You are on page 1of 44

Licensing and Project

Development of
New Nuclear Plants
Licensing & Permitting Task Force
Title: Licensing and Project Development of New Nuclear Plants
Produced by: Licensing & Permitting Task Force of the World Nuclear
Association. The Task Force is jointly sponsored by the World Nuclear
Association’s Cooperation in Reactor Design Evaluation and Licensing
(CORDEL) Working Group and the Nuclear Law and Contracting (NLC)
Working Group.
Produced by: World Nuclear Association
Published: January 2013 / Reprinted August 2015
Report No. 2015/005

Cover image: AREVA

© 2015 World Nuclear Association.


Registered in England and Wales,
company number 01215741

This report reflects the views


of industry experts but does not
necessarily represent those of any
of the World Nuclear Association’s
individual member organizations.
Contents

Executive Summary 1

1. Introduction 3
Methodology3
Scope of the survey 3
Licensing processes around the world – managing variety 3
Different types of new build countries 4
First-of-a-kind, nth-of-a-kind, first-in-a-country 5
Risk management and timeline 5

2. Structures of Licensing and Permitting Systems 7


General overview 7
One-step and multi-step licensing – the differences 8
One-step or multi-step licensing – the preferences 10
Pre-licensing10
Alignment of schedules 11
Duration of licensing steps 11
Nuclear safety requirements in licensing 12
First-of-a-kind and nth-of-a-kind13
Non-nuclear permits 13

3. Technology and Site Selection 14


Site selection 14
Vendor (technology) selection 14

4. Contracting 15
General15
Timing and sequence of contracts; pre-contracting 15
Pricing methodologies and the licensing regime 17

5. Design Development 18
Timing of design development steps 18
Time needed for design development steps 21
Design completion 21

6. Financing 23
Financing mode 23
Financial investment decision 23
Does the licensing regime have an impact on availability of finance? 24
Financing and the regulator 24

7. Involvement of Stakeholders 25
Role of government 25
Participation of the public 26
Role of law courts 27
Other issues 27

8. Procurement, Documentation and Manufacturing Oversight 28


Timing of procurement 28
Managing documentation 28
Long-lead items 29
Component manufacturing oversight 30
9. Support for International Standardization 32
Standards and requirements 32
Licensing33
Qualification of subcontractors and/or quality control of manufacturing 33
Where would standardization have the greatest benefits? 33
Investment in nuclear 34

10. Conclusions 35

Appendix37
Executive Summary

This report is based on the results of a survey of World Nuclear Association


(WNA) members. It explores the relationship between licensing and regulatory
systems on the one hand and important commercial project decisions on the
other. While many documents on licensing procedures exist, the report brings
some new aspects into the international discussion on new nuclear build.

In the introduction, the report identifies different categories of new build countries
and gives an overview of the main commercial project decisions, such as
technology selection, financial investment decision, and contracting or
procurement. These project milestones then constitute the chapters of the report.

The results of the survey and the subsequent discussions among WNA
members give a comprehensive picture of the relationship between licensing
processes and commercial project decisions. This picture is full of variety as
members’ views and experience depend on the regulatory system as well as
the commercial and political environment into which each project is set. For
example, in countries with a competitive market and private project developers,
there is a strong tendency to reduce risk as far as possible before entering into
irreversible commitments. This leads to taking the financial investment decision
(FID) and concluding binding full-scope contracts as late as possible in the
project timeline. Other countries, with state-owned industries and government-
led projects, put less emphasis on these issues.

It is interesting to note that respondents generally felt that predictability


and stability of a regulatory system are more critical to making commercial
decisions than the adherence to any specific regulatory system. Respondents
generally preferred the regulatory system with which they were familiar, and no
consensus emerged on any one system.

Nevertheless, some key conclusions and recommendations can be drawn out


of the survey results. The most important are:
• The licensing system must be predictable and stable. Pre-licensing of a
design or a site is seen as an important feature of a regulatory system,
reducing the risk of licensing and making the outcome of a licensing process
more predictable. The adherence, as far as possible, of all parties to a pre-
agreed timescale is crucial.
• Vendor selection (if applicable) should occur as early in the process as
possible, ideally before the construction licence application.
• Particularly in a market-driven environment, contracting consists of a series
of steps in which the partners gradually enter commitments. Increased
commitment is dependent on the progressive reduction of licensing risk as
the licensing procedure goes forward. In less market-driven environments,
the survey shows that the ‘classic’ approach of concluding an early
engineering-procurement-construction (EPC) contract covering licensing and
construction is still in use. In any case, regulators need to be aware of these
circumstances.
• A reasonable level of design maturity should be reached before applying
for a licence for a first-of-a-kind (FOAK) project – and, by the time of first
concrete, a high proportion of the detailed design should have been
completed. The same goes for first-in-a-country (FIAC) projects – a notion
introduced in this report.

1
• A clear and predictable licensing regime makes financing for nuclear power
plants easier.
• A formally binding positive decision about a nuclear plant project taken
by the government (and possibly parliament) at the outset would remove
political considerations from the licensing process, which could then focus
on safety issues.
• Design documentation and manufacturing documentation needs to be
efficiently and effectively reviewed between all parties involved. Enhanced
international standardization and greater cooperation of regulators may
be a means to reduce some of the difficulties and to make component
manufacturing more predictable.
• On a more general level, international harmonization of safety requirements
and standardization of reactor designs could greatly facilitate licensing.
Particularly in the case of a FIAC project, implementing a standardized
design and using licensing results already obtained in another country would
be much easier than starting from scratch. However, there is still a great deal
of work to do before this can be achieved.

2
1 Introduction

Methodology Ideally, governments would impose


regulatory requirements with a
This report analyzes the results of a
full appreciation of the timing and
survey issued by the World Nuclear
nature of commercial decisions;
Association’s (WNA’s) Licensing
and commercial decisions could be
& Permitting Task Force, which is
made with a complete appreciation
jointly sponsored by the WNA’s
of the timing and nature of regulatory
Cooperation in Reactor Design
requirements.
Evaluation and Licensing (CORDEL)
Working Group and the Nuclear Law
International bodies such as the
and Contracting Working Group.
International Atomic Energy Agency
(IAEA) and the Organisation for
The survey was sent to WNA
Economic Co-operation and
members in December 2011 and the
Development’s (OECD’s) Nuclear
results were discussed in April 2012
Energy Agency (NEA) produce
at a Task Force meeting in Helsinki.
standards, guides and reports on
The Task Force received 15 sets of
recommended nuclear regulatory
responses: ten from utilities, four from
systems and processes. The main
vendors and one from an architect
purpose of the WNA’s Licensing
engineer. In terms of geographical
& Permitting Task Force survey
coverage, eight responses came
was to collect the views of the
from Europe, four from North
nuclear industry on the relationship
America, two from Asia and one
between nuclear licensing processes
from Africa. The regulatory systems
and commercial activities (such
of 10 countries were covered by
as scheduling, procurement,
the respondents: Canada, Czech
contracting, and finance) which
Republic, France, Germany, Japan,
need to be carried out during the
Korea, South Africa, Ukraine, UK
development of new nuclear projects.
and USA. Some respondents
The results of the survey presented
made occasional remarks on other
in this report aim to better define the
countries as well.
gap between these two processes.

The report covers the relationship


between licensing and commercial Licensing processes
issues of new nuclear power plant around the world –
projects. Recommendations are drawn managing variety
from the survey responses given by
The survey answers showed that
individual WNA members as well as the
there is great variety in the regulatory
analysis carried out by the Task Force
structures and the general project
members. It is anticipated that the Task
environment in countries with new
Force will continue its analysis on some
nuclear projects, and commercial
of the topics in this report.
considerations need to be tailored to
those differences. Two main factors
Scope of the survey have been identified. The first is the
As governments develop and project framework and the regulatory
implement or update nuclear and business model adopted in the
regulatory programs in response to country where licensing takes place,
new nuclear projects, their primary for example whether the new build
focus is appropriately on safety and project is driven by the state itself
security requirements. Developers and implemented by state-owned
of new nuclear projects must meet companies or whether the project
these requirements whilst making is conceived and implemented by
important commercial decisions. private industry in a competitive

3
environment. The second factor is resources. As for the countries
whether the reactor is the first-of-a- in category 1, predictability and
kind (FOAK) to be built anywhere stability is important for countries
or the first-in-a-country (FIAC), or in this category, as well as for the
neither. Both factors are addressed in foreign investors who are invited
the following two sections. to participate.
4. Countries with emerging nuclear
Different types of new programs (United Arab Emirates,
build countries Turkey, Poland, Indonesia,
Vietnam). The main concern in
There are many different regulatory
this category – which in itself
and business models but most of
is very wide-ranging – appears
these fit into the following broad
to be an adequate regulatory
categories:
infrastructure. Within this
1. Countries with large mature group, there may be significant
nuclear programs and market- differences in approach, for
driven projects (US, UK, Canada). example the extent to which the
The main concern in this category regulatory system is ‘imported’
is achieving predictability and from the vendor country.
certainty so that investors and
5. Regulatory and commercial
financers can make an investment
aspects of small modular reactors
decision. As the licensing
(SMRs). The main issue here,
system is already established
regardless of whether a project is
in these countries, the focus is
in a mature or emerging market,
on identifying elements of the
is establishing an adequate
system that either hinder or foster
regulatory infrastructure with a
predictability and certainty.
licensing process that is hoped
2. Countries with large nuclear to be less complicated than
programs and state-driven for larger reactors. The unique
projects (China, Russia, Korea, aspects of SMRs in licensing are
India). These countries constitute currently under discussion.
the majority of today’s nuclear
new build projects. Here, Many of the issues covered in the
licensing procedure and risk survey have different relevance
are not as big an issue as in the for different types of new build
first category. It is less clear how countries. For example, in countries
licensing and permitting regimes with market-driven development
can be improved to reduce risk (category 1) some commercial
in these countries, but it does decisions are taken only after
seem likely that they would a thorough assessment of the
benefit from some improvements financial risks involved, including the
in licensing, for example a higher regulatory and licensing risk. In these
degree of international design circumstances, timing is extremely
standardization or of international important. Some financial decisions
cooperation in licensing and may be taken only after the licensing
oversight. process has reached a sufficiently
3. Countries with small mature developed status. In countries with
nuclear programs (Czech state-driven programmes (category
Republic, Slovakia, Bulgaria). 2), commercial decisions tend to be
These programs place a greater taken right at the outset and financial
reliance on external support, risk considerations do not seem to
given the limitation of national play such an important role.

