GOVERNMENT OF ODISHA
FOREST, ENVIRONMENT & CLIMATE CHANGE DEPARTMENT
No. FE-OE-ESTT-0061-2020_ 824. /FE&CC, Date.13-o4 /2028
From
Smt. Usharani Das, OAS (SAG),
Additional Secretary to Government.
To
PCCF & HoFF, Odisha, Bhu! ar,
‘The PCCF (Wildlife) & Chief Wildlife Warden, Odisha, Bhubaneswar,
‘The PCCF (KL), Odisha, Bhubaneswar,
The Director, Environment-cum-Special Secretary to Govt., FE&CC Department,
Sub: RESCO model for Rooftop solar system and OREDA's end-to-end E-Mobility
EV fleet services in the State.
Madam/Sir,
In inviting a reference to the subject cited above, | am directed to enclose herewith a
copy of the details on implementation of RESCO model for Rooftop solar system and
OREDA's end-to-end E-Mobility EV fleet services by hiring E-Vehicles from OREDA for
Departmental/ Official use of Govt. offices on hiring basis.
It is therefore requested to kindly circulate the same to all subordinate offices under
administrative control of your organization to place their requirements directly to OREDA.
and further needful action at their end.
Yours faithfully,
69>
Additional Secret ‘to Government.OREDA’s end-to-end E-Mobility EV fleet Services
Roles & Responsibilities of Beneficiary
Beneficiary Department:
*
Beneficiary department to give their consent for availing EV fleet service from OREDA
Beneficiary department to provide details of their vehicle requirement
Share required information for data room preparation
.
.
.
.
Total number and type of vehicles required by the beneficiary departments
Details of availability of space for installation of charging station
Indicative average running of vehicle
Indicative number of operating days
Beneficiary department will allocate space for installation of charging station and parking
of EVs.
Secure a separate connection from DISCOM for providing supply to EV charging stations.
Maintain a logbook to record the daily running of vehicles.
Timely payment to OREDA against the presented monthly invoice.
Beneficiary Department shall be responsible for Toll Tax, Parking Charges, etc, wherever
charged
Go Electric, Go GreenRESCO Model for Rooftop Solar System
Roles & Responsibilities of Beneficiary
Beneficiary Department:
* Beneficiary department to provide consent for installations of project under RESCO
program:
+ Beneficiary department to share following required data set with OREDA for carrying out
feasible capacity estimation
* List of available sites and their dimension
+ Location & address of the sites
+ Electricity bills for last 12 months
* Site photograph
+ Contact person details
+ Provide support in site inspection by OREDA / RESCO Developer
+ Provide payment security to developer as per PPA
+ Letter of Credit (proposed 300% of average monthly bill)
* Letter of consent by beneficiary department for timely payment of monthly bill to
beneficiary department.
Beneficiary to sign PPA for procurement of solar energy as per the term of the PPA.
“+ Beneficiary department to provide access to sites for installation.
‘+ Beneficiary department shall ensure safety and security of assets and manpower.
Beneficiary entity shall avoid tampering with the RTS system installed in their premises
* Beneficiary departments will sign net metering agreement and facilitate net metering
through DISCOM.
Beneficiary departments will ensure timely payments against the monthly bills raised by
RESCO developers for the solar energy generated by the rooftop solar projects
+ Beneficiary department has to make budgetary provision for payment of transaction fee,
which is 3% of the total project cost of the installed RTS system in their premises.