EPIC
JR12:L731/L71121/L2123 J3413:X721
CI/SfB
(52.5) (H1)
October 2015 QS001
Water management
PRODUCT AND INSTALLATION MANUAL
Wavin QuickStream
Siphonic Roof Drainage
Contents
QuickStream
1.1 Introduction
A specially designed roof outlet with an air baffle and anti vortex
vane only allows the intake of water and prevents the ingress of
air, so allowing full-bore flow to be achieved (see figures 1 & 2).
At full-bore flow, the difference in height between the roof outlets
and the rainwater discharge level is utilised to gain the energy
that will increase the flow velocity of the water in the pipework.
2 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
1.2 The Wavin QuickStream Roof Drainage System A small selection of customers who have already benefited
from the Wavin QuickStream system:
Wavin has decades of experience in the drainage of roof surfaces
using siphonic drainage. The Wavin QuickStream system has Palm Paper factory, Kings Lynn, UK.
been used widely across, Europe and in many international 53,000m2 roof area
projects. Aldi Central Warehouse, Radevormwald, Germany.
32,000m2 roof area
Wavin system benefits: Central Railway Station, Rotterdam, Netherlands.
Smaller pipe dimensions 20,000m2 roof area
Thanks to a special calculation procedure, the pipes can be Airbus A380, Hamburg, Germany.
designed with very small diameters. 20,000m2 roof area
Fewer roof outlets Carrefour Shopping Centre, Fiano di Pontecagnano, Italy.
High-performance roof outlets achieve an excellent litre 40,000m2 roof area
performance even at low back up heights. Audi, Münchsmünster, Germany.
Less groundwork 39,000m2 roof area
Most of the groundwork can be saved by reducing the Meander Medical Centre, Amersfoort, Netherlands.
downpipes. 21,000m2 roof area
Fast installation BMW, Regensburg, Germany.
Special clamp designs and a well-matched bracketing 70,000m2 roof area
system allow for fast installation. United Nations City, Copenhagen, Denmark.
Reduced maintenance overhead 28,000m2 roof area
Fewer downpipes also means that fewer manholes are Blokker Distribution Centre, Geldermalsen, Netherlands.
required. This saves maintenance/inspection time and thus 86,000m2 roof area
money. Mercedes factory, Kecskmet, Hungary.
No pipe gradient required 250,000m2 roof area
The lines can be routed through apertures in the binder
without a gradient.
Shorter building time
The concreting work for the foundation slab is less
dependent on siphonic drainage, since very few downpipe
connections are required inside the industrial building.
Lower insulation costs
Smaller pipes also mean lower costs for insulation at the
same time.
The Wavin project team, comprising numerous skilled ...With a user-friendly software and an extensive training program
professionals, is happy to provide support to help you implement (software training, hydraulic training, or processing training) we
your building project... are happy to share our knowledge and our experience with you...
...Qualified advice in your office or on the construction site, for ...High static and dynamic loads that occur in siphonic drainage,
example, at a project meeting, are a matter of course for the are no problem for the quick installation system. Wavin offers a
Wavin field service team... complete bracketing system from 40-315mm...
...The “heart” of a siphonic drainage system. Wavin offers an ...An extensive pipe system especially tailored to the requirements
extensive roof outlet range with extensive accessories to ensure of the siphonic drainage technique is available in the dimensions
optimum system performance... 40-315mm.
4 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
Installation
QuickStream
2. General Installation Principles 2.1.2 Fix Roof Outlets and Pipe System According to
Wavin’s Instructions
2.1 Basic Rules
One of the key elements in a Wavin QuickStream system is the
To ensure proper functioning of the Wavin QuickStream siphonic roof outlet. Improper or incomplete installation might cause
roof drainage system, some general requirements related to the condensation and/or leakages. In most Wavin QuickStream
design and installation of the system must be met. Therefore systems, long horizontal pipes will be installed below the roof.
please note the following important rules: For this part of the installation please follow Wavin’s installation
1. Installation to Wavin system design recommendations mentioned in section 3. Wavin has developed
2. Fix Roof Outlets and Pipe System according to Wavin’s special brackets for an easy and secure installation of the
instructions horizontal collector pipes.
3. No slope in horizontal pipes
4. No siphons in the system 2.1.3 No Slope in Horizontal Pipes
5. No obstructions in the pipe system
6. Only use 45° Bends and 45° Tees unless specified differently In horizontal pipes, no slope is required to transport the water to
7. Use only Eccentric Reducers / Increasers the downpipe since the system operates at high velocities due
8. Only install expansion joints where provided in the design to the energy head, which is equal to the height of the building.