4
The Table in the Appendix indicates regulatory schemes around the
the relevance of the survey items world in order to help with making
(and chapters of this report) to the commercial decisions, the same
different types of new build countries. respondents said this should not be
at the expense of a predictable and
First-of-a-kind, nth-of-a- stable regulatory regime.

kind, first-in-a-country
The survey responses and Task Force
Risk management and
discussion revealed that a major timeline
factor for both regulators and new There is a logical progression of
project developers is whether the necessary commercial decisions that
project under consideration involves correlate to project implementation.
a first-of-a-kind (FOAK) or an nth-of- Evaluating commercial
a-kind (NOAK) reactor design. This considerations of a project against
choice makes a huge difference the impact of licensing processes
for both regulatory and commercial can be accomplished by analyzing
decision-making. For example, the the sequence of commercial
question of the degree of design decisions as steps designed to adapt
maturity and design completion to progressively reduced regulatory
necessary for making both regulatory risk and to advance project goals.
and commercial decisions is a Licensing processes in their turn
primary issue for a FOAK. On the can be evaluated according to their
other hand, only site-specific aspects ability to support the commercial
of a design or enhancements decisions and to afford certainty and
over previous projects need to be predictability to developers.
considered in adopting a NOAK.
As the survey focuses on the
A further factor to be taken into interaction between regulatory
account is whether the design is processes and the industry’s
constructed for the first time in a commercial activities, the topics in the
given country. Such a first-in-a- report are arranged according to this
country (FIAC) project may be a progression of commercial decisions.
FOAK or – more frequently – a NOAK.
However, many of the advantages The first milestone is the decision
of a NOAK may be weakened if the to develop a new nuclear project
design is being built for the first time within a specific legal and regulatory
in a particular country – in this case, framework. A political decision may
if the earlier licensing processes in have been taken, or there may be an
the country (or countries) where the incentive provided by the government,
design has already been built are not to start a particular project.
taken into account, the project may
be closer to a FOAK, at least for the Next, the project owner will have
licensing processes. to select a site and choose a
design. Depending on the particular
The final chapter of the report deals circumstances, one or both of these
with international harmonization and may be pre-defined so a selection
cooperation, which would greatly process might not take place. For
help to maintain the benefits of a example, in some countries state-
NOAK project, even if the design owned utilities might work together
is implemented in other countries. with the national vendor; or sites
While most respondents are in favour might be selected by the government,
of harmonization of the numerous rather than by the project developer.

5
Following site selection and choice regulations, which may involve In all stages of the licensing and
of technology, the contractual considerable redesign. In both cases, implementation process, stakeholder
arrangements must be negotiated. major parts of the detailed design involvement is essential, particularly
These are closely linked to financing may have to be carried out after the the participation of the public. There
issues and there can be some construction licence has been issued. needs to be a strong framework for
remarkable differences. In some The requirements of the regulatory this, ensuring that participation is
projects where there is high certainty authorities in terms of delivery of meaningful but at the same time that
(for example because the project is the design documentation and its issues resolved in an early phase of
defined by government plans and approval process may significantly the regulatory process are not re-
executed by state-owned entities), influence the project time schedule – opened later on.
full-scope contracts will be concluded and a precise licensing plan shared
right at the start. In other instances, by all stakeholders is necessary to Furthermore, enhanced
especially in market-driven scenarios achieve predictability. Besides, the standardization of reactor
with private-owned utilities, contracting ongoing design development will designs and close collaboration
will be more complicated as the have to be covered in the contractual of regulators would help to save
project owners would want to avoid arrangements with the vendor. time and resources, reduce
being fully committed to the project risk and enhance stability and
from the outset. In these cases, In cases where the FID is taken predictability. Newcomer regulators
contracting will be an on-going late, after major stages of design will learn from their peers, and
process with levels of commitment development have been carried international fleets of standardized
increasing as the licensing process out, an elaborate system of designs will be a better basis for
develops and the certainty that the preliminary contracts and limited operation experience feedback
project can be delivered on time and scope agreements will be needed to and for implementation of design
on budget increases. support design development in earlier improvements.
stages. This is a good example of
For similar reasons, the financial the intricate relationship between The structure of this report follows
investment decision (FID) could be the different aspects of project this sequence of project decisions:
taken any time from the very start of the development and their interaction • The commercial decision to start
process up to when the construction with the licensing procedure. within a specific licensing and
licence has been granted. Obviously permitting system.
there is a strong link between During the construction stage (and • Site selection and choice of
contracting and the FID: the final sometimes before), components technology.
contract, involving full commitment, can need to be manufactured. This
• Contractual arrangements.
only be made effective after the FID. involves complicated systems of
quality certification and control and • Design development – level of
In case of FOAK or FIAC projects, the the creation, endorsement and review detail and extent of completion.
design development is also an issue. of documents, with several parties • Financing.
In FOAK cases, the design has to involved (applicant, manufacturer, • Involvement of stakeholders.
be created before and – to a certain subcontractors, regulator, technical
• Procurement, supply chain,
extent which sometimes is not clear support organizations). This needs
documentation.
– during and even after licensing. to be managed by the project
In FIAC cases, the existing design organization and reflected in the • Manufacturing of components.
may have to be adapted to national contractual arrangements. • International standardization.

6
2 Structures of Licensing
and Permitting Systems
The main structures of any given protection) and could be better
licensing and permitting system will coordinated with such reviews.
be taken into account prior to any
commercial decision to start a new Figure 1 shows the major licensing
nuclear project. steps for a new nuclear plant. A one-
step licensing process (such as the
With regard to the relative merits combined construction and operating
of one-step, two-step or multi-step licence in the US) and multi-step
licensing, the survey indicated process (here depicted as a two-step
that commercial developers value process with separate licences for
predictability and certainty in any construction and operation) are given
system over a preference for a as alternatives. The timeline is given
particular system. One-step licensing for illustrative purposes and does not
may offer somewhat more certainty reflect the survey results.
while two-step licensing is seen to
allow for more flexibility. In any case, General overview
it is essential that the process and In the countries covered by survey
decision criteria are well-defined and responses, there are big differences
understood, and that the process in the regulatory systems including
offers enough stability so that the number of licensing steps and the
business decisions are valid for the possibility of pre-licensing.
entire life of the plant.
Looking at the licensing process for
Accordingly, this chapter gives details a particular nuclear power plant, in
on the licensing systems that the seven of the ten countries addressed
survey respondents are familiar with. in the survey there are at least two
These systems are evaluated and licensing steps (e.g. construction
their advantages and drawbacks licence and operating licence), and
analyzed with regard to scheduling, sometimes up to four (e.g. a siting
project development and commercial licence or a commissioning licence
decisions. in addition). One country (UK) has a
one-step licensing process and two
Pre-licensing of a design or a site other countries (US and South Africa)
is seen as an important feature of a offer both options.
regulatory system, reducing the risk of
licensing and making the outcome of There can also be pre-licensing
a licensing process more predictable. steps, where the regulatory authority
The adherence, as far as possible, gives generic approval for a design
of all stakeholders, including the or a site, independently of a particular
regulator, to a pre-agreed timescale is nuclear power plant project.
another crucial element. These steps might be referred
to as certifications, acceptance
Non-nuclear permitting and licensing confirmations or other terms.
adds complexity to the regulatory The important aspect is that in a
process and thus may affect subsequent licensing process for a
commercial decisions. However, it particular nuclear power plant, such
does not appear to conflict with nuclear approvals can be referenced so that
regulatory milestones. A possible the assessment and evaluation does
exception is the environmental review, not have to be done again. There is
which under some systems appears a range of pre-licensing systems in
to partly overlap with nuclear reviews the countries covered in the survey.
(particularly concerning radiation Some countries have a strong, legally

7
defined pre-licensing process (such what was sometimes said by the hold point. In addition, each licence
as the US with the design certification promoters of the one-step licensing.” contains “licence conditions” which
and early site permit processes), must be achieved prior to stated
others do not have one at all, and One-step licensing obviously does milestones as well as programs
some have pre-licensing options that not mean that the regulatory authority which must be established and
do not have the scope or importance ceases its approval activities after implemented prior to operation.
they have in the US. having given the comprehensive
licence. There will be a number of Generally, there seems to be a
One-step and multi- regulatory hold points, formally below distinction between ‘hard’ hold
the level of licences, which in practice points, pre-defined in regulations
step Licensing – the are very important milestones. In the and involving formal consent by the
differences UK, for example, there is only one regulator, and ‘control points’ which
The answers show that the number licence – the nuclear site licence – are not contained in regulations,
of steps in any licensing process but this is rather formal and sets the but proposed by the applicant. If
may be less crucial than expected. framework for a system of regulatory the regulatory authority agrees with
One respondent stated: “We consents at pre-defined milestones. these control points, it makes them
consider that these two alternatives The overall requirement is for mandatory by including them in
are not necessarily antagonistic: for “adequate arrangements” to control the licence. In some countries (e.g.
example the construction licence work related to the construction and UK), the emphasis is on the latter
(authorization decree) in France operation of nuclear plant. In the case approach, with the applicant/licensee
signed by the government represents of the US combined construction controlling activities at agreed
a major step which gives also a good and operating licence (COL), the hold points and the regulator only
degree of confidence regarding the licensee must complete inspections, ‘controlling the controller’.
granting of the operating licence later tests, analysis and acceptance
on.” Another respondent seconded: criteria (ITAAC) that are specified in The same goes in multi-step licensing
“It is certainly not a ‘black and white’ the licence and report completion to – for example the construction
situation and the actual difference is the Nuclear Regulatory Commission licence may contain regulatory
probably much less important than (NRC); this is a major regulatory hold points established for critical
construction or manufacturing items
and incorporated into the project
y1 y2 y3 y4 y5 y6 y7 y8 y9 y10 schedule (Canada).
pre-licensing
design? Altogether, it seems that the number
pre-licensing and sequence of regulatory hold
site?
points is more or less independent of
develop PSAR develop FSAR the number of formal licensing steps.
And, as a vendor noted: “The number
prepare appl. CL application CL OL application OL
of hold points in the procurement
construction operation and manufacturing process has the
or, alternatively
tendency to increase in all countries.”

prepare appl. COL application COL RHP1 RHP2 RHP3 In some countries, there is a choice
construction operation depending on whether the applicant
wants to submit a safety case for
the entire life cycle of the installation
CL: construction licence
or whether it prefers to submit safety
OL: operating licence
cases with limited scope (South
COL: combined construction and operating licence
Africa). Similarly, the US offers
RHP: regulatory hold point (consent, permit, ITAAC....)
the choice of the COL process
PSAR: preliminary safety analysis report
(10 CFR part 52) or the traditional
FSAR: final safety analysis report
two-step process with a separate
construction licence and operating
Figure 1: Major Licensing Steps for a Nuclear Power Plant licence (part 50).

8
Table 1: Pre-licensing and licensing steps in different countries

Pre-licensing Licensing steps

Canada (Licence to prepare site) 1. Licence to prepare site


2. Licence to construct
Pre-Licensing Vendor Design Review: an 3. Licence to operate
optional service provided by the CNSC
(Canadian Nuclear Safety Commission)
when requested by a vendor

Czech 1. Site licence


Republic 2. Construction licence
3. A number of ‘small’ licences for particular commissioning
stages
4. Operating licence

France ASN (Autorité de sûreté nucléaire) 1. Authorization decree for the creation of a basic nuclear
opinion on safety options (review of installation
safety options) 2. Licence for the commissioning of the installation

Germany ‘Pre-statement’ on project aspects (e.g. 1. Construction licence in several steps (the first one being a
design) in the Nuclear Energy Act but type of design approval)
never used 2. Operating licence in several steps

Japan 1. Site selection phase: environmental review


2. Preparation phase for construction: reactor installation
licence, safety examination, construction plan
3. Construction phase: pre-service inspection, operational
safety program
4. Operation phase: periodical inspection, safety inspection

Korea Standard design approval for new design 1. Construction licence


2. Operating licence

South Africa Both options (one-step or multi-step) are available.


