Professional Documents
Culture Documents
BEFORE THE
MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION
BHOPAL
Filing No
IN THE MATTER Petition for True up of Tariff of Unit-1 (45 MW) for FY 2016-
OF 17, FY 2017-18 & FY 2018-19 of M/s B L A Power Pvt. Ltd. for
Sale of Contracted Capacity to M. P. Power Management
Company Ltd.,
The above-named Petitioner, B L A Power Pvt. Ltd., Mumbai, respectfully submits as under:
2. According to the terms of the MoU and the Implementation Agreement, GoMP or its
nominated agency has the first right to purchase up to thirty percent (30%) of the
aggregate capacity of the generating units for a period of twenty (20) years, at a rate to
be approved by appropriate commission, in this case the Ld. Madhya Pradesh Electricity
Regulatory Commission (“Ld. MPERC” / “Ld. Commission”).
3. Furthermore, the MoU and the Implementation Agreement provide that GoMP or its
nominated agency has a right to purchase five percent (5%) of the net power generated
by the power stations (i.e. electrical energy generated less auxiliary energy consumption
in kWh) of the Petitioner, at a price equivalent to Variable Charge / Cost only, which
shall be determined by Ld. MPERC.
4. In accordance with the above terms of the Implementation Agreement and upon the
GoMP exercising its right as aforesaid, the Petitioner, in compliance with its obligations,
entered into the following Power Purchase Agreements:
5. In accordance with Article 10.1.1 of the 27 MW PPA, the “… Tariff shall comprise
Capacity Charge, Variable Charge and any other charges as may be determined by the
Appropriate Commission under law and as per the norms contained in the tariff
regulations notified by the Appropriate Commission.” In Article 1.1 of the 27 MW PPA
“Appropriate Commission” is defined as Ld. Madhya Pradesh Electricity Regulatory
Commission.
6. The Ld. Commission approved the 27 MW PPA vide its order dated 7 September 2012
in Petition no. 10/2012 read with order dated 7 February 2013 in review Petition No.
85/2012.
7. Vide order dated 14 December 2022 in Petition No. 52 of 2022, the Ld. Commission
determined true up of tariff for FY 2014-15 & FY 2015-16 and MYT Tariff for FY 2016-
17 to FY 2018-19 for Unit-1 of the Petitioner’s Generating Station based on actual data
and figures as per Annual Audited Accounts.
8. The Petitioner is filing the present petition for the true up of the tariff for FY 2016-17 to
FY 2018-19 for Unit-1 of its Generating Station.
9. The Ld. Commission vide its Order dated 14 December 2022 has admitted the following
Capital Cost of Rs. 302.33 Crore as on 31 March 2016 of Unit-1 of the Petitioner’s
Generating station in Petition No. 52 of 2022.
10. The funding of the capital expenditure, as per order dated 14 December 2022 of this Ld.
Commission is mentioned in the table given below:
11. It is humbly submitted before the Ld. Commission to kindly permit the same.
12. It is further submitted that during FY 2016-17, FY 2017-18 and FY 2018-19, the
Petitioner is not claiming any additional capitalization in the present true up Petition for
Unit-1 for FY 2016-17, FY 2017-18 and FY 2018-19.
13. It is further submitted that Ld. MPERC has worked out Energy Charges vide order dated
14 December 2022 in Petition No. 52 of 2022, as follows:
“225. Accordingly, Energy Charges for the period from FY 2016-17 to FY 2018-
19 are worked out as given below:
226. The base rate of the energy charges as determined above shall however,
be subject to month to month adjustment of actual fuel price and actual
GCV of coal. For the period FY 2016-17 to FY 2018-19, the recovery of
energy charges shall be made in accordance with Regulations 36.6 to
36.8 of MPERC (Terms and Conditions for determination of Generation
Tariff) Regulations, 2015.”
14. It is submitted that Unit-1 and Unit-2 of the Petitioner’s Generating Station have achieved
commercial operation on 3 April 2012 and 20 March 2017 respectively. The present
petition is for true up of Tariff of Unit-1 for the period from FY 2016-17 to FY 2018-19.
The Ld. Commission is requested to kindly determine the true up of tariff for Unit-1 for
the period from FY 2016-17 to FY 2018-19.
Filing No.:
Case No.:
IN THE MATTER OF: Petition for True up of Tariff of Unit-1 (45 MW) of M/s B L
A Power Pvt. Ltd. for FY 2016-17 to FY 2018-19 for Sale of
Contracted Capacity to M. P. Power Management Company
Ltd.
