Activity Plan

MULTILYNX

Activity Plan

Century Paper Mills 62 km, Multan Road,

Prepared By: Iftikhar Ahmad Document Version 1.7


Date: 29 April 2023
Page 2 of 2
Activity Plan

Firmware’s update is required:


Customer: Century Paper Mills Requested By: Mr. Ghazanfar Hasan
Application Name: N/A Number of Servers 01
Serial #: HPE DL380 Gen10
CTO Server - SGH908V1DT

Host Names: Contract Details:


Active
Task Description Hard Drive Replacement is Required

Notes & Assumptions:


1- Century Paper Mills will take the backup of the server before drive replacement.
2- Physical access to datacenter shall be required.

Drive Replacement
Activities list and timelines
Total
Sr. Downtim
Scope and Activity details Activity Owner
# e
Time
Hard Drive update Multilynx
1. Access the server though iLO Console
2. Verify the logical drive status
3. Remove currently installed drive
4. Verify logical drive warranting 1hr. No. Multilynx
5. Install new hard drive and wait for logical drive to sync
6. Again check the logical drive status for rebuild process
7. Verify the health and Successful Replacement
Total Time required for 1 Node 1 hr.

* This is tentative time, data rebuild process time may vary.

Prepared By: Iftikhar Ahmad Document Version 1.7