Aroad embankment 10 m wide at the formation level with side slopes 2:1 and with an
average height of 5 m Is constructed with an average gradient of 1:40 from the contour
220 m to 280 m. Find the volume of earthwork.
This question was previously asked in
Ss crs ow ep 0 el
on 30 Oct 2020 Evening)
View all SSC JE CE Papers >
1. 6,40,000 m?
2. 1,40,000 m3
3. 3,40,000 m?
4. 2,40,000 m?
‘Answer (Detailed Solution Below)
Option 4 : 2,40,000 m3roan)
Crack AE/JE + DRDO + AAI ATC with Ir
Gs eae
CeCe eons
Detalled Solution
Concept:
Gradient:
A gradient is the rate of rise or falls along the length of the road with respect to horizontal. It is
expressed as ‘1’ vertical unit to 'N' horizontal units
L
Tand = ®
hel
+o
Area of trapezoidal:
According to the trapezoid area formula, the area of a trapezoid is equal to half the product of the
height and the sum of the two bases.
Area = ¥ x (Sum of parallel sides) x (perpendicular distance between the parallel sides),
Calculation:
10m'*—10m—110m
Road embankment = 10 m
Average height = 5m ~Difference in elevation(h) = 280 - 220 = 60m
1
Average gradient = 0
bh — J
+ te
eo — 1
+ 40
L=2400m
10m
Sm
————.- —™§|_—"
30m
1
Average cross-sectional area(A) = + * (10 + 30) x 5
A= 100m?
Volume of earthwork = Ax L
Volume of earthwork = 100 x 2400
+ Volume of earthwork = 2,40,000 m?