ENERGY SAVINGS

HERON ISLAND
RESORT
 

Prepared for Wide Bay Water Corporation

Integrated Energy Services Corporation Pty Ltd


ABN 56 106 199 991
Project No: 1087
Prepared: 4 March, 2010
Revision: Draft

Integrated Energy Services Corporation Pty Ltd PO Box 5926 West End Qld 4101
Ph: 61 7 3844 8338 Fax: 61 7 3036 6245 Email:office@ensight.com.au website:www.ensight.com.au
TABLE OF CONTENTS
ENERGY SAVINGS HERON ISLAND RESORT ......................................................................................... 1  
1   EXECUTIVE  SUMMARY............................................................................................................................................ 4  
2   IMPLEMENTATION .................................................................................................................................................. 6  
3   INTRODUCTION ........................................................................................................................................................ 7  
3.1   GENERAL....................................................................................................................................................................................7  
3.2   OBJECTIVES ..............................................................................................................................................................................7  
3.3   SCOPE  OF  WORKS...................................................................................................................................................................7  
3.4   METHODOLOGY ......................................................................................................................................................................7  
3.5   LIMITATIONS ...........................................................................................................................................................................7  
3.6   CAVEAT.......................................................................................................................................................................................8  
3.7   SITE  INSPECTIONS  AND  INTERVIEWS..........................................................................................................................8  
4   BACKGROUND ........................................................................................................................................................... 9  
4.1   LOCATION..................................................................................................................................................................................9  
4.2   HERON  ISLAND  RESORT .....................................................................................................................................................9  
4.2.1   HERON ISLAND RESORT FACILITIES ............................................................................................................ 9  
5   CURRENT  ENERGY  USAGE ...................................................................................................................................10  
5.1   ANNUAL  ENERGY  USAGE ................................................................................................................................................. 10  
5.2   PEAK  POWER  DEMAND  &  LOAD  DURATION........................................................................................................... 10  
5.3   RESORT  ENERGY  SERVICES  USAGE............................................................................................................................. 11  
6   AUDIT  –  ENERGY  SERVICES.................................................................................................................................13  
6.1   RESORT  ENERGY  SERVICES............................................................................................................................................ 13  
6.2   LIGHTING ................................................................................................................................................................................ 14  
6.2.1   DESCRIPTION OF EXISTING SYSTEM.........................................................................................................14  
6.2.2   LIMITATIONS OF EXISTING DESIGN.............................................................................................................14  
6.2.3   EFFICIENT ALTERNATIVE DESIGN ................................................................................................................14  
6.3   AIR-­‐CONDITIONING  &  VENTILATION ........................................................................................................................ 16  
6.3.1   DESCRIPTION OF EXISTING SYSTEM.........................................................................................................16  
6.3.2   LIMITATIONS OF EXISTING DESIGN.............................................................................................................16  
6.3.3   EFFICIENT DESIGN ALTERNATIVE ................................................................................................................17  
6.4   HOT  WATER........................................................................................................................................................................... 18  
6.4.1   DESCRIPTION OF EXISTING SYSTEM.........................................................................................................18  
6.4.2   LIMITATIONS OF EXISTING DESIGN.............................................................................................................18  
6.4.3   EFFICIENT ALTERNATIVE DESIGN ................................................................................................................18  
6.5   CATERING  FACILITIES ...................................................................................................................................................... 19  
6.5.1   DESCRIPTION OF EXISTING SYSTEM.........................................................................................................19  
6.5.2   LIMITATIONS OF EXISTING DESIGN.............................................................................................................19  
6.5.3   EFFICIENT ALTERNATIVE DESIGN ................................................................................................................19  
6.6   REFRIGERATION  FACILITIES......................................................................................................................................... 20  
6.6.1   DESCRIPTION OF EXISTING SYSTEM.........................................................................................................20  
6.6.2   LIMITATIONS OF EXISTING DESIGN.............................................................................................................20  
6.6.3   EFFICIENT ALTERNATIVE DESIGN ................................................................................................................20  
6.7   LAUNDRY  FACILITIES ....................................................................................................................................................... 22  
6.7.1   DESCRIPTION OF EXISTING SYSTEM.........................................................................................................22  
6.7.2   LIMITATIONS OF EXISTING DESIGN.............................................................................................................22  
6.7.3   EFFICIENT ALTERNATIVE DESIGN ................................................................................................................22  
6.7.4   UNMET SERVICES......................................................................................................................................................22  
6.8   OTHER  SERVICES....................................................................................................................................................................... 23  
6.8.1   DESCRIPTION OF EXISTING SYSTEM.........................................................................................................23  
6.8.2   EFFICIENT ALTERNATIVE DESIGN ................................................................................................................23  
7   CONCLUSIONS ..........................................................................................................................................................24  
8   RECOMMENDATIONS ............................................................................................................................................25  
8.1   OVERVIEW.............................................................................................................................................................................. 25  
8.2   ENERGY  EFFICIENCY  AND  ENERGY  MANAGEMENT  INITIATIVES................................................................ 25  
APPENDIX  1  -­  PROJECT  METHODOLOGY................................................................................................................27  
APPENDIX  2  -­  LOAD  STATISTICS...............................................................................................................................29  
APPENDIX  3  -­  PEAK  POWER  DEMAND ....................................................................................................................30  
APPENDIX  4  -­  LOAD  DURATION ................................................................................................................................31  