AFFIDAVIT
I, Manoj Sahu, S/o of Shri K. L. Sahu, aged 44 years, R/o A-59, Nirupam Royal Palm,
Hoshangabad Road, Bhopal, Madhya Pradesh, do hereby solemnly affirm and state as follows:
2. That, the statement made in paragraphs of the Petition and enclosures herein shown to
me are true to my knowledge and the statement made are based on information and I
believe them to be true.
3. Solemnly affirmed at Bhopal on this 1st day of February 2023 that the contents of the
above affidavit are based on available documents and true to my knowledge and no part
of it is false and nothing material has been concealed there from.
DEPONENT
VERFIFICATION
I, Manoj Sahu, the above named deponent, do hereby verify that the contents of above affidavit
are true and correct to the best of my knowledge and belief.
DEPONENT
1.2. Representatives
Name Email
2.1. B L A Power Pvt. Ltd., Mumbai, hereinafter referred as the “Petitioner” / “Company”, a
company incorporated under Companies Act, 1956 and having its registered office at 84,
Maker Chamber III, Nariman Point, Mumbai, was incorporated in the month of
November 2006. The Petitioner entered into a Memorandum of Understanding with
GoMP on 10 August 2007 for setting up of a thermal Generating Station at Tehsil
Gadarwara, Dist. Narsinghpur in the State of Madhya Pradesh. Subsequently, as
envisaged by the terms of the MoU, GoMP and the Petitioner entered into an
Implementation Agreement on 01.09.2008.
2.2. According to the terms of Implementation Agreement, GoMP or its nominated agency
has the first right to purchase up to thirty percent (30%) of the aggregate capacity of the
generating units for a period of twenty (20) years, at a rate to be approved by the Ld.
MPERC.
2.3. The MoU and the Implementation Agreement further provide that the GoMP or its
nominated agency has a right to purchase five percent (5%) of the net power generated
by the Generating Station (i.e. electrical energy generated less auxiliary consumption in
kWh) of the Petitioner), at a price equivalent to Variable Charge / Cost only, which shall
be determined by Ld. Madhya Pradesh Electricity Regulatory Commission.
2.4. In accordance with the above terms of the Implementation Agreement and on the GoMP
exercising its right as aforesaid, the Petitioner, in compliance with its obligations, entered
into the following Power Purchase Agreements:
b. A Power Purchase Agreement was executed on 4 May 2011 between the Petitioner
with GoMP. By and under the said Concessional Energy PPA, the GoMP
nominated MP Power Management Company Ltd, Jabalpur (earlier being M.P.
Power Trading Co. Ltd.), an undertaking of GoMP (hereinafter referred to as
Respondent No.1), to purchase the 5% power referred to in the Implementation
Agreement on its behalf.
2.5. The Ld. MPERC approved the 27MW PPA vide its order dated 7 September 2012 (read
with order dated 7 February 2013 in Petition No. 85/2012) for sale of capacity to
MPPMCL.
2.6. Pursuant to the above agreements, the Petitioner installed and commissioned its first and
second unit of 45 MW each at Village Niwari, in Tehsil Gadarwara, in Narsinghpur
District of Madhya Pradesh. Unit-1 successfully achieved its COD on 3 April 2012.
Unit-2 has successfully achieved its COD on 20 March 2017 (in terms of the 27MW
PPA). The present petition is for True up of tariff order for Unit-1 for the FY 2016-17 to
FY 2018-19.
3. LEGAL PROVISION
3.1.2 Also, section 62 of the Electricity Act 2003 provides for determination of tariff
by the Appropriate Commission for supply of electricity by a generating
company. Some relevant clause of the Act is as stated below:
3.1.3 The Ld. Commission, under Section 86(1) (a) of the Electricity Act 2003, is
vested with the jurisdiction to regulate the tariff of the Generating Companies
within the State.
3.2.1 The Ld. Commission has notified the MPERC Generation Tariff Regulations
2015, which specifies the terms and conditions and methodology of tariff
determination under Section 62 of the Electricity Act 2003.
3.2.2 Regulation 8.4 of the aforesaid Regulations provides that for every provisional
tariff order issued by the Ld. Commission, the Petitioner shall file a true up
petition of Capacity Charges based on the Audited Statements after completion
of the respective financial year. The clause is reproduced below:
3.2.3 In accordance with the provisions contained in this regulation and the tariff order
issued by Ld. Commission on 14.12.2022, B L A Power Pvt. Ltd. (the Petitioner)
is submitting its request for determination of generation tariff for the control
period FY 2016-17 to FY 2018-19 for Unit No 1.