Depending on the application, the NNR (National Nuclear
Regulator) could issue the following types of authorizations
for nuclear installations:
a) N uclear installation licence (NIL) to site, construct and
or operate or decontaminate or decommission the
installation
b) Nuclear installation site licence (NISL) for new installations
c) Nuclear authorization to design a nuclear installation
d) N uclear authorization to manufacture components/parts

Ukraine Operator can ask authority to do a safety 1. Construction licence (including commissioning) with
review of a design afterwards a number of regulatory hold points (e.g. first
delivery of nuclear fuel, first criticality, commissioning,
Feasible sites are on a list to be experimental operation phase)
established by government 2. Operating licence

UK GDA (Generic Design Assessment) Nuclear site licence. Establishes hold points/consent points,
typically:
• First nuclear concrete
• First nuclear island construction
• First fuel brought to site
• Start of active commissioning

US Design certification 10 CFR part 52: COL (combined construction and operating
Early site permit licence)

10 CFR part 50:


1. Construction licence
2. Operating licence

9
One-step or multi- who left the question of preference design certification and early site
open, stated that a two-step licence permit. Both documents have a
step licensing – the has higher risk but, on the other certain legal and binding effect
preferences hand, the separation of licensing which stays valid for a certain
When asked about their preference, and construction may result in number of years.
all respondents seemed to be quite simpler project management. In
happy with the system they have – any case, it was identified that it is This is not the case for some
everyone indicated a preference for necessary to make sure that the other pre-licensing processes. In
the one-step or multi-step system existence of several steps does not Canada, the regulator can be asked
they already have in place. lead to uncertainty and issues being to perform a pre-project design
re-opened. The potential drawback review of a new reactor design in
In the view of proponents of a of the two-step system – lack of order to assess compliance with
one-step system, this gives more certainty that an operating licence Canadian regulatory requirements
certainty and reliability. At the time would eventually be issued – needs and identification of any fundamental
the first concrete is poured and the to be balanced by a system that barriers to licensability. However,
main expenses are incurred, the fact ensures a smooth transition from as a survey respondent points out,
that there is no further licence to be construction to operating licence. this is not very formal nor is it legally
As one respondent put it: “The binding and the applicant cannot
applied for gives comfort to project
preference would be an integrated rely on such reviews for licensing
developers. However, this advantage
two-step system which allows for purposes. Similarly, in the UK, the
might not apply to all nuclear power
transition from one licence to another Generic Design Assessment (GDA)
plant projects. One respondent
with minimal risk or regulatory was created by the regulator without
made the point that the advantages
burden.” Finally, as for a one-step legislation. Its aim is to improve
of a single-licence process are
procedure, the benefits of a previous predictability by reviewing potential
more apparent for standardized
generic design approval and of the designs and assess whether they
plant built at several sites, where
deployment of a standardized design will be able to be licensed once
“licensing/design finality after the
were stressed. site-specific factors have been
first unit makes the remainder of the
taken into account. The nuclear
units very predictable,” whereas for
In summary, the survey demonstrated and environmental regulators have
single units and unique technology
that, from a developer’s perspective, “undertaken not to re-review matters
applications, “a two-step process can
it is more important that the process considered in the GDA process
be advantageous as the licensing as long as there are no safety
process can proceed while detailed is understood (predictable) and
stable (certain) rather than whether it significant design changes,” which
design and some construction is is obviously less binding than the
underway.” Another respondent is one-step or multi-step.
US design certification. Similarly,
emphasized that a COL gives more the “review of safety options” done
certainty, “given enough lead time to Pre-licensing by the French regulator ASN is
a project and not a FOAK project.” Generally, pre-licensing of designs or expressly stated by ASN not to be
Finally, one respondent stressed sites is seen by the nuclear industry binding. Nevertheless, in practice
that the one-step licensing approach as an effective means of enhancing the ASN would, in a subsequent
needs a previous generic design predictability. Pre-licensing allows licensing process, not contradict
approval (such as the US design for an important part of licensing to its own “review of safety options”
certification) and the existence of be resolved by the time the licensing statement unless there is a
standardized design. process for a particular nuclear compelling reason to do so.
power plant starts. A confirmation
Proponents of a two- or multi-step statement by the competent authority It also became apparent that the
system stressed the fact that it gives can give potential project developers terminology is not entirely clear and
more flexibility and that it may allow confidence that they can implement that it may be difficult in some cases
for an earlier start of construction. the project. to assign a regulatory statement to
Besides, it was stated that activities the pre-licensing or licensing phase.
and responsibilities of the operator The most clear-cut and well-known Concerning design approval, this
are very different during construction example of generic pre-licensing should be rather straightforward: if a
and operation. One respondent, of designs and site is the US NRC design is approved upon application

10
by the vendor (not the operator) and be beneficial or viable, and whether procedure, the answers varied to a
if it is approved independently of a they thought mandatory deadlines for high degree.
specific site, then this is clearly pre- steps by regulators could be feasible.
licensing. Legally speaking, it is not For a multi-step procedure, nine
a ‘licence’ since it does not authorize In some countries, there is a answers were received, with the
the vendor or anyone else to construct scheduling process between following ranges:
a nuclear power plant of this design. applicant/licensee and regulator, • Preparation of application – 12 to
Nevertheless this is sometimes seen in others not. Most respondents 48 months.
as the first step of the overall licensing make the point that mandatory
• Construction licence process – 12
procedure. To give an example, one deadlines for regulators are not
to 40 months.
respondent from the UK qualified the feasible because the regulator has
UK process as a two-step process, to complete his thorough safety • Operating licence process – 6 to
with the Generic Design Assessment review before granting any licence. 36 months.
and Nuclear Site Licence processes; Deadlines and schedules (to be
whereas the conventional definition extended when justified) may have For a one-step procedure (COL), four
is that the Nuclear Site Licence is a the function, however, to put some answers were received. Here, the
one-step process with GDA as pre- responsibility on the regulator to plan range of answers was as follows:
licensing. The two French respondents his budget, resources and activities • Preparation of application – 12 to
qualified the French process as two- in a manner to make compliance 24 months.
step, with authorization decree (DAC) possible. The practical answer to
• COL (US) – 24 to 60 months,
as the main licence plus the operating these conflicting requirements is
depending on whether the COL is a
permit; however, one respondent accurate anticipation of work by
first or a subsequent one. For the UK
noted that the French regulator ASN all parties (regulator, licensee and
Nuclear Site Licence the timeframe
defines the French system as a three- vendor).
seems to be somewhat less.
step process by including the previous
generic ‘review of safety options’. Keeping to time schedules is stated
This wide range between responses
to be particularly challenging for
might be at least partly due to the
Concerning the approval of a site, FOAK projects. These require
various national regulatory and
the distinction between pre-licensing maximum efforts from all parties
licensing systems in place. For
and licensing may be less apparent involved, concerning both the quality
example, the longest preparation
because normally the owner/operator of submissions and the quality and
times were given by respondents
is applicant in both processes. timeliness of review.
from Germany (48 months) and
However, the difference is that in pre-
Causes for delay can be due to a Ukraine (36 months). This possibly
licensing the site is assessed against
lack of sufficient communication, reflects the fact that there was
an envelope of criteria and not against
underestimation of effort required, an (Germany) or is (Ukraine) no design
the parameters of a specific design.
initial application that lacked quality certification process. There might
A model for this is the US early
or was incomplete, requirements also be a trade-off between the time
site permit. In Canada, the survey
changing during the licensing or taken for preparing the application
answers seem to suggest that the
construction process, political and the actual licensing process.
licence to prepare a site can be done
changes, reactions of the public In Germany and the Ukraine, the
according to design-independent
(contested hearings, appeals against duration of the licensing processes
criteria, which would qualify it as pre-
licences), delays in regulatory as indicated by the respondents is
licensing. In the Czech Republic, the
assessment of the applicant’s safety somewhat below average.
site licence is the first step of the legal
licensing procedure for any particular case, and limited resources of the
regulator for multiple projects. The range probably also reflects
nuclear plant.
the different situations that the
respondents had in mind, whether
Alignment of schedules Duration of licensing they dealt with FOAK and/or FIAC
The WNA members were asked steps reactor construction or with NOAK
whether in their view a formal When asked about the time reactor construction; the latter
integrated schedule – agreed in needed for preparation of a licence situation would obviously involve a
advance with the regulators – would application and for the licensing reduction in licensing times.

11
As some respondents pointed out, it has the responsibility of defining
is difficult to make a clear distinction his “owner’s requirements” in the
between preparation time and contract with the vendor (Canada).
licensing time. Both will overlap:
preparation of documents and their Again, the importance of good
regulatory review go simultaneously. upfront communication with the
Therefore, the overall time period regulator is stressed in order to
may amount to less than the sum of minimize differing interpretations of
preparation and licensing phases requirements.
indicated by respondents.
Comparing the three groups
A final aspect may be the tendency to of requirements addressed by
reduce risk as far as possible before this question (design safety
starting construction, which may requirements, site requirements
result in project developers investing and requirements on the applicant),
more time in preparing and handling it seems that the last group
the licensing process. (requirements on the applicant)
is most susceptible to unclear
In any case, the fact remains that regulations. Part of this issue
there are significant differences in the is that ‘soft’ requirements like
answers which cannot be explained safety culture cannot be defined
merely by a different depth and in great detail and are open to
length of safety review. interpretation. A similar issue is
the requirement on the licensee to
Nuclear safety be an ‘intelligent customer’ and to
requirements in licensing retain a sufficient level of design
expertise (‘design authority’). Such
This question is aimed at whether
a lack of clear requirements is not
respondents were satisfied that they
had sufficient certainty concerning seen as a big problem but one
regulatory expectations and respondent proposed some work on
requirements and knew what was international standards (which may
expected of them. question whether existing IAEA and
INSAG1 documents are known well
The answers show that some enough or whether they indeed need
regulatory systems are more to be revised).
detailed and prescriptive than
others but generally respondents One respondent noted that in his
claimed to be able to cope with view it is not beneficial to prepare
their systems. For example, the ‘sophisticated’ regulations (in
UK guidance, which is well known the sense of detail). He instead
for its non-prescriptive, goal- proposed working on a common
setting approach, was described understanding of requirements by
as “providing adequate guidance regulators and industry and common
without being prescriptive.” evaluation of design prior to the
licensing process.
Some countries have only high-
level requirements. On the design Even if requirements are clear and well
safety level, there may be room understood, there may be arguments
1
International Nuclear Safety Group, a group for applying requirements from the about practical implementation.
of experts convened under the auspices
country of origin of the chosen design One respondent noted that the best
of the IAEA which issues highly relevant
recommendations and opinions. See http:// (South Africa). Some respondents solution is a NOAK project with a clear
www-ns.iaea.org/committees/insag.asp emphasized the fact that the licensee reference project.

12
First-of-a-kind and nth-of- between the nuclear licence and
any particular non-nuclear permit;
a-kind however, the different licensing
Almost all respondents who have had and permitting schemes can be
experience with a series of nuclear complicated and confusing. Some
plants confirm that the schedule of the respondents hint at difficulties in
following units (“nth” units) is shorter the radiological impact assessment
than that of the first one. A country with which may be treated both in
significant experience in this respect is the nuclear licensing and the
France. In the US, the concepts of ‘lead environmental permitting processes.
plants’ and ‘one issue, one review’ help
to generally shorten time schedules for Sometimes non-nuclear permits
all subsequent plants. may be subject to special political
interference or to appeals and
Some respondents, however, caution can therefore bring an element of
that site-specific aspects should uncertainty into the entire project.
not be neglected and may limit the
shortening of the time schedule. Considering the parallel handling of
nuclear licensing and non-nuclear
Non-nuclear permits permitting processes, effective
There are a number of key non- coordination of authorities seems
nuclear permits required for nuclear essential to avoid any omissions or
projects, and the survey attempted undue duplication. In the regulatory
to identify those most important systems covered by the survey,
to commercial considerations. there appears to be no issue with
From the various answers given, coordination amongst authorities.
environmental permits emerge as Sometimes there is a lead authority,
the most relevant (for example, US for example the US NRC. The NRC
Section 404 Clean Water Act permit). Environmental Impact Statement
In addition, there are planning/zoning includes a list of permits that either
permits, construction authorizations have been obtained or must be
applicable to any large infrastructure obtained prior to certain activities
project, grid connection permits, for a nuclear power plant project.
and so on. At some stages, the Sometimes the nuclear licence
applicant must demonstrate/obtain can only be granted if all other
the necessary rights and titles, requirements have been met by the
for example the public domain applicant. This sometimes simplifies
concession (France). the procedure (Germany) but it can
also be a problem for the nuclear
The majority of respondents agree regulator. In Canada, for example, a
that some of the non-nuclear permits site operation licence requires that all
are time critical for the project. Most laws of the land (municipal, provincial
also agree that some non-nuclear and federal) must be complied with
permits should be in place before in addition to the laws and regulatory
the FID is taken. One respondent requirements for nuclear power. The
noted the practice in his country that potential issue is to determine how
the availability of certain key permits the regulator ensures that those laws
must be confirmed before the FID. (of the land) are addressed and met.
The actual delivery of these permits Problems such as these underline
will take place afterwards. the importance of clearly defining
the competencies and duties of all
In general, there does not appear to authorities involved in the licensing
be any contradiction or duplication and permitting processes.

