Professional Documents
Culture Documents
Method Statement For Form Work
Method Statement For Form Work
Project Incharge
FABS
Issued by
SRI HITECH INFRA
*TABLE OF CONTENTS
1.PURPOSE
2.SCOPE
3.REFERENCES
4.RESPONSIBILTIES
5.METHODOLOGY
6.HEALTH, SAFETY&ENVIRONMENT
7.QUALITY ASSURANCE & QUALITY CONTROL
SECTION-02: SCOPE
This procedure applies to the installation of formwork and the controls
required during assembly, erection and final positioning of formwork used in
Structural concrete operations.
SECTION-03: REFERENCE
1.Contractor documents/Technical specification.
2.GFC drawings of both structural and architectural.
3.Quality assurance manual
4.Quality system manual
5.Health,Safety Environment plan
SECTION-04: RESPONSIBILTIES
Site Incharge:
- Shall be report to project manager
-Shall be responsible for supervision, control, Implementation and execution
of plans
-Shall also be responsible for supervision of construction activities and
preparation of construction records Develop construction schedules,
procedures and prepare progress and accomplishment reports.
Site Engineers:
-Shall report to Site in charge.
-Shall be responsible for day to day planning of site, Construction activities
and preparation of construction records.
Survey Engineer/Surveyor:
-Shall report to Project Manager
QA/QC Engineer:
-Shall report to Project Manager
-Shall be responsible for overall control of QC
-Supervision of activities and sub-contractors QC activities, implementation
of Quality plan.
Safety Engineer:
-Shall report to Project Manager
-Shall be responsible for overall control of safety system.
-Supervision of activities and sub-contractors
-Safety activities, implementation of safety plan.
.2 After studying the structural drawings, the Project Engineer will plan
for sizes, numbers and type of formwork to be used in consultation with the
Structural Engineer, if required. Depending upon the programme, the
number of repetitions will be decided.
.6 Ensure that the props, shores, waling, bearers, clamps and tie rods are
the right size and at the correct spacings. The Formwork designer shall
check the falsework system with respect to load imposed on it and design
parameters as laid down in the specification.
.10 Tie – rod holes to be made in the formwork shall be neat so that they
can be patched or plugged later on.
.11 Particular attention will be paid to the rigidity and line of stop ends
and joint formers.
.12 Remove all tie-wire clippings and nails, which may stain both the
formwork and the concrete.
.13 Ensure that adequate access and working platforms are in place for
the concreting gang and that toe boards and guardrails are provided.
.16 A prop should not be used if it is bent, creased or, rusted or has a
bent head or base plate, damaged pin etc.
.18 New timber and plywood forms shall be given first coat of the
appropriate release agent 36 hours in advance, then a second coat just
before they are used. Avoid excessive use of release agent as this can cause
staining or retardation of the concrete.
.19 A close watch should be kept on all wedges and fastenings. Make sure
that they do not work loose. Grout loss is an indication that some movement
has occurred.
.20 When unsleeved tie bars are being used, ease them slightly before the
concrete sets, and remove them as soon as it is safe.
iii) Cleaning the face of forms shall start as soon as they have been struck.
v) Paint code numbers on them so that they can be readily identified when
next needed.
SECTION-6 : HEALTH, SAFETY AND ENVIRONMENT
iii) Where lifting is done by the vertical soldiers, check that they are
adequately connected to the walings.
vii) Lighting should be provided in dark hours near the work in site.
ix) Dedicated supervisor and engineer to be deployed for the following works
carried out in the site.
Quality control and assurance shall be strictly followed as per the approved
quality assurance plan and work method statement.
The formwork and the bracket must have sufficient strength, rigidity
and stability. When installing and pouring concrete in concrete forms,
the formwork and its supports should be observed and maintained.
When an abnormal situation occurs, it shall be handled in time
according to the construction technical plan.
The contact surface between the formwork and the concrete should be
smooth and painted with a release agent, but no release agent that
affects the structural properties or hinders the construction of the
decorative works.
The floor structure formwork and the removal of the support shall be
demolished after the floor has reached the specified strength. The
removal of the special formwork shall be subject to the approval of the
project technical person in charge and the supervision of Party A.
For embedded parts fixed on the formwork, the reserved holes shall
not leak slurry, and the annual solid shall be installed, and the
deviation shall comply with the regulations.