Professional Documents
Culture Documents
Untitled
Untitled
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Ka Kalili Mandir (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Table of Contents
TABLE OF CONTENTS
CHAPTER PAGE
1 EXECUTIVE SUMMARY ................................................................
.......................................................... 1
1.1 OBJECTIVE ................................
................................................................................................
.......................................................... 1
1.2 PROJECT ROAD DESCRIPTION................................................................
........................................................ 1
1.3 EXISTING PROJECT ROA ROAD/SITE DESCRIPTION ...........................................................
................................ 1
1.1.1 Carriageway ...............................................1
Carriageway................................................................................................
1.1.2 Major Bridges, Road over bridges (ROB)/Road under under-brid bridges (RUB), Grade
Separator Structures, and Railway Level Crossings, Underpasses (Vehicular, Non Non-
Vehicular): ................................
................................................................................................
..............................................................1
1.1.3 Minor Bridges: ................................................................................................
...........................................1
1.1.4 Culverts: ................................
................................................................................................
.....................................................1
1.1.5 Bus Bays, Truck lay byes, Other Structures:..............................................................1
................................
1.1.6 Road side drains: ................................................................................................
.......................................2
1.1.7 Major Junctions/Minor Junctions:................................................................
.............................................2
1.1.8 Other Structure ................................................................................................
..........................................2
1.4 PROPOSED DEVELOPMENT PLAN ................................................................
................................................. 2
1.1.9 Traffic Data ................................................................................................
................................................2
1.1.10 Pavement Design................................................................................................
........................................2
1.1.11 Major/Minor Bridges: ................................................................
................................................................4
1.1.12 Intersections and Grade Separators ................................................................
..........................................5
1.1.13 Road Embankment and Cut Section ................................................................
...........................................5
1.1.14 Culverts ................................
................................................................................................
......................................................6
1.1.15 Highway Lighting ................................................................................................
.................................... 10
1.1.16 River training works & Vehicular underpass. ........................................................
................................ 10
1.1.17 Rest area and parking area ................................................................
..................................................... 10
1.1.18 Protection works (retaining wall/ breast wall) .......................................................
................................ 10
1.1.19 Widening and geometrical improvement ................................................................
................................ 10
1.1.20 Minor Junctions: ................................................................................................
..................................... 12
oadside Drainage. ................................................................
1.1.21 Roadside ................................................................ 12
1.1.22 Bus Bays/ Bus Stops: ................................................................
............................................................... 12
1.1.23 Utility Duct: ................................................................................................
............................................ 12
1.1.24 Special Landslide Treatment: ................................................................
................................................. 12
1.5 ROADSIDE FURNITURE ................................................................
.................................................................. 12
1.6 TRAFFIC SIGNAGE, PAV PAVEMENT MARKING, LIGHTING ING AND ROAD SAFETY
APPURTENANT ................................................................................................
................................................. 13
1.7 PRE-CONSTRUCTION
CONSTRUCTION ACTIVIT ACTIVITIES ................................................................
............................................... 13
1.1.25 Land acquisition ................................................................................................
...................................... 13
1.1.26 Environmental clearance ................................................................
........................................................ 13
Page i
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Ka Kalili Mandir (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Table of Contents
Page ii
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Ka Kalili Mandir (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Table of Contents
Page iii
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Ka Kalili Mandir (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Table of Contents
Page iv
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Ka Kalili Mandir (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Table of Contents
Page v
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Ka Kalili Mandir (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Table of Contents
Page vi
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Ka Kalili Mandir (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Table of Contents
LIST OF TABLES
Table 3.1: List of Settlements ................................
................................................................................................
..................................................... 24
Table 3.2: List of Existing Structures ................................................................................................
......................................... 26
Table 3.3: Project Road Deficiencies and Improvements Required ...........................................................
................................ 28
Table 5.1:: Characteristic strength of reinforcement steel ................................................................
........................................... 61
Table 5.2: Values of Runoff Coefficient ................................................................................................
..................................... 64
Table 6.1: Schedule of Traffic Surveys ................................................................................................
...................................... 71
Table 6.2: Vehicle Classification System ................................................................
................................................................... 72
Table 6.3: Vehicle Classification and PCU Factors Used in the Study ......................................................
................................ 73
Table 6.4: Average Daily Traffic at Count Locations (veh.) ................................................................
...................................... 74
Table 6.5: Daily Variation of Traffic (P (PCUs) at Each Count Station .........................................................
................................ 75
Table 6.6: Peak Hour Details ................................
................................................................................................
...................................................... 77
Table 6.7: AADT Observed at Count Locations................................................................
......................................................... 79
Table 6.8: Sample size of OD survey urvey ................................................................................................
......................................... 81
Table 6.9: Zoning Scheme ................................
................................................................................................
.......................................................... 82
Table 6.10: Peak Flows at Intersections................................................................................................
...................................... 84
Table 6.11: Projected Peak Hour Traffic at Intersections and Improvement Proposals ............................. 85
Movement Location................................................................
Table 6.12: Pedestrian/ Cattle Movemen .................................................... 86
Table 6.13: Summary table for the Pedestrian/ Cattle Movement ..............................................................
................................ 86
Table 6.14: Pedestrian Facilities ................................................................................................
................................................. 87
Table 6.15: Final Traffic Growth Rates (%) ................................................................
............................................................... 90
Table 6.16: Projected Normal/Total Traffic AADT (PCU) ................................................................
........................................ 90
Table 6.17: Projected Normal/Total Traffic on Intersection ................................................................
....................................... 92
Table 7.1: Geometric Design Standards for Road works ................................................................
............................................ 96
Table 7.2: Summary of Widening Scheme ................................................................
................................................................. 98
Table 7.3: Details of Typical Cross Sections ................................................................
............................................................ 102
Table 7.4 : Summary of Widening Overlay and New Construction ......................................................
................................ 7-117
Table 7.5: Cross Sectional Elements of Structures ................................................................
................................................ 7-117
Table 7.6: Stretches with Built- Up section ................................................................
........................................................... 7-119
Table 7.7: Details of Bypasses ................................
................................................................................................
............................................... 7-119
Table 7.8: Details of Curve Improvement ................................................................
............................................................. 7-119
Page vii
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Ka Kalili Mandir (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Table of Contents
LIST OF FIGURES
Page viii
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
1 EXECUTIVE
1: SUMMARY
1 EXECUTIVE SUMMARY
1.1 OBJECTIVE
Widening to 2-lane
lane with Paved Shoulder configuration of Tawaghat (Ch. 56.935) & Kali
Mandir (Ch. 133.078) road (Excluding Bypass portion) on NH
NH-09
09 under Bharatmala Pariyojna
in the State of Uttarakhand
The Site of the Single Lane Project Highway comprises the section of Highway. Project road
starts from Km. 0+000 at Tawaghat village (Design Chainage 56+935) and traverses a
length of 38.812km and ends Km.19+170 at Budhi Village (Design Chainage 95+748) And
starts at End of Tunnel P Portal
ortal (Design Chainage 113+828) and traverses a length of
19.25km and ends at Kali Mandir (Design Chainage 133+078) . The Project Highway is part
of NH-09.
09. The stretch passes through winding hilly terrain of Himalayas and sight distance is
restricted at places
aces due to sharp horizontal curves and vertical cuts slopes. The land,
carriageway and structures comprising the Site are described below.
1.3.1 Carriageway
The present carriageway of the Project Highway is Double Lane with carriage way width of
7m from Design Chainage 56.935 to 75.889 except 1117.8m road stretch (single lane) and
unsurfaced carriage way from design Chainage from 75.889 to 95.748 & from Km 113.828 to
133.078. The type of the existing pavement from Desig
Design
n Chainage 56.935 to 75.889 is
flexible.
1.3.4 Culverts:
Total 165 nos (Existing 96 nos to be retained and 69 no. new construction)
Page 1
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
1 EXECUTIVE
1: SUMMARY
Nil
The Project Highway shall follow the approved alignment unless otherwise specified by the
Authority.
a. Bypasses:
Nil.
The carriageway width to be adopted is 7m with Paved Shoulder 1.5 m on each side
except from Chainage Km 75.92 to 95.748 the proposed carriage way width is 7m with
Paved shoulder 0.9m on either side.
c. Design Speed
Traffic count in PCU varied from 1052 to 2006 of the Project road section of NH09 and
projected traffic for design life of structure will be more than 5000 PCU.
The pavement shall be designed as per IRC 37:2018 and IRC SP 73:2018 for 20 years design
period for minimum 10 MSA traffic and 10% C.B.R.
Page 2
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
1 EXECUTIVE
1: SUMMARY
Page 3
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
1 EXECUTIVE
1: SUMMARY
(v) The railings of existing bridges shall be replaced by crash barriers at the following
locations:
Page 4
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
1 EXECUTIVE
1: SUMMARY
All intersections and grade separators shall be as per Section 3 of the Manual. Existing
intersections which are deficient shall be improved to the prescribed standards.
Major Intersections
Cross Road Left Cross Road Right
Type of Category Category Junction
Existing Cross
Sl. Junctio (NH/SH/ (NH/SH/M Cross Layout as
Chainage Surfac Road Surface
No n MDR/OD DR/ODR/V Road per the
as per GPS e Type Leads Type
(+,T,Y) R/Village illage/ Leads to Manual
to
/Res.) Res.)
Nil
Minor Intersections
Design
S. No Location Road to be carried over/ under the structure
Chainage
Nil
Page 5
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
1 EXECUTIVE
1: SUMMARY
1.4.6 Culverts
(i) Retained
Design
Sl. No. Type of Culvert Span Arrangement/Dia. (m) Remarks
Chainage (km)
1 57+224 Slab Culvert 1 x 2.0 Retained
2 57+420 Slab Culvert 1 x 2.0 Retained
3 57+676 Slab Culvert 1 x 2.0 Retained
4 57+831 Slab Culvert 1 x 2.0 Retained
5 58+085 Slab Culvert 1 x 2.0 Retained
6 58+305 Slab Culvert 1 x 2.0 Retained
7 58+908 Slab Culvert 1 x 2.0 Retained
8 59+111 Slab Culvert 1 x 2.0 Retained
9 59+481 Slab Culvert 1 x 2.0 Retained
10 59+992 Slab Culvert 1 x 2.0 Retained
11 60+732 Slab Culvert 1 x 2.0 Retained
12 62+392 Slab Culvert 1 x 2.0 Retained
13 63+222 Slab Culvert 1 x 2.0 Retained
14 63+322 Slab Culvert 1 x 2.0 Retained
15 63+662 Slab Culvert 1 x 2.0 Retained
16 64+572 Slab Culvert 1 x 2.0 Retained
17 64+612 Slab Culvert 1 x 2.0 Retained
18 65+142 Slab Culvert 1 x 2.0 Retained
19 65+234 Slab Culvert 1 x 2.0 Retained
20 65+370 Slab Culvert 1 x 2.0 Retained
21 65+642 Slab Culvert 1 x 2.0 Retained
22 65+999 Slab Culvert 1 x 2.0 Retained
23 66+107 Slab Culvert 1 x 2.0 Retained
24 66+640 Slab Culvert 1 x 2.0 Retained
25 67+231 Slab Culvert 1 x 2.0 Retained
26 67+410 Slab Culvert 1 x 2.0 Retained
27 67+940 Slab Culvert 1 x 2.0 Retained
28 68+400 Slab Culvert 1 x 2.0 Retained
29 69+026 Slab Culvert 1 x 2.0 Retained
30 69+400 Slab Culvert 1 x 2.0 Retained
31 69+620 Slab Culvert 1 x 2.0 Retained
32 70+240 Slab Culvert 1 x 2.0 Retained
33 70+933 Slab Culvert 1 x 3.0 Retained
34 71+440 Slab Culvert 1 x 2.0 Retained
35 72+520 Slab Culvert 1 x 2.0 Retained
36 72+640 Slab Culvert 1 x 2.0 Retained
37 73+120 Slab Culvert 1 x 2.0 Retained
38 73+830 Slab Culvert 1 x 2.0 Retained
Page 6
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
1 EXECUTIVE
1: SUMMARY
Design
Sl. No. Type of Culvert Span Arrangement/Dia. (m) Remarks
Chainage (km)
39 74+023 Slab Culvert 1 x 2.0 Retained
40 74+342 Slab Culvert 1 x 2.0 Retained
41 74+510 Slab Culvert 1 x 2.0 Retained
42 74+640 Slab Culvert 1 x 2.0 Retained
43 74+920 Slab Culvert 1 x 2.0 Retained
44 75+053 Slab Culvert 1 x 6.0 Retained
45 75+071 Slab Culvert 1 x 2.0 Retained
46 75+400 Slab Culvert 1 x 2.0 Retained
47 75+480 Slab Culvert 1 x 2.0 Retained
48 75+500 Slab Culvert 1 x 2.0 Retained
49 75+720 Slab Culvert 1 x 2.0 Retained
50 76+200 Slab Culvert 1 x 2.0 Retained
51 77+270 Slab Culvert 1 x 2.0 Retained
52 77+470 Slab Culvert 1 x 2.0 Retained
53 77+670 Slab Culvert 1 x 2.0 Retained
54 78+100 Slab Culvert 1 x 2.0 Retained
55 78+400 Slab Culvert 1 x 2.0 Retained
56 78+610 Slab Culvert 1 x 2.0 Retained
57 78+830 Slab Culvert 1 x 2.0 Retained
58 79+350 Slab Culvert 1 x 2.0 Retained
59 80+270 Slab Culvert 1 x 2.0 Retained
60 80+730 Slab Culvert 1 x 2.0 Retained
61 81+050 Slab Culvert 1 x 2.0 Retained
62 81+190 Slab Culvert 1 x 2.0 Retained
63 81+300 Slab Culvert 1 x 2.0 Retained
64 81+400 Slab Culvert 1 x 2.0 Retained
65 82+930 Slab Culvert 1 x 2.0 Retained
66 83+170 Slab Culvert 1 x 2.0 Retained
67 83+725 Slab Culvert 1 x 2.0 Retained
68 84+365 Slab Culvert 1 x 2.0 Retained
69 84+840 Slab Culvert 1 x 2.0 Retained
70 85+240 Slab Culvert 1 x 2.0 Retained
71 88+130 Slab Culvert 1 x 2.0 Retained
72 88+510 Slab Culvert 1 x 2.0 Retained
73 88+790 Slab Culvert 1 x 2.0 Retained
74 89+020 Slab Culvert 1 x 3.0 Retained
75 89+180 Slab Culvert 1 x 2.0 Retained
76 89+700 Slab Culvert 1 x 2.0 Retained
77 90+576 Slab Culvert 1 x 2.0 Retained
78 90+680 Slab Culvert 1 x 3.0 Retained
79 91+180 Slab Culvert 1 x 2.0 Retained
80 91+280 Slab Culvert 1 x 2.0 Retained
Page 7
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
1 EXECUTIVE
1: SUMMARY
Design
Sl. No. Type of Culvert Span Arrangement/Dia. (m) Remarks
Chainage (km)
81 92+610 Slab Culvert 1 x 2.0 Retained
82 120+910 Slab Culvert 1 x 2.0 Retained
83 125+595 Slab Culvert 1 x 2.0 Retained
84 126+960 Slab Culvert 1 x 2.0 Retained
85 127+110 Slab Culvert 1 x 3.0 Retained
86 127+338 Slab Culvert 1 x 2.0 Retained
87 127+410 Slab Culvert 1 x 2.0 Retained
88 127+760 Slab Culvert 1 x 6.0 Retained
89 128+110 Slab Culvert 1 x 2.0 Retained
90 129+140 Slab Culvert 1 x 2.0 Retained
91 129+500 Slab Culvert 1 x 2.0 Retained
92 129+790 Slab Culvert 1 x 2.0 Retained
93 129+890 Slab Culvert 1 x 2.0 Retained
94 130+490 Slab Culvert 1 x 2.0 Retained
95 131+275 Slab Culvert 1 x 2.0 Retained
96 131+475 Slab Culvert 1 x 2.0 Retained
Page 8
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
1 EXECUTIVE
1: SUMMARY
Page 9
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
1 EXECUTIVE
1: SUMMARY
Nil
Nil
A. Rest Area
Nil
B. Parking Area
1 No.
The retaining wall shall be constructed as per requirement of site conditions for slope
protection in accordance with manual requirement. However, minimum protection
works shall be constructed as per details given below:
a) Retaining Wall with minimum length of 7441m as per site condition with stone
masonry in cement mortar 1:3 & 1200m with RCC as per site condition is required.
b) Breast wall with minimum length 13088mm having height of 3m for 5418m length,
lengt 4m
for 7520m length and 5m for 150m length is proposed.
Nil.
A. Details of Project: -
Page 10
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
1 EXECUTIVE
1: SUMMARY
B. General Cross-Section
Section of Highway
Type of
Sl Length
TCS Type Pavemen Description
No (in m)
t
Typical Cross Section For Widening To 2-Lane
Road With Hard Shoulder From Single Lane
1 1 Flexible Road. 18308
(LHS - Hill) (Formation Cutting Done By BRO
Upto 10.0m Formation)
Typical Cross Section For Widening To 2-Lane
2
Road With Hard Shoulder From Single Lane
2 1A Flexible 1390
Road. (RHS - Hill) (Formation Cutting Done By
BRO Upto 10.0m Formation)
2 Lane Carriageway With Hard Shoulder
3 1C Flexible (Realignment/New Construction) (LHS - Hill 1240
Side ) Carriageway Width =12m
Two Lane With Hard Shoulder (LHS-Hill)
(LHS
4 1E Flexible 14933
Already Constructed ByBRO
Typical Cross Section For Widening Of Single
5 1G Flexible Lane Road To 2 Lane With Hard Shoulder (LHS 2314
- Hill)
Typical cross section for widening 2 lane
6 1H Flexible with hard shoulder from Single lane 3125
Earthen Road (LHS - Hill)
Typical Cross Section For Existing 2--Lane Road
7 2 Flexible With Hard Shoulder (LHS - Hill) (Formation 11439
Cutting Done ByBRO Upto 12.0m)
Typical Cross Section For Existing 2--Lane Road
8 2A Flexible With Hard Shoulder (RHS - Hill) (Formation 1772
Cutting Done ByBRO Upto 12.0m)
Typical Cross Section Of 2 Lane Carriageway
With Hard Shoulder (Realignment/New
9 2B Flexible Construction)-(LHS - Hillside ) Realignment 903
Due Geometric Improvement (Existing
Formation Done ByBRO Upto 12.0m)
Typical Cross Section Of 2 Lane Carriageway
With Hard Shoulder (Realignment/New
10 2C Flexible Construction)-(RHS - Hillside ) Realignment 558
Due Geometric Improvement (Existing
Formation Done ByBRO Upto 12.0m)
Page 11
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
1 EXECUTIVE
1: SUMMARY
Type of
Sl Length
TCS Type Pavemen Description
No (in m)
t
Typical Cross Section Of 2 Lane Carriageway
With Hard Shoulder At Built-up
up Location-(LHS
Location -
11 3B Flexible 718
Hillside ) (Existing Formation Done ByBRO
Upto 12.0m)
Typical cross section of 2 lane carriageway with
12 3C Flexible 522
hard shoulder at built up location
2 Lane Carriageway With Hard Shoulder (At
13 4 Flexible 200
Sinking Zone) (LHS - Hill Side )
Major/ Minor Bridges under Construction/
14 STR (U/C) 323
Constructed by BRO
15 STR STR MNB under Bharatmala 318
Total Length (in m) 58063
3 nos.
Construction of KC-drain
drain and Construction of V
V-shaped
shaped drain as per TCS & drawings.
The utility duct has been proposed in entire section of the project in either side (58.147km
excluding the structure locations cons
considering
idering the drawings and applicable typical cross
section).
Nil
Roadside Furniture shall be provided in accordance with section 09 of the Manual and
relevant IRC codes. The roadside furniture shall also include the following minimum
provisions:
(a) Thrie-Beam
Beam metal crash barrier: 45131m
(b) Road Boundary Stone: It shall be provided for the entire Project Highway.
