You are on page 1of 13

AZZAWIYA OIL REFINING COMPANY INC.

PREVENTIVE MAINTENANCE OF 29 ATMOSPHERIC STORAGE TANKS


AT AZZAWIYA REFINERY

BILLS OF QUANTITIES

ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)
A- TANK DESLUDGING, CLEANING AND GAS FREEING:
Desludging, cleaning and gas freeing of the following tanks in accordance with API Std.
last edition and enclosed Technical Specifications in Section 2 including internal sweep
blasting of total surface area of the Tank Bottom and 1st Course of Internal Shell to
facilitate the Inspection of the Surface by the Inspector. Transport the sludge to the
designated locations, all as per Scope of Work:
A-1 Black Oil Product: (Floating Roof Type)
Crude Oil Tanks No.611-C3(1-3), No.611-C4(1-4), No.611-C6(1-6) and No.611-
A-1.1 EA 4
C7(1-7), each Ø 57.92 m .
A-1.2 LIGHT SLOP Ø21.34M 616-SL2 (5) EA 1
A-2 Black Oil Product: (Fixed roof type)
A-2.1 Fuel Oil Ø 42.67 m 615-F8(2-6) EA 1
A-2.2 Fuel Oil Ø 6.100 m 670-S1A & 670-S1B & 670-S2B EA 3
A-2.3 HEAVY SLOP Ø21.34M TK 616-SL1(4) EA 1
A-3 White oil product: (Floating roof type)
A-3.1 Kerosene Tanks Ø 30.48 m 613-K4(3-4) &613-k5(3-5) EA 2
A-3.2 Gasoline Ø 36.58 m 612-G5(5-5) & 612-G7(5-7) & 612-G11(6-11) EA 3
A-4 White oil product: (Fixed roof type)
A-4.1 Gas Oil Ø 36.58 m 614-S1(4-1) EA 1
A-5 Asphalt Product :
A-5.1 Asphalt Ø 15.00 m TK-148 EA 1
A-6 Water Tank: (Fixed roof type):
A-6.1 Distillate Ø13.5 m 1641-T10 EA 1
LPG Sphere (Sphers)
A-7 EA

Page 1 of13
ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)

LPG Sphere Ø 10.20 I.D (617-LPG 1) & (617-LPG 2) & (617-LPG 3) &
A-7.1 EA 4
(617-LPG 4)
A-7.2 LPG Sphere Ø 12.814 I.D (617-LPG 5) EA 1
A-8 Base Oil: (Fixed roof type)
A-8.1 Base Oil Ø10.67 m (T-2) EA 1
A-8.2 Base Oil Ø 9.145 m (T-8) EA 1
A-8.3 Base Oil Ø 14.63 m (T-4 ) & (T-5 ) EA 2
A-8.4 Base Oil Ø 24.385 m (T-9 ) & (T-10 ) EA 2
B- BOTTOM PLATES (FIXED& FLOTING ROOFS)
Complete replacement of bottom plates inclusive of annular plates with
B-1 underneath painting, drain sump, nozzles, roof support pads and Cathodic
protection lugs as per enclosed specifications.
B-1.1 For floating roof tanks. MT 230
B-1.2 For tanks with out support columns of fixed roof. MT 177
B-1.3 For tanks with support columns of fixed roof tanks MT 00
Partial replacement (up to a max.50%) of bottom plates complete with
underneath painting, drain sump, nozzles, roof support pads and lifting of tank
B-2
if necessary. (For tanks without annular plates, the bottom plates design
should be changed to annular plate design).
B-2.1 Partial replacement including annular plates for floating roof tanks. MT 40
Partial replacement excluding annular plates for floating roof tanks i.e. Sketch
B-2.2 MT 25
plates only.
Partial replacement including annular plates (For fixed roof tanks without roof
B-2.3 MT 45
support Columns for fixed roof tanks).
Partial replacement excluding annular plates i.e. Sketch plates only. (For fixed
B-2.4 MT 30
roof tanks without roof support Columns for fixed roof tanks).
Partial replacement including annular plates i.e. Sketch plates only. (For fixed
B-2.5 MT 50
roof tanks with roof support columns for fixed roof tanks).
Partial replacement excluding annular plates (For fixed roof tanks with roof
B-2.6 MT 30
support columns for fixed roof tanks).

