You are on page 1of 2

INSTRUMENT SIZE SUPPLIER UNIT PRICE QTY TOTAL CURRENCY DELIVERY TOTAL PRICE JOD

PRICE
Gate Valve PN 10 (with bolt set and gasket) 400 MOGS 585 15 8,775.00 USD 7 DAYS 6,230.25
TERMO 750 15 11,250.00 USD 6-8 WEEKS 7,987.50
JABALI BROS 500 15 7,500.00 JOD IMMEDIATE 7,500.00
ANWAR JORDAN 700 15 10,500.00 JOD - 10,500.00
FOCO 450 15 6,750.00 JOD 7 DAYS / 14-30 DAYS 6,750.00
OMRANIA

Gate Valve PN 10 (with bolt set and gasket) 180/200/150 MOGS 87 4 348.00 USD 7 DAYS 247.08
TERMO 258 4 1,032.00 USD 6-8 WEEKS 732.72
JABALI BROS 100 4 400.00 JOD IMMEDIATE 400.00
ANWAR JORDAN 100 4 400.00 JOD - 400.00
FOCO JOD 7 DAYS / 14-30 DAYS 0.00
OMRANIA

Gate Valve PN 10 (with bolt set and gasket) 500 MOGS 1092 1 1,092.00 USD 7 DAYS 775.32
TERMO 1100 1 1,100.00 USD 6-8 WEEKS 781.00
JABALI BROS 0.00 JOD IMMEDIATE
ANWAR JORDAN 0.00 JOD -
FOCO 900 1 900.00 JOD 7 DAYS / 14-30 DAYS
OMRANIA

Non return Resilient Check valve , PN 10 (with bolt set and gasket) 400 MOGS
TERMO 1350 3 4,050.00 USD 7 DAYS 2,875.50
JABALI BROS 200 3 600.00 JOD 6-8 WEEKS 600.00
ANWAR JORDAN 300 2 600.00 JOD IMMEDIATE 600.00
FOCO
OMRANIA

Sch40 DN 500 CS pipe 500 MOGS 269 30 8,070.00 USD 7 DAYS 5,729.70
TERMO
JABALI BROS
ANWAR JORDAN
FOCO 220 36 7,920.00 JOD 7 DAYS / 14-30 DAYS 7,920.00
OMRANIA 150 30 4,500.00 JOD - 4,500.00

Sch40 DN 400 CS pipe 400 MOGS 166 126 20,916.00 USD 7 DAYS 14,850.36
TERMO
JABALI BROS
ANWAR JORDAN
FOCO 155 144 22,320.00 JOD 7 DAYS / 14-30 DAYS 22,320.00
OMRANIA 115 126 14,490.00 JOD - 14,490.00

Sch40 DN 400 CS Tee 400 MOGS 277 5 1,385.00 USD 7 DAYS 983.35
TERMO 6-8 WEEKS
JABALI BROS IMMEDIATE
ANWAR JORDAN -
FOCO 320 5 1,600.00 JOD 7 DAYS / 14-30 DAYS 1,600.00
OMRANIA 420 5 2,100.00 JOD - 2,100.00

Sch40 CS 90 degree Elbow DN 400 400 MOGS 245 9 2,205.00 USD 7 DAYS 1,565.55
TERMO 6-8 WEEKS
JABALI BROS IMMEDIATE
ANWAR JORDAN -
FOCO 140 10 1,400.00 JOD 7 DAYS / 14-30 DAYS 1,400.00
OMRANIA 350 9

Slip-on Steel Flange class 150 DN 500 500 MOGS 166 8 1,328.00 USD 7 DAYS 942.88
TERMO
JABALI BROS 200 2 400.00 JOD IMMEDIATE 400.00
ANWAR JORDAN
FOCO 140 3 420.00 JOD 7 DAYS / 14-30 DAYS 420.00
OMRANIA 300 8 2,400.00 JOD - 2,400.00

Slip-on Steel Flange class 150 DN 400 400 MOGS 115 86 9,890.00 USD 7 DAYS 7,021.90
TERMO
JABALI BROS 180 86 15,480.00 JOD IMMEDIATE 15,480.00
ANWAR JORDAN
FOCO 90 90 8,100.00 JOD 7 DAYS / 14-30 DAYS 8,100.00
OMRANIA 190 86 16,340.00 JOD - 16,340.00

Slip-on Steel Flange class 150 DN 250 250 MOGS 43 3 129.00 USD 7 DAYS 91.59
TERMO
JABALI BROS 40 3 120.00 JOD IMMEDIATE 120.00
ANWAR JORDAN 44 3 132.00 JOD - 132.00
FOCO
OMRANIA 72 3 216.00 JOD - 216.00