Page 12
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
1 EXECUTIVE
1: SUMMARY
1.6 Traffic Signage, Pavement Marking, Lighting and Road safety Appurtenant
(i) Traffic control devices and road safety works shall be provided in accordance with IRC:
25, IRC: 26, IRC:35, IRC:67, IRC:79, IRC:103 and section 800 of MoRT&H.
(ii) Specifications of the reflective sheeting shall be as per paragraph 9.3 of Manual.
1.7 Pre-construction
construction Activities
Environment Clearance is not required for two laning of Project Highway as per MOEF
Notification on 22ndAug 2013.
The proposal involves shifting of electric pole and water pipeline. An amount of ₹19.00 Lakhs
has been kept in total project cost for shifting of these utilities
The total cost of project including shifting of utilities is Rs. 274.96 Cr. This cost is excluding
GST.
Page 13
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
2: INTRODUCTION
2 INTRODUCTION
2.1 PROJECT BACKGROUND
The National Highways & Infrastructure Development Corporation LLtd.td. (Ministry of Road Transport
& Highways) has been entrusted with the assignment of Consultancy Services for Feasibility study
and preparation of Detailed Project Report for 2 lane with paved shoulders for work of Upgradation
for selected road stretches/ corridors under BHARATMALA project.
Accordingly, NHIDCL intends to take up the preparation of the feasibility and detailed project report
for same.
In order to access the financial and technical feasibility M/s Voyants Solutions Private Limited,
Gurugram have been entrusted by NHICDL for the above work to carry out the Feasibility Studies
and Detailed Project Report.
Page 14
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
2: INTRODUCTION
During the course of project preparation, few stretches were transferred to BRO.
BRO The matter is
briefly stated below:
2.2 OBJECTIVE
Objective of the consultancy services is to carry out the Feasibility Studies and Detailed Project
Report including field investigations, road inventory, ststructure
ructure inventory, road crust sample (trial
pits), material investigation, secondary data collection and traffic survey (classified volume count, O
O-
D, intersection counts, axle load survey, animal/pedestrian crossing counts, toll rate survey, truck
parking survey and speed-delay
delay survey on the above mentioned project highway.
Page 15
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
2: INTRODUCTION
The consultant “Voyants Solutions Pvt. Ltd. (VSPL)” has carried out a general reconnaissance survey
with sample measurements of the entire road and has prepared this reconnaissance report on the
project road. Brief description of the route is described bel
below.
ow. The Index Map is enclosed as Figure
2.1.
The Site of the Single Lane Project Highway comprises the section of Highway. Project road starts
from Km. 0+000 at Tawaghat village (Design Chainage 56+935) and traverses a length of 38.812km
and ends Km.19+170 70 at Budhi Village (Design Chainage 95+748) And starts at End of Tunnel Portal
(Design Chainage 113+828) and traverses a length of 19.25km and ends at Kali Mandir (Design
Chainage 133+078) . The Project Highway is part of NHNH-09.
09. The stretch passes through winding hilly
terrain of Himalayas and sight distance is restricted at places due to sharp horizontal curves and
vertical cuts slopes.
The project road starts from Tawaghat in the district of Pithoragarh on the co co-ordinate of
29°57'29.05"N, 80°36'4.23"E and ends near Kali Mandir on the co co-ordinates
ordinates of 30°14'9.00"N,
80°55'19.11"E.. The total design length is 58.063 km. The road passes th
through
rough Pithoragarh district in
the state of Uttarakhand.
Page 16
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design
km 113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bha Pariyojna on EPC mode
2: INTRODUCTION
Page 2-17
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
2: INTRODUCTION
The existing road geometry is fair to poor, but the presence of sharp curves and bends after long
straights hamper the general goodness of the geometry.
The proposed road shall follow mostly the existing alignment and profile with local improvements
for sharp/steep horizontal/vertical curves and gradients due to the terrain condition. Cross-sectional
Cross
elements of the proposed road shall include improved and updated existing road to proper two lane
road with hard shoulders. Here it is prudent to mention that the latest publication of SP SP-73:2018
specifies
ifies provision of 1.5m wide paved shoulders at each side of carriageway and 1.0m wide hard
shoulder on valley side along hill roads. However, considering the traffic volume, it may be more
appropriate to confine the cross
cross-sections to two lane carriageway with hard shoulder on either side.
10.0m-12.0m
12.0m formation cutting is under progress at site and accordingly width of hard shoulder on
either side shall be 1.5m or 2.5m to ensure utilization of the formation to the maximum extent.
The main objective of this consultancy services is to carry out the feasibility study and preparation of
detailed project report for the purpose of firming up the Authority’s requirement
requirements in respect of
development and construction of the Project Highway and Project Facilities and enabling the
prospective bidders to assess the Authority’s requirements in a clear and predictable manner with a
view to ensuring:
(i) Enhanced safety and level of services for the road users;
(ii) Superior operation and maintenance enabling enhanced operational efficiency of
the Project Highway;
(iii) Minimal adverse impact on the local population and road users due to road
construction;
(iv) Minimal adverse impact on environment;
(v) Minimal additional acquisition of land; and
(vi) Phased development of the Project Highway for improving its financial viability
consistent with the need to minimize frequent inconvenience to traffic that may be
caused if additional works are undertaken within a period of seven years from the
commencement of construction of the Project Highway.
Page 18
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
2: INTRODUCTION
General scope of services shall cover but shall not be limited to the following major tasks:
After review of the TOR, following surveys, field investigations and tests have be
been
envisaged at this stage. Those are:
a) Topographical Survey
b) Traffic survey – mid block volume counts (24 hrs x7 days) at three locations and
intersection counts (8 hrs x 1 day) at two locations along the project highway.
c) Origin-Destination
Destination (OD) survey at two proposed toll plaza locations (24 hrs x 1 day).
d) Turning Movement Survey
e) Axle load survey at two proposed toll plaza locations (24 hrs x 1 day).
f) Speed-Delay
Delay Survey
g) Pedestrian/animal cross traffic surveys
h) Truck Terminal Surveys
i) Road inventory and pave
pavement
ment condition surveys for the entire stretch.
j) Bridge / culverts inventory and condition surveys for the entire stretch.
k) Topographical survey with DGPS and Total Stations
l) Sub-grade
grade soil characteristics through trial pits @ 3 km or closer where change in so
soil
Page 19
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
2: INTRODUCTION
type is encountered.
m) The characteristics of the existing soil, 2 samples from every five km of the Project
Highway or closer where change in soil type is encountered.
n) Material investigations and tests for borrow earth, aggregates
o) Sub-soil
soil explorations as per IRC 78:2000
p) Detailed hydraulic data for bridges, design discharge, HFL, LWL, etc. with a view to
checking adequacy of existing waterway.
q) A broad assessment of the drainage condition and requirement of the Highway.
Page 20
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
2: INTRODUCTION
The stages will generally follow a sequence though stages are inter
inter-related
related and inter-dependent
inter on
one another. This report is under Stage 5: Detailed Project Report deliverables of Tawaghat to Kali
Mandir road of Askot-Lipulekh
Lipulekh Section.
The Draft Detailed Project Report has been prepared in following Eleven volumes:
Volume-III
III : Materials Report
Page 21
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
2: INTRODUCTION
Volume-V
V : Technical Specifications
Volume-VI
VI : Rate Analysis
Volume-VIII
VIII : Bill of Quantities
Volume-IX
IX : Drawing Volume
Page 22
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
2: INTRODUCTION
This Main Report has been presented in the following structural format:
Chapter-2 : Introduction
Page 23
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
3.1 General
The Site of the Single Lane Project Highway comprises the section of Highway. Project road starts
from Km. 0+000 at Tawaghat village (Design Chainage 56+935) and traverses a length of 38.812km
and ends Km.19+170 at Budhi Village (Design Chainage 95+748) An Andd starts at End of Tunnel Portal
(Design Chainage 113+828) and traverses a length of 19.25km and ends at Kali Mandir (Design
Chainage 133+078). The Project Highway is part of NH NH-09.
09. The stretch passes through winding hilly
terrain of Himalayas and sight didistance
stance is restricted at places due to sharp horizontal curves and
vertical cuts slopes. The road passes through Pithoragarh district in the state of Uttarakhand.
2 Mangati
3 Budhi
4 Jaikot
5 Napalchu
6 Gunji
8 Kalapani
3.3 Connectivity
The Road starts near Askot in the district of Pithoragarh which 435 km from Dehradun is, Capital of
Uttarakhand by National Highways NHNH-7.
Page 24
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
The terrain of this road is hilly and mountainous terrain. The road stretch passes through a mixed
land use between forest cover and settlements.
No ROW pillars were found at site. Visual investigation and manual measurements
indicate that existing ROW varies from 4.6m
4.6m–16.1m. Details are available in Annexure 3.1.
Road inventory.
Roadway Width
Drains
Unlined drains are found mainly at hilly section and line drain are found some major and
minor built up section areas respectively. Average width of drain is found as 0.5 to 1.5 m.
3.7 Geometry
3.8 Pavement
The existing pavement mostly varies from poor to fair condition on the bituminous surface. At some stretches
the carriageway is having of both major & minor cracks, raveling, patching and potholes. The shoulder
condition is varying from poor to fair. This can also be seen at the road and shoulder interfaces where the edge
drop is quite prominent. Some portion of the road is not visible due to the landslide.
Page 25
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
The existing pavement structure mostly comprises of two and three layers, namely
bituminous layer, base course and sub
sub-base course. The total thickness of the pavement varies from
265 mm to 300 mm. The thickness of the bituminous surfacing layer varies from 55 mm to 90 mm
thick, base course varies from 195 mm to 240 mm.
3.9 Road Intersections/Cross Roads
There is no Major junction in this stretch, 03 minor Junctions are in this stretch
There are exist 95 nos. existing structures as mentioned in below Table 3.2.
1 Causeway -
2 Slab Culvert 96
3 Minor Bridge 12
4 Major Bridge 1
Total 109
Inventory and condition survey data for the above structures are presented in Annexure 3.2
Page 26
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
3.12 Utilities
The existing utilities (parallel and across) along the project stretch include:
Page 27
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
The major deficiencies of the existing road as identified are summarized in Table 3.3
below for identifying possible improvement proposal.
2 Existing shoulders functionally 1.5m wide paved shoulders on both Hill and
and structurally inadequate valley side has been provided
7 Absence of
Page 28
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
4.1 Introduction
The districts through which the study corridor passes through are considered to be the primary
project influence area. The study corridor is the NHNH-09
09 with ROW varying from 24 m. The Project
road
ad pass through Major Town Askot, Jauljibi, Ghatibagad, Dhungatoli, Bainiyadoli, Gagharu,
Kimkhola, Teen Tala, Ghasku, Zaykot, Pangla, Ghatiyabagad, Gunji, Kali Mandir and Lipulekh Pass Pass.
The project passes through two rivers
rivers-Kali Nadi, Gori Nadi. The total design length of road is 58.063
km which runs in only one district Pithoragarh. The Government of India is trying to give a direct
connection between Askote and Lipulekh Pass via Jauljibi, Dharchula, Tawaghat, Sirkh, Garagadi,
Bundhi, Garbyang, Ghatiabagad,d, Gunji and Kali Mandir.
The Site of the Single Lane Project Highway comprises the section of Highway. Project road
starts from Km. 0+000 at Tawaghat village (Design Chainage 56+935) and traverses a length
of 38.812km and ends Km.19+170 at Budhi Village (Design Chainage 95+748) And starts at
End of Tunnel Portal (Design Chainage 113+828) and traverses a length of 19.25km and
ends at Kali Mandir (Design Chainage 133+078) . The Project Highway is part of NH-09.
NH The
stretch passes through winding hilly terra
terrain
in of Himalayas and sight distance is restricted at
places due to sharp horizontal curves and vertical cuts slopes. The following road passes
through Pithoragarh district in the state of Uttarakhand.
In general, the main mode of transport to connect the ttowns owns of Askote, Jauljibi, Dharchula,
Ghatiabagarh, Gunji and Kali Mandiris by road. Daily needs and goods are being transported through
LCV & 2 axle trucks mainly. Some important trekking places and tourist places on the project roads
are Dharchula Range up p towards the Kailash and Mansarover and many more which attracts tourists
from all over India. During tourist period many car movements can be seen on the project roads.
Page 29
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Therefore, the influence area of the project corridor, for the purpose of the study, is defined
at the State level, though the major economic characteristics and development of Backward,
Religious and Tourist Places are addressed at the project district level, which are Pithoragarh
District in the State of Uttarakhand
4.3 Methodology
The economic characteristics of the PIA with respect to demography, income, industrial
development, agricultural development, mineral exploitation, tourism potential, motor vehicle
registration, transport sector policy, economic development policy and plans ha
have been examined.
The base data required was collected from numerous agencies and various literature available from
the Directorate of Economics and Statistics, Govt. of Uttarakhand. Meetings were also held with
relevant organizations in order to assess th
the future potential growth.
All statistics used to study the past economic performance of the PIA are based on secondary official
sources of information.
4.5.1 History
Uttarakhand was formed on the 9th November 2000 as the 27th State of India, when it was carved
out of northern Uttar Pradesh. Located at the foothills of the Himalayan mountain ranges, it is
largely a hilly State, having international boundaries with China (Tibet) in the north and Nepal in the
east. On its north-west
west lies Himachal Pradesh, while on the south is Uttar Pradesh. It is rich in natural
resources especially water and forests with many glaciers, rivers, dense forests and snow snow-clad
mountain peaks. Char-dhams,
dhams, the four most sacred and revered Hin Hindu
du temples of Badrinath,
Kedarnath, Gangotri and Yamunotri are nestled in the mighty mountains. It’s truly God’s Land (Dev
Bhoomi). Dehradun is the Capital of Uttarakhand. It is one of the most beautiful resort in the
submountain tracts of India, known for its scenic surroundings. The town lies in the Dun Valley, on
the watershed of the Ganga and Yamuna rivers.
Page 30
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
With levels of literacy higher than the national average, the State has abundant availability of quality
human resources. Within a short span of its existence
existence,, Uttarakhand has emerged as a significant
destination for investments in manufacturing industry, tourism and infrastructure. Emphasis is on
stimulating all three sectors of its economy (agriculture, industry and services),to their fullest
potential in tandem
dem with the geographic profile of the state. The Government of Uttarakhand has
undertaken several policy measures and incentives in order to encourage inflow of investment into
the various sectors of its economy.
Geographical Data
i. Hill i. 46035
ii. Plain
ii. 7448
Demography
Population [2011-Census]
Census] Total 10086292 persons
Males 5137773
Females 4948519
Rural 7036954
Page 31
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Urban 3049338
Total 6880953
Male 3863708
Female 3017245
Total 78.80
Male 87.40
Female 70.00
Male 968586
Female 923930
Rural 1496665
Urban 395851
Male 148669
Female 143234
Rural 264819
Urban 27084
Religious Population
Hindus 8368636
Muslims 1406825
Sikh 236340
Buddhist 14926
Jain 9183
Christian 37781
Page 32
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Rural 18.9
Urban 15.7
Rural 6.4
Urban 4.8
Rural 34
Urban 22
Uttarakhand state located in northern part of India has a total area of 53,483 sq. km, of which 93% is
mountainous and 65% is covered by forest. The total population of the state as per census 2011 is
10,086,292 showing a growth rate of 18.81% from census 2001. Of the total population, 51% are
male, while remaining 49% are female. The state constitutes approximately 70% rural population
pop
and 30% urban population. The state is divided into 13 districts which are grouped into two divisions
– Kumaon and Garhwal.
Approximately 38% of the population of Uttarakhand is below poverty line (BPL). Among the
thirteen districts of the state, Uttarkashi district has the highest proportion of BPL population, while
Udham Singh Nagar district has the lowest BPL population. The district wise BPL population of
Uttarakhand is shown in the adjustment figure. The state has a per capita income ofINR82,1
ofINR82,193 and is
higher than the national average of INR 60,603.
4.5.4 Literacy
The literacy rate of the Uttarakhand State as per 2011 census is 78.82%. Male literacy and female
literacy are 87.4% and 70.01%, respectively.
Page 33
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
4.5.5 Climate
Uttarakhand is a region which has some of the most majestic places, and also provides some
outstanding natural beauty. It is a part of the Greater Himalayan ranges and is covered by beautiful
Himalayan peaks and glaciers. Two very important and holy rivers of India, the Ganga and Yamuna
start
tart their journey from here. In this article, we provide you information about Uttarakhand
weather.
Uttarakhand mainly has two different climatic regions, namely, the hilly terrain and the smaller plain
region. So, the weather is also quite varied, depen
depending on the particular place.
Summers
Summers in the plain region of Uttarakhand have similar climate as other surrounding plain regions
of different states i.e. the maximum temperature can cross the 40°C mark and there can be
considerable humidity. Warm temperate conditions prevail in the Middle Himalayan valleys with
temperature around 25°C making it an idle getaway for people of the plains to beat the heat.
However, in the higher areas of middle Himalayas the temperature is around 15 to 18°C, still
pleasant.
asant. The season extends from April to June.
Winters
The Climate of Uttarakhand during summers in the plain region can be chilly with temperatures
going below 5°C mark. The winters in the middle Himalayan valleys are very cold and in the higher
areas thee temperature can drop below the freezing point. The Himalayan peaks remain snowcapped
throughout the year and many places receive regular snowfall. Throughout the state the
temperature ranges from sub-zero
zero to 15°C and the season lasts from November to Feb
February.
Monsoon
The monsoon is the most pleasant season when temperature differs from 15 to 25°C at most places
which reigns from July to September. The state receives 90% of its annual rainfall in this season. The
eastern parts of Himalayas are subjected to heavier rainfalls when westerns are relatively drier.
4.5.6 Forest
Page 34
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Uttarakhand comprises of 13 districts spreading over an area of 51,082 sq km, floristically, it falls
under the west Himalayan Biogeography zone and it is well
well-known for floral
oral diversity similar to any
other Himalayan region in the country with an estimated 4,000 species of flowering plants having
great economic medicinal, aromatic and artistic value. The endemic plant wealth of Uttarakhand is
worth mentioning as it ultimate
ultimately
ly forms part of the National heritage. Uttarakhand Himalayas have
about 116
Besides, many plant species new to science have been added from different parts of Uttarakhand.
Some such species are Anemone raui, Arenariacurvifolia, Carexnandadviensis, List era
nandadeviensis, Saussureasudhanshui, Euphorbia sharmae, Androsacegarhwalicum, etc. More
interesting to note is the presence of one of the smallest flowering plants
Arceuthobiumminutissimum, parasitising over Pinusgerardiana (Chilgoza) and the tallest plant of
Asia, the Pinusroxburghii, in Ut
Uttarkashi
tarkashi district. The sacred Mulberry, Morusserrata, said to have
been planted by the AdiShankaracharya at Joshimath, the tree fern Cyatheaspinulosa, the gigantic
Aesculusindica on way to Panwali, the tall Shore a Robusta (Raja Sal) near Byasi are some ot other
curiosities of the area. The narrative of the plant wealth of Uttaranchal will not be complete unless a
mentioned about the sacred plants commonly used in worship in "The Abode of Gods". Besides, the
earlier mentioned "Brahmakamal", Zanthmlumarmatum (T (Timur),
imur), Prunuspuddum (Panya),
Skimmialaureola, Primula denticulata, and Artemisia nilagirica, Eagle marvelous etc. are offered to
deities. Some other representative and interesting plants of Uttaranchal are enumerated below with
a brief description:
The vegetation
getation of Uttarakhand can be divided in the following zones:
1. Sub-Tropical
Tropical Zone of Uttarakhand
Page 35
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
The sub-tropical
tropical zone has pure as well as mixed forests of Shore Robusta (Sa I), the others being
Lanneacoromandelica (Jhingan), Buchananialanzan, Dalbergi
Dalbergiaa disso (Shis ham), 411 Haldinacordifolia
(Haldu), Syzygiumcumini (Jamun), Mallotusphilippinensis (Rohini), Mitragynaparvifolia, Terminalia
spp. (Myrobalans), Ficus spp. (Figs), Macarangapustulata, Callicarpaarborea, Diopoknemabutyracea
(Chyura), Bauhinia variegate (Kachnar), Bomb axcobia (Semal), Lydia claying (Pula), Schleicher oleos
(Kokum), Holoptelea integrities (Karanj), Cassia fistula (Amaltas), Nyctanthesarbor
Nyctanthesarbor-tristis (Parijat),
Anogeissuslatifolia (Bakli, Dhaura), etc. The shrubbyvegetation is repr
represented
esented by Murrayakoenigii,
Carissa opaca, Clerodendrum viscous, Adhatodavasica, Jasminummultiflorum, Solanumerianthum,
Cal/icarpamacrophylla, Eranthem um nervosum, Phlogacanthusthyrsiform is, Jatropha curcas,
Rhusparviflora, Dodonaeaviscosa, Woodfordiafru
Woodfordiafruticosa and many others.
