G F E D C B A

TOP OF PARAPET WALL TOP OF PARAPET WALL


ELEV. +- 5.90 M ELEV.+- 5.90 M

1.50

1.50
SECOND FLOOR BEAM SECOND FLOOR BEAM
ELEV. +- 4.40 M ELEV.+- 4.40 M

5.9M

5.9M
4

4
FFL FFL

0.40

0.40
NGL ELEV.+- 0.40 M ELEV.+ 0.40 M NGL
ELEV. +- 0.00 M ELEV. +- 0.00 M

PROPOSED EVACUATION CENTER


RIGHT-SIDE ELEVATION
SCALE 1:100 MTS

A B C D E F G

TOP OF PARAPET WALL TOP OF PARAPET WALL


ELEV. +- 5.90 M ELEV.+- 5.90 M
1.50

1.50
SECOND FLOOR BEAM SECOND FLOOR BEAM
ELEV. +- 4.40 M ELEV.+- 4.40 M
5.9M

5.9M
4

4
FFL FFL
0.40

0.40
NGL ELEV.+- 0.40 M ELEV.+ 0.40 MNGL
ELEV. +- 0.00 M ELEV. +- 0.00 M

PROPOSED EVACUATION CENTER


LEFT-SIDE ELEVATION
SCALE 1:100 MTS

Project Title: Prepared by: Checked by: Checked by: Recommending Approval: Approved by: PROJECT NO:

CONSTRUCTION OF
EVACUATION CENTER SHEET NO:
@ BRGY. PANGAO, LIPA CITY
Reydelio S. Tumambing Ireneo V. Adaya Emigdio M. Ilagan Ronaldo F. L. Castillo Josephine M. Kalaw Eric B. Africa
Building Inspector Engineer IV Asst. City Engineer Asst. City Engineer City Engineer City Mayor