You are on page 1of 9

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/265215755

Power flow analysis of Rafah governorate distribution network using ETAP


software

Article  in  International Journal of Physical Sciences · June 2013

CITATIONS READS

7 2,580

1 author:

Nadia Mahdi
GEDCO
1 PUBLICATION   7 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Master Thesis View project

All content following this page was uploaded by Nadia Mahdi on 22 February 2017.

The user has requested enhancement of the downloaded file.


International Journal of Physical Sciences Vol. 1(2), pp. 019-026, June 2013
Available online at http://academeresearchjournals.org/journal/ijps
©2013 Academe Research Journals

Full Length Research Paper

Power flow analysis of Rafah governorate distribution


network using ETAP software
Nadia M. Mahdi
Electrical Engineering, Technical Administration, GEDCO Company, Gaza, Palestine.
E-mail: engineer_nadia@yahoo.com.
Accepted 29 May, 2013

The results of a load flow analysis can be used for operational purposes to evaluate various operating
states of an existing system. They can also be used in the planning stages to evaluate possible future
extension projects. This paper discusses the analysis of the power distribution network in Rafah
governorate by using ETAP software. The aim is to evaluate the technical status of the present medium
voltage network (22-kV). The problems and challenges faced by the existing network are analyzed.
Those problems include the power deficit, high power losses, poor voltage levels and feeders’
overloading. Then some solution techniques are suggested considering the system current state and
future growth for different scenarios for each problem to obtain a full understanding of the system
problems and solutions.

Key words: Distribution network, power flow analysis, ETAP.

INTRODUCTION

The power-flow analysis of a distribution feeder is similar is for the design, simulation, and analysis of generation,
to that of an interconnected transmission system. transmission, and distribution power systems. For a
Typically, before starting the power-flow analysis, the power distribution system, it is capable of calculating
three-phase voltages at the substation and the complex balanced and unbalanced load-flow. This analysis
power of all of the loads and the load model must be produces detailed reports of system losses, line flows,
known. A load flow study determines the voltage, current, and voltage at every node. The software is capable of
power and reactive power in various points and branches recommending optimum capacitor placement, and wire
of the system under simulated conditions of normal size upgrades (Barn and Jewell, 2005). ETAP Load Flow
operation (William, 2002). Load flow studies are essential Analysis module calculates the bus voltages, branch
in optimizing existing networks, ensuring an economical power factors, currents, and power flows throughout the
and efficient distribution of loads, and plan future electrical system on both radial and loop systems (ETAP
networks (Jan de Kock and Kobus, 2004). The analysis 7.0.0 User Manual, 2009).
of a distribution feeder will typically consist of a study of As a power distribution system load grows, the system
the feeder under normal steady-state operating power factor usually declines. Load growth and a
conditions. All of the approximate methods of modeling decrease in power factor leads to a number of
assume perfectly balanced three-phase systems, challenging problems such as: voltage regulation
balanced three-phase loads, and perfectly transposed problems, increased system losses, power factor
three-phase line segments (William, 2002). penalties and reduced system capacity (Holm et al.,
There are wide ranges of power system analysis 2010). The distribution network in Rafah experiences
programs available in the world market that perform all many technical problems which need quick solutions. The
sorts of electrical analyses. They range from basic, most pressing problems are high power losses and poor
commercially packages to large, complex programs voltage especially at the feeder ends. To face these
developed for a specific customer (Jan de Kock and challenges, a power flow study for the distribution
Kobus, 2004). The software used in this paper is ETAP. It network must be carried out to find the suitable technical
Mahdi 020

Figure 1. The main feeders of Rafah Governorate.