9. Do not connect gravity pipelines to the Wavin QuickStream A small slope is neither beneficial nor disadvantageous for the
system operation of the system. For ease of installation, we recommend
10. Use prescribed pipe materials and pipe classes to use no slope in the horizontal pipes. If a slope in the horizontal
pipe is desirable to improve emptying of the system after a
2.1.1 Installation to Wavin System Design rainfall, Wavin advises to keep the slope below 1:200.
For each Wavin QuickStream system, Wavin will make a 2.1.4 No Siphons in The System
site-specific hydraulic design. Deviations from design might
impair design criteria and discharge capacities. A negative slope or an upward placed bend into the flow direction
will create a siphon. In siphonic systems this is not allowed
Wavin uses dedicated software to design Wavin QuickStream since during the start-up of the system air might be entrapped,
systems. This means that the installation should be made exactly preventing a full-bore flow.
according to the drawings supplied by Wavin. Every deviation
from design in the installation might lead to an imbalance of Figure 4: No negative slope Figure 5: No upward placed
the system, resulting in incorrect functioning of the system. bends
All deviations from the supplied drawings should therefore be
discussed in advance with Wavin’s design department. Wavin
will always send a written reply to such a request.
All pipe ends should be checked and freed from burrs. Burrs, dirt Diameter changes in horizontal collecting pipes must be made
and other obstructions might influence the proper functioning of with eccentric reducers. In order to accelerate the evacuation of
the system. Preferably, electro-fusion couplers should be applied. air, the topside of the collector must remain on the same level
However, butt welds are also allowed in the Wavin QuickStream when a reducer / increaser is installed in the flow direction.
polyethylene pipe system.
Figure 9: Use only eccentric reducers in the flow direction with
Figure 6: Wrongly and properly cut pipe ends the top side at the same level
Bends of 90° have a higher flow resistance than two 45° bends.
The design of the system is based on using two 45° bends
instead of one 90° bend unless specified differently. Installing 90°
bends is consequently not allowed unless specified by Wavin
(see Figure 7). Pipe diameter must never reduce in the flow direction in
horizontal pipes.
For the same reason only 45° Tees are allowed instead of 90°
Tees unless specified by Wavin (see Figure 8). Figure 10: Install increasers in the flow direction before a Tee
6 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
Figure 11: Install eccentric reducers in a vertical pipe with the 2.1.8 Only Install Expansion Joints Where Provided in
level side facing the wall The Design
H≥0.2xL L
Figure 12: Only use Wavin recommended and quoted pipework H
8 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
Bracketing System
QuickStream
3. Wavin QuickStream Bracketing Benefits of Wavin QuickStream bracketing system:
Approved system from 40 – 315mm
System
Only a few tools required for installation
Time saving during installation
3.1 Introduction
Special pipe clamp design holds pipe in place
Rail connections are longitudinally friction locked
Particularly high dynamic forces occur in siphonic roof drainage
Constant distance (35mm) between the rails and the pipe
systems in addition to the expansion forces of PE pipework; this
from 40 – 315mm
is due to high speeds in combination with large volume flows.
The bracketing system must be dimensioned so that all resultant
Anchor point constructions:
forces be safely absorbed.
An anchor point is located at least every 10m in the drainage
system. The anchor points distribute the forces, e. g., from
The Wavin QuickStream bracketing system has been
longitudinal extension to the rail system and from the rail system
independently, externally assessed & accredited as suitable for
to the building. The fasteners must be suitable for these forces.
use in siphonic drainage systems. All forces (caused by static,
This is why the Wavin QuickStream bracketing system includes 3
dynamic and thermal stresses) that occur during operation of a
different anchor rails (parallel rails above the pipe) and appropriate
siphonic drainage system are safely absorbed by the bracketing
accessories (connectors, hangers, etc.), to match the pipe size.
system. The system thus meets the requirements of DIN 1986-
100 dedicated rainwater discharge system.
Type 1) Dimension 40 – 160mm – Rail dimension 30/30mm
Type 2) Dimension 200 – 250mm – Rail dimension 30/45mm
Based on decades of experience Wavin has developed an
Type 3) Dimension 200 – 315mm – Rail dimension 41/62mm
innovative quick-mounting system. The bracketing system is
designed for particularly easy installation. The special clamp
Anchor points can be easily created using anchor point insert
design holds the PE pipe in place during mounting & installation
shells. Complicated arrangement of electrofusion sockets (on
preventing the pipe from moving. This considerably facilitates
both sides) is not required. The insert shells are inserted into the
installation.
pipe clamp, and then the clamp is tightened. This makes it easy
to retroactively create an anchor point construction.