3. Sub-Alpine
Alpine and Alpine Zones of Uttarakhand
The
he altitude above 3,000 metres is general lyconsidered a zone of sub
sub-alpine
alpine and alpine vegetation.
The tree species are represented by Pinus wall ichiana, Abiespindrow, Prunuscornuta, Aber
caesium., Betulautilis (BhojPatra) and Salix sp. Species of the gen
genera
era Cotoneaster, Rosa, Berberis,
Ribes, Junipers, Rhododendron anthropogenic, Rhododendron campanulas are the shrubby
components of the zone. The herbaceous vegetation is represented by a number of species of
Page 36
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
genera Po ten till, Primula, Aster, Saxifrage, Achaean, Delphinium, Polygonal, Corydalis, Pleuras perm
um ,I'vleconops is, Pedicularis, Saussurea, Rheum, Silene, etc. The Bugyals of this zone are well
known for a rich and diversified flora. Plant species like Nardostachys grand flora (Jatamansi),
Podophyllurnhexandrum
hyllurnhexandrum (Himalayan May May-Apple,
Apple, Papri), Picrorhizakurrooa (Kutaki), Gentian burro,
Atmeniaberithonic (Bal char), Rheum moorcroftianum (Dole), Ephedra gerardiana,
Dactylorhizahatagirea (Hafthajari), etc., common in this zone, are of immense medicinal value.
The floral diversity is further exhibited bythe species that grow in the rain shadow areas of
Uttaranchal. Such species develop adaptive characters to survive the wrath of adverse climate.
Labium rhomboid, Thylacospermumcaespitosurn, Acantholi mon lycopodioides,
Dracocephalurnheterophyllumetc are a few such examples.
Orchids
Uttarakhand has more than 225 species of this charming group, well known for ornamental flowers
with great horticultural potential and long shelf life. Aerides, Cool ogyne, Cymbidium, Dendrobium,
Thunia and Rhynchostylis, for which Mandai, Baram, Shandev, DafiaDhoora, Kaflani, etc are rich.
Among the global orchids, species of Calanthe, Habenaria, Anoectochilus, Satytium, etc are fairly
common while the Lady's Slipper Orchid
Orchid-Cypripedium is scarcely distributed.
Many small river valleys offer wonderful experience to nature lovers and hikers. The vast open hay
field, above the tree line present endless views of the variously colored Himalayan flowers. The most
interesting of them,
em, aesthetically or botanically are seen in the higher altitudes, from 2,450 meters
and above. The arrival of spring brings forward an uprising of colours when the Semal and Palash
put the lower altitude forests on fire with their blazing red flowers. IItt is also the time for Burans to
spread its fire at a height of or above 2,450 metres adding colour to the blue and white panorama of
snow. The flowers do not grow only in the Valley of Flowers but are found on different treks
habitually up to great heightss as also on the hayfield and even in rock cracks or moraines.
Source: http://forest.uk.gov.in
About 90 per cent of the population of Uttarakhand depends on agriculture. The total cultivated
area in the State is 7,84,117 hectares.
Uttaranchal
ranchal is an agrarian state. About 80% of the population of the state is dependent on
agriculture for its livelihood. 12% of the available land is irrigated and 64% are fed by natural springs.
The topography of Uttaranchal is characterized by sandy soils which do not retain water for long
Page 37
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
time. Due to unavailability of moisture in the soil the crop productivity is not very good in the region.
Also, due to variation in altitude the rainfall also differs from place to place affecting the crop
production.
The
he major crops produced in the state include Rice, Wheat, Barley, Corn, Mandua, Jangora etc. The
state is a major supplier of fruits like Apple, Leachy, Pulam, Naashpati, and Maalta etc. There are
various organizations which are involved in the state to he
help
lp in improving the productivity as well as
to promote the cultivation of medicinal plants in the state. One such project is functioning near
Pinder Valley in Chamoli district of the state which aims to produce fruits and vegetable by utilizing
poly houses.
The predominantly hilly State of Uttarakhand has a varied hydrogeological setup and can be divided broadly
into two distinct hydrogeological regimes viz. the Gangetic alluvial plain and the Himalayan mountain belt. The
former is covered with a vast expanse of alluvium and unconsolidated sedimentary material of varying size
fractions (ranging from boulder to clay) and iiss a promising zone for ground water development. The latter
zone, being predominantly hilly, offers much less potential for large scale development of ground water.
Ground water in the hilly region occurs mostly in fissures/fractures and emerges as springs
springs. The springs are
amenable to small scale development of ground water resources in the State. The yield of tube wells in
3 3 3
Shiwalik formation ranges from 50.4 m /hr to 79.2 m /hr, in Bhabar formations yield is upto 332.4 m /hr. In
3 3 3
Tarai belt yield of tubewelll ranges 36m /hr to 144 m /hr and in Indo-Gangetic
Gangetic plains yield varies from 90 m /hr
3
to 198 m /hr.
The main drainage system of Uttarakhand have been grouped into following six catchments
Yamuna Catchment - The Yamuna river originates from the base of Bandarpunch peak. It has carved a deep V-
shaped gorge. The Yamuna cuts across the Nag Tibba range and Mussoorie range near a place called Yamuna
bridge. The rivers Tons, Pabar and Aglar are its important tributaries. It passes through the Doon valley on its
Western boundary.
Page 38
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Bhagirathi Catchment – This is one of the two rivers which join to form the river Ganga. It originates from the
snout of the Gangotri glacier at Gaumukh which is at the base of Chaukh
Chaukhamba
amba peak. The Bhagirathi river has
cut a deep gorge across the granitic rocks of the higher Himalayas of Garhwal. Its main tributaries are the river
Janhavi and theBhilangana.
Alaknanada Catchment - This river joins the river Bhagirathi at Devprayag to fform
orm the river Ganga. It originates
from the eastern slopes of Chaukhamba – from the Bhagirathi kharak and Satopanth glaciers. The river flows
along the Badrinath temple. Its main tributaries are the Khiraonganga, Pindar Dhauliganga, Birahi, Nandakini,
Mandakini
akini etc. It has formed a broad valley at Srinagar (Garhwal).
Mandakini Catchment - It comes out from the Mandakini glacier near Kedarnath. It cuts through a gorge of
glacial debris. The river has formed road terraces at Augustmuni and Tilwara. At Tilwar
Tilwaraa it is joined by the river
Lastar Gad. The river Mandakini joins the river Alaknanda at Rudraprayag.
Pindar Catchment- The river Pindar originates from the Pindari Glacier which is located between Nanda Devi
and Nanda kot peaks. Sundar dhunga river joins the Pindar near Dhakuri. The Pindar joins the river Alaknanda
near Karanprayag.
Kali Catchment – The river Kali forms the boundary between Kumaon and Nepal. The Towns of Champawat
and Pithoragarh are situated on the back of the Kali River. Its important tributaries are Darma and Saryu rivers.
The Land Survey Directorate (LSD) has divided the Uttaranchal into 8 catchments, and then into 26
watersheds, then into 110 SWS and finally into 1110 MWS and shown in Map. Haridwar district is yet to be
delineated byy the Land Survey Directorate but essentially an area of 2.33 lac ha. needs to be taken up for the
watershed works.
Uttarakhand has a great diversity of flora and fauna. It has a recorded forest area of 34,651
km2which constitutes 65% of the he total area of the state. Uttarakhand is home to rare species of
plants and animals, many of which are protected by sanctuaries and reserves. National parks in
Uttarakhand include the Jim Corbett National Park (the oldest national park of India) at Ramnagar in
Nainital District, and Valley of Flowers National Park and Nanda Devi National Park in Chamoli
District, which together are a UNESCO World Heritage Site
Site.. A number of plant species in the valley
are internationally threatened, including several that have not been recorded from elsewhere in
Uttarakhand. Rajaji National Park in Haridwar District and Govind Pashu Vihar National Park and
Sanctuary and Gangotri National Park in Uttarkashi District are some other protected areas in the
state.
Page 39
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Leopards are found in areas which are abundant in hills but may also venture into the lowland
jungles. Smaller felines include the jungle cat, fishing cat, and leopard cat.. Other mammals include
four kinds of deer (barking, sambar
sambar, hog and chital),slot hand Himalayan black lack bears,
bears Indian gray
mongooses, otters, yellow-throated
throated martens
martens, bharal ,Indian pangolins,, and langur and rhesus
monkeys. In the summer, elephants can be seen in herds of several hundred. Marsh crocodiles
(Crocodyluspalustris),gharials(Gavialisgangeticus
Gavialisgangeticus)) and other reptiles are also found in the region.
Local crocodiles were saved from extinction by captive breeding programs and subsequently re re-
released into theRamgangariver.Several
river.Several freshwater terrapins and turtles like the Indian sawback
turtle (Kachuga tecta),brahminy
brahminy river turtle turtle(Hardellathurgii),
), and Ganges softshell
turtle(Trionyxgangeticus)) are found in the rivers. Butterflies and birds of the region in clude
cludered
Helen(Papiliohelenus), the great eggfly (Hypolimnosbolina), common tiger((Danausgenutia),pale
wanderer(Pareronia
Pareronia avatar avatar
avatar),jungle babbler, tawny-bellied babbler ,great
great slaty woodpecker,
woodpecker
red-breasted parakeet, orange-breasted
breasted green pigeon and chestnut-winged
winged cuckoo.
cuckoo In 2011, a rare
migratory bird, the bean goose,, was also seen in the Jim Corbett National Park.
4.5.10 Culture
Culture and people are very closely associated with each other. The
term ‘culture’ refers to the complex collection of knowledge, ffolklore,
language, rules, rituals, habits, lifestyles, attitudes, beliefs, and
customs that link and give a common identity to a particular group of
people at a specific point in time.
Page 40
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
All social units develop a culture. Thus it is the inhabitants of a specific region that collectively
contribute to form that extraordinary cornucopia of life we call culture.
“In those lovely valleys there is still the romance and poetry of life:
each tree has its god, each bush its sspirit” – So wrote the 19th
century British anthropologist and surveyor Charles A. Sherring,
describing a fair part of Uttarakhand, in his great research ‘Western
Tibet and British Borderland’.
Collective celebrations become the order of the day – the many fairs and festivals bear testimony to
this. These fairs have now become remarkable stages for all sort of uncluttered social, cultural and
economic exchange. Visitors from far and wide are drawn to these events in mu
multitudes.
ltitudes.
There are a number of religious events attached to River Ganga - the holiest of all the rivers. Daily
aartis performed every evening at the banks of the Mother
Mother-River in Haridwar and Rishikesh present
a memorable sight to behold when the star
star-studded
studded sky seems to be reflecting the serene waters of
the river upon the surface of which float countless diyas offered to the goddess. The Kumbh Mela
Page 41
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Overwhelming natural panoramas accompany the pilgrims taking part in the Nanda Devi Raj Jaat and
Kailash Mansarovar Yatras. The shrines of Hemkund Sahib and Na Nanakmatta
nakmatta Sahib are visited by
thousands of Sikh devotees while a symbol of national integration - the Dargaah at PiranKaliyar
Sharif, holds a significant religious rank for Muslims and people from other faiths alike.
Legends, myths and anecdotes galore in the state of Uttarakhand which has in turn been bestow
bestowed
by the richest, holy rivers and the most esteemed mountains. Series of legends and tales are
intricately woven around the sacred shrines, temples and rivers by simple hearted, god
god-fearing
people that simultaneously reflect the socio
socio- cultural diversity of the state.
4.5.11 Economy
The Uttarakhand state is the second fastest growing state in India. It's gross state domestic product
(GSDP) (at constant prices) more than doubled from ₹24,786 crore in FY2005 to ₹60,898 crore in
FY2012. The real GSDP grew at 13.7% (CAGR) during the FY2005–FY2012
FY2012 period. The contribution of
the service sector to the GSDP of Uttarakhand was just over 50% during FY 2012. Per capita income
in Uttarakhand is ₹1,03,000 (FY 2013) which is higher than the national average of ₹74,920 (FY201
(FY2013).
According to the Reserve Bank of India, the total foreign direct investment in the state from April
2000 to October 2009 amounted to US$46.7 million.
Like most of India, agriculture is one of the most significant sectors of the economy of Uttarakhand.
Basmati rice, wheat, soybeans, groundnuts, coarse cereals, pulses, and oil seeds are the most widely
grown crops. Fruits like apples, oranges, pears, peaches, litchis, and plums are widely grown and
important to the large food processing industry. Agricul
Agricultural
tural export zones have been set up in the
state for leechi, horticulture, herbs, medicinal plants, and basmati rice. During 2010, wheat
production was 831 thousand tonnes and rice production was 610 thousand tonnes, while the main
Page 42
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
cash crop of the state, sugarcane, had a production of 5058 thousand tonnes. As 86% of the state
consists of hills, the yield per hectare is not very high. 86% of all croplands are in the plains while the
remaining is from the hills.
Other key industries include tourism and hydropower, and there is prospective development in IT,
ITES, biotechnology, pharmaceuticals and automobile industries. The service sector of Uttarakhand
mainly includes tourism, information technology, higher education, and banking.
During 2005–2006,
2006, the state successfully developed three Integrated Industrial Estates (IIEs) at
Haridwar,
aridwar, Pantnagar, and Sitarganj; Pharma City at Selaqui; Information Technology Park at
Sahastradhara (Dehradun); and a growth centre at Siggadi (Kotdwar). Also in 2006, 20 industrial
sectors in public private partnership mode were developed in the state
state.
4.5.12 Industries
Having tremendous growth potential, Uttarakhand Business and Industries sector is thriving across
the state. The Uttaranchal Industries sector mainly consists of Sugar Mills, Cloth Mills, Paper Mills,
Flour and Rice Mills, Pharmaceuticals, aandnd Stone Rolling Mills etc. The Agricultural Sector, on the
other hand, consists of Dairy farms, Rice and Wheat Production, Fish Farming, Poultry Farming,
Floriculture, Horticulture, and Pickle and Sauce Industries, which are flourishing in the state. Besi
Besides,
Handicrafts, handlooms, wool based industry, khadi and village industry, waxed based industry are areo
ther traditional industries spread across the state. The state government is also assisting to establish
a number of small and medium size agro parks, ffood ood parks etc., to aid the agriculture and food
processing industry to provide common infrastructure facilities for storage, processing, grading and
marketing.
The size of Uttarakhand's Economy as measured by its Gross State Domestic Product (GSDP) for
2011
11 (Financial year ending March 2011) is estimated at SIDCUL, the State Industrial Development
Corporation of Uttarakhand has established seven industrial estates in the southern periphery of the
state, while dozens of hydroelectric dams are being built in the upper reaches.
The primary sector includes conventional components like agriculture, cultivation, and mining
Page 43
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
activities. The composition of the primary, secondary and tertiary sectors is as follows:
Primary sector constituting Agriculture; Forestry & Logging; Fisheries; Mining and
Quarrying
Secondary sector constituting Manufacturing; Construction; Electricity, Gas & Water
Supply
Tertiary sector constituting Transport & Communication; Trade, Hotels & Restaurants;
Banking & Insurance; Real Estate, Own
Ownership
ership of Dwellings and Business Services; Public
Administration; and Other Services.
The state is essentially driven by the tertiary sector. Tourism is one of the key components with a
major contribution to the economy primarily due to the state’s natura
naturall beauty and the potential to
offer varied forms of activities ranging from religious to adventure tourism. But, by and large, the
Tourism Industry remains as one of the major industries of the state and generates most revenue for
the Uttaranchal Business and Economy. Hotel Industry, Travel Agencies, and all hospitality related
business are other subsidiaries of the tourism industry are also growing as potential Uttaranchal
Industries.
4.5.13 Transportation
Uttarakhand has 28,508 km of roads, of which 1,328 km aare re national highways and 1,543 km are
state highways. The State Road Transport Corporation (SRTC), which has been reorganized in
Uttarakhand as the Uttarakhand Transport Corporation
Corporation,, is a major constituent of the transport
system in the state. The Corporat
Corporation
ion began to work on 31 October 2003 and provides services on
interstate and nationalized routes. As of 2012, approximately 1000 buses are being plied by the
"Uttarakhand Transport Corporation" on 35 nationalized routes along with many other non non-
nationalized
ed routes. There are also private transport operators operating approximately 3000 buses
on non-nationalized
nationalized routes along with a few interstate routes in Uttarakhand and the neighboring
state of U.P. For travelling locally, the state, like most of the coun
country, has auto rickshaws and cycle
rickshaws.. In addition, remote towns and villages in the hills are connected to important road
junctions and bus routes by a vast network of crowded share jeeps.
Page 44
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
As over 86% of Uttarakhand's terrain consists of hills, railway services are vevery
ry limited in the state
and are largely confined to the plains. In 2011, the total length of railway tracks was about 345 km.
Rail, being the cheapest mode of transport, is most popular. The most important railway station in
Kumaun Division of Uttarakhand is at Kathgodam,, 35 kilometers away from Nainital. Kathgodam is
the last terminus of the broad gauge line of North East Railways that connects Nainital with Delhi,
Dehradun, and Howrah. Other notable railway stations are at Pantnagar, Lalkuan and Haldwani.
Dehradun railway station is a railhead of the Northern Railways. Haridwar station is situated on the
Delhi–Dehradun and Howrah–Dehradun
Dehradun railway lines. One of the main railheads of the Northern
Railways, Haridwar Junction Railway Station is connected by b
broad
road gauge line. Roorkee comes under
Northern Railway region of Indian Railways on the main Punjab–Mughal
Mughal Sarai trunk route and is
connected to major Indian cities. Other railheads are Rishikesh, Kotdwar and Ramnagar linked to
Delhi by daily trains.
4.5.14 Tourism
Mussoorie and Environs: The colonial “Queen of the Hills” is still on of the best hill
stations in the state. During colonial time it was the favoured holiday location for the
rulers. Around 12 - 14 km from Mussoorie on NH 123 towards Barkot is located
Kempty Falls which is a 40 40-foot
foot perennial waterfall on the downside of the road
cascading into a number of pools at the valley floor.
Dhanaulti and Environs: Located 24 km fromom Mussoorie, Dhanaulti is an attractive and
sleepy mountain village. Its main claim to fame is the attractive forested surroundings
dominated by Himalayan Deodar Cedars.
Haridwar: Haridwar Town is located around 200 km north east of Delhi and 54 km
south of Dehradun and is probably the most important gateway to Uttarakhand by rail
and road. Haridwar is the gateway to the four pilgrimages of Uttarakhand.
Rishikesh / Muni Ki Reti: Rishikesh is located 25 km north of Haridwar at the
confluence of the Ganges aand
nd Chandrabhaga Rivers and at the foot hills of the Middle
Himalayan Region. It is famous for adventure sports like water rafting, bungee
jumping and nature and rejuvenation centers.
Rajaji National Park: The National Park is an 830 square km pristine and beautiful
natural forest environment located south of Dehradun
Nainital and the Lake District: Nainital is the “centre” and focal point of the Kumaon
Lake District, combining around 15 lakes of various sizes in an area of approximately
Page 45
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
600 sqkm surrounding Nainital mainly east and south of the city.
