You are on page 1of 4

Steel-Free Bridge Decks

Defy Corrosion
By building concrete bridge decks having no internal steel
reinforcement, Canada is eliminating the source of corrosion
problems
By Baidar Bakht and Aftab A. Mufti foot of steel Transportation of Ontario have gone
reinforce- even further in exploiting the arch
he cancerous corrosion of ment when designed for bending. action of deck slabs. Based on tests on
T reinforcing steel in highway
bridge decks exposed to salt-
However, the Ontario Highway
Bridge Design Codes of 1979, 1983,
both small- and large-scale laboratory
models, they concluded that a deck
laden air or deicing salts leads to and 1992 (Ref. 1) included an empiri- slab supported by parallel longitudi-
ongoing problems of maintenance, cal design method for deck slabs that nal beams does not require any rein-
repair, and even deck replacement. But took into account their inherent arch- forcement, provided that the slab is
recent Canadian research and ensuing ing action in such slabs. Following the suitably confined in both longitudinal
code developments now point the way OHBDC method, designers could and transverse directions (Ref. 2). In
to a cure: Build concrete bridge-deck reduce steel content of the slabs by the longitudinal direction, the deck
slabs free of internal steel reinforce- approximately one-third. Hundreds of slab is confined by making it compos-
ment. The satisfactory performance of deck slabs have been designed by this ite with the beams and by using edge
the steel-free deck slabs of five method in Ontario and in other parts beams having suitably high flexural
Canadian bridges under unrestricted of the world. rigidity in the plane of the slab.
traffic solidly supports the validity of Researchers at Dalhousie Uni-
the concept. versity, Halifax, Nova Scotia (former-
ly the Technical University of Nova
Relying on arch action Scotia), and at the Ministry of
The typical concrete slab-on-gird-
er highway bridge deck, with support-
ing girders spaced at about 7 feet,
requires roughly 6 pounds per square

The Crowchild Trail Bridge in Calgary, Alberta, prior to deck reha-


bilitation with a steel-free concrete slab 7.3 inches thick. Figure 1
(next page) shows design details of the deck rehabilitation.
ments for the transverse confinement
0.75-inch diam. Double- system, which is essential to ensure
Headed Stainless
Steel Bar @ 12 inches arch action in the slab. To control
3 - 0.87-inch diam. early cracking, CHBDC sets minimum
Studs on Straps GFRP Bars requirements for the use of randomly

41 inches
distributed low-modulus fibers in the
7.3 inches GFRP Bars concrete. The requirement for the
5.1 inches
addition of fibers is quantified
through an index Ri, which is
obtained as the ratio of load required
2 x 0.8-inch to fail a precracked beam to the load
Steel Strap required to crack the beam.
@ 3.9 feet

6.6 feet 6.6 feet 3.4 feet


Success stories
The four cast-in-place bridge-
deck slabs described here, all built in
Figure 1. A cross-sectional view of Transversely, slab confinement is pro- Canada between 1995 and 1998, have
the Crowchild Trail Bridge after vided by keeping the top flanges of the successfully applied the steel-free
rehabilitation. Studded steel girders from moving laterally (for design concept. A fifth bridge deck
straps laid directly on the steel example, by welding steel straps to (Ref. 4), constructed in British
girders, but not welded, provide them). Where deck slabs cantilever Columbia in 1997, has precast deck
transverse confinement. out beyond the girders, some rein- panels made without internal steel. All
Haunching of the steel-free slab forcement may be needed. of these bridge-deck slabs contain
above the girders leaves space for polypropylene fibers to reduce plastic
form removal and minimizes strap New code provisions shrinkage cracking and to provide
contact with the slab. Because of As a result of significant research post-crack ductility for the slab under
the cantilever overhang, GFRP and experimental construction in the load. The fibers are considered sec-
bars were used to resist trans- field, the new Canadian Highway ondary reinforcement and do not
verse negative moments. A solid Bridge Design Code (Ref. 5), succes- enhance the strength properties of the
barrier rail also was added. sor to OHBDC, includes provisions concrete.
for steel-free deck slabs. The new code Salmon River Bridge. The first
requires the thickness of a steel-free steel-free deck slab was constructed
deck slab to be at least 6.9 inches or 1⁄15 on the Trans Canada Highway and
of the beam spacing, whichever is opened to traffic in December 1995.
larger. The code also defines require- The steel-plate-girder bridge across

Comparison of Canadian bridge-deck slabs


built without internal steel
Bridge Girder type, Slab Polypropylene fiber Unique features
spacing thickness, content, % by volume
in.
Salmon River, Steel plate, 7.9 0.55 First steel-free deck slab in new
Kemptown, Nova 8.9 ft (8.4 lb/cu yd) construction; transverse confine-
Scotia ment by welded steel straps.

Chatham, Ontario Steel plate, 6.9 0.55 First steel-free deck slab in reha-
7 ft (8.4 lb/cu yd) bilitation work; transverse con-
finement by welded steel straps.
CFRP reinforcement for trans-
verse negative bending.

Crowchild Trail, Steel plate, 7.3 0.44 First steel-free deck slab on con-
Calgary, Alberta 6.6 ft (6.7 lb/cu yd) tinuous-span bridge; transverse
confinement by studded straps,
and GFRP reinforcement for
transverse negative moment.

Waterloo Creek, Precast concrete, 7.5 0.44 First steel-free deck slab on pre-
British Columbia 9.2 ft (6.7 lb/cu yd) cast concrete girders; transverse
confinement by studded straps.
Figure 2. View from steel-free slab. A primary reason for
below the deck of the the 6% premium for the steel-free slab
Salmon River Bridge was that the contractor, having no
in Nova Scotia shows experience with fiber-reinforced con-
the steel straps weld- crete, was wary of problems with the
ed to the top flanges new mix. His apprehension proved
of the girders to pro- unjustified. As demonstrated on
vide transverse con- another project, a steel-free deck slab
finement for the steel- can be more economical than conven-
free deck slab. tional reinforced concrete, even on a
first-cost basis. Enhanced durability
makes it even more economical on a
life-cycle-cost basis.
Chatham Bridge. The second
steel-free deck slab, only 6.9 inches
the Salmon River in Nova Scotia has The deck is supported on steel thick, was cast on the existing steel
two simply supported spans, each 102 plate girders spaced 8.9 feet on center. girders of a highway bridge in
feet long. One of the spans has an 8.9- Straps welded to the top flange of the Chatham, Ontario, in 1996. Because
inch-thick concrete deck slab, with girders at a spacing of 3.9 feet provide it has cantilever overhangs, which
steel reinforcement designed by the transverse confinement (Fig. 2). require some reinforcement, it con-
empirical method of the OHBDC Because of the virtual absence of can- tains a grid of carbon-fiber-reinforced
(Ref. 1). The other span has a 7.9- tilever overhangs, and a direct connec- plastic (CFRP) near the top surface.
inch-thick concrete slab containing no tion of the barrier wall to the cross Transverse confinement was provided
tensile reinforcement, but with frames of the bridge, the steel-free by galvanized steel straps welded to
chopped polypropylene fibers ran- deck is not subject to transverse nega- the top flanges of the girders at a 3.3-
domly mixed at a volume of 0.55% tive moments calling for supplemen- foot spacing. As in all bridges using
(8.4 pounds per cubic yard). Since tary reinforcement. this technology, the straps lie well
eastbound traffic passes over the steel- The contractor quoted the follow- clear of the haunched slab. With a
reinforced deck and then over the ing unit prices (Canadian) for the large gap between the straps and the
steel-free deck, this structure provides Salmon River bridge deck: $13.28 per slab, crews had no difficulty removing
an excellent opportunity for compar- square foot for the conventional slab the slab formwork. The unit cost of
ing the performance of conventional and $14.12 per square foot for the the deck slab was significantly higher
and steel-free deck slabs (Ref. 3).