Latching clamp
Rail
Pipe
Ø 40 – 160mm
Ø 200 – 250mm
Ø 315mm
3 4 1 2 3
FP SP SP FP
30/30
Trapezoidal hanger
30/45
6
41/62 30/30 – 30/30 Threaded rods M 10
30/45 – 30/45
30/30 – 30/45
2 Rail hangers
1 Rail connectors
QuickStream
Bracketing System
6
3.2 Wavin QuickStream Bracketing Components
Threaded rod
www.wavin.co.uk
90 0.90 1.40 2.00* Y Vertical pipe clamp (see pages 20 and 21) (see pages 20 and 21)
110 1.10 1.70 2.00* distances
T Fixing distance for anchor 88.5º-Bend 88.5º-Bend 88.5º
125 1.25 1.90 2.00* ≤ 0.8m > 0.8m to 2.0m X X
rail channel -Bend
160 1.60 2.40 2.00* > 2.0m
* The anchor rail must be
200 2.00 3.00 2.00* fastened to the supporting
250 2.00 3.00 2.00* structure at a maximum
315 2.00 3.00 2.00* distance of 0.3m after a fixed
anchor point.
x FP x SP FP x FP x SP xSP FP
FP
Email: technical.design@wavin.co.uk
Fixed anchor point instructions: Building structure connections:
To create a fixed anchor point, inlay shells are used inside the pipe clamps. To prevent the anchor rail being able to move horizontally, a fixed connection to the
For dimensions 40 – 250mm one anchor point inlay shell is used; 2 are used for 315mm. building structure must be made in the following situations:-
When making a fixed anchor point at a welded joint, only complete the anchor connection after the jointing cooling a break in the anchor rail
time has elapsed. a change in direction (including branch connections)
maximum distance between building connections = 12m
only required for pipe lengths > 2.0m
maximum distance between 2 fixed anchor points = 10m
SP before and after branches, bends and reducers.
Note 1: The anchor rail must be fastened to the supporting structure within 0.3m of a fixed anchor point.
The following pages provide a detailed description of the bracketing installation process.
FP Anchor point
with inlay shell
Branch pipe
11
Bracketing System
QuickStream
3.4 Wavin QuickStream Bracketing Installation Principles The following specifications assume a maximum temperature
difference of 40 Kelvin (temperature difference between the
3.4.1 Wavin QuickStream Bracketing Rules installation temperature of the PE material and the expected
operating temperature). For larger temperature differences,
3.4.1.1 Pipe Clamp Distances we recommend the use of long sleeves. – Please refer to the
Appendix for a description of this installation (page 60).
When installing pipes with pipe clamps on anchor rails, make
sure that the maximum installation distances as per Table 1 are
not exceeded.
DN
Max. fastening distance (m)
40 50 56 63 75 90 110 125 160 200 250 315
Horizontal – Ambient Temperature 0.8 0.8 0.8 0.8 0.8 0.9 1.1 1.25 1.6 2.0 2.0 2.0
Vertical 0.9 0.9 0.9 0.9 1.2 1.4 1.7 1.90 2.4 3.0 3.0 3.0
DN
Max. fastening distance (m)
40 50 56 63 75 90 110 125 160 200 250 315
Horizontal 0.6 0.6 0.6 0.6 0.6 0.6 0.7 0.8 1.4 1.4 1.4 1.4
Table 3:
12 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
3.4.2 Building Structure Connections 3.4.3 Fastening Downpipes on The Building Structure
To prevent the anchor rail channel being able to move horizontally All downpipes must be fastened securely to the building structure
due to dynamic forces acting on it, a fixed connection of (walls, columns or beams) using pipe clamps due to resulting
the anchor channel with the building structure (for example, forces. The resulting forces can be absorbed in different ways.
downstand beams) is required every 12m. Fastening the downpipe with an anchor rail channel
(type 1–3)
Additionally, in case of interruptions to the anchor channel Taking the maximum distances between pipe clamps into
(bends, for example), a fixed connection to the building structure consideration (see Table. 1, row 2) downpipes can be
must be created at both ends of the anchor channel. Material fastened on a parallel anchor rail channel. The anchor rail
provided by the customer is used for connecting to the building channel must be fastened using material provided by the
structure material (see Figures. 14-16). customer to, e.g., the exterior walls or concrete columns at
least every 2m.
