Professional Documents
Culture Documents
Port Planning - Chapter 1
Port Planning - Chapter 1
I. Artificial Port:
(a) Artificial port are those constructed along a shoreline by means of earth fill (or) excavation.
(b) These ports have to be protected from adverse of waves and currents.
(c) Land part of port is created by earth fill and water part by means of excavation of land adjacent to the
shoreline.
(d) Geometry of excavated land depends on the size of port.
(e) Excavated harbour is joined to sea via the approach channel. Entrance protected by breakwater and dikes from
waves and currents.
Planning a Port location
(i) Ownership of land
(ii) Topography and survey records
(iii) Existing utilities and structures at site
(iv) Wind and rainfall data
(v) Hydrographic information
(vi) Geotechnical data
(vii) Environmental Impact Assessment (EIA) studies
General Layout of Port works
(i) Easy berthing of vessels
(ii) Efficient cargo loading and unloading facilities
(iii) Safe passenger embarkation and disembarkation
(iv) Appropriate navigation channel
(v) Adequate manoeuvring area
(vi) Avoidance of undesired erosion and deposition of materials in and
around harbour area
Responsible factors includes, (i) winds, (ii) waves, (iii) currents, (iv)
sediment transport, (v) river discharge in immediate vicinity, (vi)
seiches (harbour resonance)
Port Entrance
Major criteria orientation and width of entrance to harbour
For comfortable navigation harbour entrance should communicate
directly with open sea, and should be wide as possible.
Narrow harbour entrance protected from wave energy and deposits
entering harbour basin.
Orientation of harbour entrance (i) prevailing wind to foreside
(usually recommended), (ii) transverse wind and wave create difficult
condition for steering the vessel.
(a) Designer should avoid placing harbour entrance in region of wave breaking.
(b) To attain calmest possible condition at harbour entrance area, external works will be formed
with sloping mounds so that wave energy is absorbed.
(c) Breakwaters with vertical front near entrance results in reflected and diffracted waves
causing difficult navigation conditions.
(d) Depth at harbour entrance is determined by maximum draft of the design vessel. This depth
is taken beneath the lowest low water level so that harbour is always accessible.
(e) In areas of large tidal range, to ensure accessibility of ports at all times dredge depth should
be equal to range in tidal level.
(f) Certain ports have gates which makes vessel wait for longer time in open sea.
(g) Safety factor of about 15% of design vessel draft is sufficient for defining minimum
entrance depth.
(h) Width of free entrance channel ranges between 100 and 250 m depending on size of the port
(recommended: width of channel to be at least equal to the length of design vessel.)
Manoeuvring Area
(i) Vessel entering harbour basin speed needs to be reduced
to proceed with anchoring and berthing.
(ii) Normal speeds (8 – 11 knots) length scale (2-3L), ‘L’
being the vessel length.
(iii) Manoeuvring area is located in outer harbour, situated
between port entrance and main port, (or) in harbour basin
close to the entrance.
Wave agitation in Port basin
(a) Main factor causing interruption in port basin is wind generated
waves.
(b) Apart from penetration through entrance, wave transmission and
overtopping in breakwaters are of major concerns.
(c) Solution (i) laboratory testing of various designs in a physical
model, (ii) mathematical models wave heights in sections of
harbour basin are determined under various environmental
conditions degrees of absorption by solid boundaries
(d) Wavelength of incident waves (certain wavelengths are extremely
dangerous) significant effect on vessel behaviour.
Long Oscillations
Apart from wind generated waves there are other causative forces,
viz; extreme events (storms) and seismically created waves.
(i) Long oscillations (seiches) trapped oscillations with periods
exceeding 30 sec. For example, barotropic lows, surf beats, edge
waves etc.
(ii) Resonant nature generate seiches, normally the flow velocity
at nodes of oscillation of free surface may reach 0.5 m/s
(iii) Phase velocity of long waves in shallow waters 𝑐𝑐 = 𝑔𝑔𝑔
For harbour basins with a rectangular plan of dimension 𝐿𝐿 × 𝑊𝑊 with entrance
on 𝑊𝑊side, the resonance period of standing waves 𝑇𝑇𝐿𝐿 is given by:
4𝐿𝐿
𝑇𝑇𝑙𝑙 = (n = 1, 3, 5, ……)
𝑛𝑛 𝑔𝑔𝑔
with a node at entrance and anti-node at the opposite side of the basin.
