Professional Documents
Culture Documents
Plant Solutions
Handled by Owner Approved by Date Version Page
Design Guide
CIP Station
Centralized
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal
Tetra Pak Processing System
Plant Solutions
Handled by Owner Approved by Date Version Page
Content
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal
Tetra Pak Processing System
Plant Solutions
Handled by Owner Approved by Date Version Page
NOTE! This document is made for YOU, NOT TO BE GIVEN TO THE CUSTOMER!
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal
Tetra Pak Processing System
Plant Solutions
Handled by Owner Approved by Date Version Page
Dimensioning of heat exchangers in the lines is based on maximum flow rate, see below and a
delta T = 20 °C per passage of the flow.
Dimensional CIP flow to tanks
The required capacity and pressure for the cleaning of a tank is determined by the number and
type of the cleaning devices (spray balls, spray nozzles or spray turbines). In addition
sufficient flow must be achieved in the inlets and the outlets of the tank.
A flow rate of approx. 1500- 21 00 l/m circumference is needed for the cleaning of a vertical
tank.
A flow rate of approx. 300 l/m2 of inner surface is needed for the cleaning of a horizontal
tank.
Dimensional CIP flow in pipes
For 1” – 3” (25-76 mm) pipes a mean velocity of 1.5 m/s should be reached.
For 4” (102 mm) pipe a speed of 1.0 m/s can be accepted.
Pipelines with a high number of valves and dead ends may need a higher velocity, as the dead
ends are cleaned by the turbulence created by high velocities. It is also essential to orientate
the T-pieces so that they are cleanable.
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal
Tetra Pak Processing System
Plant Solutions
Handled by Owner Approved by Date Version Page
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal
Tetra Pak Processing System
Plant Solutions
Handled by Owner Approved by Date Version Page
Depending on what type of product and temperature the plate heat exchanger is used for there
are three different kind of fouling:
3. Low fouling - Particularly for cooling of none fouling, viscous product 0-50°C
Example:
Type of heat exchanger: xx
Type of plates: Normal plates/High fouling
Grouping: 3 x 4 + 3 x 4
Flow rate/channel: 2000 l
Required flow rate: 4 x 2000 = 8000 l/h
Cleaning of valves
Mixproof valves, like Unique mixproof valves, need to do seatlifts to clean their seats to the
leakage chamber. This activity could be one of the factors that have the most impact on water
consumption.
Specific mixproof valves, like Unique UltraClean and HighClean, also need to clean the outer
parts of the balance plugs and the leakage chamber. This is done through a separate small pipe
separated from the main pipe with a valve. The distances between valves and pipes for this
internal cleaning must be as short as possible. If this solution is not correctly designed it can
consume a large amount of water.
When flip times are set as short as possible there will be an increased need for more cleaning
result inspections.
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal
Tetra Pak Processing System
Plant Solutions
Handled by Owner Approved by Date Version Page
If objects with both high and low capacities are connected to the same cleaning line, it must be
assured that the pump could handle also the low capacities (in some cases flow restrictions
need to be added).
Procedure:
Make a list of all the cleaning circuits and indicate the cleaning capacity, cleaning program
and area for each circuit.
Prepare a time (occupation) schedule to determine the number of cleaning lines. Based on the
production program, the starting time might be fixed for each circuit to avoid possible
conflicts.
The most difficult part of the design job is the grouping of the circuits. Capacities of the
circuits, basic layout of the plant and availability have to be taken into consideration.
As a dimensioning rule a cleaning line for long programs (PHE) can be used 3 times a day, i.e.
the running time will be about five (5) hours a day and a cleaning line for short programs
(tanks and pipe lines) 10-15 times a day corresponding to a running time of 6 – 7.5 hours.
These figures may, however, only be used as approximate ones.
First of all you have to look upon each cleaning circuit to determine the volume of the circuit.
Line cleaning
You have to determine which diameter the pipe has and then do a rough calculation of the
length of the circuit and the line to and from the cleaning plant.