If the pipe system (anchor channel with pipe) is exposed to Direct fastening of the downpipe without an anchor rail
temperature (e.g. solar radiation or heat sources on the shop channel
floor) on one side, we recommend bracing the anchor channel Downpipes are typically fastened directly to the building
laterally in these areas every 5m. Our project team is glad to structure using threaded pipe clamps without a parallel
support you with your implementation needs. anchor rail channel. The clamp connections safely transfer
the resulting forces into the building. The choice of the
Figure 14: Steel structure Figure 15: Concrete threaded rod dimension depends on the pipe dimension and
downstand beam the distance L between the pipe and the building structure
(see Figure. 17). The required threaded tube dimension can
be read off in table. 4. The distances between pipe clamps
as per Table. 1, row 2 must be observed.
Insert shells are inserted into the pipe clamps as a quick and Figure 21: Anchor point insert Figure 22: Anchor point insert
easy method of creating anchor points. Up to a pipe dimension shell DN 40 – DN 250 shells DN 315 (2 insert shells)
of 250mm, one anchor point inlay shell is used; 2 anchor point
insert shells are used per anchor point for the dimension 315 mm
(see Figures. 21 and 22). The maximum distance between two
anchor points (horizontal/vertical) must not exceed 10m.
Anchor point
with inlay shell FP
Anchor point
with inlay shell
Branch pipe
14 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
3.4.5 Fastening The Anchor Rail Channel must not be exceeded. Depending on the roof structure, it may
be necessary to reduce the distance between the fasteners.
3.4.5.1 Fastening The Anchor Rail Channel on The Before starting the work, the resulting loads (see Table. 5)
Building Structure (e.g. Trapezoidal Roof) on the supporting structure must be coordinated with the
responsible planning office. Table. 5 also shows the total weight
The anchor channel is fastened to the building structure with a of the individual pipe dimensions, including complete filling and
rail hanger, a threaded rod, and the connection to the structural fastening material.
component. The distance between rail hangers as per Table 5
1
Distance “T”
F F F Table 5, Row 1
F
F: Table 5, Row 3
3
2 8
16 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
Table 6: Load dependent distances between fasteners
1 2 3 4 5 6 7 8 9
15 kg/m2 Distance “T” 20 kg/m2 Distance “T” 25 kg/m2 Distance “T”
Da mm F kg/m Tmax m 1-point m 2-point m 1-point m 2-point m 1-point m 2-point m
40 3.40 2.00 2.00 2.00 2.00 2.00 2.00 2.00
50 4.20 2.00 2.00 2.00 2.00 2.00 2.00 2.00
56 4.70 2.00 2.00 2.00 2.00 2.00 2.00 2.00
63 5.40 2.00 2.00 2.00 2.00 2.00 2.00 2.00
75 6.70 2.00 2.00 2.00 2.00 2.00 2.00 2.00
90 8.80 2.00 1.70 2.00 2.00 2.00 2.00 2.00
110 12.10 2.00 1.24 2.00 1.65 2.00 2.00 2.00
125 15.00 2.00 X 2.00 1.33 2.00 1.67 2.00
160 23.30 2.00 X 1.29 X 1.72 X 2.00
200 35.80 2.00 X X X 1.12 X 1.40
250 54.60 2.00 X X X X X X
315 86.90 2.00 X X X X X X
1 2 3 4 5 6 7 8 9
30 kg/m 2 Distance “T” 35 kg/m2 Distance “T” 40 kg/m2 Distance “T”
Da mm F kg/m Tmax m 1-point m 2-point m 1-point m 2-point m 1-point m 2-point m
40 3.40 2.00 2.00 2.00 2.00 2.00 2.00 2.00
50 4.20 2.00 2.00 2.00 2.00 2.00 2.00 2.00
56 4.70 2.00 2.00 2.00 2.00 2.00 2.00 2.00
63 5.40 2.00 2.00 2.00 2.00 2.00 2.00 2.00
75 6.70 2.00 2.00 2.00 2.00 2.00 2.00 2.00
90 8.80 2.00 2.00 2.00 2.00 2.00 2.00 2.00
110 12.10 2.00 2.00 2.00 2.00 2.00 2.00 2.00
125 15.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00
160 23.30 2.00 1.29 2.00 1.50 2.00 1.72 2.00
200 35.80 2.00 X 1.68 X 1.96 1.12 2.00
250 54.60 2.00 X X X 1.28 X 1.47
315 86.90 2.00 X X X X X X
Explanation of columns
1 Pipe dimensions
2 Weight of pipe dimensions (filled, including fasteners)
3 Maximum distance between anchor channel fasteners
4, 6, 8 Installation using single-point hangers (see Figure 25)
5, 7, 9 Installation using two-point hangers – Load distribution (see Figure 26)
X Fastening with one-or two-point hangers not possible. In this case, a project-specific, custom solution must be developed (e. g., suspending the drainage system on steel beams).