Corbett National Park East: is one of India’s most unique nature and wild life reserves
with an area of 1288 square km
Mukteshwar: Mukteswar is a quaint village getaway at 2290 m altitude views east
towards the Ramgarh Valley and its many fruit orchards
Ramgarh: At almost 1800 m altitude in the Gagar Mountain Range a picturesque quiet
place dominated by some of the highest altitude apple orchards in the state.
Lansdowne: is a famous Cantonment Town and the origin
original
al home of the Gharwal
Rifles, a legendary military force.
Gangotri: the Town and Temples, Bhojbasa “Tourist Centre”, Gaumukh and the source
of the Ganges, the Gangotri Glacier and Tapovan
Dayara Bugyal: and the Barsu – Raithal village cluster. An upcoming ski and soft
adventure and village tourism destination.
Tehri Lake: the 50 – 60 km long reservoir created by stemming up the waters of
Bhagirathi River, the surrounding rural village clusters in the hills and the dam at the
south- eastern end of the lake. New Tehri Town is a modern hill township located over
Tehri Lake on a mountain ridge at 1600 maltitude.
Binsar Wild Life Sanctuary: This is a unique high altitude protected forest
environment with an outstanding view to greater Himalayas
Almora: This is a historic town with many tourism resources, a thriving service center
and District Capital with many permanently residing foreigners.
Ranikhet: This is a famous hill station amid lush highlands and dense forests. Founded
as a major Cantonment in the late18
late1860’s.
Kedarnath Town: Its imposing Temple which is one of the twelve most sacred places
dedicated to Shiva is attractively set in a small Valley surrounded by the Mandakini
and Saraswati Rivers.
Badrinath Town: Its 8th century Temple are remotely situated on the brink of the
Alaknanda River and is the end point of NH 58 from south. The last rural settlement
before the Tibetan border is 3 km north of the town.
The Valley of Flowers National Park: This is a unique and pristine natural environment
10 km in length
gth and 2 km wide located from 3658 to 3962 m altitude with an
extraordinary flora and fauna.
Nanda Devi National Park: This is a unique and spectacular mountain range with
some of India’s highest peaks and is a UNESCO World Heritage site with limited acce
access
for visitors. Nanda Devi is a sacred Peak surrounded by a “protective” ring of 12 high
Mountains and numerous temples.
Devaprayag Town: It is located at the holiest of the 5 confluences of the Alaknanda
River and is beautifully set at the confluence between Bhagirathi, Alaknanda and
Upper Ganges
The Yamunotri Char Dham: This is the origin of the Holy Yamuna River lying next to
Page 46
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
the Indo-Chinese
Chinese border.
Auli: Auliis renowned for the fascinating ski resorts and stunning natural vistas. At
an averagee height of 2800 meters it is famous for winter sports
Pithoragarh District having its entire northern and eastern boundaries being international, assumes a
great strategic significance and, obviously, is a politically sens
sensitive
itive district along the northern frontier
of India. Being the last district adjoining Tibet, it has tremendous strategic importance as the passes
of Lipulekh, Kungribingri, Lampia Dhura, Lawe Dhura, Belcha and Keo, open out to Tibet. The breath
taking beauty of Pithoragarh - Himalayas, wide expenses of grassy meadow, perennial streams
roaring down the zig-zagzag course, a stupendous variety of flora and fauna, above all, pure nature yet
unsullied, seem to beckon the beholder into their folds, into a charmed w world
orld of virgin beauty.
The Pithoragarh town is located at a height of 1645 meters above sea level. The district lies
between 29.4° to 30.3° North latitude and 80° to 81° East longitude along the eastern and
southern part of the central Himalayas with Indo
Indo-Tibetan
Tibetan watershed divide in the north and
the Kali river forming a continuous border with Nepal in the east. The Pithoragarh district is
surrounded by the national boundaries of Almora, Champawat, Bageshwar and Chamoli
districts
istricts and extends over an area of 7,217.7 sq. Kms.
Pithoragarh town, being in a valley, is relatively warm during summer and cool during winter. During
the coldest months of December and January, the tropical and temperate mountain ridges and high
locations receive snowfall and have an average temperature of 5.5 5.5–8.0
8.0 °C (41.9–46.4
(41.9 °F).
Pithoragarh district has extreme variation in temperature due to the large variations in altitude. The
temperature rises from mid-March
March through mid mid-June.
June. The areas above 3,500 metres (11,500 ft)
remain in a permanent snow cover. Regions lying at 3,000 3,000–3,500
3,500 metres (9,800–11,500
(9,800 ft) become
snowbound for four to six month
months. At places like the river gorges at Dharchula,, Jhulaghat, Ghat and
Sera, temperatures reach 40 °C (104 °F). The annu annual
al average rainfall is 36.7 centimeters (14.4 in)..
in)
After June the district receives monsoon showers. Winter is a time for transhumance – the seasonal
migration of the Bhotiya tribe with their herds of livestock to lower, warmer areas.
4.6.3 Literacy
Page 47
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
There has been a steady improvement in basic education scenario. As per the provisional District
Elementary Education Report Card for the year 2010 2010-11,11, 97.2 percent of the students were able to
complete primary education and transit to upper primary level. At primary level, there are a total of
1,421 schools in this District but only 45 schools till Higher Secondary level. A majority of the schools
are Government funded and enrollment over the years has seen a marginal upward trend at the
upper primary level. Only in few schools though, the medium of instruction is English
English.
For higher education, there are six Government degree colleges and one post post-graduate college in
Pithoragarh. Degree colleges in this District offer courses in arts, sciences and commerce streams.
For the year 2011-12,
12, the total students enrolled in these colleges were 4,584. In terms of streams,
there is higher proportion of students in arts, followed by commerce and science. Data published on
the Directorate of Higherr education (DHE) website shows that maximum enrolment is in Hindi
literature followed by political science and geography
4.6.4 Demography
Pithoragarh is home to 4.80 percent of the total population of the State. It is the eighth most
populated District of the State and has had a decadal growth rate in population of 5.13 percent in
the total population compared to the population as per Census 2001. Approximately, 85.69 percent
of the population lives in rural areas and rest of the population lives in urban aareas.
reas.
According to Census 2011 (provisional data), the sex ratio in Pithoragarh was 1,021 females per
1,000 males. Pithoragarh has a population of 4.86 Lakh of which males and females were 2.40 Lakh
and 2.45 Lakh respectively. The population density of Pi
Pithoragarh
thoragarh was 69 in 2011 making it the third
Page 48
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Primary Sector
Page 49
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
As per recent data (2012-13) 13) provided by District Agriculture Officer (DAO), around 8 percent of the
total cultivatable land is irrigated, rest is rain
rain-fed.
fed. Wheat, Rice, Maize, Rajma and Barley remain the
major crops across the District. In terms of productivity, the other main crops are Manduwa and
Lentil. In the past 3-44 years, there has been diversification in agricultural activities with vegetables and
fruits. Due to the efforts of the Krishi Vigyan Kendra, there has been improvement in productivity of
the crops.
4.6.6 Industrialization
4.6.7 Hospitals
The rural health care system is a three tier structure. It has “Sub
“Sub-center”
center” at the most peripheral level,
“Primary Health Centre” at the intermediate level and “Community Health Centre Centre” at the secondary
level. The population covered by a “Sub Centre”, “Primary Health Centre” and “Community Health
Centre” are “3,000-5,000”,
5,000”, “20,000
“20,000-30,000” and “100,000”, respectively. In
Addition, there are Private Voluntary Healthy Facilities, also. As per Uttarakhand government
organizational set up, the District is headed by a District Magistrate, who is also the chair person
of the Integrated District Health Society of Pithoragarh district. The District health set up of
Page 50
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
There are 253 government health care facilities in the district, as can be seen fro
from the table given
below.
Category Number
District Hospitals 01
No. of CHC 04
No. of PHC 04
No. of APHC 14
Ayurvedic Hospital 57
Homeopathic Hospitals 05
The salient features of land use data for Pithoragarh district is given below:
Page 51
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Pithoragarh is known for its Kandali festival that is essentially celebrated by the Rung tribe when the
Kandali plant comes to bloom, which is once in twelve years. The area is full of local eateries, most of
which are designed to be an outdoor affair making the most of Pithoragarh’s scenic beauty. Kumauni
cuisine is famous for its dairy touch in most of the dishes along with clarified butter. Lentils are a
popular pick for most of the dishes too and some typical Kumauni dishes are Chainsoo (black gram
lentil), Kafuli (spinach gravy), Phaanu (lentils), Roat (sweet bread) and Jholi (tomato & potato gravy).
4.6.10 Agriculture
Department of Agriculture was set up in 1875. Initially, the Department of Agriculture was limited
only to compiling statistics and to establish model form. In 1880, it was attached to the Department
of Land Records. After implementation of Govt. of India Act 1919 and as a result in order to establish
State Agriculture Policy, the Agriculture Department came into existence on 01.12.1919. After
Uttarakhand State came into existence in the yea yearr 2000, Uttarakhand Govt. had notified the
restructuring of the Agriculture Department on 02.08.2003.s
4.6.11 Soil
The Lesser Himalayan range iss mainly composed of highly compressed and altered rocks like granite,
amphibolite, quartzite etc. and a major part of it is under forest. Intermittent sparse patchy terraced
cultivation is also practiced on fairly steep hill slopes whereas dry and wet cul
cultivation
tivation are prevalent
on the uplands and low-lying
lying valleys respectively. The broader valley slopes dominantly have deep,
well drained, fine-loamy,
loamy, moderately acidic and slightly stony.
Page 52
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
4.6.12 Communication
Page 53
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
5.1 Introduction
The Consultants have conducteducted different types of field studies, engineering surveys and
investigations to gather data and information necessary for project preparation. The aim of the
investigations was to develop an adequate supportive database for Selecting and preparing the momost
appropriate proposal to meet the functional and structural efficiency and safety requirements. The
engineering investigations and surveys have been carried out in line with the specifications laid out
in the TOR. The basic data and results of investigat
investigation
ion are compiled and included in Volume-II
Volume of this
Report.
a) Road Inventory
b) Pavement Condition Survey
c) Inventory and Condition Survey of Existing Bridges, Culverts and Other Structures
d) Alternative Alignment Study for Bypasses
e) Topographic Survey
f) Traffic Survey
g) Axle Load Survey
h) BBD Survey
i) Pavement Investigation
j) Material Investigation
k) Sub Soil Exploration
Page 54
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Rut depth, measured transversely across the outer wheel paths using 22-meter-long
long straight edge and
graduated wedge. Shoulder and embankment conditions by visual means and the existence of
distress modes and extent thereof were noted. The field data has been recorded at 200m interval.
5.4 Inventory and Condition Survey of Existing Bridges, Culverts and Other Structures
Alternative alignment study was generally conducted to find out the best option to avoid the
congestion area. In this package, no bypass option has been explored.
Page 55
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
5: ENGINEERING SURVEY
Y AND INVESTIGATION
NIL
The specific objective of the topographical survey is to delineate accurately the complete existing
natural and man-made
made features, so as to study and develop the existing road to 2 lane with paved
shoulder of Bharatmala Project––Tawaghat to Kali Mandir (Design Length – 58.063 Km), creating an
accurate Digital Terrain Model, which is also a fundamental requirement to design the highway
through latest software. The detailed topographi
topographical
cal survey for the new and existing road had been
carried out in consonance with the procedure outlined in the TOR using Total Station and Auto Level.
The survey was performed over 20m (in general) on either side w.r.t. the proposed center line or up
to the existing Right-of-Way
Way (ROW) line on either side, whichever is more. The survey involved the
following sequential steps:
(2) Establishing Bench Marks:: in order to ensure locational and directional as well as vertical control
along the project road, bench mark pillars (BM) were established at about 250m interva
interval, in general,
depending upon visibility between two pillars. This bench mark pillars were connected to the GPS
pillars.
(3) Traversing and levelling:: has being done to connect the reference BM pillars.
(3) Cross-section
section Surveying/Detailing
Surveying/Detailing: Detailed cross
ss sections are surveyed at 50 interval, in general,
using Total Station. The cross sections are extended up to the survey limits mentioned earlier. The
main features captured in the cross
cross-sections were:
Page 56
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
standardization of works of different survey teams and to facilitate further CAD works, a rational
coding system has been developed and used. The survey data collected in the field ha has been
downloaded in text file format and converted to graphic files using suitable software.
Page 57
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Following traffic surveys were conducted at site to assess the present and future traffic on the
project highway.
The basic objective of the investigation was to form a database for characterization of existing
pavement. The investigation was carried out by digging trial pits staggered left/right.
Trial pits of size 1m x 1m x 1m were dug at the pavement shoulder interface, extending through the
pavement layers down to the subgrade level. Pits were at least 300 mm within the carriageway. Pits
were made in such a way that half of the pit remains within the carriage
carriageway
way and the other half (in
the shoulder), ensuring minimum damage to the original pavement and disruption to the traffic.
Large test pits are done on both sides of the project road were dug at the pavement shoulder
interface extending through the pavement layers down to the sub-grade level
The following sequence of operation was followed for each large test pit:
• Manual excavation of 1.0 m x 1.0 x1.o m and pit down to subgrade level .The
thickness of the different pavement layers were measured and type of ma material
examined and logged from three sides.
• Field (in-situ)
situ) dry density using sand replacement method as per IS 2720: Part 28 was
carried out at the subgrade level.
• Adequate sample in sealed polythene bag were collected for classification tests as
per IS: 2720 (relevant parts)
- Field moisture content
Page 58
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
One sample of 40 kg was collected from the top 300 mm of subgrade for the following laboratory
tests (as per IS: 2720)
After the completion of field tests and collection of samples, the pits were backfilled with
the excavated materials and compacted suitably so as not to jeopardize the smooth
movement off traffic of the existing road.
The existing pavement structure mostly comprises of three layers, namely bituminous layer,
base course and sub-base
base course. During the present investigation the surfacing course is reported,
on the whole, as bituminous course (BC). The base course comprises of stone, gravel, cobble mix
with sand only and few stretch present in WBM mix . The subsub-base
base course consists mainly occasional
presence of sand layer along the stretches. The total thickness of the pavement varies fr
from 265 mm
to 300 mm. The thickness of the bituminous surfacing layer varies from 55 mm to 90 mm thick, base
course varies from 195 mm to 240 mm.
The existing pavement structure mostly comprises of two and three layers, namely
bituminous layer 30mm to 100 mm thick, base course and sub
sub-base
base course 260 to 350 mm thick.
The laboratory test results consist of gradation, Atterberg limits, field moisture content,
Field dry density (FDD), compaction characteristics (maximum dry density and optimum
moisture content relationship as per heavy compaction), CBR (soaked) etc. for the subgrade
soils underneath the existing pavement
Page 59
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
%. The result indicates that the maximum dry density of existing sub sub--grade soil is greater
3
than 17.5 kN/ m at alll chainages which satisfies the unit weight requirement of sub sub-grade
soil as specified by MORT&H.
5.9.7 CBR of existing sub-grade
grade soil
California Bearing Ratio (CBR) tests were carried out on the pit samples in the
laboratory as per standard procedures. At optim optimum
um moisture content (OMC) soil samples
were compacted at three different energy levels corresponding to 10 blows, 35 blows, 65
blows as per IS:2720 (Part 8). These compacted soils at different compaction levels were
tested after immersion in water for four days. Soaked CBR at 97% maximum dry density
(MDD) has been interpolated from CBR CBR-dry
dry density curve. The Stretch I soil, soaked CBR
value at 97% MDU ranges from 9.0 % to 11.0 %.
5.9.8 Objective
Source locations indicating places, kilometerage, availability and the status whether in
operation or new source.
Access to source, indicating the direction and nature of the access road i.e. left/ right of
project road, approximate lead distance from the gravity center and type of access
road.
Ownership of land/ quarries, either government or private.
Test results, indicating the quality of materials with respect to their suitability in
construction.
Probable use indicating the likely use of materials at various stages of construction
work i.e. fill material, sub
sub-grade, sub-base,
base, base, bituminous surfacing and cross
drainage structures.
The potential sources of construction materials were selected from consideration of the
availability and suitability of the materials, easy access to the source and minimum
hauling distance from the source in order to make the construction economical and
feasible as far as possible. The samples from various identified sources have been
collected for laboratory testing as per IRC/MORT&H/BIS standards.
Cement, bitumen, steel are the manufactured materials. Cement and steel with I.S. certification are
indigenously available in abundance from the manufacturers. Bitumen of VGVG-10,VG
10,VG-20,VG-30&VG-
40 viscosity grade and emulsion are available from IOCL Mumbai, within the vicinity of project road
.The regular supply of bitumen and cement can be satisfactorily met by advance agreements with
Page 60
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
5.10.2 Cement
Cement to be used in the construction work shall be any of the following types with the prior
approval of the Engineer:
The chloride contentt in cement shall in no case exceed 0.05 percent by mass of cement. Also, total
sulphur content calculated as sulphuric anhydride (SO3) shall in no case exceed 2.5 percent and 3.0
percent when tri-calcium
calcium aluminates present by mass is upto 5 or greater tha
than
n 5 respectively. Good
quality Cement is locally available.
5.10.3 Steel
For plain and reinforced concrete (PCC and RCC) or pre pre-stressed
stressed concrete (PSC) works, the
reinforcement/un-tensioned
tensioned steel as the case may be shall consists of the following grades of
reinforcing bars as shown in Tabl
Table 5.1are
are available with local stockists. Before incorporation into the
work, steel shall be got approved by the engineer.
5.10.4 Bitumen
Page 61
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
5.10.5 Water
Detailed survey for locating water sources for the use in concrete works and for construction
of road works were carried out in the vicinity of the project road. The most suitable source
of water was which are in close proximity to some points of the alignment of the rivers rivers,
along with numerous nallas and irrigation canals cross the alignment at suita
suitable intervals.
However, to facilitate construction works it is always advisable to install wells with due
permission from authority at suitable places for obtaining water for construction purposes.
The hydrological study aims at estimating the peak discharge of the flood gener
generated
ated by the run-off
run of
rainfall within the catchment area. The hydrological study requires:
Data Collection
Topographic surveys shall be done at all the major and minor river crossings with a view to obtain
the cross section of the rivers at the center line of the road and up to a reasonable distance at
upstream and downstream. The High Flood Levels (HFL) shall be obtained from existing flood marks
or ascertained from enquiry with local knowledgeable persons. There are two major and 46 minor
bridges alongg the project corridor.
The characteristics of the catchment areas has been ascertained from available information (which
Page 62
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
will be verified from Survey of India topo sheets, to a scale of 1: 50,000 from which, catchment area
at the proposed bridge site, len
length
gth of the stream and fall in elevation from originating point to the
point of crossing, could be determined). Slope of the stream shall be determined from the contours
on the topo sheets.
For streams having catchment area more than 25 sq. km, CWC Report - Flood Estimation Report for
Lower Godavari sub zone 3(f) in which the project site lies has been obtained. This report is for
determining the characteristics of peak rainfall regimes. The report has been jointly prepared by
CWC, MOST, Ministry of Railways and IMD and contains all the rainfall data required for estimation
of design discharge for returns periods by applying the Synthetic Unit Hydrograph approach. The
streams having catchment area less than 25 sq. km, IRC: SP
SP-13-2004
2004 to be followed.
The design flood of a specific return period for fixing the waterway visvis-versa
versa the design HFL of
bridges depends upon their size and importance to ensure safety as well as economy. The design
discharge should be the maximum flood on rec record
ord for a period not less than 50 years. This was
accepted by IRC. IRC 5-2015- Section I General Features of Design specify that the waterway of a
bridge is to be designed for a maximum flood of 50 years return period.
The following methods have been used to estimate the peak discharge for bridge sites on major and
minor streams:
Empirical methods
Rational Method
Area velocity method
SUH method
Empirical Methods
Discharge is calculated by Empirical Methods using catchment areas from the available topo
topo-sheets.
Dickens Formula
Q = C M3/4
M = Catchment area in sq km
Page 63
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Ryve's formula
Q = CM2/3
C = Coefficient of run-off,
off, depends upon annual rainfall
Rational Formula
Discharge is calculated by Rational Method for the Catchment area’s less than 25 sq Km. The
Rational Method uses Rainfall Run off co
co-relation
relation procedure for estimation of flood. This method is
very widely
ly used for urban runoff computations, and is also recommended by CPHEEO.