Integrated Energy Services Corporation Pty Ltd PO Box 5926 West End Qld 4101
Ph: 61 7 3844 8338 Fax: 61 7 3036 6245 Email:office@ensight.com.au website:www.ensight.com.au
APPENDIX  5  -­  EQUIPMENT  DETAILS........................................................................................................................32  
APPENDIX  6  –  SERVICE  USAGE ..................................................................................................................................33  

Integrated Energy Services Corporation Pty Ltd PO Box 5926 West End Qld 4101
Ph: 61 7 3844 8338 Fax: 61 7 3036 6245 Email:office@ensight.com.au website:www.ensight.com.au
Prepared by EnSight  

1 EXECUTIVE SUMMARY

The Heron Island Resort is currently using energy in-efficient technologies with an estimated existing
energy demand of 1,767 MWh per annum. The resort currently spends $621,358 per annum on diesel
fuel with the cost of diesel fuel to generate the electricity (excluding maintenance) being $0.35/kWh,
and LPGas at a cost of $0.11/kWh. This means that there are generally very short payback periods on
investment in energy efficient technologies and practices.

Based on implementing all the initiatives the resort could decrease its energy demand by 802 MWh,
reducing total operating costs by $280,000 a reduction of 47%. The capital investment required to
achieve this saving is estimated to be $996,000 providing a rate of return on investment of 29%. The
environmental benefits are also significant, with a reduction in greenhouse gas emissions estimated to
be 721 tonnes per annum. These energy savings are made up of several separate initiatives that are
summarised below.

Lighting - Through the wide spread adoption of energy efficient lighting in the resort, energy usage
will be reduced by over 178,000 kWh per annum, and operational savings of $62,400 will be achieved
for an estimated capital investment of $159,000 giving a rate of return on the investment of 39%.

Climate Control - Through the wide spread adoption of energy management in the application of air
conditioning throughout resort, energy usage will be reduced by over 165,900 kWh per annum, and
operational savings of $58,000 will be achieved for an estimated capital investment of $307,000 giving
a rate of return on the investment of 19%.

Hot Water - The implementation of a hot water ring main to some accommodation units, use of gas
boosters instead of electric water heaters, will reduce energy usage by over 117,000 kWh per annum
and operational savings of $41,000 will be achieved for an estimated capital investment of $206,000
giving a rate of return on the investment of 20%.

Refrigeration - The implementation of super efficient refrigeration equipment for cold rooms and
freezer rooms, upgrading 30 guest bar fridges and removing the remainder will reduce energy usage
by over 78,400 kWh, saving over $27,400 per annum. The estimated capital cost to upgrade the
energy management system would be in the order of $102,000 giving a rate of return on the
investment of 27%.

Laundry - The implementation of cold water laundry washing product will reduce energy consumption
by over 16,300 kWh saving over $5,700 per annum. The estimated capital cost to upgrade the
washing detergent would be in the order of $1,000 giving a rate of return on the investment of nearly
500%.

Kitchen - The implementation of new gas kitchen equipment will reduce electricity consumption by
over 56,400 kWh saving over $19,700 per annum. The estimated capital cost to upgrade the energy
management system would be in the order of $91,500 giving a rate of return on the investment of
21.5%.

Metering - The implementation of extensive online metering along with an Energy Management Plan
with efficiency benchmarks for each major energy use has the ability reduce electricity consumption by
over 80,000 kWh saving over $28,000 per annum. The estimated capital cost to upgrade the energy

Page 4 of 4
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

management system would be in the order of $85,000 giving a rate of return on the investment of
33%.

Page 5 of 5
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

2 IMPLEMENTATION

Heron Island Resort’s diesel generators currently operate with 3 generators on during peak demand
and a minimum of two generators at other times. By implementing immediate demand management
strategies, the diesel generators will be able to operate with 2 generators at peak and 1 generator at
off peak hours. The key implementation measures for the resort are:

• implement energy efficient lighting

• implement energy efficient ceiling fans

• implement boosting hot water services with gas on other guest and staff accommodation water
heating

• installation of gas based clothes drying equipment in guest laundries

• installation of gas appliances in the kitchen including rack conveyor, urn, combi steamer, pass-
through, and espresso machine

• installation of room based air conditioning system controls

• installation of energy meters to monitor resort building energy use

• Establish and implement an energy management program

Page 6 of 6
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

3 INTRODUCTION

3.1 GENERAL

Wide Bay Water Corporation engaged EnSight to undertake a detailed energy audit and develop cost
and energy saving strategies for Heron Island Resort.

3.2 OBJECTIVES

In preparing this Energy Service Report, the objectives include:

• Reduce annual energy costs without compromising the Resort's level of service to its clients.

• Identify energy saving opportunities from the adoption of energy efficient technologies

3.3 SCOPE OF WORKS

Stage 1: Audit/Review of Existing Energy Utilisation Technologies

Stage 2: Audit/Review of Existing Power Generation System

Stage 3: Analysis and Review

This Report:

• Describes energy consuming appliances and energy supply technologies and their current usage
patterns in the resort;

• Recommends cost effective energy efficient strategies.