18 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
3.4.6 Fastening The Roof Outlet Connection Pipes When installing the pipe clamps, make sure that the maximum
horizontal fastener distance as per Table 1, page 15, is observed.
No fastener is required for horizontal connecting pipes up to To prevent high forces acting on the roof inlet due to expansion
a length of 0.8m (see Figure 27). For connecting pipes > 0.8m of the vertical connecting pipe, the distance between the first
to 2.0m (see Figure 28), the pipe should be fastened directly pipe clamp to the roof inlet should not be less than 0.5m.
to the load bearing component without an anchor rail channel
using material provided by the customer. Horizontal connecting When using the vapour barrier with drainage connection (see
pipes > 2.0m always require a parallel anchor rail channel, and page 38) the connecting pipe must always be secured against
at least one anchor point clamp (see anchor point insert shells in dropping.
Section 3.4.4).
88.5º-Bend
≤ 0.8m
Figure 28: Drain connecting pipe > 0.8m – 2m (Installation without anchor channel)
88.5º-Bend
> 0.8m to 2.0m
Figure 29: Drain – connecting pipe > 2.0m (Installation with anchor channel)
88.5º-Bend
X X
> 2.0m
H3 H2
H1
r(5.5) Not
20 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
4.3 Wavin QuickStream QS-M-75 Roof Outlets
Roof cutout:
30
20
10
0
0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00
Drainage performance in l/s
Vapour barrier connection Vapour barrier with drainage Insulating block, non-
set 40 – 75mm connection (only with 75mm flammable, pressure seal
linear expansion socket) type
2 2
5
9
8 4
10
12
13
16 5
17
6
3 Nuts M8 (8 pcs.)
4 Loose flange 12
5 Roof foil
6 EPDM seal 13
16 Reinforcement plate
22 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
4.3.2 Roof Outlet QS-M-75-260, Compression Flange Type
Roof cutout:
40
40 – 75mm
30
20
10
0
0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00
Drainage performance in l/s
Vapour barrier connection Vapour barrier with drainage Insulating block, non- Backup ring 44.5mm
set 40 – 75mm connection (only with 75mm flammable, pressure seal
linear expansion socket) type
6 2 2
5
8 3
10
9 11
4
13 14
17
6
18
7
10
3 Nuts M8 (8 pcs.)
4 Loose flange 13
7 EPDM seal 15
16
16
8 Roof drain inlet element (2.5“ connection)
11 Roof insulation
17 Reinforcement plate
24 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
4.3.3 Roof Outlet QS-M-75-260, Compression Flange
Type, Gravel Protection
Roof cutout:
40 – 75mm
Water backup in mm
40
30
20
10
0 18.00
0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00
Drainage performance in l/s
Vapour barrier connection Vapour barrier with drainage Insulating block, non-
set 40 – 75mm connection (only with 75mm flammable, pressure seal
linear expansion socket) type
5
2 2
4 3
9
8
10 4
12
13
16
5
17
6
5 Roof foil
6 EPDM seal 13
10 Roof insulation 16
16 Reinforcement plate
26 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
4.3.4 Roof Outlet QS-M-75-400, Bitumen Type
Roof cutout:
30
20
10
0
0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00
Drainage performance in l/s
Vapour barrier connection Vapour barrier with drainage Insulating block, non-
set 40 – 75mm connection (only with 75mm flammable, pressure seal
linear expansion socket) type
2 3
6
5
7
9 10 3
13
14
7 Roof insulation 12
11
12
8 Vapour barrier connection screws (6 pcs.)
13 Reinforcement plate 14
28 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
4.3.5 Roof Outlet QS-M-75-260, Bitumen Type
Roof cutout:
40
30
20
10
0
0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00
Drainage performance in l/s
Figure 35. Performance chart roof outlet QS-M-75-260, bitumen type (DIN EN 1253)
Vapour barrier connection Vapour barrier with drainage Insulating block, non- Backup ring 44.5mm