13
3 Technology and Site
Selection
After an initial decision to proceed, early as possible. At the latest, the
two early commercial considerations vendor should be chosen before the
are site selection and choice of actual licence application is made.
technology. The role each commercial Indeed, a licence application must be
decision plays in the licensing process based on a specific design and many
varies widely among jurisdictions. In issues in the licensing process depend
market-driven systems, site selection on the technology chosen for the
and choice of technology are key project. One respondent also pointed
commercial decisions that form the out that the owner must establish his
basis for entering the licensing process. ‘intelligent customer’ capability early
on, and be able to demonstrate this
Concerning technology selection, to the regulator during the licensing
the survey responses emphasize the process. Some answers seem to
need to make a choice as early in the suggest that it is theoretically possible
process as possible, ideally before to go into licence application with
the licence application. several designs but this would lead
to substantial additional costs. These
costs would be particularly high in a
Site selection non-prescriptive licensing regime (UK).
Site selection decisions must be made
particularly early in a free-market Some respondents commented on
system where the developer (as distinct the relationship between a design
from the government) chooses the certification/approval process and
site, because much of the necessary vendor selection. If the applicant
site-specific information requires years has the choice between several
to develop (for example, information pre-approved designs, it seems this
on site-specific hydrology, seismology, can slightly prolong the time window
meteorology). For this reason, some in which the applicant can keep the
countries, such as the US, have choice open, because it can refer to
created an early site permit process the existing approvals/certifications.
to enable a developer to bank a site
for potential future use. This enables a In other countries, it is the reverse:
critical regulatory decision to be made the regulator will not make a design
in advance of a significant FID. assessment and certification until
a design has been chosen by the
In some countries, such as the applicant (Ukraine).
UK, site selection is an initial
governmental decision reached in One respondent suggested that
advance of a commercial project. political influences may delay
technology selection, leading to the
Vendor (technology) problem that some project workstreams
would have to go on without this
selection selection. On the other hand, it may be
Some respondents indicated disadvantageous for the vendor to be
they had not carried out a vendor selected very early, if the first licensing
selection process, obviously because steps (for example the Environmental
the technology was pre-determined Impact Assessment) take very long and
from the beginning of the project. the contract is more or less idle during
In some countries (Russia, France, this time. However, this may be taken
Korea), choice of technology is care of by contractual clauses.
linked more to national policy than
commercial considerations. One respondent makes the point
that the necessity of early choice
Those respondents that did carry out a of vendor applies only to the NSSS
vendor selection process unanimously vendor. For other contracts, the
recommended that this be done as choice may be made later.

14
4 Contracting

As soon as the technology/vendor is the responsibility more to the


chosen, contracts need to be signed. owner and its architect engineer.
Over the last few years, a system As is also pointed out, regulations
of contractual steps has become put a minimum responsibility on
more preferred to single contracts. the licensee (‘intelligent licensee’,
Particularly in a market-driven ‘informed customer’, ‘design
environment, contracting now consists authority’) which cannot be delegated
of a step-by-step process in which the to the vendor, even in a turnkey
partners enter into commitments at arrangement. However, new ways
each step, as risk gradually reduces in of sharing design responsibility
line with the progress of the licensing between operators and vendors
procedure. In less market-driven may be needed (as investigated by
environments, the survey shows that the Design Change Management
the ‘classic’ approach of concluding Task Force of the World Nuclear
an early full-scope engineering- Association’s Cooperation in Reactor
procurement-construction (EPC) Design Evaluation and Licensing
contract covering licensing and Working Group)2.
construction, is still in use.
Generally, fit-for-purpose contractual
The Task Force initially considered arrangements help define roles and
– but later rejected – the merits of responsibilities and make the licensing
developing ‘standardized’ contracts process more efficient. Naturally,
similar to the concept of standardized licensing milestones and steps have
plants. The survey results confirm to be taken into account in developing
it is not practical to develop such the contractual arrangements. For
contracts due to the large range example, one respondent noted
of factors driving commercial that contracts of main components
considerations in specific projects. are concluded after the regulator’s
acceptance of the safety inspections
and that this acceptance is the
General condition for finalizing the plant’s
As is well known, there is a variety specifications. Another respondent
of implementation models used for made the point that a lack of
nuclear power plant projects, the main pre-defined and ‘prescriptive’
types being turnkey, split package requirements in the regulations of his
and multiple package contracts. The country made it impossible to include
survey results show that there is no plant specifications in the contractual
strict interrelation between the overall model at an early stage.
licensing approach of a country and
the implementation model/contractual Timing and sequence
approach. No respondent stated that
any particular implementation model
of contracts;
could not be used with a certain pre-contracting
licensing system. In most projects, the contractual
situation evolves to some extent as
At the same time, respondents the project unfolds. Initial contractual
2
make the point that the contractual arrangements need to be in place for
Design Change Management in
Regulation of Nuclear Fleets, WNA
arrangements do have an impact the licence application, as this is not
Cooperation in Reactor Design Evaluation on the way the licensing process is possible without the support of the
and Licensing Working Group (July implemented. For example, a turnkey vendor. On the other hand, at this point
2012), http://www.world-nuclear.org/
contract puts more responsibility in many projects the FID has not yet
uploadedFiles/org/reference/pdf/
CORDEL_Design_Change_Management_ in the licensing process on the been taken (often it will occur once the
Report.pdf vendor. A multi-lot contract shifts construction licence or COL has been

15
issued) so – according to the majority on milestones being reached. For
of respondents – it is not feasible to example, one respondent identified
commit to full project implementation. in the contract a limited work
Generally, the approach in these cases authorization (LWA) phase and final
seems to be to commit to contractual notice to proceed (FNTP) phase. If
obligations stepwise, as the risks the LWA phase does not result in a
connected to each step become construction licence, the FNTP phase
understood and controlled. will not be released.

Such an approach may lead to According to the respondents, the


a decoupling of the licensing pre-contracts aim to:
phase from the actual construction • Enable the submission of the
phase, which seems to be a major licence application.
development over the past years. To
• Achieve cost and schedule
try to eliminate, or at least mitigate,
certainty for design and
the risk of the regulator taking de
construction.
facto control of the construction
schedule, several project promoters • Define the customer’s
have concluded that the only remedy specifications and to adapt the
is to change the way the main phases design accordingly (e.g. to the
of the project are sequenced. specific site conditions).

Thus a two-stage reactor contracting In some cases, the government


scheme is emerging. The first-stage is involved and imposes some
contract will cover engineering and prerequisites on the pre-contract (US).
preparation works and will include
the bulk of the licensing work. The In this system of entering stepwise
real construction would be covered into contractual obligations, some
by a separate contract. This new respondents suggest that large
approach results in a lengthening the components (long-lead items)
overall time schedule between the may be a difficulty because they
start of the first phase of the project may have to be ordered before
up to commercial operation. It might the licence is issued. However,
well be that under some regulatory no generic solutions for this are
environments this way of proceeding suggested. One respondent makes
is the only realistic method for the general statement that “the
controlling the regulatory risk. safety-related equipment contracts
can be placed when the risk of
Following this approach, a number change through the licensing
of respondents split the contractual process is understood.”
approach into a pre-contract with
limited scope, focussing on licence In contrast, some respondents
application, and a final contract seem to take a generally different
which is concluded after the licence approach, suggesting that final
has been issued and the FID has contractual arrangements are taken
been taken. The pre-contract might at the outset of the project. As with
be referred to as an ‘early works the early FID (see above) this model
agreement’ or ‘early contractor seems to be feasible for projects
involvement’. The same situation is with state ownership or strong state
reached by another model where management. For example, in the
one contract is concluded before the Ukraine the contracts are signed
licence application, but with several after Parliament has taken the
parts, the later ones conditional decision to implement the project.

16
In line with this, there were different some respondents chose not to
views about whether the desire to give any answer. However, most
control project risks leads to early respondents did answer and gave
or late conclusion of final contracts. some generic views.
The answers seem to depend on
slightly different notions of risk. Some respondents indicated
Some respondents feel that licensing there is a connection between
risks could be better managed the licensing system and pricing
if binding and comprehensive methodologies: to the extent the
contractual arrangements were licensing system provides for certainty
concluded early on, as this forms a and predictability, it becomes
firm framework in which all parties easier to make lump sum pricing
know what is required through the arrangements. Quite naturally, in
entire project. Those respondents this group of respondents there are
active in a competitive commercial differing views between operators and
environment (such as the UK) focus vendors. Operators seem to prefer
on their own risk of entering into lump sum arrangements even more
costly financial commitments at a when licensing is uncertain, in order
time when it is not yet entirely clear to transfer as much risk as possible
whether the project will succeed. to the vendor, whereas vendors would
Consequently, those respondents prefer reimbursable models.
agreed that the final contract should
be concluded as late as possible, Other respondents stated bluntly
with pre-contracts with limited scope that there is no connection
filling the gap in between. whatsoever between the licensing
system and pricing methodologies.
Concerning pre-licensing activities Instead, one respondent suggested
(design certification), this is not that options for pricing methodology
automatically part of a contracting may rather be predetermined by the
scheme for a particular project legal regime of public tender than by
since it is a generic exercise and in the licensing regime.
most cases the vendors, and not
the future operators, are the project Generally, any uncertainty in the
owners. It would seem to depend licensing process will have to be dealt
on the situation whether there is with in the pricing arrangements.
a direct contractual relationship The same respondent suggested
with a future applicant/licensee that contractual clauses are based
(‘sponsor’) at this stage or not. In on current licensing requirements;
some countries there might be a in case any new requirements are
co-application from the vendor and established by legislation after the
an architect engineer (e.g. in the contract is signed (which could lead
UK). In France the regulator would to design modification of the plant),
normally respond to the application there would have to be arrangements
of the licensee but it is also willing about who bears the additional cost.
to review the direct application of a
vendor (an example for this is the Some answers also made clear that
ATMEA1 safety review). pricing methodologies may evolve
and change as the project unfolds.
Some pricing methodologies require
Pricing methodologies
a minimum level of certainty and may,
and the licensing regime for example, only be the preferred
As the aspect of pricing methodologies option when the design is completed
is somewhat commercially sensitive, or when the licence has been issued.