4 PROJECT COST AND FUNDING FOR TRUE UP OF UNIT NO. 1 (FY 2016-17 TO
FY 2018-19)
4.1.1 Ld. Commission has considered the closing capital cost of Rs 302.33 Crore as on
31st March’ 2016 as admitted in last tariff order dated 14th December’ 2022 in P
No 52 of 2022.
4.1.2 Therefore, Closing Capital Cost of Rs 302.33 Crore as on 31st March’ 2016 is
considered as opening capital cost as on 1.04.2016.
4.2 Funding:
4.2.1 Debt – The Ld. Commission had approved debt of Rs. 159.93 Crore towards
funding the capital cost of Unit-1.
4.2.2 Weighted average rate of interest is calculated on the basis of the actual loan
portfolio is as under:
4.2.3 Equity – Similarly, the Ld. Commission had approved equity of Rs. 84.75 Crore
to fund the capital cost of Unit-1.
4.2.4 Thus, the Ld. Commission is requested to approve opening capital cost as on 1
April 2016 for Unit-1 as Rs. 302.33 Crore and funding through debt of Rs.217.58
Crore and balance from equity of Rs. 84.75 Crore. It may be seen that for funding,
debt equity ratio is well with the limits permitted by applicable tariff regulations.
5. TARIFF STRUCTURE
5.1.1 The Tariff Regulations, 2015 specify a two-part tariff for sale of electricity from
a generating station as follows:
5.1.2 The annual Capacity (fixed) Charges consists of costs which are independent of
actual generation. They are as under:
Return on Equity
Interest on Loan Capital
Depreciation
Interest Charges on Working Capital
Operation and Maintenance Expenses
5.1.3 Energy charges shall be derived on the basis of the Landed Fuel Cost (LFC) of a
generating station and shall consist of the following cost:
5.2.1 Some relevant clauses of the regulation of the Ld. Commission are reproduced
below:
30.1 Return on equity shall be computed in rupee terms, on the equity base
determined in accordance with Regulation 25.
30.2 Return on equity shall be computed at the base rate of 15.50% for thermal
generating stations and hydro generating stations:
31.1 The base rate of return on equity as allowed by the Commission under
Regulation 30 shall be grossed up with the effective tax rate of the respective
financial year. For this purpose, the effective tax rate shall be considered on
the basis of actual tax paid in the respective financial year in line with the
provisions of the relevant Finance Acts by the concerned generating
company. The actual income tax on other income stream including deferred
tax i.e., income of non-generation business shall not be considered for the
calculation of “effective tax rate”.
31.2 Rate of return on equity shall be rounded off to three decimal places and
shall be computed as per the formula given below:
Where “t” is the effective tax rate in accordance with Clause 31.1 of
this Regulation and shall be calculated at the beginning of every financial year based
on the estimated profit and tax to be paid estimated in line with the provisions of the
relevant Finance Act applicable for that financial year to the company on pro-rata
basis by excluding the income of non-generation business and the corresponding tax
thereon. In case of generating company paying Minimum Alternate Tax (MAT), “t”
shall be considered as MAT rate including surcharge and cess.”
31.3 The actual tax paid together with any additional tax demand including
interest thereon, duly adjusted for any refund of tax including interest
received from the income tax authorities pertaining to the tariff period 2016-
17 to 2018-19 on actual gross income of any financial year shall be trued-
up every year. However, penalty, if any, arising on account of delay in
deposit or short deposit of tax amount shall not be claimed by the generating
company . Any under-recovery or over-recovery of grossed up rate on return
on equity after truing up, shall be allowed to be recovered or refunded to
beneficiaries on year to year basis.”
5.2.2 The Petitioner is not claiming any additional capitalisation during control period
from FY 2016-17 to FY 2018-19 under Unit-1. Thus, return on equity is requested
on the equity of Rs. 84.75 Crore already approved vide order dated 14.12.2022.
5.2.3 The RoE is proposed @ 15.50% only, as detailed in the table below. Further, in
first year of operation of Unit-1, i.e., FY 2016-17, there was loss of Rs. 61.38
Crores to the Petitioner. In second and third year there was also a loss of Rs 48.60
Cr and Rs 56.90 Cr respectively. Though it is a natural phenomenon for any
generating plant to have losses in initial few years and there are always chances
for the Company to earn profit in later years. Hence, grossing up of the tax has
not been done on RoE. The RoE is being claimed @ 15.50%. The claim of RoE
as submitted by the Petitioner for the period of FY 2016-17 to FY 2018-19 is as
under:
5.3.1 The interest charges are to be computed as per the Regulation 32 of the Tariff
Regulations, 2015.