In undertaking the project, the following activities were undertaken:

1. Pre-site visit research

2. Site familiarisation

3. Site energy audit

4. Computer energy and financial modeling

5. Analysis of modeling data and preparation of report including an implementation strategy.

3.4 METHODOLOGY

Details of the methodology used in the development of this report are contained in Appendix 1.

3.5 LIMITATIONS

This report is only concerned with issues that impact upon energy use. The report has relied on data
provided by Heron Island Resort, and the analysis and recommendations are based on this data.
Water issues have been addressed only in the context of their impact on energy use and do not
address matters such as water supply, and matters that impact on the site such as sewerage

Page 7 of 7
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

treatment infrastructure design, groundwater management or environmental issues relating to sewage


treatment facilities are the responsibility of Wide Bay Water.

3.6 CAVEAT

Whilst every effort is taken to ensure that the accuracy of this report, EnSight does not accept any
liability for any economic loss to the Heron Island Resort from reliance of the findings of this report. To
obtain the benefits outlined in this report detailed engineering is required to be undertaken. Due to the
report’s conceptual approach, this detailed engineering may identify additional technical issues that
need to be addressed that are not identified in this report. EnSight does not intend that Heron Island
Resort will proceed with any project identified in this report without undertaking detailed engineering
designs and budgets to confirm or otherwise the report’s recommendations unless this report was
accepted and EnSight took full responsibility for implementing the report’s findings.

3.7 SITE INSPECTIONS AND INTERVIEWS

EnSight’s Energy Auditors, Francis Barram and Paddy Atkinson carried out an inspection of the site
th th
between the 8 and 12 February 2010. As part of the site visit, extensive interviews were carried out
with the Resort’s Maintenance Manager.

Page 8 of 8
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

4 BACKGROUND

4.1 LOCATION

Heron Island, east of Gladstone by some 72km on Queensland’s Capricorn Coast. The 18-hectare
coral cay. The island is located on the World Heritage-listed Great Barrier Reef and is one of a handful
of coral cays off the Queensland coast.

4.2 HERON ISLAND RESORT

Heron Island comprises 109 rooms across 5 distinct accommodation styles: 1 Beach House, 4 Point
Suites, 2 Wistari Suites, 20 Beachside Suites, 50 Reef Suites and 32 Turtle Rooms.

4.2.1 HERON ISLAND RESORT FACILITIES

The Resort was developed in 1990. Resort facilities include:


• 50 x Reef Suites (guest accommodation)
• 32 x Turtle Rooms (guest accommodation)
• 20 x Beachside Suites (guest accommodation)
• 1 x Beach House
• 4 x Point Suites
• 2 x Wistari Suites
• 1 x Central Building with bar
• Shearwater Dining area and main kitchen
• Administration, Shop, and Day room
• Aquaspa
• Swimming Pool
• Island Environmental Education
• Various staff accommodations
• Staff Ablutions Block
• Wobbly Bar and Gym for Staff
• Diesel Generator Room
• Desalination Plant
• Workshop
• Pump House
• Sewerage Plant
• Guest laundries
• Resort Laundry
The Resort is responsible for generating its own electricity and potable water.

Page 9 of 9
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

5 CURRENT ENERGY USAGE

5.1 ANNUAL ENERGY USAGE

This section details the current annual energy consumption of the Resort facilities. Because electricity
consumption is not metered, fuel usage is the best indicator of annual electricity use. Resort purchase
records were provided for the past 2 years, along with recorded electricity consumption of the resort
and the readings for the University of Queensland’s Research Station. Details of annual fuel usage
based on purchases as related to over the past year are provided in the table below.
Total Power Station
Diesel Fuel Use
Fuel Yearly Fuel Yearly Cost
Usage
Diesel 649,523 L $746,951

Table 1a: Total Power Station Annual Fuel Consumption

Based on total fuel consumption records 649,523 litres and electricity generation records 2,092 MWh
(refer to Appendix 2: Load Statistics). Based on diesel fuel costs of $1.14 per litre, the cost per kWh to
generate electricity is estimated at $0.35. Generator efficiency is at 30.3%.

The resort’s portion of the Total diesel fuel consumption is 540,311 litres which costs the resort some
$621,358 per annum.
Heron Island Resort
Diesel Fuel Use
Fuel Yearly Fuel Yearly Cost
Usage
Diesel 540,311 L $621,358

Table 1a: Total Heron island Resort Annual Fuel Consumption

5.2 PEAK POWER DEMAND & LOAD DURATION

The energy audit and computer modeling of hourly electricity use (and based on the results from on-
site monitoring), indicates that the resort has a peak power demand of 450kW (refer to Appendix 3:
Peak Power Demand). The load duration curve, which is the estimated hourly load ranked from
highest demand to lowest demand for each of the 8,760 hours per year is in Appendix 4: Load
Duration.