Page 2 of13
ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)
Repairing of the existing damaged or corroded bottom/shell plates/ roof plates
20000
B-3 by welding first and then covering up the area by welding a patch plate over KG
and above the existing plate including the testing of the welding by air test.
B-4 Repairing of the existing damaged or corroded Bottom plates by insert pieces CM² 10000
B-5 Renewal of wearing pad plates for loading and unloading pipes KG 500
Removal and renewal of tank bottom accessories which is not falling within the
B-6 area of plate replacement such as drain nozzles, bottom sump, roof support EA
pads and level deck.
C- FOUNDATION PAD:
Renewal of foundation pad and the berm up to the base course as per API 653
C-1
specifications & Item 4.4 of Section-1 of the Scope of Work for the following:
Renewal of 80 mm thick asphalt concrete layer of the foundation pad and berm
C -1.1 M² 800
as per specification
Carry out surface repairs of the pad and berm by renewing the asphalt
C -1.2 M² 400
concrete layer partially up to max. 40 mm depth as per specifications.
C -2 Repair damaged portion of the concrete foundation and pipe supports
Dismantling the damaged portion of the surface concrete foundation and pipe
supports up to 50 mm depth behind the reinforcement bars, applying anti-
C-2.1 corrosive paint to the reinforcement bars after proper surface preparation and M² 210.00
casting the concrete with non-shrinkage mortar (Thixotropic) as detailed in
Para 4.4.3 of Section 1 of Scope of Work.

Dismantling the damaged portion of the concrete foundation and pipe supports
behind the reinforcement bars, applying anti- corrosive paint on the
C-2.2 reinforcement bars after proper surface preparation and casting the concrete m³ 35
with non-shrinkage mortar (Thixotropic) as detailed in Para 4.4.4 of Section 1.

Demolition of the bund wall and making good the same after inspection and
C-2.3 maintenance of pipes in bund wall.as detailed in Para 4.4.7 of Section 1 of m³ 100
Scope of Work.
Installation of new concrete pipe supports and sleepers as per Drawings duly
C-3 approved by the Owner complete with supply of all necessary material. M³
80

Page 3 of13
ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)
Removal of soil around the tank soaked with oil, and filling back the excavated
C-4
area with well compacted sand including its supply.
Removal of soil around the tank soaked with oil to a depth of 500mm ,
transporting it to the rubbish area and filling back the excavated area with well
C -4.1 m³ 750
compacted sand including its supply as detailed in Para 4.4.6 of section 1 of
the Scope of Work.
Removal of soil around the tank soaked with oil to a depth of more than
500mm upto the soil free of oil is reached, transporting it to the rubbish area
C -4.2 m³ 260
and filling back the excavated area with well compacted sand including its
supply as detailed in Para 4.4.6 of section 1 of the Scope of Work.
Filling up the gap between the bottom plates and the pad at the bottom plates
outer periphery to avoid the water ingress between them as detailed in para
C -5 4.4.5 of section-1. Bidder to submit along with the offers their proposal with LM 2,080
full technical details.

C-6 Sphere tanks legs fire proofing.

C-6.1 Clean the support legs by grit blasting and apply primer coat M2 250

C-6.2 Supply and lay fire proofing (H.D. cement) including all metal mesh, etc. as M3 40
detailed in para 4.4.8.4 of section-1 of the Scope of Work.

C-6.3 Supply and install fire proof coating for 6 hours fire rating M2 498

C-6.4 Remove insulation cement surrounded the legs of the LPG spheres. A new M3 5
insulation cement to be reinstalled on tanks legs including supply of materials.
D- TANK SHELL:
Partial/ complete replacement of shell course plates with new plates, in tank
shell and partial replacement of the nozzle, the replacement is excluding nozzle
D -1
replacement Item No.J shall be applicable, complete with welding joints
radiography as per API Std for the following sizes:
D-1.1 First and second course from bottom. MT 30
D-1.2 3rd to 5th course from bottom. MT 62
D-1.3 Over and above 5th course from bottom. MT 27.5

Page 4 of13
ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)
D-1.4 Lower part of LPG sphere MT 5
D-1.5 Upper part of LPG sphere MT 5
D-2 Repairing of the existing damaged or corroded shell plates by insert pieces CM² 310,000

Dismantling 24 “ side entry mixer from the tanks, transporting to the


D-3
OWNER’s workshop and installing them back in position
Dismantling side entry mixers from the tanks and re-installing them back in
D-3.1 EA 18
position

D-4 Tanks side gauges dismantling, installation and testing.

