PT DINITO JAYA SAKTI

TIME LINE PROJECT MOLD BLUE GAS NEW DESIGN


SEPTEMBER
NO DESCRIPTION
###11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7
1 DESIGN
1.1 Drawing product
1.2 Design mold
1.3 Approval drawing product by customer
2 MATERIAL
2.1 Order Material
2.2 Proses Material by supplier
2.3 Kedatangan Material
3 PROSES MOLDING
3.1 Machining material mold
3.2 Finishing process mold
3.3 Assembling mold
4 TRIAL MOLD & PRODUCT
4.1 T0 - Trial Mold
4.2 Trial Analysis T0
4.3 Improvement mold
4.4 T1 - Trial Mold & Product
4.5 Trial Analysis T1
4.6 Improvement product
4.7 Harden mold parts
4.8 T2 - Trial Product
4.9 Trial Analysis T2
5 APPROVAL PRODUCT
5.1 Submit product sample to customer
OKTOBER NOVEMBER
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
MBER DESEMBER
20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
27 28 29 30 31