32.3 The repayment for each of the year of the tariff period 2016-19 shall be
deemed to be equal to the depreciation allowed for the corresponding year/period. In
case of de- capitalization of assets, the repayment shall be adjusted by taking into
account cumulative repayment on a pro rata basis and the adjustment should not
exceed cumulative depreciation recovered upto the date of de-capitalisation of such
asset.
32.5 The rate of interest shall be the weighted average rate of interest calculated
on the basis of the actual loan portfolio after providing appropriate accounting
adjustment for interest capitalized:
Provided that if there is no actual loan for a particular year but normative loan is still
outstanding, the last available weighted average rate of interest shall be considered:
Provided further that if the generating station does not have actual loan, then the
weighted average rate of interest of the generating company as a whole shall be
considered.
32.6 The interest on loan shall be calculated on the normative average loan of the
year by applying the weighted average rate of interest.
32.7 The generating company shall make every effort to re-finance the loan as
long as it results in net savings on interest and in that event the costs associated with
such re-financing shall be borne by the beneficiaries and the net savings shall be
shared between the beneficiaries and the generating company in the ratio of 2:1.
32.8 The changes to the terms and conditions of the loans shall be reflected from
the date of such re-financing.”
5.3.2 Considering the Regulations as discussed above, the interest and finance charges
have been computed as per the following table. The Petitioner requests the Ld.
Commission to approve the same.
5.4 Depreciation
5.4.1 Depreciation is computed based on the capital cost of the assets pertaining to
Unit-1 in accordance with the provisions of the Tariff Regulations, 2015. The
Regulation 33 of the Tariff Regulations, 2015 is reproduced below:
“33. Depreciation:
33.2 The value base for the purpose of depreciation shall be the capital cost
of the asset admitted by the Commission. In case of multiple units of a
generating station, weighted average life for the generating station shall
be applied. Depreciation shall be chargeable from the first year at the
commercial operation.
33.3 The salvage value of the asset shall be considered as 10% and
depreciation shall be allowed up to maximum of 90% of the capital cost
of the asset:
…..
Provided also that any depreciation disallowed on account of
lower availability of the generating station or generating unit shall not
be allowed to be recovered at a later stage during the useful life and the
extended life.
33.4 Land other than the land held under lease and the land for reservoir in
case of hydro generating station shall not be a depreciable asset and its
cost shall be excluded from the capital cost while computing depreciable
value of the asset.
5.4.2 Here it is submitted that the Petitioner in its petition has requested for the rate of
depreciation as 4.84%, considering the capital cost as Rs 302.33 Cr. The
Petitioner requests the Ld. Commission to approve the depreciation as computed
in the following table for FY 2016-17 to FY 2018-19.
5.5.1 Operation and Maintenance expenses are required to meet out the expenses
towards repair and maintenance of the plant, salaries and wages of the employees,
administration and general expenses for management of the plant.
5.5.2 The Tariff Regulations, 2015 specify the norms of operation for Unit of 45 MW size.
Some relevant provisions of the Regulations are reproduced below:
35.1 Operation and Maintenance Expenses for thermal and hydro power stations
for the Tariff period shall be determined based on normative O&M expenses
specified by the Commission in these Regulations. The normative operation
and maintenance expenses for the thermal generating stations are specified
separately for the thermal power stations commissioned on or before
31.03.2012 and the power stations commissioned on or after 01.04.2012. The
normative operation and maintenance expenses are also specified separately
for the existing and new projects.
35.2 The cost components for employee expenses, repair & maintenance expenses
and administrative and general expenses are considered as per Regulations
35.7 to 35.8 and 35.10 to 35.11 of these Regulations. The Operation and
Maintenance expenses including employee expenses, repair and
maintenance expenses, and administrative and general expenses, for the
power stations commissioned prior to 01.04.2012 are derived by considering
the average of these expenditures for past four years (i.e. FY2010-11 to
FY2013-14) as per Annual Audited Accounts. The average expenditure of the
aforesaid four years is considered as base opening figure for FY 2012-13.
Thereafter, the figures of O&M expenditure are derived upto FY 2015-16 by
applying the annual escalation rate specified for the relevant year in the
applicable Regulations.