D-4.1 Old side gauges dismantling, instalation of new and testing EA 29


E- FIXED ROOF:
Complete/ Partial replacement of damaged roof plates inclusive of all nozzles
E-1 and accessories falling with in the replacement area complete with inspection MT 100
and testing as per API Std. 650 & 653.
E-2 Repairing of the existing damaged or corroded Roof plates by insert pieces CM² 10,000
F- FLOATING ROOF:
Complete/ Partial replacement of deck and/or pontoon plates inclusive of
F-1 nozzle, accessories and existing roof support legs falling with in the MT 90
replacement area as per API std 650 & 653.
Complete replacement of roof drain system including supply of pipe and its
F-2 acceseries & swivel joints and final hydro test for the following floating roof
tanks:
F-2.1 Ø 57.92 m Tank. Drain Pipe size Ø 6’’ EA 4
F-2.2 Ø 36.58 m Tank. Drain Pipe size Ø 4’’ EA 3
F-2.3 Ø 30.48 m Tank. Drain Pipe size Ø 4 ’’ EA 2
F-2.4 Ø 21.34 m Tank. Drain Pipe size Ø 4 ’’ EA 1
Dismantling of the existing sealing system and Installation of a new double
sealing system (HMT stainless steel scissor type) including primary and
F-3
secondary seals. Bidder to submit along with the offers their proposal with full
detailed technical specifications.
F-3.1 Crude Oil Tanks : Ø 57.92 m EA 2

Page 5 of13
ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)
F-3.2 White Oil Product : Ø 36.58 m EA 2
F-3.3 White Oil Product : Ø 30.48 m EA 1
Partial replacement of existing roof sealing system (HMT stainless steel scissor
F-4 LM 30
type).
F-5 Renewal of roof supporting legs as per relevant drawing:-
Renewal of roof supporting legs (legs, sleeves, reinforcement pad on roof and
F-5.1 reinforcement pad on bottom) including reinforcement pad on roof and bottom EA 210
plates.
F-5.2 Renewal of sleeves only with reinforcement pad on roof. EA 100
F-5.3 Renewal of the roof legs only. EA 115
G- HEATING COILS:

Complete replacement of heating coils system with all its accessories, with
G-1
100% radiography of the joints ond hydro test.
Including
G-1.2 616-SL1 (4) Dia 21.34 m EA 1
heating element
Including
G-1.3 616-SL2 (5) Dia 21.34 m EA 1
heating element
G-1.4 T -2 Dia 10.67 m EA 1
G-1.5 T –4 & 5 Dia 14.63 m EA 2
G-1.6 T -8 Dia 9.145 m EA 1
G-1.7 T –9 & 10 Dia 24.38 m EA 2
Including
G-1.8 670S1 A/B & 670 S2B Dia 6.10 m EA 3
heating element
Including
G-1.9 615F8(2-6) Dia 42.67 m EA 1
heating element
G-2 Complete replacement steam trap station unit EA 10
H TANK CALIBRATION:
Recalibration of tanks and sphers as per std API 2555 and 2552 respectively including as
per Para 4.11 of Section -1 and specification for the following tanks:
H.1 FLOATING ROOF TANKS:
H-1.1 Ø 57.92 m X17.08 m Height max EA 4
H-1.2 Ø 36.58m X 14.64m Height max EA 3

Page 6 of13
ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)
H-1.3 Ø 30.48m X 14.64m Height max EA 2
H-1.4 Ø 21.34m X 14.64m Height max EA 1
H-2 FIXED ROOF TANKS:
H-2.1 Ø 42.67m X 14.64m Height max. EA 1
H-2.2 Ø 36.58m X 14.64 m Height max EA 2
H-2.4 Ø 24.385m X 13.10 m Height max EA 2
H-2.5 Ø 21.34m X 14.64 m Height max EA 1
H-2.6 Ø 15.0m X 14.64 m Height max EA 1
H-2.7 Ø14.63m X 12.911 m Height max EA 2
H-2.8 Ø 13.5 m and below EA 5
H-3 SPHERE TANKS:
H-3.1 LPG SPHERE: Ø 9.020 I.D EA 4
H-3.2 LPG SPHERE: Ø 12.814 I.D EA 1
I PIPING:

Dismantling of existing damaged piping in following sizes at various elevations


and replacing the same with the new piping including wearing patch plates at
I-1
pipe support as per Para 4.7.1 of Section-1 of Scope of Work and piping code
ANSI B-31.3:

I-1.1 Ø ½” Sch.80 LM 650


I-1.2 Ø ¾” Sch.80 LM 650
I-1.3 Ø 1” Sch.80 LM 200
I-1.4 Ø 1½” Sch.80 LM 60
I-1.5 Ø 2” Sch.40 LM 300
I-1.6 Ø 3” Sch.40 LM 200
I-1.7 Ø 4” Sch.40 LM 60
I-1.8 Ø 6” Sch.40 LM 60
I-1.9 Ø 8” Sch.40 LM 48
I-1.10 Ø 10” Sch.40 LM 48

Page 7 of13
ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)
I-1.11 Ø 12” Sch. STD LM 36
I-1.12 Ø 14” Sch. STD LM 36
I-1.13 Ø 20” Sch. STD LM 24
I-1.14 Ø 24” Sch. STD LM 24
I-1.15 Ø 30” Sch. STD LM 24
I-2 FIRE FIGHTING PIPES:
Dismantling of existing system piping , and provide new design, fabrication,
installation, inspection and testing of new fire water piping in the following
tanks sizes at various elevations inclusive of testing of lines as per para 4.7 of
section-1 of the Scope of Work including supply of materials (Hot Dip
Galvanized & painted flanged pipes and fittings)
Note: The design shall comply with ARC specification and the following Codes
and Standards : (NFPA [11, 15, 25 &30] , API 521 & 2021 and ASQ Q9000)
Painting system
for this material
Option
Alike to item I-2 description but with using Copper Nickel Alloy material shall bespecified
(1)
on item M
(Painting)

Option
Alike to item I-2 description but with using carbon steel material
(2)

I-2.1 Crude Oil Ø 57.92 m 611-C3(1-3) & 611-C4(1-4) & 611-C6(1-6) & 611-C7(1-7) EA 4
I-2.2 LPG Sphere Ø 10.20 I.D (617-LPG 1) & (617-LPG 2) & (617-LPG 3) &
EA 4
(617-LPG 4)
I-2.3 LPG Sphere Ø 12.814 I.D (617-LPG 5) EA 1
I-4.2 LIGHT SLOP Ø21.34M 616-SL2 (5) EA 1
I-4.3 Fuel Oil Ø 42.67 m 615-F8(2-6) EA 1
I-2.4 HEAVY SLOP Ø21.34M 616-SL1(4) EA 1
I-2.5 Kerosene Tanks Ø 30.48 m 613-K4(3-4) &613-k5(3-5) EA 2
I-2.6 Gasoline Ø 36.58 m 612-G5(5-5) & 612-G7(5-7) K& 612-G11(6-11) EA 3
I-2.7 Gas Oil Ø 36.58 m TK614-S1(4-1) EA 1
I-2.8 Fuel oil tranks Ø 6.10 m 670-S1 A/B, 670- S2B EA 3

Page 8 of13
ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)

I-3 Fixed roof tanks : Dismantling, inspection, repair or renewal and reinstallation
of foam chamber & Foam Maker
I-3.1 Foam chamber EA 28
I-3.2 Foam Maker EA 28
I-4 TANKS COOLING PIPES:

Dismantling of existing system piping and provide New design, Fabrication,


installation, inspection and testing of new cooling water piping in the following
tanks sizes at various elevations inclusive of testing of lines as per para 4.7.3 of
section-1 of the Scope of Work. including supply of materials: (Hot Dip
Galvanized & painted flanged pipes and fittings)
Note: The design shall comply with ARC specification and the following Codes
and Standards : (NFPA [11, 15, 25 &30] , API 521 & 2021 and ASQ Q9000)

Painting system
for this material
Option
Alike to item I-2 description but with using Copper Nickel Alloy material shall bespecified
(1)
on item M
(Painting)

Option
Alike to item I-2 description but with using carbon steel material
(2)