solutions. The main contribution of this paper is that it about 68800 m feeding 133 of distribution transformers.
evaluated the 22-kV network in Rafah and suggests the Moreover, the overhead lines cover about 93.8% of the
suitable available technical solutions. overall length of the network. This is because the
overhead network is much cheaper than the underground
METHODOLOGY network. Most of the 22-kV lines are constructed using
ACSR 150/25, ACSR 50/8 and ACSR 95/15 conductors.
First of all, the MV grid was analyzed using ETAP It is important to know that all the previous mentioned
software in a way such that all problems and deficiencies data of Rafah network and all work done in this paper
are investigated clearly and then suitable solutions are represent the network status till the end of 2011.
tested by simulation.
SIMULATION RESULTS AND ANALYSIS
Description of the existing network
Since all feeders in Rafah city are in radial configuration,
Rafah is a Palestinian city that is located in the south of then each feeder can be analyzed separately. The four
Gaza Strip on the border between Egypt and Palestine. feeders are simulated in separate projects. Their one-line
Rafah receives power through four feeders operating at diagrams are drawn and their parameters are entered
22 kV as shown in Figure 1 (Gaza Electricity Distribution into ETAP software. Then they are exploited in different
Corporation [GEDCO], 2010). Three of the feeders are study cases to evaluate the performance of the grid. The
from Egypt and they enter Rafah from the southern side. feeders are studied assuming balanced load-flow. For
The first feeder has a maximum capacity of 5 MW. The each study case, the program produces detailed
second feeder has a maximum capacity of 12 MW, and accounts of system losses, line flows, and voltage at
it’s divided into two feeders. The fourth feeder enters every node or bus. These detailed reports are used to
Rafah from its eastern side and is owned by the Israeli investigate all problems and deficiencies of the grid.
Electric Company (IEC). All those feeders are governed Figure 2 depicts a part of the one-line diagram of the IEC
by Gaza Electric Distribution Corporation (GEDCO), the feeder.
unique electric distribution company in Gaza Strip. MV The results of load flow module for all feeders are
distribution system is stepped down to 400-V at divided into three parts: the first part of the results is
distribution transformers. Then the power is distributed to concerned with power demand and capacity issues, the
individual consumers via low voltage distribution second is related to the system losses, while the third
networks at 400-V. This network serves 22,038 part is for voltage magnitude and voltage drop at each
customers which represent 12% of the total customers of node on the feeders.
GEDCO in year 2011. The MV network falls into two It is found that there is a deficit in the available power
categories: overhead lines and underground cables. by about 35%. Also the grid suffers from phase load
It is fairly wide spread in Rafah that a total length of imbalance in the LV networks. The line current unbalance
Int. J. Phy. Sci. 021

Figure 2. One-line diagram of the 1st Egyptian Feeder.

rate is 7.4% in average to all feeders. Moreover, the according to the actual power demand. Also it is
percentage voltage drop obtained by power flow solution important to predict the future growth of the power
drops below 90% of the nominal voltage in the first one demand to be taken into account in the upgrade and
third of the feeders’ length except the second Egyptian planning of new projects. So the forecasted growth in the
feeder. The estimated cost of the resulted average power demand was evaluated for the coming ten years
energy losses reaches 3.3 million NIS for MWH and 5 from 2012 to 2022. The predicted data were evaluated by
million NIS for MVAR in year 2011. It is observable that excel “FORCAST” function which predicts the future
the percentage of reactive power loss is approximately values along a linear trend by using the existing values
about 1.6 times more than the active power loss and this and they are shown in Figure 3. It is perfectly suitable
is due to the nature of the lines which normally have the since the existing data have a linear behavior.
value of X/R larger than unity. In addition to these According to the power demand requirements, it is
problems, the existing grid has a poor lagging power found that the preferred solution to support the existing
factor in all 22-kV feeders which stay in the range of 81 - load and the future demand growth is to install a new
84%. substation in Rafah as an extension to the Egyptian high
voltage network. The Palestinian Authority of Energy and
SOLUTION TECHNIQUES Natural Resources in Gaza proposed a complete study of
a project to install two new substations in Gaza Strip, one
After the presentation of all problems and deficiencies of of them is intended to extend the Egyptian system and
network, the study addresses and suggests solution rated at 220/22 kV. It will have two of three winding
techniques for those problems. power transformers rated at 60/75 MVA. This substation
will feed the southern part of Gaza Strip with the required
Managing the growing power demand power demand.

