PHYSICAL FACILITIES REPAIR AND MAINTENANCE NEEDS ASSESSMENTS FORM
FACILITIES Condition Remarks Nature of Improvement needed Material Resource Needed Manpower Needed
(Check One) (e.g. repair, repainting, (Indicate Kind and Quantity)
Satisfactory Unsatisfactor If unsatisfactory, replacement, construction, fixing
y describe the problem etc.)
1. Roofs/Gutters / With holes replacement 1 gutter 10 ft., 1 vulca zeal, nails 4 carpenters
2. Ceilings /
3. Walls / - No school function -To dismantle the wall that Hammer, crowbar 6 carpenters
hall separates Grade 4 and 3 that
- No library will serve as the school function
hall
- to dismantle the wall that
divides the temporary rooms of
Grade 1 and kindergarten then
fix it as a library room.
4. Doors / No door in the proposed To construct a door in the Hammer, 20 screw, 4 hinges 2 carpenters
ICT rooms proposed ICT room
5. Blackboards / -Needs to be transferred -To detached from Grade 1, Hammer, crowbar 4 carpenters
in other rooms Kinder, Grade 3, Grade 4 old
rooms
-Boards in the new room - To detached and adjust the
are too high for Grade 1- height of the boards
2
6. Water facilities / -no water supply in - to provide water supply in Faucet, 1 kl tie wire, 100 m hose, 2 volunteers
Kindergarten room kindergarten room 10 T pipe
7. Signage / Damaged and rusty replacement Paints, boards, paint brush 4 volunteers/ painters
9. Lighting / No electricity in kinder to install electrical wirings 50 m Electric wire, 2 pcs. electrical 2 electricians
room tape
10.Windows / No hooks and damaged Replacement hooks 1 volunteer
hooks in HE and
Principal’s office
11. a. Comfort room for / Improper water drainage to repair water drainage 2” PVC pipe, 1 drainage trap 2 volunteers
pupils
b. H.E Comfort / /
Office Room
12. School Ground / With stagnant water To cement 5 sacks cement, 25 sacks sand 4 volunteers
13. School Fence / - the stage has To replace fence 8 steel mat, 1 kl welding rod 6 carpenters
temporary fence
-no fence under the new - To enclose the space that - 3 kls nails (1,2,3”), old flat 20 carpenters
building that serves as will serve as a stock room sheets
stock rooms for logs
15. School Library / No school library To dismantle the wall that Hammer, crow bar 5 volunteers
divides the Grade 1 and kinder
temporary room and fix as
library room
16. Wash through / - Not enough wash - To construct 5 sacks Cement, 25 sack sand, 4 volunteers
through pipes, elbow, faucets
- No water supply in - To provide water supply
the old wash through
17. Stairway / - Damaged hand drills - To repair Nails, woods 2 volunteers
of the stairs to Grade
3 room
18. Classrooms - There are 2 grades - Hauling of classroom Hammer, nails 50 volunteers
in 1 room furniture equipment and
school learning resources
from the old building to the
new building
19. School stage - faded paints - to repaint Steel mats, paints 3 painters