C = Runoff Coefficient
The runoff coefficient, C, depends on nature of soil, soil cover and location of the catchment, and is
given in Table 5.2.
Page 64
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
L
t c 0.9 0.1 0.2
M S
Rainfall intensity (I) in cm/hr, to be used in the rational formula will be computed based on
the following formula.
I = (R50 (tc))/ tc
Q=AxV
Page 65
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
V = Velocity in m/sec
P = Wetted perimeter in m
n = Rugosity Co-efficient
Flood discharges es are estimated in different methods as explained above. The values
obtained are compared. The highest of these values is adopted as Design Discharge Q, provided it
does not exceed the next highest discharge by more than 50 percent. If it exceeds, it is rrestricted to
that limit (As per Article 7.1 of IRC: SP: 13
13-1998).
Page 66
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Traffic is one of the key components of a Highway feasibility study. As part of Feasibility study, a
systematic methodology has been followed to assess the characteristics of the traffic on the project
road before and after the proposed improvement and tolling. The details pertaining to the data
collection, primary as well as secondary, and results from its analysis are presented in the followin
following
sections. This section presents the existing traffic characteristics of the project road and forecasted
traffic.
A comprehensive methodology has been evolved to carry out the work as per the scope of traffic
studies. A stepwise methodology is presented in the below chart.
Page 67
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Page 68
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Road network surrounding the project road has been studied in details to appreciate the regional
connectivity and to select appropriate locations for traffic count stations. The connectivity, in terms
of locations is briefly explained in the following paragraphs.
The Site of the Single Lane Project Highway comprises the section of Highway. Project
road starts from Km. 0+000 at Tawaghat village (Design Chainage 56+935) and traverses a length of
38.812km and ends Km.19+170 at Budhi Village (Design Chainage 95+748) And starts at End of
Tunnel Portal (Design Chainage 113+828) and traverses a length of 19.25km and ends at Kali
Mandir (Design Chainage 133+078
133+078) . The Project Highway is part of NH-09.
09. The stretch passes
through winding hilly terrain of Himalayas and sight distance is restricted at places due to sharp
horizontal curves and vertical cuts slopes.
Information
ation about traffic is indispensable for any highway project since it would form the basis for
the design of the pavement, fixing the number of lanes and economic appraisal of the project, etc. In
order to limit number of cross--sections through the length of the project, the section having the
same traffic intensity (in PCU per day) will be considered as a homogenous section. The main criteria
in selection of homogenous section for this project were the traffic volume and no. of lanes.
Based on the traffic flow characteristics, project road has been divided into 2 homogenous sections
and the classified volume count surveys carried out accordingly.
Page 69
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
The important dispersal/generation locations identified along the project road sections include:
Jauljibi
Kalika
Baluwakot
Dharchula
Traffic survey stations have been selected by the Consultant on the basis of
understanding of the road network as well as consideration of the following aspects:
To capture the traffic flow characteristics and the travel pattern of the users passing through the
project road and other characteristics related to miscellaneous requirements as per ToR following
primary surveys were conducted.
7-days
days classified traffic volume count survey at two locations on the project road.
3-days
days classified traffic volume count survey at one location on the project road.
1 Day (12
12 hours) OD Survey at one location on the project road.
1 Day (12 hours) Turning Movement Surveys at one major intersection on the project
road.
1 Day (12Hours) Pedestrian Count Surveys at two major town locations.
Speed & Delay Survey - 2 trip of project road
Page 70
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Brief description and analysis of each of the above surveys are presented in the following sections. The
schedule of all traffic surveys is presented in Table 6.1.
17-09-2017
Km 63+800 of 3 Days x 24
Jauljibi to 23-09-
SH-29 Hours
Classified To know the present 2017
Volume Count traffic scenario of road 16-09-2017
Km 90+400 of 7 Days x 24
Dharchula to 22-09-
SH-29 Hours
2017
To know major
Pedestrian Jauljibi & 1 Day x 12
pedestrian movement 2 Town Area 20-09-17
Count Survey Dharchula Hours
area
Page 71
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
For carrying out the traffic survey, vehicle classifications, as given in Table 6.2, were
adopted. The vehicle classification used is based on IRC
IRC-64-1990.
Page 72
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Specially trained enumerators were deployed for counting traffic under the supervision of
experienced traffic engineers. For the purpose of counts, a day has been divided into two shifts of 12
hours each and different groups of enumerators with a supervisor were assigned for each shift. The
count data has been recorded at 15-minute
minute intervals for each vehicle group for each direction of
travel separately. Trained enumerators were deployed for counting and recording by making tally
marks in the five-dash system.
Table 6.3:: Vehicle Classification and PCU Factors Used in the Study
Vehicle Type PCU Factor
Fast Moving Vehicles
Car, jeep and van (New and Old technology) 1.0
Taxi 1.0
Three wheeler 1.0
Two wheeler 0.5
Mini bus 1.5
Bus (Private & Government classified) 3.0
Light goods vehicle (Passenger & Goods carrying) 1.5
Truck 2-axle 3.0
Truck 3-axle 3.0
4-6 Axle Truck 4.5
> =7 Axle Truck 4.5
Agricultural tractor 1.5
Agricultural tractor with trailer 4.5
Slow Moving Vehicles
Cycle 0.5
Cycle rickshaw 2.0
Animal/Hand drawn cart 6.0
The directional classified traffic volume counts, observed at the count stations, are
analyzed to obtain:
Page 73
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
The summary of ADT, in terms of each class, vehicles and PCUs at the three count stations on the
existing and adjacent road are given in Table 6.4.. ADT (PCU) is 595 at Km 63+800 of SH-29SH near
Jauljibi and 1374 at Km 90+400 of SH SH-29
29 near Dharchula on the project road. The classified
directional traffic observed at each count location and summary is given in Annexure 6.1 to 6.2.
Taxi 0 0
Two-wheeler
wheeler 126 566
3wh(pass) 1 0
Minibus 4 3
School Bus 2 18
Bus (Govt) 7 11
Bus (Pvt) 0 0
3wh (Goods) 0 0
LMV 0 0
LCV 81 156
2-Axle
Axle 10 10
3-Axle
Axle 1 0
4-Axle
Axle and 6 Axle 0 0
7 Axle Above 0 0
Tractor 0 0
Cycle 0 3
Cycle Rickshaw 0 0
Animal cart 0 0
Others 0 2
Page 74
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Car/Jeep 7 63
Bus 1 4
Toll exempted vehicle
LCV 1 50
Truck 5 34
Daily variation of traffic at each count locations is shown in Table 6.5.. The variation from average is
ranging from -11.29% to o +12.49% at Jauljibi, -4.22%
4.22% to +5.54% at Dharchula. Daily variations of traffic
at different locations are presented in Figure 6.2 and Figure 6.3.
Day4 1366
Day5 1414
Day6 1350
Day7 1365
Page 75
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Analysis has been carried out to understand hourly variation and peak hour traffic characteristics.
The hourly distribution of traffic at different locations is illustrated in Figure 6.4 and Figure 6.5.
Page 76
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
70
Hourly Variation of Traffic at Km 63+800
Passenger Vehicles Freight Vehicles
60 Total Fast Moving Vehicles Total Slow Moving Vehicles
50
No. of Vehicles
40
30
20
10
0
10:00-
11:00-
12:00-
10:00
7:00-8:00
8:00-9:00
1:00-2:00
2:00-3:00
3:00-4:00
4:00-5:00
5:00-6:00
6:00-7:00
9:00-
11:00
12:00
1:00
Time Period
120
No. of Vehicles
100
80
60
40
20
0
10:00-11:00
11:00-12:00
7:00-8:00
8:00-9:00
1:00-2:00
2:00-3:00
3:00-4:00
4:00-5:00
5:00-6:00
6:00-7:00
9:00-10:00
12:00-1:00
Time Period
The peak hour factor and Peak hour PCUs details of each location are give
given in Table 6.6.
Page 77
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
c) Directional Distribution
Directional distribution of traffic has been analyzed. The analysis reveals that there are no tidal flows
on the project road. The directional distribution observed is 51:49 at all the locations.
d) Commercial Traffic Composition
Analysis has been carried out to find out the composition of commercial traffic and the results are
illustrated in Figure 6.6 and Figure 6.7.. The composition traffic is dominated by Car/Van/Jeep
Car/ (77%)
followed by LCV (20%) and 2-Axle
Axle Truck (2%) nnear Jauljibi. Share of Car/Jeep/Van (74%) is the highest
for the Traffic near Dharchula followed by LCV (24%) and 22-AxleAxle Truck (2%) near Dharchula.
Cars
78%
LCV
2 Axle 20%
2%
Page 78
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
For deriving seasonal variation and correction factors, petrol and diesel sales data has been used.
SCF work out for the combined data of all petrol pumps which will give realistic figure by reducing
the error. These data have been collected from various petrol pumps for different years which are
located along the project corridor. However, the data collected from fuel pumps of project road is
insufficient which cannot help to give the realistic picture of traffic data. So as per standard SCF
considered for
or the project road is 1.0 for petrol driven vehicles and 1.0 for diesel driven vehicles.
Taxi 0 0
Two-wheeler
wheeler 126 566
3wh(pass) 1 0
Minibus 4 3
School Bus 2 18
Bus (Govt) 7 11
Page 79
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Bus (Pvt) 0 0
3wh (Goods) 0 0
LMV 0 0
LCV 81 156
2-Axle
Axle 10 10
3-Axle
Axle 1 0
4-Axle
Axle and 6 Axle 0 0
7 Axle Above 0 0
Tractor 0 0
Cycle 0 3
Cycle Rickshaw 0 0
Animal cart 0 0
Others 0 2
Car/Jeep 7 63
Bus 1 4
Toll exempted vehicle
LCV 1 50
Truck 5 34
Page 80
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Origin Destination (O-D) D) surveys were conducted to elicit information related to the base year travel
characteristics of goods and passenger trips using the project road and likely future traffic diversions
to or from the project road. The Origin Destination (O (O-D)
D) data is analyzed by its origin and
destination, Trip length etc. at both the locations in order to understand the travel pattern of both
passengers as well as goods vehicles. The travel characteristics obtained by O O-D survey would
facilitate the identification of (i) local and through traffic on the project road, (ii) traffic diversion and
(iii) commodity movement pattern.
OD at near Jauljibi
The O-DD survey locations on the Project road are also sshown in Figure 6.1 along with the other
survey locations.
b) Zoning System
For the purpose of delineating the growth centers affecting the influence area, the entire country has
been broadly divided into two regions. They are, Immediate Influence Area (IIA) and Broad Influence
Page 81
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Important towns and industrial areas along or near the Project Road
Important roads
Administrative
tive boundaries, e.g., district and state boundaries.
The adopted zoning scheme has been given in Table 6.9 and graphically shown in Figure 6.8.
Page 82
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
The origin – destination details were collected from the trip makers during the survey on
sample basis. Sampling varied with the changes in traffic flow across the day. Care has been
taken to eliminate any element of bias in sampling. Since data has been ccollected on sample
basis, expansion factors are required to replicate the pattern as reflected in the sample to
the total number of vehicular trips made during the day. These expansion factors are
calculated separately for each class of vehicle and directi
direction
on wise. For example, if xc is
number of cars interviewed and Xc is the total number of cars counted during the day, then
Xc/xc would be the expansion factor for cars.
The roadside interview survey data was coded and entered into the computer for the anaanalysis. This data was
then checked for the zones, mode type and commodity type and matrices were developed. Vehicle wise O O-D
matrices were developed for both directions combined for 24 hrs using expansion factors. O – D matrices are
developed to assess the traffic movement pattern. These matrices actually speak about distribution of trips for
each zone as intra-zonal
zonal and inter
inter-zonal movements. The vehicle wise O – D matrices are developed by
multiplying the sample O – D matrix obtained from survey data with expansion factors.
Page 83
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
d) Travel pattern
The influence of various zones along the project corridor is analysed. Askote, Jauljibi and
Dharchula are the major trip generators along the project road. Other than that major traffic
running on project road is coming from Lohaghat, Pithoragarh, Almora, Haldwani, Didihat,
Bageshwar and Munsiyari town.
e) Trip Share
f) Trip Purpose
The trip purposes of passengers as revealed during the OD survey is mainly work followed by
social trips.
Intersection turning movement surveys are conducted at the following a major junction on the
project road. The survey was carried out for 12 hours.
Page 84
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
To assess the requirement of grade separation at intersections, peak hour traffic was projected and
type of improvement presented in Table 6.11 and the detailed are presented in Annexure 6.4.
Table 6.11:: Projected Peak Hour Traffic at Intersections and Improvement Proposals
Pedestrian/ Cattle movements were observed all along the project road where it passes through
villages, built-up
up areas, schools, colleges and religious places. The predominant flows were observed
at the following village locations tabulated in Table 6.12.
Page 85
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
The pedestrian/ cattle movement surveys were carried out at 2 locations and these pedestrian/
cattle flows present a potential problem for the free flow of traffic. The pedestrian/ cattle flows are
an important element in the design of intersections also in the vicinity of these areas. The pedestrian
counts give justification for planning pedestrian facilities such as subway or signals for pedestrians
crossing. The cattle counts give justification for planning of cattle facilities such as CUP.
6.8.2 Methodology
The pedestrian/ cattle movement surveys were conducted at selected locations from morning 7:00
AM to evening 7:00 PM for total 12 hours period. The pedestrian flows were recorded ffor each 15-
minute interval by counting pedestrian and animals crossing/ parallel the road.
The Table 6.13 give the peak hours of pedestrian flows and peak volumes of pedestrian crossings of
Project Road.
The pedestrian vehicular conflict index, which is the product of number of pedestrians crossing the
road and square of number of motorised vehicles on the road, which is based on IRC: 103 103-1988
“Guidelines for Pedestrian Facilities”. The code suggests controlled crossing measures for
pedestrians, if PV2 value is more than 1X108 for undivided roads and 2X108 for divided roads. It is
observed that no pedestrian control crossing measures is required presently. Considering safety of
pedestrians and animals some basic controlling measures are suggested such as pedestrian marking
Page 86
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
The maximum number of pedestrians crossing the project road, and corresponding average hourly
motorized traffic and the estimated pedestrian vehicular conflict for the same period are presented
in Table 6.14.
Speed and Delay survey was carried out along the project road of Askote to Rock point section. After
Rock point there is no motorable road.
The objective of the study was to assess the journey speed, delays and causes of delays, in order to
reduce the delays and improve the quality of the traffic flows.
6.9.2 Results
There is not much traffic on project road. The road condition is also not good. The average journey
speed in Askote to Lipulekh direction is worked out as 30.5 km/hr and in opposite direction is
Page 87
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
6.10.1 Introduction
The investment priorities are governed by the traffic demand, assessed benefits and cost of
the project. The methodology adopted for traffic forecasting incorporates perspective
growth envisaged in economy and changes in transport demand elasticity ove over a period of
time. Demand plays the important role, which governs which type of facility / infrastructure
to be created. This in turn determines likely benefits and costs to develop the same. A
highway project of this nature calls for significant investme
investment.
nt. Prediction of traffic demand
becomes an important task and has to be carried out near accurately. The accurate
estimation of traffic has direct bearing on the viability of project. Recognizing this, efforts
are to be made to carefully assess all the pa parameters
rameters that help in predicting the traffic
demand in future which necessitates realistic estimation of traffic growth rates. Traffic
growth on a road facility is generally estimated on the basis of historical trends, in the
present case traffic growth ra
rates
tes are estimated using Elasticity method as per IRC-108-2015.
IRC
Demand changes are usually because of shifts in the pattern of economic activities in the
surrounding regions. Hence, future traffic estimation necessitates a preview, however
imprecise, of the probable pattern of future growth of the economy.
Projections are made taking into account the traffic flow pattern by origin
origin-destination
destination pairs and
changes in vehicle mix expected during the study period. TThis his requires estimation of traffic and
traffic generation along the corridor. Since transport demand changes due to shifts in pattern of
economic activities, both temporarily and spatially, consideration has been made to the potential of
generation of transportation
sportation services. In view of this, projection of future traffic incorporates
consideration of basic socio-economic
economic characteristics and rate of change expected during the study
period in the project influence area
Where:
P = Traffic volume (of any vehicle type)
Page 88
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Where,
Ri = Growth in PCI and Population index of Uttarakhand
E=Elasticity Value
Where,
R=economic index (NSDP (Uttarakhand)
Uttarakhand)
E = Elasticity Value
The share of goods traffic (Influence factor) in Uttarakhand is applied in estimating growth
rate of goods traffic.
Normally, the growth potential of passenger traffic in a zone depends on its population and
economic growth rates. Therefore, both these parameters have been incorporated in forecasting of
passenger traffic. Further, taking into account the fact that the different modes of passenger traffic
grow at different rate, the elasticit
elasticityy (as discussed earlier) with respect to population and income
growth rates is graded differently by different modes.
Growth potential of goods traffic is different from passenger traffic. This is more directly
related to zone’s economic activity and prod
production
uction levels than its population and income
Page 89
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
growth, although the latter may strongly correlate with the former, especially the income
growth.
For the traffic study, growth rate of all vehicles plying on project road is considered as 5%, as
tabulated in theTable 6.15.
Table 6.15: Final Traffic Growth Rates (%)
Vehicle Type 2017
2017- 2022- 2027- 2032- 2037-
2037 2042-
2021 2026 2031 2036 2041 2046
Traffic projection for the project road is calculated at Two locations up to the year 2047 and shown
in below Table 6.16.. It includes both direction of the traffic. Vehicle wise projected traffic has been
shown in Annexure 6.5 and Annexure 6.6.
Table 6.16
16: Projected Normal/Total Traffic AADT (PCU)
At Km 63+800 of SHSH-29 At Km 90+400 of SH-29
SH
Year
Nos/Day PCU/Day Nos/Day PCU/Day
Page 90
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
At Km 63+800 of SH
SH-29 At Km 90+400 of SH-29
SH
Year
Nos/Day PCU/Day Nos/Day PCU/Day
Traffic projection has also done on one intersection taking highest peak hour traffic and their results
are presented in below Table 6.17
17.
Page 91
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Page 92
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Jauljibi Km 62+000
Year
Veh/Hr PCU/Hr
Page 93
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
7 DEVELOPMENT PROPOSAL
7.1 General
Geometric Design for a highway deals with the visible dimensions of a roadway and is dictated by
the requirements of the traffic and economic limitations. There are various elements / factors that
would govern the geometric design and functioning of the highway. These geometric design
elements can be broadly grouped under the following:
Horizontal Alignment
ent
Longitudinal Profile
Cross Sectional Layout
Sight Distance
Traffic Composition / Intensity
Pavement Composition
Intersection
Bridges and Structures
Drainage
Land Use
Access Control
Traffic Control and Safety measures
Efficiency and Comfort in Vehicle Operation
Aesthetics
The design philosophy basically involves providing suitable horizontal alignment, longitudinal
section, cross section layout, and safety and access control to cater to the fast and uninterrupted
movement of through traffic.
Considering the realignments and geometric improvement, design length for the Tawaghat to Kali
Mandir section of the project road has been calculated as 58.063km.
The design criteria / method applied for important components of the project are as follows:
Page 94
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Geometric Design : 1) IRC: 52: 2001 Recommendations about the alignment survey
and Geometric Design of Hill Roads.
2) IRC: SP: 73-2018
2018 Manual of Standards & Specification for Two
Laning of Highways through Public
blic Private Partnership by IRC
and other relevant IRC Codes and guidelines on geometric
design.
3) IRC: SP: 48 -1998 Hill road manual.
Pavement Design : Overlay
- IRC 81-1997
1997 for designing and strengthening requirements of
existing pavement
New Pavement
- IRC 37-2018
2018 for design of flexible pavements
Road Furniture & : Related standards of IRC Manual of Specification & MoRT&H
Publications
Roadside Facilities
Following points have been considered during preparation of layout at this stage:
Page 95
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
This project is existed as Single lane and intermediate lane of having fair to poor condition of existing
pavement. The geometric of thi thiss road will be proposed according to two lane with hard shoulder.