In order to satisfy the ever increasing energy demand, Load balancing


several actions have to be implemented. These actions
have to be carried out in parallel. Those actions include A three-phase, four-wire distribution system has been
the load balance and upgrading of the supplied power widely used to facilitate low voltage supply to single-
Mahdi 022

Figure 3. Growth of peak power demand in summer.

Figure 4. Power demand in balanced and unbalanced loads.

phase and three-phase loads. This mixed loading in the It is noted that the current imbalance exceeds the
secondary distribution system may result in serious standard limit of LCUR which equals 3% at maximum.
phase unbalance (Nikhil et al., 2011). By calculations, it is Figure 4 indicates the capacity release which can be
found that the line current unbalance rate in average is obtained through balancing loads on the LV network.
6.37% for the 1st Egyptian feeder, 9.99% for the 2nd The figure shows that the load balance can release
Egyptian feeder, 7.21% for the 3rd Egyptian feeder, and about 7% of the active and reactive powers.
5.76% for the IEC feeder. The line current unbalance rate
(LCUR) is calculated by equation (1) as shown thus: Voltage improvement

Max line current deviation from average Voltage (1)


improvement is considered as power quality
LCUR%  100 issue and there are several techniques that can be used
Average line currents
(1) to improve the voltage profile of the feeders. The voltage
profile is enhanced by three techniques: raising the
Int. J. Phy. Sci. 023

Figure 5. Voltage profiles of the 1st Egyptian Feeder.

Figure 6. Voltage profiles of the 2nd Egyptian Feeder.

sending end voltage, changing the tap settings of the This improvement is achieved at the expense of higher
distribution transformers, and the last method is current and power demand, so this approach must be
accomplished by installation of capacitor banks. applied carefully.

Approach 1: Raising the voltage at the feeder Approach 2: Adjustment of transformers’ tap setting
sending-end
Another method that can be used to enhance the voltage
The most intuitive way in voltage improvement is to raise levels along the feeders in the LV side is to readjust the
the voltage at the sending end node. Even though the transformers’ tap changer. The transformers’ tap changer
voltage control is done only from the substations, this is on high tension side and can be stepped to +1×2.5% or
method is implemented based upon request from to -3×2.5%. Since the nominal value of the system is 22
technical department of Rafah branch. Figures 5 to 7 kV, then each step can raise or lower the voltage rating
show the improvement of the voltage profiles considering by 0.55 kV. The tap changer must be adjusted to suitable
both the peak and average loading cases. settings to suit both light and heavy loading cases. The
Since the IEC feeder suffers more voltage drop than 1st Egyptian feeder is tested for this method in summer
Egyptian feeders due to higher loading and longer length, loading case and the voltage profile along the LV nodes
it is raised to 23 kV as a suitable value for the feeder to is shown in Figure 9. The tap changers of all transformers
operate within the allowable range of voltage in peak and connected to LV nodes that experience voltage drop
off-peak loading. The effect of raising the sending-end below 90% of the nominal value are adjusted to -3×2.5%
voltage is presented in Figure 8. position of their tap changers.
Mahdi 024

Figure 7. Voltage profiles of the 3rd Egyptian Feeder.

Figure 8. Improvement of voltage profile on IEC feeder.

Figure 9. Voltage profile variations by adjusting transformer’s tap-changer settings.


Int. J. Phy. Sci. 025

Figure 10. Voltage improvement by capacitors’ placement.

Table 1. Capacitor banks and power carrying capability.