35.3 The O&M expenses for the subsequent years shall be determined by
escalating the expenses of the base year i.e. FY 2015-16, as determined
above with the escalation factor @ 6.30% and @ 6.64% for thermal power
stations and hydro power stations respectively as considered by the Central
Commission in its Tariff Regulations, 2014 for the respective financial years
to arrive at permissible O&M expenses for each year of the Control Period.
Rs. in lakhs/MW
Units (MW) FY 2016-17 FY 2017-18 FY 2018-19
45 MW 32.07 34.09 36.24
200/210/250 MW 27.00 28.70 30.51
300/330/350 MW 22.54 23.96 25.47
500 MW 18.08 19.22 20.43
600 MW and above 16.27 17.30 18.38
5.5.3 The Petitioner has computed the O&M expenses for FY 2016-17 to FY 2018-19 as shown
in the following table. The Petitioner requests the Ld. Commission to approve the same.
5.6.1 The Tariff Regulations, 2015 specify the norms for computation of interest on working
capital. Some relevant Regulation is reproduced below:
(c) Cost of secondary fuel oil for two months for generation
corresponding to the normative annual plant availability factor,
and in case of use of more than one secondary fuel oil, cost of fuel
oil stock for the main secondary fuel oil;
34.3 Rate of interest on working capital shall be on normative basis and shall
be considered as the bank rate as on 1.4.2016 or as on 1st April of the
year during the tariff period 2016-17 to 2018-19 in which the generating
station or a unit thereof, is declared under commercial operation,
whichever is later.
5.7.1 In summary of True up proposal as elaborated in the foregoing sections above, Petitioner
respectfully submits before the Ld. Commission to kindly permit:
5.7.2 Permit recovery of fixed cost & other charges as elaborated above.
The regulation permits the actual expenses paid by the Petitioner to the
Ld. Commission against various submissions as pass through. The
Petitioner had deposited an amount of Rs 1,00,000/-, via RTGS in
favour of “Madhya Pradesh Electricity Regulatory Commission”
towards filing fee of the present true-up Petition for FY 2016-17 to FY
2018-19. Further the Petitioner had also deposited an amount of Rs.
3,15,000/- towards filing fees of MYT for FY 2016-17 to FY 2018-19.
The O&M charges also exclude the cost of various chemicals and
consumables consumed by the generating company during the year.
Petitioner has incurred expenditure of Rs. 42,27,426/- during FY 2016-
17, Rs.18,08,577/- during FY 2017-18 and Rs. 19,93,622/- during FY
2018-19 towards Unit-1 & Unit-2, out of which incurred expenditure
Rent, rates and taxes actually paid to the statutory bodies are permitted
as pass through. Company has incurred expenditure of Rs.
2,34,19,847/- during FY 2016-17, Rs. 1,27,34,709/- during FY 2017-
18 and Rs. 49,44,382/- during FY 2018-19 towards Unit-1 & Unit-2,
out of which incurred expenditure of Rs. 2,32,70,647/- during FY
2016-17, Rs. 1,26,98,709/- during FY 2017-18 and Rs. 48,72,382/-
during FY 2018-19 is towards Unit-1.
5.8.2 The expenses have duly been extracted from the Annual Statements of Accounts of the
Petitioner, which have been duly audited by the Statutory Auditor and are summarised
below:
Lakh
Total 301.73 28.26 329.99 160.43 15.80 176.24 90.52 22.37 112.89
Rs.
Cr.
3.02 0.28 3.30 1.60 0.16 1.76 0.91 0.22 1.13
Rs.
5.8.4 It is humbly prayed that this Ld. Commission may graciously be pleased to condone any
inadvertent delay in filing the present true-up petition for FY 2016-17 to FY 2018-19.
Tariff for Unit-1 for the aforesaid control period was determined by the Ld. Commission
by an order dated 14.12.2022. Accordingly, the Petitioner is filing the present true-up
petition with the audited accounts and the accompanying details seeking a true-up for the
relevant control period.
6. Prayer:
In view of the above, the Petitioner respectfully prays that the Ld. Commission may:
a) Carry out the truing-up of tariff for Unit-1 of the Project for the period from FY
2016-17 to FY 2018-19 and allow to recover the difference amount;
b) Allow to recover E.D., Water Charges and Cess on auxiliary power consumption
and other taxes, if any, levied by the Statutory Authorities from Respondent No.
1;
c) Allow to recover the fees paid to the Ld. Commission and publication expenses
from Respondent No. 1;
e) Pass such Orders, as this Ld. Commission may deem fit and proper, and necessary
in the facts and circumstances of the case, to grant relief to the Petitioner.
List of Annexures: