Professional Documents
Culture Documents
Investigation of Distress of A Reinforced Earth Wall in Hong Kong
Investigation of Distress of A Reinforced Earth Wall in Hong Kong
net/publication/331928831
CITATIONS READS
0 577
6 authors, including:
All content following this page was uploaded by John Boscawen Burland on 21 March 2019.
Forensic Engineering
1 2 3
During an intense rainstorm on 22 May 2013, severe distress occurred at a reinforced earth wall in Hong Kong. The
wall was under construction and nearing completion at the time of the incident. The distress involved the
dislodgement of 78 facing panels, a total soil loss of about 1300 m3 and a disturbed groundmass of some 5500 m3.
The distress occurred at three localised areas along the wall, with the formation of a sinkhole within the backfilled
soil mass, referred to as the backyard of the wall. The incident resulted in significant soil deposition within the
surface drainage system, flooding and debris overspill onto the road carriageway below, and it caused havoc to the
local community. Subsequent to the incident, a detailed investigation was conducted to establish the probable
causes and mechanism of the incident. This paper highlights some salient points of the investigation, the key
findings and the lessons learnt from the incident.
Wall R22 is a 300 m long reinforced earth wall with a curved The localised distress at the interface between bays 4 and 5 involved
alignment on plan, subdivided longitudinally from bays 1a to 22b the dislodgement of 40 panels at the middle and upper tiers, with
127
Forensic Engineering Investigation of distress of a reinforced
Volume 171 Issue FE3 earth wall in Hong Kong
Lo, Cunningham and Burland
Kowloon
842 000 E
The site N
Buried
drainage line
Haul
750 UC
N
ad
Road
Formed C1
Ro
Hong Kong
ul
Ha
Island
Platform
Key plan CP
Drainage
channel CP
ST16
UC
9
4 to
525
Buried
drainage
CP
Bays
Wall R22
UC
675
line ad
oad
Ro
ul
Ha
ul R
821 000 N
Ha
Cascade Shun On Ro
ad
Staircase Culvert 0 10 20 30
m
Shu Anderson
Scale 1:1700
nO
nR Road
oad
Quarry Figure 3. Layout plan of Wall R22
Wall R26
Wall R22
128
Forensic Engineering Investigation of distress of a reinforced
Volume 171 Issue FE3 earth wall in Hong Kong
Lo, Cunningham and Burland
Elevation: mPD
L-shape RC wall
+150
Tier
openings
Top
+145 Peg footing
Fill
500 mm inclined
drainage layer
Upper
+140
Reinforced
500 mm vertical
fill
drainage layer
+135
Geotextile
Lower Middle
Peg footing
+130
500 mm thick base
Dummy panels
drainage layer
+125
Grade III/IV or better rock
Tier
+120
Mass concrete foundation
NTS
0 5 10
m
Scale 1:500
Inclined drainage layer
Vertical drainage layer Fall
A
B3
Sinkhole
B1c B1d B2 B4
B1b B5
B6
B7 Soil loss
B8
B9
Fall
CP B10
Staircase Seepage A
CP
Cascade Debris
deposition
+146·20
145
Lower tier Middle tier Upper tier
140
135
130
129
Forensic Engineering Investigation of distress of a reinforced
Volume 171 Issue FE3 earth wall in Hong Kong
Lo, Cunningham and Burland
130
Forensic Engineering Investigation of distress of a reinforced
Volume 171 Issue FE3 earth wall in Hong Kong
Lo, Cunningham and Burland
distressed zones. The implication of this drainage layer Vertical connecting drainage
Inclined drainage layer
layer
arrangement is further discussed in Section 7.
Base drainage layer 250 mm dia. subsoil drain pipe
131
Forensic Engineering Investigation of distress of a reinforced
Volume 171 Issue FE3 earth wall in Hong Kong
Lo, Cunningham and Burland
Wall R22 until it reached one of four outlet points along the 500 mm, while the localised exposure of the base drainage layer
300 m long wall. At either end of the wall (over bays 1 and 21/ above the bay 4 mass concrete foundation varied from 300 to
22), the base drainage layer directly discharged to a 250 mm dia. 400 mm in thickness. The contamination of the drainage layers with
toe drain located beneath a footpath in front of the wall. At bay 9 finer soil particles was observed in the local exposures of the base
and at bay 15, respectively, 150 and 225 mm dia. subsoil drain drainage layers over bays 4 to 6 and the vertical connecting
pipes were prescribed to divert the water from the base drainage drainage layer at the interface between bays 4 and 5.
layer to the toe drain (Figure 10). Additionally, a row of
weepholes (100 mm dia. at 2·5 m horizontal spacing) were 5.2 Construction of Wall R22
prescribed at the concrete facing panels along the base drainage The wall was generally constructed in accordance with the
layer at bays 5, 6, 12 to 14 and 18a to 19b. engineering design as mentioned above, except that the inclined
and vertical drainage layers at the back of the wall were
Following an incident on 24 July 2012 (see Section 6), additional constructed as a single combined layer between bays 3 and 11 as
100 mm dia. weepholes at the joints of dummy panels were shown in the pre-incident cross-section in Figure 8.
prescribed at bays 5 and 6, and an additional 250 mm dia. half-
perforated subsoil drain pipe embedded subhorizontally at the vertical At the time of the incident, the construction of the reinforced fill
connecting drainage layer at the interface between bays 4 and 5 was portion of the wall between bays 2 and 16 was ongoing. The top
prescribed (Figure 10). This outlet pipe was fed by three subvertical tier of the wall was under construction, with the top surface of
250 mm dia. half-perforated subsoil drain pipes installed at the back the compacted fill at about +146 mPD. The top surface of the
of bays 2 to 6. Underneath the 250 mm dia. subsoil drain outlet pipe compacted fill was slightly graded away from the wall face. The
was a layer of 600 mm thick compacted soil fill. backyard at bays 4–7 of the wall was a topographical low point in
the vicinity, as evidenced by water ponding observed on the day
The provisions of the drainage arrangement of the wall appeared before the incident. No temporary surface drainage was provided
to be on a prescriptive basis. No assessment was found to show at this location. The top end of the drainage layer at the back of
the adequacy of the drainage arrangement of the wall or the Wall R22 was exposed in this area (Figures 8 and 11). This
possible impacts of a large amount of surface water ingress to the allowed any surface water that accumulated at the backyard to
wall through the drainage layers. penetrate inside Wall R22 in the vicinity of the low point.
The investigation identified that the thickness of the drainage layers 5.3 Monitoring of Wall R22
was found to be variable. Photographic records show the drainage A series of movement markers was erected at the top panel of
layers at some locations at the rear of the wall were thicker than each tier along the wall alignment with measurements taken since
250 mm Æ subsoil drain pipe wrapped by geotextile embedded 150 mm Æ subsoil drain
into 500 mm thick drainage layer (at the backyard of RE wall) pipe just behind panel
Elevation: mPD +146·20
Top tier
Reinforced concrete
retaining wall
145 Approximate
level of backfill
Middle tier Upper tier
140
135
130
125
Lower tier
Pipe extends
to B11
150 mm Æ subsoil
120 drain pipe outlet
250 mm Æ subsoil (into catchpit) Catchpit
drain pipe outlet
115 Catchpit
110 Bay ref. Bay 1c Bay 1d Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Bay 8 Bay 9 Bay 10 0 2 4
m
Scale 1:500
Mass concrete
foundation with Top of tier Design flow direction in drainage layer Subsoil drain pipe outlet
dummy panels 500 mm thick drainage 150 mm Æ subsoil drain pipe 100 mm Æ weepholes
layer (original design) (original design)
Grade III/IV or better Base level of peg footing 250 mm Æ subsoil drain pipe 100 mm Æ weepholes
rock resting on compacted fill (July 2012 remedial works) (July 2012 remedial work)
Figure 10. Original and remedial drainage conditions following the 2012 incident
132
Forensic Engineering Investigation of distress of a reinforced
Volume 171 Issue FE3 earth wall in Hong Kong
Lo, Cunningham and Burland
Site records showed that at the time of the 24 July 2012 incident,
there was no temporary drainage in the backyard of bays 4 and 5.
21.05.2013 15:55
Water ponding in this area was observed shortly after the incident,
suggesting that it was a local low point. Similar to the 22 May
Figure 11. Backyard of Wall R22 on 21 May 2013 2013 incident, the upper end of the combined vertical/inclined
drainage layer in the backyard of bays 4 and 5 was exposed. Such
arrangement could allow the significant ingress of surface water
19 July 2012 at typically fortnightly intervals. The maximum into Wall R22 during rainstorms.
movement recorded over the affected bays prior to the incident
was 20 mm vertical settlement at the upper tier of bay 4 and It was probable that ingress of surface water by way of the
18 mm outward horizontal movement at the middle tier of bay 7. exposed drainage layer at the back of the wall was a key
The recorded movements of the affected bays were all within the contributory factor of the distress. Following the 24 July 2012
allowable tolerances. incident, the wall was partially removed from bays 2 to 6 in a
stepped profile down to the level of the collapsed panel and then
Based on available site records, seepage flows issuing from the reconstructed with enhanced internal drainage measures.
wall face were noted since May 2012. Seepage was mainly
observed between bays 1 and 5 as well as bay 9 of the wall. Both 7. Diagnosis of the 22 May 2013 incident
clear and muddy seepages had been noted with varying degrees of At the time of the incident, the rainstorm was intense, with a 1 h
intensity. Most of the seepage was through the joints of the maximum rolling rainfall of 135 mm, which corresponded to a
dummy panels (i.e. at a level at or below the base of the base return period of more than 200 years. It was established that at the
drainage layer). Limited water seepage points were observed at time of the incident, the site drainage provisions at formed
bays 6 and 7. platforms of the project site were not efficient in conveying
Front edges of
adjacent panel sheared
Middle
tier
Dislodged panel
133
Forensic Engineering Investigation of distress of a reinforced
Volume 171 Issue FE3 earth wall in Hong Kong
Lo, Cunningham and Burland
surface runoff off-site, resulting in the overflow of surface water middle tier). The post-incident ground investigation works involving
towards Wall R22. This overflow, together with surface runoff GCO probe tests showed the loosening of the soil beneath the void.
collected at the backyard of Walls R22 and R26, constituted the
primary sources of water reaching the wall on 22 May 2013. The ravelling process which involved slumping of the fill would
induce tensile forces in the reinforcement straps attached to the
In addition, there was no temporary drainage provision at the panels. When the induced tensile forces were large enough to
backyard of bays 4–7 to drain away any surface runoff that would shear off the socket connections at the panel joints, as well as to
have accumulated at this local low point. The exposed drainage overcome any remaining earth pressure of the fill behind the
layer at the back of the reinforced fill body remained unguarded panels, backwards panel dislodgement would occur. The observed
against surface runoff and allowed water ingress at times of damage on the panels at bays 4 and 5, and bays 6 and 7 where the
rainfall over this area. This exposed drainage layer would allow a front part of the panel sockets had been sheared off while the rear
large amount of water to percolate into the base drainage layers of part of the socket generally remained intact, supports this
Wall R22. The water ingress probably exceeded the flow capacity postulated onset mechanism of the panel dislodgement.
of the drainage outlets of Wall R22. As a result, high water
pressures would have built up in the base drainage layers as well The distress would proceed with the displacement or even
as in the vertical connecting drainage layers. dislodgement of the panels above due to the loss of support by
the supporting panels below, which could further promote soil
Figure 9 is a three-dimensional depiction of the arrangement of loss. The postulated progression of the distress mechanism at the
the subsurface drainage layers and tiers between bays 4 and 9. It interface between bays 4 and 5 is summarised in Figure 13 with
can be seen from various sections shown in Figure 9 that the each stage being numbered and described. The distress at the
lowest tier openings are all located above the base drainage interface between bays 6 and 7 appears to be more developed
layers. In particular, at the sections coinciding with the vertical than that between bays 4 and 5, with the formation of a sinkhole
steps in the mass concrete foundations (denoted by an asterisk), at the back – see the post-incident cross-section in Figure 8(b).
the tier openings are almost coincident with the vertical This sinkhole formation could have been due to a larger amount
connecting drainage layers. The thickness of soil cover between of water ingress into the wall or due to the presence of a subsoil
the tier openings and the vertical connecting drainage layers was drain pipe at the latter location, which could help reduce the
very thin (see the sections at Figures 9(b), 9(e) and 9(h) cut along volume of water issuing out of the top of the tier.