Page 10 of 10
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

5.3 RESORT ENERGY SERVICES USAGE

A breakdown of energy usage for Resort facilities based upon audit results and computer modeling is
provided in Table 2 and Figure 1.
Component of Energy Use Annual Energy Proportion of Total
Use Energy Use (%)
(kWh/yr)
Air Conditioning 287,245 16.3%
Ventilation 122,561 6.9%
Workshop Equip. 766 0.0%
Cooking & Catering 82,084 4.6%
Lighting 279,934 15.8%
Laundry 28,691 1.6%
Refrigeration 292,634 16.6%
Office & Entertainment Equipment 80,303 4.5%
Pumping 280,855 15.9%
Hot Water 259,624 14.7%
Miscellaneous 52,762 3.0%
TOTALS 1,767,459 100.0%
Table 2: Breakdown of Total Energy Use by Service

Page 11 of 11
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

Total energy use on site (including water services detailed in Section 7) is 1,767 MWh (refer to
Appendix 5: Equipment Details). As can be seen from the table and pie chart, air conditioning &
ventilation followed by water heating, lighting, pumping, and refrigeration constitutes the highest
energy uses on site.

The following sections consider each service in detail.

Page 12 of 12
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

6 AUDIT – ENERGY SERVICES

6.1 RESORT ENERGY SERVICES

This section details our audit findings for each of the services provided on site, excluding water that is
provided in Section 7.
1. Lighting
2. Air conditioning
3. Hot water – guest, staff and operational services
4. Cooking facilities – Main kitchen.
5. Refrigeration – guest, staff and operational services.
6. Other services – includes appliances, office equipment, and workshop equipment.

For each of these energy services, the following will be provided:


• Description of Existing System
• Limitations of Existing System
• Efficient Alternative Design - results of our computer modeling, including energy savings, capital
and operational savings for a number of alternative efficient designs.
• Un-Met Services - details of energy service needs that are currently not been met by the existing
systems and also recommendations for future energy efficiency measures. No modeling has been
undertaken for these measures.

Page 13 of 13
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

6.2 LIGHTING

6.2.1 DESCRIPTION OF EXISTING SYSTEM

Lighting uses 89,709 kWh/year of energy per year and accounts for an estimated 18% of the total
energy use of the Resort. Lighting sources at the Resort include:
• Low voltage halogen spot lighting and compact fluorescent lighting accommodation and central
core

• Low voltage halogen and CFLs for path and garden lighting

• T8 Fluorescent fittings throughout resort kitchen, offices and workshops

• Floodlights to provide security lighting

Lighting System Summary


1
Component of Energy Use Energy Use/yr Op. Costs GHG
(kWh/yr) ($) (Tonnes/yr)

Lighting 279,934 $97,977 228

Table 3: Lighting - Energy Use - Audit Results

6.2.2 LIMITATIONS OF EXISTING DESIGN

Equipment

 The existing lighting system in the guest accommodation and facilities of the resort utilises a range
of 35 watt to 50 watt halogen lamps. There is program of replacing all failed 50 watt lamps with 35
watt lamps, reducing lumen output for each application.

 The existing lighting system does not utilise efficient energy management practices.

 The existing lighting system in the office and back of house areas utilise the inefficient T8
fluorescent lamps.

Practices

 In many cases, 66% of unoccupied guestrooms were found to have one or more lights left on.

6.2.3 EFFICIENT ALTERNATIVE DESIGN

Equipment

 Replace all halogen downlights with a 10 watt LED (similar lumen output to 50watt halogen)
downlight.

                                                                                                                                       
1
Based on the cost of electricity generation of $0.35/kWh.

Page 14 of 14
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

 Replace all T8 fluorescent fittings with LED fluorescent.

 Replace all compact fluorescent lamps with LED replacements.

Practices

 Educate staff and guests to switch off lights when not in use. For example, switching off halogen
downlights in the Shearwater Restaurant during daylight occupancy can reduce energy usage
from 18,000 kWh/year.

Recommended Lighting Efficiency Improvements

Energy Efficiency Initiative Energy Capital Op. Rate of GHG


Savings/yr Investment Savings Return (Tonnes/yr)
(kWh/yr) ($) ($) (%)
1. 16W Led fluro replacements
58,050 42,000 20,318 48% 47.40
(some energy management)
2. 6W LED incandescent and CFL
replacements (some energy
17,591 24,000 6,157 26% 14.36
management)
3. 10W LED halogen replacement
102,751 93,671 35,963 38% 83.90
(some energy management)

Table 4: Lighting - Recommended Efficient Alternatives

Page 15 of 15
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

6.3 AIR-CONDITIONING & VENTILATION

6.3.1 DESCRIPTION OF EXISTING SYSTEM

Air-conditioning and Ventilation which also ceiling fans uses around 409,806 kWh/year of energy per
year and accounts for an estimated 23.2% of the total electricity use of the Resort. Air conditioners are
used in seven guest units, the Shop, Aqua Spa, dive training room, Wobbly Bar, Staff Gym, Head
Chef, Pastry Kitchen and staff accommodation. All of the air conditioners are of the refrigerative direct
expansion split air conditioner type. This type of unit has a maximum technical efficiency of 300%.
Ventilation consists of kitchen exhausts and

Resort Air Conditioning & Ventilation Summary

Component of Energy Use Energy Use Op. Costs GHG


(kWh/yr) ($/yr) (Tonnes/yr)
Air Conditioners 287,245 100,536 235

Ceiling Fans 69,652 24,378 57

Kitchen Exhaust Fans 40,207 14,072 33

Table 5: Air-conditioning & Ventilation- Energy Use - Audit Results

6.3.2 LIMITATIONS OF EXISTING DESIGN

Equipment

 The performance of DX type air conditioners are not controlled by room based energy
management technology, resulting in air conditioners operating in unoccupied rooms.