The geometric designs are formulated as per the recommendations of IRC: SP: 73 73-2018/ IRC: SP: 48-
1998. IRC:SP:73 is general two laning manual, hence IRC: SP:48 has been followed in particul
particular cases
when IRC:SP:73 is either silent or not specific. The general design standards for improvement are
enumerated in Table 7.1:
Design Speed
Page 96
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Sl
Attributes Geometric Design Standards
No.
Camber
Minimum Radius of
Horizontal Curves
7
a) Mountainous and Steep Desirable Minimum: 150m Desirable Minimum: 50m
Terrain Absolute Minimum: 75m Absolute Minimum: 30m
Longitudinal Gradient
9 a) Mountainous
Ruling: 5.0%, Limiting: 6.0% Ruling: 5.0%, Limiting: 6.0%
Terrain
b) Steep Terrain Ruling: 6.0%, Limiting: 7.0% Ruling: 6.0%, Limiting: 7.0%
10 21-40m - 1.5m
41-60m - 1.2m
61-100m - 0.9m
Page 97
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Sl
Attributes Geometric Design Standards
No.
(2) Proposed shoulder width has been changed at some selected locations to suit the site condition.
The project involves widening/upgrading the existing single lane/Intermediate lane to 2-lane road
with hard shoulderalong with new 2 lanes at bypass and Major realignment locations in
mountainous/hilly terrain
in respectively.
The horizontal geometry of the project road is generally poor. The broad features of
geometric improvements are:
Page 98
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 99
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Ideally, the flexible pavement is built to such a depth that stresses on any given layer should not
cause unwarranted rutting, fatigue, shoving, or other differential movements which may result in an
uneven wearing surface. The thickness design of these layers principally depend on the subgrade
CBR and the traffic loads that the pavement has to carry during its design life.
Flexible Pavement Shall be provided for the entire Project stretch. Pavement shall be designed for a
minimum design period of 20 years for Flexible pavement (as per Clause 4.3.1 of IRC:37
IRC:37-2018) and
30 years for Rigid Pavement.
As per Traffic Analysis maximum MSA for a design life of 20 years is 2.75 (Annexure 7.4). With
Design CBR of 10% and minimum 10 MSA Design Traffic, the following pavement thickness as per
Figure 12.6 of IRC:37-2018
2018 is proposed.
Overlay Design
Page 100
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Overlay design has been carried out based on the results of the BBD Tests.
From the above results it is evident that the existing pavement crust is not sufficient to carry the
corresponding design traffic. Hence considering the bituminous overlay the results obtained are
presented in below.
km 66+590 to km 66+630
km 66+690 to km 66+780
km 66+930 to km 66+995
km 67+940 to km 67+980
km 68+500 to km 68+560
30mm BC + 50mm DBM
km 68+695 to km 68+710
km 72+710 to km 72+860
km 130+396 to km 130+798
km 131+528 to km 131+648
Total 0.983 km
7.2.6 Cross-section
section for Improved Facility
Cross-section
section for the improved facility should be adequate to cater to the traffic expected over the
design period and offer safe and convenient traffic operation at speeds consistent with the terrain
conditions and functional classification of this road.
The cross-sectional
sectional elements (lane/shoulder width etc.) are as per standards specified in geometric
design manual. Eight nos. typical cross sections have been envisaged for the subje
subject project at this
stage as mentioned below. These have been prepared on the basis of site reconnaissance, design
guidelines and improvement objectives.
Typical cross sections for the project road are presented. The summary of cross sections is shown in
Table 7.3.
Page 101
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 102
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Total 58063
Page 103
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 7-104
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 7-105
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 7-106
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 7-107
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 7-108
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 7-109
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 7-110
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 7-111
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 7-112
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 7-113
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 7-114
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 7-115
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 7-116
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935
to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063 km] under
project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
On the basis of above typical cross sections total length of overlay and new construction has been
worked out which has been presented in Table 7.4.
1, 1A, 1E, 1G, 1H, 2, 2A and 4 53481 202 Widening and Strengthening
Cross section for culverts shall be as per corresponding TCS for full width of the particular TCS.
For non-built
built up locations from inner side of drain to outer end of parapet / retaining wall. For
built-up
up location the total width of culverts will be distance between the inner edge of drains.
For bridge the section will be 2 x 0.3m railing + 2 x 1.5m footpath + 2 x 0.45m crash barrier +
7.5m carriageway. Total width will be 12.0m.
Page 7-117
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935
to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063 km] under
project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
The geometric design has been done within the broad framework of design standards
mentioned in Table 7.1.. The design speed adopted is 60/40kmph, with an allowable maximum
super elevation of 5% to 7%, in general. Widening of the existing road is done mostly on the hill
side. While designing, utmost attempt has been made to avoid acquisition of residential as well
as commercial / religious / historic structures. Summary of horizontal curves proposed along
project road is given in Annexure 7.2
7.2.
Vertical alignment has many hag and sag locations. Gradient of project road has change at many
locations
ations and there is many rise and fall on project road. Sharp bends & Inadequate sight distance is a
major issue in most of the sharp curves. So the whole project road has poor geometry.
Page 7-118
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935
to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063 km] under
project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
The proposed alignment is basically following existing road section. Considering this for future
development, TCS Type-3B
3B & 3C have been proposed at Built up locations, the details of which are
provided in Table 7.6:
No Bypass has been proposed in this section. Curve Improvement have been incorporated as per design
needs for geometric improvements. The details of Bypasses are given in Table 7.7.
7 Curve Improvement
has been proposed at 79 locations.
NIL
Page 7-119
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935
to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063 km] under
project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Stretch
Sl. NO Length (m) TCS Type
From (km) To (km)
7.3 Drainage
Due consideration has been given to drainage while preparing the design. The cross cross-sections
incorporating roadside drains have been proposed at various stretches of the highway taking into
account the existing and natural conditions as well as anticipated situation.
On hill side KC drain is proposed throughout the project stretch except at dense built
built-up locations. At
dense built up locations RCC covered cum footpath drain is proposed.
Page 7-120
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935
to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063 km] under
project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
1 CC V-shaped
shaped drain 56901 TCS- 1, 1A, 1C, 1E, 1G, 1H, 2,2A,2C,3B, 4
Page 7-121
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Total 8 nos. minor bridges have been considered for the project road provided in Table 7.11:
Page 7-122
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Proposed Span
Design River/ Width of
Arrange (No. of Proposed Total Proposed Type of Improvement
Sl No Chainage Bridge proposed Remarks
Span x Span Length (m) Superstructure Proposal
(km) Name structure (m)
length in m)
Steel composite
7 131+414 Local Stream 1 x 45.0 45.0 12 New construction
Girder
Steel composite
8 132+432 Local Stream 1 x 45.0 45.0 12 New construction
Girder
Page 7-123
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
7.4.3 Culvert
A considerable number of structures have been proposed along the alignment as per detailed site
inventory. Details of widening and reconstruction of existing culverts are provided in Table 7.12 and
Table 7.13 respectively .
Page 124
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 125
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 126
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 127
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 128
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Page 129
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
7.4.4 Underpasses
NA
7.4.5 ROB
NA
Page 130
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Total 179
The proposed project road will form major and minor intersections with existing roads.
Improvement of these intersections has been thought off with minimum of land acquisition.
However, proper acceleration and deceleration lanes have been considered with p proper
traffic signage. In general, standard codal provisions have been followed for design of these
intersections. There are 2 nos. minor intersections along the project road which shall be
developed. Improvement proposals of major and minor intersections are provided in Table
7.15and Table 7.16 respectively.
pectively.
Nil
Page 131
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
Landslide occurrence and its prevention and mitigation is one of th thee most critical components of a
hill road design. Study of stability of natural and cut slopes helps in identifying problem areas and
formulation of appropriate counter
counter-measures.
measures. Following are the details of land slide in this section:
Nil
The retaining wall shall be constructed as per requirement of site conditions for slope protection
in accordance with manual requirement. However, minimum protection works shall be
constructed as per details given below:
c) Retaining Wall with minimum length of 7441m as per site condition with stone
masonry in cement mortar 1:3 & 1200m with RCC as per site condition is required.
Several towns, villages and settlements are abutting the project corridor and buses shall be
one of the major modes of passenger traffic movement along the corridor. It is imperative to
provide bus bays in order to eliminate the conflict between buses and other moving vehicles
as well as to ensure safety of passengers boarding and alighting. Proposed bus bays have
been kept sufficiently away from the intersections to avoid traffic congestion. Total 5 nos.
bus bays have been considered for the project corrid
corridor,
or, locations of which are presented in
Table 7.17.. The bus bays will have provision for accommodation of two buses at one
passenger shelter at a time.
Page 132
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
7: DEVELOPMENT PROPOSAL
1 66+690 Ghasku
2 68+500 Pangla
4 76+020 Ghatiabagarh
5 89+010 Lameri
NA
NA
Page 133
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
8 ENVIRONMENTAL SCREENING
8.1 INTRODUCTION
8.1.1 Project Background
The National Highways & Infrastructure Development Corporation Ltd. (Ministry of Road
Transport & highways) has awarded M/s Voyants Solutions Pvt. Ltd. the “Consultancy
Services for Feasibility study and preparatio
preparationn of Detailed Project Report for 2 lane with
paved shoulders for work of Upgradation for selected road stretches/ corridors to two lane
with paved shoulder NH configuration under BHARATMALA project.
NHIDCL has transferred the stretch from Askot to Lipulekh Pass to BRO through Chief
Engineer, STF Hirak, Border Roads Organization w.r.t. MoRTH Letter no. NH NH-
12037/28/2018/SARDP--NE/Zone-VV dated 12.02.2019 and Chief Engineer STF-Hirak.
STF
Page 134
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design km
113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bharat Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
Page 8-135
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
Environmental screening has been carried out to identify critical issues and areas that would
be studied in detail for Environment Impact Assessment (EIA). Findings of the screening are
presented in this report. This report has been based mainly on field survey and collection of
secondary data.
Screening process consisted of both onsite as well as desktop assessment of the project
activities.
A. Desktop Study
Study of Laws and regulations: Laws and regulations enacted by Government of India
I and
Uttarakhand State relevant to road construction and environment were studied.
Study of Guidelines, Standards etc.: Various documents and publications of the Ministry of
Environment Forest and Climate Change (MoEF&CC) and Indian Road Congress (IRC (IRC) were
studied for screening exercise.
B. Onsite Study
A team of environmental and social experts jointly carried out field visit of the project road.
Important environmental components including, water bodies, forests, public utilities,
community resources, cultural sites etc. along the corridor of impact zone were identified.
Page 8-136
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
Discussions with local people and administrators were also held to obtain their opinion
about the project.
8.2 PROJECT DESCRIPTION
8.2.1 Project Road
The Site of the Single Lane Project Highway comprises the section of Highway. Project road
starts from Km. 0+000 at Tawaghat village (Design Chainage 56+935) and traverses a
length of 38.812km and ends Km.19+170 at Budhi Village (Design Chainage 95+748) And
starts at End of Tunnel Portal (Design Chainage 113+828) and traverses a length of
19.25km and ends at Kali Mandir (Design Chainage 133+078) . The Project roject Highway is part
of NH-09.
09. The stretch passes through winding hilly terrain of Himalayas and sight distance is
restricted at places due to sharp horizontal curves and vertical cuts slopes
slopes.
8.2.2 Road Design
The project road has generally 22-lane carriageway of width 3.1m to 8m. Drainage is generally
conspicuous due to absence of drains on road sides. The existing Right of Way (RoW) varies
between 4.6m-16.1m.
16.1m. The Proposed RoW area in built
built-up
up area 13m, in open areas 24m and
in by-pass
pass and realignment the prop
proposed RoW is 24m.
8.2.3 Project Proponent
The proposed development will be managed by Border Road Organisation (BRO), Govt. of
Page 8-137
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
India.
8.2.4 Need of the Project and benefits associated
Will provide easy access to commuters from Askote to Lipulekh Pass through the
highway
Will provide easy accessibility for school, medical facilities, etc. for the nearby villages
even in the rainy season.
The project road has generally intermediate lane carriageway of width 3m to 8m.
Entire project
oject road is of Flexible pavement
A. Alignment Proposal
This project is essentially widening of 2 lanes and bringing the existing 2 lanes to proper
2 lanes carriageway as per provisions of codes.
Drains have been provided on both the sides for the entire length of the road
B. Pavement
Page 8-138
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
D. Service Road
The project road shall have the same CD structures as per existing or it may be changed
as per the proposed alignment.
F. Other Structure
G. Land Acquisition
Road will be widened to two lanes with paved shoulders. Land acquisition is required for
proposed road depends on the stretch at different locations and different areas.
H. Intersection Design
All junctions have been studied thoroughly with respect to traffic volume and geometric
design. The important junctions leading to settlements have been identified and proper
junction layouts (including road marking, and traffic signs) shall be applied as per IRC
IRC-SP:
41-1994.
Project road under study is mostly lies in hilly region and has been upgraded for
development. Any developmental activity has both adverse as well as beneficial impact on
surrounding environment. The present report is an effort for scrutinised the applicable
environmental laws and legislative framework under Ministry of Environment Forests&
Climate Change,
nge, Govt. of India. This section elaborates on the various clearance
requirements for the project from the State Government and MoEF&CC, GoI.
8.3.2 Environment Legislation
Legislation- India
The Government of India has formulated various policy guidelines; acts and regula regulations
aimed at protection and enhancement of environmental resources. The following table
surmises the existing legislations pertaining to the project, the various clearances required
for the project.
Page 8-139
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design
km 113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bha Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
Page 8-140
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design
km 113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bha Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
Applicability Implementing /
S. No. Law / Regulation / Guidelines Relevance Reason for Application
Yes / No Responsible Agency
certain facilities.
Empowers SPCB to set and
Consent required for establishing
The Air (Prevention and Control monitor air quality standards and State Pollution Control
5 Yes and operation of batching, hot mix
of Pollution) Act. 1981 to prosecute offenders, excluding Board
plants and crushers
vehicular air and noise emission.
Construction machineries and
Noise Pollution (Regulation And Standards for noise emission for State Pollution Control
6 Yes vehicles to conform to the standards
Control) Act, 1990 various land uses Board
for construction
Conservation and definition of
Part of road packages passes
forest areas. Diversion of forest Forest Department,
7 Forest (Conservation) Act, 1980 Yes through the reserved
land follows the process as laid MoEF&CC
forest/protected forest
by the Forest conservation Act.
The project area is located in MoEF&CC, State
Coastal Regulatory Zone
8 Protect and manage coastal areas No landlocked region and there is no Department of
Notification, 1991
designated coastal zone. Environment
No ecological sensitive area
(National Park, Wildlife Sanctuaries
Protection of wild life in NBWL, SBWL & Chief
9 Wild Life Protection Act, 1972 Yes and Biosphere reserves are located
sanctuaries and National Park Wild Life Warden
within 10 km distance from the
project road.
Baijnath Temple are notified
Ancient Monuments and Archaeological Survey
To protect
ect and conserve cultural archaeological monument by ASI
10 Archaeological sites & Remains No of India, State Dept. of
and historical remains found. which is located in the proximity of
Act 1958 Archaeology
the planned project road
Empowers State Transport All vehicles used for construction
State Motor Vehicles
11 The Motor Vehicle Act, 1988 Authority to enforce standards Yes will need to comply with the
Department
for vehicular pollution. provisions of this act.
The Explosives Act (& Rules) Sets out the regulations as to New quarrying operation may Chief Controller of
12 Yes
1884 (1983) regards the use of explosives and require blasting Explosives
Page 8-141
Improvement/ Construction of 2-lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km. 56+935 to km 95+748) and from end of tunnel portal to Kali Mandir (Design
km 113+828 to km. 133+078) [Total Design length = 58.063 km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala
Bha Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
Applicability Implementing /
S. No. Law / Regulation / Guidelines Relevance Reason for Application
Yes / No Responsible Agency
precautionary measures while
blasting & quarrying
Protection to the general public
Public Liability and Insurance Hazardous materials like Bitumen State Pollution Control
13 from accidents due to hazardous Yes
Act,1991 shall be used for road construction Board
materials
Hazardous Wastes Hazardous wastes shall be
Protection to the general public
(Management, Handling and generated due to activities like of State Pollution Control
14 against improper handling and Yes
Trans-Boundary Movement) maintenance and repair work of Board
disposal of hazardous wastes
Rules, 2008 vehicles
Chemical Accidents (Emergency Protection against chemical Handling of hazardous (flammable, District & Local Crisis
15 Planning, Preparedness and accident while handling any Yes toxic and explosive) chemicals Group headed by the
Response) Rules, 1996 hazardous chemicals resulting during road construction DM and SDM
Mines &Minerals (Regulation & Permission of Mining of
State Department of
16 Development) Act, 1957 as aggregates and sand from river Yes Mining of sand or aggregates
Mining
amended in 1972 bed & aggregates
The Building & Other
Construction Workers
District labor
17 (Regulation of Employment & Employing Lab our / workers Yes Employment of labors
Commissioner
Conditions of Service) BOCW
Act, 1996
Page 8-142
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
Key international agreements that India is signatory to and relevant for the project are
provided below:
Convention Relative to the conservation of Flora and Fauna in their Natural State (1933)
International Plan Protection Convention (1951)
Convention on Wetlands of Intern International
ational Importance, Especially as Waterfowl Habitat
(Ramsar, 1971)
Convention concerning the Protection of the World Cultural and Natural Heritage (Paris,
1972)
Convention in International Trade in Endangered Species of Wild Fauna and Flora
(Washington, 1973)
Convention on Migratory Species of Wild Animals (Bonn, 1979)
Convention on the Prior Informed Procedure for Certain Hazardous Chemicals and
Pesticides in International Trade (PIC or Rotterdam, 1990)
United Nations Framework Convention on Climate Change (Rio De Janeiro, 1992)
Convention on Biological Diversity (Rio De Janeiro, 1992)
Protocol to the United Nations Convention on Climate Change (Kyoto, 1997)
United Nations Convention on the law of sea (Jamaica, 1982)
Convention concerning the Protection of the World's Cultural and Natural Heritage
(1975)
The above list of international conventions served as requirements for the project to
comply.
8.3.4 Environment and Social Safeguard Policies
Environmental assessment;
Environmental planning, and management;
Information disclosure;
Consultation and participation;
Grievance Redress mechanisms;
Monitoring and Reporting;
Unanticipated Environment Impacts;
Biodiversity and sustainable natural resources management;
Pollution prevention and abatement;
Page 143
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
Table 8.3:
.3: Application of ADB Safeguard Policies to the Project
ADB Safeguard Policy Project Information/
Requirements
statement Application
1. Environmental Environmental assessment term is used to The assessment is made in
assessment identify potential direct, indirect, reference to the ADB
cumulative, and induced impacts and risks standard checklist
at an early stage of the project
2. Environmental As per this requirement, borrower should Management and
planning and prepare an environmental management monitorin plan for the
monitoring
management plan (EMP) that addresses the potential project is based on the
impacts and risks identified by the Impact Intensity in a
environmental assessment. particular aspect of
The EMP should include the proposed environment. Performance
mitigation measures, environmental Indicators are established
monit
monitoring and reporting requirements, for post project monitoring.
emergency response procedures, related
institutional or organizational
arrangements, capacity development and
training measures, implementation
schedule, cost estimates, and performance
indicators.
3. Information Under this requirement borrower should Regular interaction with
Disclosure establish regular interaction with the affected population and
affected populations and stakeholders stakeholders are being
made.
4. Consultation and The borrower / client should carry out Consultation is a regular
Participation meaningful consultation with affected practice at the project site.
people and other concerned stakeholders, BRO should keep regular
including civil society, and facilitate their interaction with all the
informed participation. stakeholders.
5. Grievance Redress The borrow
borrower / client should establish a Grievance Redressal
Mechanism mechanism to receive and facilitate Mechanism of BRO,
resolution of affected peoples’ concerns, MoRTH, Govt. of India shall
complaints and grievances about the be followed.
follo
project’s environmental performance.