2𝑊𝑊
𝑇𝑇𝑤𝑤 = (n = 1, 2, 3, ……)
𝑛𝑛 𝑔𝑔𝑔
𝑘𝑘𝑘𝑘
( )𝑛𝑛
−𝑘𝑘𝑘𝑘/𝑇𝑇 ∑𝑘𝑘−1 𝑇𝑇
• 𝑃𝑃 𝑡𝑡 = 𝑒𝑒 This equation is the Queuing
𝑛𝑛=0 𝑛𝑛!
theory and (𝑇𝑇) is the average vessel servicing time.
Berth Occupancy
(1) Occupancy rate of group of berths expresses the percentage of
time the berth positions are occupied by ships being serviced.
(2) Effect of berth occupancy on waiting time depends on the
probability distribution of arrival and servicing time as well as
number of berths available to the sector.
(3) For example, w.r.t. general cargo terminal the berth occupancy
𝑀𝑀
factor (𝑘𝑘0 ) is equal to /𝑛𝑛 (In this equation, 𝑀𝑀 represents the
𝐸𝐸𝑟𝑟
Poisson distribution; 𝐸𝐸𝑟𝑟 represents the Erlang distribution; and 𝑛𝑛
represents the number of vessels.
Problem – I
Assume that there are 10 general cargo berths
available, and an average of 2 vessels/day are heading
for a berth. If the average servicing time is 3.5 days, the
berth occupancy factor 𝑘𝑘0 is:
2 × 3.5
𝑘𝑘0 = = 0.70
10
Number of Berths
Key parameter in the design aspects of general cargo terminal is the
number of berths. Mathematically it is expressed in the form:
𝑄𝑄
𝑛𝑛 =
24𝑘𝑘0 𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞
In this formula:
𝑄𝑄 Annual cargo flow estimate (in tonnes)
𝑘𝑘0 Berth occupancy factor
𝑞𝑞 Average tonnage handled by one gang/hour (calculated from
statistical data of similar port).
𝑝𝑝 Fraction of time during which the berths are operational. For
example, if total daily working hours per berth is 16 hours over 6
6
days per week, then 𝑝𝑝 = 16 × × 7 = 0.572
24
𝑟𝑟 Average number of gangs concurrently loading/unloading on
averaged sized vessel (depends on the cargo type & vessel size).
𝑁𝑁 Days of berth operation in a year.
𝑄𝑄
As a first approximation, 𝑛𝑛 ≅
𝑘𝑘0
1.7 𝑄𝑄𝑄𝑄 𝑃𝑃
𝐴𝐴 = 1+
365 𝑑𝑑𝑑𝑑 100
𝑄𝑄 Indicates the annual tonnage to be stored (capacity) that depends on the
portion of total cargo flow requiring storage.
𝐷𝐷 Indicates the average storage duration (in days).
𝑑𝑑 Indicates the cargo density (tons/m3) that is calculated using the stowage
factor (m3/ton). Stowage factor ratio of weight to stowage space required
under normal conditions how many cubic meters one metric ton of particular
type of cargo occupies in hold takes into account stowage losses also
depends on the packing methods.
𝐻𝐻 Indicates the average stowage height (in meters) average value 2 – 3
m.
𝑝𝑝 Indicates the peak factor multiplies the average area to accommodate
cargo flows (typically, 25 – 40%)
Schematic representation: Layout of Berths and Facilities
Busiest Ports in India
1 TEU is Twenty-foot Equivalent Unit =
1. Mundra Port, Gujarat 20 feet (6.1 meters) long x 8 feet (2.4
meters) wide x 8.5 feet (2.6 meters)
high having a maximum load of
23.600 Kg.
Third oldest port in India established in 1881. Major exports includes include cotton, textiles, automobiles, iron,
and leather. The main imports are wheat, machinery, iron, steel, and raw cotton. It has three docks and 24
berths – including a cruise terminal.
