ART.

1: DEFINITIONS
ACT OF GOD OR FORCE MAJEURE includes an event adjustments and/or escalation, acceleration of work, and
which cannot be foreseen, or which though foreseen, was others. It does not include the retention money.
inevitable. Rain, wind, flood or other natural phenomenon GUARANTEE BOND is the approved form of security
of inconsequential degree for the locality shall not be furnished by the Contractor and his Surety as a guarantee
construed as an Act of God or Force Majeure. of the quality of the materials provided, the equipment
ADVERTISEMENT or INVITATION TO BID refers to the installed, and the workmanship performed by the
notice published by the Owner or the invitation issued to Contractor.
prospective bidders, giving information as to the nature of INSTRUCTION TO BIDDERS refers to the list of
the proposed project, conditions for the issuance of instructions regarding the manner bids are to be prepared
Contract documents, date of bidding, and information that and the conditions for the award of the Contract.
would give the Contractor a general idea of the magnitude LAWS refers to all laws, ordinances and other
and extent of the project. governmental rules and regulations applicable to the
AGREEMENT is the term used to describe the agreement project and to its execution.
signed by the Owner and the Contractor excluding the OWNER is the person or entity or authorized
Contract Documents which are attached thereto. representative thereof who signed the Contract as Owner.
BID is the tender, or proposal, or quotation, or offer of a OWNER'S REPRESENTATIVE refers to the person or
bidder to perform the work described in the Contract which entity commissioned by the Owner or authorized in writing
in form and substance complies with the Instruction to by the Owner to act on his behalf.
Bidders. PAYMENT BOND is the approved form of security
BID BOND refers to any acceptable form of bond furnished by the Contractor and his Surety as a guarantee
accompanying the Bid submitted by the bidder as a of good faith on the part of the Contractor to faithfully
guarantee that the bidder will enter into the Contract with comply with the Contract in respect of its obligations arising
the Owner for the construction of the Work, if the Contract therefrom to its workers, subcontractors, and suppliers.
is awarded to him. PERFORMANCE BOND is the approved form of security
BID DOCUMENTS collectively refer to all documents furnished by the Contractor and his Surety as a guarantee
provided or made available to prospective bidders which of good faith on the part of the Contractor to execute the
include the Invitation to Bid and a copy of the Contract Work in accordance with the Contract.
which the winning bidders would be required to sign with SCHEDULE OF MATERIALS AND FINISHES is an
the Owner. outline specification enumerating the type or trade names
BID BULLETIN is a document containing additional of materials required to be used by the Contractor for the
information on Bid Documents issued to bidders before Work.
date of bidding. SPECIFICATIONS are the written or printed description of
BREAKDOWN OF WORK AND CORRESPONDING the work to be done describing qualities of the material to
VALUE is a listing of the different parts of the work be used, the equipment to be installed and the mode of
indicating each part and its corresponding value. construction.
CHANGE ORDER is a written order to the Contractor SPECIAL PROVISIONS OR CONDITIONS are
issued by the Owner after the execution of the Contract, instructions which are issued prior to bidding to
authorizing a change or variation in the work or an supplement and/or modify the Drawings, Specifications
adjustment in the Contract Price or Contract time. and/or General Conditions of the Contract.
CONTRACT is the term used to describe the Agreement SUB-CONTRACTOR is a contractor duly registered and
and the Contract Documents licensed by the Philippine Contractors Accreditation Board
CONTRACT DOCUMENTS are the documents attached having a direct contract with the Contractor who acts for or
to the Agreement identified therein as in behalf of the Contractor in executing any part of the
Contract Documents, including all additions, deletions and Contract. One who merely furnishes materials without
modifications incorporated therein. These generally labor is a supplier and not a Sub-Contractor.
include the following documents: SUPPLEMENTARY SPECIFICATIONS refers to
a. Special Provisions or Conditions additional information which may be issued as an addition
b. General Conditions to or amendment of the provisions of the Specifications.
c. Drawings SURETY is the person, firm or corporation which issues
d. Specifications the bond required of the Contractor.
e. Other Bid Documents TIME LIMIT OR COMPLETION TIME is the period of time
CONTRACT PRICE is the amount in money or other allowed by the Contract for the
consideration to be paid by the Owner to the Contractor for completion of the project or any stipulated portions thereof.
the execution of the Work in accordance with the Contract. WRITTEN NOTICE means information, advice or
CONTRACTOR is the person or firm duly registered and notification pertinent to the project delivered in person or
licensed by the Philippine Contractors Accreditation Board sent by registered mail to an individual, firm or corporation
whose proposal has been accepted and to whom was at the latter's last known business address.
awarded the Contract to execute the Work. WORK refers to all the Contractor-provided labor or
DRAWINGS are graphical presentations of the Work. They materials or both as well as equipment
include all supplementary details and shop drawings. transportation, or other facilities necessary to commence
FINAL PAYMENT refers to the payment of the final and complete the construction and to fulfill all his
progress billing and all approved claims including but not obligations which are called for in the Contract.
limited to those variations in the work, Contract Price