 The ceiling fan technology used throughout the resort uses on average 70 watts of power at high
speed compared with world best practice 25 watts, with higher air movement output, resulting in
wasted power.

 The kitchen exhaust ventilation fans are currently operated from early AM to late PM, the fan
exhaust volume is unable to be adjusted in accordance with the need of the kitchen’s levels of air
pollution.

Practices

 In areas such as the back of house, the air conditioners are on when there is often no occupancy,
wasting electrical energy.

Unmet Energy Services

 The resort has a desire to offer more wide spread guest room air conditioners. Current power
station constraints however, do not allow additional air conditioners to be installed.

Page 16 of 16
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

6.3.3 EFFICIENT DESIGN ALTERNATIVE

1. Install a movement-controlled energy management system on all air conditioners in the Resort
that allow the air conditioner to turn off when no one is utilising the office area, savings of up to
50% are estimated.

2. Replace all ceiling fans with high efficiency pulse modulated DC motor type units, saving up to
75% of the energy.

3. Install variable speed drive and light sensors in the main kitchen hoods to control the ventilsation
fans, this will reduce the expected energy usage by up to 70%.

Recommended Air Conditioning Improvements

Energy Efficiency Initiative Energy Capital Op. Rate of GHG


Savings/yr ($) Savings Return (%) (Tonnes/
(kWh/yr) ($) yr)
1. Energy Management on all air
conditioning systems 89,375 128,500 31,281 24% 73

2. Efficient fans 54,356 166,000 19,024 11% 44


3. Energy management on kitchen
exhaust 22,124 12,500 7,743 62% 18

Total 165,855 307,000 58,049 19% 135

Table 6: Air conditioning & Ventilation - Recommended Efficient Alternatives

Page 17 of 17
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

6.4 HOT WATER

6.4.1 DESCRIPTION OF EXISTING SYSTEM

Hot water uses an estimated 144,387 kWh/year of energy per year and accounts for 28% of the total
energy use of the Resort. The resort has a range of water heating solutions it uses, including electric
storage, electric boosted solar, gas instantaneous and heat recovery.

Hot Water System Summary

Component of Energy Use Energy Use/yr Op. Costs GHG


(kWh/yr) ($) (Tonnes/yr)
Electric Water Heating 259,624 90,868 212

Table 7: Hot Water - Energy Use - Audit Results

6.4.2 LIMITATIONS OF EXISTING DESIGN


Equipment
• Electric boosted solar water heater and direct electric immersion element based water heaters are
used to provide hot water to a substantial part of the resort staff and guests. Electricity at 35
cents/kWh for diesel compares with 11 cents/kWh makes electricity a very expensive option. In
some instances an electric storage water heater is plumbed in series with the

6.4.3 EFFICIENT ALTERNATIVE DESIGN


1. Install solar water heaters with/or inline gas water heater in situations where direct electric storage
water heaters are used or install inline gas water heater where the solar water heater has electric
boosting.

2. A hot water supply line, in the order of 40mm pipe, with a return pump, would connect into the
existing power station hot water ring main and connect to the maintenance house water heater. A
controller would be installed on the existing hot water return in the maintenance shed to reduce
unneeded hot water recirculation.

Recommended Hot Water System Improvements


Energy Efficiency Initiatives Energy Capital Op. Rate of GHG
Savings/yr ($) Savings Return (Tonnes/yr)
(kWh/yr) ($) (%)
1. Solar with gas instantaneous 96,445 33,756 191,000 18% 79

2. Heat recovery from generator to 20,971 7,340 15,000


supply maintenance managers
49% 17
hot water system

Total 117,417 41,096 206,000 20% 96

Table 8: Hot Water - Recommended Efficient Alternatives

Page 18 of 18
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

6.5 CATERING FACILITIES

6.5.1 DESCRIPTION OF EXISTING SYSTEM


Catering uses an estimated 82,084 kWh/year of energy and accounts for 4.6% of the total electricity
used on site.
Both electrical and LPGas appliances are used for cooking in the main kitchen, although LPGas
predominates. Electric appliances include a 20kW combi steamer, 2 x 3kW belt toasters, 3.6kW Urn,
passthrough, and a 26kW Hobart Rack Conveyor Dishwasher. Gas appliances include a gas oven, a
gas combi steamer oven, deep fryer, hot plates and griller.

Cooking System Summary

Component of Energy Use Energy Use/yr Op. Costs GHG


(kWh/yr) ($) (Tonnes/yr)
Catering 82,084 28,729 67

Table 9: Catering - Energy Use - Audit Results

6.5.2 LIMITATIONS OF EXISTING DESIGN


Due to the cost of electricity relative to LPGas, the use of an electric based catering equiments puts
additional load on the power station, at 3 times the cost per hour of an equivalent gas unit.

6.5.3 EFFICIENT ALTERNATIVE DESIGN


1. Replace electric rack conveyor dishwasher with an equivalent Fajor gas model. The current cost
of running an electric unit on a one-hour basis is $9. Using current pricing, the equivalent gas unit
would cost $2.1 for the same period.

2. Replace electric passthroughts, urn and 3 group coffee machines with an equivalent gas model.
The current cost of running an electric passthrough over one shift is $15. Using current pricing,
the equivalent gas unit would cost $5 for the same period.

