You are on page 1of 1
17. The Indian Construction Co. Lid. has undertaken the construction of bridge aver the River Yamuna for a Corporation, The value of the contract is 15,00,000 subject to retention of 20% until ane year after certiled completion of the contract, and final approval of the Corporation's engineer. The following are the details as shown in the books en 30th June, 2020, Materials dire to ste 4.20,000 Materials from stores ‘81,200 Hire and use of plant 12:10 Direct expenses 23,000 General overhead allocated to the cont 37,100 Material on hand on dune 30¢h, 2020 6,300 Wages accrued on sine 30th, 2020 7,800 Digect expenses accrued on June 30th 2020 1600 Work not yet corifed at cost 16,500 ‘Amount certified by the Corporation's engineer 11,00,000 Cash received on account 5}80,000 Prepare (a) Contract Account, b) Contractee's Accaunt, and (3) show how it would appear inthe Balance Shee. Ad & a \ ae va a

You might also like