You are on page 1of 1

PERBANDINGAN PROYEK RETREAT AND CONVENTION PLESUNGAN SOLO

HARGA PENAWARAN PERMINTAAN BU MELIN HARGA SOLO URBANA


DISCRIPSI VOLUME SATUAN
harga total harga total harga total

PERSIAPAN 1.00 LS 456,000,000.00 456,000,000.00 125,000,000.00 125,000,000.00 440,000,000.00 440,000,000.00


- - -
PENGEBORAN D 800 2,667.00 M 260,000.00 693,420,000.00 240,000.00 640,080,000.00 250,000.00 666,750,000.00
PENGEBORAN D 801 56.00 M 240,000.00 13,440,000.00 225,000.00 12,600,000.00 240,000.00 13,440,000.00
- - -
PEMBUANGAN TANAH 1,356.20 M3 110,000.00 149,182,000.00 30,000.00 40,686,000.00 70,000.00 94,934,000.00
- - -
PENGECORAN 1,339.91 M3 1,224,000.00 1,640,049,840.00 947,071.00 1,268,989,903.61 1,200,000.00 1,607,892,000.00
- - -
PEMBESIAN 108,615.63 KG 14,106.00 1,532,132,076.78 11,547.00 1,254,184,679.61 10,954.00 1,189,775,611.02
- - -
SLURY 1,339.91 M3 100,000.00 133,991,000.00 45,000.00 60,295,950.00 90,000,000.00 90,000,000.00
- - -
PDA TEST 2.00 ttk 12,000,000.00 24,000,000.00 8,000,000.00 16,000,000.00 8,000,000.00 16,000,000.00
- - -
PIT TEST 12.00 ttk 2,000,000.00 24,000,000.00 2,000,000.00 24,000,000.00 2,000,000.00 24,000,000.00

TOTAL 4,666,214,916.78 3,441,836,533.22 4,142,791,611.02