Professional Documents
Culture Documents
Arc Flash
Example 1
This document and the information within it are confidential and proprietary to ETAP/Operation
Technology, Inc. and may not be modified, copied, published, disclosed, distributed, displayed
or exhibited in either electronic or printed formats without the written authorization of
ETAP/Operation Technology, Inc., 17 Goodyear, Irvine, CA 92618, USA. © 2022 ETAP/Operation
Technology, Inc.
All Rights Reserved.
ETAP Workshop Notes ©1996-2022 ETAP/Operation Technology, Inc. All Rights Reserved. Page 1 of 8
Rev3 – 10/19/22
System1 and System2 are identical, each without transformer primary-side protection. There are four TCC views
included in the project, which allow you to see the current protective device settings for the secondary protective
devices.
Add the primary protective devices to the one-line diagram and after to the corresponding TCCs. After adding the
devices, compare and adjust their settings with respect to the 4.16 kV secondary side PDs. Adjust the settings as
necessary to reduce the incident energy. You may also plot the primary protection by itself if needed, or you can
use the TCC 2nd axis feature to show a second axis plotted on the primary side base kV (plot kV = 12).
Setup
• Load the project file named “AF-Example1”. (The solution to this example is located in a directory called
“Solution1”. Open the solution project only to compare against your exercise once completed.)
• Utilize the library from ETAP xxx\lib (xxx= ETAP version currently being used)
• Load “Example1.rul” provided in the example1 folder.
Procedure
Step1
Add the enclosures for “BusA” and “Bus2”. Table 1 below shows the data to be entered for the switchgears. Use
the “Add bus and protective devices” option.
914 mm
(36 inch)
914 mm
(36 inch)
Fig 2: Rear view of the MV switchgear showing exposed conductors and cable lugs
In addition to the switchgear compartments, it is required to evaluate the arc-flash incident energy at the load
terminals. Add a load terminal type of enclosure to both buses. These two load terminal enclosures are separate
locations and should have their own dimensions and working distances.
NOTE: There are other compartments or enclosures in Fig 1; however, only a couple are used for this example.
The remaining fields in the enclosure editor should be left with default settings.
ETAP Workshop Notes ©1996-2022 ETAP/Operation Technology, Inc. All Rights Reserved. Page 3 of 8
Rev3 – 10/19/22
1.1 Why has the option “Symm. 1.5 to 4 Cycle” been selected? (Clue: Look at the bus nominal kV)
____________________________________________________________________________________
1.2 What is the incident energy limit for Level B based on NFPA 70E 2021/Z462 2021/ User-defined? (Clue: Go
to the AF Study Case/Parameters page/ “Edit/Approve PPE” button under the PPE Requirements section.)
_____________________________________________________________________________________
Step2
• Select study case called “AF MV”, configuration “Normal” run AF and name the report “AF MV”.
• Observe the arc flash results displayed on the one-line diagram (OLD)
• Double click on Bus A and then Bus2. Navigate to the Arc Flash page of each.
• Open the Arc Flash Analysis report as well, and answer the following questions:
Step3
Add a fuse for transformer “T2” (primary winding protective device) in System1.
ETAP Workshop Notes ©1996-2022 ETAP/Operation Technology, Inc. All Rights Reserved. Page 4 of 8
Rev3 – 10/19/22
1. Standard = ANSI
2. Manufacturer = Southern States
3. Model = BPA-PF
4. Slow Speed
5. Interrupting current = 10 kA
6. Size = 200A (200 Amp continuous current)
3.1 What is the Incident energy released for a fault at line side of Main CBA?
(Clue: Go to the AF Mode Display Options \ Arc fault location and select Source PDs)
3.2 What is the Fault Clearing Time for a fault at line side of Main CBA?
(Clue: Go to the AF Mode Display Options \ Arc fault location and select FCT)
Step4
• Select study case called “AF MV_Min”, configuration called “Gen.Only”, run AF and name the report
“AF MV_Min”.
• Observe the arc flash results displayed on the one-line diagram (OLD)
• Double click on Bus A and then Bus2. Navigate to the Protection page of each.
• Open the Arc Flash Analysis report as well, and answer the following questions:
4.1 What are the maximum and minimum 3-phase fault currents on BusA (Clue: See the bus protection page)
4.2 What is the I.E released for a fault at line side of Main CBA based on “AF MV_Min”?
(Clue: Go to the AF Mode Display Options \ Arc fault location and select Source PDs)
4.3 How can the incident energy be displayed in TCC for Bus side, line side and load side respectively?
4.4 Why are the constant incident energy values different for Bus side, Line side and Load side?
ETAP Workshop Notes ©1996-2022 ETAP/Operation Technology, Inc. All Rights Reserved. Page 5 of 8
Rev3 – 10/19/22
Step5
• Switch to STAR mode (Protective device and co-ordination)
• Select study case called “SM”, select “AF-Rules” from Star Auto page
• Highlight “BusA” and run Auto Star evaluation , and name the report as “SM”. Go to Arc flash tab
in the Star Auto-Evaluation analysis viewer and answer the following questions:
5.1 Did the evaluation pass for all the locations flagged in the Star Auto-Evaluation viewer? If not, what are the
failed locations?
5.2 Select the fuse continuous amp rating which can reduce the line side incident energy below 8 cal/cm²?
ETAP Workshop Notes ©1996-2022 ETAP/Operation Technology, Inc. All Rights Reserved. Page 6 of 8
Rev3 – 10/19/22
Step6
Add a high-voltage circuit breaker to transformer “T1” (primary winding protective device) in System2.
Add Relay,
CT and
HVCB
ETAP Workshop Notes ©1996-2022 ETAP/Operation Technology, Inc. All Rights Reserved. Page 7 of 8
Rev3 – 10/19/22
4.2 What is the Fault Clearing Time for a fault at line side of Main CB1?
ETAP Workshop Notes ©1996-2022 ETAP/Operation Technology, Inc. All Rights Reserved. Page 8 of 8