17
5 Design Development

Throughout the course of the that some maturity of design is


project, the design undergoes beneficial or even necessary for
some specific steps: basic design, licensing and that a certain degree
detailed design and procurement of completion of the detailed design
specifications (the latter can be should be reached at the time of
more or less included in the detailed first concrete, the percentages
design). All this applies to a full of design completion actually
extent only to a FOAK project – or, suggested vary considerably.
to some extent, to a FIAC project,
namely when the design has to Timing of design
be adapted to specific national
regulations and some redesigning is development steps
necessary. For a NOAK project or for Respondents were asked to give
a FIAC project where the regulatory their views on the timing of the
system allows for an ‘international’ three design development steps –
design to be taken over without basic design, detailed design and
national safety requirements component specifications – in relation
necessitating major redesigning, the to licensing milestones (application
design may be ready from the start. and construction licence) and the
main contract (e.g. an EPC contract).
Two main questions arise. One is the
timing of the design development Respondents were not provided
steps and their relationship to with a definition of basic design or
licensing phases and to contractual detailed design. The responses
arrangements (EPC contract). Here, reflected their own definition or
the survey again gives a range of practice, which might partly explain
solutions which largely depend on the variations in responses.
the given regulatory system and
commercial environment. Four respondents indicated the
order (with some slight differences)
The other question is closely given in Figure 2.1. According to
connected to the first: a crucial these respondents, the design
issue for FOAK projects is to must be essentially finished at the
what extent the design needs time of the licence application. The
to be developed at the time the EPC contract comes much later,
construction licence or COL is after granting of the construction or
issued. While there is a consensus combined licence.

Timeline 

basic design

detailed design,
component specs

CL/COL CL/COL
application issued

EPC contract

Figure 2.1: Timeline of design development steps, variant 1

18
Timeline  Four other respondents had a similar
order of design development steps
as related to licensing, but placed
basic design
the EPC contract at the outset of the
procedure instead of after the licence
detailed design,
has been issued (see Figure 2.2).
component specs
The issue of timing of the EPC
CL/COL CL/COL contract – whether it is right at the
application issued start or as late as possible, only after
the construction licence/COL has
EPC contract been issued – is covered in Chapter
4. The sequence shown in Figure 2.2
reflects the traditional way to handle
Figure 2.2: Timeline of design development steps, variant 2 construction of nuclear plants for
which an owner-architect engineer or
a vendor would take the responsibility
from the onset of the project up to the
end through a full turnkey contract.
However, as explained earlier, the
present trend at least in market-
Timeline 
driven environments is to shift the
final investment decision to a later
basic design time of the project when key licensing
milestones have been reached.
detailed component
design specs Two respondents had the order of
events shown in Figure 2.3, which
CL/COL CL/COL deviates from the one shown in Figure
application issued 2.2 only by giving a distinct place
to the preparation of component
specifications, which takes place after
EPC contract
the licence is issued.

Figure 2.3: Timeline of design development steps, variant 3 Two respondents gave an order
of events where the detailed
design would come only after the
construction licence has been issued.
The respondents, however, had
differing views on the timing of the
EPC contract (see Figure 2.4).
Timeline 

detailed component
basic design
design specs

CL/COL CL/COL
application issued

2 different responses
EPC contract concerning timing of contract EPC contract

Figure 2.4: Timeline of design development steps, variant 4

19
Finally, one respondent took the view Timeline 
that component specifications should
be prepared before the detailed component detailed
basic design
design is finished (see Figure 2.5). specs design

This respondent added: “It is CL/COL CL/COL


possible to finalize the long lead application issued
item equipment specifications as
soon as the key structural integrity
questions have been resolved with EPC contract
the regulator.”
Figure 2.5: Timeline of design development steps, variant 5
Looking at the large variety of
answers, once again it seems
difficult to draw conclusions
because the respondents had
different project organization
schemes and different regulatory
conditions, and they may have
also had different notions of basic
design and detailed design.

Table 2: Duration of design development steps as indicated by Survey respondents

Basic design Detailed design Component specifications


2 years 5 years Typically around 2 years (during the first
phase of the detailed design)
5 to 10 years (from scratch) 3 years 3 years
Several months (modification of Several months to years Several months to years
standard design)
1 to 2 years depending on design ~ 3 years ~ 3 years
(which could be preceded by a pre-
project design phase)
For a nuclear plant where the basic Around 2 to 3 years Perhaps 1 year; can be done
design is ready (as technology) simultaneously with detailed design
2 to 3 years 2 to 3 years Included in detailed design
5 to 7 years depending upon the 2 to 4 years 1 to 2 years
licensing process
3 years 3 years 2 years
12 to 18 months 22 months 22 months
There is a 1-year period after design 2 years following the basic design, It is possible to finalize the long lead
approval where the basic design but in parallel with the preliminary item equipment specifications as soon
is updated with site specific and works and early construction as the key structural integrity questions
owner’s requirements have been resolved with the regulator
Several years Several years Several years. Detailed design and
component specifications together:
More than 4 years in total

20
The situation is of course depends to be that these tend to overlap with Some respondents say it is difficult to
very much on whether it is a FOAK, the detailed design phase. Some reconcile the aim of design maturity
FIAC or NOAK design. Nevertheless respondents expressly indicated at the time of licensing with other
in all cases the trend is the same. that component specifications are aspects. One is the fact that, in many
The design completion ratio is a key included in the duration given for cases, the FID and conclusion of
factor to facilitate the licensing. Quite detailed design. Other respondents final contracts take place only after
obviously, it is much easier to meet may have been of the same opinion approval of the construction licence.
a high completion ratio for a NOAK without expressly stating it, especially For the optimal design maturity,
design than for the other cases. For those who gave the same duration it would be necessary to contract
a NOAK construction project it even to component specifications as to much earlier with the engineering
seems possible, while keeping risk at detailed design. companies. Another respondent
a low level, to place the EPC contract wrote that the licence should be
upstream of all the other phases. obtained as early as possible to
Design completion
ensure public acceptance before
The most complicated case is the The issue of how far a design should substantive financial decisions are
FOAK/FIAC construction for which be completed before application for, made. A US respondent made the
staggered development phases with or granting of, a construction licence point that US applicants have an
most of the design work performed or COL is rather specific to FOAK interest to obtain the licence rather
in advance of the construction is the and, to some degree, FIAC projects. early in order to secure financing,
most recommendable sequence. gain political support and ease
Clearly, some respondents had One respondent argued that this public controversies. According
this situation in mind when they is a clear advantage of the NOAK to this respondent, completion
answered. projects when they are possible. of detailed design after licence
Generally, an investor should have a approval is possible.
natural wish to develop a consistent
Time needed for design fleet of reactors whenever possible. Several respondents suggested that
development steps not only is the percentage of design
Concerning the length of time needed The same respondent stated completion important, but also what
for the different steps, the responses that for FOAK or FIAC projects is covered by this percentage. As
were given as shown in Table 2. the licensing plan needs to be one respondent stated: “The amount
defined and agreed between the of detailed design for licensing is
Concerning the basic design, once stakeholders concerned. Different weighted to systems/components
again a large variety of answers was scenarios for the licensing and with the most significant impact on
received. Some respondents did the design completion can be safety for the particular design.”
not give any duration for the basic envisaged in this case. The safest
design at all as the basic design solution for all parties is to achieve Some respondents mention the role
was obviously supposed to be in a large part of the detailed design of the Preliminary Safety Analysis
existence and offered by the vendor before licensing; however for Report (PSAR). This is a prerequisite
as soon as the project starts. Others obvious reasons it is also the for the construction licence and
seem to have taken into account only solution which will lead to the cannot be obtained without the
the time needed to adapt a pre- longest overall schedule. Finding design having reached a certain
existing basic design to the project. the right balance to suit all parties is degree of maturity.
Others clearly had in mind the entire a matter of compromise.
process of basic design, starting Some respondents emphasized
from scratch. All respondents agreed that the benefits of having completed
design maturity is highly important the design certification process
Concerning the detailed design, a and beneficial for licensing and before actual licensing starts. One
qualitative analysis gives the majority construction, and that a relatively respondent from the UK stated that
of responses ranging from around 2 high degree of completion of the the generic design approval accounts
to 3 years. detailed design should be reached at for about 80% of the detailed
the time of first concrete. On the other design even before any site-specific
Concerning component hand, there may be advantages of aspects have been introduced. This
specifications, the problem seems obtaining an ‘early’ licence. greatly helps in licensing as well as

21
contractual negotiations with the • CL or COL can be obtained should already be made. The
vendor. Other respondents from the with about 30 % of the design respondent acknowledged this is
UK made similar statements. completed. difficult to reach and theoretically
• 40% of detailed design complete at results in a longer schedule.
UK respondents also made the first concrete (however, difficult to
point that the UK Nuclear Site achieve in practice). A basic issue concerns the level
Licence is not fixed to a stage in of design completion the regulator
• An estimate of completeness
the design process and therefore requires before allowing the start
would be 60-70% complete before
does not suppose a specific degree for ‘irreversible’ construction or
issuance of construction licence.
of design completion. It is more manufacturing activities. One
of a formal step that establishes • 70% would be ideal (but it is respondent explained that this has to
the 36 standard licence conditions important which 70%). be addressed and agreed between all
and defines hold points for future • Suggest 70%. parties before the contract is signed.
regulatory consents where the • The basic design should be better The list of required documentation for
actual evaluation process will take than 90% complete at the point of full design completion, the required
place. This is obviously different in licence award. timing for, and licensing significance
other countries, where the licence of, each document, as well as the
• For first concrete, a detailed design
supposes a safety evaluation which procurement time schedule must be
maturity of approximately 95%
requires a certain degree of design part of the contractual arrangements.
needs to be achieved.
information to be available. The respondent also stressed that the
• Ideally, the design should be 100% overall schedule should be reviewed
complete prior to the submission by the regulator upfront and that the
Some respondents stated that a
of the construction licence regulator should, to some extent,
multi-step approach gives more
application, but it may not be commit to this.
flexibility in that the detailed design
practically possible.
can continue after the construction
licence has been issued and • Detailed design completion (100%) In addition to the reasons given
construction is underway. (and safety analysis report) is above, there may be other
necessary for the construction explanations for the wide spread
Given the very sophisticated scope licence to be issued. of answers. Some respondents
of answers balancing the benefits give a percentage of basic design,
of licensing a (largely) completed There seem to be three groups of some of detailed design, some
design against the benefits of earlier opinions: one requires about one-third just of ‘design’ completion – all of
licensing, it is not surprising that the of the design to be completed, the which might lead to different results.
respondents differed considerably second about two-thirds, and the last Furthermore, respondents are
in their estimates of the degree full or near-full completion of design used to different licensing systems
before the relevant licence is issued. and might also have different
of design completion needed for
All three groups seem to be fairly understandings for what is meant by
a construction licence/COL. The
balanced in terms of respondents. ‘design completion’.
responses, arranged in order of
magnitude of design completion, are
One respondent said that figures Concerning the detailed design,
as follows:
are not very meaningful. Instead, it is important to find ways to
• The basic design completion he argued that the detailed design progressively freeze the detailed
required to support design for almost all the civil works should design through milestones that are
approval/certifications is be available. This means that main agreed in advance with the regulator
approximately 10-15%. piping routing is defined and therefore – who should commit to not review
• 30% design completion for CL. the choice of the main components the design again.

