The document provides recommendations for controlling critical safety and health hazards during bunkering processes. It lists installing more fire sprinkler systems, isolating crews after bunkering to clean spills, conducting toolbox talks, and providing protective equipment as measures to control fire hazards. For noise hazards, it recommends installing sound absorbing materials, conducting safety training, monitoring crew noise exposure, and providing ear protection.
Original Description:
Control Measures For Critical Safety & Health Hazards
The document provides recommendations for controlling critical safety and health hazards during bunkering processes. It lists installing more fire sprinkler systems, isolating crews after bunkering to clean spills, conducting toolbox talks, and providing protective equipment as measures to control fire hazards. For noise hazards, it recommends installing sound absorbing materials, conducting safety training, monitoring crew noise exposure, and providing ear protection.
The document provides recommendations for controlling critical safety and health hazards during bunkering processes. It lists installing more fire sprinkler systems, isolating crews after bunkering to clean spills, conducting toolbox talks, and providing protective equipment as measures to control fire hazards. For noise hazards, it recommends installing sound absorbing materials, conducting safety training, monitoring crew noise exposure, and providing ear protection.
6.1. CONTROL MEASURES FOR CRITICAL SAFETY & HEALTHHAZARDS
CRITICAL SAFETYHAZARDS
6.1.1. FIRES HAZARD
NO. CONTROL MEASURES EXPLANATION OF CONTROL MEASURES
1 ELIMINATION N/A 2 SUBSTITUATION N/A 3 Isolate crews of vessels after complete the bunkering ISOLATION process to clean the oil spillages. 4 ENGINEERING Installation more fire sprinkler system (automatic CONTROL actuation) in the vessels. 5 ADMINISTRATIVE Conduct a toolbox talks to crews before start a bunkering CONTROL process. 6 (PPE) PPE such a coverall, safety shoes and mask.
CRITICAL HEALTH HAZARDS
6.1.2. NOISE HAZARD
NO. CONTROL EXPLANATION OF CONTROL MEASURES
MEASURES 1 ELIMINATION N/A 2 SUBSTITUATION N/A 3 ENGINEERING Installation of sound absorbing materials and CONTROL soundproofing that reduce noise hazard. 4 ADMINISTRATIVE Conduct safety training and monitor the noise level to the CONTROL crew. 5 (PPE) PPE such as ear muffs and ear plugs.