Ia <7 1.5
Ib 7 – 10 4.5
II 10 – 20 25
III a 20 – 30 85
III b 30 – 60 400
IV 60 – 170 500 – 3500
Andhra Pradesh 15.8 4.38 20.18 15.03 4.75 19.79 18.32 5.2 23.52 21.86 5.8 27.66 28.45 6.05 34.5
West Bengal 13.92 1.88 15.81 14.38 1.79 16.17 14.93 1.78 16.71 15.25 1.77 17.02 15.57 1.85 17.42
Gujarat 0.98 6.96 7.93 1.11 6.98 8.1 1.12 6.97 8.1 1.17 6.99 8.16 3.34 12.11 15.45
Kerala 1.94 3.2 4.14 1.36 3.33 4.7 1.77 4.45 5.21 5.55 5.53 10.08 5.35 10.00 15.35
Tamil Nadu 1.92 4.32 6.24 2.4 4.57 6.98 2.43 4.67 7.09 1.97 4.72 6.69 1.85 6.97 8.82
Uttar Pradesh 4.64 0 4.64 4.94 0 4.94 5.05 0 5.05 6.18 0 6.18 6.29 0 6.29
Maharashtra 1.35 4.67 6.03 1.44 4.64 6.08 1.46 4.34 5.8 2 4.63 6.63 1.31 4.75 6.06
Odisha 1.98 3.57 5.55 2.23 4 6.23 1.69 4.12 5.81 1.59 3.99 5.57 1.88 4.14 6.03
Bihar 4.32 0 4.32 4.8 0 4.8 5.07 0 5.07 5.09 0 5.09 5.88 0 5.88
Karnataka 1.86 5.22 7.09 2.02 5.24 7.26 2.11 5.17 7.28 1.61 4.31 5.93 1.48 4.14 5.63
India 61.36 34.43 95.79 66.91 35.69 102.6 71.62 36 107.62 78.06 36.25 114.31 89.02 36.88 125.9
Fish production (In Lakh tonnes) Annual Average Growth Rate (Percent)
Marine Inland Total Marine Inland All India
1 1950-51 5.34 2.18 7.52 - - -
2 1980-81 15.55 8.87 24.42 - - -
3 1981-82 14.45 9.99 24.44 -7.07 12.63 0.08
4 1982-83 14.27 9.40 23.67 -1.25 -5.91 -3.15
5 1983-84 15.19 9.87 25.06 6.45 5.00 5.87
6 1984-85 16.98 11.03 28.01 11.78 11.75 11.77
7 1985-86 17.16 11.60 28.76 1.06 5.17 2.68
8 1986-87 17.13 12.29 29.42 -0.17 5.95 2.29
9 1987-88 16.58 13.01 29.59 -3.21 5.86 0.58
10 1988-89 18.17 13.35 31.52 9.59 2.61 6.52
11 1989-90 22.75 14.02 36.77 25.21 5.02 16.66
12 1990-91 23.00 15.36 38.36 1.10 9.56 4.32
13 1991-92 24.47 17.10 41.57 6.39 11.33 8.37
14 1992-93 25.76 17.89 43.65 5.27 4.62 5.00
15 1993-94 26.49 19.95 46.44 2.83 11.51 6.39
16 1994-95 26.92 20.97 47.89 1.62 5.11 3.12
17 1995-96 27.07 22.42 49.49 0.56 6.91 3.34
18 1996-97 29.67 23.81 53.48 9.60 6.20 8.06
19 1997-98 29.50 24.38 53.88 -0.57 2.39 0.75
20 1998-99 26.96 26.02 52.98 -8.61 6.73 -1.67
21 1999-00 28.52 28.23 56.75 5.79 8.49 7.12
22 2000-01 28.11 28.45 56.56 -1.44 0.78 -0.33
23 2001-02 28.30 31.26 59.56 0.68 9.88 5.30
24 2002-03 29.90 32.10 62.00 5.65 2.69 4.10
25 2003-04 29.41 34.58 63.99 -1.64 7.73 3.21
26 2004-05 27.79 35.26 63.05 -5.51 1.97 -1.47
27 2005-06 28.16 37.56 65.72 1.33 6.52 4.23
28 2006-07 30.24 38.45 68.69 7.39 2.37 4.52
29 2007-08 29.20 42.07 71.27 -3.44 9.41 3.76
30 2008-09 29.78 46.38 76.16 1.99 10.24 6.86
31 2009-10 31.04 48.94 79.98 4.23 5.52 5.02
32 2010-11 32.50 49.81 82.31 4.70 1.78 2.91
33 2011-12 33.72 52.94 86.66 3.75 6.28 5.28
34 2012-13 33.21 57.19 90.40 -1.51 8.03 4.32
35 2013-14 34.43 61.36 95.79 3.67 7.29 5.96
36 2014-15 35.69 66.91 102.60 3.66 9.04 7.11
37 2015-16 36.00 71.62 107.62 0.87 7.04 4.89
38 2016-17 36.25 78.06 114.31 0.70 8.99 6.21
39 2017-18 36.88 89.02 125.90 1.73 14.05 10.14
Source: State Governments/Union Territory Administration
Percentage contribution
of Inland and Marine
Fisheries in different
time spans
Pradhan Mantri Matasya Sampada
Yojana (PMMSY)