22
6 Financing

The main issue in this section is the licensing the FID is taken and what
timing of the financial investment prerequisites need to be in place.
decision (FID) and its relationship
to the main licensing steps. The The responses show that the main
situation is similar to contracting decision to be taken by a project
(and indeed both aspects are developer is whether the FID
strongly linked, as the main EPC should be taken before or after
contract supposes that the FID the construction licence. As one
has been taken and the project respondent noted, this depends on
developer has resolved to enter the investor or group of investors,
into full commitment). Again, the and on their degree of experience
main question is whether the FID is and risk appetite. Because final
taken before the licence application contracts can only be concluded after
or only after the licence has been the FID has been taken, the question
issued. Both views were given by of timing is strongly connected to the
respondents – again depending on question of early or late contracting
their national regulations and the discussed above.
commercial and market environment.
As might be expected, two diverging
Another question is whether the sets of answers were received on this
licensing regime has any impact on question. A number of respondents
the availability of financing. There stated that the FID can only be taken
seems to be a connection in the sense after the CL or COL has been issued
that a clear and predictable licensing because only at that point has a
regime makes financing easier. sufficient degree of certainty been
reached. As one respondent noted:
“The main final contracts will only
Financing mode enter into force following delivery of
When asked about the financing the CL. As a general rule, it may be
of their projects, all respondents said that in order to take the FID, it is
essentially referred to balance sheet necessary to have a sufficient view
financing, partly with additional over the economic state of the project
elements such as participation of in order to estimate cost.” Even after
foreign investors or government the CL or COL has been issued, one
loans/loan guarantees and borrowing respondent believes an additional
and debt financing. There seems project review is required, to evaluate
to be no example of a pure project specific financing plans based on
financing approach. In a regulated the prevailing market conditions,
environment, cost recovery policy and regulatory considerations.
mechanisms (like in some US One respondent identifies the
states) or state funds financed by a environmental authorization as a
portion of the electricity price play an prerequisite for the FID, another the
important role. Preliminary Safety Analysis Report.

Financial investment Other respondents take the opposite


approach and locate the FID much
decision earlier, at the outset of the project.
From a commercial perspective, the This seems to be the case when
FID is a vital milestone. According to the nuclear power programme is
one response, it can be defined as supported by the state and largely
“the decision to mobilise the capital depends on a government decision
and means to carry out a project.” to proceed, or on the government’s
The survey asked at what stage of long-term energy plan.

23
Does the licensing Yet another respondent suggests
that a non-prescriptive approach
regime have an impact eases financing: “Certainly, a less
on availability of finance? prescriptive licensing process and
fewer formal stages before a plant
Generally, the respondents state is placed into operation benefits
that the licensing system must be the cost of obtaining funds (interest
predictable and stable in order to charges) and minimizes the effects of
give certainty to investors. One issue inflation on construction materials and
is the length of the licensing and plant equipment.” Similarly, another
construction process which, if too respondent states that financing
great, exposes the investor not only would become easier with “more
to increased financing costs, but flexibility” in the licensing system.
also to inflation and foreign currency
risks. Therefore, all elements of Financing and the
uncertainty leading to delay should
be avoided as much as possible. regulator
One respondent mentioned While regulators clearly require the
prolonged public hearings as a applicant/licensee to have sufficient
potential risk leading to delay and financial means to guarantee safety
possibly to changes in regulatory – which seems to be more relevant
requirements which are not justified for the operating licence than for the
on technical grounds. construction licence – the responses
show that regulators do not interfere
Some respondents claim that to any significant extent with the
a non-prescriptive, goal-setting financing scheme and that the FID is
regulatory regime such as in the UK not a milestone the regulator would
leads to some uncertainty and that necessarily want to look at. Should
this enhances the importance of any problems occur during licensing
licences and permits to be obtained and/or construction due to a lack of
before the FID can be taken. Another financial resources, the regulator has
respondent suggests that more its own tools to ask for improvement
prescriptive requirements do not or to stop any activity by the
automatically give more certainty. applicant/licensee.

24
7 Involvement of
Stakeholders
Involvement of stakeholders is an involvement, parliament decision)
important aspect of a nuclear new from the technical phase.
build project throughout the timeline
of the project. Again, the aspect of giving certainty
to investors is more relevant
The government is an important for projects in a market-driven
stakeholder (if not a shareholder) and commercial environment. The
a formally binding positive decision survey responses made clear that
about the nuclear plant project at for projects developed by state-
the outset may ease licensing by owned organizations and/or driven
relieving the licensing process of by government, the necessity of a
political considerations and allowing formally binding government decision
it to focus on safety issues. is less pronounced.

During licensing and sometimes An early strong statement by the


even before the licensing procedure government has nothing to do with
actually starts, the public will be the independence of regulators (a
involved. Laws and regulations point made by some respondents).
define the extent of mandatory An early decision in principle by
involvement of the public; this tends political bodies does not relieve
to increase. The main issue seems the regulator of its task and duty to
to be how to balance meaningful decide whether the planned reactor
public involvement with the necessity complies with safety regulations.
to take basic decisions early in the
project and not to open them up for In some countries there is a
discussion again at a later stage. binding political decision. In France
for example, the government
After licensing decisions have been establishes the multiannual
taken, law courts may play a role if investment programme (PPI - plan
appeals are filed. All stakeholders in the pluriannuel d’investissement)
licensing process must take care that which identifies the need for a new
sound and well-documented decisions reactor. Afterwards, the authorization
are taken so they will successfully decree is adopted by the ministers
withstand scrutiny by the courts. responsible for nuclear safety and
thus represents a governmental
decision. For the UK, respondents
Role of government presented slightly diverging views.
By taking a formal and binding While one respondent said there
decision at an early stage in the is no formally binding decision,
project, a government can give others mentioned the national policy
comfort to investors that the statement on energy infrastructure
necessary licences will be issued as such a document. This may be
(provided of course no technical a problem of defining what “formal
reasons emerge that would result in and binding” means.
refusal of the licences). A well-known
example for this is the decision in There seems to be a range of
principle in Finland which is taken governmental programmes and
by government and confirmed decisions which is not formally
by Parliament. One respondent binding but which can be used as
mentioned that the Finnish system a basis for nuclear power projects.
in his view is a good model because For South Africa, a white paper with
it separates very clearly the political a clear government statement was
phase (feasibility study, public mentioned. In Canada, there is a

25
government directive establishing separate the ‘political phase’ (which
a target share of nuclear in the should include the participation
electricity mix of a province. In Japan, of the public) from the ‘industrial
the utilities execute the projects in phase’. In the industrial phase the
accordance with the energy policy of public should be informed of the
the government. project progress in full transparency,
but the project’s merits, previously
In other countries there is no discussed in the political phase,
government decision. This was should be protected from being put
the case in Germany at the time into question once again.
the nuclear plants were built. In
the Czech Republic, there is only In some countries, the public is
a programmatic statement by consulted once (e.g. Germany),
government with no binding effect. in other countries this happens
In the US, the government likewise several times as the project unfolds
does not take decisions about (e.g. UK). In most countries, site
nuclear projects. In these countries, selection and the environmental
respondents nevertheless seem impact assessment (EIA) processes
to be generally happy with the constitute the main opportunities
situation: US respondents mention for public participation. In some
their trust in the stable regulatory countries, there is an initial public
framework. Several respondents consultation even earlier. In France,
stated that there is a supportive the process of public debate (débat
political environment and that the public) requires the developer to
risk of negative political interference submit to the National Public Debate
is considered to be low. Commission a file presenting the
objectives and main characteristics
of the project, including its social
Participation of the public and economic impacts, estimated
Almost all respondents stress the cost, and an identification of the
fact that early and adequate public significant impacts of the project
involvement is essential. They are on the environment or on town and
mostly satisfied with the transparency country planning. Only after this
achieved in their countries. debate has taken place and the
commission has summarized the
Fairness in the process of public results can the developer file its
consultation certainly is a vital factor licence application.
for acceptance of nuclear projects.
At the same time, it seems crucial There may be an issue with parallel
to achieve a balance between authorization processes leading to
meaningful public participation and repeated public involvement. One
the fact that basic decisions need respondent mentioned that the public
to be taken early in the licensing is consulted during the EIA as well
process and should not be revisited as the nuclear licensing process.
later. Perhaps a principle could be The respondent stated it would be
established that public participation preferable to have public involvement
should coordinate with the steps of in one consolidated process. Such
the licensing process, concentrating a consolidated process exists, for
on the early phases when the example, in Germany, where the
basic decisions are taken, and that EIA is incorporated in the nuclear
discussions, once they are resolved, licensing process and there is only
should not be re-opened later. As one one public enquiry serving both
respondent noted, it is essential to purposes at the same time.

26
Because licensing and permitting Germany and the US. In the US, there
processes often involve public is currently a contention against a
participation, important project COL application which will require
milestones tend to intersect with a contested hearing. According
public involvement. In a project to one respondent, this hearing is
environment where the investor likely to add about six months to the
gives high priority to reducing risk COL application review schedule.
as far as possible, before entering In Canada, an appeal against a site
commitments, major project hearing process has been filed.
decisions such as the FID can
therefore only be taken when both In France, there were several cases of
the licence has been granted and judicial reviews but the law courts did
the public consultation has taken not grant an interim order (which would
place. Survey answers made it clear have affected the project schedule)
that the timing and extent of public and eventually dismissed the claims.
information and participation are
established in laws and regulations The best way of coping with the risk
and do not depend on the project of appeals is summarized by one
developer. Nevertheless, a distinction respondent: “The potential of appeal
can be made between the legal of a regulatory decision is a known
requirements for public consultation risk to the project and a reason to
and the voluntary efforts of the project ensure sound regulatory decisions,
developer to engage the public clarity as to the scope of each
beyond the legal requirements. For decision, and a regulatory process
example, one respondent explained that allows for involvement of external
that utilities hold explanatory sessions participants in a practical manner
for the local population. throughout the review preceding
the decision. This may extend the
Role of law courts regulatory process leading up to a
decision, but will minimize the risk of
When asked whether the project
delay after the decision.”
schedule was at any point influenced
by an appeal (in a law court)
against a regulatory decision, some Other issues
respondents said yes, others no, Two respondents mentioned the
and some said that, though it hasn’t issue of transboundary consultation
happened yet, it could be possible. of governments and the public. This
seems to become more and more
Those countries where projects important and has to be taken into
have actually been delayed are account by project developers.

27
8 Procurement,
Documentation, and
Manufacturing Oversight
Procurement is a stepwise process acceptance of those components
with integrated decision-making needs to be set up and agreed by
based on pre-defined requirements all parties – which might itself be a
and factors such as regulatory review, significant challenge.
design progression, economic and
financial review and commercial Some respondents explained
procurement activities. As with their hold point system and the
contracting and the FID, the right prerequisites for giving the green
timing can be an issue. light, other than the necessary
permits being in place. It follows from
Design documentation and several answers that procurement is
manufacturing documentation a stepwise process with integrated
needs to be efficiently and effectively decision-making based on pre-
reviewed between all parties involved. defined requirements and factors
The answers given by the respondents such as regulatory review, design
reveal a great variety of measures progression, economic and financial
aimed at making sure this happens. review and commercial procurement
activities. One respondent put
As to manufacturing, there is again special emphasis on quality
a timing issue. On the one hand, the management processes which
project developer is ‘on the safe side’ must be in place and agreed with
if relevant qualifications, reviews and the regulator before any safety
approvals are fully completed prior related processes can begin. This
to manufacturing. On the other hand, is demanding and time-consuming,
this may put a strain on the project as well as critical for the schedule,
schedule. One of the outcomes of the but later on it saves time and gives
survey in this respect is the suggestion more certainty by defining the
to take more ‘flexible’ solutions into roles of all parties. Generally, there
account and to proceed on a case-by- were different statements about
case basis, provided regulations leave mandatory involvement of the
room for this. Issues such as these are regulator in procurement. This seems
felt most acutely in the case of long- to reflect different approaches to
lead items. licensing and regulation.

