Professional Documents
Culture Documents
Defy Corrosion
By building concrete bridge decks having no internal steel
reinforcement, Canada is eliminating the source of corrosion
problems
By Baidar Bakht and Aftab A. Mufti foot of steel Transportation of Ontario have gone
reinforce- even further in exploiting the arch
he cancerous corrosion of ment when designed for bending. action of deck slabs. Based on tests on
T reinforcing steel in highway
bridge decks exposed to salt-
However, the Ontario Highway
Bridge Design Codes of 1979, 1983,
both small- and large-scale laboratory
models, they concluded that a deck
laden air or deicing salts leads to and 1992 (Ref. 1) included an empiri- slab supported by parallel longitudi-
ongoing problems of maintenance, cal design method for deck slabs that nal beams does not require any rein-
repair, and even deck replacement. But took into account their inherent arch- forcement, provided that the slab is
recent Canadian research and ensuing ing action in such slabs. Following the suitably confined in both longitudinal
code developments now point the way OHBDC method, designers could and transverse directions (Ref. 2). In
to a cure: Build concrete bridge-deck reduce steel content of the slabs by the longitudinal direction, the deck
slabs free of internal steel reinforce- approximately one-third. Hundreds of slab is confined by making it compos-
ment. The satisfactory performance of deck slabs have been designed by this ite with the beams and by using edge
the steel-free deck slabs of five method in Ontario and in other parts beams having suitably high flexural
Canadian bridges under unrestricted of the world. rigidity in the plane of the slab.
traffic solidly supports the validity of Researchers at Dalhousie Uni-
the concept. versity, Halifax, Nova Scotia (former-
ly the Technical University of Nova
Relying on arch action Scotia), and at the Ministry of
The typical concrete slab-on-gird-
er highway bridge deck, with support-
ing girders spaced at about 7 feet,
requires roughly 6 pounds per square
41 inches
distributed low-modulus fibers in the
7.3 inches GFRP Bars concrete. The requirement for the
5.1 inches
addition of fibers is quantified
through an index Ri, which is
obtained as the ratio of load required
2 x 0.8-inch to fail a precracked beam to the load
Steel Strap required to crack the beam.
@ 3.9 feet
Chatham, Ontario Steel plate, 6.9 0.55 First steel-free deck slab in reha-
7 ft (8.4 lb/cu yd) bilitation work; transverse con-
finement by welded steel straps.
CFRP reinforcement for trans-
verse negative bending.
Crowchild Trail, Steel plate, 7.3 0.44 First steel-free deck slab on con-
Calgary, Alberta 6.6 ft (6.7 lb/cu yd) tinuous-span bridge; transverse
confinement by studded straps,
and GFRP reinforcement for
transverse negative moment.
Waterloo Creek, Precast concrete, 7.5 0.44 First steel-free deck slab on pre-
British Columbia 9.2 ft (6.7 lb/cu yd) cast concrete girders; transverse
confinement by studded straps.
Figure 2. View from steel-free slab. A primary reason for
below the deck of the the 6% premium for the steel-free slab
Salmon River Bridge was that the contractor, having no
in Nova Scotia shows experience with fiber-reinforced con-
the steel straps weld- crete, was wary of problems with the
ed to the top flanges new mix. His apprehension proved
of the girders to pro- unjustified. As demonstrated on
vide transverse con- another project, a steel-free deck slab
finement for the steel- can be more economical than conven-
free deck slab. tional reinforced concrete, even on a
first-cost basis. Enhanced durability
makes it even more economical on a
life-cycle-cost basis.
Chatham Bridge. The second
steel-free deck slab, only 6.9 inches
the Salmon River in Nova Scotia has The deck is supported on steel thick, was cast on the existing steel
two simply supported spans, each 102 plate girders spaced 8.9 feet on center. girders of a highway bridge in
feet long. One of the spans has an 8.9- Straps welded to the top flange of the Chatham, Ontario, in 1996. Because
inch-thick concrete deck slab, with girders at a spacing of 3.9 feet provide it has cantilever overhangs, which
steel reinforcement designed by the transverse confinement (Fig. 2). require some reinforcement, it con-
empirical method of the OHBDC Because of the virtual absence of can- tains a grid of carbon-fiber-reinforced
(Ref. 1). The other span has a 7.9- tilever overhangs, and a direct connec- plastic (CFRP) near the top surface.
inch-thick concrete slab containing no tion of the barrier wall to the cross Transverse confinement was provided
tensile reinforcement, but with frames of the bridge, the steel-free by galvanized steel straps welded to
chopped polypropylene fibers ran- deck is not subject to transverse nega- the top flanges of the girders at a 3.3-
domly mixed at a volume of 0.55% tive moments calling for supplemen- foot spacing. As in all bridges using
(8.4 pounds per cubic yard). Since tary reinforcement. this technology, the straps lie well
eastbound traffic passes over the steel- The contractor quoted the follow- clear of the haunched slab. With a
reinforced deck and then over the ing unit prices (Canadian) for the large gap between the straps and the
steel-free deck, this structure provides Salmon River bridge deck: $13.28 per slab, crews had no difficulty removing
an excellent opportunity for compar- square foot for the conventional slab the slab formwork. The unit cost of
ing the performance of conventional and $14.12 per square foot for the the deck slab was significantly higher
and steel-free deck slabs (Ref. 3).