Figure 3. The first known steel-


free deck slab on precast con-
crete girders was placed on this
British Columbia bridge, opened
to traffic in 1998. Studded
straps at a 4.1-foot spacing pro-
vide transverse confinement for
the 7.5-inch-thick slab.
than that of a conventional deck, Patented technology
however, due to the use of the expen- The concepts of both cast-in-place
sive CFRP grid for negative reinforce- and precast steel-free deck slabs are
ment. Such an increase in initial cost is protected by patents. The patent for
unlikely to be acceptable to most cast-in-place, steel-free deck slabs has
bridge owners, even though the life- been granted in the United States, the
cycle cost is favorable. United Kingdom, and France, and is
Crowchild Trail Bridge. The pending in Germany, Canada, and
Crowchild Trail Bridge, Calgary, Japan. A global patent for steel-free
Alberta, was rehabilitated with a new precast arch panels is pending.
steel-free deck slab and reopened to Licensing opportunities for use of the
traffic in 1997. The 7.3-inch-thick patented technology are available.
slab rests on steel plate girders at 6.6- The chief benefits of a steel-free
foot spacings (Fig. 1). Having can- concrete bridge deck are lower life-
tilever overhangs, it resembles the cycle and user costs. By eliminating
Chatham bridge deck, but less-expen- the source of corrosion, designers can
sive glass-fiber-reinforced-plastic extend the service life of the deck and
(GFRP) rods were used to provide substantially cut maintenance and
reinforcement for the transverse can- repair costs. In addition, there is less
tilever moments and for the barrier need to delay or reroute traffic for
walls. Because of girder continuity deck repairs. ■
over three spans, longitudinal GFRP
rods also were needed to resist crack- Baidar Bakht is adjunct professor of
ing stresses over the two piers. civil engineering at Dalhousie
The cast-in-place deck slab con- University, Halifax, Nova Scotia, and
tains polypropylene fibers at a volume vice president, of JMB Structures
Research Inc., Toronto. Aftab A. Mufti
of 0.44%. Straps containing welded is professor of civil engineering and
shear studs directly over the girders director of the Nova Scotia CAD/Cam
provide transverse confinement, and Centre, Dalhousie University. Both
despite the lack of a direct connection authors are professional engineers.
to the girders, are as effective as weld-
ed straps. References
1. Ontario Highway Bridge Design Code
In this rehabilitation project,
(OHBDC), Ministry of Transportation of
alternative bids were sought for con- Ontario, Downsview, Ontario, Canada,
ventional as well as steel-free deck 1979, 1983, and 1992.
slabs. The steel-free slab had the lower 2. Aftab A. Mufti, Baidar Bakht, and
bid, thus confirming that the more Leslie G. Jaeger, Bridge Superstructures:
durable slab can also be cheaper. New Developments, National Book
Waterloo Creek Bridge. Opened Foundation, Islamabad, Pakistan, 1996.
3. John P. Newhook and Aftab A. Mufti,
to traffic in 1998, the Waterloo Creek “A Reinforcing Steel-Free Concrete Deck
Bridge in British Columbia is made up Slab for the Salmon River Bridge,”
of precast concrete girders with a sin- Concrete International, June 1996, pp.
gle span of 82 feet, spaced 9.2 feet on 30-34.
center (Fig. 3). The steel-free deck slab 4. Baidar Bakht and Aftab A. Mufti,
is 7.5 inches thick. Like the Salmon “Taking the Steel Reinforcement Out of
River structure, this bridge has no Precast Bridge Deck Slabs,” The Concrete
Producer, January 1999, pp. 45-49.
cantilever overhangs and thus needs 5. Canadian Highway Bridge Design
no transverse tension reinforcement. Code, issued by the Canadian Standards
Horizontal loads on the barrier rails Association, Toronto, 1998.
are transferred directly to the concrete
girders and steel cross frames. Studded Publication #C00B087
straps at a 4.1-foot spacing provide Copyright© 2000, The Aberdeen Group
transverse confinement. a division of Hanley-Wood, Inc.
All rights reserved

You might also like