Enhanced international Another respondent mentioned


standardization and greater a government requirement for
cooperation of regulators may be localization of procurement, which
a means to reduce some of the will lead to delays due to the fact that
difficulties and to make component local industry has to be ramped up to
manufacturing more predictable. comply with nuclear standards.

Timing of procurement Managing


Several respondents made a documentation
connection between FID and the Experience shows it is essential
decision to start manufacturing to make sure that design and
and construction. Some stated that manufacturing documentation is
the construction licence or COL efficiently produced, communicated
must first be in place. At least the and reviewed (before and after
regulatory framework required for the manufacturing) by the relevant

28
parties: applicant, contractor, possible with an exit clause in the
subcontractors and regulator. The contract. This is again a good
respondents stress the importance of reason for licensing to take place
this and offer a wide range of aspects early on in the process.
and solutions to be considered:
• Strong architect engineer. In case orders for long-lead items
are placed before the (construction)
• Efficient document management
licence is obtained (which is the
system.
standard situation for FOAK or FIAC
• Sufficient resources for all parties projects), there may be a risk that
involved to ensure timely review of components manufactured before
documents. the licence is granted run into non-
• Procurement plan. compliance with the licence once it is
• Support by qualified suppliers and issued. Obviously, one solution would
vendors. be to agree on specifications with the
• Quality assurance system. regulator before orders are finalized.

• Correctly translating regulatory


Some respondents seek the regulator’s
requirements and owner’s
approval for the specifications of long-
requirements into documents – “it
lead items before ordering them, others
is fundamental to get the design
do not. Those respondents who replied
requirements captured in the right
that they do not agree specifications
way.” Here, a pre-licensing design
beforehand and proceed at their
review is helpful.
own risk can mostly be attributed to
• All parties should agree early on in countries with a state-driven nuclear
the schedule to a comprehensive development programme (e.g.
list of requirements. Ukraine, Korea).
• Challenges to be managed
proactively by vendors and by If previous consent of the regulator is
owners’ groups. needed for ordering components, the
• Using lessons learned from scope of the consent can differ from
previous projects. country to country. In some countries
• Adequate attribution of the regulator has to agree with the
responsibility to all parties for specifications (either in broad terms
consequences of wrong decisions. or in full detail). In other countries,
the regulatory consent encompasses
• Regular meetings between relevant
quality and safety management
parties.
systems, which allows leaving the
detailed specifications to a later phase.
The main message seems to be the
importance that clear processes are
In other systems, it seems the regulator
in place to attribute responsibilities
cannot relieve the licensee of risk by
and roles, and that requirements are
giving a manufacturing consent before
clearly established and understood
the licence is granted. In these cases,
by all parties.
the decision whether to wait or to
place an order is with the applicant.
Long-lead items If it decides to proceed, it will try to
For long-lead items, early negotiate with the supplier to reach a
procurement is necessary, if satisfactory sharing of the risk.

29
In this context, pre-certification of Not all activities are used in all
design is again important. Major regulatory environments. In Korea,
specifications may be part of the for example, the regulator does not
design certification so the applicant review component specifications. In
can confidently go on with ordering France, there is no qualification of
the components. This is especially manufacturers as such; instead, the
important for FOAK components. manufacturing programme is qualified.
As respondents pointed out, in
the US the design certification is If there is qualification of the
expected to be at a level of detail to manufacturer, it is generally done
permit preparation of procurement by the vendor or the future operator
specifications and construction (licensee) and reviewed by the
and installation specifications. regulator.
Procurement specifications need
not be developed at the time of The degree of regulatory review seems
certification, but the level of detail to vary. One respondent suggests this
would support such development, is a question of confidence between
with more detail being added later in operator and regulator.
the procurement specifications. The
US NRC does not require applicants Obviously, the degree of involvement
or licensees to submit procurement of the vendor and the owner/licensee
specifications for review. However, is also a function of the contract
the NRC may audit procurement (EPC/turnkey or multi-lot with
specifications or the information that owner’s engineer).
would be contained in them3.
One respondent indicates some key
Some respondents stress the principles to be enforced as part of
important role of an independent the supplier selection process:
inspection body. Clearly, the role • Availability of multiple qualified
of such bodies varies greatly from suppliers.
country to country. • Proven suppliers.
• Nuclear qualified.
Component • Full suite of capabilities to
manufacturing oversight manufacture equipment depending
Concerning component on its nuclear class, testing
manufacturing, the answers give requirements; and suitable quality
a range of activities carried out by assurance and quality control
the regulator, authorized inspection facilities.
bodies, the vendor or the licensee. • A ‘lessons learned’ database.
Those mentioned are: • Not too many exceptions to
• Review of component specifications.
specifications.
• Qualification of manufacturing Concerning timing, on the one hand
programme. there seems to be a consensus that
the relevant qualifications, reviews
• Qualification of manufacturer.
and approvals should be completed
• Approval of quality assurance prior to manufacturing in order to
(QA) programme (licensee and reduce risk. On the other hand, some
manufacturer). respondents suggest that this may
3
As an example, see US-NRC regulations in 10 • Inspection and oversight during put a constraint on schedules. They
CFR 52.47 manufacturing. advocate introducing more flexibility

30
– by offering a choice – and/or to country, participation of authorized
proceed on a case-by-case basis. inspection bodies is agreed before
For example, one respondent stated manufacturing starts and that for
that the ‘ideal’ order would be to some components a system of
first fully agree the specifications of witness and hold points is put in
the component and then qualify the place. The respondent believes this
manufacturing program based on is good practice, however he says
the agreed specifications. However, the licensee has to foot the bill of
according to this respondent it is the inspection body which is “quite
not always possible to proceed in expensive”.
this way. Therefore, there should
be an option to depart from this An interesting aspect mentioned
general principle and, for example, by some respondents is the
to start qualification before the full development towards international
specifications are available. In this component manufacturing
case, the owner would have to prove oversight, for example through the
later on, when the specifications Multinational Design Evaluation
are completed, that the qualification Programme (MDEP). In the long-
complies with them (which puts term, harmonization of requirements
a certain risk on him). In some and strong cooperation of
jurisdictions, however, this may not regulators could lead to ‘off-the-
be possible since regulations state shelf’ manufacturing of large
that specifications and qualification components, meaning that
must be fully in place before components do not necessarily
manufacturing. have to be destined for one
particular nuclear plant, but could
The survey also addressed the be employed in a range of projects
issue of the role of the regulator of the same design. This would
in inspection and oversight during obviously ease the scheduling
manufacturing. There seem to be issues mentioned above.
some slight differences from country
to country in the regulatory approach, Another interesting issue raised
whether the regulator is ‘deeply was that, in the case of a ‘deferred’
involved’ or not. Some respondents construction project that has been
stress the responsibility of the revived after a long pause, there is
licensee or vendor. One respondent the issue of regulatory approval for
clearly stated that in his view the level using equipment which has been
of regulatory inspection is too high. stored for a long time or was supplied
Another respondent said that in his for a slightly different design.

31
9 Support for International
Standardization
International harmonization of safety Evaluation and Licensing (CORDEL)
requirements and standardization Working Group and described
of reactor designs could greatly in the 2010 report International
facilitate licensing. Particularly in Standardization of Nuclear Reactor
the case of a FIAC, implementing Designs.4
a standardized design and using
licensing results already obtained The survey answers indicate that
in another country would be much there is a certain level of cooperation
easier than starting from scratch and mutual acceptance between
and re-doing the entire assessment. regulators, which would help with
However, there is still a long way to working towards international
go to reach this aim, as the survey standardization. At the same time,
answers show. there is a limit to this. A substantial
principle emerging from the answers
Another issue covered by the survey is that, while regulators may accept or
concerns the point at which reactor take into account the requirements,
design standardization would be standards or codes of other countries,
most beneficial and would have the they never accept the design approval
highest impact. For example, the decision of another regulator.
site qualification and selection stage
would likely not be directly influenced Standards and
by international standardization,
whereas reactor design licensing or requirements
procurement would tremendously Several respondents mentioned that
benefit from making use of already the requirements in their country are
existing approvals and qualifications. based on International Atomic Energy
Agency (IAEA) and – if applicable
International standardization of – Western European Nuclear
reactor designs would mean that Regulators Association (WENRA)
each reactor design, regardless of models. This leads to a degree of
its country of origin, could be built harmonization, at least concerning
in every country with few changes, if high-level requirements.
any. Changes should only be due to
site-specific factors and to specific Several answers suggest that
requests by the operator, and not the regulator does look at the
because the national regulations of requirements to which the design was
the host country are different from originally designed. A respondent
those of the design’s country of origin. from France pointed out that foreign
standards can be used provided they
Therefore, standardization would comply with the French regulations
require national safety standards and their equivalence is established.
to be aligned, as well as increased A respondent from the UK noted that
cooperation among regulators. In the non-prescriptive nature of the UK
a world of standardized designs, it regulatory approach allows for some
should be possible for regulators, flexibility with regard to accepting
4
International Standardization of Nuclear during their safety assessment, international standardization. As
Reactor Designs, World Nuclear
Association’s Working Group on to give some consideration to the long as the foreign standards and
Cooperation in Reactor Design Evaluation certification of similar designs already certifications are logically consistent
and Licensing (January 2010), http:// issued in other countries or to the and meet the expectations of the UK
www.world-nuclear.org/uploadedFiles/
resolution of generic safety issues in regulator, they can be used.
org/reference/pdf/CORDELreport2010.pdf
5 other countries. These issues have
RD/GD-369: Licence Application Guide,
Licence to Construct a Nuclear Power been investigated by the WNA’s There are, however, limits to such an
Plant Cooperation in Reactor Design acceptance. One respondent from

32
the UK mentioned local design codes Licensing whether they would be substantially
and grid codes; another said the facilitated if the regulator would
Most respondents pointed out
UK-specific requirements that would make relevant use of approvals and
that their regulators participate in
lead to design changes are: safety activities already performed by the
international regulators’ groups like
classification methodology; fracture regulator of another country.
MDEP and WENRA. At the same
mechanics analysis design codes;
time, they said that each regulator
and civil structures. Besides, it was Site selection 1 yes / 9 no
takes its own decision in licensing,
mentioned that it was essential to and qualification
based on its own processes and
provide adaptation documents for the
the national legislation. As one Almost all respondents pointed
use of foreign standards in the UK.
respondent stated, the cooperation out that site selection and
among regulators has the status of qualification is based on site
A respondent from the US gave the
experience exchange and is not part specific evaluation; therefore they
example of steel plate reinforced
of the licensing regime. Currently, do not see any potential for foreign
concrete structures. There are no US
there is no mutual acceptance of licensing decisions to facilitate this.
codes and standards on this topic. The
approvals or licences. One respondent noted that site
Japanese standard which does exist
is not accepted as such by the NRC. selection criteria are not sufficiently
One respondent suggested that standardized to be of use in another
However, it was taken into account in
discussions between his regulator country. The one respondent who
the way that comparison of test data
and other regulators may have an answered “yes” stated that the
against test data from Japan was
effect on the level of depth of scrutiny foreign site licensing decision
found to be acceptable to regulatory
in some areas. builds confidence in the ability of a
reviewers in limited instances.
specific technology to meet siting
Another respondent, who is currently requirements.
In Canada, in a Licence Application
undergoing a tender process
Guide identifying the information that
including some foreign designs, says
should be submitted in support of an Design/vendor 6 yes / 3 no
that the bid invitation specifications
application for a licence to construct
(BIS) contain the requirement that selection
a nuclear power plant5, the regulator the design is licensed in its country Here, a majority is of the opinion
states: “Where the licence applicant of origin or in an EU country. The that the approval of a foreign
relies on the use of documents not regulator is expected to collaborate design licence would facilitate this
traditionally used in the Canadian closely with the regulator who has step. Quite obviously, the design
nuclear industry, the applicant already issued the licence. certification would give confidence
should submit an accompanying that the design is mature enough
assessment to facilitate a timely to be licensable. One respondent
review of the submission. This Qualification of
said that a ‘proven design’ is
assessment may be a gap analysis subcontractors and/ a prerequisite for the tender
between the documents referenced or quality control of process. On the other hand, some
in the application versus Canadian
industry-equivalent documents.” The
manufacturing respondents caution that the design
must still comply with the national
Canadian respondent concluded About half of the respondents
standards. For this reason, three
that this seemed to suggest some stated that foreign standards can
respondents came to the conclusion
regulator consideration of vendor be used in this context, provided
that the foreign design approval
documents that may have been their equivalence and compliance
would not substantially facilitate their
used as part of a design certification with national regulations can be
national licensing processes.
process elsewhere. established. The other half gave a
negative answer.
One respondent made the point that
Licence 6 yes / 2 no
more predictability would be achieved Where standardisation application
in the licensing process if standards A majority of respondents answered
for safety culture were internationally
would have the greatest positively, stating that relevant
standardized, particularly those benefits documentation like Preliminary Safety
requirements concerning supplier and The survey mentioned certain Analysis Review, detailed studies
sub-supplier control. actions and milestones and asked and specifications for systems,