the vertical connecting drainage layers). These three locations
were also coincident with the development of the three distress It is probable that the 24 July 2012 incident underwent the same
areas at the interfaces between bays 4 and 5, between bays 6 and distress mechanism as that of the 22 May 2013 incident. The site
7 and between bays 8 and 9. settings at the time are similar with the presence of a low point at the
backyard of the wall and the presence of exposed end of drainage
The overburden pressure exerted by the soil layers at the tier layer at the backyard, together with the distressed location occurring
openings would have been very small. The build-up of high water at the interface with the vertical connecting drainage layer in close
pressures at the underlying drainage layer would have exceeded proximity to a tier opening. There is also the close correlation of the
the overburden pressures resulting in hydraulic uplift of the soil time of the incident with rainfall, as well as the similarity in the
layer and piping at the tier opening. Given the configuration of distress mode (i.e. the backwards dislodgement of panel with soil
the wall, it is also possible that the soil in the vicinity of the tier loss behind the panels and at the backyard). The smaller scale in
openings was subject to a high local stress ratio (shear/effective distress observed in the 24 July 2012 incident would be due to the
vertical stress) and was therefore susceptible to local failure under less intense rainfall at the time of the incident and, hence, lower
a build-up of high water pressure in the vicinity. volumes of water discharging through the tier opening.
It is probable that the large cross-sectional area of the vertical A review of the design records indicates that the provisions of the
connecting drainage layers at a single location meant that much drainage arrangement of the wall appeared to be on a prescriptive
larger upward flows of water could take place above these layers basis for a permanent condition where the drainage layer behind the
than elsewhere above the base drainage layer. Therefore, once the reinforced fill body would be capped by compacted fill at the top.
loss of soil was initiated, the upward flow of water would No assessment was made of the adequacy of the drainage provisions
concentrate at these locations along the tier, causing erosion and of the wall or the likely adverse impacts under the excessive ingress
continued soil loss. This would lead to the formation of voids in the of water into the wall, in particular during construction. The tiered
compacted fill near the tier opening. Such a continuing erosion structure of the wall was not designed to cater for build-up of high
process would allow the upward migration of voids (ravelling) water pressure near the tier openings, and there were no provisions
combined with the slumping of the compacted fill into the to guard against soil loss in the tier opening.
underlying voids. The phenomenon is supported by the void
observed at the top of a tier (i.e. the upper tier) at bays 8 and 9, Upon the review of related design and construction records, there is
together with soil debris deposited on the tier opening below (i.e. the no indication that the distress was caused by any fault in the
134
Forensic Engineering Investigation of distress of a reinforced
Volume 171 Issue FE3 earth wall in Hong Kong
Lo, Cunningham and Burland
Reinforced Reinforced
140 fill
140 fill
Displacement or
135 Slumping of fill
Tension induced Water and 135 dislodgement of panels Water and
induced tension in in reinforcement debris above due to loss of
reinforcement straps debris
130 130 support by the supporting
to displace the panels panels below. Promoted
125 125 further soil loss
120 120
(c) (d)
permanent design or workmanship of the permanent works of Wall Subsequent to the incident, the following technical recommendations
R22. However, the internal detailing involving a vertical connecting were promulgated by the Geotechnical Engineering Office (GEO,
drainage layer adjacent to the step of mass concrete foundation, in 2014).
the vicinity of a tier opening, is vulnerable to piping in the event of
an unintended ingress of a significant amount of water. This is ■ A risk assessment should be carried out for projects involving
precisely what took place in this incident during an intense rainstorm site formation which may be vulnerable to severe rainfall
while the wall was under construction. events causing adverse landslide impacts on the public in case
of uncontrolled overflow of surface water towards slopes,
8. Lessons learnt retaining walls and other features.
The key lessons learnt from the incident are as follows. ■ Temporary drainage plans should be updated in a timely
manner to suit the site conditions during construction.
