You are on page 1of 9

Flex2power – a

“gamechanger”
within renewable
energy production
offshore
Offshore Wind Haugesund 9. June 2022

Knut Høiland
Manager BD

Rosenberg Worley – Stavanger

2
✓ A complete EPCI contractor
Flex2power S1 10,2 MW – pilot plant

• DnV Certification in process


• Consession process has 136 m x 136 m
started. Area opened by
OED
• Funding and financing is in
process
Solar panels

Concrete
bottom frame


The pilot project

Eigerøy location 4




Industrialization plan - alternative powerplant configurations
PILOT
Flex2power S1 - 10,2 MW Flex2power Q1 – 65 MW Flex2power P1 - 260 MW+

5



Pathway towards commercialization and industrialization
• Realizing the Pilot Plant. 10,2 MW at LCoE 55 €/MWh. With
public funding from EU and Enova it is possible to bring the
business case cost at an attractive 30 €/MWh.

• Fullscale plant - based on monitoring and optimisation of pilot -


installed capacity of 65 MW at LCoE at 46 €/MWh.

• Collaboration with UiS, DNV, SINTEF Ocean and Skywind A 4 year


plan is established.

• Parklevel plant – realising large potential wind and wave energy

• Parklevel configuration 260+ MW with LCoE at 35 €/MWh


reflecting cost savings for mooring, marine operations,
industrialisation, substation, cable grid, turbine innovations.

• Industrialisation potential through Cooperation Agreement


with Norsea to produce plants at Windworks Jelsa site.
The Windworks Jelsa prospect – could be operating from 2027.

Flex2Power – large local value creation at an attractive cost


Wave Energy System (IKM systemdesign)

Power = (flow x pressure) / 600


72 hydraulic cylinders delivers 15280 l/min in average at 240/200 (230) bar.
Average power 5857 KW. We have chosen to install 4 generators at 1,5 MW each – all together 6 MW.
Capacityfactor at 68 %.

Moving parts Flex2power consept


Cross unit Seesaw arm
Casted component weight of approx. 5 tons. Will be installed with laminated rubber Lazercut and maskined component – weight approx. 2 tons. Lashes around axis with
bearing designed by Vipo AS. Rubber bearing is designed for 25 years lifetime. pivot bearing delivered by SKF. Designed for 25 years lifetime. Seesaw arm is 3 meters
long and has a width of 350 mm.
Cross unit is designed to be changed if needed.
Seesaw arm and/or bearing is designed to be changed if needed.
Measures component: 2,40m x 1,74m (height x width)
Bearing for hydraulic cylinder is a sliding bearing and needs to be changed every 6th
Unit is designed for +/- 3 degrees in vertical movement and +/- 1 degree horisontal year.
movement

Cross unit
Seesaw arm
Kr

DISCLAIMER

This presentation has been prepared by a representative of Rosenberg, Worley group.

The presentation contains the professional and personal opinions of the presenter, which are given in good faith. As such, opinions presented herein may not always necessarily reflect the position of Worley as a whole, its officers or
executive.

Any forward-looking statements included in this presentation will involve subjective judgment and analysis and are subject to uncertainties, risks and contingencies—many of which are outside the control of, and may be unknown to,
Worley.

Worley and all associated entities and representatives make no representation or warranty as to the accuracy, reliability or completeness of information in this document and do not take responsibility for updating any information or
correcting any error or omission that may become apparent after this document has been issued.

To the extent permitted by law, Worley and its officers, employees, related bodies and agents disclaim all liability—direct, indirect or consequential (and whether or not arising out of the negligence, default or lack of care of Worley and/or
any of its agents)—for any loss or damage suffered by a recipient or other persons arising out of, or in connection with, any use or reliance on this presentation or information.
9

You might also like