set 40 – 75mm connection (only with 75mm flammable, pressure seal
linear expansion socket) type
3
2
5
7
6 4
3
8
10
11
14
15
5
8
1 Wing nuts (2 pcs.) 9
8 Roof insulation
14
9 Vapour barrier connection screws (6 pcs.)
14 Reinforcement plate
15 Trapezoidal roof (alternatively concrete slab)
30 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
4.3.6 Roof Outlet QS-M-75-260, Bitumen Type, Gravel
Protection
Roof cutout:
40
30
20
10
0
0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00
Drainage performance in l/s
Vapour barrier connection Vapour barrier with drainage Insulating block, non-
set 40 – 75mm connection (only with 75mm flammable, pressure seal
linear expansion socket) type
1
4 2
5 2
7 8
6
10
11
14 3
15
3 Gravel protection
8
4 Roof sheet (bitumen) 9
14 Reinforcement plate 15
32 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
4.3.7 Roof Outlet QS-M-75-260, Rain Gutter Type
Roof cutout:
40
30
20
10
0
0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00
Drainage performance in l/s
PE outlet connector 40 –
75mm
6
2
9 4
6 5
6 Gutter
8 Mating flange
34 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
4.3.8 Roof Outlet Accessories
Technical data:
Heating power: 10W
Supply voltage: 230V/~50Hz
A/C power supply
Long connection cable: 1.5m
If the on-site roof insulation cannot be laid due to rain, the Wavin
QA vapour barrier with drainage connection prevents delays in
the installation work. When installing the vapour barrier with a
230mm
36 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
Pipe and Fittings
QuickStream
5. Wavin QuickStream Pipes and Quality assurance
All pipes and fittings are subject to continuous internal quality
Fittings
controls. In addition, the pipe system is externally monitored
by Materialprüfanstalt Darmstadt. The pipe system meets the
5.1 Technical Data
requirements of the Building Regulations List A Part 1 Issue
2003/1 Section 12.1.8 published technical rules as per DIN EN
Material
1519-1:2001-01 in conjunction with DIN 19535-10:200-01.
Wavin QuickStream pipes and fittings are made of HDPE.
Colour
Black
Marking
Wavin QuickStream, nominal width, year of manufacture,
material, audit mark, fire class: B2
Physical properties
Melt index 0.3 to 0.89 g/10 min
Thermal expansion coefficient 0.2 mm/mºC
UV-resistant through carbon fraction of 2 to 2.5%
Burning behaviour DIN 4102 B2 Pressure levels (SDR
classes)
Note on transporting and storing PE pipes and fittings
During the installation of Wavin QuickStream pipework, basically
PE pipes must be protected against damage during transport
two pressure levels can be used. For pipe sizes greater than
and particularly during loading and unloading. Before unloading,
DN 200 reinforced material may be required due to the negative
the pipes must be inspected for damage in transit. Where lifting
pressure load on the pipe. The required pressure strength is
equipment is used wide straps are recommended. Nonpalletised
determined by a calculation.
pipes should be supported over their entire length where
possible, and must be secured against rolling apart. The cargo
Pipe data
area and storage location must be free of sharp objects. Do not
store loose pipes over 1m in height.
DN d1) di2) s 3) SDR4) Px5)
40 40 34.0 3.0 13.6 – 900
Please note: Single-sided exposure to temperature, e.g. solar
50 50 44.0 3.0 17 – 900
radiation, can cause short-term deformation of the pipes. For
56 56 50.0 3.0 17 – 900
this reason, the pipes must be protected against direct sunlight.
63 63 57.0 3.0 21 – 900
75 75 69.0 3.0 26 – 900
Keep fittings clean by storing inside buildings or containers and
90 90 83.0 3.5 26 – 900
110 110 101.4 4.3 26 – 900 unpack just before use. Always store rubber fittings in a cool
125 125 115.2 4.9 26 – 900 place, free from direct sunlight.
160 160 147.6 6.2 26 – 900
200 200 187.6 6.2 33 – 450
200 200 184.6 7.7 26 – 900
250 250 234.4 7.8 33 – 450
250 250 230.8 9.6 26 – 900
315 315 295.4 9.8 33 – 450
315 315 290.8 12.1 26 – 900
1. Outer diameter in mm
2. Inner diameter in mm
1,00 m
3. Wall thickness in mm
4. SDR class
5. Max vacuum pressure in mbar
Electrofusion sockets are equipped with a resistance wire. Heat Step 4a Step 4b
is applied to the weld zones by means of a welding device (see
page 56). Polyethylene expands on melting and this expansion
creates the necessary welding pressure. Wavin electrofusion
machines automatically apply the energy needed for correct
welding.
38 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
9. After scraping, the surface of the weld zone must be Step 13 Step 14
cleaned with PE cleaner
Use a clean, lint-free cloth for cleaning. Keep the weld zone
clean after cleaning.
10. Again mark the insertion depth on the insert part (it may
no longer be visible through scraping)
Step 9 Step 10
11. Also clean the inside of the electrofusion socket with a 5.2.2 Butt Fusion Welding
clean, lint-free cloth
After cleaning, allow the cleaner to briefly dry (for a few Butt fusion welding is a very economical jointing technique.
seconds). Keep the weld zone clean after cleaning. Correctly made butt-welds reach the strength of the pipe.
