You are on page 1of 2
Sone) Project Responsibility Prior to the start of construction, John (Project Engineer) has delegated job responsibilty as following: Dave's assignéd as a Ste engineer responsible for project scheduling and coordinating with 3 AE \(rchitectural/Engineering) design firm, CM consultant, and ABC head office. Carls in charge of on-site operations and general supervision of all foremen. Car reports directly to John. 1 Bob is:responsible for on-site resources management (labor, material, and equipment) including ordering (work in concert with Dave), warehousing, , and distribution. "His major task js to make: sure that resources wil be available when needed. Moreover, site planning and layout for efficient construction operation is also fis responsibilty. Bob works directly under Carl for on-site operations and Dave for administrative functions. 1M Nai is in charge of on-site operations. His major responsibity isto ensure that work progress i satisfactory. He has to synchronize work activities of subcontractors and ABC so that works wil go as smooth as possible. He reports directly to Carl and John, ML Soott and Tom are site foremen whose major tasks are: 1) to perform quality inspection in conformance with technical specifications; and 2) to supervise and control in-house skiled and unsklled labors in order to ensure productive work performance. ‘The ABC on-site organizational structure is shown in igure 1. ohn (Project Engineer) r 1 Cal Dave (Chief Foremen) (Gite Engineer) r Neil Bob (Production Foremen) (Resource Foremen) ‘Scott Tom (Field Forerien) | | (Field Foremen) Fi Figure 1. ABC on-site organizational structure AJEDesign [ARC Is the AJE design firm of this project. The role of A/E during construction is to carfy whenever there are problems conceming drawings and specications arisen. Tn the event that there is problem, Request for Tnfomation (RFD from ABC willbe sent to NE through CM consultant for dariicaton, Moreover, Eis responsible for periodic inspections to ensure thatthe contractor's wor is completed in accordance with contract ict eee ae ‘CM Consultant 7 ‘CHCON is the CM consultant firm and the representative of the project owner to supervise ABC works. CMCON is responsible for on-site quality Inspection, maintaining project progress, and the ABC payment approval. so that the project wil be competed on time and within Specter quanRY. CHICON has three full ime staffs on sis, ‘Smith {Project Engineer with 10 years bulking construction work experience), Will (Senior Foreman with 20 years experience), and Shane (unior Foreman with 1 year work experience). ‘Case Study IPart 2 & 2 ‘Any or-site problems regarding unclear of errors in drawings and specications will be sent to CMCON and, if ‘cannot be solved by CMCON, will be forwarded to ARC. CMCON engineer and foremen perform routing on-site inspection, approval of shop drawings (showing detail construction methods for major activities), and request for {esti ond approval of conetucion materials, Situations In this project, two schedule categories have been requested by CMCON as listed: |. ESO ek 9 reo CHEN hin 1 oe aor nt er a ae 2. Ceetional ScheduleSectional schedules are required for the detailed site planning of the contract. They are. Prepared as the detalled work schedules for specific parts or paiticular areas of the work such a5 piling, concrete structure, etc. Itis important that their preparation ties with the master schedule. lule Responsibility: Other than the two above mentioned schedules, John requests threé mofe types of schedules to be applied during construction so that close monitoring of work activities can be accomplished. GD Weeidy Schedule: This schedule wil provide the ability to contol activities on a'short term basis and allow regular short term reviews of progress. Furthermore, it enables effective communication on a day-to-day basis over the span of a week. (O Subecntiactor Schedule: Al major subcontractors (eleccal, mechanical, et.,) are asked to submit their ‘etal schedule of work activities showing completion within the periods allowed by ABC to ensure the proper progress of the main contract QO | Procurem 3: Material procurement. schedules are developed to ensure that all critical materials will be on-site when needed. This type of schedule falls into two phases on site: first, material delivery schedules to meet the requirements of the master and sectional schedules; secondly, the monitoring ‘and control of deliveries together with ensuring that they are efficiently used. Questions: 1) Please give three most important reasons, why CMCON: request for master and sectional schedules? 2) What do you think about gveral yoms, explain briefly? 3) Please identify three major advantages and disadvantages of overall schedule programs? 4) Please predict two major incoming problems regarding the schedule development during the planning (pre- construction) stage. (Case Smdy I Part 2

You might also like