Capacity
Before adding capacitors After adding capacitors
release (MVA)
Average Loading 20.5 kV Sending Average Loading 20.5 kV
Sending Peak Avg.
MW Mvar end MW Mvar
end PF% MW Mvar MW Mvar Load Load
Loss Loss PF% Loss Loss
83.39 6.43 4.25 0.188 0.387 96.17 6.58 1.87 0.153 0.324 1.044 0.86

Approach 3: Installation of capacitor banks Distribution losses in a facility can be reduced by addition
of capacitors as clearly investigated by Equation (4)
Placement of capacitors has been considered mainly to (Osama and Ahmad, 2011):
enhance the line voltage levels above 90% of the nominal
voltage, power factor correction, and losses reduction.
Power factor correction permits additional loads to be   PF 2 
served by the existing system. In case if the transformers Loss reduction%  1-  initial   ×100
or cables get overloaded, improving the power factor will   PFfinal  
(4)
be the most economical way to reduce the current and
therefore eliminate overload condition. This can be
clearly investigated by Equations 2 and 3 (Osama and After installing the capacitor banks, the feeder was tested
Ahmad, 2011): for a combination of different operating scenarios
including under voltage of the sending end, overvoltage
PFinitial of the sending end both at minimum and maximum
S
Snew  PF
new PF
×S×S
initial loading cases. The load flow simulation indicates
(2) that the
old old
capacitors operate with its full rating without leading to (2)
PFfinal final (2) under voltage or overvoltage conditions and this is what
we are searching for. Figure 10 shows the enhancement
Snew
IInew  S new of the voltage profile after installing the capacitor
(3) banks
new 3V regarding different cases of the sending end voltage at (3)
3V the average loading condition.
(3)
Mahdi 026

Not only that the voltage levels are improved, but also REFERENCES
the power factor at the sending end is increased from
83.39% to 96.17%. Another advantage is that the current Barn L, Jewell W (2005). Review: power system analysis
loading is decreased; hence the power losses are software tools. IEEE.
decreased. Moreover, the increased power factor ETAP 7.0.0 User Manual (2009).
increases the feeder capacity by capacity release which Jan de K, Kobus S (2004). Power Distribution for
lowers the consumed KWH annually. These improvement Industry. IDC Technologies., p. 151.
results are displayed in Table 1. Nikhil G, Anil S, Niazi KR (2011). A Novel Strategy for
The capacitors’ banks are highly costly, so the project Phase Balancing in Three-Phase Four-Wire Distribution
of capacitor placement needs an economic evaluation Systems. IEEE.
study. The investment cost of this project must be Osama A, Ahmad KA (2011). Impact of Power Factor
considerable in comparison to profit obtained in the near Correction on the Electrical Distribution Network of
future. It is seen that the payback period is 4 years and in Kuwait – A Case Study. Online Journal on Power and
the fifth year, the pure profit starts assuming that the Energy Engineering (OJPEE), 2: 1.
energy price is fixed at 0.28 NIS for 1 KWH and summer Holm RMU, Chopade PV, Prornod J (2010). Optimal
loading. Placement of Capacitor for Power Loss Reduction
Using ETAP Software. ICSES' 10 International
Conclusion Conference on Science. Engineering & Spirituality.
Studies and Documentation Branch in Technical
Power flow analysis is an essential step for operational Administration of Gaza Electricity Distribution
purposes to evaluate various operating states of an Corporation GEDCO (2010).
existing system. Also it is necessary for enhancement William HK (2002). Distribution System Modeling and
and development projects. By using ETAP load flow Analysis. CRC Press LLC, 39: 269.
program, it is found that the MV network in Rafah
experiences many technical problems including: deficit in
the available power, poor power factor, low voltage levels
and power losses. Based on the obtained results, some
technical solutions are suggested to help in the network
improvement. The solutions are tested by simulation. The
proposed solutions were suggested considering the
financial investment cost and profits such that the
solutions are acceptable from the economic view. ETAP
shows powerful functionalities in load flow analysis field.
Thus it is strongly recommended to be available for
usage in the technical administration of GEDCO.

View publication stats

You might also like