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal
Tetra Pak Processing System
Plant Solutions
Handled by Owner Approved by Date Version Page
Example
The cleaning circuit: 130 m pipe diam. 76 =540 l
25 m pipe diam. 63.5 = 72 l
The cleaning line: 15 m pipe diam, 76 = 62 l
(pressure and return) 25 m pipe diam, 76 = 104 l
= 778 l
Tank cleaning
The main volume needed for a tank cleaning is in the line to and from the tank. So first of all
you have to determine the diameter of the pressure and the return line and the length of the
lines as above.
The volume which is inside the tank during cleaning is as follows:
Example
Cleaning of a vertical tank 10 000 1
Tank: = 75 l
Line: 47 m pipe diam, 63.5 = 134 1
23 m pipe diam. 51 = 43 1
= 252 l
Milk Pasteuriser
For calculating the cleaning volume for a pasteuriser, use a figure of 7% of the nominal
capacity for the product flow (20 000 l x 0.07 = 1400 l)
Nowadays, the regenerative effect has increased very rapidly from 80% to 90% and even to
96%. If you are going to clean a pasteuriser with 96% regenerative, you must have the
required volume of cleaning solution tanks to be able to circulate.
This calculation is based on P&ID, layout and isometric drawings:
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal
Tetra Pak Processing System
Plant Solutions
Handled by Owner Approved by Date Version Page
Detergent Tanks
The determination of the necessary volumes of the detergent tanks (caustic and acid) is based
on the maximum volume of the cleaning solution that can be simultaneously in the cleaning
lines (Cleaning System Volume = VCS). This volume is equal to the volume of the largest
circuit of each cleaning line.
The volume for a system for cleaning of plate heat exchangers is equal to the volume of the
pipe line plus the volume of the heat exchanger itself.
The volumes of all the lines that could be in operation at the same time are added together.
Example 1 (Cleaning system volume for three lines)
Line Volume
W01 650 Litres
W02 200 Litres
W03 350 Litres
Total 1200 Litres
Four additional volumes are added:
1. Volume between overflow pipe and LSH = 20 % of VCS.
2. Margin volume between LSM and LSL = 30 % of VCS.
3. Volume between distribution pipe and LSL = 10 % of VCS.
4. Volume in the cone of the tank (dependent on diameter and slope)
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal
Tetra Pak Processing System
Plant Solutions
Handled by Owner Approved by Date Version Page
The summary of these 5 volumes gives the necessary size of the CIP tank. The nearest
standard tank size is chosen.
The Matrix Toolbox No 28 “CIP Circuits and Tank) gives help with the calculation.
The dimensioning of the Detergent tanks should normally allow all CIP lines to operate in the
same step at the same time. Especially at extensions of the number of CIP lines in one existing
CIP station the number of CIP lines operating at the time could be limited. An extra interlock
is then added in the software.
The feeding capacity of water to these tanks should be enough to refill an empty tank in less
than 60 minutes.
Water tanks
Pre-rinse water (collected post-rinse water from the previous cleaned circuit).
The necessary volume of the pre-rinse water tank is based on the maximum rinsing throughput
required simultaneously and the estimated time for the pre-rinse phase.
Necessary volume = max. throughput (litres) x Time (min) / 60 (min)
The necessary volume of the fresh water tank is calculated in the same way.
The feeding capacity of water to this tank should be approx. 30% of the maximum rinsing
flow.
Neutralisation tank
The necessary volume of the neutralisation tank is based on 2.5-3 times the volume of the
detergent tanks.
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal
Tetra Pak Processing System
Plant Solutions
Handled by Owner Approved by Date Version Page
the distribution system and it is possible to design the system in the same dimension as the
circuit (Option).
V50 and V58 are distributing and collecting the CIP detergents. V51-V54 are distributing and
giving CIP safety when having many similar CIP circuits located near each other. V56 and
V57 are design elements with CIP return pumps and are needed when objects with open
surfaces to the atmosphere are cleaned, i.e. tanks, fillers etc.