Slip-on Steel Flange class 150 DN 200 200 MOGS 32 23 736.00 USD 7 DAYS 522.56
TERMO
JABALI BROS 28 23 644.00 JOD IMMEDIATE 644.00
ANWAR JORDAN 30 23 690.00 JOD - 690.00
FOCO
OMRANIA 45 23 1,035.00 JOD - 1,035.00

CSA. Y-Shape Strainer DN 400 200 MOGS


TERMO
TOTAL
INSTRUMENT SIZE SUPPLIER UNIT PRICE QTY CURRENCY DELIVERY TOTAL PRICE JOD
PRICE
JABALI BROS 700 3 2,100.00 JOD IMMEDIATE 2,100.00
ANWAR JORDAN 1200 3 3,600.00 JOD - 3,600.00
FOCO
OMRANIA

Dismantiling Joint DN 400 400 MOGS


TERMO 768.82 9 6,919.38 USD 6-8 WEEKS 4,912.76
JABALI BROS 140 9 1,260.00 JOD IMMEDIATE 1,260.00
ANWAR JORDAN 1200 3 3,600.00 JOD - 3,600.00
FOCO
OMRANIA

Rubber Vibration Isolater DN 250 250 MOGS


TERMO
JABALI BROS 170 3 510.00 JOD IMMEDIATE 510.00
ANWAR JORDAN 210 3 630.00 JOD - 630.00
FOCO
OMRANIA

Rubber Vibration Isolater DN 200 200 MOGS


TERMO
JABALI BROS 180 3 540.00 JOD IMMEDIATE 540.00
ANWAR JORDAN 160 3 480.00 JOD - 480.00
FOCO
OMRANIA

Sch40 DN 200 CS pipe 200 MOGS 55 6 330.00 USD 7 DAYS 234.30


TERMO
JABALI BROS
ANWAR JORDAN
FOCO
OMRANIA 62 6 372.00 JOD - 372.00

Sch40 DN 500 CS Tee 500 MOGS 570 5 2,850.00 USD 7 DAYS 2,023.50
TERMO
JABALI BROS
ANWAR JORDAN
FOCO
OMRANIA 546 5 2,730.00 JOD - 2,730.00
.
Sch40 DN 500 CS Blind flange 500 MOGS 285 1 285.00 USD 7 DAYS 202.35
TERMO
JABALI BROS
ANWAR JORDAN
FOCO
OMRANIA 420 1 420.00 JOD - 420.00
.
Sch40 CS reducer 500-400 500-400 MOGS 245 5 1,225.00 USD 7 DAYS 869.75
TERMO
JABALI BROS
ANWAR JORDAN
FOCO
OMRANIA 308 5 1,540.00 JOD - 1,540.00
.
Sch40 CS reducer 400-200 400-200 MOGS 131 7 917.00 USD 7 DAYS 651.07
TERMO
JABALI BROS
ANWAR JORDAN
FOCO
OMRANIA 200 7 1,400.00 JOD - 1,400.00
.
Sch40 CS reducer 400-250 400-250 MOGS 124 3 372.00 USD 7 DAYS 264.12
TERMO
JABALI BROS
ANWAR JORDAN
FOCO
OMRANIA 200 3 600.00 JOD - 600.00
.
Sch40 CS 90 degree Elbow DN 500 500 MOGS 510 2 1,020.00 USD 7 DAYS 724.20
TERMO
JABALI BROS
ANWAR JORDAN
FOCO
OMRANIA 546 2 1,092.00 JOD - 1,092.00
.
HDPE Pipe 12m 400 MOGS 590.00 292 172,280.00 USD 7 DAYS 122,318.80
HDPE Pipe 12m 500 MOGS 1,365.00 6 8,190.00 USD 7 DAYS 5,814.90
HDPE 45 degree elbow 400 MOGS 39.00 3 117.00 USD 7 DAYS 83.07
HDPE 90 degree elbow 400 MOGS 57.00 6 342.00 USD 7 DAYS 242.82
HDPE Tee 400 MOGS 73.00 4 292.00 USD 7 DAYS 207.32
HDPE Reducer 400-180 MOGS 42.00 4 168.00 USD 7 DAYS 119.28
Stub-end with steel flange 500 MOGS 117.00 2 234.00 USD 7 DAYS 166.14
Stub-end with steel flange 400 MOGS 61.00 18 1,098.00 USD 7 DAYS 779.58
Stub-end with steel flange 180 MOGS 10.50 4 42.00 USD 7 DAYS 29.82
PVC 45 Degree Elbow 110 MOGS 3.00 3 9.00 USD 7 DAYS 6.39
PVC 90 Degree Elbow 100 MOGS 4.00 4 16.00 USD 7 DAYS 11.36
PN 16 11.9MPVC PIPE 110 MOGS 38.00 2 76.00 USD 7 DAYS 53.96

You might also like