMIC RETROFIT
FRP composite systems have been used extensively in seismic zones for
confinement of concrete columns and walls. Improvements in ductility
factors of up to 10 fold have been realized through the use of FRP column
wrapping. Specific FRP systems, offered by some of the manufacturers
referenced below, address seismic requirements according to the load
capacities anticipated and geometric considerations of the building structure.
In addition, FRP systems can be used for stabilizing hollow clay tile, brick
and other unreinforced and lightly reinforced masonry walls in life-safety
applications where vital egress and exit paths in buildings are required.
7.3.3 INSTALLATION/APPLICATION
1. Prepare Substrate
The concrete, masonry or steel surface must be properly prepared prior to
bonding. There shall be no spalling or delamination in the case of concrete
and the corners must be ground to a minimum radius of 10mm (3/8 in.).The
bearing substrate surface is typical roughened by grinding or sandblasting.
Sandblasting is normally used on steel. Any unevenness in the concrete or
masonry is removed with a mineral-based re-profiling mortar.
2. Prime Concrete Surface
Some systems require that the dust-free surface be coated with a primer. For
steel a sandblasted surface yields the best results.
3. Apply Epoxy
To saturate the sheet and simplify installation, the adhesive/matrix resin is
applied to the front and back of the material. Mix and apply epoxy onto
surface using a roller or brush. Once the material has been wet-out with the
liquid resin, the material may be rolled for ease of transport and/or
application to the place of application.
4. Place FRP Sheet on Structure
Unroll sheet rolls onto the structural element being strengthened. Tension is
maintained to minimize intrusion of air entrainment behind sheet. Placing
one layer at a time, apply pressure to wrap using a roller. A hard rubber
roller with ridges (air relief roller) works well for this application.
5. Apply Epoxy to Sheet Surface
A topcoat of epoxy can now be applied to the sheet to fully saturate the
material. If applicable, quartz sand can be applied to topcoat prior to curing
to provide a textured surface for plaster or painting.
Shear walls have three basic failure modes that are sliding, rocking and
bending Fig 7-20.
Increasing the gravity load on the wall can minimize failure. Increasing the
dead load generally does this. However as the dead load is increased the
ductility of the structure as a whole reduced.
7.8.2 DIAPHRAGM FLOORS
The term 'diaphragm's used to identify horizontal resisting elements,
(Generally floors and roofs) that transfer lateral forces between vertical
resisting elements (shear walls or frames).The diaphragm acts as a horizontal
beam: the diaphragm itself acts as the web of the beam, and its edges act as
flanges, Fig 7-21.
When diaphragms form part of a resisting system, they may act either in a
flexible or stiff manner.
- MOVEMENT JOINT
A joint which is formed to accommodate relative movement between
adjoining parts of a structure or diaphragms is a called a movement joint. It
is caused by shrinkage, temperature changes, creep and settlement. It divides
the structure into a number of individual sections and passes through the
structure above the ground in one level. For reinforced concrete structures,
movement joints are at least 25mm wide normally provided at 25m
longitudinally and transverse.