■ Overwhelming of temporary drainage provisions during site Adequate drainage provisions shall be maintained on site at
formation works in severe rainfall events can lead to the all times, including during the period when the temporary
failure of reinforced fill structures and serious consequences. drainage works are being rerouted or reconstructed in
Due attention should be given during construction to ensuring accordance with any updated temporary drainage plans to suit
adequate temporary drainage provisions and precautionary various stages of construction.
and mitigation measures to discharge the surface water and ■ The integrity and stability of a reinforced fill structure during
subsurface water safely. construction are particularly vulnerable to excessive water
■ The integrity and stability of reinforced fill structures are ingress. Adequate temporary drainage provisions and
vulnerable to excessive ingress of water, and such structures precautionary and mitigation measures should be implemented
require special attention in design and construction control. to prevent excessive water ingress into the reinforced fill
■ The tiered wall arrangement, with tier openings in close structure not allowed for in the design and thereby
proximity to internal drainage layers, proved to be vulnerable overwhelming its drainage capacity, causing distress or
in the event of unintended water ingress. structure instability.
135
Forensic Engineering Investigation of distress of a reinforced
Volume 171 Issue FE3 earth wall in Hong Kong
Lo, Cunningham and Burland
■ The adequacy of the subsurface drainage capacity of a Wall R22. However, the internal detailing involving a vertical
reinforced fill structure should be assessed and regularly connecting drainage layer adjacent to the step of mass concrete
reviewed during construction, taking account of the changing foundation, in the vicinity of a tier opening, is vulnerable to
site topography and temporary drainage provisions. The piping in the event of unintended ingress of a significant amount
design and detailing of the subsurface drainage system of the of water, which took place in this incident during an intense
reinforced fill structure should be robust enough against the rainstorm while the wall was under construction.
build-up of water pressure from unintended ingress of water,
which may cause hydraulic (piping) failure, internal or This incident highlights that overwhelming of temporary drainage
external instability or distress. provisions during site formation works in severe rainstorms can
lead to geotechnical failures and serious consequences. The
9. Conclusions integrity and stability of reinforced fill structures are vulnerable to
The 22 May 2013 incident at Wall R22 was piping related and excessive ingress of water, and such structures require special
initiated during an intense rainstorm. The site surface drainage attention in design and construction control.
provisions at the filled platforms at the time of the incident were not
efficient in conveying surface runoff off-site and were overwhelmed The combined use of a UAV and a large deployment of ground
by the large volume of surface water during the intense rainfall, personnel was essential to gather the post-incident details to
resulting in the overflow of surface water towards Wall R22. The understand and examine the probable causes and mechanisms of
wall was under construction and the backyard at bays 4 to 7 was a the incident. The amalgamation of methods suited the gathering
topographic low point. The temporary site drainage provisions were of information on the macro- and microscales. In particular, the
yet to be constructed at this location. The exposed drainage layer at use of the UAV enabled the rapid gathering of both vantages and
the backyard of Wall R22 in this area was susceptible to the ingress large area coverage that would otherwise be impossible to gain
of surface water. Excessive water ingress through the exposed top due to access and safety standpoints.
end of the drainage layer behind the reinforced fill body probably
generated high water pressure at and in the vicinity of the drainage Acknowledgements
layer near the wall face. The high water pressure would have This paper is published with the permission of the head of the
initiated hydraulic uplift and piping at tier openings. The presence of Geotechnical Engineering Office and the director of Civil
the vertical connecting drainage layers beneath resulted in a large Engineering and Development, Government of the Hong Kong
amount of locally concentrated water flowing through and eroding Special Administrative Region.
the drainage and fill materials within the wall.
REFERENCES
The surface water that reached and accumulated at the exposed FSWJV (Fugro Scott Wilson Joint Venture) (2013) Report on the 22 May
drainage layer during the severe rainstorm was probably the 2013 Distress at a Reinforced Earth Wall at a Construction Site above
principal source of water leading to the distress. The contribution Shun On Road, Sau Mau Ping. FSWJV, Hong Kong, P. R. China.
GEO (Geotechnical Engineering Office) (2014) GEO Technical Guidance
of subsurface water was probably insignificant.
Note No. 40 – Guidelines on Temporary Drainage Provisions and
Precautionary Measures against Severe Rainfall during Site
There is no indication that the distress was caused by any fault in Formation Works and Construction of Reinforced Fill Structures.
the permanent design or workmanship of the permanent works of GEO, Hong Kong, P. R. China.
136
View publication stats