3. Replace electric conveyor toasters with sensor controlled conveyor toasters. The current cost of
running the electric units each morning is $6.5. Using current pricing, the equivalent units with
sensor controls would cost $2 for the same period.

Recommended Cooking System Improvements

Energy Efficiency Initiatives Energy Capital Op. Savings Rate of GHG


Savings/yr ($) ($) Return (%) (Tonnes/yr)
(kWh/yr)
1. Gas passthroughs, gas instant
hot water, gas espresso
machines
12,263 26,500 4,292 16% 10
2. Automatic conveyor toasters 3,581 5,000 1,253 25% 3
3. Gas rack conveyor dishwasher 45,370 60,000 15,880 26% 37
Total 82,084 91,500 21,425 23% 50

Table 10: Catering - Recommended Efficient Alternatives

Page 19 of 19
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

6.6 REFRIGERATION FACILITIES

6.6.1 DESCRIPTION OF EXISTING SYSTEM

Refrigeration uses an estimated 292,634 kWh/year of energy per year and accounts for 16.6% of the
total energy used on site. Most of the Resort’s refrigeration capacity is located in the kitchen and
dining area. Equipment includes:
• freezer room (kitchen)
• cool room (kitchen)
• 4 door underbench cooler (kitchen)
• 4 door fridge/freezer ((kitchen)
• ice machine (kitchen)
• 2 door fridge (dining room)
• 2 door underbench fridge (dining room)

Refrigeration System Summary

Component of Energy Use Energy Use/yr Op. Costs GHG


(kWh/yr) ($) (Tonnes/yr)
Refrigeration 292,634 $102,422 239

Table 11: Refrigeration - Energy Use - Audit Results

6.6.2 LIMITATIONS OF EXISTING DESIGN

Equipment

The existing refrigeration requirements appear to meet the current needs of the Resort with reference
to storage volume. The key limitations of the systems are as follows:

 Use of on/off controls is very inefficient relative to newer analogue controls

 Use of multiple small compressors, which are relatively inefficient, compared to a few larger type
refrigerator compressors.

 No redundancy in any one unit compressor, if a unit fails, its system will fail to operate.

The 109 x 100L bar fridges used in the guest rooms are inefficient relative to newer models.

6.6.3 EFFICIENT ALTERNATIVE DESIGN

1. Rationalise the number of small compressors, with efficient larger compressor and establish a
racking system, with a variable speed drive to improve overall performance of the refrigeration
system.

 Install digital controls on the refrigeration system, with each evaporator installed with a digital
TX valve, pressure and temperature monitoring equipment.

2. Install more efficient 100L bar fridges and modify suite cabinets to allow bar fridges to breath and
cool.

Page 20 of 20
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

3. Install a vending machine miser on the staff vending machine.

Recommended Refrigeration Improvements

Energy Efficiency Initiatives Energy Capital Op. Rate of GHG


Savings/yr ($) Savings Return (%) (Tonnes/
(kWh/yr) ($) yr)
1. Bar fridges in family suites 6,578 10,000 2,302 23% 5
replaced with efficient models
2. Bar fridges in non-family suites 20,082 2,000 7,029 351% 16
removed
3. VSD racked compressors with 54,207 89,500 18,972 21% 44
digital controls for kitchen
coldrooms and freezer rooms and
VSD and digital controls for bar
coldroom
4. Staff vending machine energy 241 500 84 17% 0
management
Total 81,107 102,000 28,387 413% 66

Table 12: Refrigeration - Recommended Efficient Alternatives

Page 21 of 21
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

6.7 LAUNDRY FACILITIES

6.7.1 DESCRIPTION OF EXISTING SYSTEM

Laundry facilities (washers and dryers in the laundry) use an estimated 114,619 kWh/year and
account for 22% of the resort’s total energy usage. The electric clothes dryers use a significant
proportion of the resort power generation capacity at the resort, approximately 20%.

Current laundry requirements are being met with the following equipment:
• 3 x Commercial Electric Washer
• 3 x Commercial Dryers
• 1 x Electric Clothes Iron

Laundry System Summary

Component of Energy Use Energy Use/yr Op. Costs GHG


(kWh/yr) ($) (Tonnes/yr)
Laundry (Washers and Dryers) 28,691 $10,041 23.4

Table 13: Laundry - Electricity Use - Audit Results

6.7.2 LIMITATIONS OF EXISTING DESIGN

Equipment

Drying clothes using electricity is very energy inefficient. The dryers operate for up to 14 hours a day.
This constitutes a substantial energy use and power load for the resort.

6.7.3 EFFICIENT ALTERNATIVE DESIGN

1. Replace the guest laundry electric clothes dryers in the guest laundry facilities similar capacity
gas dryers.

Recommended Laundry System Improvements

Energy Efficiency Initiatives Energy Capital Op. Rate of GHG


Savings/yr ($) Savings Return (%) (Tonnes/yr)
(kWh/yr) ($)
1. Replace guest laundry electric 4,030 11,000 1,411 13% 3.3
dryers with gas models.
2. Replace main laundry detergent 12,264 4,000 4,292 107% 10.0
with cold water detergent.