I-4.1 Crude Oil Ø 57.92 m 611-C3(1-3) & 611-C4(1-4) & 611-C6(1-6) &611-C7(1-7) EA 4
I-4.2 LIGHT SLOP Ø21.34M 616-SL2 (5) EA 1
I-4.3 Fuel Oil Ø 42.67 m- 615-F8(2-6) EA 1
I-4.5 HEAVY SLOP Ø21.34M -616-SL1(4) EA 1
I-4.6 Kerosene Tanks Ø 30.48 m 613-K4(3-4) &613-k5(3-5) EA 2
I-4.7 Gasoline Ø 36.58 m 612-G5(5-5) & 612-G7(5-7) K& 612-G11(6-11) EA 3
I-4.8 Gas Oil - Ø 36.58 m TK614-S1(4-1) EA 1
I-4.9 LPG Sphere Ø 10.20 I.D-(617-LPG 1)& (617-LPG 2) & (617-LPG 3)& (617-LPG
EA 4
4)
I-4.10 LPG Sphere Ø 12.814 I.D-(617-LPG 5) EA 1

Page 9 of13
ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)
I-5 LPG sphere tanks legs ( ASTM/ASME A53 Gr.B)
I-5.1 Replace of LPG spher tank legs pipe Ø 24” Sch.40 -(617-LPG 1)& (617-LPG 2) LM 22
I-5.2 Replace of LPG spher tank legs pipe Ø 12” SCH. 30 (617-LPG3) & (617_LPG4) LM 20
I-5.3 Replace of LPG spher tank legs pipe Ø 24” Sch.40 -(617-LPG 5) LM 36
J- NOZZLES:
Renewal of the damaged nozzles of tanks shell in the following sizes at various
J-1 elevations using Reconditioned/ new flanges as per Para 4.8 f Section-1 of the
Scope of Work and Specifications:
J-1.1 Ø 2” and below. Sch. 80. EA 15
J-1.2 Ø 3” Sch. 80 # 150 EA 15
J-1.3 Ø 4” Sch. 80 # 150 EA 15
J-1.4 Ø 6” Sch. 80 # 150 EA 20
J-1.5 Ø 8” Sch. 80 # 150 EA 10
J-1.6 Ø 10” Sch. 80 # 150 EA 10
J-1.7 Ø 12” x 12.7mm thk, with flange # 150 EA 1.00
J-1.8 Ø 14” x 12.7mm thk, with flange # 150 EA 1.00
J-1.9 Ø 16” x 12.7mm thk, with flange # 150 EA 1.00
J-1.10 Ø 18” x 12.7mm thk, with flange # 150 EA 1.00
J-1.11 Ø 20” x 12.7mm thk, with flange # 150 EA 1.00
J-1.12 Ø 20” Sch. 80 # 150 and above. EA 8
Fabrication and weld new nozzles with reinforcement plates at various
J-2 elevations of tank for fire water and circulation pipes as per para 4.7.1 of
section-1 of the Scope of Work - size of nozzles:
J-2.1 Ø 4” Sch 80 with flange 150 EA 4
J-2.2 Ø 6” Sch 80 with flange 150 EA 4
K- INSULATION REPAIRS:
Complete removal of existing mineral wool insulation and installing back the
insulation using existing/ new mineral wool and cladding including fabrication
K1 of new cladding. Supports for fixing aluminum sheets, if required, and supply
of the fasteners required for the insulation work. As per Para 4.13 of Section 1
of the Scope of Work.

Page 10 of13
ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)
K-1.1 From tank shell and roof M² 1,000
From the piping of any size including the piping which was replaced during the
K-1.2 M² 800
execution of the Work.
K-1.3 Only removel of the existing mineral wool and cladding for any piping. M² 280
L- TANK HYDRO TESTING: (Including final settlement)
Hydro testing of the tank by filling with water taken from the nearest hydrant points to
the respective tanks as indicated in Para 6.5 of section-1 of the Scope of Work.
L-1 Volume of hydro test water > 30000 m³ EA 4
L-2 Volume of hydro test water, volium between 30000 & 75000 m³ EA 7
L-3 Volume of hydro test water between 7500 & 3000 m³ EA 4
L-4 Volume of hydro test water < 3000 m³ EA 14
M- PAINTING:
Grit blasting, priming and painting of the following sections of the tank including material
supply (Grit Blasting , painting ,etc ) as per enclosed Painting Specifications as indicated
in para 4.12 of section 1 of the Scope of Work.
External surfaces of tank shell and all accessories mounted on it such as wind
M-1 girders, ladders, handrail, platforms, external side of foam deflectors and fire M² 18,000
fighting pipes of the tank.
Internal surfaces of top 1m portion of tank shell and foam deflectors of floating
M-2 M² 2,600
roof tanks.
M-3 Internal surfaces of of top 1m portion of tank shell for fixed roof tanks. M² 17,400
M-3 Internal surfaces of tank bottom plates and shell Internal 1 ST
course M 2
800
M-1 External surfaces of fixed roofs including all Accessories mounted on it. M² 8,000
External surfaces of floating roofs including rolling ladder and all other
M-5 M² 13,400
accessories mounted on it
M-6 Loading and unloading lines in the tank boundary wall area. M² 2,300
All internal surfaces of bottom, shell, roof plates and roof supporting structure
M-3 M² 900
of water service tanks.