12. After preparing the pipe ends and fittings, the Well-trained personnel are recommended for making butt-welds.
electrofusion socket can be pushed onto the tube/fitting
It is especially important that the entire insert depth of the In butt welding, two pipe ends, two fitting ends or a pipe end
electrofusion socket is used, and that the pipe is stress free. and a fitting end are bonded by melting the circular pipe faces
simultaneous and pressing these together. Butt fusion welding
Step 11 Step 12 can only be performed using a butt fusion welding machine.
Step 4 Step 5 11. Maintain heat soaking till a bead is formed of approximate
1mm for diameters 40 up to 200 and 1.5mm for diameters
250 and 315mm
Use the figures mentioned in table 7 as guidance for the
heat soaking duration.
Step 6 Step 7
12. After heating time is elapsed, quickly open the welding
machine, remove the heater plate and close immediately
This part of the welding operation must be kept as short as
possible in order not to loose too much heat!
Step 12
40 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
Table 8: Guidance of the minimum cooling time (in seconds) for Step 1
butt fusion welding at 20ºC.
250 280
315 340
Step 5
Table 9. Insertion depth of pipes into an expansion socket, max. pipe length 6m
Pipe diameter mm
Ambient
≤ 50 63 75 90 110 125 160 200 250 315
temperature
Insertion depth in [mm] for pipe length of 6m
-10ºC 65 70 70 80 85 90 100 140 140 140
0ºC 75 80 80 90 95 100 110 150 150 150
+10ºC 85 90 90 100 105 110 120 160 160 160
+20ºC 95 100 100 110 115 120 130 170 170 170
+30ºC 105 110 110 120 125 130 140 180 180 180
In humid environments there can be a need to insulate the pipe Like any rainwater system, siphonic roof drainage systems
system to prevent condensation and subsequent water dripping. generate noise when transporting rainwater. In sensitive areas
Condensation can happen when the relative humidity is above within buildings such as offices, concert halls, courthouses and
40%. Commonly the temperature in the top of buildings is rather hospitals, where noise should be kept to a minimum level, it is
high. recommended to wrap the Wavin QuickStream system in the
relevant area with acoustic insulation sheets.
42 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
Product Details
QuickStream
6. Product Range
Description Part
Number
QS-M-75-400 outlet – membrane 4029737
QS-M-75-400 outlet – bitumen welding 4029740
QS-M-75-260 outlet – membrane 4036539
QS-M-75-260 outlet – membrane, gravel 4029739
QS-M-75-260 outlet – bitumen welding 4036540
QS-M-75-260 outlet – bitumen, gravel 4029741
QS-M-75-260 outlet – gutter 4029738 4029738 4029738 4029738
Description Part
Number
QS PE outlet connector BL 40x2,5" L=0.4 3011033
QS PE outlet connector BL 50x2,5" L=0.4 3011034
QS PE outlet connector BL 56x2,5" L=0.4 3011035
QS PE outlet connector BL 63x2,5" L=0.4 3011036
QS PE outlet connector BL 75x2,5" L=0.4 4025977
QS vapour barrier connection set – 50mm 3021234
QS vapour barrier connection set – 75mm 3021231
QS vapour barrier drainage fitting 4025968
QS-M-75 Back up Ring 4042217
QS-M-75 Insulating Block – membrane 4038062
QS-M-75 Insulating Block – bitumen 4038063
QS Heat-coil membrane 230 V/10 W 4044412
QS Heat-coil bitumen 230 V/10 W 4025997
Trapeze Hangers*
Description Part
Number
QuickStream trapeze-hanger+cross-beam 4024418
*For the transition from a trapezoidal roof to a threaded rod anchor M10. For suspending
the anchor channel on e. g., concrete roofs, wooden structures or other components
additional fastening material is required.
Threaded Rod*
*Connecting piece between the fastener and the load-bearing component (e.g. trapeze
hangers) and the channel support.
44 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
Rail Hangers*
DN – DN Description Part
(mm) Number
40 – 160 QS rail hanger 30x30mm 4011962
For rail type 1 200 – 250 QS rail hanger 30x45mm 4023272
315 QS rail hanger 41x62mm 4024522
*For transitioning between anchor rails (type 1 – 3) and M10 threaded rod fasteners.
Rail Connectors*
*The type 2 rail connector (DN 200 – DN 250) can also be used to create a longitudinal
frictional joint between the anchor channel types 30/30mm and 30/45mm.