Table 14: Laundry - Efficient Alternatives

6.7.4 UNMET SERVICES

A sheet flattener, which dries and flattens sheets has been purchased.

Page 22 of 22
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

6.8 OTHER SERVICES

6.8.1 DESCRIPTION OF EXISTING SYSTEM

Other energy loads of the Resort include Office Equipment, Appliances (such as dive air compressors,
TVs, audio equipment, etc), Ventilation and Workshop Equipment. The energy use attributed to each
of these services is given in Table 15.

Summary of Other Energy Consuming Services

Component of Energy Use Energy Use/yr Op. Costs GHG


(kWh/yr) ($) (Tonnes/yr)
Office Equipment 3,277 $983 0.8

Appliances 23,236 $6,971 5.8

Workshop Equipment 743 $260 0.6

Table 15: Appliances, Office, Ventilation and Workshop Equipment - Audit Results

6.8.2 EFFICIENT ALTERNATIVE DESIGN

Practices

1. In the short term there are no cost-effective recommendations with respect to the existing
equipment. However, in the longer term it is recommended that energy efficiency be included as
part of the purchase decision when procuring future equipment. For example, photocopiers,
printers, and computers with the Energy Star label have the capacity to 'go to sleep' when not in
use, potentially cutting consumption by around two-thirds.

Recommended Energy Efficiency Purchasing

Energy Efficiency Initiative Energy Capital Op. Savings Rate of GHG


Savings/yr ($) ($) Return (%) (Tonnes/yr)
(kWh/yr)
Include energy efficiency as part 2,185 - $656 - 0.6
of the purchase decision when
procuring future equipment.
Table 16: Appliances, Office and Workshop Equipment- Recommended Efficient Alternatives

Page 23 of 23
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

7 CONCLUSIONS
Heron Island Resort can achieve substantial energy savings from the implementation of energy
efficient technologies and energy management practices. The total energy demand of 1,767 MWh per
annum can be reduced by approximately 832 MWh, bringing the Resorts’ total electricity load down to
965 MWh per annum. This can be seen in Table 24.

HERON ISLAND RESORT


ESTIMATED ENERGY SAVINGS FROM IMPLEMENTING
ENERGY EFFIENCY AND ENERGY MANAGEMENT INITIATIVES
Component of Energy MODELLED EXISTING MODELLED EFFICIENT
Use ENERGY USE ENERGY USE
ENERGY SERVICE Annual Proportion of Annual Proportion of Energy
Energy Use Total Energy Energy Use Total Energy Savings
(kWh/yr) Use (%) (kWh/yr) Use (%) (kWh)
Air Conditioning & 409,806 23.2% 409,806 42.4% 165,855
Ventilation
766 0.0% 766 0.1% -
Workshop Equip.
82,084 4.6% 25,691 2.7% 56,393
Cooking & Catering
279,934 15.8% 101,543 10.5% 178,392
Lighting
28,691 1.6% 12,397 1.3% 16,294
Laundry
292,634 16.6% 214,277 22.2% 78,356
Refrigeration
Office & Entertainment 80,303 4.5% 76,385 7.9% 3,919
Equipment
280,855 15.9% 95,838 9.9% 185,016
Pumping
259,624 14.7% 142,209 14.7% 117,417
Hot Water
52,762 3.0% 52,389 5.4% 372
Miscellaneous
1,767,459 100.0% 965,447 100.0% 802,014
Total
Table 24: Audit Energy Use versus Efficient Energy Use

Modelling of the peak power demand indicates it will be reduced from 460kW to 250kW (refer to
Appendix 3: Peak Power Demand). This reduction in load equates to an annual saving in fuel
consumption of 241,000 litres of diesel valued at $280,000.

Page 24 of 24
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

8 RECOMMENDATIONS

8.1 OVERVIEW

Heron Island Resort has an opportunity to reduce its diesel purchases by nearly $280,000 per annum
through investing an estimated $966,000 in energy efficiency and energy management initiatives
(these savings are based on the Resort’s current occupancy rates). This represents a rate of return on
investment of 29%. In addition, it provides greenhouse gas savings of approximately 620 tonnes per
annum. A summary of the recommendations for implementation of energy efficiency measures is
given in Table 25. It contains the electrical savings achievable by implementing the recommendations.
Please note that the difference between the totals in Table 24 and 25 equates to the increased use of
LPGas, a cheaper, cleaner fuel supply.

8.2 ENERGY EFFICIENCY AND ENERGY MANAGEMENT INITIATIVES

Energy Efficiency and Energy Management Initiatives fall into two categories: technology and
practices. The implementation of the recommended technology initiatives appears easy, but is only the
beginning of an effective Energy Management Program. Without the implementation of best practice
policies and procedures, long term energy savings can be compromised.

All levels of Management and Staff need to feel they have ownership of energy efficiency
management within the Resort. The energy efficiency paradigm needs to be a part of the business
culture. Senior Management needs to demonstrate commitment through their business plans,
reporting and actions, and needs a particular Manager to champion energy efficiency. Other Staff
members need training to raise awareness of how to achieve energy efficient outcomes. Lodge
Guests will require education about energy and water conservation measures.

Throughout the report the implementation of a systemic Energy Management System is


recommended. It could be incorporated into an overall Environmental Management System, or be an
independent system. A monthly reporting system that allows ongoing reporting of energy efficiency or
inefficiency should be implemented.