Page 11 of13
ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)
M-1
External surfaces of spheres including all accessories mounted on it like
M-4 M² 2,400
ladders, platforms, supports, level indicators, hand rails, piping etc.
M-6
M-1 sand papering and cleaning the external surface of tank shell with soap
M-4 solution and water thoroughly and apply one coat of a finish paint as per Para
M² 15,200
M-5 4.12.10 of section 1 of the Scope of Work and painting specifications to match
M-6 the colour with the surrounding tanks.

Tanks with insulated roofs, the roof plates in these tanks should be coated by
M-4 MASCOAT layer (minimum total thickness of 3mm) instated of the existed M² 1000
mineral wool insulation.

N- STRUCTURAL:
Dismantling existing damaged structural like shell ladder, platform, hand rail,
wind girder, foam deflectors, foam dam supports, level indicators and roof
N-1 supporting structure of fixed roof tanks etc at any elevation, fabrication and MT 60
erection of the new structural to replace the existing one as per Para 4.9 of
Section-1 of the Scope of Work.
O- SEAL WELDING:
Seal welding of the existing tack welded structural/ plates by fillet weld to
O-1 LM 1,200
avoid corrosion at any location as instructed by the Inspector.
P- WELD BUILD UP:
Repairing of the pitted/ grooved surfaces of shell, bottom, roof plates and the
structural at any elevation by weld build up after thoroughly cleaning the
P-1 CM² 200,000
surface and flushing the excess weld projection to the metal surface by
grinding.
Q- Sweep Blasting
sweep blasting for any location from tank surface to facilitate the inspection of
Q-1 M² 2,700
the surface by the Inspector:
R- VALVES:

Page 12 of13
ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)
Removal of the existing isolating valves of the following sizes from
the position, blinding the open pipe ends after the valve removal,
R-1 transporting to the OWNER’s workshop and re-installing back on
position the reconditioned/ new valve as per Item 7.4 of Section 1 of
Scope of Work.
Removal of the existing isolating valves of the following sizes from the position,
R-1.1 blinding the open pipe ends after the valve removal and re-installing back in
position the reconditioned/ new valve
R-1.1.1 Up to Ø 3” EA 51
R-1.1.2 From Ø 4” to Ø 6” EA 57
R-1.1.3 From Ø 8” to Ø12” EA 44
R-1.1.4 From Ø 14” to Ø 18 EA 3
R-1.1.5 From Ø 20” and above. EA 5
Removal of safety valves, transporting to the OWNER’s workshop and
R-2
fix back in position.
R-2.1 Removal of safety valves, and fix back in position EA 56
S- Permanent reference electrodes of Tank bottoms:
Fixing of permanent reference electrodes for monitoring the cathodic.
Cut asphalt basement at three location on tank bottom at (north, centre and
S-1 south) to lay down the pre-packaged permanent reference electrodes, pit Pit 36
dimensions shall be (30 W x 50 L x 30 Depth) cm.
Cut asphalt basement to form straight cable trench to lay down the reference
S-2 electrode cable tails, dimension shall be (30 W x 30 Depth) cm, backfill the LM 790
cable trench by soft sand and asphalt basement cover.
Weld stud bolts and fix the flush mounted test station on north side of tank
S-3 EA 12
shell exterior and connect the identified reference electrodes cable tails.
T- Training on (API & ASME) standards
The Contractor shall provide training for (20) Owner's Specialist Engineers for a
two weeks period (abroad) at an ASME and API approved training provider,
Including the provision of training materials in various specializations and
T-1 EA 20 Per trainee
accredited certificates (all training expenses shall be included in the
contract price and at the expense of the contractor), provided that ARC
bears travel and accommodation expenses.
Legend: LM = Linear Meter, EA = Each, M2 = Meter Square, MT = Metric Ton, KG = Kilogram, CM2 = Centimeter Square, M3 = Cubic Meter, L.S. = Lump sum