Professional Documents
Culture Documents
Damages
In general terms, upon proof of breach, the innocent party is
automatically entitled to claim damages, i.e. Compensation of
loss caused by that breach.
This is because a failure to perform a primary or performance
obligation under the contract automatically gives rise to a
secondary obligation to pay damages.
The right to damages may however, be excluded or limited by
an exemption clause in the contract.
However, unless the breach is a repudiatory breach, the contract
will continue in force and both parties must continue to perform
their obligations under it.
Consequences of Breach
The courts will not allow a claim for both expectation and
reliance loss.
An injured party can also make a claim in restitution –
recovery of a benefit received by the defendant from the
unperformed contract.
– This claim places the parties in the position they were in before the
contract was made to prevent unjust enrichment.
Damages are not intended to be punitive but
compensatory.
Expectation Damages
The basic measure is that of the claimant‟s position and the position
he would have been in had the contract been performed.
The plus side is the claimant‟s expectation loss from breach,
comprising of the promised performance; consequential losses of
not getting the due performance and consequential losses of not
being made better off.
In Parsons (Livestock) Ltd v Uttley Ingham & Co Ltd [1978]
– A pig farmer bought storage hopper from U for pig food. The storage
hopper was installed defectively and food became mouldy and many pigs
died. On the plus side P, claimed: not getting a hopper fit for purpose
(promised performance); the dead pigs (consequential loss – undue
performance); and the profits which would have been made on sale of pigs
(consequential loss not being made better off).
Measure of expectation damages
Reliance damages seek to put the claimant into the position they
would have been in had they not entered into the contract.
Reliance damages are therefore described as being backward
looking.
In some cases, particularly where expectation damages are too
speculative, a claimant may be able to recover damages on the
reliance interest.
The injured party can claim reliance damages where the reliance
loss does not exceed expectations (cannot avoid bad bargain).
Expectation measure is usually more favourable because the
claimant would be profiting but where the contract would not
have been profitable, reliance measure would be favourable.
Restitution
Parsons (Livestock) Ltd v Uttley Ingham & Co Ltd [1978] – the majority
view was that only type of harm, not the extent of the harm, needs to
be within the reasonable contemplation of the parties. Lord Denning
was however, of the view that the relevant test of remoteness should
be determined by the type of harm suffered, drawing a distinction
between physical and economic harm.
Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd [1915]
– The House of Lords, in distinguishing between liquidated damages
and a penalty clause, the court should have regard to whether the
amount agreed is a genuine pre-estimate of loss. The court will
interpret the clause as a penalty if the sum stipulated is extravagant in
comparison to the loss that could be proved to have followed from
the breach.