HERON ISLAND RESORT


ENERGY EFFICIENCY AND ENERGY MANAGEMENT
RECOMMENDED COST EFFECTIVE INITIATIVES

kWh
LIGHTS Saving CapX Opx ROI GHG
16W Led fluro replacements (some
energy management) 58,050 42,000 20,318 48.4% 47.4
6W LED incandescent and CFL
replacements (some energy
management) 17,591 24,000 6,157 25.7% 14.4
10W LED halogen replacement (some
energy management) 102,751 93,671 35,963 38.4% 83.9
Total 178,392 159,671 62,437 39.1% 145.7
kWh
AIR CONDITIONING Saving CapX Opx ROI GHG
Energy management air conditioners 89,375 128,500 31,281 24.3% 73.0
Efficient fans 54,356 166,000 19,024 11.5% 44.4
Energy management on kitchen 22,124 12,500 7,743 61.9% 18.1

Page 25 of 25
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

exhaust
Total 165,855 307,000 58,049 18.9% 135.4
kWh
WATER HEATING Saving CapX Opx ROI GHG
Solar with gas instantaneous 96,445 33,756 191,000 17.7% 78.8
Heat recovery from generator to supply
maintanance managers hot water
system 20,971 7,340 15,000 48.9% 17.1
Total 117,417 41,096 206,000 19.9% 95.9
kWh
CATERING Saving CapX Opx ROI GHG
Gas passthroughs, gas instant hot
water, gas espresso machines 12,263 26,500 4,292 16.2% 10.0
Automatic conveyor toasters 3,581 5,000 1,253 25.1% 2.9
Gas rack conveyor dishwasher 45,370 60,000 15,880 26.5% 37.0
Total 91,500 21,425 23.4% 50.0
kWh
REFRIGERATION Saving CapX Opx ROI GHG
Bar fridges in family suites replaced
with efficient models 6,578 10,000 2,302 23.0% 5.4
Bar fridges in non-family suites
removed 20,082 2,000 7,029 351.4% 16.4
VSD racked compressors with digital
controls for kitchen coldrooms and
freezer rooms and VSD and digital
controls for bar coldroom 54,207 89,500 18,972 21.2% 44.3
Staff vending machine energy
management 241 500 84 16.9% 0.2
Total 81,107 102,000 28,387 412.5% 66.2
kWh
LANUDRY Saving CapX Opx ROI GHG
All guest dryers replaced with gas types 4,030 11,000 1,411 13% 3.3
Use cold/warm water detergents in
laundry 12,264 4,000 4,292 107% 10.0
Total 16,294 15,000 5,703 38% 13.3
*  This  is  the  modelled  electricity  saving  in  kWh.  It  does  not  include  LPGas  usage  as  Table  24  does.  

Table 25: Summary of Recommended Energy Efficiency Initiatives

Page 26 of 26
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

APPENDIX 1 - PROJECT
METHODOLOGY

Stage 1: Audit/Review of Existing Energy Utilisation Technologies

A detailed audit including the installation of energy measuring equipment at the main switchboard and
testing of particular equipment was undertaken to determine:
• The Resort’s total energy load and its power demand pattern
• Individual energy consuming loads throughout the resort
• Energy use patterns of end-use appliances and technologies
• Current maintenance regime and annual operating costs

Particular attention was given to:


• Lighting systems including assessment of current lighting levels and control strategies,
years till end of life and resort/maintenance staff satisfaction
• Climate control/Refrigeration/Ventilation including assessment of current air conditioning,
ventilation and distribution systems. This included assessment of the general condition of
the plant, control strategies, inventory of air conditioning/ventilation/distribution equipment
and resort/maintenance staff satisfaction.
• Water Heating assessment of current insulation and condition.
• Energy Management Practices assessment of current energy management practices.

Stage 2: Audit/Review of Existing Power Generation System

A detailed audit will be undertaken of the power generation system to determine:


• The resort’s total fuel inputs
• Current power generation loading and efficiency
• Current maintenance regime
• Annual operating costs

Stage 3: Analysis and Review

EnSight will provide a summary of design solutions and recommendations that satisfy eco-efficient
principles and:
• Meet established quality service standards
• Meet clients’ investment criteria
• Meet maintenance and building user requirements
• Meet the clients’ Environmental Management System requirements

Modeling of audit and demand management options for the resort was undertaken using EnSight’
proprietary software ECO-EFFICIENT DESIGNSOFTWARE.

Project Deliverables:

Page 27 of 27
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

A comprehensive report outlining energy efficiency measures for implementation are provided. The
report provides a tiered action plan for immediate opportunities and longer-term eco-efficient
opportunities. Topics covered in this report include:
• Power generation
• Renewable energy systems
• Air conditioning
• Lighting
• Water heating
• Passive strategies

Page 28 of 28
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

APPENDIX 2 - LOAD STATISTICS

Page 29 of 29
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

APPENDIX 3 - PEAK POWER DEMAND

Page 30 of 30
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft
Prepared by EnSight  

APPENDIX 4 - LOAD DURATION

Page 31 of 31
Project No: 1087
Energy Services Report – Heron Island Resort
Prepared: 3 March 2010 Revision: Draft

You might also like