6. Monitoring and The borrower / client should monitor and Monitoring plan is defined
Reporting measure the progress of implementation of in this report and same
the EMP. The extent of monitoring activities shall be followed during
should be commensurate with the project’s operation of the project.
risks and impacts.
The borrower / client should prep
prepare
Page 144
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
Page 145
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
Page 146
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
The World Bank has 10 operational safeguard policies for the development projects that are
funded by the Bank. The purpose of these policies is to ensure that social and environmental
risks are prevented or at least minimized while increasing socio socio-economic
economic benefits of
approved projects in addition to preserving the environment.
These policies have been a means to increase the effectiveness and positive impacts of
development projects and programs supported by the Bank.
With respect to this project, three key policies are being triggered. These are Environmental
Assessment (OP/BP 4.01), Involuntary Resettlement (OP/BP 4.12) and Physical Cultural
Resources (OP/BP 4.11)
The project’s ESIA and ESMP take into account the natural environment (air, water, and
land); human health and safety; and social aspects (involuntary resettlement, physical
cultural resources, etc.) in addition to trans
trans-boundary
boundary and global environmental aspects.
The policy requires consultat
consultations
ions with potentially affected persons and analysis of
Page 147
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
alternatives as key parts of the process and documentation. The OP 4.01 is applicable to all
components of Bank financed projects.
This policy requires that adverse social impacts of projects it supports be mitigated,
including when land or property is acquired or its use modified under a project so that
Project-affected
affected Persons (PAPs) suffer loss of income, residence, livelihoods or access to
resources, either perman
permanentent or temporary, whether the land occupation/use is legal or
illegal. Resettlement or relocation of PAPs adversely affected by project activities must be
undertaken in accordance with laws, regulations and guidelines for Resettlement/Land
Acquisition in Govt.
ovt. of India/State of Uttarakhand Resettlement & Rehabilitation Policy and
OP 4.12. If there is a gap between Govt. of India/State of Uttarakhand Resettlement &
Rehabilitation Policy and the Bank’s OP 4.12 then the Bank’s provisions must apply.
Displaced persons should be assisted in their efforts to improve their liv livelihoods and
standards of living or at least to restore them, in real terms, to pre
pre-displacement levels
or to levels prevailing prior to the beginning of project implementation, whichever is
higher.
o Loss of income sources or means of livelihood, whether or not the affected persons
must move to another location; or
The involuntary restriction of access to legally designated parks and protected areas
resulting in adverse impacts on the livelihoods of the displaced persons.
Page 148
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
This Bank Policy supports decision making process by the Borrower and Bank through
allowing public access to information on environmental and social aspects of projects.
Disclosure of key project documents, including Executive summaries in English and in the
local language, is mandated:
In the World Bank Info Shop before project appraisal, in English with the Execu
Executive
Summary in English and in the local language (documents can be in draft but must meet
World Bank standards).
D. OTHER WB GUIDELINES
Other useful guidelines and manuals that have been considered during the ESIA phase of the
project include:
The World Bankk Participation Source book
IFC Involuntary Resettlement Guide book
Safeguards Policy Basics – Red book
Environmental, Health and Safety (EHS) General Guidelines of the World Bank Group
Roads and the Environment. A Handbook. World Bank Technical Paper 376.
Doing Better Business through Effective Public Consultation and Disclosure – A good
Practice Manual, issued by IFC.
Handbook for Preparing a Resettlement Action Plan, issued by IFC.
8.4 ENVIRONMENT SCREENING
8.4.1 Introduction
Page 149
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
Details of affected structures were collected for 22.5m on either side from the center line of
the road. Details of sensitive receptors, those are located beyond 22.5 m were also collected
as the noise and air pollution may take place beyond direct area (a
(approximately
pproximately 500 meters)
of impact.
8.4.3 Data Collection
Efforts have been made to collect the latest information both at regional as well as local
level especially along the project roads alignment.
A. Secondary Data
B. Primary Data
Field study / monitoring have been carried out to generate and collect primary data in the
study corridor, which involves:
Inventory of road features like drinking water source, water bodies, ccommunity
structures, environmentally sensitive locations areas, congested locations etc. from
physical surveys
Enumeration of roadside trees by Contractor
Biological Diversity Data
Environment Monitoring
Forest Data from the concerned forest Department.
8.4.4 Location
Uttarakhand State is located in the northern part of India and is often referred as
“Devbhumi”. It is known for its natural beauty of the Himalayas, the Bhabhar and
the Terai. It borders the Tibet in the north; the Mahakali Zone of the Far-Western
Page 150
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
Region, Nepal in the east; and the Indian states of Uttar Pradesh in the south
and Himachal Pradesh in the west and north-west as well as Haryana in its south-
western corner. Economically, the stat
statee is the second fastest growing state in India. The
interim capital of state is Dehradun, the largest city in the region, which is a railhead. The
natives of the state are generally called Uttarakhandi or more specifically either Garhwali or
Kumauni by their region of origin. Agriculture is one of the most significant sectors of the
economy of the state.
a) Pithoragarh District: It is a district in the Kumaon division of the state. Pithoragarh is the
easternmost district of Uttarakhand, neighboring Tibet in the north and Nepal in the
east. Pithoragarh is popularly known as the 'Little Kashmir'. It is n naturally landscaped
with high Himalayan mountains, snow-capped peaks, passes, valleys, valleys alpine, meadows,
forests, waterfalls,, perennial rivers, glaciers, and springs. The flora and fauna of the area
have rich ecological diversity. Pithoragarh town is a historical landmark. It was a major
center of power during the regime of the Chand Kings in Kumaon. The distri district is
administratively divided into six tehsils: Munsiyari, Dharchula,, Didihat, Berinag,
Gangolihat and Pithoragarh.
Project Corridor
Project corridor links Askote to Lipulekh Pass in Uttarakhand State. The length
considered for the study is 40.141km.
8.4.5 Topography, Geology, Seismicity and Soil
Pithoragarh h District: The Pithoragarh is located at a height of 1645 meters above sea level.
The district lies between 29.4° to 30.3° North latitude and 80° to 81° East longitude along the
eastern and southern part of the central Himalayas with Indo Indo-Tibbetan
Tibbetan watershed
watersh divide in
the north and the Kali river. The Pithoragarh district is surrounded by the national
boundaries of Almora, Champawat, Bageshwar and Chamoli districts. The district lies in
seismic zone V.
The soils are natural, dynamic, heterogeneous, non non-renewable
wable resource, which support
plant and animal life. These hills possess very little level land. The soils have developed from
rocks like granite, schist, gneiss, phyllites, shales, slate etc. under cool and moist climate.
The Lesser Himalayan range is mainly composed of highly compressed and altered rocks like
Page 151
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
granite, phyllites, quartzite etc. and a major part of it is under forest. Intermittent sparse
patchy terraced
ed cultivation is also practiced on fairly steep hill slopes whereas dry and wet
cultivation are prevalent on the uplands and low low-lying
lying valleys respectively. The broader
valley slopes dominantly have deep, well drained, fine
fine-loamy,
loamy, moderately acidic and slightly
sl
stony.
8.4.6 Climatology
The project road passes through district i.e. Pithoragarh. Table below shows the climatic
condition in all three districts.
Climatic Pithoragarh District
Factors
Rainfall The average annual rainfall of the District is 1317.5 mm.
Pithoragarh is relatively warm during summer and cool during winter.
During the coldest months of December and January, the tropical
and temperate mountain ridges and high locations receive snowfall and
have an average temperature of 5.5
5.5–8.0 °C
The entire district exhibits four broad seasons in the year. Winter (mid
Dec. - mid March) 2. Summer (mid
(mid-March - mid June) 3. Season of general
g
rains (South - West monsoon season) 4. Season of retreating monsoon
(mid-September
September to mid
mid-November)
Temperature The average temperature in the district is about 25°C in May and during
the coldest months of December - January, the temperature ranges
between -2to 9 degrees Celsius.
Humidity The relative humidity is high during monsoon season, generally exceeding
67% on the average.
Wind The average wind velocity 5.2 to 12 km/hr.
velocity
8.4.7 Surface Water-Bodies
The drainage of the Pithoragarh District is mainly controlled by Ramaganga, dhauli , Gori,
Sarju and kali. Pithoragarh district is crisscrossed by several important rivers and their
tributaries. Gori, traversing a distance of 104 km before it confluence wiwith Kali at Jauljibi is
the major river. The rivers of Pithoragarh district generally flow with great force in steep and
narrow channels often resulting in excessive erosion and collapse of the banks.
Air quality along the project stretch is observed healthy and clean in the study area. No
major dust emitting activities was observed along the project road. Ambient air quality
monitoring for various parameters like PM10, PM2.5, SOx, NOx, CO shall be started at project
site and surrounding area. Central and State Pollution Control Board guidelines shall be
followed for sampling and analysis. The data will be compared with the National Ambient Air
Quality Standard of CPCB as given in Table below.
Page 152
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
Annual Arithmetic mean of minimum 104 measurements in a year at a particular site taken
twice a week 24 hourly at uniform interval.
The noise level on road side was found low on the stretch except the market area that has
some traffic during day time otherwise the noise level is normal as observed during
consultation. Day and night time ambient noise levels will be determined based on
monitored data. Monitoring location shall be finalized based on the sensitive receptors and
source of noise pollution. The data will be compared with Ambient Noise level standards as
given in Table below:
Page 153
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL
VIRONMENTAL SCREENING
Note-:
1. Day time shall mean from 6 a.m. to 10 p.m. and Night time shall mean from 10 p.m. to
6 a.m.
2. Silence Zone is an area comprising not less than 100 meters around hospitals,
education institutions, courts, religious places or any other area, which is declared as
such by Competent Authority.
3. Mixed categories of areas may be declared as one of the four above above-mentioned
categories by the Competent Authority.
4. * dB(A) Leq denotes the time weighted average of the level of decibels on scale A
which is related to Human Beings
5. A “decibel” is the unit in which noise is measured
6. “A” in dB (A) Leq, denotes the frequency weighted in the measurement of the noise
corresponds to frequency response characteristics of the huma
human n ear.
7. Leq: It is an energy means of the noise level over a specified period.
8.4.10 Ecological Feature
The project road crosses the protected forest and reserve forest at some portion. The major
species as present along the alignment are Pine ((Pinus Pinus roxburghii),
roxburghii Oak (Quercus
leucotrichophora),
), Rhododendron ((Rhododendron arboretum), Cedar (Cedrus
Cedrus deodara),
deodara etc.
The domestic animals observed in the study area are mainly mammals. The wild animals
observed and reported during interaction are Leopard, Jungle cat, Monk Monkey, Wild boar and
India fox that are generally have their habitat in the forest along road.
8.4.11 Social and Cultural Feature
A. Educational Facilities
Details of education facilities, medical facilities, religious facility and public consultation will
be done during
ng site visit, which will be done in July month.
B. Religious Facilities
There are 8 Temples are located along the corridor. Boundary of most of the religious places
was found beyond the expected widening width.
8.5 STAKEHOLDER CONSULTATION
8.5.1 Process and Methodolog
Methodology
As a part of the project preparation and to ensure that the community support is obtained
Page 154
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
8: ENVIRONMENTAL SCREENING
and the project supports the felt needs of the people; stakeholder consul
consultations were
carried out as an integral component. A continuous involvement of the stakeholders and the
affected community was obtained.
Individual interviews, field level observations, transect walk, community consultations &
meetings were used to collec
collectt stakeholders input on the project. Meetings with community
were conducted in both ways i.e. formal as well as informal.
8.6 CONCLUSION
The proposed project road is a part of national highway and being improved under National
Highway Improvement Program. Pro Proposed
posed widening will help in reducing the noise pollution
and air pollution due to free
free-flow
flow traffic condition. The widening of the road shall be two
lanes with paved shoulder NH configuration. Hence, project road will affect the household
property and environment
ronment due to widening of road. Most of the project road lies in Hilly
area and also passes through forest area; therefore, forest clearance will be required. Some
trees are needed to be felled for the widening purpose. Detailed EIA study should cover all
the impacts related to Social and biological environment in detail.
Page 155
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
9: SOCIAL SCREENING
9 SOCIAL SCREENING
9.1 INTRODUCTION
The National Highways & Infrastructure Development Corporation Ltd. (Ministry of Road
Transport & highways) has awarded M/s Voyants Solutions Pvt. Ltd. the “Consultancy
Services for Feasibility study and preparation of Detailed Project Report for 2 lane with
paved shoulders for work of Upgradation for selected road stretches/ corridors to two lane
with paved shoulder NH configuration under BHARATMALA project.
NHIDCL has transferred the stretch from Askot to Lipulekh Pass to BRO through Chief
Engineer, STF Hirak, Border Roads Organization w.r.t. MoRTH Letter no. NH NH-
12037/28/2018/SARDP--NE/Zone-VV dated 12.02.2019 and Chief Engineer STF-Hirak
STF
Result in lower transport costs for freight and passengers of motorised and non
non-
motorised vehicles;
Improved road transport corridors;
Road network connectivity;
Improved management of road sector institutions;
Enhanced maintenance of priority roads;
Rural prosperity;
Reduced risk of highway related diseases; and
Basic amenities to the villages along the proposed highways.
Although such benefits were not quantified, the project is also expected to help alleviate
development constraints in agriculture, commerce, education, health, social welfare, and
public safety and contribute to general expansion and diversification of devdevelopment
activities.
The project road runs throughhilly area. This is the terrain of Uttarakhand, which has
combination of Sharp bends &inadequate sight distance. The project road has poor
geometry as a whole and required major improvement in the alignme
alignment.
nt. The existing ROW
in the stretch varying between 33-16.1mts,
16.1mts, even at few critical locations, Additional Land
acquisition will be required to make the ROW to 13 meter in built
built-up
up area, 24 meter in open
area and 24 meter in the proposed bypasses and realig
realignment.
Page 156
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
9: SOCIAL SCREENING
Assessment results are considered with technical and economic feasibility findings in the
final selection of roadss to be rehabilitated and up
up-graded.
graded. The assessments also contribute
to engineering design and result in the preparation of social action plans governing project
implementation and the resettlement and rehabilitation of those who may be displaced by
road improvements.
The project’s social impacts and resettlement component includes assessment of social
impacts of the project and development of appropriate mitigation plans as required. These
plans must comply with appropriate national and local laws and guid guidelines. Social
assessment is carried out in close co
co-ordination
ordination with environmental assessment team and
design team and includes consultation and participation among project stakeholders, local
communities and potentially affected groups. The social impact assessment and
resettlement planning component has following elements:
Follow-up
up consultations (to be carried out after finalisation of drawings).
Social screening was undertaken in conjunction with project feasibility studies. It provided
important
nt inputs and guidance to engineering designs. A full census will be undertaken in
20m at settlement corridor, 24 m at open corridor and 60m at proposed bypasses (at new
alignment, re-alignment)
alignment) to register and document the status of the potentially affect
affected
population within the project impact area, their assets, and sources of livelihood.
The baseline data will be collected in 20 m corridor to get information of a wider corridor as
it gives more flexibility for deciding widening options. Census data wil
willl provide the basis for
establishing a cut-off
off date for non
non-title
title holders in order to determine who may be entitled to
relocation assistance or other benefits from the project.
Socio-economic
economic survey will also be carried out so that it will provide a basel
baseline against which
mitigation measures and support will be measured and includes comprehensive examination
of people’s assets, incomes, important cultural or religious networks or sites, and other
sources of support such as common property resources. Analys
Analyseses of survey results will cover
the needs and resources of different groups and individuals, including intra
intra-household and
gender analysis.
Preparation of the Resettlement Action plan (RAP) will be undertaken within the project’s
Social Impact Assessment ccomponent.
omponent. A key prerequisite of the RAP is a policy framework
for resettlement containing categories of impacts and their corresponding entitlements. The
RAP will provide detailed guidance on how to implement provisions in the policy framework,
Page 157
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
9: SOCIAL SCREENING
including institutional
nstitutional arrangements and budgets based on enumeration of project
project-affected
people with entitlements under the framework. The RAP is also an important component of
the project’s overall Environmental Management Action Plan developed in the
environmental assessment.
The project road passes through hilly areas and rolling terrains, a number of dwelling
settlements and markets, Religious/ tourism circuits and having mostly agricultural fertile
land. The major Rabi andkhariffcropsare wheat, rice, pear & walnut.
Detail of main townships and Villages in the project stretch is outlined below in Table:
After adopting a Proposed ROW is 18.0 m and in realignment section is 24m. the total land
area required to be acquired is 30.46 hectares. The bifurcation of land required is as detailed
below:
Reserve Forest Land – - Ni;
Revenue Land - 2.85 hectares
Forest Land – 30.46 hectares
The land acquisition will affect the following category of loss. The details of land acquisition
and quantum of loss under each category will be given in DPR stage.
No genuine data/report is available with reference to the available ROW for the project
road. However, as per visual investigation with sample measurements at site the existing
Page 158
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
9: SOCIAL SCREENING
ROW is varying from 4.6m. to 16.1m. At few critical locations it was found to come down at
4.6m total.. Moreover, the existing ROW is not free of encumbrances. The limit of
displacement will be limited not to the legal right of way but to the corridor of impact. The
corridor of impact is the corridor required for the actual construction of the road, including
carriageway, shoulders, embankments and longitudinal drainage. Within this corridor there
should be no structures or hindrances.
9.4.2 Impact on
n Settlement and Community Resources
In some of the areas in the project the road traverses through densely populated
settlements. On the basis of preliminary survey approximately 35 structures are estimated
to be affected due to widening and improvement o off proposed project road. Actual figure will
be brought out after Census and Property Inventary survey. Some of the infrastructures built
to facilitate the basic needs of the communities in these areas are affected by the project.
People who are losing land - as per R&R definition they are called titleholder;
People who are losing structures but the structures have been erected in some one else’s
land. The landowner may be government or private people. This category of people is called
non-titleholder.
titleholder. The kiosks or tenant affected by the project (may be due to business
disruption, livelihood problem etc.) are also considered in this category.
9.6 PUBLIC CONSULTATION
The consultation with the identified project affected people and the local stake holders will
be done. Their views and the suggestions are beibeing
ng considered for finalising the alignment.
The basic objectives of public consultation at project planning stage are as follows
follows:
To familiarise the local people regarding the development of the road; and to
provide to the design team the micro social issu
issues
es concerning corridor management
(road safety, local traffic movement, intersection improvement, provision of via duct,
provision of underpass, provision of junction improvement, provision of service road,
provision of parking place) etc.
To understand views of the people affected w.r.t to the impacts of the road.
To identify and assess all major economic and sociological characteristics of the
village to enable effective planning and implementation and,
Page 159
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
9: SOCIAL SCREENING
There has been active participation by the communities residing along the project corridor in
the consultation process and decision making. Major issues, concerns and findings observed
during the consultation process by the participants are as below
below:
Major findings related to key issues such as: general perception about the project,
suggestions to mitigate hardships resulting from dislocation and loss of livelihood are
presented below.
Requests for facilities and amenities like underpasses, bypasses, bus stands and safer
accessibility at points of congestion and intersect
intersections.
On site relocation for small business enterprise (SBE) within the ROW at the edges of
the carriageway were suggested. SBEs are not interested to relocate at far far-off
locations. They perceive low business growth at such locations.
Page 160
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
9: SOCIAL SCREENING
With the 2 Lane of the existing commercial units along the road may not function in a
manner as they are functioning at present, because of heavy and fast moving traffic on the
road
oad after its up gradation. Moreover, the commercial centres are located within the
existing ROW. In certain places there will be land acquisition impacting on the residential
area and agricultural land. This situation will produce considerable no. of proj
project affected
people. The resident will not enjoy uncontrolled access to various social facilities situated on
both sides of the road. Therefore, adequate provision shall have to be made in the proposed
project road design for at appropriate places to reduc
reducee the negative effects of the project.
According to the Policy Framework involuntary resettlement is an integral part of the Project
design from the earliest stage of the project preparation.