V50 is distributing cleaning detergents to the different cleaning circuits connected to the same
CIP pressure line. Activations and error control is done from the cleaning circuit.
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal
Tetra Pak Processing System
Plant Solutions
Handled by Owner Approved by Date Version Page
V58 is collecting cleaning detergents from the different cleaning circuits connected to the
same CIP pressure line.
V56 is pumping back cleaning detergents from a tank, filling machine or equal. The suction
side is connected to tank lines, balance tanks or equal. The pressure side is connected to the
CIP return collecting system V58. Activations and error control is done from the cleaning
circuit.
V57 is pumping back cleaning detergents from a tank, filling machine or equal. The suction
side is connected to tank lines, balance tanks or equal. The pressure side is connected to the
CIP return collecting system V58. It is possible to bypass the pump if a part of the CIP circuit
is a pipe (i.e. the tank line) that needs to be cleaned with a higher CIP flow than the rest of the
CIP circuit (i.e. tank and tank line together). Activations and error control is done from the
cleaning circuit.
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal
Tetra Pak Processing System
Plant Solutions
Handled by Owner Approved by Date Version Page
V51 Includes vertically positioned Single seat valves which makes the installation use little
floor space. (In this installation there is a slight risk of having CIP liquid in the wrong tank if
the valve plug is indeliberately detached from the actuator.)
V52 Includes horizontally positioned Single seat valves. No risk of having CIP liquid in the
wrong tank if the plug is indeliberately detached from the actuator. It needs more welding than
V51.
V53 Includes a swing bend plate where the different CIP circuits are connected manually
when needed. Proximity switches could be necessary to avoid CIP liquid in the wrong tank.
This solution is mostly used for CIP circuits that are not cleaned with the normal daily
production, for example CIP tanks.
V54 Includes vertically positioned mix proof valves which makes the installation use little
floor space. The valves normally don’t need seat lifts.
Sizing of CIP return pumps
The rated capacity of cleaning equipment should be more than 50% of the nominal capacity.
The choice of the return pump for each cleaning line is based on the calculated pressure drop
(length of pipes, number of bends, static pressure, spray balls etc.) and nominal capacity.
To save energy for the CIP return pumps they could be equipped with speed controllers.
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal
Tetra Pak Processing System
Plant Solutions
Handled by Owner Approved by Date Version Page
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal
Tetra Pak Processing System
Plant Solutions
Handled by Owner Approved by Date Version Page
Diaphragm pumps are suitable for dosing caustic and acid. The pumps must be equipped with
flexible connections on both suction and pressure side and a suitable overflow valve leading
the concentrate back to the respective tank.
In order to avoid that the pumps are drowned if the “safety basin” is filled up due to tank
leakage, they should be placed on consoles on the wall or outside the basins.
Pipes and Fittings
Thick walled acid proof steel shall be used and everything shall, if possible, be welded
together. The dimensions of the pipes should be ½”- 1 “,
The flexible connections for the dosing pumps must be resistant against concentrated caustic
and acid.
The valves shall be acid proof ball valves and, if they should be remote controlled, equipped
with pneumatic actuators and feedbacks.
The inlets and outlets of the tanks must be equipped with shut-off valves.
All fittings shall be made of acid-proof steel with pressure limits and temperature limits
according to local regulations.
Protective shields must be erected around such equipment where leakage can occur, e.g, pump
connections, valves etc.
Tanks, pipes etc. must be marked with special warning signs against corrosive chemicals.
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal
Tetra Pak Processing System
Plant Solutions
Handled by Owner Approved by Date Version Page
Seals should for resistant to the cleaning agents used. For connections to the recovery system
the resistance against the food products must be secured.
•
• Instruments need to be fast reacting to be able to control the separation of liquids
in the CIP returns in the best way.
Copyright © 2008 Tetra Pak Processing Systems, Lund Tetra Pak Internal