Description Part
Number
QS fixed point inlay-jacket 40 4012330
QS fixed point inlay-jacket 50 4012332
Anchor point insert shells
DN 40 – DN 250
QS fixed point inlay-jacket 56 4012346
QS fixed point inlay-jacket 63 4012334
QS fixed point inlay-jacket 75 4012336
QS fixed point inlay-jacket 90 4012338
QS fixed point inlay-jacket 110 4012340
QS fixed point inlay-jacket 125 4012342
QS fixed point inlay-jacket 160 4012344
QS fixed point inlay-jacket 200 4023374
QS fixed point inlay-jacket 250 4023375
Fixed-point loading shells DN 315 QS fixed point inlay-jacket 315* 4023376
(2 insert shells)
46 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
Sliding Pipe Clamps
Threaded Pipe
48 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
Wavin DUO Electrofusion Couplers
For welding with the DUO "Cubo" socket welder. DN 40 – 150 also with Geberit or Geberit
compatible devices.
Dimensions (mm)
d ts
40 – 160 82
200 – 315 370
*Welded type.
50 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
PE Eccentric Reducer Long
*Welded type.
*Welded type.
52 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
PE Branch 45 Degrees
*Welded type.
54 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
6.4 Tools and Accessories
Electrofusion Welding Tool DUO "315"*
• Supplied with two different welding cables, which must
be used as follows:
—— Dimension 40 – 160mm: green welding cable
—— Dimension 200 – 315mm: brown welding cable
• Observe the installation and processing instructions
when using the welding tool
Description Part
Number
Electrofusion welding tool DUO 315 4036330
*The DUO "315" electrofusion welding tool is for creating longitudinal frictional joints. The
tool is designed exclusively for welding Wavin Duo and Geberit* brand, or Geberit
compatible* electrofusion sockets (*up to max. 160mm).
Description Part
Number
VR 160, 40 – 160mm 4011398
Description Part
Number
Media 250, 75 – 250mm 4011401
Description Part
Number
Maxi 315, 90 – 315mm 4011402
PE Pipe Cutter
DN Part
(mm) Number
40 – 63 4026014
50 – 125 4011390
110 – 160 4011393
200 – 315 4011396
Pipe Scraper
• Delivery period on request
DN Part
(mm) Number
75 – 315 4026921
Description Part
Number
PE marker pen China Marker 4011453
PE pipe scraper 4025891
PE cleaner 0.7 litre bottle 4025509
56 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
General Information
QuickStream
7. Commissioning and Maintenance 7.2 Maintenance
7.1 Commissioning In line with DIN 1986-30 the following maintenance must
be performed for roof drainage systems as a minimum
As a Wavin QuickStream roof drainage system operates at requirement:
both positive and negative pressures, it is necessary to carry The roof and roof outlets must be maintained regularly. This
out a leak tightness test: includes, e. g., cleaning the roof and the roof outlets and
Close the discharge of Wavin QuickStream system and fill runoffs (wall edge openings). The completeness of the roof
up the system with water to roof level outlets must be checked. Missing components must be
Check all the connections for leakages replaced
Unplug the discharge on completion of the inspection For roof outlets, check whether the inlet is freely accessible.
If the building is over 40m high, the pipe system needs to be To do this, you can, remove the functional part of the
split up in to sections no higher than 40m roof outlet. All components must be reinstalled after
maintenance
The following steps are also recommended for commissioning Maintenance (especially cleaning) must be carried out at
the system: least twice a year, typically Spring and Autumn, directly
Check the installed system (pipe dimensions, roof drain after the trees have dropped their seeds and after leaf
numbers and positions). It must be ensured that the system fall. Depending on local conditions (e. g., trees), it may be
was implemented as per the current state of planning necessary to adjust the maintenance intervals
(dimensions, pipe guide) Inspect the emergency overflow chamber at least once a
Based on the planning requirements check that all fasteners year
(anchor points, building shell connections, fastening
distances) have been implemented as per the installation
guidelines
Check the emergency run-off system. Number, positions
and dimensions of wall edge openings
In the case of emergency drainage through a separate
piping system, verify that the piping system is routed to an
area that can be flooded without damage. (The emergency
drainage system must not be connected to the sewer
system)
The roof and roof outlets must be cleaned before
commissioning. While doing so, check the roof outlets for
completeness. If any components are missing, you must
replace them
In the case of roof outlets for emergency drainage, check
whether the back-up ring has been assembled as per the
plans
8. Appendices
58 Wavin QuickStream PIM Customer Services: 0844 856 5152 Technical Advice: 0844 856 5165
Distance between two roof outlets >10m
Anchor point type >A< branch Anchor point type >B< sections > 10m Anchor point type >C< - deflector
Long sleeve socket in combination with Anchor point clamp with long sleeve Anchor point clamp with 2 electrofusion
anchor point clamp in flow direction socket. sockets.
upstream of branch.