Page 161
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
10 ROAD
10: SAFETY AUDIT
10.1 INTRODUCTION
Road safety is now recognized as a major socioeconomic concern in India. Increasing traffic
volumes, the rapid growth in two and tthree hree wheeled traffic, higher speeds due to
construction improvement / rehabilitation of roads has increased safety problem. A Road
Safety Audit (RSA) is the safety performance examination of a road section through
experienced road safety expert. It qualita
qualitatively
tively estimates and reports on potential road
safety issues and identifies opportunities for improvements in safety for all road users. The
road safety audit investigates general safety conditions, focuses on specific concerns or
users. This also includes pedestrian safety as well as safety of bus and train users.
As per the scope of works RSA needs to be performed in the following stages:
This chapter is related to safety audit report at feasibility study stage (planning stage). The
audit team reviewed proposed design from road safety perspective and checked the
following aspects.
RSA related
elated to construction stage and monitoring existing road stage is not discussed here.
Broadly following items have been checked or reviewed during the feasibility study stage
based on site data, existing road and proposed designs.
Page 162
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
10 ROAD
10: SAFETY AUDIT
Safety
ty and operational implications of proposed alignment and junction strategy
with particular references to expected road users and vehicle types likely to use the
road.
Width options considered for various sections.
Departures from standards, if any and acc
accordingly
ordingly actions taken.
Provisions of pedestrians, cyclists and intermediate transport.
Safety implications of the schemes beyond its physical limits, i.e., how the scheme
fits into its environs and road hierarchy.
Road Safety Audit is a formal procedure that uses extensive safety engineering knowledge to
identify safety deficiencies in road sections. A broad experience in road, traffic and safety
engineering needs to be acquired to ensure that a Road Safety Auditor has the knowledge
and ability to refer back
ack to the basic principles in road safety, and propose appropriate
mitigation measures. Following points are generally adequately clarified during a road safety
audit.
Confusion or ambiguity due to design layout for road users that could lead to potential
road traffic accidents
Insufficient information for road users
Improper visibility, or an obstruction to road view s of road users
Hazards in layout create or obstacles to road users that could contribute to an increased
risk of injuries
In the above cases safety of the scheme may be compromised and remedial measures may
be required to remove this potential or actual deficiency. Road users need to perceive and
process vast amounts of sensory and visual information to negotiate a road layout. On the
other
er hand, role of designer is to provide a safe road environment that should:
Provide adequate information for road users of the layout and conditions ahead;
Provide adequate warning of hazards or unusual layouts ahead;
Provide positive control of road use
users
rs passage through conflict points or unusual
sections;
Provide a road performance that can nullify road users errors or inappropriate behavior.
Desirable minimum Design Standards should be used wherever possible and advance
information and warning should be used to inform road users of the layout ahead. However,
driver overload must be avoided as it may cause road users to focus too much on the
unimportant data and shed vital information. Conflicting information, an overabundance of
road signs or a lack o off delineation can cause overload. Therefore, a “safer” road
environment can be defined as a layout that:
Page 163
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
10 ROAD
10: SAFETY AUDIT
It is important that a road improvement caters for all road users. Often the needs of the
motorist are incorporated within a scheme whilst the needs of the vulnerable user are
ignored. The vulnerable road users that need to be cons
considered
idered are: pedestrians – the old,
young and those with mobility or sight impairment; cyclists – children, commuters and
leisure users; and motorcyclists.
Each vulnerable road user has different needs from the road network. In the habitation
environment thehe pedestrian is likely to be the principal user and designs must incorporate
safe crossing locations, adequate visibility to and from the crossings and appropriate
lighting. In addition to the needs of vulnerable road users, particular attention should be
paid to the needs of trucks, buses or other specialist vehicles.
Safe road design varies from the urban to the rural road network; and a number of external
factors can create a situation in which a safe road in one location becomes unsafe due to
external factors. These factors can include traffic volumes, population density, noise, or road
user familiarity. The function of a road should be clear to all road users, and a well
well-planned
and defined road hierarchy can assist in providing a safe road network. TThe design speed can
also be an important factor in influencing the safety of a road and should be appropriate to
the location, local road users and level of private access control.
One important aspect to the safety of junctions is that layout as well as control method need
to be simple and clear, with defined priorities for all road users. The assumption that
‘straight on’ traffic has priority is widely accepted and it needs to be remembered that
alterations to this, despite reinforcement with signs and llines
ines can still be confusing if visual
clues such as fences, kerbing or lighting remain unchanged. It is important to attempt to
make any minor approach perpendicular to the main road. YY-junctions junctions with acute angles
should be avoided. These angled junctions pose problem for road users, including restriction
of forward and side visibility. Similarly, it is advisable to avoid intersections on the inside of
bends as foliage often encroaches into sight lines after several years. Roundabouts used as a
form of junction
tion control have their own rules and design requirements. One of the primary
requirements in good roundabout design is that the radius is tighter on the entry than the
exit. This ensures a slow entry and lower circulating speed. Visibility is a key requir
requirement for
Page 164
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
10 ROAD
10: SAFETY AUDIT
all junction types, all road users need to see and be seen by others. Care should be taken
with fixing street furniture and vegetation within visibility splays. Vulnerable road users
often experience difficulties during crossing at junctions. It is important that their needs are
provided for and that safe crossing places are implemented where required.
Parked vehicles causing physical obstructions which are sideswiped or run into;
Parked vehicles causing sudden braking or nose
nose-to-tail shunts;
Parked vehicles which deflect oncoming vehicles into adjacent vehicle paths;
Parked vehicles blocking visibility for any road user;
Parked vehicles between which pedestrians emerge.
To reduce the risk of parked vehicles contributing to an accident it is important that designs
should minimize parking in main traffic lanes. Trees and foliage can greatly enhance the
environmental impact of the street scene. However, left un un-maintained,
maintained, they can also
restrict visibility considerably. In addition to thi
this,
s, saplings grow into large trees, which can
provide an unforgiving road hazard in the event of a road traffic accident.
With the above discussions and study / analysis of the project road sections safety issues
have been conceived, which are presented in the following table.
Page 165
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
10 ROAD
10: SAFETY AUDIT
Page 166
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
10 ROAD
10: SAFETY AUDIT
Page 167
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
10 ROAD
10: SAFETY AUDIT
No truck lay
lay-byes
have been observed
Lay-byes Nil
along the existing
road.
Page 168
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
10 ROAD
10: SAFETY AUDIT
It is proposed to provide
No emergency
Emergency vehicles at two
Emergency vehicle have been No toll plaza has been
Toll Plaza Locations to
vehicles found along the proposed
operate within a certain
existing corridor
time frame.
Page 169
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
10 ROAD
10: SAFETY AUDIT
Provide pedestrian
Existing junctions are 0 Major Junctions and 3 guard rail on Footpath,
not properly minor junctions to be median for the safety
Minimize developed with developed with proper of pedestrians
A3.
potential insufficient turning turning radius, signage and
Junctions
conflicts radius and absence of markings to minimize
road signage as well potential conflict between Pedestrian crossings
as markings pedestrians and vehicles shall be provided in
proper places in the
junctions with signage
Page 170
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
10 ROAD
10: SAFETY AUDIT
and markings
Existing Scenario
Pedestrians shows Pedestrians,
Cyclists and non non-
motorized vehicles
are plying on the In built up stretches 1.0m
A4. Non- existing road du
due to wide footpath has been
Motorized damage road proposed for less conflict
Cyclists
road users shoulder and absence between fast moving
provisions of footpath in built
built- vehicle and pedestrians,
up areas and causing cyclists etc.
conflicts with fast
Non-
moving vehicles
motorized
which decrease the
vehicles
design speed
Page 171
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
10 ROAD
10: SAFETY AUDIT
road
Following Road safety measures has been recommended with reference to the Road safety
RW/NH-35072/04/2004-S&R (R)) issues by MORTH dated 27th April,
circular (Circular No. RW/NH
2010.
1.) “Metal Beam Crash barrier for High embankment” - The Metal beam crash barrier
barrie is
proposed at all locations where embankment height is more than 3 m.
2.) “Pedestrian Safety” – Provision of Footpath has been made considering the pedestrian
safety at built-up
up locations.
a.) All curves with R < 750 m to be delineated on outer side of the curve from both
the directions.
b.) All embankment with height 3 m or more shall have W – beam metal crash
barriers with delineating reflectors fitted on them
c.) 17022 nos. of Red reflectors to be pr provided
ovided and 22581 nos. of Road stud to be
proposed at center line.
d.) One way reflective road studs shall be provided on edge lines and lane lines on
the approach to an intersection or a high level bridge/ culvert/ ROB etc. with
high embankment. Also such studstudss shall be provided along the sharp curves.
Page 172
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
11 COST ESTIMATE
11.1 General
Cost estimate has been prepared for the total project considering the various items of works
associated with identified improvement proposals using unit rates prevailing currently in
order to assess the updated cost structures in general.
11.2 Methodology
Quantities of different items of work have been calculated on the basis of typical existing
cross-sections
sections as developed from the information obtained through
inventory/topographical
ventory/topographical survey and typical proposed cross
cross-sections.
sections. Quantities for other
work items have also been computed based on proposed improvement, road alignment
and widening proposals as recommended. The major items of work considered are:
The Improvement proposals considered for the corridor are detailed below:
Road Excavation and Pavement Works are considered for the realignment locations.
Quantity of Bituminous works are consid
considered
ered for the entire stretch.
Drainage is considered for the realignment section.
All the Bridges and Cross Drainage Structures are newly constructed and hence not
considered for costing.
Landslide protection measures considered for the entire stretch.
Breast
st Wall/ Retaining Wall have been considered for the realignment stretch and
also on the stretches where protection works are damaged along the project
corridor.
Road Appurtenances including Safety Barriers have been considered for the entire
stretch.
Page 173
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
Unit rates are derived using MoRTH standard data book by providing the necessary cost
inputs related to labour, material and equipment from “Common Schedule of Rates as
per Pithoragarh District of Uttarakhand. Unit rates for other iitems
tems of work were finalized
after considering the current market rates or from information or other major projects of
similar standards..
Considering various items of works associated with identified improvements and current
unit rates, cost estimate has been prepared. The total cost of civil work including cost of
utility shifting is Rs 274.96 Cr
Cr. This cost is excluding GST.
Page 174
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
12 ECONOMIC
12: ANALYSIS
12 ECONOMIC ANALYSIS
12.1 INTRODUCTION
The benefits accruing to society from the proposed improvement are as follows:
Road User Benefits:
- Vehicle Operating Cost Savings
- Value of Travel Time Savings
Page 175
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
12 ECONOMIC
12: ANALYSIS
Road users experience different costs in the “With Project” and “Without Project
(Base Option)” conditions. The benefits to road users are con constituted
stituted by the savings in costs.
Increasing traffic volumes as a result of the project implies more vehicle kilometres and hence more
vehicles operating costs and, possibly showing more saving in with project conditions viz. benefits as
a result of the project.
Based on traffic, Road network and Socio
Socio-economic
economic characteristics of the project
road, improvement option (with project) have been considered by the consultants with proposed
up-gradation
gradation / improvement Option (4 (4-Lane) of the project road. The Economic analysis is carried
out for the following improvement options
“Without project/ Do minimum” - Routine maintenance of the existing road (Base option)
“With Project”- Two laning of Project Road as per warrant.
Page 176
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
12 ECONOMIC
12: ANALYSIS
This model provides for calibration of crucial input parameters to suit the local
condition and analysis of a number of alternatives and sections at relatively greater speed than is
possible with HDM III. The Road user cost streams generated by HDM
HDM-4 4 are extracted and Economic
Internal Rate of Return (EIRR), Net Present Value (NPV) and sensitivity analysis have been carried
out.
12.2 MEASURES OF PROJECT ANALYSIS
n n
Bi Ci
∑ i
−∑ i
i=1
1 +r i=1
1
1 +r
NPV = Discounted Benefit – Discounted Cost
n n
Bi Ci
∑ i ∑
÷ i
i=1
1 +r i=1
1 +r
Page 177
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
12 ECONOMIC
12: ANALYSIS
n
Bi − C i
or, ∑ i
= 0
i=1
1 +r
The IRR is that discount rate r which makes NPV = 0
IRR represents
epresents average earning power of the money used in the project over the
project life.
12.3 DECISION CRITERIA
The formal decision criterion is to accept all projects with a BCR of one or greater
than one, NPV greater than Zero or IRR greater than opportunity cost of capital, since primary
tangible returns are greater than primary tangible costs. If funds are limited, the magnitude of IRR or
BCR can be used in ranking the order of priority of undertaking projects whose ratios are more than
one. This assumes, off course, that the indirect tangible and intangible benefits and costs are of
minor importance or are approximately the same for the various projects under consideration.
Sometimes, however, the indirect tangible and intangible benefits may dictate over di direct tangible
benefits and so the projects with even less than one BCR may be selected for the overall intangible
benefits of the society. In practice, there is really no single yardstick to measure the economic and
financial viability of the project.
12.4 PRICE
CE ELASTICITY OF DEMAND AND TRAFFIC FORECASTING
Page 178
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
12 ECONOMIC
12: ANALYSIS
consequence of the lower user cost. Additional research is needed to narrow the range of elasticity
values that are applicable to a given set of circumstances - whether facility, corridor, or region - and
to develop methods for better incorporating demand elasticity into traffic forecasting.
Page 179
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
12 ECONOMIC
12: ANALYSIS
Discount rate - 12 %
Construction Period - 2 Years
Construction Beginning Year - 2022
Opening year to Traffic - 2025
Standard Conversion factor - 0.85
Salvage value - 15 %
st
Construction Phasing - 60% 1 Year
The classified Traffic Volume data (ADT) has been converted in to AADT, by applying the seasonal
factor as applicable to the area. The traffic data is given below in Table 12.2.
Taxi/ Tata
Chainage
Vehicles
Minibus
Std. Bus
Magic/
Above
2-Axle
3-Axle
6 Axle
7 Axle
Sl No.
Total
(No.)
LMV
LMV
Car/
LCV
Roadside friction has to be computed for each project road considering the following:
Page 180
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
12 ECONOMIC
12: ANALYSIS
Total traffic Volume and its Composition (Slow, Two & Three wheelers Traffic)
Settlement pattern along the road side
Percentage of Built-up
up Area
Number and location of Dhabas and Fuel Stations
The number of settlements along the roadside and especially the extensive ribbon development that
take place is a major factor influencing rroad
oad performance. The maximum friction factor for the
existing condition is taken as 0.9 and the minimum 0.8 amongst different sub projects.
Following the improvements of the roadside friction factor for the two lanes has to be taken as 1.0.
Roadside friction
iction factors have been incorporated into VOC as well as vehicle speeds for the given
volumes and composition of traffic. It is considered that the creation of free flow conditions will be a
more important yardstick with which to measure the success of an anyy project improvement rather
than increase in vehicle speeds.
Base vehicle characteristics and its utilization data has been obtained from manufacturer’s literature
and various literatures. The same has b been used as Vehicle input data for HDM-4.
4.
The capital costs (financial) of the project road have been converted into economic cost by using a
standard conversion factor of 0.85, as suggested by the World Bank for highway projects in India.
The conversion factor of 0.85 has been applied to all cost items except land acquisition cost and R&R
cost. The economic cost excludes the cost of toll plazas. A salvage value of 15% of capital cost has
been considered in the terminal year for flexible pavements. The project costs in financial and
economic terms for different schemes are presented in Table 12.3.
Page 181
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
12 ECONOMIC
12: ANALYSIS
Routine maintenance, Periodic maintenance costs have been considered as per latest MORT&H
guidelines.
The direct benefits of road improvement considered in the study include vehicle operating cost
(VOC) savings for vehicular traffic using the project road and time savings for passengers and goods
(carried) in transit. The benefit streams have been computed annually over the 30 year benefit
period for all the sections.
VOC Savings
The unit Vehicle Operating Cost (VOC) by vehicle type and VOC savings section section-wise has been
computed by the HDM model. The VOC computation takes into account capacity augmentation,
pavement characteristics, roughness progression vis vis-à-vis
vis intervening surface treatment and
strengthening policies, traffic characteristics, geometric conditions and vehicle characteristics.
Time Savings
The HDM Model has generated average speeds in km/hr by vehicle type, in the existing (without
project) and the improved (with project) road conditions. The time savings for passengers and goods
(in transit) vehicles have been derived separately. For computing time saving for passengers of ca
cars
and buses, a weighted average occupancy was used viz. Car – 4 persons and Bus – 30 persons. The
average payloads considered for goods vehicles are: LCV – 6 tonnes, Truck-16.2
16.2 tonnes and MAV –
24 tonnes.
Page 182
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
12 ECONOMIC
12: ANALYSIS
A distinction made between main cause of accident and the contributory factors of accident. It is
usually difficult to identify the main cause of accidents; whereas several factors which could have
contributed to accidents can be identified.
It is possible to predict the reduction in accidents on account of road improvements. The accidents
costs collected from IRC-SP-3030 (the values are in the year 1990 and escalated @ 5% pe
per year to get
the values in the year 2017 are given in Table 12.4.
Page 183
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
12 ECONOMIC
12: ANALYSIS
Page 184
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
The Site of the Single Lane Project Highway comprises the section of Highway. Project road
starts from Km. 0+000 at Tawaghat village (Design Chainage 56+935) and traverses a
length of 38.812km and ends Km.19+170 at Budhi Village (Design Chainage 95+748) And
starts at End of Tunnel Portal (Design Chainage 113+828) and traverses a length of
19.25km and ends at Kali Mandir (Design Chainage 133+078) . The Project Highway is part
of NH-09.
09. The stretch passes through winding hilly terrain of Hi
Himalayas
malayas and sight distance is
restricted at places due to sharp horizontal curves and vertical cuts slopes.
The Design length of the project road is 58.063km and it traverses through major
Built-up
up areas such as Pangla, Tawaghat, Ghatiyabagad and Gunji etc.
The route passes through hilly terrain. This is primarily due to the location in
Kumaon hilly terrain of the Central Himalaya in the state of Uttarakhand. The road
land boundary pillars are not found along the road.
Existing carriageway width of most of the project road is about 3.1m to 8m.
The pavement condition of the existing project road is generally fair to Poor.
There are 3 minor junctions proposed.
There are total 14 bridges (1 nos. major (Retain) and 5 nos. (Retain) + 8 nos. (New
Construction) of minor bridge) has been Proposed along the project road.
There are 165 culverts proposed along the road alignment (69 New Construction and
96 retain.
The proposal is to construct 5 new bus bays.
1 nos. Parking Area proposed
During initial survey, it is observed that the project road passes through forest land
(reserve forest/protected forest/community forest etc.) at several locations. Forest
Clearance Shall be obtained from MoEF&CC in accordance to the Forest
(Conservation) Act, 1980 and all the conditi
conditions
ons required by MoEF&CC in the Stage-I
Stage
and Stage-IIII Forest Clearance shall be fulfilled prior the commencement of the
construction of the planned project road. No Ecological Sensitive Zone, National
Park, Wildlife Sanctuary and Biosphere reserve is located within 10 km distance of
the project road package.
Out of the four seismic zones of India, project falls within Zone V.
The overall existing air quality of the project area is within acceptable limits.
An Environmental Management Plan (EMP) has been pr proposed
oposed for the planned road
package describes the environmental management procedures during design,
construction and operation phase, including mitigation & enhancement measures,
institutional and monitoring requirements.
EMP also provides the guidelines and instructions to be followed by the project
Page 185
Improvement/ Construction of 2-lane
lane with paved shoulder of Askote – Lipulekh road from Tawaghat village to Budhi village (Design km.
56+935 to km 95+748) and from end of tunnel portal to Kali Mandi
Mandirr (Design km 113+828 to km. 133+078) [Total Design length = 58.063
km] under project Hirak of BRO in the State of Uttarakhand under Bharatmala Pariyojna on EPC mode
13.2 RECOMMENDATION
The proposed project road being developed as two lane carriageway configuration for 58.063 Km is
recommended under EPC Construction.
Page 186