Lot 1 - Construction of SMKN Palu
Lot 1 - Construction of SMKN Palu
Week
No MANPOWER Unit
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
1 Pekerja People 8 8 8 8 8 8 8 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 8 8 8 8 5
8 Instalator People - - - - - - - - - 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1
12 Mandor People 1 1 1 1 2 2 2 2 2 2 2 2 4 4 4 4 4 4 4 4 4 4 4 2 2 2 2 2
TOTAL 22 26 34 37 45 47 50 55 58 62 62 62 65 68 68 68 68 68 68 68 66 66 63 59 43 29 27 20
70 68 68 68 68 68 68 68
66 66
65
62 62 62 63
59
60 58
Number of Manpower
55
50
50 47
45
43
40 37
34
29
30 26 27
22
20
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Week
Week
No MATERIAL
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 17 18 19 20 21 22 23 24 25
1 Pasir Urug
2 B.0 Slump 10 ± 2
3 Batu Bata Ukuran 5 x 11 x 22
4 Batu Kali / Batu Belah
5 Besi Beton Polos
6 Atap Spandek
7 Granite Tile 40 x 40 cm Polished
8 K. 175 Slump 10 ± 2
9 K. 250 Slump 10 ± 2
10 Kayu balok/kaso
11 Granite Tile 40 x 40 cm Unpolished
12 Keramik Dinding 25 x 40 cm (Unpolish)
13 Lampu LED
14 Multipleks
15 Paku
16 Pasir Beton
17 Pasir Pasang
18 Pipa PVC Type AW
19 Roster Beton 20 x 20 cm
20 Saklar
21 Semen Portland (50 Kg)
22 Semen Putih 25 Kg
23 Sika Top 107 Seal Waterproofing
24 Stop Kontak
VOL Week
No EQUIPMENT
(UNT) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
1 Dump Truck 2
2 Generator set 1
3 Concrete Mixer 4
4 Concrete Vibrator 2
5 Horse Stamper 1
6 Hammer Drill 2
7 Theodolite 1
8 Waterpass 1
KETERANGAN
: MOBILISATION
: DEMOBILISATION Palu, 20 March 2023
PT. NURMAN ABADI
SYAFRUDDIN ABDULLAH
Directur