E. PEKERJAAN PAS.

KERAMIK
Lantai:
Luas = 11 m²
kebutuhan:
Keramik 20x20 = 11 dus
Semen = 2.2 zak
Pasir = 0.5 m³
Semen Warna = 2.75 kg

F. PEKERJAAN ELECTRICAL
Jumlah Titik = 10 Titik
1. Titik lampu (LED Philips 8watt) = 7 (lampu 7pcs)
2. Saklar Ganda (Panasonic) = 1 pcs
3. Saklar Tunggal (Panasonic) = 4 pcs
4. Imbodus = 5 pcs
5. Pipa Kabel = 4 btg
6. MCB 10A (Broco) = 1 pcs
7. Box MCB = 1 pcs
8. Kabel Jalur Eterna 2x2.5 = 0.5 rol
9. Kabel Lampu eterna 2x1,5 = 1 rol
10. Kabel Eterna 1x1.5 = 1 rol

G. PEKERJAAN KUSEN PINTU


1. Daun Pintu PVC = 4 pcs
2. Kusen Roster Beton = 8 pcs

H. PEKERJAAN PLUMBING
1. Pas. Closet Jongkok = 4 bh
2. Pas. Instlasi air bersih = 5 btg pipa AW rucika 1/2'
3. Pas. Instalasi air kotor = 3 btg Pipa AW rucika 3'
4. Pas. Instalasi air kotor (WC) = 2 btg Pipa AW Rucika 4'
4. Pas. Kran Air Stainlis = 4 bh Stainless 1/2'
5. Pas. Floor drain Stainless = 4 bh
6. T 4 inch = 3 bh Rucika
7. L 4 inch = 1 bh Rucika
8. T 3 Inch = 3 bh Rucika
9. L 3 inch = 2 bh Rucika
10. T 1/2 inc = 3 bh Rucika
11. L 1/2inch = 2 bh Rucika
12. Stop kran 1/2 inch = 3 bh Rucika
13. Lem Pipa = 1 kaleng
14. Shelltip = 2 bh
15. L drat 1/2 inch = 1 bh Rucika
16. SDD 1/2 inch = 3 bh Rucika
1. Pas. Kunci tanam+Handle pcs 5 Rp 120,000 Rp 600,000
2. Pas. Engsel Pintu 4inch kotak 5 Rp 40,000 Rp 200,000
3. Pas. Engsel Jendela 3inch kotak 5 Rp 30,000 Rp 150,000
10 Pek. Kunci dan Kaca 4. Pas. Grendel Pintu pcs 5 Rp 10,000 Rp 50,000
5. Pas. Grendel Jendela pcs 5 Rp 10,000 Rp 50,000
6. Pas. Tarikan Jendela pcs 5 Rp 10,000 Rp 50,000
7. Hak Angin pcs 5 Rp 10,000 Rp 50,000
1. Pas. Closet Jongkok bh 4 Rp 100,000 Rp 400,000
2. Pas. Instlasi air bersih pipa AW rucika 1/2' btg 5 Rp 30,000 Rp 150,000
3. Pas. Instalasi air kotor Pipa AW rucika 3' btg 3 Rp 150,000 Rp 450,000
4. Pas. Instalasi air kotor (WC) Pipa AW rucika 4' btg 2 Rp 250,000 Rp 500,000
4. Pas. Kran Air Stainlis bh 4 Rp 20,000 Rp 80,000
5. Pas. Floor drain Stainless bh 4 Rp 20,000 Rp 80,000
6. T 4 inch bh 3 Rp 30,000 Rp 90,000
7. L 4 inch bh 1 Rp 30,000 Rp 30,000
8. T 3 Inch bh 3 Rp 25,000 Rp 75,000
11 Pek. Plumbing 2
9. L 3 inch bh Rp 25,000 Rp 50,000
10. T 1/2 inc bh 3 Rp 4,000 Rp 12,000
11. L 1/2inch bh 2 Rp 4,000 Rp 8,000
12. Stop kran 1/2 inch bh 3 Rp 25,000 Rp 75,000
13. Lem Pipa kaleng 1 Rp 55,000 Rp 55,000
14. Shelltip bh 2 Rp 7,000 Rp 14,000
15. L drat 1/2 inch bh 1 Rp 5,000 Rp 5,000
16. SDD 1/2 inch bh 3 Rp 5,000 Rp 15,000
17. Tower Air 1000L bh 1 Rp 1,500,000 Rp 1,500,000
A. TOTAL BAHAN MATERIAL Rp 94,008,520

1. WC+Septitank
2. Mess 5 pintu
1 Borongan Sarino 3. Tutup pagar Rp 25,000,000 Rp 25,000,000
4. Bobokan + buat pedestal
5. Pondasi
B. TOTAL BORONGAN Rp 25,000,000

A. TOTAL BAHAN MATERIAL Rp 94,008,520


B. TOTAL BORONGAN Rp 25,000,000
GRAND TOTAL Rp 119,008,520
Kebutuhan Material:
-Kayu Kaso 4/6 = 5 ikat
-Batu Belah Uk 15 / 20 cm = 19 m3
-Semen 50 kg = 166.27 zak
-Pasir Pasang = 54.84
-Bata Bolong = 17423
-Split 1/2 = 5.51
-Kayu Papan = 1.57
-Besi 8 =
-Besi 6 =
-Bendrat =
-Paku 3' =
-Cat dasar =
-Cat Tembok =
-Semen Warna =