33
structures and components would Manufacturing 5 yes / 2 no
be immediately available. This Here, a majority of respondents
would greatly ease licensing. One agreed that manufacturing would
respondent cautioned, however, that be facilitated by an approach of
this effect depended on the reputation international acceptance. One
of the regulator of the reference respondent acknowledged that
licence. Another respondent held that this was not straightforward due to
licensing processes were too different different national specifications for
to transfer over licence approvals components, but having a vendor
from other countries. with a functioning QA/QC system
and a long list of qualified suppliers
Financing 3 yes / 3 no would significantly reduce the risk of
scheme, FID delay. Another respondent, who is a
Here, the opinions were balanced. vendor, mentioned that it would be
Three respondents answered particularly beneficial if regulators
positively: a licence in another could accept ingots (for long-lead
country would show that the design items) accepted by other regulators.
is mature enough and that risks are
under control. It would also help One of the two respondents who
reduce timescales for the design gave negative answers concentrated
review. Three other respondents on the contractual situation and
answered negatively, stressing stated that differences in international
the responsibility of the national regulations had little impact on
project owners. There were many manufacturing contracts.
abstentions, suggesting that the
connection between international Investment in nuclear
acceptance of design licence and the
One respondent stated that,
financing of a project is not obvious.
beyond the possible advantages of
standardized designs and mutual
Main contract 2 yes / 4 no acceptance of standards and
(EPC) approvals for licensing, the overall
While two respondents saw a positive decision to start a new project might
influence on the main contract, for the be facilitated if such an approach
same reasons as given for FID, four exists. Clearly, standardization
respondents did not share this view. reduces uncertainty and licensing
As one of them put it: “Placing the risk and may be crucial to allow
EPC is purely a commercial decision. project developers to take the final
The ability to work with the EPC is far decision to proceed with a nuclear
more important than the technology.” new build project.

34
10 Conclusions

The results of the survey and the For a two-step licensing system,
discussions within the report’s however, a predictable and smooth
drafting group have provided a transition between both licence
comprehensive picture of the processes is considered essential.
relationship between licensing
processes and commercial Pre-licensing of a design or a site
project decisions. This picture is seen as an important feature of
is full of variety because views a regulatory system, reducing the
and experience depend on the risk of licensing and making the
regulatory system and commercial outcome of a licensing process
and political environment within more predictable. The adherence, as
which each project has to be much as possible, of all stakeholders
carried out. including the regulator, to a pre-
agreed schedule, which should
In countries with a competitive market include the list of documents to be
environment and with private project provided and subject to review, is
developers, the survey has revealed another crucial element.
the strong tendency to reduce risk as
far as possible before entering into Vendor/technology and
irreversible commitments. This results
in approaches such as:
site selection
In market-driven systems, site
• Late FID.
selection and choice of technology
• Multi-stage contractual approach, are key commercial decisions that
with separation of licensing and form the basis for the licensing
construction stages. process. Particularly for technology
• Design to be as mature as possible selection, the survey responses
before first concrete. emphasize the need to make a
• Facilitative role of pre-licensing. choice as early in the process as
possible, ideally before the licence
Some responses suggest that these application.
approaches may extend the project
schedule, which opposes the need Contracting
in a competitive environment to keep During the last few years, there
schedules to a minimum. has been a tendency for single
contracts to give way to a system
Other countries, with state-owned of contractual steps. Particularly
industries and government-led in a market-driven environment,
projects, put less emphasis on contracting consists of a series of
these issues. steps during which the partners
enter into further commitments as
Main structures of the project risk reduces with the
progress of the licensing process.
various licensing and
This means the main contract is
permitting systems concluded relatively late in the
Concerning the topic of one-step project, sometimes only after the
licensing versus two- or multi-step licence has been issued. In less
licensing, the survey indicated market-driven environments, the
that commercial developers value survey shows that the ‘classic’
predictability and certainty in approach of concluding an early full-
any system rather than having a scope contract covering licensing
preference for a particular system. and construction is still in use.

35
Design development relieving the licensing process of if relevant qualifications, reviews and
political considerations and allowing approvals are fully completed prior
The survey shows that there is a
it to focus on safety issues. to manufacturing. On the other hand,
range of solutions, which largely
this may put a strain on the project
depend on the given regulatory
The main issue concerning public schedule. One of the outcomes
system and commercial environment,
involvement seems to be balancing of the survey in this respect is the
to address the timing of the design
meaningful public involvement with suggestion to take more ‘flexible’
development steps and their solutions into account and to
the necessity to take basic decisions
relationship to licensing phases and proceed on a case-by-case basis
rather early in the project and not
contractual arrangements. if the regulatory system allows for
to open them up for discussion
again at a later stage. A separation this. Long-lead items are a group of
A crucial issue for FOAK (and FIAC) of a ‘political’ phase with the main components where these issues tend
projects is the extent to which the decision about the project and a to come up in a particular urgent way.
design needs to be developed at ‘technical phase’ with the review of
the time the construction licence safety issues is recommended. Enhanced international
or COL is issued. While there is a standardization and greater
consensus that a certain degree of All stakeholders in the licensing cooperation of regulators may be
design maturity is beneficial or even process must take care that sound a means to reduce some of the
necessary for licensing and that a and well-documented decisions difficulties and to make component
relatively high degree of completion are taken so they will successfully manufacturing more predictable.
of the design should be reached withstand scrutiny by the law courts.
at the time of first concrete, the
Support for international
percentages of design completion
actually suggested are varied.
Procurement, supply standardization
chain, documentation, International harmonization of safety
Financing component manufacturing requirements and standardization
of reactor designs could greatly
As to the timing of the financial oversight facilitate licensing, regardless
investment decision (FID) and its Procurement is shown by the survey of the regulatory and economic
relationship to the main licensing steps, responses to be a stepwise process environment in a country. Particularly
the situation is similar to contracting. with integrated decision-making in the case of a FIAC project,
Again, the main question is whether based on pre-defined requirements implementing a standardized design
the FID is taken before the licence and factors such as regulatory review, and using licensing results already
application or only after the licence has design progression, economic and obtained in another country would
been issued. Both views were given financial review and commercial be much easier than re-doing the
by respondents – again depending procurement activities. As with entire assessment. However, there
on their national regulations and the contracting and the FID, the right is still a long way to go to reach this
market environment. timing can be an issue. aim, as the survey answers show.
While regulators are often open to
There seems to be a consensus that Design documentation and taking into account standards and
a clear and predictable licensing manufacturing documentation requirements stemming from the
regime makes financing easier. needs to be efficiently and effectively vendor’s country, they may never
reviewed between all parties formally accept or endorse, even
Involvement of involved. The answers given by the partially, the design approval of
respondents reveal a great variety of another regulator.
stakeholders measures aimed at making sure this
The government is an important happens. Areas identified in the survey where
stakeholder (even if it is not a international standardization would
shareholder) and a formally binding As to manufacturing, there is again bring the greatest benefits to nuclear
positive decision on the project at a timing issue. On the one hand, the projects are vendor selection, licence
the outset may ease licensing by project developer is ‘on the safe side’ application and manufacturing.

36
Appendix

The following Table illustrates the relevance of the survey items to the different types of new build countries.

“(x)” means “possibly relevant”, “x” means “relevant”, “xx” means “extremely relevant”.

1 2 3 4 5
Established Established Established Newcomers SMRs
market-driven state-driven but small
Licensing and permitting
Multi-step vs. one-step x x x x
Pre-licensing x Small number (x) xx
of projects Depends on Could be
the number of special
of projects relevance
and the size for SMRs
of the national
programme
Keeping to schedule xx (x) x x x
Prescriptive vs. non-prescriptive x (x) x x x
Coordination with non-nuclear permits x x x x
Financing
Timing of FID xx x
Important
if foreign
partners
involved
Contracting
Contracting model xx x x xx xx
Contract
may include
‘import’ of
regulations
Relevance of pre-contracts x x x
(early works agreement)
Vendor selection
Time of vendor selection x x x x
Design development
Design development and its relationship xx x xx xx xx
to contracting, licensing and FID
Importance of design completion at xx Would rather Would rather ??
the time of licensing If FOAK not be FOAK not be FOAK
Subcontractors, supply chain, manufacturing, documentation
Timing of procurement, relationship xx x x x
with licensing milestones
How to best manage licensing documents xx x x x
Role of regulator in manufacturing process x x x x x

37
1 2 3 4 5
Established Established Established Newcomers SMRs
market-driven state-driven but small
Involvement of stakeholders
Managing involvement of the public and xx (x) xx (x) (x)
other stakeholders Depends on Depends on
legal system legal system
in country in country
Necessity of political decision before xx x Part of Part of
licensing general general
decision to decision to
start nuclear start nuclear
energy energy
programme programme
Role of legal appeals x x
Role of international standardization
Role of foreign standards Depends on Depends xx xx xx
whether there
is a domestic
vendor
Importance of using earlier licences Depends on xx xx xx
given in another country whether there
is a domestic
vendor

38
World Nuclear Association +44 (0)20 7451 1520
Tower House www.world-nuclear.org
10 Southampton Street info@world-nuclear.org
London WC2E 7HA
United Kingdom

This report is based on the results of a survey of World Nuclear Association


conducted by members of the joint Task Force organized by the CORDEL
and Law Working Groups. It explores the relationship between licensing
and regulatory systems on the one hand and important commercial project
decisions on the other. The results of the survey and the discussions within
the report’s drafting group have provided a comprehensive picture of the
relationship between licensing processes and commercial project decisions.
As shown in the report, this picture is full of variety because views and
experience depend on the regulatory system and commercial and political
environment within which each project has to be carried out. In any case,
it does show that international harmonization of safety requirements and
standardization of reactor designs could greatly facilitate licensing.

Licensing and Project Development of New Nuclear Plants


© 2015 World Nuclear Association. Registered in England and Wales, company number 01215741

You might also like