Professional Documents
Culture Documents
z
Module 1:
Introduction
z
Material Management
Production planning
Forecasting.
Master planning.
Capacity planning.
Inventory management
z
Priority–capacity relationship
z
Production Planning and Control System
Aggregate
Planning
Forecast
Master Production
Schedule
Demand
Material
Requirements
Planning
Individual Order
Scheduling
z
Sales and operations planning (S&OP)
The aggregate plan is concerned with determining the quantity and timing
of production for the intermediate future, often from 3 to 18 months ahead.
z
Aggregate Planning Strategies
When generating an aggregate plan, the operations manager must answer several
questions:
3. Should part-timers be used, or should overtime and idle time absorb fluctuations?
A firm can choose from the following basic capacity (production) options:
Subcontracting
Influencing demand
For most firms, neither a chase strategy nor a level strategy is likely to
prove ideal, so a combination of the eight options (called a mixed
strategy) must be investigated to achieve minimum cost. However,
because there are a huge number of possible mixed strategies,
managers find that aggregate planning can be a challenging task.
z
Graphical Methods
z
z
Level Output Strategy
z
z
z
Use of Subcontracting
MPS
z
Inventory
z
MPS
It forms the basis for calculating the capacity and resources needed.
Inputs Outputs
Amalgamated Nut Crackers, Inc., makes a family of nut crackers. The most popular model is
the walnut, and the sales department has prepared a 6-week forecast. The opening inventory
is 50 dozen (dozen is the unit used for planning). As master planner, you must prepare an
MPS. The nutcrackers are made in lots of 100 dozen.
Week 1 2 3 4 5 6
Forecast sales
75 50 30 40 70 20
Project
Available 50
MPS
z
The MPS and Delivery Promises
Using the MPS, sales and distribution can determine the available to
promise (ATP). Available to promise is that portion of a firm’s
inventory and planned production that is not already committed and is
available to the customer. This allows delivery promises to be made
and customer orders and deliveries to be scheduled accurately.
z
Problem (Contd.)
Sometimes, customer orders are greater than the scheduled receipts. In this
example can the master planner accept an order for another 20 for delivery in
week 3?
Calculate the available to promise for the following example. Can an order for 30
more be accepted for delivery in week 5? What will be the ATP if the order is
accepted?
z
Projected Available Balance
The demand time fence is the number of periods, beginning with period
1, in which changes are not excepted due to excessive cost caused by
schedule disruption.
A schedule that shows the total demand for an item (prior to subtraction of
on-hand inventory and scheduled receipts) and (1) when it must be ordered
from suppliers, or (2) when production must be started to meet its demand
by a particular date.
z
Net Requirements
The result of adjusting gross requirements for inventory on hand and scheduled
receipts.
Gross requirement = 50
Inventory available = 20